You are on page 1of 1

Installation instruction Pre-insulated joint sleeves for LV-ABC lines

MJPT...
Crimp the joint, from mark 1 to mark 3 (or mark 6 for neutral
1 Remove insulation as indicated on the product 3 messenger sleeves), and using the die indicated on the product

Strip length
Sleeve for neutral messenger : 2x6 crimping

Sleeve for phase : 2x3 crimping


2 1
3
PN: 2107585-1 Rev A - CREATION - 04/01/12

2 Introduce the cable up to stop 4 Carry out the same operations for the 2nd cable

You might also like