Professional Documents
Culture Documents
A. Navarra
To cite this article: A. Navarra (2016) Automated scheduling and scientific management
of copper smelters, Mineral Processing and Extractive Metallurgy, 125:1, 39-44, DOI:
10.1179/1743285515Y.0000000018
Article views: 57
Download by: [University of Sussex Library] Date: 05 June 2016, At: 20:48
Automated scheduling and scientific
management of copper smelters
A. Navarra*
The Altonorte Smelter implemented a daily scheduling algorithm in 2013, which has now been
generalised for all conventional copper smelters. It applies a combinatorial search, in which the
possible converter feeding sequences are evaluated using a greedy heuristic; the daily schedule
is then constructed using the heuristically optimal sequence. Depending on the mode of oper-
ation, the objective may be to maximise copper production, maximise profits or control con-
centrate stockpiles. This combinatorial greedy approach has been incorporated within discrete
event simulations, which mimic hundreds of days of operation, hence analysing alternate modes
Downloaded by [University of Sussex Library] at 20:48 05 June 2016
1 Interaction between smelting furnaces and Peirce–Smith converters creates semidiscrete dynamics
3 Converting schedule takes into account plant and market conditions, as well as mode of operation, and is used to construct
complete schedule
40 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2016 VOL 125 NO 1
Navarra Copper smelters
4 Continued feeding of Converter i, even after converting process has begun; similarly for Converter j
In general, a greedy algorithm applies a unidirectional objective would be to maximise profits, hence consider-
traversal, always making decisions that maximise short- ing operational costs, such as oxygen consumption,
term yield, ignoring the possibility that a short-term offgas handling and crane motions. Certain objectives
sacrifice might lead to a net benefit (Cormen et al., 2001; may be to maximise the consumption of a particular feed
Ruiza and Stützle, 2008). (e.g. a high arsenic concentrate) in order to control
The method obtains the starting time of the first batch stockpiles. In general, a smelter may define several
t1, which is to be performed in converter i, modes of operation, which are distinguished by the
various objectives, as well as the constraint parameters
t1 ¼ max tBIC
1 ; t1 ; t1 ; t1
CA MPC OHC
ð1Þ (Navarra and Acuña, 2013).
The combinatorial greedy algorithm identifies the best
where tBIC
1 is the earliest starting time for the first cycle sequence for the given operational mode. This sequence
that would not violate the BIC restriction; likewise, tCA 1 ,
Downloaded by [University of Sussex Library] at 20:48 05 June 2016
Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2016 VOL 125 NO 1 41
Navarra Copper smelters
coefficient of variation 0.1 resulted in Gantt charts that zero and cycles through the top row of Fig. 6. The daily
are typical of actual operations (Ek and Olsson, 2009). schedule is produced as the entity passes through the
Of course, the technique presented in this paper is VBA block, and the subsequent submodel uses sto-
readily adaptable to observed plant data. chastic simulation to mimic the actual daily operations.
Following the converting cycles, the batches of blister The entity then waits until the next scheduling event, as
copper are coupled together, so that each couple forms a a copy of the converter Gantt information is used to
single fire refining batch, which is a common industrial simulate the downstream operations. (The second row of
practice. There are always two identical refining fur- Fig. 6 is thus a standard use of Arena, in which entities
naces, functioning in parallel. Each furnace has an represent refining batches. Once again, each refining
expected fire refining rate of 100 T Cu h21, following a batch is composed of two converting batches.)
Gaussian distribution with a standard deviation of 20 T Figure 7 compares a simulated scheduling period of
Cu h21. Such a large standard deviation is typical of mode A to one of mode B. The black lines represent the
smelters that have not installed a converting end point scheduled production for the given period, whereas the
control system (Prietl et al., 2005). shaded bars represent the actual production. The
To simulate the system described in Tables 1 and 2, difference between the scheduled and actual production
the combinatorial greedy algorithm has been im- is due to the probabilistic variation in converting times
plemented within Rockwell Arena; this is a common (Table 2), as can be observed in actual plant data
DES software that has previously been used for smelter (Ek and Olsson, 2009).
analysis (Coursol and Mackey, 2009). The scheduling For both modes, converter 1 has a batch from the 149th
algorithm has been programmed using Arena’s internal day that extends into the 150th day; additionally, mode A
implementation of VBA (Seppanen, 2000). has a carryover from converter 2. Indeed, the combina-
The DES model considers two types of entities. First, torial greedy algorithm uses these batches to define the
a single entity represents an extensible Gantt chart of the initial conditions for the 150th scheduling period.
converter operations. This Gantt entity is created at time In Fig. 7, mode A exhibits a 97.6% utilisation of the
offgas handling equipment. There are only two intervals,
Table 1 Matte production
from 13.2 to 14.1 h and from 23.7 to 24.0 h, in which a
single batch is being processed; during these brief times,
Grade Copper per ladle Max. production rate the overall throughput is limited by the matte pro-
duction, instead of the offgas handling. For mode B,
Mode A Low 10 T 3 ladles h21 there are seven different periods in which the matte
Mode B High 12 T 2 ladles h21
production is the limiting factor, corresponding to an
81.4% utilisation of the offgas handling equipment. This
Table 2 Converter production comparison is reaffirmed in Table 3, showing that mode
B does not fully utilise the offgas capacity.
Converter Table 3 summarises the results of 300 simulated days,
using randomly generated initial conditions (Navarra
1 2 3 4 and Mendoza, 2013); 20 replicas were performed on
each of the two modes, showing that mode B produces
Initial charge (ladles) 7 4 4 4
Total charge (ladles) 10 6 6 6
*15% more copper anodes than mode A. In both cases,
Preparation time (h) 1.5 1 1 1 the utilisation of the refining furnaces is remarkably low;
Expected converting time* for mode A (h) 8 6 6 6 scheduling algorithms may be designed to anticipate low
Expected converting time* for mode B (h) 7 5 5 5 usage of refining furnaces (Navarra and Mendoza, 2013;
* Assume a Gaussian distribution with coefficient of variation
Pradenas et al., 2011), to decide when to deactivate a
of 0.1. furnace, hence to control operating costs.
42 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2016 VOL 125 NO 1
Navarra Copper smelters
Anode production (thousands of tons) Utilisation of offgas handling equipment/% Utilisation of refining furnaces/%
Mode B is far more productive than mode A, even As an alternative to combinatorial greedy scheduling,
though it does not fully utilise the offgas capacity. This type a more advanced approach has been proposed, which
of observation is counter to conventional wisdom, which hybridises constraint programming (CP) and mixed
would expect a positive correlation between copper pro- integer linear programming (MILP) (Navarra and
duction and offgas utilisation. This is not always true in Acuña, 2013; Maravelias and Grossmann, 2004), hence
practice, however, due to operational dynamics, and sec- to harmonise the thermochemistry with the operational
ondary phenomena such as offgas dilution (Navarra and dynamics. The CP-MILP approach can sustain a rich
Kapusta, 2009). Furthermore, a converting strategy is description of operational modes, coordinating key
generally suboptimal if it does not simultaneously coordi- operating costs, such as oxygen injection and combus-
nate upstream operations (drying, smelting, etc.), down- tibles (Navarra and Kapusta, 2009). Nonetheless, the
stream operations (refining, casting, etc.) and ancillary efficacy of CP-MILP hybrids depends on internal
equipment (offgas handling, slag cleaning, etc.). heuristics to rapidly identify and discard suboptimal
solutions. For this purpose, it is useful to incorporate
the combinatorial greedy algorithm into a CP-MILP
Future work hybrid.
Computerised scheduling is fundamental to the manage- The approach demonstrated in this paper is suffi-
ment of copper smelters. This insight can be used to revisit ciently general to be adapted to all conventional copper
previous approaches, such as the ‘smart smelter concept’ smelters. Moreover, the concepts of automated sche-
(Guo, 2003) and the ‘profit adviser’ (Navarra and Kapusta, duling and scientific management can be adapted to
2009). The DES can include features that are of particular other metallurgical systems. The author of this paper is
interest to individual smelters, including unscheduled committed to working with metal producers, as well as
events (Campbell et al., 2013), such as equipment break- related suppliers, consulting firms and information
downs, irregular feeds and mitigating tactics. systems specialists.
Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2016 VOL 125 NO 1 43
Navarra Copper smelters
44 Mineral Processing and Extractive Metallurgy (Trans. Inst. Min. Metall. C) 2016 VOL 125 NO 1