Professional Documents
Culture Documents
Steam System Design and Commissioning Guidance: Precommissioning Checklist
Steam System Design and Commissioning Guidance: Precommissioning Checklist
PRECOMMISSIONING CHECKLIST
1. Boiler installation
______ Ensure SRV and SRV tail pipes on each boiler vented to outside
boiler room.
______ Ensure sight glass assemblies and pressure gauges are installed on
each boiler.
______ Ensure combustion air ducting and hot exhaust venting are installed.
______ Ensure fuel train assemblies are installed on each boiler.
______ Ensure blowoff valves/piping is installed on each boiler to blow off
separator.
______ Ensure main power supply to boiler panel(s) is installed.
______ Ensure steam outlet valves and piping are installed to main steam
header.
______ Ensure boiler feed water line is piped to the boiler(s).
2. Feed water tank installation
______ Ensure tank sight glass and thermometer assemblies are installed.
______ Ensure level control system is installed.
______ Ensure preheat steam source/controls are installed.
______ Ensure condensate return piping to the tank is installed to tank.
Process Steam Systems: A Practical Guide for Operators, Maintainers, and Designers,
First Edition. Carey Merritt.
© 2016 John Wiley & Sons, Inc. Published 2016 by John Wiley & Sons, Inc.
294 STEAM SYSTEM DESIGN AND COMMISSIONING GUIDANCE
______ Ensure tank is vented to atmosphere (for DA, make sure you can see
vent plume).
______ Ensure feed water pumps and controls are installed and piped to the
boiler.
______ Ensure makeup water source is piped to the tank.
3. Blowoff separator installation
______ Ensure blowoff separator vent line is installed in a safe manner.
______ Ensure blowoff separator drain line is installed to a safe location.
______ Ensure blowoff drain water is cooled to less than 140°F, manually or
automatically.
4. Water treatment system installation
______ Ensure boiler blowdown scheme will keep the boiler TDS at or below
the warranty limits.
______ Ensure the boiler has ample corrosion, fouling, and scaling protection
via chemical or nonchemical means.
______ Ensure there is a boiler sample valve installed.
5. Steam delivery system installation
______ Ensure steam boiler outlets are piped to the main steam header.
______ Ensure all valves and sensors are installed in the steam piping.
______ Ensure there is a means to dump steam for boiler testing and over
pressure protection.
6. Condensate system installation
______ Ensure all steam using equipment is trapped.
______ Ensure the condensate return lines all cascade to a collection tank or
the condensate is discarded.
______ Ensure there are sample locations installed in the condensate lines.
Commissioning Engineer_______________________
______________________________________________________________
______________________________________________________________
______________________________________________________________
______________________________________________________________
______________________________________________________________
_________________________________________________________
b. Verify the feed water tank (for pressurized DA only) is being maintained at
3–5 psig and the stored water temperature corresponds to that pressure.
c. Record the feed water tank temperature (for atmospheric tanks) and deter-
mine the residual oxygen concentration.
d. Verify the residual oxygen is rendered harmless by water treatment chemical
additions.
e. Verify the makeup water level control system keeps the feed water tank
level within the sight glass visible range.
f. Verify the feed water pumps operate without cavitation and are able to keep
the boiler(s) full of water.
g. Verify the feed water pump discharge pressure puts the pump operation in
the correct part of the pump curve.
h. If the feed water tank is equipped with a steam injection system, verify the
steam injection is adjusted to keep the tank greater than 190 and less than 210°F.
i. Verify the tank can be drained to a safe location.
5. Commissioning the condensate system
a. Verify condensate traps of the right size and type are installed for each piece
of steam using equipment.
b. Verify there are condensate drain valves installed that will allow cold con-
densate to be drained during startup periods.
c. Verify the steam traps are functioning properly and not causing water log-
ging of the steam equipment.
d. Verify the condensate receivers and pumps are functioning properly.
e. Verify the surge tank (if installed) is logic tied to the feed water tank and
level control is being maintained in both.
f. Verify adequate temperature sensors/gauges are installed to allow for steam
trap performance monitoring.
6. Commissioning the water treatment systems
a. Verify the boiler blowdown scheme is keeping the boiler solids level within
warranty limits.
b. Verify the boiler oxygen level is being maintained at less than .005 cc/l.
This can be done by showing a residual level of oxygen scavenging chemical
in the boiler.
c. Verify the chemical feed pumps and tanks are installed and being operated
by competent operators.
d. Verify the chemical feed pumps are delivering enough water treatment
chemicals to the steam system to protect the equipment.
e. Verify each chemical storage tank is clearly labeled with the chemical
contained in the tank.
f. Verify there is a safety shower/eyewash station in the vicinity of the
chemical treatment area.
STEAM SYSTEM DESIGN CHECKLIST 297
Steam Load
1. Calculated load Btus / 34,500 Btu/bhp = __________ BHP
2. Pick up losses (30%), total steam requirement is BHP × 1.3 = __________
BHP