Professional Documents
Culture Documents
PV Series Traming - en
PV Series Traming - en
Tower
The tower must be lowered when tramming distances outside the drill pattern, or when tramming
over rough or uneven ground. Keep in mind that the machine must be leveled using the jacks be-
fore the tower may be raised or lowered.
Tracks
The tracks are sensible for rocks and debris and must be cleaned before tramming a long dis-
tance.
Time limitation
You may only tram in 20 minute segments. For each time you have been tramming for 20 min-
utes, you must stop the machine and check the temperature of the rollers before proceeding. The
temperature should be checked by using a temperature gun. Do not touch the rollers with your
hands, as the rollers may be hot.
If it is not possible to step out of the machine to check the temperature of the rollers, i.e. when
tramming on a haul road, it is recommended to let the machine rest for 10 minutes for each 20
minute of tramming.
Please note
When tramming a PV 271 for long distances, it is advised the second rod is stowed in
the carousel and the “bit in head, head at middle tower” function is used.