Project: LAND BACKFILL SUPERVISION AND SOIL IMPROVEMENT

Location: Hun Sen Blvd, Phnom Penh, Cambodia

NON CONFORMANCE REPORT

Date: 22-Dec-21
From: Mr Renaud Groisy. email JEB
To: e-mail Contractor name
Subject: Low resource assignement and pace of work
Reference: R60-JEB-CON-NCR-001

Dear sir,
Reference is made by the report (Weekly Site Report for Land Backfill Supervision report 13-18.12.2021), sent on 21-Dec-2021.
The resource deployed to carry the work on the project is currently:
- Manpower
Formman = 1
Worker = 1 (for spray water)
Operator = 3
- Equipment
Backhoe = 1
Bulldozer = 1
Roller = 1
- The percentage of work progress since the Contractor has started the works is less than 5.0% average per week.
- The initial schedule or time frame for this phase of the work scope shall be completed at the end of March 2022.

Therefore, re-calculating the project duration according to the statement above, this duration would be extented 12 weeks as shown in figure 01
The completion date will be delayed to the 3rd week of June 2022.
Planning Progress (%) Contractor Progress Estimate (%)

100.00
95.00
90.00
85.00
80.00
75.00
Completed Percentage (%)

70.00
65.00
60.00
55.00
50.00
45.00
40.00
35.00
30.00
25.00
20.00
15.00
10.00
5.00
-
4th week - 3rd week - 1st week - 3rd week - 1st week - 3rd week - 1st week - 3rd week - 1st week - 3rd week - 1st week - 3rd week -
Dec 2021 Jan 2022 Feb 2022 Feb 2022 Mar 2022 Mar 2022 Apr 2022 Apr 2022 May 2022 May 2022 June 2022 June 2022

Completed Date

Figure 01: Comparision of Planning Progress and Contractor Progress Estimate


Supportive documents:

Corrective action:
- We recommend the Contractor to increase the resources on site to reach the xx% weekly work progress required on this
project.
Correspondence:

Prepared by: SES Vongsothea


Approved by: Mr. Renaud Groisy