Professional Documents
Culture Documents
QMS/ENG/D/002
2. Past performance of
Suppliers
Suppliers and Sub Supervisor
evaluation,
Contractors Within the
Awarding
time period 1.Supply 2.Check with
Site take over and latter,BOQ, During site
1 3. Brand, Gauge, mention in the incorrect the approved
Mobilization drawings & Client mobilization Suppliers
Material size, Quantity, awarding Material materials
specification performance
Price, Punctuality and as letter.
sheet,
per specifications
Material test
4.Sample test of material
reports,
Should be
Awarding clean enough
1.Check with Check list for
latter,BOQ, 1.Get the consultant’s During & After to carry out 1.Clering PM / Eng / SE /
2 Site Clearing the client land site clearing (CL
drawings & Client approvals the site clearing setting out other land TO
area 02)
specification without any
obstruction.
3.Removal of structures
BOQ, drawings & 2, Parallel /Perpendicular During work Dimensions of 1.error of Measuring Check list for
to existing building PM / Eng /
3 Setting out-General Client setting out measuring equipment setting out-
survey / TO
specification drawing. equipment Calibration General (CL 03)
3, Checking diagonals At end work
4, Cross checking
dimensions from two or
more directions
1.Get the consultant’s During & After Check list for
Setting out-Anchor
4 approvals for anchor bolt the Anchor Bolt setting out-
bolt placing Placing
material General (CL 03)
7. Thickness of welding
8. Checking diagonals
9. Protection of threaded
area
10. Check with the
existing floor level
Check list for
BOQ, drawings &
Excavation and Earth 1.Get the consultant’s SCA /4 Building 1.Using proper PM / Eng / SE / Excavation &
5 consultants During work 1.Earth claps
work. approvals works. shoring method TO Earth work (CL
specification,
05)
After each
2.Dimension excavation, Supervisor Level sheet
After backfilling.
Compaction test
3.Height
report
4.Levels
7.Method of shoring
8.Used the proper
equipment & machines
9.Quality of shoring
material
10.Quality of soil
11.Back filling layer
thickness
12.Sand binding layer
Sub contractor’s
4.Aggregates
agreements.
5.Polythene is
required/not
6.Leveling
7.Dimension
8.Water cement ratio
9.Mixing method &
mixing equipment
condition
10.Slum test
11.Curing
1.Making
BOQ, drawings & Check list for
Random Rubble 1.Get the consultant’s SCA /4 Building drawings PM / Eng / SE /
7 consultant At start work 1.Wall crack Random Rubble
masonry approvals works. marking TO
specification Masonary (CL 07)
expansion joint
4.Levels
5.Type of bond curing,
6.Type of wall
7.Size of rubble
8.Mortar ratio
9.Shoring method
10.Size of rubble
11.Finishing of surface
2.Evertime
BOQ, drawings & 1.wrong bar check with the Check list for
1.Get the consultant’s SCA /4 Building PM / Eng / Qs /
9 Reinforcement work consultant At start work spacing and drawings bar reinforcement
approvals works. TO
specification lap length spacing and lap work(CL 09)
length
2.Quality of bar (SLS
Bar schedule During work Supervisor bar schedule
certified)
10.Quality of work
2.Using proper
2.Levels & Dimension During work 2.Hony comb vibrating Supervisor Test report
method
3.Condition of
At end work Slum test
equipment
4. Aggregates Level sheet
5.Grade of concrete
6. Slum
7.Setting time,
8.Final cleaning &
Checking
9.Test Cube
10. Compaction method
11. Finishes(Honeycomb)
2.Insert of
3.Verticality During work Supervisor
Bonding mesh
4.Right angles
5.Alignment
6.Type of bond,
7. Curing.
8. Stiffener columns.
9. Mortar thickness
10.Openings to be
provided
11.Type of wall
12. Quality of material
13. Test report
14. Size of Brick/block
15. Mortar ratio
16. Size of wall
17. Quality of wall
1.idetify the
BOQ, drawings & Check list for
1.Get the consultant’s SCA /4 Building 1.Water leakage point PM / Eng / Qs /
14 Water proofing work consultant At start work water proofing
approvals works. leakage and re-water TO
specification work (CL13)
proofing
2.Compliance with Grantee
During work Supervisor
specification certificate
3.quality of materials At end of work
4.Quality of equipment
10. Correctness of
marking line & point
6. Thickness of painting
coats
7. Colour
8. Skill of painter
9. Covering area for paint
yard
10. painting check list
BOQ, drawings & 1.Get the consultant’s Check list for
Erecting of steel PM / Eng / Qs /
19 Consultant approvals for errection At start work Erecting steel
structure TO
specification method structure (CL19)
2. Correctness of anchor
Erecting manual During work Supervisor
bolts
3. Suitability of
machinery weight At end work
capacity & length
4. Skill of erector
5. Safety rule &
regulation
2. Preparation of the
During work Supervisor As built drawings
shop drawing
Electrical
3.Quality of materials At end work
certificate
4. Laying of conduits
8. Permanent fixing of
sun boxes and dist
boards after completion
of plastering
4. Plumbing work.
5. Fixing height
6. Colour
7. Type of standard
8. Dimension
BOQ, drawings &
1.Get the consultant’s SCA /4 Building 1.Ceiling sheet 1.Change bar PM / Eng / Qs / ceiling
24 Ceiling Work consultant At start work
approvals works. sagging spacing TO work(CL24)
specification
2.Type During work Supervisor
3. Quality of materials At end work
4. Thickness
5. Dimensions
6. Ceiling Level
7. Painting
8. Neatness
9. Opening for service
line
10.Color
BOQ, drawings
Client & 1.Get the consultant’s SCA /4 Building 1.Roof sheet PM / Eng / Qs / Check list for
25 Roof Work At start work 1.Roof leakage
consultant approvals works. replace TO roof work (CL25)
specification
2.Apply water
2.Type of roof During work Supervisor
proof chemical
3. Quality of materials At end work
5. Dimensions of roof
sheet / tile
6. Color of roof sheet /
tile
6. Roof angle/curvature
11. joints
13.Slopes
16. Alignment of pipe &
Valance board
15.Including paint &
primer
1.Dimolished
BOQ, drawings & Check list for
1.Get the consultant’s SCA /4 Building 1.Plaster cracking line PM / Eng / Qs /
27 Plastering work Client At start work Plastering Work
approvals works. cracking and insert mesh TO
specification (CL 27)
, re-plastering
2.macking
2.wrong
correct opening
2. Surface preparations During work opening for Supervisor
& -re-rendering
service line
wrong opening
Customer
2.Cleaning all area Section 3 satisfaction
report & letter
Condition of
3.Identified defects
Contract,
4.Get the consultants
Clause 55.1
approvals
5.Get the client
satisfaction
Project
Agreement, BOQ,
drawings &
consultant, Client
Handing over the After
specification, as Contract MD/PM/ENG/ Handing over
32 project & 1.Delivery date rectification of
built drawings, Document T O letter
Maintenance period list of defects.
guarantee
certificates,
warrantee cards
list of key