You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/353908992

CLAIMS MANAGEMENT: UNDERLYING CAUSES IN MEGA-CONSTRUCTION


PROJECTS

Conference Paper  in  Proceedings of International Structural Engineering and Construction · August 2021


DOI: 10.14455/ISEC.2021.8(1).CON-27

CITATION READS
1 207

5 authors, including:

Dikeledi Anna Matseke Nthatisi Khatleli


University of the Witwatersrand University of the Witwatersrand
2 PUBLICATIONS   1 CITATION    92 PUBLICATIONS   68 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

A Framework towards an effective claims management process in construction industry using a hybridized SWOT-AHP Mode View project

Construction Projects Supply Chain and Blockchain Technology View project

All content following this page was uploaded by Nthatisi Khatleli on 14 August 2021.

The user has requested enhancement of the downloaded file.


Proceedings of International Structural Engineering and Construction, 8(1), 2021
Interdisciplinary Civil and Construction Engineering Projects
Edited by El Baradei, S., Abodonya, A., Singh, A., and Yazdani, S.
Copyright © 2021 ISEC Press
ISSN: 2644-108X
www.doi.org/10.14455/ISEC.2021.8(1).CON-27

CLAIMS MANAGEMENT: UNDERLYING CAUSES


IN MEGA-CONSTRUCTION PROJECTS
DIKELEDI ANNA MATSEKE and NTHATISI KHATLELI
Dept of Construction Economics and Management, University of the Witwatersrand,
Johannesburg, South Africa

Construction claims remain unavoidable in any megaproject contractual relationship


and can quickly escalate to misunderstandings, disputes and litigations if not
appropriately managed. Disputes pose a significant risk in hindering project progress;
they are characterised by lengthy legal battles that consume substantial time and
financial resources. This study identifies the causes of claims encountered by clients,
contractors and consultants in transport and energy sector mega construction projects in
South Africa. A semi-systematic literature review was used to identify, select and
appraise existing literature on this issue. Content analysis using NVivo 12 was used to
identify factors causing claims in the construction sector, particularly in MCPs.
Findings of the study revealed that construction projects occurring outside of South
Africa experienced a delay in payments, time and cost overruns, change orders,
inadequate project and drawing specifications, natural risks or force majeure. In South
Africa, delays and cost overruns (due to insufficient experience and expertise of project
managers and engineers) frequent to be the causes attributable to claims.
Keywords: MCP, Contract issues, Project delays, Construction sector, Cost overruns.

1 INTRODUCTION
Mega Construction Projects (MCPs) play a pivotal role in boosting economies (Maqsoom et al.
2019). Claims within construction are a problem area that requires much attention because they
are considered to be the most disruptive and unpleasant occurrences in a project (Zaneldin 2020).
The escalation in claims emanates from the increasing complexity and large size of MCPs (Xue et
al. 2020). Therefore, construction claims are ineluctable in contractual relationships and often
lead to misunderstandings, disagreements, and litigation if not correctly handled (Akinradewo
2017). If not sufficiently resolved, claims tend to stifle project progress since they are associated
with prolonged legal fights that consume large amounts of time and money (Pourhashemi et al.
2019). The effective management of the generic problem of construction claims lies in procuring
effective claims management strategies (Parchami et al. 2019). This paper aims to identify the
underlying factors causing claims in MCPs in the South African context. The global perspective
of these causes will also be looked at to determine what is perceived by the world to be the
common causes of claims in MCPs.

2 LITERATURE REVIEW
2.1 Mega-Construction Projects
MCPs are large, complex projects that involve substantial investments (over $1 billion), social
importance and time (Cerić et al. 2020). MCPs are needful because they lead to infrastructural
development and economic growth (Rothengatter 2019).

CON-27-1
El Baradei, S., Abodonya, A., Singh, A., and Yazdani, S. (eds.)

2.2 Importance of Claims Management


Recent experiences with MCPs are bedevilled large volumes of claims, which adversely affect
their economic performance (Akinradewo 2017). Claims remain endemic to construction projects
and tend to result from several factors that often contribute to project delays and escalated project
costs (Kasapoğlu 2018). Claims tend to cause suspension of construction work, time extension in
carrying out projects and delays in payment for work done (Al Malki and Alam 2021). Claims
management, therefore, exists to ensure that disagreements that give rise to claims do not escalate
into disputes (Komurlu and Arditi 2017). Table 1 provides a summary of the causes of claims
mentioned by various scholars.

2.3 Causes of Construction Claims: Global


Al Malki and Alam (2021) mentioned delay in payments to contractors, change or variation
orders, inadequate investigation before bidding, delay approval of shop drawings and insufficient
time for bid preparation as causes of claims. Parikh et al. 2019 also stated that delays in
payments and/or reduced payments caused claims. According to Iskandar, Hardjomuljadi and
Sulistio (2021), factors such as contractor delay in work completion, ambiguous definition of
contract documents and project delays as the causes of claims. Owner-dominated contracts and
lack of knowledge about contractual rights (Kisi et al. 2020). Noushad et al. (2021) cited the
following as causes of claims; changes in scope and definition of a project, project delay, delay in
handing over the site and work permissions as causes of claims. According to Shrestha and
Neupane (2021), change orders, contract ambiguity, project delay, project acceleration, extra
work time and different site conditions in design vs on-site were common causes of clams.
Ekhator (2016) cited delay in payments, insufficient detail in the contract, delay in the release of
drawings. Shen et al. (2017) listed contract risk, client behaviour and lack of project definition,
natural risk. Other causes of claims mentioned in the literature survey include schedule delays
(Sakate and Dahwale 2017), errors and omissions in design or specifications (Jalal et al. 2020),
project delays, cost overruns and adverse weather conditions (Akinradewo 2017), delay in
payment, incomplete contract, inadequate specifications and drawings, variation order, change
order by owner, lack of communication, poor project management, weather conditions and site
conditions (Saad, 2017), design changes introduced at the post-tender stage, implementation of
project in unduly short periods with inadequate site investigation, design work, tender and
contract documentation and inadequate definition or specification of the scope of contract works
(Bakhary et al. 2015). Khekale and Futane (2015) also mentioned schedule delays, changes in
contract work, differing/unusual site conditions, suspension of work, variation in quantities,
damages from natural disasters and force majeure, cost overruns, ambiguity in specifications and
drawings and acceleration of work progress

2.3 Possible Causes of Claims in South Africa


According to Tshidavhu and Khatleli (2020), contractual claims are significant causes of schedule
and cost overruns in South African MCPs. MCP failure is also a result of organisational and
management-related challenges such as poor site management, inadequate monitoring and
control, an unstable management structure, lack of experience and expertise, inadequate
management skills (Tshidavhu and Khatleli 2020). Medupi and Kusile Power Stations in South
Africa have been subjected to intense political scrutiny because of their runaway costs (Yelland
2019). The two projects experienced geological problems as a direct result of a rushed

CON-27-2 © 2021 ISEC Press


Proceedings of International Structural Engineering and Construction, 8(1), 2021
Interdisciplinary Civil and Construction Engineering Projects

implementation. The absence of appropriate project management capabilities and engineering


contributed to project delays.
Moreover, it was initially estimated that the Medupi project would cost ZAR69bn. However,
costs increased massively to ZAR154bn (Phahla 2018). Kusile’s cost to completion budget is
also projected to double from ZAR81bn to an estimate of ZAR161.4bn in 2025 (Madubela 2021).
Similarly, a constructed Multi-Product Pipeline project meant to transport liquid fuel from
Durban to Johannesburg (slightly over 500km stretch) to meet the forecasted inland demand for
fuel in South Africa was estimated at ZAR12.7 bn. The projected costs have since been raised to
ZAR30 bn due to severe delays and cost overruns (Groenewald 2017).

3 RESEARCH METHODOLOGY
This research is a qualitative semi-systematic literature review, also referred to as a narrative
literature analysis. The interpretivism philosophy underpins this study (Kelly et al. 2018).
Google Scholar, Science Direct and Scopus were used in identifying existing literature
mentioning or discussing claims and their causal factors in their titles, abstracts and content.
Nodes, simply described as containers for gathering related data on claims, were done. The
causes of claims were then extracted from the uploaded articles using the search query’ claims.
All the information that discussed or mentioned claims were then coded into the nodes.

4 RESULTS AND FINDINGS


Figure 1 illustrates the causes of claims frequently mentioned by authors as per the literature
review.
These include:
• Contract problems (Iskandar et al. (2021), Shrestha and Neupane (2021), Saad (2017),
Shen et al. (2017) Ekhator (2016), Bakhary et al. (2015)).
• Site related errors (Noushad et al. (2021), Shrestha and Neupane (2021), Tshidavhu and
Khatleli (2020), Saad (2017), Bakhary et al. (2015), Khekale and Futane (2015)).
• Project delays (Tshidavhu and Khatleli (2020) Iskandar et al. (2021), Noushad et al.
(2021), Shrestha and Neupane (2021)).
• Delays in payments (Al Malki and Alam (2021), Parikh et al. (2019), Saad (2017)
Ekhator (2016)).
• Drawing errors (Al Malki and Alam (2021), Saad (2017), Ekhator (2016) Khekale and
Futane (2015)).
• Change or variation orders (Al Malki and Alam (2021), Saad (2017), Khekale and Futane
(2015)).
• Weather/natural risks/force majeure (Akinradewo (2017) Saad (2017) Shen et al. (2017)
Khekale and Futane (2015)).
• Schedule delays (Tshidavhu and Khatleli (2020), Sakate and Dahwale (2017), Khekale
and Futane (2015)).
• Cost overruns (Tshidavhu and Khatleli (2020), Akinradewo (2017), Khekale and Futane
(2015)).
• Poor project management (Tshidavhu and Khatleli (2020), Saad (2017)).

CON-27-3 © 2021 ISEC Press


El Baradei, S., Abodonya, A., Singh, A., and Yazdani, S. (eds.)

Figure 1. Frequency of mentions of causes of claims in the construction sector.

In MCPs outside of South Africa, contract issues, site-related errors, and project delays were
the most mentioned. The predominant causes of claims in MCPs in South Africa result from
project delays, cost overruns, poor site management and poor project management.

5 CONCLUSION AND RECOMMENDATIONS


The pivotal role that the construction sector plays in contributing to the GDP of nations and
employment creation remains undeniable, in addition to the inevitability of claims in MCPs.
Construction claims need adequate management strategies that can consistently aid in the de-
escalation of claims before their evolution into disputes. Ineffective management of claims tends
to cause delays in project progress and are often associated with legal battles that require
significant amounts of time and money. Since MCPs in themselves are characterised by huge
expenditures, the management of their claims remain vital and are a desirable approach to curbing
increased expenses. The management of claims requires a critical and thorough identification of
the causes of claims. This study has found that the various causes of claims are dependent on the
type of MCP and the common internal and external factors that such MCPs are characterised by
Inadequate planning, unclear project specifications, schedule delays are factors that cause claims
in South African MCPs in the energy and transport sector. Since most studies tend to focus on
disputes, it remains expedient that further studies interrogating specific causes of claims within
the transport and energy MCPs are undertaken to supplement secondary data collection from
professionals within these two sectors.

References
Akinradewo, O. F., Stakeholder Awareness of Construction Claims Management Models in Nigerian
Construction Industry, FUTY Journal of the Environment, 11(1), 76-90, November, 2017.
Al Malki, Y. M, and Alam, M. S., Construction Claims, Their Types and Causes in the Private
Construction Industry in the Kingdom of Bahrain, Asian Journal of Civil Engineering. 22(3),477-84,
April 2021.
Bakhary, N. A, Adnan, H, and Ibrahim, A., A Study of Construction Claim Management Problems in
Malaysia, Procedia Economics and Finance, 1(23), 63-70, January, 2015.
Cerić, A., Vukomanović, M., Ivić, I., and Kolarić, S., Trust in Megaprojects: A Comprehensive Literature
Review of Research Trends, International Journal of Project Management, November, 2020.

CON-27-4 © 2021 ISEC Press


Proceedings of International Structural Engineering and Construction, 8(1), 2021
Interdisciplinary Civil and Construction Engineering Projects

Ekhator, O. J., Investigating Causes Of Disputes in Building Construction Projects in Nigeira, International
Journal of Science, Environment and Technology, 5(5), 3516-27, October, 2016.
Groenewald, Y., Durban/Joburg Fuel Pipeline Opens After Years of Delays, Spiralling Costs, October,
2017. Retrieved from https://www.news24.com/fin24/Companies/Industrial/durbanjoburg-fuel-
pipeline-opens-after-years-of-delays-spiralling-costs-20171006%20 on 20 March, 2020.
Iskandar, H. S., and Sulistio, H., The Most Influencing Factors on the Causes of Construction Claims and
Disputes in the EPC Contract Model of Infrastructure Projects in Indonesia, Review of International
Geographical Education Online, 11(2), 80-91, June, 2021.
Jalal, M. P., Roushan T. Y., Noorzai, E., and Alizadeh, M., A BIM-Based Construction Claim Management
Model for Early Identification and Vivisualisation of Claims, Smart and Sustainable Built
Environment, May, 2020.
Kasapoğlu, E., Risk Management in Construction. Sustainable Buildings: Interaction between a Holistic
Conceptual Act and Material Properties, IntechOpen. 49-71, July, 2018.
Kelly M., Dowling, M., and Millar, M., The Search for Ynderstanding: The Role of Paradigms, Nurse
Researcher, 25(4), 9-13, March, 2018.
Khekale, C., and Futane, N., Management of Claims and Disputes in Construction Industry, International
Journal of Science and Research (IJSR), 4(5), 848-56, May, 2015.
Kisi, K. P., Lee, N., Kayastha, R., Kovel, J., Alternative Dispute Resolution Practices in International Road
Construction Contracts, Journal of Legal Affairs and Dispute Resolution in Engineering and
Construction. 12(2), May, 2020.
Komurlu, R., and Arditi, D., The Role of General Conditions Relative to Claims and Disputes in Building
Construction Contracts, New Arch-International Journal of Contemporary Architecture, 4(2), 27-36,
August, 2017.
Madubela, A., Kusile Power Station to be Completed by 2025 within its R161bn Budget, says Mabuza, June. Retrieved
from https://www.news24.com/fin24/economy/eskom/kusile-power-station-to-be-completed-by-2025-
within-its-r161bn-budget-says-mabuza-20210617/ on 19 June, 2021.
Maqsoom, A., Choudhry, R. M., Umer, M., and Mehmood, T., Influencing Factors Indicating Time Delay
in Construction Projects: Impact of firm Size and Experience, International Journal of Construction
Management, 1-12, May, 2019.
Noushad, M., Thomas, A. V., and Ramawsamy, K. P., Evaluation of Dispute Prone Areas in Construction
Projects. AIJR Proceedings, 11:62-8, April, 2021.
Parchami, J. M., Noorzai, E., and Yavari, R. T., Root Cause Analysis of the Most Frequent Claims in the
Building Industry through the SCoP3E Ishikawa Diagram, Journal of Legal Affairs and Dispute
Resolution in Engineering and Construction, 11(2), May, 2019.
Parikh, D., Joshi, G. J., and Patel, D. A., Development of Prediction Models for Claim Cause Analyses in
Highway Projects, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction,
11(4), November, 2019.
Phahla, E., Medupi Timeline: Costs, Delays Spiralling - No Completion in sight, Aug, 2015. Retrieved from
https://www.news24.com/fin24/BizNews/Medupi-timeline-Costs-delays-spiralling-no-completion-in-
sight-20150806 on 2 November, 2019.
Pourhashemi, S. M., Azali, S. T., Ghorbani, M., and Khorasani, E., A Review on the Risk Analysis and
Construction Claims in Tehran Underground Projects, InTunnels and Underground Cities:
Engineering and Innovation meet Archaeology, Architecture and Art, 4547-4557, April, 2019.
Rothengatter, W., Megaprojects in Transportation Networks, Transport Policy,75:A1-5, March, 2019.
Saad, A. S., Operational Framework to Settle Contractual Claims in Construction Projects, August, 2017.
Retrieved from http://etd.cput.ac.za/bitstream/20.500.11838/2521/1/214129667-Saad-
Awad%20Saad%20Abdulla-M.Const-Construction-Eng-2017.pdf on June 11, 2021.
Sakate, P., Dhawale, A.W., Dispute Resolution Mechanism in Commercial Construction Projects: A
Review, International Journal Of Engineering Sciences & Research Technology, 6(2), 84-8, February,
2017.
Shen, Q., Wang, J., Li, Y., and Wang, L., Railway Risk Assessment of the EPC General Contract in
Ethiopia Based on the Improved Fuzzy Comprehensive Evaluation Method, ICCREM 2016: BIM
Application and Off-Site Construction. Reston, VA: American Society of Civil Engineers,1376-1387,
June, 2017.

CON-27-5 © 2021 ISEC Press


El Baradei, S., Abodonya, A., Singh, A., and Yazdani, S. (eds.)

Shrestha, P. P., and Neupane, K. P., Identification of Geotechnical-Related Problems Impacting Cost,
Schedule, and Claims on Bridge Construction Projects, Journal of Legal Affairs and Dispute
Resolution in Engineering and Construction, 12(2), May, 2021.
Tshidavhu, F. and Khatleli, N., An Assessment of The Causes of Schedule and Cost Overruns in South
African Megaprojects: A Case of the Critical Energy Sector Projects of Medupi and Kusile, Acta
Structilia, 27(1), 119-43, June, 2020.
Xue, J., Shen, G. Q., Yang, R. J., Wu, H., Li, X., Lin, X., and Xue, F., Mapping the Knowledge Domain of
Stakeholder Perspective Studies in Construction Projects: A bibliometric approach, International
Journal of Project Management, 38(6), 313-26, August, 2020.
Yelland, C., The Crisis at Kusile and Medupi Continues, moneyweb.co.za, July, 2019. Retrieved from
https://www.moneyweb.co.za/news/south-africa/the-crisis-at-kusile-and-medupi-continues/ on April
14, 2021.
Zaneldin, E. K., Investigating the Types, Causes and Severity of Claims in Construction Projects in the
UAE, International Journal of Constrution Management, 20(5), 385-401, September, 2020.

CON-27-6 © 2021 ISEC Press

View publication stats

You might also like