Professional Documents
Culture Documents
18CBA08
PSG COLLEGE OF ARTS & SCIENCE
(AUTONOMOUS)
OPTIMIZATION TECHNIQUES
OR
b A department head has four tasks to be performed and three subordinates, the
subordinates differ in efficiency. the estimate of the time, each subordinate
would take to perform is given below in the matrix. How should he allocate
the tasks one to each man, so as to minimize the total man- hours?
Task Men
1 2 3
I 9 26 15
II 13 27 6
III 35 20 15
IV 18 30 20
Cont…
Page 3
18CBA08
Cont…
13 a Determine whether the following two person zero-sum games are strictly
determinable and fair. Give optimum strategies for each player in the case of
strictly determinable games.
Player B
Player A 5 0
0 2
OR
b For the game with the following payoff matrix, determine the optimum
strategies and the value of the game.
P2
P1 5 1
3 4
14 a Write the rules for network construction.
OR
b Draw a network diagram for the following data.
Activity: A B C D E F G H I J
Preceding None A A B A B, E C D, F G H, I
Activities:
15 a Find the optimal sequence that minimizes the total elapsed time required to
complete the following tasks on machine M1 and M2 in the order M1, M2.
Task : A B C D E F G H I
M1 : 2 5 4 9 6 8 7 5 4
M2 : 6 8 7 4 3 9 3 8 11
OR
b Explain sequencing problem.
SECTION -C (40 Marks)
Answer ALL questions
ALL questions carry EQUAL Marks (5 x 8 = 40)
OR
b A pharmaceutical Company is producing a single product and is selling it
through five agencies located it different cities. All of a sudden, there is a
demand for the product in another five cities not having any agency of the
Company. The Company is faced with the problem of deciding on how to
assign the existing agencies to dispatch the product to needy cities in such a
way that the traveling distance is minimized. The distance between the
surplus and deficit cities ( in km) is given in the following table.
Deficit cities
a b c d e
Surplus cities A 85 75 65 125 75
B 90 78 66 132 78
C 75 66 57 114 69
D 80 72 60 120 72
E 76 64 56 112 68
Determine the optimum assignment schedule.
B1 B2 B3 B4
A1 4 -2 3 -1
A2 -1 2 0 1
A3 -2 1 -2 0
OR
b Solve the following 2 X 2 game graphically.
Player B
Player A B1 B2 B3 B4
A1 2 1 0 -2
A2 1 0 3 2
Cont…
Page 5
18CBA08
Cont…
19 a The following table indicates the details of a project the duration are in days.
‘a’ refers to optimistic time ‘m’ refers to most likely time and ‘b’ refers to
pessimistic time duration.
Activity 1-2 1-3 1-4 2-4 2-5 3-4 4-5
a 2 3 4 8 6 2 2
m 4 4 5 9 8 3 5
b 5 6 6 11 12 4 7
(i) Draw the network
(ii) Find the critical path
(iii) Determine the expected standard deviation of the completion time.
OR
b Three time estimates (in moths) of all activities of a project are given as
below:
Time in months
Activity a m b
1-2 0.8 1.0 1.2
2-3 3.7 5.6 9.9
2-4 6.2 6.6 15.4
3-4 2.1 2.7 6.1
4-5 0.8 3.4 3.6
5-6 0.9 1.0 1.1
(i) Find the expected duration and standard deviation of each activity.
(ii) Construct the project network.
(iii) Determine the critical path, expected project length and expected variance
of the project length.
(iv) What is the probability that the project will be completed.
a) two months later than expected
b) not more than 3 months earlier than expected.
20 a In a factory there are six jobs to perform each of which should go through
two machines A and B in the order A, B. The processing timings (in hours)
for the jobs are given here. You are required to determine the sequence for
performing the jobs that would minimize the total elapsed time T. what is the
value of T?
Job J1 J2 J3 J4 J5 J6
Machine A 1 3 8 5 6 3
machine B 5 6 3 2 2 10
OR
b Solve the following sequencing problem when passing out is not allowed:
Machine
Item A B C D
I 15 5 4 15
II 12 2 10 12
III 16 3 5 16
IV 17 3 4 17
Z-Z-Z END