JADWAL PELAKSANAAN PEKERJAAN

1 Pekerjaan Rehabilitasi Jaringan Irigasi DI. Cigasong


S C H E D U L E
JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Bobot 05 12 19 07 14 21 28 05 12 19 26
Jenis Barang/Jasa Vol Sat 29 August - 26 31 October -
(%) 01 August - 08 August - 15 August - 22 August - September - September - September - 03 October - 10 October - 17 October - 24 October - November - November - November - November - December - December - December - December -
09 July - 10 11 July - 17 18 July - 24 25 July - 31 04 September - 06
07 August 14 August 21 August 28 August 11 18 25 09 October 16 October 23 October 30 October 13 20 27 04 11 18 25 30
July 2021 July 2021 July 2021 July 2021 September 02 October November
2021 2021 2021 2021 September September September 2021 2021 2021 2021 November November November December December December December December
2021 2021 2021
2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021
I PEKERJAAN PERSIAPAN
99,68 100,0 100,00
1 Papan Nama Proyek 1,00 m2 0,02% 0,0002
98,68 99,38
2 Foto Dokumentasi menggunakan camera digital tanpa film 1,00 set 0,11% 0,0011
3 Uitzet/Pengukuran 1,00 ls 0,33% 0,0033 96,57
II SMK3 -
1. Penyiapan RK3K terdiri atas - - 93,51 93,76
a. Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja 1,00 set 0,04% 0,0004
b. Pembuatan Kartu Identitas Pekerja (KIP) 40,00 org 0,01% 0,0001 90,00
2. Sosialisasi dan Promosi K3 terdiri atas -
89,36 89,65
a. Induksi K3 (Safety Induction ) 40,00 org 0,01% 0,0001
Pengarahan K3 (safety briefing) Pertemuan Keselamatan (Safety Talk dan/atau Tool Box 86,18
b.
Meeting)
40,00 org 0,02% 0,0002 85,21
c. Pelatihan K3 -
Analysis Keselamatan Pekerjaan 40,00 org 0,02% 0,0002 82,67
Perilaku Berbasis Keselamatan (Budaya K3) 40,00 org 0,02% 0,0002 81,04 80,00
P3K 2,00 org 0,01% 0,0001
d. Simulasi K3 40,00 org 0,03% 0,0003 78,26
e. Spanduk (banner) 3,00 lb 0,01% 0,0001 76,84
f. Papan Informasi K3 2,00 bh 0,01% 0,0001
74,43
3. Alat Pelindung Kerja dan Alat Pelindung Diri terdiri atas -
a. Tali Keselamatan (Life Line) 2,00 ls 0,02% 0,0002 71,97
b. Penahan Jatuh (Safety Deck) 2,00 ls 0,02% 0,0002 70,58 70,00
c. Topi Pelindung (Safety Helmet) 40,00 bh 0,02% 0,0002
d. Pelindung Mata (Goggles, Spectacles) 20,00 psg 0,01% 0,0001
66,98
e. Pelindung Pernafasan dan Mulut (Masker) 20,00 bh 0,00% 0,0000
66,56
f. Sarung Tangan (Safety Gloves) 20,00 psg 0,01% 0,0001
g. Sepatu Keselamatan (Safety Shoes) untuk Staf 20,00 psg 0,02% 0,0002
h. Rompi Keselamatan (Safety Vest) 40,00 bh 0,01% 0,0001
60,81
60,77 60,00
5. Asuransi dan Perijinan terdiri atas - 31
BPJS Ketenagakerjaan dan Kesehatan Kerja (BERDASARKAN KEPMENAKER
a. 1,00 ls 0,26% 0,0026 32
NOMOR KEP-196/MEN/1999, untuk Tenaga harian Proyek)
b. Surat Ijin Pengesahan Panitia Pembina Keselamatan dan Kesehatan Kerja (P2K3) 1,00 ls 0,04% 0,0004 33
Fasilitas sarana kesehatan Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat
6. 1,00 ls 0,04% 0,0004 34
Luka, Perban, dll)
7. Rambu- Rambu terdiri atas - 54,03
53,57 35
a. Rambu Petunjuk 3,00 bh 0,02% 0,0002
b. Rambu Larangan 3,00 bh 0,02% 0,0002
50,00
c. Rambu Peringatan 3,00 bh 0,02% 0,0002
d. Rambu Kewajiban 3,00 bh 0,02% 0,0002
e. Rambu Informasi 2,00 bh 0,01% 0,0001
46,97
46,27
8. Lain- Lain Terkait Pengendalian Risiko K3 -
a. Bendera K3 1,00 bh 0,00% 0,0000
b. Jalur Evakuasi (Escape Route ) 1,00 ls 0,01% 0,0001 41,90
c. Lampu Darurat (Emergency Lamp ) 1,00 bh 0,01% 0,0001 40,00
d. Pelaporan dan Penyelidikan Insiden. 1,00 ls 0,02% 0,0002 38,27 31
III. PEKERJAAN POKOK - 33
A. PEKERJAAN BANGUNAN DAN LINING SALURAN 34
1. Galian tanah biasa sedalam 0 s.d. 1 m 2.121,74 m3 2,39% 0,0011 0,0013 0,0015 0,0012 0,0012 0,0011 0,0010 0,0008 0,0015 0,0029 0,0007 0,0014 0,0011 0,0011 0,0018 0,0017 0,0007 0,0008 0,0004 0,0005 35
2. Galian tanah berbatu sedalam 0 s.d. 1 m 155,21 m3 0,27% - - - 0,0009 0,0008 0,0011 - 32,52- - - - - - - - - - - - -
3. Timbunan tanah atau urugan tanah kembali termasuk perataan dan perapihan 59,56 m3 0,33% - - - - - - - 31,27- 0,0033 - - - - - - - - - - -
4. Timbunan tanah atau urugan tanah kembali termasuk perataan dan perapihan 647,84 m3 0,46% - - - - - - 0,0004 - 0,0004 0,0006 0,0006 0,0011 0,0007 0,0003 - 0,0004 - - - - 30,00
5. Timbunan tanah atau urugan tanah (mendatangkan) termasuk perataan dan perapihan 1.043,46 m3 2,85% - - - - - - - - - - - - - - - 0,0015 0,0115 0,0038 0,0117 -
6. Bongkar pasangan batu dan Pembersihan Batu (manual) 999,75 m3 3,07% - - 0,0037 0,0022 0,0044 0,0031 0,0047 0,0031 0,0056 - 0,0010 0,0008 0,0022 - - - - - - -
Mortar tipe N (mutu PP tertentu setara dengan campuran 1 PC4 PP) Menggunakan
7. 2.333,39 m3 44,82% - - 0,0151 0,0079 0,0121 0,0131 0,0250 0,0247 0,0446 0,0357 0,0189 0,0150 0,0163 0,0145 0,0227 0,0271 0,0278 0,0257 0,0203 0,0379
Mollen
8. Mortar tipe N (mutu PP tertentu setara dengan campuran 1 PC4 PP) Menggunakan Mollen (Batu Bekas
534,31
Bongkaran
m3 di pakai kembali)
8,58% - - 0,0055 0,0128 0,0136 0,0078 23,74
23,57
0,0155 0,0029 0,0037 - 0,0151 0,0040 0,0048 - - - - - - -
9. Siaran dengan mortar jenis PC-PP tipe M 3.323,65 m2 3,80% - - - - 0,0007 0,0010 0,0014 0,0005 0,0016 0,0013 0,0012 0,0016 0,0022 0,0022 0,0021 0,0025 0,0028 0,0032 0,0018 0,0024
10. Plesteran tebal 1 cm, dengan mortar tipe S, fc = 12,5 MPa (setara 1 PC 3 PP) 1.811,40 m2 2,08% - - - - 0,0006 0,0003 0,0011 0,0004 0,0012 0,0006 0,0010 0,0011 0,0015 0,0023 0,0020 0,0021 0,0014 0,0015 0,0006 0,0003 20,00
11. Pembesian dengan besi polos atau ulir 41.888,13 Kg 10,31% - - - - 0,0057 0,0262 0,0265 0,0447 - - - - - - - - - - - - 32
12. Pembesian Jaring kawat (wire mesh) untuk pelat atau dinding atau Ferrocement 1.161,20 m2 3,21% - - - - - - - - 0,0012 0,0017 0,0071 0,0074 0,0056 0,0071 0,0020 - - - - - 33
13. Beton mutu, fc = 19,3 MPa (K225), slump (122) cm, Menggunakan Molen 423,93 m3 8,13% - - - - - 16,18
16,07- - - 0,0231 0,0080 0,0155 0,0237 0,0110 - - - - - - - 34
14. Beton mutu, fc = 14,5 MPa (K175), slump (122) cm, Menggunakan Molen 129,75 m3 2,24% - - - - - - - - - - 0,0073 0,0070 0,0062 0,0019 - - - - - - 35
15. Bekisting Beton dengan Multiplek 12mm 988,50 m2 3,12% - - - - - 0,0035 - 0,0108 0,0076 - - - 0,0027 0,0067 - - - - - -
16. Perbaikan Pintu B= 30 2,00 Bh 0,22% - - - - 11,13
10,46-
- - - - - - - - - - - 0,0011 - - - -
17. Perbaikan Pintu B= 100 1,00 Bh 0,33% - - - - - - - - - - - - - - - - - - - 10,00
18. Perbaikan Pintu B= 40 1,00 Bh 0,14% - - - - - - - - - - - - - - - - - - - -
19. Pemasangan Handrail 170,00 m 2,07% - - - 6,56 -
6,21 - - - - - - 0,0022 0,0047 0,0073 - 0,0046 0,0019 - - - -
20. Pasangan Bronjong Kawat Pabrikasi - m3 0,00% - - - - - - - - - - - - - - - - - - - -
21. Pekerjaan Borpile K225 dia 400 mm - m2 0,00% - - 4,06 -
3,65 - - - - - - - - - - - - - - - - -
IV. PEKERJAAN PEMBANTU - - - - - - - - - - - - - -
1,24 1,35 -
0,77 1,48
1,15 -
1. Kistdam pasir/tanah 1,00 ls 1,00
0,00
0,0 0,46 - - - - - - - - - - - - 0,0033 - - -
0,00

Rencana Progres Mingguan : 0,00 0,46 0,31 0,38 2,50 2,56 4,92 4,94 7,50 7,70 7,00 8,00 7,30 7,20 5,79 5,41 4,87 4,20 4,17 4,15 4,15 3,06 2,11 0,70 0,30 0,32
Kumulatif Progres Mingguan : 0,00 0,46 0,77 1,15 3,65 6,21 11,13 16,07 23,57 31,27 38,27 46,27 53,57 60,77 66,56 71,97 76,84 81,04 85,21 89,36 93,51 96,57 98,68 99,38 99,68 100,00
Aktuali Progres Mingguan : 0,00 1,24 0,11 0,13 2,58 2,50 3,90 5,71 7,56 8,78 9,37 5,07 7,06 6,78 6,17 3,60 3,85 3,83 4,41 3,51 3,47 4,11 0,00 0,00 0,00 0,00
Kumulatif Aktual Progres Mingguan : 0,00 1,24 1,35 1,48 4,06 6,56 10,46 16,18 23,74 32,52 41,90 46,97 54,03 60,81 66,98 70,58 74,43 78,26 82,67 86,18 89,65 93,76