Professional Documents
Culture Documents
MY/Program
Name of Component(s), Sub-System(s) or System(s):
Part Number(s):
Responsible Supplier:
Responsible FCA US LLC Supplier Quality Engineer:
Name of Auditor:
Date Reviewed:
Date of PFMEA audited (Later of Original or Rev. Level):
Note 1: "E/I" = only minor "E"xceptions or requirement "I"nconsistently applied (approx. 25% or less) and correction still required.
Note 2: Do not allow a "No" answer to one question (e.g., Detection ranking too low) result in a "No" answer to another related question (e.g., lack of
"Recommended Actions" or "Action Results"). Evaluate each question based only on their own merits.
2 General Requirements for all PFMEAs Yes E/I No N/A Auditor Comments
2a All operations included in the Process Flow Diagram have been included in the
PFMEA or a risk assessment was done and only medium/high risk operations have -
been included?
2b All process steps included in the Work Instructions have been included in the PFMEA
or a risk assessment was done and only medium/high risk steps have been included? -
2c A review of all Safety Office Campaign and Yard Hold records was done and all
relevant issues are included in the PFMEA? Notes: 1) FCA US LLC Supplier Quality
Engineer must be contacted to provide response. 2) If no relevant Campaign or Yard
Hold exists, answer "N/A".
2d A review of applicable FCA US LLC Master PFMEA (MPFMEA, formerly known as
Lessons Learned) was done and all relevant information is included in the Supplier's
PFMEA? Notes: 1) FCA US LLC Supplier Quality Engineer must be contacted to
provide response. 2) If no applicable MPFMEA exsits, answer "N/A".
2e All internal nonconformance over the past 6 months minimum caused by the existing
or a surrogate process have been included in the PFMEA? -
2f All external (customer) nonconformance over the past 12 months minimum caused by
the existing or a surrogate process have been included in the PFMEA? -
564392835.xlsx 1
MY/Program
Name of Component(s), Sub-System(s) or System(s):
Part Number(s):
Responsible Supplier:
Responsible FCA US LLC Supplier Quality Engineer:
Name of Auditor:
Date Reviewed:
Date of PFMEA audited (Later of Original or Rev. Level):
4b All applicable Failure Modes from the DFMEA have been included in the PFMEA?
Notes: 1) If Failure Mode description is not acceptable, mark "N/A". 2) If no DFMEA
exists, mark "N/A".
Additional Comments (not to impact audit results): - - - -
If all answers "Yes" or "N/A" check "Yes." If one or more "No," check "No."
-
Otherwise, "E/I."
7c Classification symbol for Severity 7 or below for the same Effect on the DFMEA have
been included in the PFMEA? Note: If not acceptable or no DFMEA exists, mark,
"N/A."
Additional Comments (not to impact audit results): - - - -
If all answers "Yes" or "N/A" check "Yes." If one or more "No," check "No."
-
Otherwise, "E/I."
564392835.xlsx 2
MY/Program
Name of Component(s), Sub-System(s) or System(s):
Part Number(s):
Responsible Supplier:
Responsible FCA US LLC Supplier Quality Engineer:
Name of Auditor:
Date Reviewed:
Date of PFMEA audited (Later of Original or Rev. Level):
10b Controls are adequately explained and do not just reference a document number?
Note: The description for Controls shall include where done (station #), how done
(go/no-go gage, variable gage, visual, poke-yoke with line lock-out, etc.), frequency -
and sample size (e.g., 100%).
r Clarify the wording in 1g, add line item 2d to including MPFMEA. 30-Jan-12
s Replaced "Chrysler" with FCA US LLC 27-Feb-15
564392835.xlsx 3
Supplier Control Plan: Document Audit Summary Revised: October 28, 2011
MY/Program:
Name of Component, Sub-System or System:
Part Number(s):
Responsible Supplier:
Responsible Supplier Quality Engineer:
Name of Auditor:
Date Reviewed:
Date of Control Plan (Original or Rev. Level):
Is the Process Failure Mode and Effects Analysis (PFMEA) available for this audit?
Note: The PFMEA must be complete prior to Control Plan Audit.
Are the most current design records (part print, GD&T sheets) available for this audit?
If one or more "No", check "No" here and STOP the audit until prerequisites are met.
Note: "E/I" = only minor "E"xceptions or requirement "I"nconsistently applied (approx. 25% or less) and correction still required. It applies to all sections.
Are all process steps listed in the Process Flow Diagram included in the Part/Process
Number column of the Control Plan?
1
Note: The Control Plan shall address all process steps from receiving inspection through
shipping.
Are all process steps listed in the PFMEA included in the Part/Process Number column
of the Control Plan?
2
Note: The Control Plan shall address all process steps from receiving inspection through
shipping.
3 Is the Process Name/Operation Description clearly stated as in the PFMEA?
Are the Machine, Device, Jig, Tools for mfg. listed correctly with identification numbers
for the individual processes?
4
Note: FCA US LLC Supplier Tool Record (STR) numbers listed in the Control Plan or in
a separate cross-reference sheet is recommended but not mandatory for this audit.
MY/Program:
Name of Component, Sub-System or System:
Part Number(s):
Responsible Supplier:
Responsible Supplier Quality Engineer:
Name of Auditor:
Date Reviewed:
Date of Control Plan (Original or Rev. Level):
Characteristics Columns:
- No.
- Product Yes E/I No N/A Auditor Comments
- Process
- Special Characteristic Class
Are all features or properties of the part, component or assembly defined in the "Product
Characteristic" column described on design records (released drawings, GD&T, Part
5 Information Page, etc.)?
(Examples: Surface Finish, Paint Appearance, Meter Accuracy,
Presence of 4 holes, etc.)
Are all unique process characteristics identified within the "Process Characteristic"
6
column which are being controlled to reduce variation in assembly characteristics?
Is the "Special Characteristics Class" identified which indicates the level of importance
7 as defined in the design record?
(Ex. <S> Safety, <H> Homologation, <D> Diamond, Stoplight, or other supplier unique)
Are all product and process characteristics listed in the PFMEA also listed in the control
8
plan. ?
Methods Columns:
- Product/Process Specification Tolerance
- Evaluation Measurement Technique
- Sample Size Yes E/I No N/A Auditor Comments
- Sample Frequency
- Control Method
- Reaction Plan
Do all Safety <S> characteristics have a (100%) primary measurement process and a
12
secondary quality measurement process identified?
Is the Control Method consistent with the Current Process Controls in the PFMEA?
13 Note: The Control Plan should cover all Current Process Controls in the PFMEA to
prevent or detect potential risks.