Professional Documents
Culture Documents
Subject COMMERCE
TABLE OF CONTENTS
1. Learning Outcomes
2. Introduction
9. Summary
Example 1: The Standard quantity of material to produce one unit of Product Y is 8 kg and the standard
price per kg of material is Rs. 5. However, it is observed that the actual material used for production of
2000 units of Product Y is 18,000 kg and actual price paid per kg of material is Rs. 6.
Calculate Material Cost Variance.
Solution:
Standard quantity of material per unit = 8 kg
Standard Price = Rs. 5
Actual quantity used of material = 18,000 kg
Actual Output = 2000 units
Actual Price = Rs. 6
Standard quantity for actual output = Actual Output x Standard quantity of material per unit
= 2000 x 8
= 16,000
Material cost variance = Standard Cost of Material for actual output – Actual Cost of
Material used
= (16,000 x 5) – (18,000 x 6)
= 28,000 (A)
Material Cost Variance can be further sub divided into Material Price Variance and Material Usage /
Quantity Variance.
Material
Material Material
Usage/
price Cost
Quantity
Variance Variance
Variance
Material price variance arises when the firm purchases the raw material at a price different than the
standard price. According to C.I.M.A. London Terminology, ‘‘Material Price Variance is that portion of
material cost variance which is due to the difference between the standard price specified and the actual
price paid.’’
Material price Variance = (Standard price – Actual price) x Actual Quantity
= (SP – AP) x AQ
Thus, MPV is the difference between the Standard price and the Actual price multiplied by actual quantity.
It is favorable when the actual price paid is less than the standard price set to purchase the material and
adverse when the actual price paid is more than the standard price. The quantum of variance is calculated
by multiplying this difference of actual and standard price with the actual quantity used for the production
of finished goods.
It is advisable to calculate MPV in advance that is at the time of purchase of material which is an earlier
event rather than to wait and look for the other material variances in terms of usage and total cost. The idea
is what can be calculated earlier, to be presented faster for early feedback and remedial measures.
Let’s continue with our Example 1 to calculate MPV.
Material price Variance = ( Standard price – Actual price) x Actual Quantity
= (5 – 6 ) x 18,000
= 18,000 (A)
It is favourable when the actual quantity used is less than the standard quantity specified to produce the
actual output and adverse when the actual quantity used is more than the specified standard.
Continuing the Example 1, we can calculate Material Usage Variance as follows:-
MUV / MQV = (SQ – AQ ) x SP
= ( 16,000 – 18,000) x5
= 10,000 (A)
The Material Usage Variance is sub divided into Material Mix Variance and Material Revised Usage
Variance or Material sub- usage Variance.
COMMERCE PAPER NO. 6 ; ACCOUNTING FOR MANAGERIAL DECISIONS
MODULE NO.18 ; MATERIAL VARIANCE - PRACTICAL
____________________________________________________________________________________________________
Material
Mix
Variance
Material
Usage
Variance
Material
Sub Usage
Variance
where, the Revised standard Quantity (RSQ) is the standard proportion of total of actual quantities of all
the materials.
RSQ takes into account the increase or decrease in the pre- determined consumption of material that leads
to different actual consumption. RSQ is calculated as follows:
Standard quantity of one material
RSQ = x Total of actual quantities of all materials
Total of standard quantities of all materials
If the total actual quantities of all the material are equal to total standard quantities of all the material, the
Revised Standard quantity would be same as Standard quantity.
There can be reasons other than those of material mix variance that attributes to material Usage Variance.
This variance takes into account those reasons and undertakes the difference between the Standard Quantity
and Revised Standard Quantity. When there is no difference between the total actual quantities of all the
material and total standard quantities of all the material then the Revised Standard quantity would be same
as Standard quantity resulting into no Material Revised Usage Variance.
It is calculated as follows:
Material Revised Usage Variance = (Standard Quantity- Revised Standard Quantity) x Standard Price
MRUV = (SQ – RSQ) x SP
Example 2: From the data given below, calculate Material Mix variance and Material Revised Usage
Variance.
Material Revised Usage Variance = (Standard Quantity- Revised Standard Quantity) x Standard Price
MRUV = (SQ – RSQ) x SP
MRUVA = (SQ – RSQ ) x SP
=(30 –36) x 50 = 300 (A)
MRUVB = (SQ – RSQ) x SP
= (70 – 84 ) x 40 = 560 (A)
Let us also calculate Material Cost Variance, Material price Variance and Material Usage Variance in this
example.
MCV= [Standard quantity for actual output x Standard Price] – [Actual quantity x Actual price]
Or, MCV = (SQ x SP) – (AQ x AP)
MCVA = ( SQ x SP) – ( AQ x AP)
= (30 x 50) – ( 40 x 50) = 500 (A)
MCVB = ( SQ x SP) – ( AQ x AP)
= ( 70 x 40) – ( 80 x 45) = 800 (A)
MUVA = ( SQ – AQ) x SP
= (30– 40) x 50 = 500 (A)
MUVB = ( SQ – AQ) x SP
= ( 70– 80) x 40 = 400 (A)
20% and standard yield is 80%. It implies that the input of both the raw material of, say, 2,000 kg will
produce 1,600 units of actual output. The actual yield may differ than the standard yield because the actual
loss may differ than the standard loss. Therefore, the material Yield variance is that part of material usage
variance that measures the difference between the standard yield and the actual yield.
Material Yield Variance = (Actual Yield – Standard Yield on actual input) x Standard Output Price
MYV = (AY – SY) x SOP
where, the Standard Output Price is the standard material cost per unit of output
Standard Material Cost
Or, SOP =
Net Standard Output ( i.e., Gross output - Standard Loss )
MYV is favourable when the Actual Yield is more than the Standard Yield and vice- versa. It is to be noted
that out of Material Revised Usage Variance and Material Yield Variance, only one has to be calculated.
The difference between the two is MRUV is an input variance and undertakes gain or loss in the input
quantities of the raw material whereas; the MYV is an output variance as it represents the loss on output of
the finished product.
Solution:
Material Yield Variance = (Actual Yield – Standard Yield on actual input) x Standard Output Price
MYV = (AY – SY) x SOP
4,400
= (65 – 80) x
80
= 825 (A)
It is important to note here that the material input of standard and actual is same, that is, 100 units, that
makes the yield comparable. However, if it is not same then the standard yield should be revised as per the
actual input. Let us take the above example with the changed actual inputs.
Example 4:
Solution:
Material Yield Variance = (Actual Yield – Standard Yield on actual input) x Standard Output Price
MYV = (AY – SY) x SOP
AY = 380
4,400
SOP = = 55
80
Standard Loss = 20% of 100 units = 20 units
Standard yield for actual material mix (500 units) =Actual material mix – standard Loss
= 500 – 20% of 500
= 400
MYV = (380 – 400) x 55
= 1,100 (A)
9. Summary
1. MCV = Standard Cost of Material for actual output – Actual Cost of Material used
Or, MCV= [Standard quantity for actual output x Standard Price ] – [ Actual quantity x Actual price]
Or, MCV = (SQ x SP) – (AQ x AP)
6. Material Revised Usage Variance = (Standard Quantity- Revised Standard Quantity) x Standard Price
MRUV = (SQ – RSQ) x SP
8. Material Yield Variance = (Actual Yield – Standard Yield on actual input) x Standard Output Price
MYV = (AY – SY) x SOP