QUESTIONS ON Basic Construction Safety: Quiz SAF102 - B37 DECEMBER 1, 2021
QUESTIONS ON Basic Construction Safety: Quiz SAF102 - B37 DECEMBER 1, 2021
a) How much does it cost per month without the painter and finisher?
b) How much is the TOTAL BUDGET required for PPE?
c) If the project is extended for another 3 months, how much is the upgraded PPE budget?
d) How much does extension of construction time cost per month with finishing and painting added?
e) What is the percentage increase of PPE cost over the original (6) months project duration?