An overview of the complete Metro Manila Subway Project (MMSP) high voltage power distribution system is
given in Figure 1, Figure 3, Figure 4 and Figure 5 for Depot, Traction and Non-Traction (Distribution) Feeding
Arrangements.
Each traction substation (TSS) and Station Substation (SSS) shall receive two separate 34.5kV circuits from
both Bulk Supply Substations (BSS) to be located at Depot and in the region of Lawton West. This is then
distributed around the Metro Manila Subway Project (MMSP) in a Ring Main fashion to each Traction
Substation (TSS) and Station Substation (SSS) located at the stations on the Main Line and in the Depot.
The Traction Substations (TSS) that will transform and rectify the supply from AC to DC and distribute Traction
Power (TP) at 1500 Volts Direct Current (VDC) via Transformer/Rectifier Unit to the Overhead Contact Line
that provides electrical power for the trains.
The Station Substations (SSS) will transform from 34.5kV to 400V AC, three phases via 34.5kV / 400V
distribution transformers located at each station and that will distribute to single phase Low Voltage (LV) 230V
LVAC to provide supply including E&M power equipment, Communications, Signalling, Platform Screen
Doors (PSD), Lifts and any other LV power requirements. However, these will be undertaken by the Civil
Contractors.
The BSS located at Depot is required to be built and ready to bring into in service to provide power supply to
CP101 Partial Operative (P.O) Section to supply the power to the trains and stations via Traction substations
(TSSs), Station Substations (SSSs) for the Main Line and Depot, respectively.
Acquisition Supervisory Control and Data Acquisition (SCADA) system with the operators control equipment,
mimic diagrams and relevant displays installed in the Operations Control Centre (OCC) located in the Depot
and a future Backup Control Centre (BCC) may be installed in the BSS located in the region of Lawton West
location. The actual location of BCC shall be identified and confirmed at the detailed design stage.
In addition, a Substation Automation System (SAS) that integrates directly with the OCC and with future BCC
equipment shall be installed in the region of Lawton West (to be confirmed), with local control at each SSS and
TSS via Remote Terminal Units (RTUs).
In general, the typical spacing between traction substation (TSSs) are installed at an interval of 3 to 5km for
1500V DC, however at this stage of design four TSSs (one for Depot and three for main line) were estimated to
be installed for the CP101 (P.O. Section) of MMSP Line.
The number of TSSs shall be determined through train simulation study based on Rolling Stocks, track profile,
operations plan and operational scenarios. The contractor shall undertake the detailed performance train
simulation studies to determine the actual number of TSSs required to be installed on the MMSP.
POW-4-1
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Station Substations (SSSs) for Non-Traction Power Supply shall be installed at each station for the power supply
to station facilities. Moreover, emergency generator will be also installed at ground level at each station to back
up the emergency loads should the main power supplies fail. However, the Contractors shall also consider and
verify the emergency loads to minimise the number of emergency generators installed at each station, meaning
if one generator can supply the emergency loads of more than one station.
The 34.5kV AC incoming feeders are then in turn connected to the TSSs and distributed to the whole network
installed on the Main Line and Depot, in the Ring format to complete as a loop.
Each TSS will receive 34.5kV power supply from a redundant network as an alternative supply to secure and
maintain their operation even if one of the networks is out of service.
All TSSs are designed and supplied to support the ultimate capacity operation of the MMSP system (10-car
train 5Tc and 5Mc, 2 minutes headway).
The Traction Power Supply at each TSS shall then convert 34.5kV AC to 1500V DC to provide power to the
OCS with DC traction supply at a nominal 1500V DC and return shall be via the running rails and return current
cables.
The 1500V DC Traction Power Substations shall include but not limited to rectifier transformers, rectifiers,
high speed circuit breakers, associated switches, protection, earthing, negative return panels and any other item
required to complete the work.
Incoming Circuit Breakers (CB) of the single pole High Speed Circuit Breakers (HSCB) type shall be installed
between the rectifier group and 1500V DC Positive busbars and shall be interlocked with the traction
transformer incoming CB.
For connecting the negative terminals of the rectifiers with negative busbars, motorized off-load switches,
interlocked with corresponding HSCB & Disconnector Switches shall be provided.
From the 1500V DC positive busbar, feeder HSCB & DC disconnector switches shall be provided to feed power
to the OCS.
The Traction Power Substations shall be designed to install with the Energy Storage System (ESS) using an
advanced technology battery system to capture and convert the disposal energy waste from the trains during
train’s regenerative braking to feed back to the Traction Power Supply system (see also section 4.1.5).
At each SSS, two off 34.5kV/400V distribution transformers shall be installed to provide station facility power.
Moreover, emergency diesel generator will be installed at station at ground level. Contractor shall interface with
Civil Contractors and other third parties for the cable route to 400V LVAC switchboards.
POW-4-2
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The 34.5kV system is designed to ensure that voltage regulation under normal feeding is maintained within +/-
10% of nominal voltage. Contractor is advised to check the voltage regulation to ensure that it is compliant with
the Power Utility Provider MERALCO.
All the 34.5kV switchgear and 34.5kV Ring-Main Unit (RMU) systems are to be designed and supplied to
support the ultimate capacity operation of the MMSP system (10-car train: 5Mc & 5Tc 2 minutes headway) and
the total loads required for station that are being specified by Civil Contractors, for TSS and SSS respectively.
Contractor shall carry out the detailed studies taken into consideration of various scenarios operations to decide
the ‘Open Point’ required on the 34.5kV Ring Circuits for TSS, SSS and Depot. However, the contractor shall
also carry out studies to determine the single end feed if it is achievable for ultimate capacity operation of the
MMSP system (10-car train: 5Mc & 5Tc, 2 minutes headway).
Each location also receives 34.5kV power supply from a redundant network as an alternative supply to secure
and maintain their operation. DC Traction Power Supply shall also be backed up from main line.
The 34.5kV/400V distribution transformers to provide at each location for facility power (see table 1 below).
Moreover, emergency generator also will be installed at three locations namely: Operation Control Centre
(OCC), Training Centre and Philippine Railway Institute (PRI), for emergency loads.
Note to Contractor: It is of interest and priority of Client’s wishes to bring in the Philippine Railway Institute
(PRI) being constructed into service as soon as possible.
POW-4-3
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-4
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-5
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Figure 3: Traction Power Supply Feeding Arrangement with ESS (Option 2A)
POW-4-6
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-7
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-8
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-9
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-10
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-11
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-12
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
* Contractor to verify and confirm the actual required capacity MVA for Main Transformers to be
installed at Bulk Supply Substations to support the ultimate capacity operation of the MMSP system
(10-car train, 2 min headway) and E&M Loads specified by Civil Contractors.
** Transformer Rectifier Unit (TRU) at TSS comprised of 4.2MVA for Traction Transformer and 4 MW
Rectifier. Contractor shall carry out the detailed simulation studies to verify the TRU capacity.
Contractor shall also carry out the detailed studies to assess the capacity of ESS during trains
regenerative braking to assess the capacity of ESS require to install at the TSS. Also confirm if ESSs
capacity are of adequate capacity to replace the rectifier unit (as OPTION 2B shown in Fig. 4).
Note: The Contractor shall undertake the detailed studies to confirm of the required installed capacity for all
the above equipment to support the ultimate capacity operation of the MMSP system (10-car train
comprised of 5Tc and 5Mc, 2 min headway) and E&M Loads specified by Civil Contractors.
Refer to Fig. 3, Fig. 4 and Fig. 5 above titled “Traction Major Line Feeding Arrangement and Non-Traction
Major Line Feeding Arrangement” indicate the number of TSSs and SSSs shall be built at the Final Phase.
Migration from P.O. Section to Final Phase shall be prepared in detailed stages sequence to ensure the maintain
of power supply.
The Contractor shall take the full responsible for the complete design and build of MMSP and interface with all
other main principle Civil Contractors, Power Supply Utility Provider MERALCO and any other third parties.
Number of TSSs and SSSs shown in Fig. 1, 3, 4 & 5 shall be assessed, verified in Contractor’s detailed studies
to confirm the ratings and sizing of the equipment to be installed in each TSS and SSS are of adequate capacity
to support the ultimate capacity operation of the MMSP system (10-car train, 2 minutes headway) and the station
loads required that are being specified by Civil Contractors.
a) Under section 3.2.3.2 - A Short Duration Voltage Variation shall be defined as a variation of the RMS
value of the voltage from nominal Voltage for a time greater than one-half cycle of the power Frequency
but not exceeding 1 minute. A Short Duration Voltage Variation is a Voltage Swell if the RMS value
of the Voltage increases to between 110% and 180% of the nominal value. A Short Duration Voltage
POW-4-13
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Variation is a Voltage Sag (or Voltage Dip) if the RMS value of the Voltage decreases to between 10%
and 90% of the nominal value.
b) Under section 3.2.3.3 - A Long Duration Voltage Variation shall be defined as a variation of the RMS
value of the Voltage from nominal Voltage for a time greater than 1 minute. A Long Duration Voltage
Variation is an Undervoltage if the RMS value of the Voltage is less than or equal to 90% of the nominal
Voltage. A Long Duration Voltage Variation is an Overvoltage if the RMS value of the Voltage is
greater than or equal to 110% of the nominal value.
b) Under section 3.2.2.2 - The Distribution Utility shall design and operate its System to assist the System
Operator in maintaining the fundamental Frequency within the limits of 59.7 Hz and 60.3 Hz during
normal conditions.
4.1.11 Harmonics
The harmonic voltages as a percentage of the light load (approx. 1 % of load) DC voltage shall be as specified
in standards. Harmonic distortion at the points of common coupling shall be limited to ensure the power quality.
The power supply design shall comply with the maximum of total permissible voltage distortion of Local
Electricity Authority MERALCO requirements for limitation of higher harmonics at the 34.5 kV termination
points to the MERALCO Power Company's grid.
The maximum total permissible voltage distortion caused by higher harmonic elements shall be not exceed 5%.
The Contractor shall supply all necessary filter plant to meet the above requirements if required.
The system shall be designed by Contractor to support the movement of ultimate maximum capacity
transportation when it is planned to run 10 Car trains (5Mc + 5Tc) in both directions, at 2 minutes headways
during peak periods. Operational scenarios that considered of trains bunching are to be studied for each scenario
and under no case shall the track voltage exceed the voltage as specified in EN-50122.
Normal Operation
The rating of the Main Line TSSs shall be designed so that adequate power is supplied to the system, with all
Substations operating, to maintain rated MMSP operating performance during peak-hour. The Depot and Main
Line Substations shall be rated to provide adequate power to maintain normal operations of the rail vehicles
within the Depot and Main Line facilities as defined under the operations plan.
Degraded Operation
Contingency/Degraded operation of the Main Line Traction Power Supply System occurs when any one traction
power substation is out-of-service on the Main Line. The rating of the Main Line traction substation and other
associated electrical equipment (including, OCS, Substation and OCS fittings and accessories, etc.) shall be
designed so that adequate power is supplied to the system to maintain operation of the metro under degraded
mode during peak-hour operating conditions until 2035 with 10 cars (5Mc & 5Tc) and 2 minutes headway.
POW-4-14
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Under degraded operations, the DC feeder circuits and positive DC bus of the out-of-service Substation must
remain in service to feed across the section break & act as a paralleling hut; and bypass-disconnect switches
shall be installed to bridge the two section in the event that the positive DC feeders or bus are out-of-service.
Contract shall also perform the single end feed scenarios to assess the performance including if one of the Bulk
Supply Substation is out of service and or maintenance to be carried out.
SCOPE OF WORKS
4.2.1 General
This specification sets out the requirements for the design, manufacturing, factory test, packing, delivery to site,
installation, training and setting, testing, commissioning, interfacing works, spare part & special tools delivery
and trial operation support for completing the Power Supply system under the Metro Manila Subway Project
(MMSP) (Quirino Highway – Bicutan, Lawton East – T3) here under the project.
1. Two new 115kV/34.5kV GIS Bulk Supply Substations including 115kV Incoming Feeders and
associated pilot protection cables.
2. Total thirteen (13) Traction Substations (TSSs), and one (1) Sectioning Post (SP) are planned to be
constructed and locate at the following site locations, as shown in Table 3.
3. Total sixteen (16) Station Substations (SSS) are planned to be constructed and locate at the following
site locations, as shown in Table 4.
4. Number of TSSs and SSSs are shown on the following Feeding Line Diagrams:
POW-4-15
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
* Transformer Rectifier Unit at TSS comprised of 4.2MVA for Traction Transformer and 4 MW Rectifier.
1. Contractor CP106 shall carry out the detailed simulation studies to confirm the number of TSSs and the
required of installed capacity at each TSS.
2. Contractor CP106 shall also liaise with various Civil Contractors for the confirmation of Station Loads
in order to calculate the required installed capacity at each Station Substation and Emergency Loads for
Diesel Generator capacity.
3. Contractor shall also carry out the detailed studies to assess the capacity of ESS during trains
regenerative braking to assess the capacity of ESS require to install at each TSS. Also confirm if ESSs
capacity are of adequate to replace the rectifier unit (as OPTION shown in Fig. 4).
No. Station Location SSS 400V LVAC, Diesel Gen. Set Site
Substation Name Capacity** 5000A, 3-Ph, Capacity
4W, 60Hz
Switchboard***
1 Quirino Highway 0km 000 2x 1 1000kVA Underground
SSS 1500kVA
2 Tandang Sora SSS 1km 711 2x 1 1000kVA ditto
2500kVA
3 North Avenue SSS 3km 886 2x 1 1000kVA ditto
2500kVA
4 Quezon Avenue 5km 200 2x 1 1000kVA ditto
SSS 2500kVA
POW-4-16
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
All equipment installed in indoor areas shall be of permeation preventive structure for the prevention of water
drops from ceiling. Regenerative power absorption device shall be provided for regenerative power absorption
(see item 6). The design shall be based on the Contractor’s simulation and shall include but not limited to the
capacity and location of the regenerative power absorption device.
The work as described below shall be carried out by the Contractor but not limited as follow:
i) Design and built two (2) new 115kV/34.5kV, 60MVA substation namely ‘Bulk Supply
Substation’ (BSS).
ii) Bring in and installation of two 115kV Incoming Feeder power cables and associated pilot
protections and control cables fed from 115kV MERALCO GRID Substation.
POW-4-17
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
iii) Procurement and installation of all equipment but shall not be limited to the following:
• 115kV GIS;
• 34.5kV Switchgear;
• Others.
6. Include in the scope of supply for the Contractor are Energy Storage System (ESS) that utilize storage
battery control technology to capture and store surplus energy produced by the train’s regenerative
braking system and enable to feed back into the Traction Power supply system as required. One ESS
shall be installed at each TSS on the main line and one in the Depot TSS. Contractor CP106 to confirm
the Option as shown on Feeding Line Diagrams.
7. Control of all electrical equipment will be via a Supervisory Control And Data Acquisition (SCADA)
system with the operator control equipment, mimic diagrams and relevant displays installed in
Operation Control Centre (OCC) located in the Depot. In addition, a Substation Automation System
(SAS) that integrates directly with OCC located at the Depot and (future Back-Up Control BOCC
location to be confirmed) shall be installed in each Bulk Supply Substation (BSS), with the local control
at each TSS and SSS via Remote Terminal Units (RTU). SAS shall be designed to comply with
IEC61850.
8. All communication between various parts of the Power SCADA system for the Power Supply System
on MMSP shall be via the fibre optic cable Backbone Transmission Network (BTN) including the Local
Area Network (LAN).
9. The complete cable network and cable support system up to connection in substations shall be carried
out (except the cable trough/trench laid along the alignment in main line and all external cable
containment in depot) by the Contractor which includes but shall not be limited to the following:
i) 34.5 kV cable to substation to cable terminal box (PCT box) including excavation, reclamation
and all facilities;
iii) Connection of 34.5 kV cable, protection / control line (including power supply line), ITV
control line / data line (including optical cable) between Bulk Supply Substation (BSS) and
Traction Substation (TSS), Station Substation (SSS) and Depot;
POW-4-18
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
In the depot, 34.5 kV RMUs cables shall be installed in the buried pipe below ground level. The installation of
buried pipes/ducts and the creation of manholes to suit 34.5kV cable sizes and routes shall be carried out by the
Civil Contractor (CP101). Therefore, the Contractor CP106 shall coordinate with the Civil Contractor regarding
the number, shape and size of buried pipes/ducts as well as cable routes details include manholes.
iv) Cabling for interlinked tripping between the BSS, TSSs and SSSs;
v) Cabling of Optical fibre cable for Power SCADA system. The Contractor shall coordinate with
Interfacing Contractors and other Interfacing Parties with regard to the details including but not
limited to cable type, size, routings and requirement for other contractors to provide cable
trough/trench laid along the alignment in main line and all external cable containment in depot
as well as installation of all other cable containment to be provided by the Contractor;
vii) The Contractor shall coordinate with Interfacing Contractors and other interfacing parties
regarding installation of the TSSs, SSSs and other equipment;
viii) TSSs, SSSs, SP and BSSs space preparation, levelling including necessary banking, building
construction including utilities such as fire detection and/or ventilation, indoor and outdoor
lighting, earthing equipment etc. will be designed and constructed by other Contractor(s). The
Contractor needs to coordinate with them for the necessary requirements;
ix) Power SCADA System for TSSs, SSSs and Electric Rooms in main line and depot includes
ITV supervising system for Depot TSS and Depot entrances and outdoor equipment. All
communication between various parts of the SCADA system shall be via the fibre optic
Transmission Network;
x) Protective provisions relating to electrical safety and earthing which includes but shall not be
limited to earthing of equipment, cables and non-current carrying metallic components, etc.
xiv) Furniture, shock treatment charts, rubber mats, first aid boxes and danger notice plates; in TSS
and electrical rooms on main line and depot;
xvi) Services.
10. Main Line Tunnel Lighting and Outlets for maintenance on the main line including associated Low
Voltage (LV) cables.
11. The tasks to be carried out by the Contractor shall include but not limited to the following:
i) Review and approval of the Employer’s electrical engineer and of others, shall submit to the
respective Employer’s engineers the design, supply, system quality management, installation,
testing including integrated testing and commissioning of the complete electrical power supply
system;
ii) Presentations, reviews and audit support as described in the General Specifications;
POW-4-19
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
c) Earthing busbar terminal and grounding rod for TSS, SSS and SP; and
d) Buried pipes, cable trench and hand holes for cable wiring.
v) System operations;
vii) Defects Notification Period of the Permanent Works after commissioning as stipulated in the
Contract.
12. This Technical Specifications (TS) shall be read in conjunction with the Employer Requirements (ER),
the General Conditions of Contract (GC), General Specifications (GS) and any other document forming
part of the Contract. In the event of a conflict between the ER, GC and GS to the TS, the requirement
of the TS shall prevail.
13. In the event of a conflict between the TS and any other standards or specifications quoted in the TS, the
requirement of the TS shall prevail.
14. All information stated and drawings included in this Employer’s Requirement are based conceptual
design for feasibility study and thus details shown on the drawings are for information only. The
accuracy of preliminary details shown on the drawings cannot be guaranteed. The Contractor shall
prepare the detailed design documents and drawings include all necessary studies to be carried out to
achieve requirements of the TS.
Cross-bonding The term used to describe cables used to electrically link parallel sets of
running rails forming the traction return system together, to reduce
voltage drop and leakage currents in a DC electrified traction ystem.
or
It is the type of bonding of HV cables to limit the sheath voltage.
Disconnecting Switch Mechanical switching device which ensures specified clearance for safety
reasons in the open position, in order to maintain OCS facilities during
night-time hours, to disconnect from a charged circuit at abnormal
conditions such as a short circuit.
Earth Means the Conducting mass of the earth or any conductor in direct
electrical connection with it.
Earthing The connection of equipment enclosure and non-current carrying metal
parts to earth to provide safety to personnel, public and to the equipment.
Earth fault Failure of insulation of a conductor having a potential above earth
POW-4-20
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-21
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Station Substation (SSS) Station Substation receives 34.5kV power and transforms to 400V AC, 3-
Ph at each Station for supplying power to each station.
Sectioning Post (SP) Insert the circuit breaker at both ends of the section and short circuit to
prevent the potential difference and protect the pantograph and section.
On the other hand, when an accident occurs, open circuit breaker to
prevent expansion of accident.
Switchgear Means Isolator Switches, Circuit Breakers, Interrupters, Cut-outs and
other apparatus used for the operation, regulation and control of electrical
circuits.
System Electric Power System comprised of traction power supply system, HV
power supply distribution system and auxiliary power control system.
Traction Substation Traction Substation receives 34.5kV AC and converts 34.5kV AC to
1500V DC for feeding traction power to the trains via OCS.
Withstand Capability Rated capability of equipment and or conductor to withstand without
damage by the mechanical forces of a short circuit or the thermal effects
of a short circuit downstream from the equipment. Also, a rated capability
of equipment which will withstand without damage for specified power
frequency over-voltage and/or for surge or impulse voltage.
4.3.2 Abbreviations
Table 6: Abbreviations Used
AC or ac Alternating Current
AFC Automatic Fare Collection
ANSI American National Standards Institute
AWG American Wire Gauge
BCC Back-Up Control Centre
BS British Standards
BSS Bulk Supply Substation
BTT Built in Test Diagnostics
CT Current Transformer
DC or dc Direct Current
DNP Defect Notification Period
E&M Electrical and Mechanical
EMI Electro Magnetic Interference
EMC Electro Magnetic Compatibility
EN European Norm (Standard)
FAT Factory Acceptance Test
g/m2 Grams per metre squared
GNAN Gas Natural Air Natural
GNAF Gas-Insulated Self-Cooled Forced-Air Cooled
GFAF Gas-Insulated Forced-Gas Forced-Air Cooled
POW-4-22
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-23
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
9. High reliability;
POW-4-24
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
17. Maximum utilization of indigenous materials and skills, subject to quality conformity.
2. The system, including all sub-systems and equipment, shall be of proven design.
3. Sub-systems and equipment proposed by the Contractor shall have been in use and have Railway
System in Revenue Service in three different countries out of their origin over a period of at least five
years.
4. The system and sub-systems equipment shall be designed to comply with FEMA 1050.
5. Where similar equipment or sub-systems of a different rating are already proven in service, the design
shall be based on such equipment.
In case these stipulations are not fulfilled, the Contractor shall furnish sufficient to prove the basic soundness
and reliability of the offered subsystem and compliance with the design criteria.
POW-4-25
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-26
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-27
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
POW-4-28
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
SYSTEM REQUIREMENTS
4.5.1 General
The MMSP shall have 15 stations and one Depot running from Quirino Highway – Bicutan and spurred at
Lawton East to Terminal T3 allowance for the future extension.
POW-4-29
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Traction Power Supply (TPS) shall be designed to fully meet the requirements of EN 50163 for a traction
supply at nominal 1500V DC. The TPS shall be capable of meeting the entire demand of peak time service
permanently with one adjacent TSS out of service and as the reduced voltage may result in reduced train
performance. The TPS voltage shall not fall to less than 1000V DC, under the worst operational mode and
supply system outage.
The 34.5kV system is designed to ensure that voltage regulation under normal feeding and abnormal feeding is
maintained within the tolerances as specified in Philippine Distribution Code 2017 Edition.
All the 34.5kV switchgear located at TSS and 34.5kV Ring-Main Unit (RMU) systems at SSSs are designed
and supplied to support the ultimate capacity operation of the MMSP system (10-car: 5Mc & 5Tc train, 2
minutes headway).
a) a complete design and installation of TSSs. Each TSS shall be equipped including but not limiting to
34.5kV Switchgear, two 4.2MVA transformer Rectifier Units, 1500V DC switchgear, Energy Storage
System (ESS), Negative busbar, busbar, battery and chargers, protection relays and all AC and DC
cablings etc.
b) a complete design and installation of SSS. Each SSS shall be equipped including but not limiting to
34.5kV Ring Main Unit (RMUs), distribution transformer, protections, cabling, battery and chargers
and diesel generator set etc. Note: Diesel Gen set to be installed at a ground level.
c) a complete design and installation of power distribution in the Depot. The distribution power supply
system shall be equipped including but not limiting to 34.5kV Ring Main Unit (RMUs), distribution
transformer, protections, cabling, battery and chargers and diesel generator set etc.
The 34.5 kV Power delivered to MMSP shall be receiving from Bulk Supply Substation(s) directly supplied
from MERALCO 115kV substation, as follow:
a) All the TSSs, SSSs on the main line and in Depot are received the power from Bulk Supply Substation(s)
and in turn the power shall be distributed in looping manner from substation to substation. Refer to
Feeding Line Diagram Drawings shown in Fig. 1, Fig.2, Fig.3 & Fig. 4 for information.
The Contractor shall coordinate with other contractor(s) for the layouts and any of other requirements
for the accommodations and facilities of the receiving equipment in TSSs, SSSs etc.
b) The Contractor shall coordinate with MERALCO for the requirement details of the metering devices at
the design stage. The energy meter (MOF) will be provided by the MERALCO. The Contractor shall
provide the space for these devices for housing the VT and CT. The Contractor shall also coordinate
with MERALCO on the necessary spaces, locations and other miscellaneous requirements.
c) The Contractor shall coordinate with MERALCO and other Interfacing Parties on the interface between
the TSS and MERALCO’s substation, if the BSS is designed and built by MERALCO.
d) The Contractor shall coordinate with Interfacing Contractors and other Interfacing Parties with regard
to the equipment weight imposed on the foundations by the substation power supply system equipment.
The Contractor shall assure that the actual loading of permanent installation and delivery does not
exceed the agreed loadings.
e) The Contractor shall provide his own electric power if required, for his own use at all sites.
POW-4-30
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall provide all cables needed but not limited to the following: 115kV, 34.5kV AC, 1500 VDC
and Low voltage using in the BSSs, TSSs, SSSs and SP, except BSSs shall include 400V and LV Voltage.
a) Interfacing with Civil Contractors for the provision of all electrical equipment rooms, including the
required structure openings, equipped with building services, for the BSSs, TSSs, SSSs and SP.
b) The Contractor shall coordinate and interface with Civil Contractors and any other Interfacing Parties
regarding the delivery, installation and structure openings of the traction substation equipment. The LV
power to traction substation including, but not limited to, lighting and battery chargers shall be provided
by operations transformer in the traction substations. The LV electric power to the operations
transformer of SP shall be supplied from both Lawton East and Lawton West stations.
Earthing and bonding at BSSs shall be done according to the requirements of MERALCO, if any.
All earthing and bonding at BSSs, TSSs and SP shall be done according to the MMSP Earthing and Bonding
Strategy in strict compliance with EN 50122 or equivalent standards.
Each earth mat shall be terminated to the substation earthing busbar through two terminals/conductors at either
end of the earthing busbar. The two terminals/conductors shall be connected onto the earthing busbar through
disconnecting links, for ease of maintenance.
The integrity of Earthing and Bonding installations shall be verified, and the design validated by an approved
competent ‘Third Party’ approved by the Engineer. Competent Third Party shall measure earth grid resistance
from ‘Clean earth’ and ‘General earth’ Busbars inside the BSS, TSS and SP.
The Contractor shall provide the earthing connection from earth mats to all outdoor facilities of substations
directly.
The Contractor should consult with Civil Contractors and related departments on earthing work and its testing
methods.
The Contractor shall coordinate its requirements for earthing (including earth mats), bonding and lightning
protection with Interfacing Contractors.
a) Test ground resistance of each ground grid after installation and before utility cable connection.
b) Test each ground bus when connected to ground grid using an approved test procedure. Test results
shall be submitted for review by the Engineer.
c) Test resistance of connections and conductors between ground buses in TSSs, SSSs for electrical
continuity.
d) Prepare and submit testing certifications for each TSS site, testing shall be signed by the testing
technician, and certified by the Contractor Quality Control Representative for review by the Engineer.
The Contractor shall perform Earthing and Bonding measures to ensure three essential aspects:
a) Provide for the electrical safety of rail system personal, passengers and other public;
POW-4-31
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
b) Protect the integrity of rail operations and of maintenance requirements from electrical hazards; and
POW-4-32
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall guarantee that the traction power supply equipment has the capability of preventing an
electromagnetic interference (EMI) from any equipment supplied by the Interfacing parties and the interfacing
contractor.
The Contractor shall submit an EMC Control Plan to Engineer for review as required in General Specifications.
The Plan shall include the measures to reduce conducted, induced and radiated emissions to acceptable levels
as specified by IEC 62236: Railway Applications-Electro-magnetic Compatibility.
The Plan shall specify the measures to increase the immunity of the traction power supply equipment for the
main track.
The Plan shall specify the basic protective measures proposed for all electrical and electronic subsystems and
components, and the specific protective measures to be adopted for selected subsystems and components.
The Plan shall analyse EMI/EMC impacts on the design of the traction power supply equipment, the train, and
wayside equipment as well as the general environment. Particular attention should also be paid to additional
requirements in grounding, bonding, shielding, filtering and cable arrangements.
The Contractor shall conduct full EMI tests on each one set of equipment and for each type as well as full EMC
tests on complete traction power supply equipment in accordance with IEC 62236.
Non-safety related systems interface. The Contractor shall take appropriate measures to ensure that EMC is
achieved between the traction power supply equipment and track-side equipment.
3. Traction and Non-Traction Power Feeding System of MMSP in this project for DC traction power
study, Station loads study as shown on the Major Feeding Line Diagrams.
POW-4-33
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
10. AC and DC Protection relay settings and system protection coordination study;
11. Cable study, main circuit, LV and control cables voltage drop, capacity etc.;
12. Power supply design study and analysis for the whole system;
15. EMC/EMI studies associated particular with Traction Power Supply system and Station supplies.
17. Return Stray current corrosion control study and coordination with the interfacing party with the Civil
Contractors.
1. Overall Power supply design study, including the whole system, each station, Depot, OCC, etc.
including the determination of the sufficiency of the minimum specified ratings.
2. DC traction power study using simulations as per track layout plan, operational scenarios. Operational
data and Rolling Stock (Train) data to be provided by the relevant Engineers. Train data will be provided
by the Rolling Stock Contractor.
3. Short circuit current, short circuit current curves, voltage dropping study and flicker study.
4. Normal peak hour RMS current and maximum current in various feeders.
5. Short time peak hour RMS current and corresponding maximum currents in various feeders.
7. Track voltage rise in Main Line and Depot under normal and fault conditions. The tracks shall be
insulated on Main Line while earthed in Depot.
9. Calculation and verification of traction transformer size, rectifier, DC switchgear, DC cables, Negative
busbar return, battery chargers and ESS (Energy storage system) capacities.
The equipment shall meet the operational requirement in normal, degraded mode of operation and under fault
conditions. The Contractor shall carry out adequate studies on the parameters specified in the bid document,
seek clarifications, and make site visits, site investigations and carry out simulation studies for ascertaining the
adequacy of the specified parameters as required.
As a minimum, the following studies or demonstrations will be required, in addition to any specific studies
required to meet RAMS including Hazard Management requirements and any studies mandated by the relevant
Metro systems standards, or to meet the requirements of the Power Utility Provider (MERALCO).
POW-4-34
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. The Stray current corrosion control study shall include an assessment of the track resistance,
conductance, regular data logging of track voltage at Sub-Stations, IRJs, at end sidings other identified
locations and its measurement in Main Line and Depot. The normal/reference parameters and values
for different operational plans shall be ascertained; and
3. Determination of Stray/leakage current flow across double IRJ near Depot when bridged.
The Contractor shall carry out a simulation study to evolve an economic design that ensures the traction power
demand, voltage requirements and RAMS requirements for full peak time services are satisfactorily met, both
under normal feed conditions and with one adjacent TSS out of service.
This study shall also finalize the size of 34.5kV AC cables, size and number of 1500V DC cables (positive and
negative), cross section of overhead conductor wire/rigid rail and rating of other associated equipment. The
failure of one BSS shall not affect the normal operation.
The Contractor shall undertake detailed studies and specify the necessary included train simulations for various
scenarios such as Normal Operation, Outages Conditions and Degrade Modes to rate and confirm the capacities
of Main Transformers are of adequate size to support the ultimate capacity operation of the MMSP system (10-
car train, 2 minutes headway) and station loads required that are being specified by Civil Contractors.
The Traction power supply system shall operate at a nominal 1500V DC. However, the average line voltage to
be used for performance calculations for various scenarios shall be in accordance with the Rolling Stocks design
specification.
POW-4-35
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
1. Train operation plan under Normal operating conditions, degraded and as defined for special events
operating conditions;
3. Speed vs Tractive effort, Speed vs Current and speed vs distance characteristics of the locomotives/train
sets;
1. Impedance of OCS;
9. Voltage rise at the return circuit track or negative earth bus under normal and fault conditions;
POW-4-36
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
10. Voltage drop locations and mitigation measures such as location and sizing of sectioning and track
cabins; and
The Contractor or its any of the partners or the designer shall not be part of this independent agency. The
approval of this independent agency shall be done by the Engineer from at least three proposals submitted by
Contractor.
The scope of work also includes the installation of the 115kV, 34.5kV, 2 x 60MVA Grid Main Power
Transformers, complete with Automation Substation Protection and Control system in compliant with IEC
61850. This includes fibre optic cables to the MERALCO Grid Substation (GSS) and all site work trenching
works, installation of cables, cable jointing (and cable jointing pits) and all protection necessary for the cables.
Contractor is advised to consult with MERALCO for the existing type of MERALCO’s 115kV/34.5kV GIS
substation were built in Manila and is currently implementing on 115kV system and they are:
1. Conventional GIS Type Substation which required approximate area of 5400sqm; and
2. Compact GIS Type Substation which required approximate area of 2000sqm which is preferable.
The Contractor shall optimize the design in accordance with the applicable building regulations and rules for
good building construction, to suit the tendered equipment and submit a fully detailed design of for the civil,
structural, architectural and electrical works for the approval of the Engineer prior to starting any construction
work.
The building shall be structurally, functionally adequate and aesthetically pleasing in all respects and special
attention shall be given to an optimized design of the BSS building; including the GIS room, so that the GIS
equipment are correctly laid out inside the room and at the same time there is adequate space for movement of
people and equipment inside the room without any inconvenience.
POW-4-37
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
It shall be noted that the GIS Equipment, including its control systems, is required to function under extreme
tropical climate conditions and under a high degree of pollution level in vicinity of Substation; therefore the
design shall include all necessary arrangements for maintaining a controlled environment within the GIS Room
(such as air conditioning / pressurized ventilation / dehumidifiers etc.).
Contract shall take full measurements including the height of the Control room and Auxiliary Main Substation
room and that of the GIS room.
The Contractor shall be required to design and execute all civil works at the BSS locations including those
required to accommodate the incoming and outgoing cables.
The Reinforced Cement Concrete (RCC) construction shall be based on framed structures in accordance with
the National Building codes and be Earthquake resistant as per zone of Manila.
Boundary walls, entrance gates, baffle walls between transformers, transformer foundations and support anchor
blocks, oil retention tanks for transformers, burnt oil pits, etc. shall also be constructed to be earthquake proof,
with protection against earth settlement or displacement.
Materials used for the construction of the building shall be new and of good quality materials shall be so chosen
that the buildings when erected shall have good heat and sound insulation properties in normal conditions, as
well as when combined with the heating or air-conditioning equipment installed by the Contractor.
The cable space for the GIS cables shall not be below ground level to avoid ingress of water and the work shall
also include land drainage in the yards and cellars for rain, waste & seepage water using natural gradients /
pumps and sumps, etc.
Provisions shall include complete building E & M services, yard lighting, circulating area lighting, landscaping
and other requirements, lightning protection masts, earth meshes and all earthing arrangements.
The provision of Gravel for the yards and all auxiliary services like water supply, lighting, ventilation, air-
conditioning, fire detection and alarm etc. and any other work required to successfully complete the work.
Design and construction of the building shall be complete in all respects including cable paths and cable trenches
in the switchyard, as well as inside the building.
The Contractor shall design and execute the normal lighting and LV power supplies for the BSSs. The lighting
and power auxiliary outgoings located in AC auxiliary cubicles, forming the exit point for all the normal lighting
supplies and power connections, shall be supplied from both LT auxiliary transformers. The lighting and power
supplies shall be distributed for lighting of complete building as per lux requirements laid by Manila National
Building Code and BS 7769. Lighting fixtures to be installed for Indoor/Outdoor lighting shall be of LED type.
All cable trays, cable ladder systems shall be in accordance with EN 61537 and all rigid conduits shall be in
accordance with EN 61386.
All the cables shall be installed on the cable trays inside room hung from the ceiling and the width of cable ways
shall enable addition of at least 15% of the number of the cables initially foreseen. All cable trays and supports
shall be suitably connected to Earthing system at two distinct and separate points. Wherever cutting / welding
process required at site, Contractor shall ensure that cold galvanizing zinc paint should be applied after doing
the process.
POW-4-38
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
network. The two 115kV overhead lines feed directly into the MERALCO switching compounds at the
BSSs.
These switching compounds will then feed the two 115/34.5kV, 60MVA Grid Main Power transformer
banks through 115kV transformer HV circuit breakers that are located inside the MERALCO switching
compound. The HV circuit breakers will supply power to the two Grid Main Power transformer banks via
overhead conductors (this is standard practice and may change to cables based on other considerations by
MERALCO). The Grid Main Power transformers will step down from 115kV to 34.5kV which is then fed
to the BSS 34.5kV GIS bus bars via 34.5kV XLPE cables and 34.5kV Low Voltage Grid transformer GIS
circuit breakers and associated equipment such as Disconnectors. The 34.5kV will then be fed to the traction
and non-traction power ring network via 34.5kV GIS circuit breakers, XLPE cables and associated
equipment.
The same switchgear configuration also exists on the 34.5kV GIS where two separate 34.5kV busbars are fed
from different Grid transformer banks through Grid transformer LV circuit breakers, the two circuit breakers
being coupled by the 34.5kV Bus Coupler circuit breaker. Similarly, the two 34.5kV GIS busbars can operate
independently to supply traction and non-traction power separately, with the Bus Coupler open. The advantage
of this configuration of splitting the 34.5kV busbars is that it limits the fault level power on the two independent
GIS 34.5kV busbars to 60MVA and it separates the two systems thereby reducing probability of introduction of
non-traction power faults onto the traction power network.
9. LV distribution boards;
POW-4-39
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
3. Current Transformers;
4. Voltage Transformers;
5. Disconnectors;
6. Earth switches;
8. 34.5kV GIS;
9. Auxiliary Transformers;
b) The required land for Compact substation is 40m*40m which is generally taken as 2000
square meters while that of Conventional substation is 54m*100m which equates to 5400
POW-4-40
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
square meters.
Cooling: ONAN/ONAF1/ONAF2
Environmental Consideration: Oil Bund if indoor and oil pit if outdoor with level controlled automatic sump
pump.
POW-4-41
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
a) Differential;
e) LV Instantaneous Overcurrent.
2. Back-up Protection
f) HV IDMT Overcurrent;
g) LV IDMT Overcurrent;
j) Earth Fault;
n) SF6 Trip.
c) Differential
Back-up Protection
c) Earth Fault.
a) Open circuit;
POW-4-42
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
c) Supply fail.
k) Buchholz Gas;
l) Winding Temperature;
m) Oil Temperature;
o) SF6 Gas.
b) DC Fail; and
1. Power supply to MMSP shall be drawn from Bulk Supply Substation 34.5kV distribution feeder, and
then distributed to the DC traction substation, Station Substations located at the Stations on the main
line and Depot.
2. DC traction equipment shall supply at nominal voltage of 1500V DC to the OCS system.
3. The Contractor shall develop its own strategy for earthing, bonding, lightning protection and corrosion
control in accordance with applicable Standards JIS, JEC, JEM, or equivalent EN and IEC standards.
4. All E&M systems equipment shall be bonded to the system earth busbar in accordance with applicable
Standards JIS, JEC, JEM, or equivalent EN and IEC standards.
5. All indoor and outdoor power supply equipment shall meet IP requirements as specified in JIS C0920-
2003 or equivalent EN and IEC standards at the appropriate location and conditions.
6. Control system of the major facilities/equipment for railway operation should employ PLC logic for
controlling the operating switches, indicators and protective relays for each circuit.
7. The control power for the SSS and TSS is supplied from the 34.5 kV / 0.23‐0.110 kV and 1.18 kV /
0.23‐0.110 kV Operation transformers respectively.
8. All main protective relays shall be of fully numerical type and shall comply as per IEC 61850 standard.
Further, the test levels of EMI as indicated in IEC 61850 shall be applicable to these.
9. All the relays shall be directly connected to inter bay bus using Electrical/fibre optic cables and shall
POW-4-43
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
support peer to peer communication. The relays shall generate GOOSE messages as per IEC 61850
standards for interlocking and also to ensure interoperability with third party relays. Each relay should
also generate an ICD file in XML format for Engineering / integration to a vendor independent SCADA
system. All the relays shall have suitable rear and front ports for connectivity to SAS and PC/LAPTOP.
1. Necessary software and hardware to up/download the data to/from the relay from/to the personal
computer installed in the Sub-Station.
2. The relay shall have suitable communication facility for connectivity to SCADA. The relay shall be
capable of supporting IEC 61850 communication standard.
3. The relays shall have fault record, event record, and disturbance record for fault diagnostic and shall
have communication ports for local communication for relay settings, modifications, extraction and
analysis of fault/event/ disturbance records from a laptop and for communication with Substation
automation system.
6. The power distribution system shall be designed to ensure continuity of supply and the specified system
performance under single outage conditions and shall be provided with a protection system to ensure
that in the event of a fault element is isolated; no other equipment is disconnected by the operation of
such a protection device.
7. The power system design shall ensure that cables and equipment shall be separated and protected to
ensure that a single failure of an element of the power supply system shall not result in the total loss of
power distribution to any part of the Line, not affect the operation and not result in failure of any other
power supply system element.
8. A Zone Protection Scheme shall be applied for 34.5kV power distribution system. In addition, the
distribution circuit shall be protected by over current protection relays.
9. The power distribution system shall be designed to ensure that a single failure of an element of the
power supply system shall not:
a) affect the operation or not result in failure of any other power supply system element;
b) not result in the total loss of power distribution to any part of the MMSP Line.
10. The opportunity for an incident external to the power supply system which affects the operation, or
results in failure of an element within the power supply system, or results in a total loss of power
distribution to any part of the MMSP Line shall be minimized.
11. The AC power distribution protection relays shall be well coordinated to ensure that no other system is
affected in the event of a fault with only the faulted element isolated from the system.
12. The DC traction system shall be designed to ensure that it shall not affect the time tabled operation of
trains by the loss of any DC busbar or by feeder circuit breaker outage.
13. The DC traction system shall include protective tripping to ensure that any faults are disconnected
quickly. The design of the protection system shall ensure that tripping is avoided, particularly during
normal operation or in the event of train bunching.
POW-4-44
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
14. It shall not be possible for faults to be masked by regenerative power from the trains.
15. A coordinated protection scheme shall be applied with 34.5 kV distribution system. The distribution
circuit shall be protected by but not limited to over current protection relays.
16. The 34.5 kV receiving bus bars in each substation shall be protected by bus zone protection relays.
The 115kV Incoming Feeders shall be included the associated pilot cables for protection and controls and
associated metering require to be installed by MERALCO.
Contractor shall interface with MERALCO for 115kV Incoming Feeders and the details of cable routes and
construction.
Both the TSSs / SSSs on the main line and Depot shall receive 34.5kV directly supplied from Bulk Supply
Substations. Contractor shall carry out the detailed studies to decide the open points for alternative back-up.
The Contractor shall coordinate the requirements for the preparation of substation layouts for the facilities of
the receiving electrical equipment in the TSSs and SSSs on the main line and Depot as well as associated cable
routes.
Estimated equipment capacity for the substations (TSSs and SSSs) shall be based on the total capacity required
to supply the entire MMSP taken into consideration of various operation scenarios and be sufficient for 10-car
train operation with 2-minute headway and Station loads to be supplied by E&M Contractors.
Two off 34.5kV/400V transformers shall be installed and supplied via 34.5kV Ring Main Units (RMUs) to be
located at each Station Substation (SSSs) to provide supply of 400V AC, 3-Ph, 60Hz to the distribution system.
The 34.5kV/400V transformers and 34.5 kV RMUs shall be designed to provide to support the worst case
scenario that could occur in the system.
Diagram Fig. 3 shown the 34.5kV Ring feeding arrangement which namely ‘Non-Traction’ for the SSSs as an
indication. The Contractor shall undertake to revise the Ring feeding arrangement of 34.5kV loop circuit for
Station Substation (SSS) in order to achieve the best voltage drops as well as to facilitate the redundant
provision.
Each RMU located at SSS are fed with two (2) 34.5kV circuits received from the Bulk Supply Substations
(BSS); one circuit from each end, to provide for back-up, if a fault occurs in the incoming line at any SSS, the
affected SSS will be supplied from the next 34.5kV feeding substation.
The Contractor’s design shall be in accordance with Power Supply Utility Provider MERALCO regulation,
through analysis and simulation, of the validity of the power supply system configuration to satisfy the
POW-4-45
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
harmonics and other requirements of the design. The Contractor shall enhance the configuration if it is found to
be inadequate.
The permissible operating voltage of 34.5 kV system shall be in the range of -10% and +10% of operation
voltage in accordance with the Local Electricity Authority MERALCO standard.
The 34.5 kV system shall be designed to ensure that voltage regulation under normal feeding is maintained
within +10% and -10% of normal voltage at any point on the 34.5 kV system and shall ensure that it is
maintained within MERALCO’s allowance under any single outage condition. Contractor shall consult with
MERALCO for compliance.
All 34.5kV system shall be designed to support the ultimate capacity operation of the MMSP System.
In Depot, looped 34.5kV power distribution line systems shall be designed and provided.
The Traction Power System shall fully meet the requirements of EN 50163 for a traction supply at nominal
1500V DC. The TPS shall be capable of meeting the entire demand of peak time service permanently with one
adjacent TSS out of service and as the reduced voltage may result in reduced train performance, the TPS voltage
shall not fall to less than 1000V DC, under the worst operational mode and supply system voltage.
The instantaneous voltage at any train along the route shall not fall below 1100 VDC during normal operations
with all substations in rated service and shall not fall below 1000 VDC with any abnormal operating condition
under any single outage condition. Contractor also advised to interface with Rolling Stock for the design
purposes.
The DC traction system shall be designed to coordinate with the train operation. The DC switchgears,
disconnecting switches and cables shall have current ratings compatible with the most onerous loadings
envisaged for the system.
Total thirteen (13) Traction Substations (TSSs), and one (1) Sectioning Post (SP) are planned to be constructed
and locate at the following site locations and shown on Major Feeding Line Diagram titled ‘Traction Major Line
Feeding Arrangement (Final Phase)’.
Two (2) rectifier banks shall be installed at every traction substation and shall have estimated capacity sufficient
for 10-car train operation with 2-minute headway. One rectifier unit shall be for normal operation and the other
for standby backup system.
In the two rectifier banks, normal operation and standby shall be alternately performed every month in order to
average the operation time of the equipment.
Preliminary design calculation study estimates Thirteen (13) DC traction substations, including the main track,
airport track, and Depot, and one (1) sectioning post, as shown for information on the Major Line Feeding
Arrangement. The Contractor shall undertake his own studies, calculations and analysis and confirm the
required number, sizing and location of traction substations.
One DC feeder circuit breaker for each traction substation shall be provided for DC feeder redundancy system.
This standby circuit breaker shall be able to operate by changing over of disconnecting switches to isolate the
failed circuit breaker.
POW-4-46
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Linked braking system utilizes optical fibre cables shall be prepared for DC traction feeder circuit protection
between mainline TSSs.
Suitable equipment shall be proposed and provided in the appropriate locations by the Contractor to limit the
rail potential to a pre-set value for personal safety consideration regarding dangerous touch potential in all
circumstances including during train operation.
EN 50122-2 Protective Provisions against the effects of Stray Currents caused by Electric Traction Systems.
The AC power distribution system shall be designed to ensure continuity of supply and the specified system
performance under single outage conditions.
The AC power distribution system shall be provided with a protection system to ensure that in the event of a
faulty element is isolated; no other equipment is disconnected by the operation of such a protection device.
The power system design shall ensure that cables and equipment shall be separated and protected to ensure that
a single failure of an element of the power supply system shall not result in the total loss of power distribution
to any part of the Line, not affect the operation and not result in failure of any other power supply system
element;
A Zone Protection Scheme shall be applied for 115kV and 34.5kV power transmission and distribution system.
In addition, the transmission and distribution circuit shall be protected by over current protection relays.
The Substation installation is subject to various faults such as operating over voltages, short circuits or lightning.
In order to ensure protection to people and equipment, an Earth mesh, sized to limit the earth rise potential, step
and touch voltages below the acceptable values, shall be provided.
The Earth Mesh design and installation shall be done in accordance with relevant provisions in IEEE 80-2000.
Earth network should be designed taking into account temperature rise under fault current levels. The temp shall
not exceed as permitted by the type of joints. Earth mesh has to be linked, by means of two conductors of
appropriate size to:
iv. Bunds and associated sump pump comprise of water, oil separator and control to be built for each
transformer;
POW-4-47
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall provide independent voltage transformers (VT) and current transformers (CT) in the BSS
for metering electrical energy on each incoming feeder. To be commensurate with the Local Utility Provider
MERALCO requirements of energy metering.
The Contractor shall also coordinate with MERALCO for the details, ratio, accuracy and capacity for the voltage
transformers and the current transformers at the design stage of installation.
The busbars of 115kV and 34.5kV switchgear shall be extendable for future use.
It is to point out that the land of BSS is generally filled up soil and has variation of resistivity with respect to
depth. Contractor shall measure the resistivity and may also have to apply multiple layer model for design of
Earth Mat.
One 34.5kV Switchboard shall be provided at each Bulk Supply Substation. Each 34.5kV Switchboard shall
consist of a single, two section busbar. The sections in each switchboard will be coupled by a bus-sectionalising
circuit breaker. Each 34.5kV Switchboard shall accommodate the incoming feed from the 115kV/34.5kV
Power Transformer, interconnector circuits, outgoing feeders for the Ring Main Systems and the Auxiliary
Transformer feeder at each Intake Substation. The switchgear will be equipped to facilitate SCADA control
and monitoring requirements.
In order to avoid circulating current problems, each 34.5 kV Switchboard will operate as a separate entity, with
the facility to be coupled together.
Adequate spare space provision shall be made to accommodate the installation of additional equipment and
busbar extension.
The 1500V DC Traction Substations shall include rectifier transformers, rectifiers, high speed circuit breakers,
associated switches, protection, earthing, negative return panels and any other item required to complete the
work.
Incoming Circuit Breakers (CB) of the single pole High Speed Circuit Breakers (HSCB) shall be installed
between the rectifier group and 1500V DC Positive busbars and shall be interlocked with the traction
transformer incoming CB.
For connecting the negative terminals of the rectifiers with negative bus bars, motorized no load switches,
interlocked with corresponding HSCB & Disconnector Switches shall be provided.
POW-4-48
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
From the 1500V DC positive busbar, feeder HSCB & DC disconnector switches shall be provided to feed power
to the overhead line.
Bypass breakers shall also be provided for bridging the supply in case of the failure of the OCS feeding breakers.
Drainage circuit to be installed at the traction substation to provide a polarized electrical circuit between
elements requiring stray current drainage and the negative busbar of the traction substation.
A. 34.5 kV Switchgears
The 34.5kV switchgears shall be equipped with all measuring and protective devices.
34.5 kV Outdoor type, metal enclosed gas insulated switchgear should be adopted.
34.5 kV Indoor type, metal enclosed gas insulated switchgear should be adopted.
The 34.5kV shall be designed and manufactured but not limit as follow:
a) All 34.5kV switchgear shall be in accordance with the requirements of IEC 62271.
b) The 34.5kV feeder shall include but not limited to 34.5 kV circuit breakers complete with all
CTs. PT, meters, indicators, earth switches, etc.; required for the successful operation.
c) Each 34.5kV switchgear unit with circuit breaker shall be designed with adequate current
ratings and short circuit braking duty according to its intended function. Conductors for the
busbars and various connectors shall be of copper, adequately dimensioned for the normal and
short circuit ratings. Wherever necessary expansion joints shall be provided to compensate for
thermal expansions.
d) 34.5 kV incoming feeder(s) and 34.5 kV circuit breaker units, bus couplers for the protecting
the rectifier transformer and distribution transformer.
e) 34.5 kV circuit breaker’s short circuit current rating shall be sized to safely interrupt the short
circuit current under the breaker’s tested condition. Likewise, the circuit breaker’s interrupting
capacity shall trip the highest current at rated voltage.
f) 34.5kV switchgear shall be the compact module type in design, metal enclosed and suitable for
indoor and below ground level installation. The switchgear shall be protected from total dust
ingress and protected from long term immersion up to specified pressure. The 34.5 kV
switchgear shall be comprised of the following:
ii) SF6 gas insulated fixed mounted vacuum circuit breakers; and
iii) SF6 gas insulated vacuum circuit breakers which can withdraw.
Note: All SF6 switchgears must be leakage free and are suitable for below ground level installation.
g) The 34.5 kV cubicles shall be protected against fire by means of an 'automatic fire detector and
POW-4-49
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
extinguisher system', 'Fire trace' type or equivalent, with provision of alarm. Rectifier, rectifier
transformers and ESS cabinets also require Fire trace type or equivalent protection. All
equipment and systems shall comply with the standards, rules and regulations which are
applicable in Philippine.
h) Switchgear shall be based on Air insulated vacuum / SF6 circuit breakers which can withdraw.
Contractor shall study the effect of the overvoltage generated due to break of max. possible
fault and its impact on the transformers. The transformers shall be designed accordingly.
i) The 34.5kV switchgear shall be designed for the following minimum ratings and not exceed
2.5 p.u. over voltages for any switching or breaking duty.
k) Number of phases: 3.
m) Rated short circuit breaking and making capacity shall meet the 34.5kV system fault level not
less than 25kA.
n) Rated current: 1250A with busbar rating of 2500A (1250A for ring breakers) or 630A with bus
bar rating of 2000A. Contract shall undertake studies to confirm the busbar rating.
o) The 34.5kV switchgear shall include earthing switches with the interlocking facility to ensure
that the earth switch is not closed when cable is charged and similarly the feeder is not closed
when the cable is earthed at any point.
p) Current transformers of suitable ratings and temperature class for protection and measuring,
Voltage transformers of suitable ratings and temperature class for protection and measuring.
q) 34.5kV switchgear shall be metal clad type. Metal clad type is not necessary for line isolator.
Earthing switch shall be provided in all outgoing and incoming cubicles.
v) Lock-out relay.
B. Rectifier Equipment
The Rectifiers shall be designed in accordance with the IEC 60146, IEC 60971, EN 50327, EN 50328,
EN 50124, EN 50122 and EN 50163. Rectifier shall be designed to run in parallel. Each rectifier
transformer and rectifier set combination shall incorporate full load overall efficiency of not less than
98% and power factor of not less than 95% lagging.
POW-4-50
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Each rectifier transformer and rectifier set combination shall provide linear inherent DC voltage
regulation for the full load voltage of not less than 6% of the full load voltage, from light transition
load (approximately 1 %) to 100% full load and shall be as linear as technically feasible up to the
300% full load current. The inherent voltage regulation at 300% full load shall ensure that the voltage
at the rectifier load terminals compliant with EN 50163.
The output DC voltage for each rectifier transformer and rectifier set combination, at light transition
load, shall not exceed the limit specified in EN 60163.
The DC traction supply system shall be designed to provide a voltage that is self-limiting at no load
as specified in EN 60163.
Rectifier Ratings
Rectifiers shall be rated in accordance with the parameters set out in Table 4 below:
Table 7: Rectifier Rating
POW-4-51
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The selection of series/parallel connection shall be done by Contractor keeping voltage drop and short
circuit currents within the design limits as per international standards and best practices.
a) Open-arm diode detection shall be provided and shall be monitored by the SCADA system.
b) The equipment covered by this specification shall be run in parallel. The rectifier unit shall be
equipped with surge protective devices to limit the reverse voltage across the silicon diodes to
a value within the peak-reverse-voltage rating of the diode, irrespective of whether the voltage
transient originates in the AC or DC power circuits. Protection shall also be provided against
lightning surges on the cathode and anode circuits.
c) Silicon Diodes shall be hermetically sealed and mounted on adequate heat sinks. Parallel strings
of diodes shall be electrically and geometrically similar, and as symmetrical as practicable, to
help balance the normal and surge electrical characteristics of each string. The rectifier shall be
capable of carrying the specified overloads and short circuit loads with one diode removed from
service from each leg of the rectifier circuit without exceeding safe junction diode temperature.
d) Each diode shall be capable of withstanding, at its maximum operating temperature during
blocking periods, voltages having a value of 2.5 times its working peak reverse voltage, without
a permanent change in diode. The rectifier shall be designed to maintain current balance
between parallel-connected diodes in each phase. This current balancing scheme shall hold
individual diode currents within their capabilities under all load conditions, with one diode per
leg removed. Current balancing shall not only be achieved by use of selectively matched diodes.
e) The rectifier cubicles shall be protected against fire by means of an 'automatic fire detector and
extinguisher system', 'Fire trace' type or equivalent, with provision of alarm.
When adopting a natural cooling system and connecting diode in parallel, diode fuses shall be
provided to disconnect any faulty diode.
Rectifier sets shall be rated for voltage of nominal 1500 VDC at continuous load (full load).
C. Rectifier Transformer
Rectifier transformer shall be used to provide the power to rectifiers. The main characteristics of the
transformer shall be as set out below:
a) Rectifier transformers shall be designed in accordance with JEC 2410-1998 or equivalent equal
and shall incorporate an earthed metal screen between high voltage and low voltage windings,
if necessary.
b) Rectifier transformers shall be rated to supply the full 1500V DC traction system load within
the continuous rating, with any one rectifier transformer out of service and without ESS. The
rating however shall not be less than 4.2 MVA. They shall also be designed to meet the parallel
operation requirements.
c) The overload ratings of rectifier transformers shall be utilized to accommodate any abnormal
loading in the event of train bunching or due to any abnormal DC traction feeding arrangements.
d) Off-load tapping links shall be provided on the high voltage winding to provide rated output at
+5.0% to -5.0% of nominal supply voltage, in increments of 2.5%. Tap indicator position shall
be visible through a viewing window.
POW-4-52
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
e) Two secondary windings shall be provided, one connected in star and the other one connected
in delta, to provide double six phase supply to the rectifier.
f) Rectifier transformers shall be fitted with a temperature alarm device, and temperature tripping
and pressure alarm and gas pressure tripping to be monitored by the SCADA.
Rating
The Rectifier Transformer shall be designed for the rating and other particular to suit the requirements
of rectifiers. The ratings given in Table 8 below are the minimum. The Contractor shall verify the
same through simulations and if required shall propose the higher rating for the successful operation
of the MMSP Project.
POW-4-53
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Cooling AN or AF
Temperature rise The temperature rise of windings and core shall not exceed the
permissible values as per IEC 60076.
Insulation rated voltage HV: - 36 kV
Primary Winding Power 70 kV
frequency withstand level
Primary Winding Surge 170 kV
withstand voltage
Fire behaviour class F1
Temperature Protection
All transformers shall be fitted with a temperature protection system that allows winding temperatures
to be monitored. Temperature monitoring devices with two thresholds (alarm and tripping) must be
provided and located on the upper part of the secondary windings. The cubicles shall be protected
against fire by means of an 'automatic fire detector and extinguisher system’, flooding type system,
complete with CO2 Gas cylinder and alarm.
Noise
Every care shall be taken to ensure that the noise produced by electrical machines/ equipment is
minimum. Necessary noise reducing methods may be applied and the noise at the machine shall not
be more than as specified in the applicable international standards. For transformers, the relevant noise
level as per (National Electrical Manufacturers Association) NEMA shall be applicable.
1500V DC Indoor type air insulated switchgear for Rectifier Positive protection.
1500 V DC Indoor type air insulated disconnecting switches for Rectifier Negative separation.
The DC traction Sub-Stations shall provide power to the OCS with DC traction supply at a nominal
1500V DC and return shall be via the running rails and return current cables.
The 1500V DC traction Sub-Stations shall include rectifier transformers, rectifiers, high speed circuit
breakers, associated switches, protection, earthing, negative return panels and any other item required
to complete the work.
Incoming Circuit Breakers (CB) of the single pole High Speed Circuit Breakers (HSCB) shall be
installed between the rectifier group and 1500 V Positive bus bars and shall be interlocked with the
traction transformer incoming CB.
For connecting the negative terminals of the rectifiers with negative bus bars, motorized off load
switches, interlocked with corresponding HSCB & Disconnector Switches shall be provided.
From the 1500V DC positive bus bar, feeder HSCB & DC disconnector switches shall be provided to
feed power to the overhead line.
POW-4-54
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
All high voltage switchgear shall be designed and manufactured in accordance with the requirements
of IEC 61992, IEC 62271, and IEC 60298 as applicable.
E. 1500V DC Switchgear
DC switchgear comprising DC high speed circuit breakers shall be provided for switching off the
rectifier DC incoming feeds and outgoing feeds to OCS. The DC switchgear shall be equipped with
necessary functions for SCADA control and indication. All breakers shall have trip free and anti-
pumping facility suitable for automatic re-closing. All breakers shall have service and disconnected
positions. When the breaker is in test position, local/remote switching and trip tests shall be able to be
carried out.
The DC switchgear shall be of metal-clad multi-cubicle type installed on the insulation pad for
isolation from earth and AC system earths, equipped with enclosure fault detection, with withdrawal
circuit breakers for positive pole switching and isolating. It shall be complete with all the current
transformers and voltage transformers of adequate capacity and requirements and as per IEC 60044.
It should have all necessary interlocking and safety features. Negative connections shall be a collector
bar incorporating earth returns and monitoring. Rectifier circuits shall incorporate reverse current
tripping.
The DC switchgear shall be inclusive of circuit breakers and isolators cubicles shall be protected
against fire by means of an 'automatic fire detector and extinguisher system', 'Fire trace' type or
equivalent, with provision of alarm. In addition, Contractor shall comply with the standards, rules and
regulations which are applicable in Manila, Philippines.
Lightning and switching surge arresters shall be provided for feeder and inter-tripping cables of feeder
circuit breakers and sectionalizing switches. The DC switchgear enclosure shall be insulated from
ground by an insulated floor topping extending one meter around it and allowing for circuit breaker
removal from the front. The DC switchgear with minimum ratings shall be provided in accordance
with the following parameters, however Contractor shall verify the adequacy of switchgear ratings
using the simulation.
DC HSCB
Fault indicator
Mimic bus
2. DS, isolation and protection for Rectifier Negative circuit minimum includes:
POW-4-55
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Fault indicator
Mimic bus
DC HSCB
current protection
Fault indicator
Mimic bus
DC HSCB
DC current transformer for over current protection and rate of rise of protection
Fault indicator
Mimic bus
DC HSCB
Fault indicator
Mimic bus
POW-4-56
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Fault indicator
Mimic bus
All DC switchgears shall be isolated from the ground and the switchgears shall be rigidly fixed to the
floor with anchor bolts.
Negative connections shall be a collector bar incorporating negative returns and monitoring.
OCS contact feeder protection shall detect short circuit (by direct acting trip devices in DC circuit
breakers) and limited faults (by multifunction relay with DC fault selective device) but shall not cause
tripping due to load current in other normal operating modes.
In the event of OCS contact feeder failure, all the circuit breakers for feeding the same track and the
same section shall trip automatically with Tele-command braking devices.
In the event of OCS contact feeder protection failure, all the circuit breakers for feeding the same
track, the adjacent section of failure section, all the circuit breakers for feeding another track shall be
opened automatically.
It shall be attached to a DC WHr meter on the 1500V DC feeder for PRI in Depot TSS so that the
power of 1500 V DC used in PRI can be recorded.
Rated current shall be a minimum of 6000A for bus & 4000A for HSCB outgoing however, Contractor
shall design and validate the ratings as per calculations, studies and standardization. The Indicative
ratings of HSCB are given in Table 9 below:
POW-4-57
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Negative disconnect switches shall be mounted, have an insulated operating handle and shall be
interlocked with the rectifier main circuit breaker.
Interlocking shall prevent opening the negative switch when the breaker is closed and prevent closing
the breaker when the negative switch is open.
The negative switch shall be rated to suit the installed HSCB as a minimum and shall have momentary
current rating equal to that of the rectifier main circuit breaker. Negative disconnect switch and 1500V
DC negative cables shall be capable of withstanding the thermal and mechanical stresses associated
with the available short circuit current at the rectifier output.
The DC negative bus shall be rated 1500V DC, to suit the complete DC switchgear and shall be of
sufficient strength to withstand the short circuit current available from two 4000 kW rectifier units
and ESS, and shall be of sufficient length for connecting the required number of negative return cables
from the tracks, cables/bus ducts from each rectifier unit, and a running rail grounding.
During braking, the induction traction motor on the train consumes reactive power that magnetizes
the stator and rotor windings and generates real power back to the system. The amount of power
regenerated depends on the receptivity of the line which in turn depends on the load location, allowable
voltage band for regeneration and distance between the TSS, under no load, the brake power is wasted
in frictional losses.
The addition of the Energy Storage System (ESS) shall make the Overhead OCS (OCS) receptive to
taking regenerated power at all times and remove the dependence of regenerative braking upon the
presence of an accelerating train in the same section as the braking train.
The Contractor shall design, manufacture, and supply eight (13) ESS units. Each ESS unit shall have
a capacity of at least more than 500kW which shall be decided based on a power simulation finally,
using Li-ion technology batteries as the storage medium. The design life of the ESS shall be 30 years.
The battery life shall be not less than 15 years design life or the suitable design life in consideration
of Life-Cycle-Cost of ESS's design life (30 years).
POW-4-58
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Contractor shall also be responsible for performing the detailed simulation studies to assess the
capacity of ESSs and that can be replaced rectifier units, as OPTION 2 proposed shown in Fig. 4.
The energy storage system shall be designed to meet the following functional requirements:
d) It shall store regenerative braking energy and shall give it back to the system to improves the
energy efficiency.
g) Under the scenarios of power failure from grid, ESS shall also act as off-grid power supply
source for bringing the trains of Main Line up to the platform, that is ESS shall also provide the
capability to move the train to the next station for passenger disembarkation at the station in the
case of power failure on a section of the line or a power failure on the entire line.
h) The Contractor shall design the ESS so that the maximum technically possible regenerative
power is consumed and used.
i) The Contractor shall declare the number of trains stuck in a section under various operational
timetables which can be bought up to the platform. The Contractor shall also prepare an
operational methodology and detailed procedures setting out the actions by which the maximum
number of trains stuck in the section can be bought up to the platform during grid failure.
j) The space earmarked for ESS at the specified location has been given in the drawings and it
will not be possible to increase the size of room.
ESS Characteristics
The characteristics of ESS shall be designed using simulation study to take into consideration the
following factors:
a) The no. of charge /discharge cycles as well as energy storage characteristics of ESS shall be
commensurate with the no. of stopping and starting required as per track plan/operational plan
so that the design life of 30 years is achieved.
b) Energy storage capacity is also determined by the requirement of power level during starting.
c) The ESS shall have power control system to make it compatible for all operating modes and
balance the load current between convertor cabinets.
d) It shall maintain time stamped log file of metered energy flow twice a day & fault levels.
e) The power density, Energy density and capacity of the batteries of ESS shall match with the
requirements ascertained after conducting simulation study under the operational scenarios.
a) Regeneration power storage equipment using Li-ion battery technology shall have proven
satisfactory service experience, and evidence shall be provided to show satisfactory operation
of similar system in commercial Metro service for a minimum period of one year.
POW-4-59
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
b) The regeneration power storage equipment shall be suitable for Metro system operation at
1800V DC.
c) ESS shall be used to prevent regeneration lapses by maintaining adequate absorption capacity
during normal operation and shall have a function which supplies sufficient power to stopped
vehicles between stations to restart running to the nearest station in case of a power outage.
d) ESS shall have a function of 'Black Start' under a power outage. All the power to restart the
equipment and the supply to the vehicles in emergency operation shall be supplied by the
batteries of the equipment.
e) The regeneration power storage equipment shall be able to withstand the strains, jerks,
vibrations and other conditions incidental to shipping, storage, installation and service use
without degradation in performance.
f) Components which perform identical functions within the regeneration power storage
equipment shall be electrically and mechanically interchangeable.
g) The regeneration power storage equipment shall be designed for quick restoration of service in
the event of a service affecting fault.
h) The regeneration power storage equipment shall be designed to operate in the environment in
which it is installed and to withstand the effects of high temperature, humidity, vibration, noise,
and air pollution.
i) The Mean Time Between Failure of the ESS leading to the system being unable to perform the
traction power energy saving shall be at least 30 years while availability shall not be less than
99%.
1. The ESS shall consist of control equipment, electronic switching circuits, filter device and
power storage equipment. The regeneration power storage equipment shall be connected to the
positive busbar of the DC switchgear through the highspeed DC circuit breaker and negative
busbar of the rectifier through the negative isolator. The ESS shall be interlocked with the DC
circuit breaker and the negative isolator to ensure the correct operation of the equipment.
2. The ESS assemblies shall be housed in an appropriately ventilated approved sheet steel type
enclosure, free-standing, forced cooled type assemblies with pad lockable doors. Access and
internal arrangement shall allow for easy inspection and maintenance.
3. All live parts and components shall be insulated from the enclosure, and the clearance and
creepage distance shall comply with the relevant requirements as specified in EN50124-1. The
enclosure shall be earthed to the TSS earth trough leakage detection.
4. The ESS shall mitigate the current of regeneration power to the OCS and batteries through
bidirectional electronic switching circuitry.
5. IGBT's in the electronic switching circuits of the ESS shall regulate the voltage and current of
the regenerated power.
6. Door open detection protection equipment shall be provided to trip the DC circuit breaker for
the ESS in each enclosure of the ESS to protect against electric shock from direct contact with
the live parts inside when the panel door is being opened.
POW-4-60
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
7. The ESS shall be provided with protection device to limit the contribution of fault current from
the ESS when OCS or busbar fault occurs.
8. The ESS shall be provided with isolators or withdrawable circuit breakers to isolate the ESS
from the DC positive busbar, DC negative busbar, battery positive and negative poles.
9. The ESS shall be provided with the flush mounted digital indicating & recording instrument to
indicate and record the following:
10. The ESS shall initiate local and remote alarm if any of the following conditions occurs:
11. The ESS shall automatically trip the DC circuit breaker and initiate local and remote SCADA
alarm if any of the following conditions occurs:
b) IGBT over-current;
h) Battery over-charge;
i) Battery over-discharge;
j) Battery over-voltage;
POW-4-61
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
I) Earth fault.
DC 1500 V Switchgear
DC 1500 V Indoor type air insulated switchgear, for DC feeder protection 400 / 230-115 V Indoor
type transformer cubicle (For 400 / 230-115 V operation transformer).
It shall be draw 400V, 3-Ph LVAC from Lawton East Station and Lawton West Station respectively
and shall be switched power supply by power outage.
The current transformer (CT) shall be designed to be compliant and meet the following requirements:
a) Design and installation shall be in accordance with IEC 60444-1 or equivalent, and
b) Class and rating shall be suitable for metering, monitoring and protection requirements.
The voltage transformer (VT) shall be designed to be compliant and meet the following requirements:
a) Design and installation shall be in accordance with IEC 60444-2 or equivalent; and
b) Voltage transformer’s accuracy class shall be suitable for metering, monitoring and protection
requirements.
L. Surge Suppression
The DC traction supply voltage shall be permitted to rise to a maximum of 2100V DC during the
regenerative breaking of the trains. In addition, the DC traction system shall sustain transient voltage
surges category OV4 as per EN 50124 between the positive and negative poles.
Suitable surge and transient absorption circuits and surge diverters shall be provided to protect the
rectifier sets from the effects of lightning strikes on the overhead contact and running rail.
This specification applies to negative earthing contact equipment ("Short Circuiting Device" or
"SCD") also referred to as OPVDs (Overvoltage protection devices for track) housed in track earthing
panel for 1500V DC system to be installed in the TSS for control and protection against voltage
difference between Running Rail Voltage and the Substation earth busbar.
Short Circuiting Devices shall be installed in all stations with TSS. At other stations, the device shall
be installed in the SSS.
In TSS the device shall be connected to negative return panel and to the return rail where it is installed
in an SSS respectively. The rails at stations shall be connected through appropriately sized insulated
conductors.
EN 50122-1 prescribes the tolerable I safe value of running rail potential for different time intervals
and in the event of running rail potential breaching these values, the SCD shall operate and earth the
return circuit (to Substation earth).
POW-4-62
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Resetting of SCD after operation shall be as per the provisions of EN 50122-2. To achieve this, the
SCD shall be provided with necessary numerical relays.
g) Return circuit;
i) Special over-voltage relay suitable for detecting both positive and negative over-voltage with
respect to earth; and
The PLC shall have defined protective characteristics for DC and AC voltages. It shall be possible to
define user characteristics for DC and AC voltages. It shall be possible to continually view the values
of monitored voltage, current and contactor state on the HMI mounted on the panel and at SCADA.
The Short-Circuiting Device shall also serve an additional purpose of stray current monitoring. The
voltage sensed by the voltage sensing devices and the conductance of the running rail with track plinth
shall be calibrated in terms of stray current in the system. These values shall be transmitted to SCADA
for monitoring. Additional logics shall also be developed to initiate an alarm in case of failure of
insulation between running rail and track plinth. In addition, provisions shall be made for connection
of SE cable to negative return path through diode only for the purpose of periodical monitoring of
stray currents. Under normal operations, switch provided for this connection will be in normally open
(NO) position and switch will be closed for monitoring of stray current once or twice in a year as
required.
Isolating and earthing facilities shall be provided in order to enable maintenance to be carried out
safely on the rectifier transformers and the rectifier sets.
110V DC supply for control and protection shall be provided for use at BSS, SSS, TSS and Sectioning
Post. The Contractor shall provide nickel-cadmium, maintenance free 110V batteries complying with
IEC 60623 system for safety tripping, service current functions and power to the SCADA remote
terminal units. The batteries shall have design life of 15 years. The battery system shall be rated to
supply the standing loads for a minimum of 08 hours in the event of a charger supply failure, and at
the end of that period shall be capable of operating each item of equipment for two cycles, i.e. one
cycle is open and close. The end cell voltage shall not be less than 1.05 volt.
POW-4-63
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Contractor shall validate the capacity after considering all applicable de-ratings as per relevant
standards. It shall not emit hazardous gases. The number of battery chargers shall be one more than
the number of battery banks so that at least one battery charger is available as a standby in case of
failure of one charger.
Battery chargers main and standby shall comply with IEC 60146 or equivalent and latest versions and
shall be provided with self-regulation and shall be capable of restoring a minimum of 80% of battery
capacity within 10 hours of full discharge. For better compatibility, the battery and battery chargers
shall be supplied from same manufacturer. Sufficient indications shall be provided on the battery
charger to provide status information of the battery charger system, as a minimum this shall include
battery voltage, trickle charge and booster charge currents, battery charge functioning and battery
charge failure. In addition, status information about the value of voltage and the status of healthiness
and unhealthiest of the charger shall be provided to the SCADA system. Battery chargers shall
incorporate measuring instruments such as ammeters and voltmeters as a minimum. A DC distribution
board to safely receive the DC power through circuit breaker of adequate capacity and similarly
distribute the outgoing power to various circuits as required through circuit breakers shall be provided.
Ripple content in the output voltage in any case shall not be more than 3%. Battery charger shall have
Automatic change-over from floating to equalization charge and conversely. Following any failure of
more than five minutes of the AC supply network, the charger shall automatically revert to the charge
position right upon return of the voltage and shall remain on this position for an adjustable time. After
this time, the charger shall return to floating operation. The charger shall remain in floating operation
if the network failure is shorter than five minutes.
The batteries and battery chargers to be installed at each site shall be the Ni-Cd type.
P. Battery Units
a) For the traction substations, and sectioning post, the Contractor shall provide 110V battery
system for safety tripping, service current functions and power to the SCADA remote terminal
units.
b) The battery system shall be rated to supply the standing loads for a minimum of 8 hours in the
event of a charger supply failure, and at the end of that period shall be capable of operating each
item of equipment for two cycles, i.e. one cycle is open and close.
c) During such duty output voltage shall be within the tolerances defined for operation in the
relevant equipment specifications.
d) The 110V batteries shall be of the Ni-Cd type, maintenance free type and shall not emit
hazardous gases.
Q. Battery Chargers
Battery chargers shall be provided with self-regulation and shall be capable of restoring a minimum
of 80% of battery capacity within 8 hours of full discharge.
Sufficient indications shall be provided on the battery charger to provide status information of the
battery charger system, as a minimum this shall include battery voltage, trickle charge and booster
charge currents, battery charge functioning and battery charge failure, DC failure and battery
impedance fault or battery earth fault.
POW-4-64
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Battery chargers shall incorporate measuring instruments such as ammeters and voltmeters as a
minimum.
The UPS supply for Power SCADA shall only be required at OCC. The RTUs at stations and other
places shall be installed with suitable converters. UPS shall be supplied after catering the load of
various subsystems. Backup period required for various subsystems shall not be less than 4 hours.
The Contractor shall liaise with the various subsystems as necessary to determine final equipment
ratings and power requirements. The Contractor shall design, install and tests of UPS system in
consideration of the subsystems' requirements mentioned in the Tender Documents.
The battery used for UPS which will be for Power SCADA shall be Ni- Cd type with end cell voltage
of 1.05 Volt.
The UPS shall comply with IEC 62040 and the rectifier shall be IGBT based whilst the Converter
shall be of the PWM type.
The UPS will be supplied from the 400V AC Distribution Boards. The contractor shall liaise with the
station Contractors in respect to the supplies on the stations, Depot and OCC.
Batteries shall be placed at least in 2 step 2 tier racks or cabinets for space saving.
a) mains UP
b) Mains Down
c) Mains restored
Refer to Fig. 1, Fig. 2 and Fig. 3 for 34.5kV Ring Main Unit (RMUs) feeding arrangements, as indication, to be
installed on the main line and Depot. Contractor shall review the Power System Supply feeding arrangements
for both main line and Depot to ensure the compliant with the operation requirements and the system is reliable.
4.8.7 Dry Type Transformer (Delta-Star) for Depot and Main Line
The minimum rating of the 34.5kV/0.4kV transformer installed on the main line and Depot shall be cast resin
dry Type, oil free and shall have an overload capacity of 125% for 15 minutes after an interval of 3 hours.
POW-4-65
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Dry type transformers shall be designed and manufactured to comply with JEC2200-1995 and or
particularly IEC60076.
34.5kV/0.4kV distribution transformers and 34.5kV/0.23-0.115 kV operation transformers shall comply with
the requirements of JEC2200-1995 or equivalent equal. 34.5/1.18 kV Rectifier transformers shall comply with
the requirements of JEC 2410-1998 or equivalent EN / IEC standards.
The Contractor shall determine actual rated power based on the station and all electrical load schedules to be
supplied by the Civil Contractors. The Contractor’s operating plan requirements, the Contractor’s evaluation of
MMSP Project power requirements.
The base of the transformer shall be designed to spread the weight of the transformer over an area as large as
possible within its space envelope.
The rated insulation level shall comply with the following minimum ratings and requirement
POW-4-66
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
winding; according to neutral earthing mode of the distribution system for the low
voltage winding.
Air-filled cable box for high and low voltage termination shall be provided.
Percent impedance:
7% or more
5% or more
The 400V LVAC Low Voltage panels shall be equipped with the air circuit breaker, meters, CT, PT etc. shall
be provided for receiving the power at 400V AC, 3-Ph, 60Hz from both distribution transformers using half
sectionalizer scheme.
In case of the SSS and TSS on the stations, the scope of LV panels is in the scope of the Building Services
Contractors. In the BSS however, AC distribution boards shall be provided for the supply to the battery chargers.
The LV panels shall be provided with microprocessor base relays for protection and shall be suitably graded
with the lower side of supply.
Main incomer and coupler receiving power from the transformers shall be capable of operating under
Auto/Manual mode as well as local/remote mode.
Busbars (copper) and circuit breakers for the entire LV panel shall be sufficiently rated to provide the
overloading and short circuit Protection.
Emergency power supply shall automatically start up in the event of the absence of incoming of 34.5kV supplies
and shall be capable of automatically delivering the essential demanded power, up to the rated value, within 10
seconds.
The emergency generators shall be diesel type having nominal output voltage of 400V, 3-Ph, 4W system. The
Contractor shall undertake details studies to determine the actual emergency loads required for the final sizing
POW-4-67
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
kVA rating of the Diesel Generator Set. The emergency generator excitation system shall be of the fast-acting
type to ensure the rapid response during motor starting and sudden load change.
The emergency generator shall be designed and installed with the complete fuel storage facilities include outlets,
exhaust ducts etc. and shall be capable to provide the specified performance continuously for a minimum period
of 8 hours without the requirement of inspection or attention.
The emergency generator set shall be capable to withstand a sudden short circuit, maximum over-speed without
any damage, as defined in JEM 13542014 or IEC 60034.
The emergency generators and exciters shall be of totally enclosed, brushless type, and shall comply with the
requirement as defined in JEM 13542014 or IEC 60034. The line and neutral phase ends shall be brought out
to separate terminal boxes. The winding insulation shall conform as a minimum to temperature ‘Class F’ in
accordance with IEC 60034.
All necessary metering instruments, current and voltage transformers for protection, control, metering and noise
control facilities shall be included. The noise control facility shall be compliant with the local codes, the
environmental requirements and pollution control. All protection systems shall be able control and monitoring
via SCADA.
Auxiliary power supply shall be provided by means of appropriately sized battery to enable starting the
emergency generator.
The support structure for Diesel Generator shall be built to withstand the seismic or any natural caused to
blackout Manila City, that has minimal impact on Diesel Generator and thus to ensure the supply is available to
provide for emergency loads in the station, for the safety of passengers inside the station and or tunnel.
The Emergency Tripping System (ETS) is to achieve an electrical tripping scheme to de-energize the OCS
section during emergency conditions. Upon activation of the ETS the HSCB feeding to relevant OCS Section
shall trip. In addition, it shall generate a signal (interfaced with signalling system) that shall stop the train from
entering the dead section. The ETS Box shall consist of a unit which is fire protected and with a breakable glass,
containing the emergency push button. The ETS Boxes shall be of such dimensions, colours and characteristics
that they shall be visible from 20 meters.
It shall also house a blue lamp to indicate its location and also be provided with a heavy duty hot line telephone
handset directly connected to the Station Controller and the OCC.
ETS boxes shall be cabled to the nearest PLC/RTU/PLC through fire survival armoured cables capable of
withstanding temperature up to 750 degree C for 3 hours and in that condition do not support combustion.
The protection and control system shall be designed to achieve a minimum of 99.99% fault detection capability
of all critical faults. Contractor shall carry out details protection studies, control and monitor for the complete
MMSP Power Supply Systems.
POW-4-68
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Protection
Each protection shall have main and separate backup protection design. The same CT shall be avoided while
incorporating the backup protection.
The Contractor shall be responsible for the verification and adjustment of protective relay settings to be
conducted during field testing subject to the satisfaction of the Engineer.
Interlocking
The complete system shall be provided with the interlocks necessary for the safe operation of the electrical
system. The interlocks shall prohibit the opening or closing of switches under conditions not intended from
safety or design. e.g. opening of isolator on load, closing of breaker when the feeder is earthed even from another
end. The system shall be incorporated with inter tripping for safe operation of the system. The hard interlocks
shall also be duplicated in soft using SCADA.
Protective Relays
All main protective relays shall be of fully numerical type and shall comply as per IEC 61850 standard. Further,
the test levels of EMI as indicated in IEC 61850 shall be applicable to these. All the relays shall be directly
connected to inter bay bus using Electrical/fibre optic cables and shall support peer to peer communication. The
relays shall generate GOOSE messages as per IEC 61850 standards for interlocking and also to ensure
interoperability with third party relays. Each relay should also generate an ICD file in XML format for
Engineering / integration to a vendor independent SCADA system. All the relays shall have suitable rear and
front ports for connectivity to SAS and PC/LAPTOP.
For numerical relays, the scope shall include the following:
1. Necessary software and hardware to up/download the data to/from the relay from/to the personal
computer installed in the Sub-Station.
2. The relay shall have suitable communication facility for connectivity to SCADA. The relay shall be
capable of supporting IEC 61850 communication standard.
3. The relays shall have fault record, event record, and disturbance record for fault diagnostic and shall
have communication ports for local communication for relay settings, modifications, extraction and analysis of
fault/event/ disturbance records from a laptop and for communication with Sub-Station automation system.
6. The Substation Automation System (SAS) shall be installed at receiving Substations including that for
the 34.5kV supply inside Depot BSS to control and monitor all the substation equipment from Operation
Control Centre (OCC), and possibly Backup Control Centre as well as from local control centre.
a) 115kV incomer: Pilot wire, distance protection, over current protection, earth fault protection. Any
specific protection required by the Power Supply Authorities MERALCO.
b) 115kV power transformers: Transformer shall be protected by the protections based on the electrical
parameter in addition to inherent protections like, bucholz, PRV, over temp, etc. The main protection
shall be transformer differential, restricted earth fault on primary and secondary, over current, earth
fault, overvoltage, over fluxing, standby earth fault Transformer shall also be protected from the
overloading characteristics. The characteristics of this protection shall be based on the transformer
overloading characteristics.
POW-4-69
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
c) Complete 115 kV systems shall be protected by the busbar protection with zones segregation.
d) The TSS and SSS receive all the power which is to be transmitted to the MMSP network. For the safe
operation of the same, the protection system is to be designed with high degree of reliability. Main
protection shall be over current, earth fault. Contractor to device solution based on the combination of
concept of direction, logical & grading to achieve high selectivity and reliability of the system protection
particularly for ring main.
The Complete network shall be protected using the pilot wire protection. The network shall also be provided
with the directional over current and earth fault protection.
Distribution transformers as well as rectifier transformer with more than 630kVA capacity shall be provided
with the transformer differential protection. The TSS and SSS have an environment that is non-air-conditioned
and equipment to suit such an environment is to be provided.
Localization of faults shall be ensured either using the logics, communications, or grading. A fault in a section
shall generally not lead to the tripping of the breakers not intended to trip.
The protection provided to 34.5kV RMUs shall be includes but not limit the following scope:
d) LV cable to the LV changeover panel against short circuits and earth fault;
LV changeover panel ACBs shall be set to protect the HV/LV transformer (provided by E&M Contractor)
secondary winding and LV cables from overload.
In order to isolate the DC system from the other system in vicinity and the leakage protections to work as per
requirements, the complete DC system shall be insulated from floor using the insulation mat. The Contractor
to upgrade the scheme as per best international practices and shall provide.
A provision shall be made to earth the running rail i.e. negative bus, in case of rail potential being higher than
limits prescribed in relevant standard (EN 50122 or equivalent) in order to ensure safety of personnel. This will
be achieved by providing Short Circuiting Device (SCD) sometimes referred to overvoltage protection devices
(OVPD) at stations close to platform. At least one short circuiting device shall be provided at each station. In
case the station has a TSS, the device shall be provided in the TSS. Whereas in case, the station does not have
a TSS, the device shall be provided inside SSS.
Provisions shall be made for continuous monitoring of the stray current as per EN-50122 at multiple locations
through SCADA system. Contractor shall provide necessary arrangements at TSS for monitoring and recording
of potential with respect to reference electrodes. The system will be based on track voltage, track resistance,
conductance of the track with or without influence of other structures with provision of Amp/hr, Amp/min and
Amp/sec. and facilities for logging of any increment. Design of the monitoring arrangement shall be agreed by
POW-4-70
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
the Engineer. Monitoring points at the substation shall be interfaced with the SCADA system for remote
monitoring and/or action at the Control Room. The Contractor will carry out regular stray current monitoring
and analysis after the start of revenue service for first 2 years, and comparisons will be made against the first
survey reference data (Baseline survey) and analytical results. The Contractor shall also provide portable
measurement system and install points of measurements for further detailed investigation or observations in
case of abnormal conditions. The provision of event logger at OCC and the concerned networking and other
required systems, subsystem complete with backend or operating software shall be in scope of Contractor.
The Contractor shall interface with track work for design and installation of stray current mesh, cross bonds and
associated cable connections.
2. Depot
A separate TSS has been provided for Depot so as to facilitate isolation of Depot traction supply from mainlines
in order to prevent the leakage of return currents to Depot area. The mainline tracks and OCS supply shall be
isolated from Depot tracks through insulted rail joints and sectioning insulators in order to minimize the stray
currents, even during the movement of the trains. Remote operated sectionalizing switches shall be provided to
feed power from Depot to mainline and vice versa in case of failure of Depot TSS to rescue the train during the
inadvertent stopping of train in dead section.
In areas, where leaky conditions exist (e.g. washing lines, pit wheel lathe etc.), insulated rail joints (IRJ) shall
be provided with power diodes to bridge the IRJ to facilitate passage of return current. The non-electrified
tracks shall also be provided with the IRJs.
The prescribed limit of highest touch potential in Depot is 25V as per EN50122 and therefore OPVDs shall be
provided at suitable locations to earth the rail in case the rail potential exceeds this limit.
POW-4-71
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. Auto re-closing.
4. Rectifier operation in single and parallel and the regulation curve of rectifier;
7. If the excessive currents or touch voltage persists for more than specified time, the protection system
shall trip off and isolate the relevant section. The time settings and specified times shall be proposed as a part
of protective system design finalized by the Contractor.
To avoid such scenarios, the use of computer simulations to examine current passing under such case and setting
the relays accordingly may help. The setting groups more than one may be used in protection with a facility to
change from one to another from remote.
POW-4-72
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. The switchgear positions shall be indicated by two auxiliary switches, normally closed (NC) and
normally open (NO), which shall give ambivalent signals. An alarm shall be initiated if these position
indications are inconsistent or if the time required for operating mechanism to change position exceeds
a predefined limit.
3. The SAS shall also monitor the status of sub-station auxiliaries. The status and control of auxiliaries
shall be done through separately with IED and with redundancy.
4.8.19 Measurements
1. Analogue inputs for voltage and current measurements shall be connected directly to the voltage
transformers (VT) and the current transformers (CT) without intermediate transducers. The values of
active power (W), reactive power (VAR), frequency (Hz), and the rms values for voltage (U) and current
(I) shall be calculated.
2. The measured values shall be displayed locally on the station HMI and in the control centre. The
abnormal values must be discarded. The analogue values shall be updated every 2 seconds.
4. Event and alarm handling: Events and alarms are generated either by the switchgear, by the control
IEDs, or by the station level unit. They shall be recorded in an event list in the station HMI. Alarms
shall be recorded chronologically with time in a separate alarm list and appear on the screen. It shall be
possible to store all events in the computer for at least one month. All, or a freely selectable group of
events and alarms shall also be printed out on an event printer. The alarms and events shall be time-
tagged with a time resolution of 1 ms. Event list shall contain:
iv. Indication when analogue measured values exceed upper and lower limits. Suitable provision
shall be made in the system to define two level of alarm on either side of the value or which
shall be user defined for each measured
v. Loss of communication
vi. Filters for selection of a certain type or group of events shall be available. The filters shall be
designed to enable viewing of events grouped per:
• Bay;
• Device;
• Alarm list.
POW-4-73
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
vii. Faults and errors occurring in the Sub-Station shall be listed in an alarm list and shall be
immediately transmitted to the control centre. Each alarm shall be audible and shall be reported
on one line that contains: the date and time of the alarm, the name of the alarming object,
descriptive text, acknowledgment state.
CABLES
4.9.1 General
All cables shall be sized to carry the continuous current required by the specification and shall be based on the
Contractor’s calculations.
The cables shall be able to withstand the short circuit currents inherent in the Contractor’s design. The cables
installed shall be non-fire propagating type (FRLS). The Contractor shall submit full technical details of all
cables the cables shall be meggered (Insulation tested) to record the (Insulation Resistance) IR value before
unloading from the drum, after laying and before connection to the switchgear.
The ratings applied to any cable shall be determined by the most onerous installation condition in any cable
route.
All cables and cable and support facilities to be installed in the substations shall be low smoke non-halogen
compound (LSZH) type and fire retardant.
Cable sheath shall bear the manufacturer’s name, conductor size, type of insulation, voltage rating and year of
manufacture.
Cables for 34.5 kV distribution shall have cross-linked polyethylene (XLPE) insulation, single core and stranded
copper or aluminium conductor in trefoil formation sized to suit the power supply system design and to satisfy
short circuit current requirements.
The Contractor shall coordinate with the Local Electricity Authority MERALCO with regard to cable routing
and conduits for cables for 115kV and 34.5 kV feeders between the MERALCO substations and the traction
substations.
34.5 kV Cables are required to be used generally for the following connections:
From the Power Transformer Secondaries to the 34.5kV Switchgear in the BSS.
POW-4-74
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
From the 34.5kV Switchgear to the 34.5kV / 400V Station Transformers and to the traction transformers in
TSS.
The 34.5kV Cables shall conform to IEC 60502 and shall be of 19/33 kV/ (36). The copper conductor shall
conform to IEC 60228. The cables shall be cross-linked polyethylene, with semi-conducting screen over a
copper conducting core, and insulating envelope and protective sheath. The cables shall be of dry-insulated,
radial-field cable, based on proven technology. The cables shall be FRLS type and protected against
(Ultraviolet) UV rays.
All cables shall be non-fire propagating; non-toxic and low smoke producing and conform to IEC 60502-1 or
equivalent. Contractor shall verify the capacities and shall install the cables as per actual thermal, climatic and
laying conditions.
In High Voltage power transmission, three single core cables are used in place of three core cables. In the single
core power transmission, the cables are usually covered with a metallic sheath to prevent ingress of moisture,
protect the core from possible mechanical damage and create an earthed shield. Unlike the three core cables,
the Single core cable behaves like a transformer. The current carrying conductor of the cable acts as the primary
winding and the metallic sheath as the secondary. The field of the current carrying conductor induces a voltage
in the metallic sheath-which is to be limited below the value specified in the standards. This in turn leads to the
circulating currents in cable. To utilize the full ampacity of the cable, special bonding methods like single point
bonding, midpoint bonding and cross bonding may be employed. The earth continuity conductor shall be used
throughout route for proper earthing. The IEEE-575 shall be followed for the bonding, sheath voltage
calculations and testing of accessories. The bonding and cross bonding requirements shall be calculated for the
most onerous laying conditions and to achieve the full ampacity of cable. The scope of work includes Supply,
Installation & Commissioning of complete kits with accessories for jointing, cross-bonding, mid-point bonding,
single point bonding, termination of cables, cable termination structure and jumping at PSA, its installation. The
joints are to be located and secured in a joint box. Provision of required number of sheath voltage limiters
(SVL's) and earthing electrodes as necessary and commensurate with soil resistivity and bonding shall be
installed.
Cable for 1500 VDC Shall have XLPE insulation and armoured, single core stranded copper conductor sized to
suit the power supply system design and to satisfy short circuit current requirements. The cable shall be fire
retardant.
POW-4-75
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
e) If heavy currents are to be carried, the economic section must also be taken into account;
f) Systematically, for control and monitoring cables, all the links of a section shall include 15% spare
conductors with at least one spare conductor per cable; and
Contractor shall interface with E&M Contractor to ensure the compliant of the above information given.
Optical Fibre cables shall be in accordance with ISO/IEC 11801 and or ISO 60793 as appropriate.
Optical Fibre cable shall be installed for interconnection between the interlinked tripping devices located in
between each traction substations.
Optical Fibre cable shall consist of four cores, including two spare cores using trunk cable constructed by
telecommunication work between stations.
Optical Fibre cable for interlinked tripping device shall be installed into the tunnel side cable troughs by
telecommunication work.
Optical Fibre cables used for line differential protection of all 115kV & 34.5kV cable and for interconnection
between the linked breaking devices located in traction substations. OFC Fibre may also be used for other inter
tripping commands between various TSS as per proposed design of Contractor. OFC shall be laid in conduits
or on trays of appropriate size. The patch cords/connecting cods at Line Interface Units and Equipment shall be
fully protected against any mechanical damage.
Optical Fibre cables shall be protected by steel wire or Kevlar type armouring for all externally mounted cables,
including those running along the tunnels.
POW-4-76
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Kelvar type armouring is preferred as there is no chance of interference with other systems and safety problems
caused by induced circulating currents in the event of incorrect, damaged or miss-installed single point earthing.
The Contractor shall be required to provide adequate justification for the choice of cables and provide evidence
that the cables are fully rodent proof.
2. Supporters shall be installed in the trench and on the racks to support cables to keep adequate distance.
3. The Contractor shall design the appropriate cable route between equipment and provide racks for
cabling in the substations. The Contractor shall coordinate with Interfacing Contractors with regard to
the openings for cable entrance on the building walls and floors.
4. All openings for cable entrance on the building walls and floors shall be stopped with non-inflammable
materials by the Contractor after all cables have been installed, to prevent fire extension.
1. Cable risers shall be protected with cable trays and steel conduit pipes.
2. Bending radius of high voltage (HV) and low voltage (LV) cables shall be as per cable manufacturer’s
recommendation.
3. Cable trays shall be fixed to the wall or the ceilings, fixing intervals shall be less than 1.5 m.
4. Cables laying with cable trays on the vertical direction shall be bound tightly at the 1.5m intervals.
6. Openings for cables drawn into cubicles shall be protected properly so that no pest or moisture can
enter.
8. The Contractor shall coordinate with Interfacing Contractors regarding the provision of cable routes
and installation, including methods of mounting the cable containment systems to the civil
infrastructure.
The cable list shall include but shall not be limited to the following information for each individual
cable:
POW-4-77
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
v) Cable size;
viii) Connection point at each end with equipment identification and terminal numbers;
x) Bending radius.
2. The Contractor’s drawing submittals shall include but shall not be limited to the following:
• Cable route and cabling method between mainline and substation/electrical supply rooms.
ii) Diagrammatic plans for cable route in tunnels, ducts, trenches and Depot.
• All drawings shall include legend for all symbols used in the drawing.
The equipment shall be controlled and monitored comprising traction substations (TSS), electric rooms such
station substation (SSS) and (HER).
At the OCC Central workstations are to be provided giving an effective means of display and control.
1. At the OCC three (3) displays showing various equipment states is to be provided.
2. The central computer server shall maintain an historical database of all messages transmitted over the
Power SCADA links and the Contractor shall provide a means of accessing that database.
Necessary RTU shall be installed to provide the most economic configuration based upon cost balances
between RTU modularity and cabling costs, consistent with the performance requirements of this
Specification.
Communications between the equipment in the traction substations, station substations to the OCC
central database shall be over a duplicated communications network dedicated to Power SCADA, which
shall be provided by the Contractor.
POW-4-78
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
In the event of a communications failure between a station and the central database, the station traction
power SCADA equipment shall continue to function as an autonomous system, maintaining a local
database and all Power SCADA facilities.
The Power SCADA system shall incorporate, but shall not be limited to, the following primary facilities:
2. Alert operations and maintenance staff rapidly to equipment malfunctions, especially those likely to
cause disruption to operation of the railway;
3. Provide clear, comprehensive displays and printed logs of equipment status to each operator
workstation;
4. Provide comprehensive displays and printed logs based upon historical data, with the option of
overlaying data from earlier periods;
5. Time-tag all events detected by the Power SCADA system, to 20 milliseconds resolution for selected
highspeed inputs, and to present this information in logs as a true system-wide sequence of events;
7. Provide automatic and manual control of receiving, traction and auxiliary power equipment;
8. Generate routine maintenance schedules automatically, based upon elapsed time and equipment
operation times;
10. Provide displays for supervising of ITVs installed in BSS, TSS and SSS for the sight overview.
The system shall be designed to achieve at least the highest levels of system availability for the following:
POW-4-79
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
ii. The availability figures for Traction Power functionality and the Traction power decision
support facilities;
iii. The availability figures for other Power SCADA subsystems viz. Software Development and
Training Simulator;
iv. Any equipment manufactured by the Contractor shall have its failure rate determined strictly in
accordance with its appropriate operating environment; and
b) Redundant Design
i. Redundancy shall be incorporated in the design to cater for failures that will have impacts on
safety and normal operation of the MMSP operation. However, redundancy shall be
incorporated where failure cannot be tolerated even for short periods.
ii. The system shall therefore be designed around small autonomous items of equipment but shall
be commensurate with an economical overall solution.
iii. Failure of any node on the network shall not affect the local operation nor prevent
communication between any other connected equipment nodes.
c) Electrical Noise
i. All Power SCADA system equipment shall operate in accordance with the design criteria in the
very high “electrical noise” environment normally associated with electrified railway systems
due to electrical fields created by traction supplies and strong magnetic fields.
ii. Equipment shall be immune to the effects of conducted and radiated electrical interference.
d) Time to Repair
The Power SCADA system shall have an MTTR less than 30 minutes.
This time shall not include the time taken for a technician to arrive at the initial reported failure site.
e) Lightning Protection
i. The Contractor shall ensure that all equipment are fully protected against the effects of mains
surges and direct and indirect lightning strikes. Protection shall be applied to incoming mains
power supplies and to input and output signal lines to externally located sensors, transducers,
actuating equipment, etc. or to any other equipment likely to be affected.
iii. The suppression equipment shall be so selected that the let through voltage specification does
not exceed the absolute maximum voltage specified for the particular equipment being
protected.
POW-4-80
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
iv. Signal lines from external sensors at risk from the effects of lightning shall have surge
suppressers fitted at both ends of each line and shall be installed and connected in accordance
with the manufacturer’s recommendations.
1. Continuous, effective monitoring and/or control of selected equipment over the entire MMSP Line;
2. Expeditious alerting of operations and maintenance personnel, by means of corresponding audible and
visual alarms, of any identified equipment malfunction, especially those likely to cause disruption to
the operation of the MMSP Line;
3. Clear, comprehensive displays and printed records of selected equipment status at each workstation;
4. Comprehensive displays and printed records based upon historical data, with the option of overlaying
data from earlier periods;
5. Records of energy demand and consumption and other data at MERALCO incoming feeders, each
station, traction and depot service substation for checking MERALCO bills, for trend analysis and cost
budgeting purposes;
6. Time-tagging of all events detected by the Power SCADA system, to a highspeed resolution for selected
highspeed inputs, and presentation of this information in records as a true sequence of events;
7. Monitoring of selected equipment running times and provision of comprehensive records of the overall
operating costs and energy efficiency;
8. Facilities for manual control of selected equipment, the Contractor shall provide detail of such facilities
for review by the Employer;
9. Facilities for recommending re-configuration of the operation of selected equipment in the event of a
failure or alarm occurring, to enable rapid action by the controller;
10. Automatic generation of maintenance requests which are based upon selected equipment running times;
and
11. Centralized data storage and software back-up facilities for the complete Power SCADA system.
2. The same requirement shall also apply to the main breakers of the main LV switchboards in each
electric room.
3. Power SCADA monitoring facilities for power supplies shall include, but shall not limited to:
• Voltage of all 115kV, 34.5 kV, 400V AC and 1500V DC bus bars;
• Current of all 115kV, 34.5kV AC receiving, 400V AC transformer secondary, and 1500 VDC
negative line;
POW-4-81
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
• Rectifier current;
2. A central recording system shall be provided to record the following events, including but shall not
limited to:
v) Faults;
3. Events shall be given an order of priority to allow events to be classified, sorted and filtered. Subject to
the requirements of the operations plan reviewed without objection by the Engineer or his
representative, events shall be classified as:
i) Emergency – This type of fault shall require instant attention in order to minimize interruption
of the normal operation of the MMSP Line or risk of injury to personnel or passengers and shall
be classified as an alarm;
ii) Urgent – This type of fault shall require reasonably prompt, but not instant attention in order to
minimize interruption of the normal operation of the MMSP Line and shall be classified as an
alarm;
iii) Non-urgent – This type of fault shall be dealt with in a more convenient manner while more
urgent events are dealt with first. This type of event shall not directly result in any degradation
of the normal operation of the MMSP Line and shall be classified as an alarm only.
4. The event records shall be available as a text table, with each event classified by its priority level and
shall be tagged with details of the date and time at which the event occurred. Additionally, the operations
personnel identification code shall be recorded for each event that is initiated by the operations
POW-4-82
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
personnel. Each event shall be displayed and highlighted until acknowledged by the operations
personnel.
5. All events shall continue to be displayed until the event has been acknowledged and cancelled in the
automatic event log and provided the fault has been satisfactorily rectified in the equipment which
generated the event.
4.10.8 Alarms
Audible alarms shall be provided to alert the operations personnel to a problem requiring immediate action or
attention. The audible alarms shall be clearly audible against ambient noise level.
There shall be three categories of audible alarms easily distinguishable by separate tones or sounds for events
classified as emergency, urgent and nonurgent.
All alarm appearance events shall generate a record in the alarm list. This record shall be recorded in event list.
Alarm disappearance events, which generate an alarm procedure, shall also generate a record in the event list.
This record shall only be erased by the System Administrator after a predefined period (minimum one year) or
number of events (minimum 2,000,000 events) whichever is more.
1. The display of each Safety Critical system shall require rapid updates of the workstation displays of the
status and event data, together with a rapid response by the Power SCADA system to control inputs.
The status of any circuit breaker trip, protecting any Safety Critical equipment, shall also be identified
on the workstations and recorded in the event record, within 2 seconds of its occurrence.
2. Updating of displays shall ensure that no displayed data shall be more than 30 seconds.
No event shall take longer to be registered on a display than 5 seconds for urgent alarms and 3 seconds
for emergency alarms. The display of non-urgent events shall take no more than 10 seconds after the
occurrence.
3. Housekeeping” commands such as changes of the display format or colour scheme philosophy shall be
executed by the Power SCADA system within 5 seconds of the completion of the input procedure.
4. The normal operation of all the remote terminal units (RTUs) shall be verified by the Power SCADA
system at intervals not exceeding 30 seconds. In the event of any failure or malfunction of a remote
terminal unit, a corresponding massage shall be displayed on the appropriate workstations as a Power
SCADA system alarm.
5. The Safety Critical systems for this Power SCADA shall include, but shall not be limited
to the following:
• Monitoring system.
POW-4-83
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
4.10.10 Noise
All Power SCADA system equipment shall operate in accordance with the design criteria in the very high
“electrical noise” environment normally associated with MMSP systems due to electrical fields and magnetic
fields created by traction supplies Equipment shall be immune to the effects of conducted and radiated electrical
interference.
1. All SCADA equipment shall be fully protected against the effects of power supply surges and transients.
2. Equipment shall be immune to the effects of conducted and radiated electrical and magnetic
interference.
3. The SCADA equipment shall be fully protected against the effects due to lightning strikes in accordance
with the requirements of BS 6651 - "Lightning Protection" or an equivalent internationally recognized
standard.
4. All surge suppression equipment shall be self-contained and self-resetting. The suppression equipment
shall be selected to ensure that the let-through voltage does not exceed the absolute maximum voltage
specified for the particular equipment being protected.
5. Signal cables from external sensors at risk from the effects of lightning shall have surge suppressor
fitted at both ends of each cable and shall be installed and connected in accordance with the
manufacturer's recommendations.
6. The SCADA system shall have 20% spare capacity (to be confirmed). In addition, the system shall have
20% expandability to incorporate additional functions and facilities, such as additional input/output
points, data storage, etc. that may be required for future expansion.
7. Communication: Communication backbone shall be provided by Telecom and however Contractor shall
provide FO cable between the RTU/PLC/Gateway & Telecom Equipment Room. Server shall
communicate with RTU/PLCs & RSS gateway on IEC 60870-5-104 communication protocol.
i) Digital input:
ⅲ) Pulse input:
ⅳ) Digital output:
ⅴ) Analogue output:
POW-4-84
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
0-10 V, 4-20 mA DC
ⅵ) Serial link:
RS232C, RS442
ⅶ) Ethernet:
b) Optical fibre network shall be provided for not only Power SCADA but also other sub packages
(telecommunication and signalling etc.).
Interface between Power SCADA and optical fibre network shall be Optical Distribution frame (ODF)
including Telecommunications System. The optical fibre cables between ODF and Power SCADA shall
be provided by the Contractor. The Contractor shall liaise with and coordinate his Works with
Interfacing Parties to ensure the Works fully comply with the design criteria and with the program
constraints of this and interfacing contracts.
2. The backup operation facility has a function that can be used as a training facility for power supply and
distribution system operation using a sequence simulator by off-line system. As PRI has training
facilities. The contractor must consult with the customer whether to use this feature.
2. The power supply for Power SCADA shall be supplied through UPS. UPS shall be capable of providing
the specified performance continuously for a minimum period of four hours.
3. Power supply to RTUs shall be supplied from 110V battery system of control source for substations.
P-SCADA will have redundant system and shall have enough reliability and functions. To realize easy extension
in the future, available distance for controlling is 30 km or more, and extension of controlled posts of further 20
or more shall be possible.
The power supply system and the distribution system shall normally be controlled remotely from the SCADA
system and monitored at the SCADA system located in the OCC. TCP/IP should be selected as communication
protocol. The P-SCADA System in OCC should have back-up power source by UPS.
A study shall be carried out to ensure of the adequacy of the SCADA system hardware and software for
guaranteed performance under the most onerous conditions shall be undertaken.
The scope of supply for the P-SCADA system includes but is not limited to the following:
POW-4-85
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
1. Traction & Auxiliary SCADA systems including Video wall & UPS, RTUs/PLCs at SSSs & TSS to
control and Monitor all Power equipment of the Power Supply System, including main low voltage
panels receiving the supply of station transformers.
2. Central control facilities (Servers, workstations, LAN equipment’s UPS of appropriate capacity etc.) at
the Operational Control Centre (OCC) Depot. Including Video Display Wall & Training Simulator.
3. SCADA equipment at BSS, Station should be integrated with the communication equipment at nearest
Tele-equipment room stations and OCC.
4. For protection, interlock and metering of the equipment, protection control unit (PCU) i.e. Digital
Protection Control System (DPCS) shall be installed on all switchgear panels. It shall be able to operate
the vital components and work as the interface with the remote SCADA system.
5. Communication between OCC SCADA and the RTUs/Gateways at the power installation ends viz,
TSSs, SSSs, BSSs and other location, if any, shall be achieved through the transmission network.
6. It shall be possible to monitor and log the various voltages, currents, power factor, maximum demand,
power consumption and status of various equipment and provide automated control throughout the
system at the OCC through the SCADA system.
7. The SCADA shall also have provision for plugging in a portable control console (laptop) with the RTU.
It shall be possible to operate and monitor the status and alarm conditions of all equipment from this
local control console.
8. An Emergency Trip System (ETS) shall be provided at each end of the station platforms, Station control
rooms, TSS and in Depot. Traction Supply power-off, in case of emergency, shall be achieved through
ETS. The status of ETS will be displayed in SCADA. The resetting of ETS shall also be possible from
OCC however; the level of authorization required shall be a step higher than that of operator. Traction
power Supply to elementary section will be tripped directly through ETS.
9. The Contractor shall define the philosophy and furnish a scheme of protection with fast discrimination
and reliable operation based on latest state-of-the-art computerized logic protection scheme. The zones
of protection shall overlap providing second and third tier back-up protections.
10. The Contractor shall submit to the Engineer for review detailed fault calculations, relay settings and
fault co-ordination curves showing proper protection, discrimination between all upstream and
downstream equipment. Pilot wire relaying and inter tripping, shall be provided as per scheme.
11. Anti-Virus Wall: The servers and networks provided for the complete SCADA system shall be
completely secured from any malware infections and virus. The security provided for the network shall
have high availability, intrusion prevention.
12. Laptops computers based on the latest generation hardware and licensed software shall be provided
with all programme utilities required for testing, commissioning, simulating, programming and
parameterization of protection and control system.
4.10.15 Power SCADA (P SCADA) Distribution and Operation Control Centre (OCC)
This Specification describes the technical and performance requirements of the Supervisory Control and Data
Acquisition (SCADA) system for monitoring and controlling the Traction and auxiliary power equipment
located in BSSs, TSS, ESS and SSS in the Main Line and Depot Power Supply system and the OCS for the
Manila Metro Subway. In addition, the SCADA system shall monitor Emergency Trip System (ETS), Stray
current detection monitoring system. Contractor shall provide a SCADA system which shall be capable of
monitoring & Controlling the Traction & Station power equipment located in the BSS (in conjunction with the
POW-4-86
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
interface with 61850 environments as discussed above), the TSS & SSS (in conjunction with the RTU/PLC with
distribution type SCADA concept) in the Main Line & Depot. As a minimum the following functional features
are required:
1. The supervision, Control and data acquisition of BSS shall be through the Substation Automation
System (SAS) using the 61850 IEDs. The IEDs shall be using the 61850 platform for the protection as
well as for Substation automation. The control and monitoring in the rest of the system i.e. BSS, TSS
& ASS shall be on RTU/PLC (which shall be installed in the non-air-conditioned environment) based
distribution SCADA; However, it shall also be possible to control the equipment using the interface
screen of Relay.
2. All materials and equipment to be provided for the Power SCADA shall be of proven design and shall
be provided by a manufacturer who has successfully accomplished supervisory control and data
acquisition system projects.
3. One OCC to be provided (and BCC as an OPTION for future to be confirmed). Central workstations
shall be provided giving an effective means of display and control. Simultaneous control operations
from the OCC and BCC shall not be allowed. Main Control shall be available at OCC. It shall be
transferred automatically to BCC in case of OCC communication Failure or Both Servers failure. Else,
BCC controller shall request OCC controller to transfer control. On BCC controller’s request, OCC
controller can transfer control to BCC & vice-versa but with an authorization In Emergency BCC
controller can forcefully take over control & vice-versa. It shall generate an audio Alarm at OCC as
well as at BCC. Each transfer shall be a recorded event with time stamping.
4. At the OCC, mimic displays showing various equipment status is to be provided. Monitoring of selected
equipment running times and provision of comprehensive records of the overall operating costs and
energy efficiency shall be available.
5. The central computer server shall maintain an historical database of all messages transmitted over the
Power SCADA links and the Contractor shall provide a means of accessing that database.
6. The tripping of critical feeders which hampers the system operations shall be communicated to the
designated mobile numbers through SMS. The arrangement shall also permit the SMS of the cumulative
energy every morning. This system shall be provided by the Contractor however the monthly charges
for the mobile service provider shall be borne by the Employer after DNP.
7. Necessary RTU/PLC shall be installed throughout the network for process bus related to BSS, SSS,
TSS & OCS for Main Line and Depot. At TSS & SSS locations, a separate RTU each for traction and
auxiliary shall be provided. The RTU/PLC shall be fully tropicalized to withstand the temperature,
humidity and dust conditions. The housing shall be made of non-corrosive material with high immunity
against electrical disturbances.
8. Communications between the equipment in the Bulk Supply Substation, traction Substations, and
Station Substation shall be over a communications network dedicated to Power SCADA.
9. Provide clear, comprehensive displays and printed logs of equipment status, based upon historical data,
with the option of overlaying data from earlier periods; to each operator workstation.
10. Time-tag all events detected by the Power SCADA system, to 20 milliseconds resolution for selected
highspeed inputs, and to present this information in logs as a true system-wide sequence of events.
11. Provide automatic and manual control of BSS, traction and station power equipment.
POW-4-87
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
13. Continuous, effective monitoring and/or control of selected equipment over the entire MMSP Line.
14. Expeditious alerting of operations and maintenance personnel, by mean of corresponding audible and
visual alarms, of any identified equipment malfunction, especially those likely to cause disruption to
the operation of the MMSP Line;
17. Records of energy demand and consumption and other data for 115kV infeed voltage & 34.5kV
incoming feeders, at each BSS, TSS & ASS Substation for checking bills, for trend analysis and cost
budgeting purposes; The energy meter installed in the system shall communicate to the system for this.
18. Implement necessary interlock logics to prevent inadvertent wrong operations. All hard-wired
interlocks as per interlocking scheme for safety shall also be provided in soft. The operator shall get
indication while selecting the equipment for operation about the interlock / blocked. The interlocks,
which are not possible through hard wiring, shall also be identified and provided in soft.
19. Define subroutines for quick isolation of faulty equipment & restoration of power supply.
20. Facilities for recommending re-configuration of the operation of selected equipment in the event of a
failure or alarm occurring, to enable rapid action by the controller.
21. Control and Monitoring Items of Power Supply System shall be as following but not limited to:
a) The Power SCADA system shall control and monitor the HV, DC and LV power supplies,
which shall include indications of the status of all electrically operated switching devices on the
infeed 115kV AC, 34.5kV AC, and 1500V DC systems, and protective devices together with
alarm.
b) The same requirement shall also apply to the main breakers and tie breakers of the main LV
switchboards in each electric room.
c) Power SCADA monitoring facilities for power supplies shall include, but shall not limited to
Voltage of all infeed 115kV, 34.5kV, 400V AC and 1500V DC busbars; Voltage of all 110 V
DC Battery banks; Current of all infeed 115kV, 34.5 kV, 400V AC and 1500V DC busbars;
Status of circuit breakers and disconnecting switches; Rectifier current; Status of all protection
equipment; Status including voltage thresholds of OCS and their various elementary sections
using colouring schemes; Operation of alarm and tripping of protection devices.
d) A central recording system shall be provided to record the following events, including but shall
not limited to:
v. Faults;
POW-4-88
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
e) Events shall be given an order of priority to allow events to be classified, sorted and filtered.
Subject to the requirements of the operations plan reviewed without objection, events shall be
classified as:
• Emergency – This type of fault shall require instant attention in order to minimize
interruption of the normal operation of the MMSP Line or risk of injury to personnel or
passengers and shall be classified as an Emergency alarm;
• Urgent – This type of fault shall require reasonably prompt, but not instant attention in
order to minimize interruption of the normal operation of the MMSP Line and shall be
classified as an urgent alarm;
• Non-urgent – This type of fault shall be dealt with in a more convenient manner while
more urgent events are dealt with first. This type of event shall not directly result in any
degradation of the normal operation of the MMSP Line and shall be classified as a non-
urgent alarm only.
The event records shall be available as a text table, with each event classified by its priority level and
shall be tagged with details of the date and time at which the event occurred. Additionally, the operations
personnel identification code shall be recorded for each event that is initiated by the operations
personnel. Each event shall be displayed and highlighted until acknowledged by the operations
personnel. All events shall continue to be displayed until the event has been acknowledged and
cancelled in the automatic event log and provided the fault has been satisfactorily rectified in the
equipment which generated the event.
The SCADA system shall comprise, but not limited to the followings:
POW-4-89
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall also detail the designs include but not limited to the following:
1. Design Stage
d) The relevant international standard proposed to be used shall be submitted for review of
Employer;
e) Load low study, fault level calculations and short-circuit current curves; and MERALCO
Distribution Impact Study;
f) Harmonic study;
POW-4-90
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
l) Detailed Earthing & Bonding design, earthing and touch potential calculations;
m) Stray current mitigation measures and implementation interface and stray current monitoring
system design;
n) Input output list for digital input, output and analogue signals for SCADA;
t) Detailed SCADA design including the RAM, CPU design. The document must substantiate
about how the SCADA system shall manage breakdowns and future metro extensions.
v) Others.
2. Construction Stage
b) Factory Acceptance Test Plan for equipment, components and its integration;
c) Quality Plans;
k) Electrical isolation drawings for station structures and outside structures like ROB/FOB &
others.
POW-4-91
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
g) Other documents and drawings required by Engineer to substantiate that the design has been
carried as per the international practice and as per the RAMS criteria.
All drawings, etc. shall be submitted to the Engineer for review. These shall include but not be limited to:
4. Return current, stray current management and Earthing & Bonding plan: Return current circuit Earthing
& bonding plan, EMC/EMI and stray current management plan in interface with Track, Signalling and
other systems and Rolling Stock shall be submitted; and
5. Location of SCDs, METs on track side, location of earthing of L.A.s and designated earthing points.
INSTALLATION REQUIREMENTS
4.12.1 General
The Contractor shall comply with all Enactments in executing the Works, at least including all statutory
provisions on occupational health and safety.
The Contractor shall coordinate with the Interfacing Parties of this Contract and other contractors in the
execution of the works.
The Contractor shall also cooperate with all Relevant Authorities in the execution of the Works.
The installation of all equipment shall be undertaken at all times by suitably trained and competent employees
of the Contractor, to the satisfaction of the Engineer.
Installation of all equipment shall be in accordance with the coordinated installation plan described in the
General Requirements (ERG).
Precautions shall be undertaken to ensure the safety of personnel and equipment for all installation works.
The Contractor shall, prior to starting any installation work, identify any possible hazards and implement
measures of eliminating and/or controlling such potential hazards, in line with safe working practices.
POW-4-92
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Further details on the Site safety assurance management plan are described in the General Requirements (ERG).
The Contractor shall coordinate with the relating Contracts regarding the provision of cable routes and
installation, including methods of mounting the cable containment systems to the civil infrastructure.
The Contractor shall coordinate its requirements for grounding and bonding system with interfacing contractors,
such as wiring routes and locations of ground rods installation.
The Contractor shall ensure that all areas of work are sufficiently illuminated for the Works to be undertaken
and that a safe system of work is employed for all activities.
The Contractor shall operate a robust system for the control of persons entering or working upon the Site. The
system shall include as a minimum:
• Levels of competency;
• Date of expiry;
• Date of issue;
• Signature; and
The Contractor shall cooperate, at all times, with the Engineer and other contractors to ensure that the Site is
protected from unauthorized admission, either will fully or otherwise.
The Contractor shall make do provision for the safe access and egress to the Site of Works for its staff and
subcontractors. This access shall be maintained such that it is free of all hazards and is in a safe condition
throughout the duration of the Works.
POW-4-93
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
As a minimum, the detailed Construction and Installation Plan shall at least include all the activities include but
not limited to, installation details and methods of all activities equipment and tools to be used for installation,
safety issues, supervision, temporary land occupation needed and the vehicles to be used for installation.
All Temporary Works shall be removed on completion of the Section, or as directed by the Engineer. All
Temporary Works shall be clearly distinguishable from the Permanent Works.
2. The Contractor shall provide sufficient number of suitably experienced supervisors and skilled workers
to ensure that the progress and quality of the work, both on the Site and in the Contractor’s workshops,
are maintained to the satisfaction of the Engineer.
3. Supervisors shall have a minimum of five years’ previous experience in a supervisory capacity on
similar projects and all the skilled workers including linesmen, electricians, fitters and craftsmen, shall
have a minimum of two years’ previous experience in installation of similar systems.
4. The Contractor’s supervision system shall be responsible not only for the supervision of the Concerned
system installation but also for the supervision of the installation of the primary fixing system (civil
inserts), the ground mats and systems, etc. that are to be installed by the Contractors. The supervisors
shall work on a full-time basis during the entire installation process.
5. The Contractor shall maintain a set of drawings at each project Site which accurately reflect the current
status of field changes. The Contractor shall obtain letter of no objection from the Engineer for any such
changes. The Contractor shall prepare final drawings showing the as built configuration.
These drawings shall be developed in a logical format to facilitate routine system maintenance and
troubleshooting. All drawings and details shall be endorsed by the Contractor.
6. The Engineer reserves the right to undertake, at any time, checks on the proficiency of the Contractor’s
staff, licensing and all associated documentation. Should any of the Contractor’s staff be found
incompetent or unlicensed he shall be removed from the site until their competency has been
established.
INTERFACE REQUIREMENTS
The Contractor shall refer to ERG Appendix VI for all interface requirements.
Contractor also liaise and coordinate with the following Interfacing Parties to ensure the effective and
compatible coordination of all aspects of design, installation, testing and commissioning of work.
POW-4-94
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. Bulk Supply Substations (BSSs): Automation Substation System, protection, metering etc.;
3. Each 1500V DC feeder. Interface with conductor terminal of DC switchgear installed in TSSs and
Interface with conductor terminal of negative disconnect switchgear installed in TSSs;
4. Location of double IRJ at Depot and dead zone at interface of Main Line and Depot;
9. Connection between rail and return circuit and bonding cables etc.;
10. Civils / Structures: All substations, equipment layouts and cable management system;
14. Harmonics and EMC with all systems including study and testing with approved plan;
17. Stop the train from entering the dead section following the ETS tripping.
1. All permissions and approvals including payment of fees/ restoration charges/penalties/ demurrages;
2. Interface with road agencies for survey works for laying of cables from Local Utility Provider
Substation (MERALCO) to MMSP Substation;
3. Obtaining all permission from road agency and other agencies for digging along road/pavements as
necessary.
5. Interface with Telecom Authorities, Gas Distribution Authorities, power supply, water Authorities and
other agencies to ensure that functioning of the utilities is not jeopardized by the actions of the
Contractor;
7. Interface including all documentation, coordination and necessary tests for obtaining statuary approval
POW-4-95
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
8. Interface, including all documentation, coordination and necessary tests, for obtaining statutory
approval and sanction of Commissioner Metro Rail Safety or equivalent authority to the Government
for opening the system for public carriage of passengers.
Contractor shall also refer to interface matrix for all interfaces required.
The Contractor shall review the interface design and coordinate with other contractors and third parties as per
interface management specified in General Specification (GS). However, detailed interface design within the
CP106 package is the responsibility of the Contractor.
2. Other items not mentioned in the interface items but are relevant to the design, installation, testing and
commissioning of permanent works, shall also be included in the interface management plan.
1. Pre-commissioning tests;
2. Commissioning tests;
4. Test Certificates.
Specific requirements for the Electrification System (Power Supply, Catenary & Energy Storage System) are
given below:
The Contractor shall conduct the tests in accordance with the reviewed test procedures and shall enter the results
in the result sheets. Full use shall be made during the tests of operator manuals and other documentation
provided by the Contractor, to provide a series of tests of their accuracy. If during Type Tests, any failure occurs
POW-4-96
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
or the equipment design is changed, it shall be reported to the Engineer who may, at his discretion, require
repetition of the previous tests.
Type tests may not be required in those cases where the Contractor can produce certified evidence that the
required type tests have been performed successfully on identical equipment and produced in the factory where
the equipment to be supplied under the contract is to be manufactured, provided the type test(s) have been
carried out and witnessed by reputed test agencies at certified labs and are not older than 5 years from actual
date of supply of equipment. The final decision regarding applicability and acceptance of the type test certificate
produced shall rest with Engineer.
The following tests shall be carried out on the equipment in addition to the tests as per the relevant international
standards and the quality control and assurance requirements of the Contractor.
General Tests:
Insulation Resistance;
Conductivity Test;
Earth Resistance;
Insulation Resistance;
Routine Tests.
All principal test records and test certificates duly endorsed by the Contractor’s professional engineer are to be
submitted for review by Engineer. These test records and certificates shall be supplied for all tests, whether or
not the Engineer has witnessed them. The information given on such test certificates shall be sufficient to
identify the materials or equipment to which the certificate refers.
FAT shall comprise Type Tests, Sample Tests, Routine Tests, Life, Endurance and Destruction Tests, and any
additional tests requested by the Engineer.
a) The testing shall be conducted such as to simulate the working conditions as closely as possible.
b) Upon the request of the Engineer, destruction tests shall be carried on components and assemblies to
verify the design loading.
c) All the tests shall be conducted both on the assembly and on the members/components of each product
in accordance with design specifications and applicable Standards.
POW-4-97
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
On completion of erection and prior to commissioning, all installed equipment shall be tested to the acceptance
of the Engineer in accordance with an agreed Inspection and test plan to demonstrate that it is entirely suitable
for commercial operation.
The Contractor shall be responsible for providing temporary electricity supply, all instruments, gauges, test
equipment, tools, accessories, personnel, services and necessary facilities required for the execution of all tests
and inspection. Wherever necessary, the Contractor shall provide two or more sets of testing equipment, tools,
and others to expedite testing. All test equipment shall be accompanied with the appropriate calibration
certificate by a testing authority of the equipment.
Test equipment, tools, and others necessary for subsequent preventive and corrective maintenance are to be
provided to the Engineer as specified herein and shall be available to assist the tests. The use of these test
equipment, tools and others shall be reviewed by the Engineer.
The Contractor shall be responsible for surveillance and security of his own scope of equipment and distribution
downstream cables or other electrical equipment is energized before it has been tested and before the relevant
contractors or sub-contractor’s facilities are ready and secured. The Contractor’s responsibility for surveillance
and security of the system shall remain in force for each part of the system until such a time that the Engineer
issues the appropriate certificate and the Employer takes over the System.
The Contractor shall submit to the Engineer for review not less than six (6) months before commissioning
activities commence his proposed format for the commissioning records. The records shall be appropriately
sub-divided to make provision for the various parts of the Permanent Works covered by the Contract.
The format of the records shall cover all mechanical and electrical tests, provide positive identification by serial
number for assemblies and sub-assemblies of the Permanent Works and show modifications to Engineer's
Drawings and diagrams or "as built" data to be certified by the Employer or the Engineer in the course of
installation, testing and setting of the Works. The Contractor shall, during the execution of the Works, prepare
such reports and records of manufacture, installation and testing as may be required in order that a license may
be issued, or statutory requirements may be met, or approval given. Such reports or records shall be adequate
to enable each part of the Permanent Works to be commissioned and to meet the requirements of the licensing
authority or any standing statutory regulations, and shall be reviewed by the Employer and the Engineer The
Contractor shall obtain reports of each inspection and/or test. Such reports shall show the results of all the
inspections and/or tests carried out and shall certify that the work has been inspected and/or tested in accordance
with the requirements of the Contract and that the work complies with the requirements of the Contract.
Any analysis of the results required to confirm that the work complies with the requirements of the Contract
shall be compiled and reported to the Engineer. A representative of the Contractor who has been allocated the
required authority under the relevant quality plans shall sign each report of inspection and/or test.
1. Power Transformer: Power frequency withstand (at 75% specified value), on load tap changer
functioning, painting & external visual inspection, Core Insulation resistance, insulation oil breakdown
strength, Auxiliary circuits insulation, Auxiliary circuits operation, Instrumentation & relays
calibration, Cooling system.
2. High Voltage Circuit Breakers: Wiring, Function, Interlocking, Painting & external visual inspection,
Exchangeability of similar devices, Auxiliary circuits insulation etc.
3. High Voltage Isolators: Wiring, Function, Interlocking, Painting & external visual inspection, Auxiliary
circuits insulation etc.
POW-4-98
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
6. HSCB & DC isolators: wiring, Function, Interlocking, Mechanical operations at rated, max. & min
voltage, Interlocking, Visual inspection etc.
7. All control and protection functions and electrical/mechanical interlocks shall be tested.
8. Primary Injection Tests: Tests on each protective system, to prove the auxiliary circuit connections, the
relay fault setting values, the correct metering indications and the stability limits.
9. AC/DC Pressure Tests: Insulation resistance of all circuits, equipment, cables and OCS system.
10. Platform resistance test during laying and after laying of membrane.
1. An inspection and visual verification of ratings and connections with equipment shall be carried out
prior to installation tests.
2. Un-energized equipment shall be inspected for its visual and tested for operation after installation of
equipment. Inspections and tests shall include the following:
a) Cleanliness;
b) Workmanship;
j) Functioning of circuit breakers, load break switches, isolating switches and their interlocks;
k) Protection devices;
m) Ground resistance shall be measured individually, and for the subsystem and system;
n) Insulation Resistance;
i) Insulation resistance;
POW-4-99
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
v) Burden
i) Insulation Resistance;
iv) Ratio
Tests shall be carried out at a minimum of three settings if multiple settings are available. Test results
of operation boundaries and operating times shall be recorded.
Discharge tests and charging tests shall be carried out to verify the capacity of the batteries and all
functions available on the charger.
Continuous measurements of battery voltages shall be made together with periodic readings of the
electrolyte specific gravities and temperatures. No addition of electrolyte is permitted during discharge
tests.
The operation of the boost charge facility and the effect of the voltage dropping diodes shall also be
demonstrated.
Insulation resistance and continuity of all cores of cables shall be identified and tested, and the correct
functioning of all control, indication and alarm devices shall be verified.
7. Switchgear
All switchgear, including circuit breakers, load break switches and earthing switches shall be operated
to prove that the operating gear, tripping devices, protective gear and mechanical interlocking are
satisfactory. SF6 gas leakage test shall be performed where applicable.
Power Transformers
Voltage ratio at all taps, functioning of tap changers and insulation measurements shall be performed.
Simulation tests shall be carried out to determine correct operation of Buchholz gas alarm and gas surge
relays.
POW-4-100
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
All current and voltage transformers, metering instruments and transducers shall be calibrated by
voltage and current injection to prove their accuracy classes.
Primary and Secondary Injection Tests: Tests shall be carried out at a minimum of three settings if
multiple settings are available. Test results of operation boundaries and operating times shall be
recorded.
Batteries and Chargers: Discharge tests and charging tests shall be carried out to verify the capacity of
the batteries and all functions available of the charger. Continuous measurements of battery voltages
shall be made together with periodic readings of the electrolyte specific gravities and temperatures. No
addition of electrolyte is permitted during discharge tests. The operation of the boost charge facility and
the effect of the voltage dropping diodes shall also be demonstrated.
Control, Indication and Alarm Functions: Insulation resistance and continuity of all cores of cables shall
be identified and tested. The correct functioning of all control, indication and alarm devices shall be
verified.
All control and protection functions and electrical/mechanical interlocks shall be tested.
The Contractor shall carry out primary injection tests on each protective system, to prove the auxiliary
circuit connections, the relay fault setting values, the correct metering indications and the stability
limits.
The insulation resistance of all circuits shall be measured before and after the DC pressure test using a
5kV insulation tester. The minimum phase-to-phase and phase-to-ground insulation resistance shall be
100 mega ohms.
Pressure tests shall be carried out on completed cable lengths of high voltage cables in accordance with
JIS C 3005, JEC 3408-2008, JEC 3411-2008 and IEC 60502.
1. Energization:
The Contractor shall prepare operation safety rules and procedures for the review by the Engineer before
energization. The Contractor shall check all to ensure safe energization.
POW-4-101
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. All power equipment shall be subject to inspection by inspectors from the Electrical Inspectorate of the
Employer before energization. The Contractor shall ensure all the Employer’s Requirements are met
and satisfied.
3. The Contractor shall be responsible for the operation of traction and auxiliary power equipment. Upon
request by the Engineer, the Contractor shall be responsible for the disconnection and the subsequent
reconnections of the power equipment.
Energization as per safety rules and procedures prepared by Contractor in accordance with the local and
international standards shall be done by the Contractor. This may also involve the preclearance from
electrical inspector or any other statutory body before charging. This clearance shall be the
responsibility of the Contractor. The Contractor shall ensure that all requirements from the Electrical
Inspector are met.
2. Power Supply tests including but not limited to control & monitoring tests from local as well as remote;
These tests shall be entirely within the requirements of one or more of the project contracts or they shall
involve a multiplicity of contract procedure.
The final Integrated Testing and Commissioning shall be conducted after the SCADA system and OCC
have become operational.
2. Systems that can be tested without depending on the running of trains, such as SCADA system, the
emergency trip system shall have their integration tests scheduled to commence as early as possible. It
is preferable that any interface problems associated with these “no train” system tests be identified and
resolved prior to the test running.
3. The following is an indicative listing of those Integrated Testing and Commissioning functions that
necessarily to be integrated with others to demonstrate that the equipment and controls of the Power
Distribution System meet the Contract Specifications and demonstrate a safe-to-operate condition. This
listing is not exhaustive and shall be updated by the appropriate contractor, to demonstrate functionality,
completeness and safety of the installed works and shall be submitted to the Engineer for his review.
a) SSS, HER, Distribution board space and Generator failure mode test;
e) EMI/EMC tests;
POW-4-102
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall provide attendance to the Engineer during integrated test in relation to the
insulation of train station platforms provided by the other contractors.
Once sufficient load current is established, voltages and currents into protection and metering
equipment shall be verified to ensure correct operation of protection relays and accuracy of meter
readings at local and remote locations.
2. One of the Performance Tests which shall be conducted by the Contractor in conjunction with relevant
Contractors, sub-contractors and other parties is the measurement of EMI levels at locations that have
received a Statement of approval by the Employer.
Such measurements shall be conducted prior to Energization of the Traction Power System, and then
during Service Trials and commercial operation of the train services to ensure that the EMI levels meet
the Employer’s Requirements and are in accordance with the Contractor’s designs reviewed by the
Engineer.
3. Should the performance of the System deviate from the Contractor’s design the Contractor
4. The Contractor shall submit a certified report of the results of these Tests to the Engineer within 14
days from the date when the Engineer confirmed that the Contractor has completed each of the Tests.
4. Bulk Supply Substations, traction Substations and Station Substation failure mode test;
POW-4-103
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
9. EMI/EMC tests;
11. The Contractor shall provide attendance to the Engineer during integrated test in relation to the
insulation of train station platforms provided by the other Contractors;
13. Once sufficient load current is established, voltages and currents into protection and metering
equipment shall be verified to ensure correct operation of protection relays and accuracy of meter
readings at local and remote locations.
2. High Voltage Circuit Breakers: Wiring, Function, Interlocking, Painting & external visual inspection,
Exchangeability of similar devices, Auxiliary circuits insulation
3. High Voltage Isolators: Wiring, Function, Interlocking, Painting & external visual inspection, Auxiliary
circuits insulation
6. HSCB & DC isolators: wiring, Function, Interlocking, Mechanical operations at rated, max. & min
voltage, Interlocking, Visual inspection
7. All control and protection functions and electrical/mechanical interlocks shall be tested.
8. Primary Injection Tests: Tests on each protective system, to prove the auxiliary circuit connections, the
relay fault setting values, the correct metering indications and the stability limits.
9. AC/DC Pressure Tests: Insulation resistance of all circuits, equipment, cables and OCS system.
10. Platform resistance test during laying and after laying of membrane.
POW-4-104
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
4.15.2 Maintainability
This criterion represents the mean time for repairing (MTTR) and has to be considered only by replacement of
faulty equipment or sub assembly. The MTTR shall not exceed 2 hours not including the dead time to reach the
site. Dead time to reach at site shall be less than 12 hrs for Manila based agency and 48 hrs for outside agency.
An approach with the use of modular and replaceable equipment shall be incorporated in the design.
4.15.3 Availability
Availability shall calculate to achieve the highest level.
Contractor shall provide built-in diagnostics and remote monitoring functions for each microprocessor-based
equipment and module of the systems such that the performance requirements can be demonstrated.
The Systems shall not give rise, or be subjected to, dangerous interactions within the MMSP or with other
systems. The design shall also consider potential interfaces with Road System. The installation shall meet the
fire safety requirements generally as per NFPA 130 or equivalent. The design of the earthing system shall
conform to IEEE-80/2000, and EN 50122.
a) The Systems design shall incorporate measures to provide for its safe management and operation.
b) The Systems shall not give rise, or be subject to, dangerous interactions within the Metro or with other
systems.
c) The design of the Systems shall consider the safety and reliability of interface to the adjoining transit
systems including Road System.
POW-4-105
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
d) The design of the earthing system shall conform to the National standards, IEEE-80 and EN 50122.
e) The installation design shall incorporate measures to avoid safety hazards to people.
f) The installation shall meet the fire safety requirements generally as per NFPA-130.
c) Equipment safety;
h) Electrical safety including safety clearance from exposed live conductors; and
i) Safety for passengers, the Engineer's staff and public, including trespassers as far as is reasonably
practicable.
The Contractor shall minimize the above-mentioned risks to a level as low as reasonably practicable in the
design and construction and operation of the System.
In the case of fault/accident, and to permit evacuation of passengers from stations by bringing the train up to
station, the sectioning shall be such that in case of fault, the faulty section can be isolated quickly and the trains
in the healthy section on the same track can either be brought to a station or can be taken on the other track
through emergency cross-over depending upon the operational requirements. Basic sectioning arrangement for
indicative purposes has been depicted ln the tender drawings. Sectioning arrangement is to be modified
/upgraded by Contractor to provide better sectioning scheme having increased flexibility with the consent of the
Engineer.
Overhead line over each track on Main Lines shall be supported independently, the design of supports of Depot
and secondary lines shall be of sufficient robustness so that an impact by a train pantograph shall not cause a
failure affecting other running lines. OCS tensioning devices shall be installed with sufficient lubrication to
prevent mechanical failure. The traction and station power supply shall interface with the SCADA system to
allow control and monitoring remotely from the OCC. The System shall provide diagnostic information to the
operator in the event of fault affecting the power supply.
POW-4-106
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
b) The Contractor shall produce a maintenance regime for the equipment that shall comprise two
constituent parts, corrective and routine/preventative maintenance.
c) Routine/preventative maintenance shall be non-intrusive to the day-to-day operation of the train service
and be capable of being pre-planned in advance of the work.
d) Permanent Corrective maintenance shall be available during non-revenue hours. Temporary/quick fix
maintenance shall be done during the revenue hours.
e) The maintenance regime shall cover all parts and equipment of the system designed, installed and
commissioned by the Contractor. The Contractor shall take into account the requirements of the
operations and maintenance when determining and proposing its maintenance regime.
1. Means of interlocking cubicle doors when apparatus is energised at dangerous voltages (e.g. rectifier
cubicles etc.).
2. Means of interlocking circuit breakers, isolators and earth switches to avoid out of sequence switching.
POW-4-107
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
b) The wire and cable identification system shall be in accordance with the requirements of IEC Standard
60445, both end dependent numbering is required and a functionally based system is preferred.
3. Oil bunds to be constructed around and oil pit under oil filled transformer transformers for oil
containment and protection of the environment against pollution in the event of oil leaks or transformer
tank explosions.
4. Acid filled batteries, oil and all other hazardous substances shall be managed, stored, used, and
transported in accordance with ISO 14,000 requirements and Philippines Control of Substances
Hazardous to Health Regulations (COSHH). These Regulations require employers to control exposure
to hazardous substances to prevent ill health.
1. The Contractor shall provide measuring and special tools for future commercial operation as follow:
a) The Contractor shall submit the lists of those tools at least six (6) months from the Completion
Date of the Works to the Engineer for his review. The list shall include detailed description with
references and correlation with the maintenance manuals.
b) The Contractor shall provide the special tools and diagnostics test equipment during
installation and testing stages and for operation and maintenance use.
2. The Contractor shall submit item unit price with quantities of each type of special tools and test
equipment and those recommended by the Contractor.
The Contractor shall provide consumables and spare parts to cover two (2) years for commercial operation.
1. The Contractor shall submit the lists of consumables and spare parts within six (6) months before the
Completion Date of the Works to the Engineer for review. The list shall include the detailed description
with references and correlation with the maintenance manuals.
POW-4-108
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
2. The Contractor shall submit unit price with quantities of each type of consumables and spare parts to
the Engineer.
3. The Contractor shall separately keep and maintain sufficient stock of his own consumables and spare
parts for the Commissioning and Defects spares. In addition, in determining the list of consumables and
spare parts for the Commissioning and Defects repairs, the Contractor shall provide calculation to
support the proposed types and quantities with the following:
4. The Contractor shall submit the list of consumables and spare parts, with the types and quantities of
spares the Contractor intends to hold, at least three (3) months before the commencement of the Defects
Notification Period to the Engineer.
5. The Contractor shall include details of the stock of the Contractor’s own spares in the Monthly Progress
Report. The status of the spares, either in store or under workshop repair, shall also be included.
The specific objectives of each course, training facilities to be used, the qualification and experience of the
training instructors and the assessment criteria shall be developed by the Contractor and submitted to the
Engineer for approval.
The training shall be carried out at such locations where the greatest benefit for trainees may be gained. This
may be in Manila, abroad, at place of manufacture, assembly or testing, or at such other locations as may be
necessary. All the expenditure for training shall be borne by the Contractor. All places of training shall be
subject to review by Engineer.
The O&M training plan shall include but not limit to the following:
b) Details of the proposed approach to structuring and providing the courses required;
c) Course details including duration, maximum number of trainees, ratio of trainees to trainers,
facilities required or available and prerequisites for attending the course; and
d) Recommendations for additional training or alternative means by which the Engineer's training,
objectives may be met.
2. The content, timing and duration of the training program shall be such that personnel trained by the
POW-4-109
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
Contractor will be able to operate and maintain the power supply system in the designed manner with
maximum reliability and economy. Training objectives in terms of minimum standards to be achieved
by each trainee shall be clearly defined by the Contractor for each trainee post, including the Employer’s
Staff.
3. The Contractor shall train and qualify the O&M Personnel in compliance with the Training and
Qualification Plan. The training shall be based on classroom courses and on on-the-job training. It shall
address every technical aspect of Operation and Maintenance of the System.
4. The training of the O&M Personnel is based on the following two stages:
6. For each course, the Contractor shall prepare and submit to the Employer the training material for
approval. The training material is composed of trainee documentation, a trainer’s manual and a
qualification set of tests.
7. The training shall deal with technical topics such as knowledge of the System and operation and
maintenance of the system.
8. When the O&M Personnel is trained, the Contractor shall qualify each member of the staff, by
organizing theoretical and practical tests. These tests shall especially but not only deal with safety
related topics. The qualification is mandatory to execute operational duties on the System.
9. All the training and qualification activity shall be completed before the Take Over.
The maintenance plan shall include but not limited to the following:
2. Working description of first line maintenance, second line maintenance, third line maintenance;
POW-4-110
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
9. Recovery method;
Software Support
The Contractor shall submit software support plan to the Engineer for review. All incompatible modification,
bug fix, update, revise, change and version up with the specifications shall not be performed.
In order to continue proper operation, The Contractor shall provide the software modification, bug fix, update,
revise, change and version up including database table configuration for all developed and supplied software.
All the modification and revision for the software shall not gave deterioration for system performance and
harmful action.
The Contractor shall retain backup copy of developed and supplied software.
The Contractor shall secure proven validity, tested completely and no objection by the Engineer before loading
the new version to the systems.
The Contractor shall educate the Employer’s staff before loading new version to the systems.
1. Software obligations
Any software produced and modified for this contract shall be submitted two backup copy before 14 days
commencing actual operation prior to the possession of the Employer. The backup copy shall include but not
limited to the following:
All source code, all execution code and all database configurations;
Not only software development tool for the maintenance, but also editor, compiler and linker system.
2. Manuals
The Contractor shall provide operation and maintenance manual. The latest version of manuals shall be supplied
before the commencement of training.
The updated manuals shall be supplied when operation and maintenance method had been changed by
modifying the equipment.
a) Operation manuals
The Contractor shall provide operation manuals regarding the purpose switching procedures, and
operation for each equipment, sub systems and systems.
b) Maintenance manuals
POW-4-111
METRO MANILA SUBWAY PROJECT PHASE 1 Part 2 - Employer’s Requirements
Package: CP 106: E&M Systems and Track Works Section VI
The Contractor shall provide maintenance manuals describing the maintenance, the focal point of failure
investigation, mounting equipment, demounting equipment, repair technique and all necessary items
for maintenance for each system and its sub system.
The Contractor shall provide sufficient quantities of manuals (hard copy) and electronics manual in the
maintenance office.
4.17.2 Storage
The shipped plant before installation shall be stored at the site or the place appropriate for storage. The plant
shall be stored at the place without fear of destruction and theft when retaining it in places other than the Site.
4.17.3 Delivery
Delivery schedule shall take into consideration carrying-in of the Plant directly to the Site without the need for
double-handling.
- END OF DOCUMENT –