You are on page 1of 28

GENERAL QUALITY PLAN Doc No.

QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
Check list for
1.Contract Document PM / Eng / SE/ site take over &
requirements TO mobilization
(CL 01)

2. Past performance of
Suppliers
Suppliers and Sub Supervisor
evaluation,
Contractors Within the
Awarding
time period 1.Supply 2.Check with
Site take over and latter,BOQ, During site
1 3. Brand, Gauge, mention in the incorrect the approved
Mobilization drawings & Client mobilization Suppliers
Material size, Quantity, awarding Material materials
specification performance
Price, Punctuality and as letter.
sheet,
per specifications

Material test
4.Sample test of material
reports,

5.Consultant approval of Sub contractor’s


material agreements.

Should be
Awarding clean enough
1.Check with Check list for
latter,BOQ, 1.Get the consultant’s During & After to carry out 1.Clering PM / Eng / SE /
2 Site Clearing the client land site clearing (CL
drawings & Client approvals the site clearing setting out other land TO
area 02)
specification without any
obstruction.

2.Used the proper 2.Not clearing


2.Reclering Soil test report
equipment & machines properly

Issue 01, dated 2017 - 01 - 02 Page 1 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

3.Removal of structures

4.Removal of trees which


could obstruct the work

5.Removal of top soil


layer with the
vegetations (150mm)
6.Soil test(If required)

7.Barricate exiting power


cable / water supply line
& drainage line in use

1.Get the consultant’s


At start work
approvals

BOQ, drawings & 2, Parallel /Perpendicular During work Dimensions of 1.error of Measuring Check list for
to existing building PM / Eng /
3 Setting out-General Client setting out measuring equipment setting out-
survey / TO
specification drawing. equipment Calibration General (CL 03)
3, Checking diagonals At end work
4, Cross checking
dimensions from two or
more directions
1.Get the consultant’s During & After Check list for
Setting out-Anchor
4 approvals for anchor bolt the Anchor Bolt setting out-
bolt placing Placing
material General (CL 03)

Issue 01, dated 2017 - 01 - 02 Page 2 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
Strength repot of
2. Quality of material
material
3. diameter & heights of
anchor bolts
4. checking template
measurement &
Thickness
5. Suitability of welding
equipment
6. Skill of welder

7. Thickness of welding

8. Checking diagonals

9. Protection of threaded
area
10. Check with the
existing floor level
Check list for
BOQ, drawings &
Excavation and Earth 1.Get the consultant’s SCA /4 Building 1.Using proper PM / Eng / SE / Excavation &
5 consultants During work 1.Earth claps
work. approvals works. shoring method TO Earth work (CL
specification,
05)

After each
2.Dimension excavation, Supervisor Level sheet
After backfilling.

Compaction test
3.Height
report
4.Levels

Issue 01, dated 2017 - 01 - 02 Page 3 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
5.Disposal of excavated
materials

6.Dewatering & Shoring

7.Method of shoring
8.Used the proper
equipment & machines
9.Quality of shoring
material

10.Quality of soil
11.Back filling layer
thickness
12.Sand binding layer

13.Watering & vibrating

14.Back filling &


Compactions method
15.Compaction test
BOQ, drawings & Check list for
1.Get the consultant’s SCA /4 Building PM / Eng / SE /
6 Screed Concreting consultants At start screed concrete
approval works. TO
specification (CL 06)
2.Thickness of screed During work Supervisor Slum test
Material test
.3Grade of Concrete
reports,

Issue 01, dated 2017 - 01 - 02 Page 4 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

Sub contractor’s
4.Aggregates
agreements.

5.Polythene is
required/not
6.Leveling
7.Dimension
8.Water cement ratio
9.Mixing method &
mixing equipment
condition
10.Slum test
11.Curing
1.Making
BOQ, drawings & Check list for
Random Rubble 1.Get the consultant’s SCA /4 Building drawings PM / Eng / SE /
7 consultant At start work 1.Wall crack Random Rubble
masonry approvals works. marking TO
specification Masonary (CL 07)
expansion joint

2.Using proper Sub contractor’s


2.Dimensions, During work Supervisor
mortar ratio agreements.

3.Alignment, At end work

4.Levels
5.Type of bond curing,
6.Type of wall
7.Size of rubble
8.Mortar ratio

Issue 01, dated 2017 - 01 - 02 Page 5 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
9.Expression joints,
10.Mortar quality
11.Weep holes
12.Finishing of wall
surface
BOQ, drawings & 1.Mistakes of Check list for
1.Get the consultant’s SCA /4 Building 1.check with PM / Eng / Qs /
8 Gabion wall consultant At start work wall level and gabion wall (CL
approvals. works. level and wide SE
specification wide 08)
2.Dimensions, During work Supervisor
3.Alignment, At end work
4.Levels
5.thickness of geo textile
6.gauge of gabion net
7.Used the proper
equipment & machines

8.Dewatering & Shoring

9.Shoring method
10.Size of rubble
11.Finishing of surface
2.Evertime
BOQ, drawings & 1.wrong bar check with the Check list for
1.Get the consultant’s SCA /4 Building PM / Eng / Qs /
9 Reinforcement work consultant At start work spacing and drawings bar reinforcement
approvals works. TO
specification lap length spacing and lap work(CL 09)
length
2.Quality of bar (SLS
Bar schedule During work Supervisor bar schedule
certified)

Issue 01, dated 2017 - 01 - 02 Page 6 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
3.Stability of the
At end work
reinforcement
4.Check with bar
schedule
5.Bar diameter
6.Clear cover
7.Cleanliness
8.Bar spacing

9.Stools & Cover blocks


10.Check with the
consultant approved lap
length
11.Check with the bar
type & marking
12.lap joints
BOQ, drawings & 2.Using proper Check list for
1.Get the consultant’s SCA /4 Building 1.Wrong PM / Eng / Qs /
10 Form work consultant At start work vertical Form work (CL
approvals works. alignment TO
specification supports 10)
2.Dimension During work Supervisor
3.Alignments
4.Accuracy of levels
5.Vertical and lateral
support
6.Quality of materials
7.Type of form work
method

Issue 01, dated 2017 - 01 - 02 Page 7 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
8.Clear cover with the
reinforcement

9.Type of form work


material (steel or timber)

10.Quality of work

Check list for


Concreting Work concrete work
BOQ, drawings &
(Footing, Columns, 1. Get the consultant’s SCA /4 Building 1. Concrete 1.properly PM / Eng / Qs / (Footing,
11 consultant At start work
Beams, Walls & approvals works. floor cracking. curing TO Columns, Beams,
specification
Others) Walls & Others)
(CL 11)

2.Using proper
2.Levels & Dimension During work 2.Hony comb vibrating Supervisor Test report
method
3.Condition of
At end work Slum test
equipment
4. Aggregates Level sheet
5.Grade of concrete
6. Slum
7.Setting time,
8.Final cleaning &
Checking
9.Test Cube
10. Compaction method

Issue 01, dated 2017 - 01 - 02 Page 8 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

11. Finishes(Honeycomb)

12. Curing & Protection


13. Vertical alignment
14. Protection of anchor
bolt
15. Bonding method &
chemicals
16. Used the proper
equipment & machines

Check list for


Concrete Works 1.Get the consultant’s SCA /4 Building 1. Concrete 1.properly PM / Eng / Qs / concrete work
12 At start work
(floor & slab) approvals works. floor cracking. curing TO (Floor & Slab)
(CL12)
2.Using proper
2.Levels & Dimension During work 2.Hony comb vibrating Supervisor Test report
method
3.Condition of
At end work Slum test
equipment
4.Aggregates Level sheet
5.Grade of concrete
6.Slum
7.setting time,
8.Final cleaning &
Checking
9.Test Cube
10.compaction method

Issue 01, dated 2017 - 01 - 02 Page 9 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
11.Curing & Protection
12.Protection of anchor
bolt
13 Protection of anchor
bolt
14. Bonding method &
chemicals
15. Type of finishing
16. Expansion or
construction joint
17. curing method
18. Used the proper
equipment & machines

19. Anti- termite method

20. Gauge of polythene


After removing form
work
21.Beam or wall
alignment
22.Finishes
(Honeycomb)

BOQ, drawings & Check list for


Brick/Block masonry 1.Get the consultant’s
13 consultant brick/block
work approvals
specification masonry (CL13)

Issue 01, dated 2017 - 01 - 02 Page 10 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

SCA /4 Building 1.making PM / Eng / Qs /


2.Dimension At start work 1.Wall crack Test report
works. expansion joint TO

2.Insert of
3.Verticality During work Supervisor
Bonding mesh
4.Right angles
5.Alignment
6.Type of bond,
7. Curing.
8. Stiffener columns.
9. Mortar thickness
10.Openings to be
provided
11.Type of wall
12. Quality of material
13. Test report
14. Size of Brick/block
15. Mortar ratio
16. Size of wall
17. Quality of wall
1.idetify the
BOQ, drawings & Check list for
1.Get the consultant’s SCA /4 Building 1.Water leakage point PM / Eng / Qs /
14 Water proofing work consultant At start work water proofing
approvals works. leakage and re-water TO
specification work (CL13)
proofing
2.Compliance with Grantee
During work Supervisor
specification certificate
3.quality of materials At end of work
4.Quality of equipment

Issue 01, dated 2017 - 01 - 02 Page 11 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
5.Surface preparation
6.Remove dust ,oil and
water on the floor
7.1st coat of
waterproofing
8.2nd coat of
waterproofing
9. Setting time
10. Protective screed.
11. Skill of worker
12, Thickness of layers
13. Thickness of water
proofing members
14. Angle & height of
fillet
15. Setting time
16. Mixing method &
ratio
17. Fixing joints
Check list for
BOQ, drawings & 1. Suitability of
Loading of steel PM / Eng / Qs / Loading of steel
15 Consultant machinery weight At start work
structure TO structure
specification capacity & length
(CL 15)
Packing list 2. Surface of unloading During work Supervisor
2. Method of unloading At end work
3. Damages

Issue 01, dated 2017 - 01 - 02 Page 12 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
BOQ, drawings & Check list for
1. Suitability of
Unloading of steel Consultant Unloading of
16 machinery weight
structure specification steel structure
capacity & length
Packing list (CL 16)
2. Method of packing Packing list
3. Quality of packing
4. Check with the packing
list
4. Check with the packing
list
Check list for
BOQ, drawings & 1.Get the consultant’s 1.Marking it
Fabrication of steel SCA /4 Building 1.change the PM / Eng / Qs / Fabrication of
17 Consultant approvals materials & At start work properly after
structure works. marking TO steel structure
specification fabrication drawings fabrication
(CL 17)
2.Close the
2.Punching the Welding check
2.Quality of materials, During work marking after Supervisor
marking list
painting
3.Sutability of welding & 3. Cracking of 3. Grinding and
At end work
drilling equipment welding joints re welding

4.Dimensions & 4.Damage of 4.safely loading


Thickness of materials painting and unloading

5.Cutting joints & edges,


6. Suitability of Cutting
equipment

Issue 01, dated 2017 - 01 - 02 Page 13 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
7. Suitability of surface to
be welded
8. Correctness of
drawings
9. Skill of welder &
fabricator

10. Correctness of
marking line & point

11. Thickness of welding


12. Surface cleaning
13. Levels
14. Alignment
15. Correctness of holes
punching
16. Welding check list
BOQ, drawings
1.Get the consultant’s Check list for
Painting of steel client & PM / Eng / Qs /
18 approvals materials & At start work Painting of steel
structure Consultant TO
fabrication drawings structure (CL18)
specification
painting check
2. Surface cleaning During work Supervisor
list
3. Sand blasting or soft
At end work
blasting.
4. Application of primer
(Anticorrosive)

Issue 01, dated 2017 - 01 - 02 Page 14 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

5. Layer of painting coats

6. Thickness of painting
coats
7. Colour
8. Skill of painter
9. Covering area for paint
yard
10. painting check list
BOQ, drawings & 1.Get the consultant’s Check list for
Erecting of steel PM / Eng / Qs /
19 Consultant approvals for errection At start work Erecting steel
structure TO
specification method structure (CL19)
2. Correctness of anchor
Erecting manual During work Supervisor
bolts
3. Suitability of
machinery weight At end work
capacity & length
4. Skill of erector
5. Safety rule &
regulation

6. Leveling of base plate

7. Starting of first bracing


bay & alignment

8. Gauge of nut & bolt

Issue 01, dated 2017 - 01 - 02 Page 15 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
9. Tightness of joints
BOQ, drawings & 1.Change the 1.Check with
Check list for
Fixing Doors & Client & 1.Get the consultant’s SCA /4 Building door or the door PM / Eng / Qs /
20 At start work fixing door &
Windows consultant approvals works. window window TO
window (CL20)
specification materials schedule
2.Quality of materials During work Supervisor
3.Colour At end work
4.Cutting
5.Sizes & Type
5.Thickness or Gauge
6.Dimensions,
7.fixing joints
8.Alignment
9.Fixing ironmongery
10.Fixing glasses
11.Fixing accessories
12.Levels
14.Protection
BOQ, drawings & SCA /8-
1.Properly Check list for
Client & 1.Get the consultant’s Electrical and 1.Current PM / Eng / Qs /
21 Electrical Work At start work insulation of electrical work
consultant approvals Mechanical leakage TO
joints (CL21)
specification works.

2. Preparation of the
During work Supervisor As built drawings
shop drawing

Electrical
3.Quality of materials At end work
certificate
4. Laying of conduits

Issue 01, dated 2017 - 01 - 02 Page 16 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

5. Breaking and drilling


the walls for piping

6. wiring the electrical


lines
7. Temporary fixing of
the sunk boxes

8. Permanent fixing of
sun boxes and dist
boards after completion
of plastering

9. Fixing of switches and


socket outlets
10. Fixing of earth
electrode

11. Insulation testing,


Earth resistance testing

12. Fixing of electrical


fittings & Accessories

13. Quality of accessories

14. Protection marking of


underground cable (
laying sand & tile)

Issue 01, dated 2017 - 01 - 02 Page 17 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
15. Size of cable

16. Weight capacity of


cable tray

17. Load capacity of


MCB,Baker & Fittings
18. Load capacity of
cable
19. Skill of electrician
20. Power testing
(whether working or
not?)
21. Existing area as built
drawings
22. Fixing level
Check list for
BOQ, drawings & 1.Change the
Plumbing & Drainage 1.Get the consultant’s SCA /4 Building 1.Over flow of PM / Eng / Qs / plumbing &
22 consultant At start work level or making
Work approvals works. man hole TO drainage work
specification extra line
(CL 22)
As built drawings
2.Quality of materials During work Supervisor

3. Type & Size of the


At end work
pipes and fittings
4. Dimensions of pipes
5. Positions and levels of
the pipes

Issue 01, dated 2017 - 01 - 02 Page 18 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
6. Groves and holes in
floor and walls
7. Fittings and joints
8. Fixing accessories
9. Standard of
accessories & fitting
10. Fixing level of fitting
& accessories

11. Spacing of man holes

12. Capacity of septic &


soakage pit
13. Levels
14. Slopes
15. pressure testing
16.Complete with all
connections to gully &
manholes
.17. Existing area as built
drawings
BOQ, drawings &
Client ,
Check list for
consultant 1.Get the consultant’s SCA /4 Building 1.Wrong fixing PM / Eng / Qs /
23 Sanitary ware At start work 1.Refixing sanitary ware
specification approvals works. height TO
(CL 23)
Fixing
specification
2. Quality of material During work Supervisor

Issue 01, dated 2017 - 01 - 02 Page 19 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

3. Surface preparations At end work

4. Plumbing work.
5. Fixing height
6. Colour
7. Type of standard
8. Dimension
BOQ, drawings &
1.Get the consultant’s SCA /4 Building 1.Ceiling sheet 1.Change bar PM / Eng / Qs / ceiling
24 Ceiling Work consultant At start work
approvals works. sagging spacing TO work(CL24)
specification
2.Type During work Supervisor
3. Quality of materials At end work
4. Thickness
5. Dimensions
6. Ceiling Level
7. Painting
8. Neatness
9. Opening for service
line
10.Color
BOQ, drawings
Client & 1.Get the consultant’s SCA /4 Building 1.Roof sheet PM / Eng / Qs / Check list for
25 Roof Work At start work 1.Roof leakage
consultant approvals works. replace TO roof work (CL25)
specification
2.Apply water
2.Type of roof During work Supervisor
proof chemical
3. Quality of materials At end work

Issue 01, dated 2017 - 01 - 02 Page 20 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
4. Thickness of roof
sheet/tile

5. Dimensions of roof
sheet / tile
6. Color of roof sheet /
tile
6. Roof angle/curvature

7. Wall plate level.


8. Painting
9 .Neatness
10.Color of inside the
roof
11.Spacing of roof nail
point / hooks
12. Roof ventilation
system required or not
13. Type of insulation
14.Thickness of
insulation
15. Spacing of purling
16. Sky light area
17. Gauge & length of
nail / hook

18. Quality of nail & hook

Issue 01, dated 2017 - 01 - 02 Page 21 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
BOQ, drawings
1.Over flow of 1.Change the Check list for
consultant & 1.Get the consultant’s SCA /4 Building PM / Eng / Qs /
26 Roof plumbing. At start work gutter ,down down pipe roof plumbing
Client approvals works. TO
pipe &gutter size (CL 26)
specification
2.Gutter
2.Rectification
2. Quality of material During work ,down pipe Supervisor
of leakage point
leakage
3. Dimensions At end work
4.Cutting joints
5.Levels of gutter &
down pipe
6.Alignment of gutter &
down pipe
7.Fixing accessories
8. Type & Size of the
pipes and fittings
9. Positions and levels of
the pipes

10. Fittings and fixtures

11. joints

12. Dimensions of pipes

13.Slopes
16. Alignment of pipe &
Valance board
15.Including paint &
primer

Issue 01, dated 2017 - 01 - 02 Page 22 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
16. Thickness of pipe &
gutter

1.Dimolished
BOQ, drawings & Check list for
1.Get the consultant’s SCA /4 Building 1.Plaster cracking line PM / Eng / Qs /
27 Plastering work Client At start work Plastering Work
approvals works. cracking and insert mesh TO
specification (CL 27)
, re-plastering

2. Whether the surface is


clean any free from all During work Supervisor
dust
3.Leveling At end work
4. Mortar quality
5. Plastering thickness
6. Vertical & horizontal
alignment with other
wall finishes
7. Corners & edges
8. Size of openings
9. surface condition
10.Quality of sand
11. Mortar ratio
12. Bonding mesh
13. Neatness
14. Right angles
15. Curing

Issue 01, dated 2017 - 01 - 02 Page 23 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
16. Protection of
electrical item , door &
window frame , pipe line
17. Molding
Check list for
BOQ, drawings &
Cement rendering 1.Get the consultant’s SCA /4 Building 1.Surface 1.Properly PM / Eng / Qs / cement
28 Client At start work
work approvals works. cracking curing TO rendering work
specification
(CL 28)

2.macking
2.wrong
correct opening
2. Surface preparations During work opening for Supervisor
& -re-rendering
service line
wrong opening

3. Levels of bed At end work


4. Mortar quality
5. Thickness of mortar

6. Color of cement grout


7. Cement grouting
8. finishing of surface
9. Surface curing
10.Motar ratio
11. Slop
12. Opening for service
line/fitting
13. Neatness

Issue 01, dated 2017 - 01 - 02 Page 24 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
BOQ, drawings
1.Changing of Check list for
consultant & 1.Get the consultant’s SCA /4 Building 1.Purching with PM / Eng / Qs /
29 Tiling work. At start work colour or tiling work (CL
Client approvals works. the sample TO
design 29)
specification
2. Quality of material During work Supervisor

3. Surface preparations At end work

4. Levels of tile bed


5. Colour & size of tile
6. Type of tile
7. Thickness of tile
8. Wetting of tiles for at
least one hour period
before fixing
9. Mortar quality &
thickness
10. Apply even mortar
thickness
11. Maintaining Tile
surface level
12. Maintaining even
grove size
13.Preventing air voids
between tile bed &
corners
14. Neatness of edges &
corners

Issue 01, dated 2017 - 01 - 02 Page 25 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
15.Alignment of grove
16. Surface Cleaning
before grouting
17. Colour of Tile grout
18. Tile grouting
19. Maintaining Slop if
required
20. Protection cover for
tile floor
BOQ, drawings
1.match with Check list for
consultant & 1.Get the consultant’s 1.Colour PM / Eng / Qs /
30 Painting work At start work SCA /4 Building existing colour painting work
Client approvals changing TO
sample (CL 30)
specification
2.Apply sample
Mixing
2. Quality of materials, During work works. one get the Supervisor
specification
approvel

3. Surface dust & oil


At end work
cleaning
4. Surface preparation
5. Colour
6. Anti-fungus paint for
external
7. Method of painting
8. Mixing ratio
9. Apply two coats of
wall putty

Issue 01, dated 2017 - 01 - 02 Page 26 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done
10. Protection of other
areas.
11. Edges & corners
preparation
12. Apply filler coats
(Primer)
13. First coat of
approved type paint

14. Touchup works

15. Second coat of


approved type paint
16. Thickness of paint
17. Final Inspection
Check list for
MD
BOQ, drawings & After Completion of
Completion of work 1. Complete balance Contract 1.Rectification /CONSULTANT
31 Client completion of 1.Defects work & Final
& Final Inspections work Document work CLIENT / PM /
specification constructions Inspections (CL
ENG
31)

Customer
2.Cleaning all area Section 3 satisfaction
report & letter

Condition of
3.Identified defects
Contract,
4.Get the consultants
Clause 55.1
approvals
5.Get the client
satisfaction

Issue 01, dated 2017 - 01 - 02 Page 27 of 28


Review By........................................MR Approved By....................................MD
GENERAL QUALITY PLAN Doc No. QMS/ENG/D/002

Related Record to prove


Frequency of Requirement / Possible Action Responsibility
document Applicable verification / Possible Non that verification
SL No Activity verification / standard to be for Non of verification /
involved in the Monitoring Conformities / monitoring
monitoring met Conformities monitoring
activity done

Project
Agreement, BOQ,
drawings &
consultant, Client
Handing over the After
specification, as Contract MD/PM/ENG/ Handing over
32 project & 1.Delivery date rectification of
built drawings, Document T O letter
Maintenance period list of defects.
guarantee
certificates,
warrantee cards
list of key

2.Delayed period Section 3 SUPERVISOR


Condition of
3.Retention date
Contract,
Clause 56.1

Issue 01, dated 2017 - 01 - 02 Page 28 of 28


Review By........................................MR Approved By....................................MD

You might also like