Professional Documents
Culture Documents
Co-funded by the
Connecting Europe Facility
of the European Union
PCI Acorn SAPLING, Action
12.2-0036
Introduction
1. Introductions via Teams
• BEIS, Pale Blue Dot, Shell, Chrysaor and Total representatives
3. Impact of Covid-19
• Energy Innovation Program COVID-19 support request submitted 31st August
• Continued remote working, current trends in reverse and hard to predict a timescale when regular office
working will return
• PBDE are prepared with a return to office protocol in place
• Any return to the PBDE office will be governed by the Scottish route map
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Objectives
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Agenda
1. Introduction
5. Next Steps
www.pale-blu.com
Pale Blue Dot Energy Limited ©
2. Acorn Project
update
• Acorn Phase 1
• Costs and schedule
• Permitting and Consents
• Phase 2
• Commercial Updates
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Acorn CCS Update - Carbon capture technology ITT issued,
commencing FEED in late October....
• End of Concept Select Stage gate assurance process completed 9th July – progressed
recommendations in 19 areas
• Define phase commencement date reviewed and set to 26th October
• Carbon capture technology procurement ITT issued to 6 bidders
• Subsea power, control & communications design progressed through study agreement with
North Sea platform Operator
• 7 of 25 BEIS deliverables have been issued to date
• Applied for project extension to BEIS due to COVID-19 extension
• FEED is on schedule to be completed end 2Q 2021
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Phase 1 leading concept full chain Capex estimate…
Indirect Tech.
CAPEX Category Direct Costs Costs Allowance Contingencies Total Cost Range
£ MM £ MM £ MM £ MM £ MM £MM
Pre-FID (inc Intelligent pig) 7.8 5.1 0.0 0.4 13.3 11.9 - 14.6
Subsurface 9.0 2.1 0.0 1.1 12.2 7.3 - 17.1
Carbon Capture Plant 147.7 40.5 47.1 70.6 305.9 214.1 - 458.8
Conditioning & Compression 55.4 15.2 17.6 26.5 114.6 80.3 - 172
Subsea & Pipelines 63.9 7.5 14.3 25.7 111.4 78 - 167.1
Wells (inc trees) 20.5 6.6 5.4 9.8 42.3 29.6 - 55
TOTAL 304.3 77.0 84.4 134.0 599.7 421.2 - 884.6
• Class 4 estimate
• Accuracy range of +50 / -30%
• Contingency equates to 22% of final estimate
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Value enhancement opportunities being evaluated…
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Acorn CCS Schedule – Phase 1 FID target now end-1Q2022
Commercial/financing timeframes drive uncertainty…
2020 2021 2022 2023 2024 2025
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Subsurface - Design
Wells - Procurement
Onshore - Procurement
Onshore - Construction
Onshore - Commissioning
Offshore - Procurement
www.pale-blu.com
Offshore - Construction Offshore - Commissioning
Pale Blue Dot Energy Limited ©
Acorn Phase 2 – supply/demand scaling economies
• ISCF Phase 2 application due 7th October
• CEF2020 application results due in
Oct/Nov
Need to
Need to
demonstrate
demonstrate
compliance with
compliance with
Wells and Pipeline
PPC, COMAH and Mean Low Water
Safety Regulations
Pipeline Safety
Regulations
July Multiple other consents and permits will follow FID and be
www.pale-blu.com
Pale Blue Dot Energy Limited gained through Detailed Design building on these consents
P&C Schedule - intent to achieve key consents before COP26,
commercial interface requires more definition…
Key Interfaces:
• Engineering BoD for assessment
• Engineering drawings and layouts
• Construction areas required
• Confirm access to land and
infrastructure
• Financial securities interfaces with
BEIS contract (risk allocation)
• Public consultation events
www.pale-blu.com
3. BEIS update/
discussion
• Acorn Project Schedule
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Acorn CCS schedule – commercial development into 2021…
2019 2020 2021 2022 2023 2024 2025
• BEIS timeframe for HoTs, contractual HoTs, full negotiations, duration and legislation?
www.pale-blu.com
• Capacity for and potential for acceleration with bespoke approach
Bespoke contract – acceleration opportunity for Acorn CCS…
• Opportunity to accelerate Acorn full chain CCS project - in operation beginning 2025
• BEIS has informed that it is not discounting projects reaching FID earlier (under existing
legislation) through bilateral bespoke contract
05/10/2020
www.pale-blu.com
Pale Blue Dot Energy Limited
4. Acorn bespoke
Contract
• Model development
• Next Steps
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Acorn CCS Project: Existing powers identified…
Key Considerations for the Acorn CCS Model:
• Structuring private law contracts to:
• Facilitate the development of the enduring regime; and
• Allow the Acorn CCS Project to transition to the enduring regime.
Potential Legislative Powers:
• Environmental Protection Act 1990 (Section 153):
• Empowers the Secretary of State (with the consent of the Treasury) to give financial assistance to or for the purposes of a list of environmental
programmes and schemes that includes:
• United Nations Framework Convention on Climate Change; and
• Any scheme for the storage, treatment or disposal of any material or product for the purpose of preventing/reducing environmental damage
www.pale-blu.com
Pale Blue Dot Energy Limited ©
CfD and Economic Regulated models appear feasible to be
incorporated into private law contracts…
Acorn Capture Plant Funding Model: Contracts for Difference (CfD) + Capital Grant Funding
• Combination of CfD and capital grant funding lends itself naturally to a private law contract with HMG
• Centered on cost differential of abatement relative to prevailing carbon emission allowance price
• Capital Grants to be structured as instalments against key construction milestones to incentivise and allocate construction
delivery risk
• Based on the Hinckley Point C Model - CfDs with financial assistance from Government Support Package
• Follows elements of support contracts proposed in the CCS Demos 1 and 2
Acorn Transport & Storage System Funding Model: Economic Regulation Model
• All key building blocks of a traditional economic regulatory model can be incorporated into a private law contract
• Analogous to mechanisms used by HMG for conventional procurement of Major Infrastructure Projects – Hinkley Point C
and Thames Tunnel Tideway
• Requires certain enablers like an Independent Certifier to review and approve RAB expenditure (Hinkley Point C), detailed
regulatory accounting procedures with verification and audit rights, and an expedient dispute resolution process
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Acorn CCS - Commercial
Bespoke Contract
Bespoke Contract: Requirements Single Entity: Split CfD
• Supports Acorn FID and Start-up objectives • Underlying characteristics sympathetic to TRI and
CfD mechanism(s)
• Pre-cursor to enduring regime • Availability / variable payments
• Demonstrable path to dis-aggregation / transition • Internal accounting facilitates:
• Funding path available under existing legislation • 3rd party access
• Dis-aggregation to enduring regime
Assumed Enduring Regime: • Grant funding of Capture would simplify transition
• Single project contract ‘control’
• ‘CapCo’ (CfD)
• T&SCo. (TRI) Dual Entity: Based on proposed enduring regime
• Approximating: 1. CapCo: CfD, 2. T&SCo.: TRI
• Dis-aggregation from outset simplifies transition
• Contracts characterised by BEIS Strawman TRI/CfD
• Limited contract duration and/or transition ‘trigger’
• Additional contract ‘control/regulation’ required
www.pale-blu.com
C&TSCo. Split CfD approach Transitioning to a T&Sco. ‘TRI’ + CapCo. Standard CfD
Or
fixed
Split CfD approach fee
(No TUSA Required) Revenue1 Revenue 2
‘Availability’ Payment: Independent of ‘throughput’ Strike Price + Reference Price
Capital Return on Fixed Opex Opex ‘Fee’ (profit Abandonment CO2 volumes captured /
+ Variable Costs
Repayment Capital Payment component) Provision stored
Transitioning To:
Entity 1: T&SCo: TRI (with TUSA) Allowed Revenue
(chargeable to CapCo & 3rd Party Entrants)
Capital Return on Fixed Opex Opex ‘Fee’ (profit Abandonment Govt. Support
Incentives
Repayment Capital Payment component) Provision Package
Revenue + Support
Residual Capture Capex
Operating Costs Strike Price
T&S Fee Ref Price
(incl. risk)
Risk
July www.pale-blu.com
Pale Blue Dot Energy Limited
5. Next steps
www.pale-blu.com
Pale Blue Dot Energy Limited ©
Next steps…
• Acorn CCS Bespoke model
• Alignment on approach with BEIS for Acorn CCS Project
• Progress - initial discussion points
• Roadmap towards bespoke agreement
• Single Entity / Dual Entity
• Contractual Architecture
• Risk identification and allocation
• Acorn build out implications
• Contract duration / transition ‘trigger’
• Continue to develop CCS business model with BEIS towards enduring regime
• Bilateral engagement and Expert Groups
• Acorn/BEIS “splinter” CCS bilateral meetings
• Infrastructure Re-Use (focus Goldeneye pipeline)
• T&S (underway)
• Capture (to be initiated)
05/10/2020
www.pale-blu.com
Pale Blue Dot Energy Limited