Professional Documents
Culture Documents
1
9/5/2020
Construction Programs
Prepared at various stages of projects for different
purposes.
Planning stage Type of program
Design Project master program
Tender Pre-tender program
Pre-contract Master program
Target program
Sub contractors’ program
Procurement program
Contract Stage program
Short-term program
As-built programme
2
9/5/2020
Levels of planning
Level Responsibility
Project planning Client/Project Manager
Pre-tender planning Tendering contractors
Pre-contract planning Main contractor
Contract planning Main contractor & Sub-
contractors
Project Planning
Starts when project master program is being prepared by
client team. This set out broad project framework.
Purpose:
To establish a realistic project master program
To identify key dates of critical project stages
To facilitate control of design & tendering process
To identify potential risks to progress
To facilitate arrangement of client cash funding
To establish realistic time period for construction
To monitor actual progress & take corrective actions
3
9/5/2020
4
9/5/2020
Pre-tender planning
Pre-tender program is prepared by contractor to aid
tendering process.
Purpose:
To establish realistic contract period on which tender
will be based on
To identify construction methods
To assess method related items which affect bid price
To aid to build up of contract preliminaries & plant
expenditure
To aid tendering process
5
9/5/2020
Pre-contract planning
Take place during the period between contract award &
commencement of work on site.
Contractor develops contract master program showing main
construction operations to be carried out.
Master Program is what the client team sees, but many
contractors produce an internal program for their own use to
save time & money, which is called a Target Program.
To help the contractor organize & manage site activities at
operational level, target program is developed in more details.
Most of the time bars in target program represent the main
work packages to be carried out by various sub contractors.
To ensure work packages start & finish on time, contractor can
produce a Procurement Program for each sub contractor.
6
9/5/2020
Contract planning
During contract stage, the master program is further
developed.
Done by main contractor to maintain control & ensure
that project is completed on time & within cost limits
established at tender stage.
A Stage Program can be prepared showing a part of the
master program in more detail.
Alternatively the contractor can produce a series of
Short-term Programs at weekly or fortnightly
intervals to plan day- to- day work in detail.
As-built Programs
As contract progresses, program change from its
original form due to delays, work disruptions due to
design changes & unforeseen events.
These changes are recorded in a revised program,
which can be constantly updated throughout the
project. These programs are referred as As-built
Programs.
7
9/5/2020
Planning a project
Requires a logical approach involving various steps.
1. Getting a feel for the project
2. Establishing key project data
3. Establishing key activities/events
4. Assessing activity durations
5. Establishing sequence
6. Deciding which programing technique to use
8
9/5/2020
9
9/5/2020
10
9/5/2020
5. Establishing sequence
11
9/5/2020
12
9/5/2020
Bar chart
Exercise 1:
For the project outlined in the following table,
prepare a bar chart. What is the total duration of
the project?
Task Follow task(s) Duration (weeks)
A Start 6
B Start 5
C Start 5
D A 3
E A,B 6
F C,D,E 1
13
9/5/2020
Exercise 2:
Task Task Description Duration Follows
(Days) task(s)
A Clear site 4 Start
B Obtain timber & other basic materials 3 Start
14
9/5/2020
15
9/5/2020
Limitations
Bar chart does not show dependencies clearly.
Linked bar charts use logical links to overcome this
problem, but these can be difficult to interpret in
projects with a large number of activities.
Complex inter-relationships cannot be clearly shown.
16