Date : 11/19/2021
TOTAL = A 1,727,791
CGST @ 9%
SGST @ 9%
IN WORDS: RUPEES TWENTY LAKHS THIRTY THREE THOUSAND THREE HUNDRED AND FIVE ONLY
Terms:
1. If bill not paid within the agreed due date the rate of interest will run @ 18% per annum.
2. The prices are fixed considering the input credit on Goods & Services.
3. For contractual deduction in the running bill as attached separate sheet.
Authorized Signatory
Project : Svamitva - HSR Mockup Building
NT -02
1 Water Load 862.50 - 10.00 8,625 10 8,625
2 Manual Excavation Cft 20.00 - 104 2,075 104 2,075
3 Drainage Cleaning LS 2,800.00 - 3 8,400 3 8,400
4 Structural Steel Aditional Cost Kg 125.00 - 4,500 562,488 4,500 562,488
Volvo 2 of 9 METEC
NT Items Mock up unit & Marketing office civil works
Volvo 3 of 9 METEC
MEASUREMENT SHEET
Total 35 6
MEASUREMENT SHEET - DEBRIES REMOVING
MEASUREMENT SHEET
Sl. No Description Unit Nos Length Breadth Depth Total Remarks
2 Fencing Removing
Floor Level Cum 1.00 35.00 13.60 1.45 690.20 JMR - 009
4 Soil Filling
Floor Level Cum 1.00 35.00 13.60 1.75 833.00 JMR - 012