PROJECT SCHEDULE MAN POWER
Week TOTAL
NO. DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 MAN WEEK
A. INDIRECT
Site Manager 1 1 1 1 1 1 1 1 1 1 1 0
Project Control 1 1 1 1 1 1 1 1 1 1 1 0
Supervisor Mechanical Piping 1 1 1 1 1 1 1 1 1 1 1 0
HSE Man / Coordinator 0 1 1 1 1 1 1 1 1 1 1 1
QC Inspector 0 1 1 1 1 1 1 1 1 1 1 1
QC admininstrasi 0 1 1 1 1 1 1 1 1 1 1 1
Document Control 0 1 1 1 1 1 1 1 1 1 1 1
SUBTOTAL A. 3 6 6 6 6 6 6 6 6 6 6 3 66

A. INDIRECT
Welder Piping 3 4 5 8 8 8 8 8 8 8 5 4
Fitter 3 4 5 8 8 8 8 8 8 8 5 4
Helper 10 12 14 16 16 16 16 16 16 14 12 10
Painter 0 0 0 0 0 0 0 0 2 2 2 2
Wrapper 0 1 1 1 0 0 0 0 0 0 0 0
maintenance operator 1 1 1 1 1 1 1 1 1 1 1 1
Technisi Hydrotest 0 0 0 0 0 0 0 0 1 1 1 1

SUBTOTAL B 17 22 26 34 33 33 33 33 36 34 26 22 349
TOTAL MAN POWER 20 28 32 40 39 39 39 39 42 40 32 25
Client : PT. Sanggar Sarana Baja
Project : Pekerjaan Diesel Fuel Storage Tank 4x45
Date : 21 Desember 2018

Week
NO. DESCRIPTION Unit Remark's
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 Mobil 4WD Unt 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Mesin Mixer Molen unit 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1
3 Excavator unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Wales unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Mesin Stamper unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Crane 25 Ton unit 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0
7 Mesin Trowel unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 Theodolite unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 Pilling Hydraulic unit 0 0 0 0 0 0 0 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0
10 Linggis, Pacul, Sekop Lot 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
11 Gerobang angkong Sorong unit 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4 4
12 welding Machine Unt 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
13 Catut Tekung Bending Unt 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
14 Compresor Unt 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
15 Magnetik Drill Unt 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2
16 Lever Block Unt 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 4 4 4 4 4 4 3 3
17 Chain Blok 1, 2, 3, 5 ton Unt 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 4 4 4 4 4 4 3 3
18 Elektrical Drill & Hand Drill Unt 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
19 Kabel Roll set 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
20 Stop Kontak set 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
21 Mesin Gerinda 4" dan 6" Lot 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
22 Stang dan selang Blender set 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
23 Regulator Oxygen & LPG Lot 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
24 Kunci Ring Pas set 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
25 Stang dan kabel las Set 4 4 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 4 4
TOTAL Set 56 56 56 56 59 59 59 61 70 70 70 70 63 63 63 63 70 70 70 70 67 67 58 58
Note : Equipment ini untuk 1 Lokasi