ITR No: C-0207A
FOUNDATION COMPLETION CERTIFICATE
2042-ITR-009 Date:
16.01.20
C-0207A Page:
1 of 1
Confirm the plan and concrete finished elevation of the foundation is as per IFC
1
drawing (attached survey report)
Confirm that position of Anchor Bolts in plan and elevation is as per IFC drawing
2
(attached survey report)
3 Confirm that the anchor bolt and threads are protected in satisfactory condition.
4 Confirm that the Anchor Bolt pockets to receive grout are cleaned
Confirm that surrounding area has been back filled and compacted to correct
6
elevation
Confirm that all construction debris have been removed prior to release to next
9
discipline
10 Confirm that concrete 7 days and 28 days test reports are available and accepted
Remarks:
*If an RFI has 2 # ITRs, record number for those ITRs shall be “RFI number/1” and “RFI number/2” Test reports will have test house
identification numbers.
Signature
Date
Page 1 of 1 Ref. ITP NO: MGP1-CP2-PIL-QA-5733-1003