SCHEDULE OF PIPING WORK ( UNILEVER )

No Pekerjaan
1 Piping Installation
1.1 Site Preparation
1.1.1 Mobilization Personal ( refer to man power loading )
1.1.2 Site Office
1.1.2.1 Mobilization of Site Office Container
1.1.2.2 Electric Power Installation
1.1.2.3 Water Installation
1.1.2.4 Office tools mobilization (furniture ,computer set , water dispenser , etc.)
1.1.3 Workshop
1.1.3.1 Panel Mobilization
1.1.3.2 Electric Power Installation
1.1.3.3 Mobilization of equipment ( refer to equipment load schedule )
1.2 Pipe Pre Pabrication
1.2.1 Pipe Support Foundation
1.2.1.1 Cooling Water pipe
1.2.1.1.1 Manual Excavation ( if needed , refer to drawing )
1.2.1.1.2 Rebar production ( if needed , refer to drawing )
1.2.1.1.3 Foundation (Anchor / Dyna Bolt / Pouring Concrete refer to drawing)
1.2.1.2 Carbon Steel Process Pipe
1.2.1.2.1 Manual Excavation ( if needed , refer to drawing )
1.2.1.2.2 Rebar production ( if needed , refer to drawing )
1.2.1.2.3 Foundation (Anchor / Dyna Bolt / Pouring Concrete refer to drawing)
1.2.1.3 Stainless Pipe
1.2.1.3.1 Manual Excavation ( if needed , refer to drawing )
1.2.1.3.2 Rebar production ( if needed , refer to drawing )
1.2.1.3.3 Foundation (Anchor / Dyna Bolt / Pouring Concrete refer to drawing)
1.2.1.4 VIP Pipe
1.2.1.4.1 Manual Excavation ( if needed , refer to drawing )
1.2.1.4.2 Rebar production ( if needed , refer to drawing )
1.2.1.4.3 Foundation (Anchor / Dyna Bolt / Pouring Concrete refer to drawing)
1.2.2 Pipe Pabrication
1.2.2.1 Cooling Water pipe
1.2.2.1.1 Pipe support production
1.2.2.1.2 Spool Production ( as per isometric drawing)
1.2.2.1.3 Sandblasting
1.2.2.1.4 Painting ( prime coat)
1.2.2.2 Carbon Steel Process Pipe
1.2.2.2.1 Pipe support production
1.2.2.2.2 Spool Production ( as per isometric drawing)
1.2.2.2.3 Sandblasting
1.2.2.2.4 Painting ( prime coat)
1.2.2.3 Stainless Pipe
1.2.2.3.1 Pipe support production
1.2.2.3.2 Spool Production ( as per isometric drawing)
1.2.2.3.3 Pipe Cleaning
1.2.2.4 VIP Pipe
1.2.2.4.1 Pipe support production
1.2.2.4.2 Spool Production ( as per isometric drawing)
1.2.2.4.3 Sandblasting
1.2.2.4.4 Painting ( prime coat)
1.3 Cooling Water pipe
1.3.1 Outsite the compressor building
1.3.1.1 Predecessor ( foundation ready to be loaded)
1.3.1.2 Install Support
1.3.1.3 Pipe Assembly
1.3.1.4 Finishing (Top Coat Painting and Foundation Grouting)
1.3.2 Insite the building except Expander Area
1.3.2.1 Predecessor ( foundation ready to be loaded)
1.3.2.2 Install Support
1.3.2.3 Pipe Assembly
1.3.2.4 Finishing (Top Coat Painting and Foundation Grouting)
1.4 Carbon Steel Process Pipe
1.4.1 Outsite The Compressor Building
1.4.1.1 Predecessor ( foundation ready to be loaded)
1.4.1.2 Install Support
1.4.1.3 Pipe Assembly
1.4.1.4 Finishing (Top Coat Painting and Foundation Grouting)
1.4.2 Insite The Building Except Expender Area
1.4.2.1 Predecessor ( foundation ready to be loaded)
1.4.2.2 Install Support
1.4.2.3 Pipe Assembly
1.4.2.4 Finishing (Top Coat Painting and Foundation Grouting)
1.5 Stainless Pipe
1.5.1 Outsite The Compressor Building
1.5.1.1 Predecessor ( foundation ready to be loaded)
1.5.1.2 Install Support
1.5.1.3 Pipe Assembly
1.5.1.4 Finishing (Top Coat Painting and Foundation Grouting)
1.5.2 Insite The Building Except Expender Area
1.5.2.1 Predecessor ( foundation ready to be loaded)
1.5.2.2 Install Support
1.5.2.3 Pipe Assembly
1.5.2.4 Finishing (Top Coat Painting and Foundation Grouting)
1.6 VIP Pipe
1.6.1 Predecessor ( foundation ready to be loaded)
1.6.2 Install Support
1.6.3 Pipe Assembly
1.6.4 Finishing (Top Coat Painting and Foundation Grouting)
1.7 Pipe Pressure Test
1.7.1 Segment Cooling Water pipe ( Group Test Package A )
1.7.1.1 Blowing
1.7.1.2 Water Filling
1.7.1.3 Hydrotest
1.7.1.4 De-watering
1.7.1.5 Cleaning
1.7.1.6 Purging ( if needed)
1.7.2 Segment Carbon Steel Process Pipe ( Group Test Package B )
1.7.2.1 Blowing
1.7.2.2 Water Filling
1.7.2.3 Hydrotest
1.7.2.4 De-watering
1.7.2.5 Cleaning
1.7.2.6 Purging ( if needed)
1.7.3 Segment Stainless Pipe ( Group Test Package C )
1.7.3.1 Blowing
1.7.3.2 Water Filling
1.7.3.3 Hydrotest
1.7.3.4 De-watering
1.7.3.5 Cleaning
1.7.3.6 Purging ( if needed)
1.7.4 Segment VIP Pipe ( Group Test Package D )
1.7.4.1 Blowing
1.7.4.2 Water Filling
1.7.4.3 Hydrotest
1.7.4.4 De-watering
1.7.4.5 Cleaning
1.7.4.6 Purging ( if needed)
K ( UNILEVER )

Total Waktu Pengerjaan Mulai Selesai


192 2/8/2024 8/17/2024
15 1/15/2024 1/29/2024

15 1/15/2024 1/29/2024

15 1/15/2024 1/29/2024

60 2/8/2024 4/7/2024
121 3/30/2024 7/28/2024
120 3/30/2024 7/27/2024

90 4/30/2024 7/28/2024

126 3/25/2024 7/28/2024


120 3/25/2024 7/22/2024

90 4/30/2024 7/28/2024

90 4/29/2024 7/27/2024
90 4/29/2024 7/27/2024

40 5/30/2024 7/8/2024

40 5/30/2024 7/8/2024

30 7/19/2024 8/17/2024
MAN POWER LOADING SCHEDULE OF PIPING WORK ( UNILEVER )

No PERSONIL Qty M1 M2 M3
1 Project Manager 1 1 1 1
2 Construction Manager 1 1 1 1
3 HSE 2 1 2 2
4 Project Control 1 1 1 1
5 Material Control / Gudang 1 1 1 1
6 Project Admin if neeeded 1 1 1 1
7 QC 1 0 1 1
8 Welder 10 5 10 10
9 Fitter 10 5 10 10
10 Helper 20 10 20 20
11 Paint Applicator 1 0 0 1
12 Helper Painting 2 0 0 2
13 Tukang Sipil 3 1 2 3
14 Helper Sipil 6 2 4 6
15 Umum 2 1 1 2
16 Insulation applicator 3 0 0 3
17 Insulation helper 6 0 0 6
)

M4 M5 M6
1 1 1
1 1 1
2 2 1
1 1 1
1 1 1
1 1 1
1 1 1
10 5 2
10 5 2
20 10 4
1 1 1
2 2 2
3 3 3
6 6 6
2 2 1
3 3 3
6 6 6
EQUIPMENT LOADING SCHEDULE OF PIPING WORK ( UNILEVER )
No PERSONIL Qty M1 M2 M3 M4
1 Mesin Welding 15 5 10 10 10
2 Mesin Cutting Plasma 2 1 1 2 2
3 Mesin Gerinda 32 16 32 32 32
4 Mesin Gerinda 15 5 5 15 15
5 Mesin Gerinda 3 1 1 3 3
6 Mesin Bor Tangan 2 1 1 2 2
7 Mesin Bor Duduk 2 1 2 2 2
ILEVER )
M5 M6
5 2
1 1
32 10
15 5
1 1
2 1
2 1