Professional Documents
Culture Documents
Matecconf
Matecconf
https://doi.org/10.1051/matecconf/201819202008
ICEAST 2018
Abstract. Construction project delays caused by contractors and suppliers are the top problems in
Thailand’s oil and gas industries. Recognizing this importance and their relationships between factors can
help reduce the risk of delays in construction projects. Therefore, this study set out to confirm factors and
inspect relationships between delay factors of contractors and suppliers. A 16 item questionnaire survey was
distributed to 134 managers, engineers, and supervisors in oil and gas platform construction projects in
Thailand. A confirmatory factor analysis (CFA) was performed by the use of Amos Version 20 software
program. The analysis results showed that delays caused by the contractors and suppliers had high
relationships, due to high regression weighs. The delays caused by the contractors included seven factors
which included poor site management and supervision (17%), lack of safety rules and regulations (16%),
poor communication and coordination with others (15%), poor procurement system management (15%),
defective components and mistakes during construction (14%), supplier payments lateness (13%), and poor
planning and scheduling (10%). The delays caused by the suppliers included six factors which included the
supply of unqualified and unskilled personnel (22%), supply of low efficiency equipment (20%), late
delivery of materials and equipment (20%), supply of low quality materials (16%), late supply of workers
(16%), and price escalation (5%).
*
Corresponding author: gomarnp@gmail.com
© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative Commons Attribution
License 4.0 (http://creativecommons.org/licenses/by/4.0/).
MATEC Web of Conferences 192, 02008 (2018) https://doi.org/10.1051/matecconf/201819202008
ICEAST 2018
Given both the financial importance caused by delays 2.3 The research instrument
and the fact that project delays can contribute to site
safety issues. However, the oil and gas platform To analyse the observed factors and inspect the
construction projects and general construction projects relationships between the latent factors, a 5-level, Likert
have a different contractual project delivery system. type agreement survey was used for data collection.
Therefore, researchers wanted to survey and study delay Part 1 of the questionnaire contained items related to
causes and factors in Thailand’s oil and gas platform the individual’s position level, experience and project
construction projects caused by contractors and value. Part 2 of the survey asked the individual to
suppliers. The results of this study can be applied in the evaluate the importance level of the cause of project
risk assessment analysis, and help with the prevention delay from contractors and suppliers on a Likert type
and reduction of project delays. scale from 1 to 5, with “1” indicating the importance
level of the item as very low, whereas a “5” rated the
importance level of the item as very high [10].
2 Research methods
2.4 Content and construct validity
2.1 The conceptual framework
From a review of the literature, Table 1 is used to present 2.4.1 Content validity
the primary reasons for construction project delays by
The questionnaire was discussed with three experts (the
contractors and suppliers.
experts are working as suppliers and contractors in the
Table 1. Cause of project delay from contractor and supplier offshore oil and gas industry with experiences more than
factors. fifteen years) to ensure content validity.
[1] [2] [3] [4] [5] [6] [7] [8] [9] 2.4.2 Construct validity
* * * * * * * * *
The Spearman Rank Correlation was used to ensure
C1** x x x x x x x construct validity of the questionnaire. The correlation
coefficient is a measure of the relationship between
C2** x x x x x x x factors from a -1 to a +1 [11]. In this study, the observed
factors were determined to be correlated.
C3** x x x x Cronbach’s alpha was also used to test the internal
consistency (reliability) of the questionnaire. The criteria
C4** x x x x x x x value of Cronbach’s alpha is suggested to be above 0.7
[12]. In this study, the Cronbach’s alpha value of 0.866
C5** x x x x is determined.
C6** x x x x x x x
3 Results
C7** x x x x
S1** x x
3.1 Respondent’s characteristics
A total of 134 questionnaires were returned from the
S2** x x x x x x respondents having experienced in oil and gas platform
construction projects in Gulf of Thailand. Of these 4.5%
S3** x x x x were managers, 67.2% were engineers, and 28.4% were
supervisors (Table 2). Experience level responses
S4** x x x x indicated that 41.8% had 5-10 years’ experience. Also,
36.6% worked in enterprises valued at over 1 billion
S5** x x x x
Thai baht ($31.4 million).
S6** x x x x x
3.2 Confirmatory factor analysis (CFA)
*References and **contractor (C) and supplier (S) factors
A CFA was used to analyze and confirm the sets of
observed factors and relationships between the latent
2.2 Panel of experts
factors by using the IBM® SPSS® Amos™ 20 software
This research was discussed with three experts to define program. Fit of the CFA model included the indices Chi-
and finalize factors from the literature review, from squares’s p-value, relative chi-square (χ2=df), goodness-
which, Table 1 was created as a summary of the related of-fit index (GFI), and the root mean square error of
factors. Additionally, the observed factors were finalized approximation (RMSEA). [13, 14] The criteria and index
into two classification groups related to contractors (C) values of the goodness-of-fit (GOF) are presented in
and suppliers (S). Table 3.
2
MATEC Web of Conferences 192, 02008 (2018) https://doi.org/10.1051/matecconf/201819202008
ICEAST 2018
Table 2. Demographic characteristic from suppliers, as the regression weight was 0.78.
Information suggests that this is due to the majority of
Position level Quantity Percent the suppliers and subcontractors have to work under the
main contractors due to financial capability and
Manager level 6 4.5% production capacity of the project’s requirements.
Therefore, any supplier mistakes and delays directly
Engineer level 90 67.2% affect contractors. These include items such as the
supply of low quality materials, low efficiency of
Supervisor level 38 28.4% equipment, and unqualified and unskilled personnel to
the contractor. Meanwhile, any delays caused from
Experience Quantity Percent contractors affect suppliers also. These include poor
supplier communication and coordination, and contractor
Less than 5 years 28 20.9% late payments to suppliers.
e8 S1 0.20
3.3 Data analysis
e9 S2 0.76
Table 3 shows the results of the goodness-of-fit (GOF)
criteria and recommended index values. e10 S3 0.64 Delays
Table 3. Goodness-of-fit criteria and indices. 0.86 caused by
e11 S4 supplier
0.64
CFA* e12 S5 0.79
3
MATEC Web of Conferences 192, 02008 (2018) https://doi.org/10.1051/matecconf/201819202008
ICEAST 2018
Table 4. Factor loading of delays causes by the contractor. communication and coordination with others, poor
procurement system management, defective components
Regression Factors and mistakes during construction, late payments to
Project delay causes suppliers, and poor planning and scheduling,
weights loading
respectively.
The delays caused by suppliers in construction
C1: Poor planning and
0.40 10% projects are the supply of unqualified and unskilled
scheduling
personnel, supply of low efficiency equipment, late
delivery of materials and equipment, supply of materials
C2: Poor communication and
0.60 15% of low quality, late supply of workers, respectively. In
coordination with others
addition, price escalation had a low impact on project
delay from supplier’s causes.
C3: Poor procurement system
0.58 15% Finally, this analysis points to the key factors that
management
have been confirmed and the relationship between the
C4: Poor site management and delays caused by the contractors and the suppliers.
0.67 17% These results may help to reduce and prevent delay risk
supervision
in ongoing and future oil and gas platform construction
C5: Lack of safety rules and projects. Furthermore, the project controller should take
0.63 16% a stronger role in evaluating contractors and suppliers in
regulations
the project’s prequalification phase and additionally
C6: Defective material and monitor projects during the execution phase.
mistakes during 0.57 14% The results of this study should be defined with a
construction
limitations as the conceptual framework was developed
based on the experts experience and an international
C7: Late payments to suppliers 0.51 13% literature review. Therefore, further inspection of the
project types is required.