Professional Documents
Culture Documents
a
Faculty of Electrical Engineering, Shahid Beheshti University, Evin, Tehran, Iran
b
Electrical and Computer Engineering Department, Southern Methodist University, 6251 Airline Rd, Dallas, TX 75205, United States
Keywords: Energy management featuring distribution feeder reconfiguration (DFR) and reactive power control, improves
Combined cooling, heating, and power (CCHP) the technical and economic efficiency of microgrids. The present work proposes a framework that leverages
Distribution feeder reconfiguration (DFR) scenarios to jointly manage the real and reactive power dispatches of the controllable generation resources as
Distributed generation (DG) well as the topology of the distribution feeder. Multiple operation measures are optimized including the op-
Energy storage system (ESS)
eration cost, real power loss, the voltage stability index (VSI), and the greenhouse gas emissions of the microgrid.
Hybrid Big Bang- Big Crunch (HBB-BC) algorithm is used to solve the formulated optimization problem. Non-
dispatchable and dispatchable distributed generation units (DGs), as well as the battery and thermal energy
storage systems (BESS and TESS), are considered as a hybrid energy system. Combined cooling, heating, and
power (CCHP) units are considered as dispatchable DGs and wind and solar photovoltaic generations are con-
sidered as non-dispatchable DGs. The efficiency of the proposed model and solution algorithm is investigated
using a 33-bus microgrid, and the simulation outcomes are discussed.
⁎
Corresponding author.
E-mail address: m_sedighi@sbu.ac.ir (M. Sedighizadeh).
https://doi.org/10.1016/j.est.2020.101301
Received 14 July 2019; Received in revised form 22 January 2020; Accepted 16 February 2020
2352-152X/ © 2020 Elsevier Ltd. All rights reserved.
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
2
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
by using a stochastic min-max problem, that minimizes the number of (CSA), to improve the power loss and voltage stability indices. In [15],
switching and the real electric power loss while stabilizes the bus vol- an expansion planning problem is formulated considering the network
tages . In [13], an alternative multi-objective optimization problem is reconfiguration and energy management to minimize the investment
proposed for optimal DFR and energy management, which maximizes and operation costs of DGs as well as demand-side management costs.
the DG owner's profit, and minimizes the cost of the distribution net- In [16], the dedicated search teaching-learning based optimization
work operator. In [14], a multi-objective optimization problem for DFR (DSTLBO) algorithm is proposed for allocating the distributed genera-
and energy management is solved using a cuckoo search algorithm tion capacity to minimize the energy loss and to improve the voltage
3
S.S. Fazlhashemi, et al.
Table 1
Recent research works addressing DFR and energy management in microgrids.
Reference No. Type of formulation Objective function Uncertainty Solution method Reactive power DER
control
Demand Generation Mathematical Heuristic
[1] Deterministic Real power loss in the network, annual operation costs – – – Strength Pareto Evolutionary Algorithm – WT, PV
and emissions 2 (SPEA2)
[2] Deterministic Operation cost, real power loss in the network, emission, and – – – HBB-BC – WT, PV, MT, FC
voltage stability index
[3] Stochastic Operation cost, real power loss in the network, emission, and ✓ – – Pareto based HBB-BC – WT, PV, MT, FC
voltage stability index
[7] Stochastic Operation cost, real power loss in the network, reliability, and – ✓ MISOCP (GAMS) – – WT, PV, BM, MT, SH, FC,
number of switching GT, Electric Vehicle
[8] Stochastic Benefit of MGO ✓ ✓ – PSO – WT, MT, BESS
[9] Deterministic Cost of energy – – – PSO – WT, PV
4
[10] Stochastic Operation cost, resiliency, and reliability ✓ ✓ – EMA – WT, PV, CHP, BESS
[11] Deterministic Phase balancing, real power loss in the network, improving the – – – Bacterial Foraging with Spiral Dynamic – General form of DER
voltage profile, and operation cost algorithm
[12] Stochastic Real power loss in the network, voltage stability, and the ✓ – – Knee point driven evolutionary – SH
number of switching algorithm
[13] Stochastic DG owner's profit and the distribution company's costs ✓ ✓ MINLP (GAMS) – – WT
[14] Deterministic Real power loss in the network and voltage stability index – – – CSA – General form of DER
[15] Deterministic Operation cost and demand side cost – – – Differential evolution algorithm – General form of DER
[16] Deterministic energy loss and voltage profile – – – DSTLBO ✓ General form of DER
[17] Deterministic Costs of line upgrades, energy loss, switching operations, – – - Non-dominated sorting genetic – General form of DER
emission, and captial, operation and maintenance cost of DGs algorithm (NDSGA)–
[18] Deterministic Real power loss and voltage profile in the network – – – Harmony Search Algorithm (HSA) – General form of DER
[19] Deterministic Real power loss and voltage profile in the network – – – integrating PSO and ABC algorithm ✓ General form of DER
with HSA
[20] Deterministic Real power loss and voltage profile in the network – – – bacterial foraging optimization (BFO) ✓ General form of DER
[21] Deterministic Operation cost, power quality and reliability – – – NSGA-II ✓ General form of DER
Current paper Stochastic Operation cost, real power loss in the network, emission, and ✓ ✓ – HBB-BC ✓ WT, PV, CCHP, TESS, BESS
voltage stability index
Journal of Energy Storage 29 (2020) 101301
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
5
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
f1 (t , s ) = Ploss = R ( k ) × I (k , t , s ) 2 t T, s S
k NBR (1)
i NHES
CTESS (i, t , s ) + i NHES
CBESS (i, t , s ) t T, s S
6
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
CPV (i , t , s ) = aPV (i) + bPV (i) × PPV (i , t , s ) t T, s S, i NHES (7) CBESS (i, t , s ) = aBESS (i) + bBESS (i ) × PBESS (i, t , s )
For CCHPs, the cost of energy generation is given by [24]: + grid (t ) × PBESS (i , t , s ) t T, s S, i NHES
(14)
PCCHP (i , t , s ) Hab (i , t , s )
CCCHP (i, t , s ) = aCCHP (i ) + bCCHP (i) × + For TESS:
ele the
CCB (l, t , s ) = aCB (l) + bCB (l) × QCB (l, t , s ) t T, s S, • Minimization of the total emission
l NCB (11)
The total emission of the upstream grid and the CCHP units in HES
where for the generating electrical and thermal energy is formulated as
7
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
+
Hab (i , t , s )
× CFDG (i) × ER (i ) t T, s S
• Branch current limit
the (19)
In order to ensure that the currents in distribution cables do not
exceed the limits, the following constraint is considered [2]:
2.2.2. Aggregating objective functions by a fuzzy operator I (k , t , s ) Ikmax t T, s S, k NBR (25)
Since the formulated objective functions (1), (3), (4), (19) have
different characteristics and scales, they should properly be scaled in
order to find a feasible optimal solution. This paper uses a Fuzzy op- • Bus voltage limits
erator for such scaling as shown below [31,32]:
The voltage at each bus should be within the minimum and max-
1 fp (t , s ) < fpmin imum limits as shown below [2]:
f pmax f p (t , s ) Vmin V (z , t , s ) Vmax t T, s S, z Nbus (26)
a p (t , s ) = fpmin f p (t , s ) fpmax t T, s S,
f pmax f pmin
0 f p (t , s ) fpmax
• Generation limits for CCHPs
p {1, 2, 3, 4} (20)
The produced electrical and thermal power by CCHPs in HES should
To combine the scaled objective functions, the “max geometric satisfy the following limits [2,22]:
mean” operator is used as shown below [31,32]: min
PCCHP (i ) PCCHP (i , t , s ) max
PCCHP (i ) t T, s S, i NHES (27)
µ (t , s ) = [ 1 (t , s ) × 2 (t , s) × 3 (t , s) × 4 (t , s )]1/4 t T, s S
min max
HCCHP (i ) HCCHP (i , t , s ) HCCHP (i ) t T, s S, i NHES
(21)
(28)
The overall fitness function is written as:
Max F = µ (t , s )
(22)
• Auxiliary boiler operation limits
s S t T
The thermal power generated by auxiliary boilers of HES should be
within the minimum and maximum limits as shown below [22]:
2.2.3. Network and generation units’ constraints
The following constraints should be considered for the proposed min
HAB (i ) HAB (i, t , s ) max
HAB (i ) t T, s S, i NHES (29)
multi-objective optimization problem.
• Reactive power limits for the capacitor banks
• Power flow equations
The output reactive power of capacitor banks should meet the fol-
Real and reactive electrical power balance at each bus of microgrid lowing conditions [34]:
should satify the following conditions [27]:
min
QCB (l) QCB (l, t , s ) max
QCB (l ) t T, s S, l NCB (30)
PG (z , t , s ) PD (z , t , s ) = V (z , t , s ) × V (r , t , s ) × Y ( z , j )
r Nbus
× cos( (z , t , s ) (r , t , s ) (z, r , t , s ))
• BESS operation constraints
t T, s S, z Nbus for z r (23) The following constraints are considered for the operation of BESS
in HES [22,35]:
QG (z, t , s ) QD (z, t , s ) = V (z , t , s ) × V (r , t , s ) × Y (z , r ) ch ch max Ch
r Nbus
0 PBESS (i , t , s ) PBESS (i) × U BESS (i , t , s ) t T, s S,
•a (35)
min max
k,z = 0 if branch k is not connected to node z EBESS (i ) EBESS (i , t , s ) EBESS (i ) t T, s S, i NHES
•a k,z= 1 if branch k is directed away from node z
•a k,z = −1 if branch k is directed toward node z • TESS operation constraints
One node is taken into account as the reference and associated The following constraints are considered for the operation of TESS
8
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
in HES [22,35]:
ch ch max Ch
0 HTESS (i, t , s ) HTESS (i) × UTESS (i , t , s ) t T, s S, i NHES
(36)
dis dis max dis
0 HTESS (i , t , s ) HTESS (i) × UTESS (i , t , s ) t T, s S, i NHES
(37)
dis
UTESS Ch
(i, t , s ) + UTESS (i , t , s ) 1 t T, s S, i NHES (38)
dis dis
ETESS (i, t , s ) = ETESS (i, t 1, s ) HTESS (i , t , s ) × TESS
ch
HTESS (i , t , s) Fig. 9. The forecasted hourly electrical demand of microgrid [7].
t T , t > 1, s S, i NHES
(39)
ch
TESS
3. Uncertainty in generation and demand The mean and standard deviation of the solar irradiance are cal-
culated using the historical data received from the meteorology stations
This section describes the models used to represent the uncertainty [37,38].
in the wind and solar PV generation and the electricity demand in the It is assumed that the PV units are in the location where μs and σs of
microgrid. the solar irradiation in a day-ahead operation horizon, are similar to
9
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 10. The participation factor of demand on distribution network buses [7].
Table 2
Parameters of HES and capacitor bank*.
CCHP [22] Auxiliary Boiler [22] Wind Generation [37]
min
PDG 0 min
HAB 0 DG
CostCapital 1500
D
max
PDGD 633 max
HAB 350 DG
PCapacity 400
min
HDG 0 ηthe 0.8 Gr 0.136
D
max
HDG 700 BESS [49] CFDG 0.2
D
ρgas 0.157 Parameter Value TLife 20
βgas 0.09043 BESS
CostCapital 1775 O& M
CostDG 0.05
ND
ηele 0.3 BESS
PCapacity 1200 Prated 400
DG
CostCapital 3674 ch max
PBESS 200 vr 12
DG
PCapacity 633 dis max
PBESS 200 vco 25
Gr 0.136 CFBESS 0.25 vct 3.5
Fig. 11. The thermal and cooling demand [22]. CFDG 0.2 min
EBESS 120 PV [37]
TLife 10 max
EBESS 1200 Parameter Value
O& M
CostDG 0.0039 ch 0.85 DG
CostCapital 6675
D BESS
ηEH 0.9 dis 0.95 DG
PCapacity 400
BESS
ER 14.447 TLife 25 Gr 0.136
TESS [49] Gr 0.136 CFDG 0.25
Parameter Value O& M
CostBESS 0.05 TLife 20
TESS
CostCapital 1800 Capacitor Bank [50] O& M
CostDG 0.05
ND
TESS
PCapacity 1200 Parameter Value ηpv 18.6
ch 0.95 CB
CostCapital 9 Spv 40
TESS
dis 0.95 CB
PCapacity 400 Grid [3]
TESS
min
ETESS 120 Gr 0.136 Vmin 0.95
max
ETESS 1200 CFCB 0.2 Vmax 1.05
CFTESS 0.25 TLife 25 ERgrid 5.46
Fig. 12. The day-ahead electricity price for microgrid [22].
ch max
PTESS 200 O& M
CostCB 0.05
dis max
PTESS 200
those in Fig. 3. TLife 25
The output power of the PV units is determined by incorporating the O& M
CostTESS 0.05
efficiency of the PV cell, the area of the cell, and the available solar Gr 0.136
irradiance. The output power of the PV unit is computed as follows
[36,37]:
⁎
Units of quantities have been expressed in nomenclature.
(46)
Ppv (si ) = pv × S pv × si
Table 3
The initial parameters selected for HBB-BC algorithm.
10
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Table 4
The network reconfiguration decisions and values of objective functions at each hour for Case 1.
Hour The expected values considering all scenarios The outcomes for the most probable scenario
Emission (Ton) Cost ($) VSI Power Loss (kW) Open Switches Emission (Ton) Cost ($) VSI Power Loss (kW) Open Switches
1 2.210 142.4 0.905 22.8 S7,S10,S34,S28,S36 2.210 160.6 0.901 24.1 S7,S9,S14,S37,S32
2 2.251 108.2 0.883 34.6 S7,S21,S11,S5,S36 2.250 127.1 0.890 32.3 S33,S9,S8,S28,S32
3 2.185 95.9 0.878 40.5 S6,S9,S34,S37,S36 2.178 111.9 0.896 27.2 S7,S9,S14,S37,S32
4 2.186 84.8 0.876 41.17 S6,S9,S14,S37,S32 2.194 101.3 0.858 54.7 S33,S9,S8,S28,S32
5 2.211 88.2 0.850 65.61 S33,S9,S34,S28,S32 2.206 104.8 0.861 56.2 S7,S9,S14,S37,S32
6 2.271 135.6 0.832 79.70 S7,S11,S13,S26,S32 2.277 154.6 0.825 90.8 S7,S9,S14,S37,S32
7 2.537 153.2 0.824 93.06 S7,S9,S14,S28,S32 2.538 182.2 0.821 95.4 S7,S9,S14,S37,S32
8 2.590 249.6 0.791 120.3 S7,S9,S34,S37,S32 2.481 278.5 0.814 104.2 S7,S9,S14,S37,S32
9 2.625 830.0 0.797 125.2 S7,S9,S13,S28,S32 2.631 863.6 0.790 134.7 S7,S9,S14,S37,S32
10 2.675 2241. 0.699 201.7 S33,S35,S34,S37,S36 2.653 2255 0.771 163.1 S7,S9,S14,S37,S32
11 2.731 2297 0.646 294.1 S33,S35,S34,S37,S36 2.679 2277 0.748 203.1 S7,S9,S14,S37,S32
12 2.762 2321 0.621 345.6 S33,S35,S34,S37,S36 2.684 2274 0.738 207.7 S33,S9,S8,S28,S32
13 2.705 883.2 0.696 277.6 S7,S33,S14,S28,S36 2.695 910.8 0.718 260.1 S7,S9,S14,S37,S32
14 2.718 2342 0.631 323.7 S33,S35,S34,S37,S36 2.667 2321 0.724 233.6 S33,S9,S8,S28,S32
15 2.588 1124 0.800 110.5 S7,S13,S11,S37,S32 2.594 1157 0.802 119.6 S7,S9,S14,S37,S32
16 2.564 1086 0.835 77.8 S6,S9,S14,S28,S36 2.565 1117 0.832 78.8 S33,S9,S8,S28,S32
17 2.552 352.5 0.855 60.8 S6,S9,S13,S28,S36 2.551 382.6 0.852 60.1 S33,S9,S8,S28,S32
18 2.563 250.6 0.829 80.2 S33,S8,S11,S28,S36 2.559 280.3 0.842 73.1 S33,S9,S34,S28,S32
19 2.568 227 0.82 96.9 S7,S11,S14,S28,S32 2.573 257.4 0.813 104.9 S7,S9,S14,S37,S32
20 2.614 246 0.78 136.8 S7,S8,S13,S28,S36 2.615 276.9 0.789 137.4 S7,S9,S14,S37,S32
21 2.617 697 0.79 119.7 S7,S9,S14,S26,S32 2.628 732.1 0.787 139.4 S7,S9,S14,S37,S32
22 2.594 291.6 0.84 70.4 S7,S11,S34,S27,S32 2.595 323.7 0.838 77.1 S7,S9,S14,S37,S32
23 2.237 194.3 0.88 35.6 S33,S11,S14,S27,S32 2.240 213.0 0.880 40.9 S7,S9,S14,S37,S32
24 2.197 165.1 0.91 21.6 S7,S11,S14,S27,S32 2.197 182.1 0.908 20.8 S7,S9,S14,S37,S32
00 v vct
(v vct )
Prated × vct v vr
Pw (v ) = (v vct )
Prated vr v vco
0 vc o v (48)
11
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
12
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Table 5
The reactive power dispatch of capacitor banks and values of objective functions at each hour for Case 2.
Hour Expected value of scenarios The outcomes for the most probable scenario
Emission (kg) Cost ($) VSI Power Loss Reactive power generated by Emission (kg) Cost ($) VSI Power Loss Reactive power generated by CBs
(kW) CBs (kVAr) (kW) (kVAr)
1 2.127 178.30 0.900 23.17 372,400,400 2.065 162.66 0.880 27.97 0,57,346
2 2.168 135.50 0.894 26.78 400,400,400 2.232 132.72 0.881 35.09 400,400,400
3 2.119 133.93 0.873 37.72 400,400,400 2.260 127.49 0.886 32.15 400,400,400
4 1.924 115.35 0.876 33.76 400,400,400 2.072 107.06 0.854 49.57 400,400,400
5 1.807 101.99 0.853 47.47 400,400,400 2.016 98.51 0.851 50.59 400,400,400
6 1.974 140.17 0.835 62.51 400,400,400 2.165 133.59 0.806 93.71 400,400,400
7 2.074 135.91 0.826 66.69 400,400,400 2.123 118.94 0.804 94.03 400,400,400
8 2.326 266.44 0.823 67.88 383,400,392 2.053 194.59 0.801 95.11 400,400,400
9 2.428 614.81 0.774 110.60 392,0,400 2.579 649.42 0.816 67.26 400,400,400
10 2.512 1071.4 0.825 62.52 165,279,400 2.551 1204.2 0.817 70.30 400,400,400
11 2.557 1009.1 0.750 149.85 400,129,400 2.257 900.56 0.811 92.95 400,60,400
12 2.499 912.65 0.741 176.11 165,0,400 2.406 1006.2 0.810 84.56 400,190,400
13 2.397 508.74 0.726 178.70 332,204,400 2.326 545.45 0.779 106.88 400,400,400
14 2.261 967.57 0.790 99.76 400,0,400 2.221 1113.3 0.795 90.23 400,400,400
15 1.973 758.50 0.788 92.15 400,350,400 2.057 888.78 0.812 74.31 400,400,400
16 2.008 945.58 0.841 55.91 400,400,400 1.598 826.14 0.852 43.98 400,400,400
17 2.064 327.46 0.857 45.39 400,400,400 2.236 366.11 0.841 62.80 400,400,400
18 2.148 231.40 0.832 65.33 400,400,400 1.904 218.77 0.842 54.37 400,400,400
19 1.994 166.12 0.830 60.50 400,400,400 1.612 116.10 0.828 59.57 400,400,400
20 2.531 284.02 0.825 60.39 190,325,400 2.463 286.66 0.830 59.28 400,400,400
21 2.534 484.11 0.788 92.13 400,400,400 2.605 520.13 0.825 62.07 400,400,400
22 2.395 264.84 0.844 56.56 400,400,400 2.314 265.15 0.824 74.60 400,400,400
23 2.212 239.63 0.871 38.14 200,400,400 2.255 226.25 0.862 47.63 400,400,400
24 2.163 206.03 0.897 23.33 400,390,0 2.320 202.25 0.881 28.46 0,290,300
Fig. 17. The output electrical power of BESSs (a: expected value of scenarios, b: in the most probable scenario).
In this optimization problem, the decision variables include the Y (t ) = [Tie ( , t ), Pgrid (t ), PCCHP (i, t ), Hab (j, t ), PBESS (i , t ),
hourly status of open switches in each loop (integer variables), the
HTESS (i, t ), QCB (l, t )]
output (electrical and thermal) power of CCHPs, the output thermal
power of auxiliary boilers, the exchanged power with upstream grid,
NTie , i NHES , l NCB , t T (57)
the exchanged power with BESSs and TESSs, and the reactive power It is worth noting that in the proposed optimization model, four
generated by capacitor banks at each hour (continuous variables). objective functions are presented as (1), (3), (4), and (19) which are
Consequently, the vector of decision variables is as follows: aggregated as (21) subjected to constraints (23) -(42) and decision
variables (57).
13
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 18. The SoC of BESSs (a: expected value of scenarios, b: in the most probable scenario).
Fig. 19. The output thermal power of TESSs (a: expected value of scenarios, b: in the most probable scenario).
The steps taken in the utilized algorithm are given below: Step 3: Check the connectivity and radiality constraint.
Step 4: Carry out load flow analysis using the direct approach
Step 1: Define the input data including the network and algorithm proposed in [47] and calculate the value of the fitness function.
data. The network data includes the base distribution network Step 5: Calculate the "best" and "global" positions of the each par-
configuration, bus and branch data, the fundamental loops and their ticle as well as the center of mass using (54).
switches. The algorithm data consists of the number of population, Step 6: Update the candidates using (55) and apply the mutation
parameters pertaining to limit the size of the search space, ad- operation (56).
justable parameters, mutation probability (Pm), and the number of Step 7: Repeat Steps 3–6 until the termination criterion is met. Here,
iterations. the number of iterations is considered as the stopping criterion.
Step 2: Randomly generating the initial population.
14
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 20. The energy stored in TESSs (a: expected value of scenarios, b: in the most probable scenario).
Fig. 21. The output electrical power of CCHPs (a: expected value of scenarios, b: most probable scenario).
Fig. 7 illustrates the flowchart of the proposed algorithm. objective optimization problem is applied to a microgrid with 33 buses
[48]. The voltage level and nominal real and reactive power con-
5. Simulation results sumptions are 12.66 kV, 3715 kW, and 2300 kVAr respectively. The
numbers of ties (normally open) and sectionalizing (normally closed)
The presented MOHBB-BC algorithm to solve the formulated multi- switches in this radial distribution network are 5 and 32, respectively
15
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 22. The output thermal power of CCHPs (a: expected value of scenarios, b: in the most probable scenario).
Fig. 23. The bus voltages (a: expected value of scenarios, b: in the most probable scenario).
16
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Table 6
The network reconfiguration decisions, reactive power dispatch of capacitor banks and values of objective functions at each hour for Case 3.
Hour The expected value of scenarios The outcomes for the most probable scenario
Emission (kg) Cost ($) VSI Power Loss Open Switches and Reactive power Emission (kg) Cost ($) VSI Power Loss Open Switches and Reactive power
(kW) generated by CBs(kVAr) (kW) generated by CBs (kVAr)
1 2.052 164.22 0.908 20.28 S7, S10, S34, S28, S36, 1.984 156.12 0.923 16.55 S6, S10, S34, S37, S32
78,39,105 ,320,320,400
2 2.167 132.90 0.905 24.99 S7, S35, S10, S37, S32, 2.222 131.61 0.903 27.47 S6, S8, S9, S37, S36
380,190,110 ,300,325,400
3 2.127 131.89 0.891 34.01 S7, S21, S13, S28, S36, 2.255 126.11 0.901 23.71 S7, S9, S14, S37, S32
40,220,380 ,350,206,400
4 1.954 114.56 0.882 36.42 S7, S35, S10, S25, S32, 2.102 108.21 0.818 40.42 S7, S11, S34, S37, S32
220,120,270 ,260,310,400
5 1.963 109.97 0.862 54.24 S7, S35, S13, S27, S32, 2.112 106.29 0.879 49.85 S7, S8, S9, S28, S32
260,175,340 ,400,400,400
6 2.064 146.39 0.840 69.81 S6, S9, S34, S25, S36, 2.272 145.23 0.847 82.51 S7, S9, S14, S28, S32,380,215,400
125,45,388
7 1.970 110.17 0.842 68.01 S7, S8, S13, S37, S32, 2.253 123.33 0.852 76.73 S6, S9, S14, S37, S32
328,394,295 ,400,400,400
8 1.970 173.55 0.839 76.17 S7, S9, S14, S28, S31, 2.041 192.96 0.847 73.94 S6, S9, S14, S37, S32
320,195,200 ,400,400,400
9 2.835 515.22 0.832 58.64 S3, S11, S13, S38, S8, 2.856 702.98 0.862 73.47 S6, S10, S14, S4, S34
214,231,382 ,350,200,400
10 2.737 846.55 0.866 63.44 S7, S13, S35, S37, S31 2.667 1104.4 0.883 53.99 S33, S12, S9, S4, S8
,0,150,115 ,400,400,400
11 2.696 804.11 0.873 67.71 S7, S8, S11, S37, S31 2.355 796.06 0.897 60.54 S33, S35, S10, S4, S31
,400,125,400 ,400,400,400
12 2.616 722.91 0.829 105.78 S19, S21, S13, S26, 2.478 914.38 0.891 57.29 S33, S10, S13, S4, S30
S30,125,340,318 ,400,400,400
13 2.857 569.63 0.823 111.61 S33, S9, S13, S27, S30 2.468 652.25 0.817 112.65 S3, S10, S13, S28, S31
,118,250,180 ,400,400,400
14 2.611 756.57 0.812 107.81 S33, S35, S13, S37, S30,400,0,25 2.442 967.97 0.880 64.53 S7, S11, S12, S37, S30
,262,400,400
15 2.607 519.61 0.895 36.41 S20, S33, S10, S37, 2.470 620.46 0.905 41.56 S6, S11, S12, S4, S31
S31,290,375,320 ,250,350,400
16 2.723 582.7 0.892 48.99 S7, S9, S13, S24, S34 2.226 530.73 0.920 21.51 S6, S35, S9, S37, S30
,52,165,80 ,150,400,400
17 2.993 389.53 0.894 30.51 S7, S33, S10, S28, S31 2.514 385.94 0.882 37.18 S7, S10, S14, S37, S32
,0,400,0 ,40,50,400
18 2.872 314.89 0.875 44.27 S7, S11, S34, S27, S31 1.906 217.91 0.877 43.88 S6, S10, S14, S37, S32
,0,132,185 ,364,340,400
19 2.201 182.30 0.819 91.56 S7, S11, S35, S25, S32 1.848 156.83 0.842 74.22 S6, S34, S9, S4, S32
,200,137,145 ,400,400,400
20 2.983 287.59 0.880 73.40 S6, S9, S13, S3, S34 1.977 167.12 0.827 88.34 S7, S33, S34, S37, S32
,306,230,125 ,190,350,400
21 2.870 417.66 0.887 58.05 S33, S10, S14, S28, 2.722 480.84 0.888 47.91 S33, S13, S9, S7, S37
S34,58,190,330 ,175,390,400
22 3.053 304.23 0.896 31.82 S33, S35, S12, S26, 2.308 244.94 0.873 48.06 S6, S11, S34, S37, S32
S34,350,400,230 ,400,320,400
23 2.091 209.02 0.898 29.43 S7, S11, S35, S28, S32 2.133 203.41 0.819 33.18 S7, S14, S9, S37, S32
,370,100,195 ,0,0,400
24 2.046 186.61 0.913 17.91 S7, S9, S14, S37, S32 2.202 183.14 0.912 21.29 S7, S14, S9, S28, S32
,62,0,145 ,0,0,0
[2]. The single-line diagram of the system is shown in Fig. 8. Two HES algorithm are presented in Table 3. Due to the utilization of the random
that were introduced in Section 2, are installed on buses 4, and 14. operators in (54) and (55), the outcome of the HBBC optimization al-
Three capacitor banks are considered at buses 7, 13, and 29 for con- gorithm is not fixed. Therefore, the simulation runs for 30 times to
trolling the reactive power and adjusting the voltage profile. The de- obtain a set of solutions. The average value of the procured solutions is
mand profile of the microgrid is given in Figs. 9 and 10. Fig. 9 displays considered as the final solution, i.e., ground truth, for the algorithm.
the maximum electrical demand at each bus and Fig. 10 illustrates the Three different cases are considered as follows:
participation factor of the maximum electrical demand at each hour for
each bus. Fig. 9 shows the mean of the hourly forecasted electrical Case 1: Energy management with DFR without capacitor banks
demand which are further represented by the normal distribution considering HESs equipped with an auxiliary boiler and TESS.
function. The standard deviation of electrical demand, σd is 1%. It is Case 2: Energy management without DFR with capacitor banks
assumed that the thermal and cooling demands are located at buses 4, considering HESs equipped with all of the components.
and 14. Fig. 11 shows the thermal and cooling demand profiles. The Case 3: Energy management with DFR and capacitor banks con-
day-ahead forecasted electricity price for microgrid is shown in Fig. 12. sidering HESs equipped with all of the components.
The simulation is performed using the MATLAB (R2014b) on a PC with
Intel Core i7, 2.5 GHz CPU with 12GB of RAM. The simulation results in the above-mentioned case studies are
The characteristics of the HES and capacitor banks are represented compared to the base case. The base case is similar to Case 1, without
in Table 2. DFR.
The initial parameters selected for the HBB-BC optimization
17
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 24. The output electrical power of BESSs (a: expected value of scenarios, b: in most probable scenario).
Fig. 25. The stored energy in BESSs (a: expected value of scenarios, b: in most probable scenario).
5.1. Case 1 – energy management with DFR without capacitor banks auxiliary boilers and TESSs, while the electrical demand is supplied by
considering HESs equipped with an auxiliary boiler and TESS the upstream main grid. It is shown in Table 4 that for the most
probable scenario, the maximum real power loss and minimum VSI
Table 4 lists the DFR decisions and the values of the objective occurred at hour 13:00. Furthermore, in most probable scenario, the
function at each hour. Given the uncertainties in the renewable gen- emission will significantly increase at hour 13:00. Similar observations
eration and demand, the simulation results represent the most probable were made at hour 12:00 for the expected emission, VSI and real power
scenario and the expected outcomes of the simulation. In this case, only loss due to the increased heating, cooling, and electrical demand.
auxiliary boiler and TESS in the HES are considered, and other assets The operation cost reached its maximum at hour 14:00 due to the
(i.e., PGU, WT, PV, and BESS) are not taken into account. Therefore, the high electricity price (Fig. 12), and charging the TESSs by auxiliary
cooling and heating demands on buses 4 and 14 are supplied by the boilers at this hour. Figs. 13 and 14 show the output thermal power of
18
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 26. The output thermal power of TESSs (a: expected value of scenarios, b: in most probable scenario).
Fig. 27. The stored energy in TESSs (a: expected value of scenarios, b: most probable scenario).
auxiliary boilers and TESSs, in both scenarios, respectively. Since the cooling demands. Fig. 14 shows the charging/discharging modes of
uncertainty in thermal demand is not modeled and distribution gen- TESS. It is shown that TESSs discharge when the thermal and cooling
eration is not rconsidered in this case, Figs. 13 and 14 are valid for both demands reach their peak level and charge in off-peak hours. Similar
scenarios. It is seen from Fig. 13 that the auxiliary boilers operate at results are observed in Table 4 for the most probable scenario.
nearly 70% of their capacity from 7:00 to 22:00 to meet the heating and Fig. 15 shows that the stored energy in TESSs remains within the
19
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 28. The output electrical power of CCHPs (a: expected value of scenarios, b: most probable scenario).
power loss and minimum VSI occurred at hour 13:00, when the elec-
trical demand is at its peak. As the electrical demand increases, the
generation of CCHPs increases as shown in Fig. 21. Here, the excess
thermal energy will be stored in TESSs as shown in Fig. 19. The gen-
erated thermal power by CCHP units is shown in Fig. 22. It is worth
noting that as CCHPs meet the thermal and cooling demand, the aux-
iliary boilers do not operate in this case. Fig. 23 depicts the voltage
profiles for all buses in maximum and minimum electrical demand. As
shown in this figure only a few buses will suffer form undervoltage
during peak hours. It is concluded that DGs reduce the electrical de-
mand supplied by the upstream grid and therefore, the voltage drop is
less than that in Case 1. As shown in Table 5, the maximum operation
cost occurs at hour 10:00 due to high electricity prices, as well as large
Fig. 29. The output thermal power of auxiliary boilers (expected value of electrical, heating, and cooling demands. Figs. 17, and 19 show the
scenarios). operation schedule of BESS and TESSs respectively. Here, the maximum
emission occurs at hour 11:00 when the CCHPs provide maximum
acceptable range. As the electric distributed generation resources were thermal energy to satisfy the cooling and heating demands. Similar
not used in the microgrid, the voltage drop along the feeder could be outcomes are observed for the most probable scenario in Table 5.
significant. Therefore, to solve the proposed optimization model ig-
noring the distributed electricity resources, it is assumed that the lower
5.3. Case 3 – energy management with DFR and capacitor banks
range in (26) is set to 0.9 (p.u). Fig. 16 shows the voltage profile in
considering HESs equipped with all of the components
maximium and minimum electrical demand. It is seen that the voltage
of buses at the end of the feeders is less than the lower limits during
This case considers the DFR and generation scheduling of DGs and
peak hours.
capacitor banks simultaneously. Table 6 shows the reactive power of
capacitor banks, the status of switches, the power loss, emission, vol-
5.2. Case 2 – energy management without DFR with capacitor banks tage stability index and the operation cost at each hour. Figs. 24, and 25
considering HESs equipped with all of the components show the output electrical power and the energy stored in BESSs at each
hour, respectively. Figs. 26, and 27 illustrate the output thermal power
Table 5 presents the reactive power supply by capacitor banks and and the stored energy in TESSs at each hour, respectively. Similar to the
the power loss, voltage stability index, emission, and operation cost at previous cases, the maximum real power loss and minimum VSI occur
each hour. Since network reconfiguration is not considered in this case, at hour 13:00, when the electrical demand reaches its peak. Similar to
the states of tie switches are not changed as shown in Fig. 7. Figs. 17, Case 2, when the electrical demand increases, the generation of CCHPs
and 18 show the output electrical power and stored energy in BESSs at increases as shown in Fig. 28 to meet electrical demand. Therefore, the
each hour, respectively. For both scenarios, Figs. 19, and 20 illustrate thermal power generated by auxiliary boilers (shown in Fig. 29), and
the output thermal power and stored energy in TESSs at each hour, CCHPs (shown in Fig. 30) satisfy the cooling and heating demands and
respectively. As shown in Figs. 18 and 20, the energy stored in BESS and the excess thermal power is stored in TESSs. The output power of TESS
TESS is within an acceptable range. In this case, the maximum real is shown in Fig. 26. As shown in Figs. 25, and 27 the energy stored in
20
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Fig. 30. The output thermal power of CCHPs (a: expected value of scenarios, b: most probable scenario).
Fig. 31. The bus voltages (a: expected value of scenarios, b: most probable scenario).
BESSs, and TESSs are within the acceptable range. Fig. 31 shows that real power losses are reduced. Similar to the previous case, the max-
the voltage at all buses is within admissible ranges. Dispatching DGs imum operation cost occurs at hour 10:00, because of high electricity
will reduce the flow in the feeders and therefore, the voltage drops and price, and large electrical, heating and cooling demand. Furthermore,
21
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
Table 7
The comparison of results for different case studies.
Case study Most probable scenario The outcomes for the most probable scenario
Total power loss Average VSI Total operational cost Total emission Total power loss Averaged VSI Total operational cost Total emission
(kWh) ($) (ton) (kWh) ($) (ton)
Base Case 3.475e+03 0.755 1.704e+04 60.104 3.62e+03 0.749 1.706e+04 60.189
Case 1 2.87e+03 0.804 1.661e+04 59.763 2.54e+03 0.821 1.704e+04 59.573
Case 2 1.733e+3 0.827 1.0219e+4 53.206 1.55e+03 0.8331 1.041e+04 52.702
Case 3 1.361e+3 0.869 0.869e+4 59.013 1.27e+3 0.879 0.941e+4 54.974
22
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
proposed formulation captures multiple objectives, including real [14] T.T. Nguyen, A.V. Truong, and T.A. Phung, "A novel method based on adaptive
power loss, VSI index, operational cost, and emission considering the cuckoo search for optimal network reconfiguration and distributed generation al-
location in distribution network," Int. J. Electr. Power Energy Syst., vol. 78, pp.
uncertainties in wind generation, solar PV generation, and electrical 801–815, 2016/06/01/ 2016.
demand. The uncertainty in generation and demand is represented [15] S. Zhang, H. Cheng, D. Wang, L. Zhang, F. Li, and L. Yao, "Distributed generation
using scenarios. Scenario reduction technique is used to limit the planning in active distribution network considering demand side management and
network reconfiguration," Appl. Energy, vol. 228, pp. 1921–1936, 2018/10/15/
number of considered scenarios in the operation horizon. To capture 2018.
the uncertainty in the operation horizon, the expected values of the [16] N. Kanwar, N. Gupta, K.R. Niazi, and A. Swarnkar, "An integrated approach for
operation indices as well as the the operation indices in the most distributed resource allocation and network reconfiguration considering load di-
versity among customers," Sustain. Energy Grids Netw., vol. 7, pp. 37–46, 2016/09/
probable scenario are taken into account. To evaluate the proposed 01/ 2016.
model three case studies and a Base Case are considered. Case 1 ad- [17] A. Zidan, M.F. Shaaban, E.F. El-Saadany, Long-term multi-objective distribution
dresses the optimal operation of microgrid with DFR and HESs with network planning by DG allocation and feeders’ reconfiguration, Electr. Power Syst.
Res. 105 (2013) 95–104.
auxiliary boiler and TESS, without capacitor banks. Case 2 addresses
[18] R.S. Rao, K. Ravindra, K. Satish, S. Narasimham, Power loss minimization in dis-
the optimal operation of microgrid without DFR with capacitor banks tribution system using network reconfiguration in the presence of distributed
considering the HESs equipped with all components. Case 3 is Case 2 generation, IEEE Trans. Power Syst. 28 (1) (2013) 317–325.
with DFR. The Base Case features no DFR, no HES and no capacitor [19] M. K and J. S, "Integrated approach of network reconfiguration with distributed
generation and shunt capacitors placement for power loss minimization in radial
bank. The following observations were made using the expected values distribution networks," Appl. Soft Comput., vol. 52, pp. 1262–1284, 2017/03/01/
of the operation indices. First, compared to the Base Case, the real 2017.
power loss is reduced by 60%, 50%, and 17% in Cases 3, 2, and 1, [20] M. Mohammadi, A.M. Rozbahani, S. Bahmanyar, Power loss reduction of dis-
tribution systems using BFO based optimal reconfiguration along with DG and
respectively. Second, compared to Base Case, the VSI index is increased shunt capacitor placement simultaneously in fuzzy framework, J. Cent. South Univ.
by 15.1%, 9.5%, and 6.4% in Cases 3, 2, and 1, respectively. Third, 24 (1) (2017) 90–103.
compared to Base Case, the total operational costs are reduced by [21] S.N. Ravadanegh, M.R.J. Oskuee, M. Karimi, Multi-objective planning model for
simultaneous reconfiguration of power distribution network and allocation of re-
49.0%, 40.0%, and 2.5% in Cases 3, 2, and 1, respectively. And Fourth, newable energy resources and capacitors with considering uncertainties, J. Cent.
compared to Base Case, the emissions are decreased by 1.8%, 11.4%, South Univ. 24 (8) (2017) 1837–1849.
and 0.56% in Cases 3, 2, and 1, respectively. A similar trend is observed [22] M. Sedighizadeh, M. Esmaili, N. Mohammadkhani, Stochastic multi-objective en-
ergy management in residential microgrids with combined cooling, heating, and
in the simulation results for the most probable scenario. power units considering battery energy storage systems and plug-in hybrid electric
vehicles, J. Clean. Prod. 195 (2018) 301–317.
Declaration of Competing Interest [23] Z. Bai, T. Liu, Q. Liu, J. Lei, L. Gong, H. Jin, Thermodynamic analysis of a CCHP
system integrated a chemical recuperation process of methanol decomposition,
Energy Procedia 142 (2017) 1582–1588.
None. [24] S. Hameer, J.L. Van Niekerk, Thermodynamic modelling of thermal energy storage
systems, Energy Procedia 93 (2016) 25–30.
[25] J.A. Osara, M.D. Bryant, A thermodynamic model for lithium-ion battery de-
References gradation: application of the degradation-entropy generation theorem, Inventions 4
(2) (2019) 23.
[1] I. Ben Hamida, S.B. Salah, F. Msahli, and M.F. Mimouni, "Optimal network re- [26] W. Gu, et al., Modeling, planning and optimal energy management of combined
configuration and renewable DG integration considering time sequence variation in cooling, heating and power microgrid: a review, Int. J. Electr. Power Energy Syst.
load and DGs," Renew. Energy, vol. 121, pp. 66–80, 2018/06/01/ 2018. 54 (2014) 26–37.
[2] M. Esmaeili, M. Sedighizadeh, and M. Esmaili, "Multi-objective optimal re- [27] M. Sedighizadeh, M. Dakhem, M. Sarvi, H.H. Kordkheili, Optimal reconfiguration
configuration and DG (Distributed generation) power allocation in distribution and capacitor placement for power loss reduction of distribution system using im-
networks using big bang-big crunch algorithm considering load uncertainty," proved binary particle swarm optimization, Int. J. Energy Environ. Eng. 5 (1)
Energy, vol. 103, pp. 86–99, 2016/05/15/ 2016. (2014) 3.
[3] M. Sedighizadeh, M. Esmaili, and M. Esmaeili, "Application of the hybrid big bang- [28] H. Nasiraghdam, S. Jadid, Optimal hybrid PV/WT/FC sizing and distribution
big crunch algorithm to optimal reconfiguration and distributed generation power system reconfiguration using multi-objective artificial bee colony (MOABC) algo-
allocation in distribution systems," Energy, vol. 76, pp. 920–930, 2014/11/01/ rithm, Sol. Energy 86 (10) (2012) 3057–3071.
2014. [29] T. Niknam, A.K. Fard, A. Seifi, Distribution feeder reconfiguration considering fuel
[4] J.C. Leite, I.P. Abril, M.S.S. Azevedo, Capacitor and passive filter placement in cell/wind/photovoltaic power plants, Renew. Energy 37 (1) (2012) 213–225.
distribution systems by nondominated sorting genetic algorithm-II, Electr. Power [30] J. Olamaei, T. Niknam, G. Gharehpetian, Application of particle swarm optimiza-
Syst. Res. 143 (2017) 482–489. tion for distribution feeder reconfiguration considering distributed generators,
[5] G. Ferruzzi, G. Cervone, L. Delle Monache, G. Graditi, F. Jacobone, Optimal bidding Appl. Math. Comput. 201 (1–2) (2008) 575–586.
in a day-ahead energy market for micro grid under uncertainty in renewable energy [31] M. Sedighizadeh, M. Ghalambor, A. Rezazadeh, Reconfiguration of radial dis-
production, Energy 106 (2016) 194–202. tribution systems with fuzzy multi-objective approach using modified big bang-big
[6] M. Di Somma, G. Graditi, E. Heydarian-Forushani, M. Shafie-Khah, P. Siano, crunch algorithm, Arab. J. Sci. Eng. 39 (8) (2014) 6287–6296.
Stochastic optimal scheduling of distributed energy resources with renewables [32] M. Sedighizadeh, S. Ahmadi, M. Sarvi, An efficient hybrid big bang–big crunch
considering economic and environmental aspects, Renew. Energy 116 (2018) algorithm for multi-objective reconfiguration of balanced and unbalanced dis-
272–287. tribution systems in fuzzy framework, Electr. Power Components Syst. 41 (1)
[7] M. Sedighizadeh, G. Shaghaghi-shahr, M. Esmaili, and M.R. Aghamohammadi, (2013) 75–99.
"Optimal distribution feeder reconfiguration and generation scheduling for micro- [33] A.Y. Abdelaziz, F. Mohammed, S. Mekhamer, M. Badr, Distribution systems re-
grid day-ahead operation in the presence of electric vehicles considering un- configuration using a modified particle swarm optimization algorithm, Electr.
certainties," J. Energy Storage, vol. 21, pp. 58–71, 2019/02/01/ 2019. Power Syst. Res. 79 (11) (2009) 1521–1530.
[8] R. Jabbari-Sabet, S.-M. Moghaddas-Tafreshi, S.-S. Mirhoseini, Microgrid operation [34] N. Ghaffarzadeh, H. Sadeghi, A new efficient BBO based method for simultaneous
and management using probabilistic reconfiguration and unit commitment, Int. J. placement of inverter-based DG units and capacitors considering harmonic limits,
Electr. Power Energy Syst. 75 (2016) 328–336. Int. J. Electr. Power Energy Syst. 80 (2016) 37–45.
[9] G. Gutiérrez-Alcaraz, E. Galván, N. González-Cabrera, M. Javadi, Renewable energy [35] N. Mohammadkhani, M. Sedighizadeh, M. Esmaili, Energy and emission manage-
resources short-term scheduling and dynamic network reconfiguration for sustain- ment of CCHPs with electric and thermal energy storage and electric vehicle,
able energy consumption, Renew. Sustain. Energy Rev. 52 (2015) 256–264. Therm. Sci. Eng. Progr. 8 (2018) 494–508.
[10] F.S. Gazijahani, J. Salehi, Integrated DR and reconfiguration scheduling for optimal [36] A. Zakariazadeh, S. Jadid, P. Siano, Smart microgrid energy and reserve scheduling
operation of microgrids using Hong's point estimate method, Int. J. Electr. Power with demand response using stochastic optimization, Int. J. Electr. Power Energy
Energy Syst. 99 (2018) 481–492. Syst. 63 (2014) 523–533.
[11] M.R. Kaveh, R.-.A. Hooshmand, S.M. Madani, Simultaneous optimization of re- [37] M. Sedighizadeh, M. Esmaili, A. Jamshidi, M.-.H. Ghaderi, Stochastic multi-objec-
phasing, reconfiguration and DG placement in distribution networks using BF-SD tive economic-environmental energy and reserve scheduling of microgrids con-
algorithm, Appl. Soft Comput. 62 (2018) 1044–1055. sidering battery energy storage system, Int. J. Electr. Power Energy Syst. 106 (2019)
[12] J. Shukla, B. Das, V. Pant, Stability constrained optimal distribution system re- 1–16.
configuration considering uncertainties in correlated loads and distributed gen- [38] S. Talari, M. Yazdaninejad, M.-.R. Haghifam, Stochastic-based scheduling of the
erations, Int. J. Electr. Power Energy Syst. 99 (2018) 121–133. microgrid operation including wind turbines, photovoltaic cells, energy storages
[13] E. kianmehr, S. Nikkhah, and A. Rabiee, "Multi-objective stochastic model for joint and responsive loads, IET Gen. Transm. Distrib. 9 (12) (2015) 1498–1509.
optimal allocation of DG units and network reconfiguration from DG owner's and [39] M. Motevasel, A.R. Seifi, Expert energy management of a micro-grid considering
DisCo's perspectives," Renew. Energy, vol. 132, pp. 471–485, 2019/03/01/ 2019. wind energy uncertainty, Energy Convers. Manage. 83 (2014) 58–72.
[40] A. Zakariazadeh, S. Jadid, P. Siano, Economic-environmental energy and reserve
23
S.S. Fazlhashemi, et al. Journal of Energy Storage 29 (2020) 101301
scheduling of smart distribution systems: a multiobjective mathematical program- Softw. 37 (2) (2006) 106–111.
ming approach, Energy Convers. Manage. 78 (2014) 151–164. [46] J. Kennedy, Particle swarm optimization, Encycl. Mach. Learn. (2010) 760–766.
[41] M. Petrollese, L. Valverde, D. Cocco, G. Cau, J. Guerra, Real-time integration of [47] J.-.H. Teng, A direct approach for distribution system load flow solutions, IEEE
optimal generation scheduling with MPC for the energy management of a renew- Trans. Power Delivery 18 (3) (2003) 882–887.
able hydrogen-based microgrid, Appl. Energy 166 (2016) 96–106. [48] M.E. Baran, F.F. Wu, Network reconfiguration in distribution systems for loss re-
[42] W. Su, J. Wang, J. Roh, Stochastic energy scheduling in microgrids with inter- duction and load balancing, IEEE Trans. Power Delivery 4 (2) (1989) 1401–1407.
mittent renewable energy resources, IEEE Trans. Smart Grid 5 (4) (2014) [49] T. Weitzel, M. Schneider, C.H. Glock, F. Löber, S. Rinderknecht, Operating a sto-
1876–1883. rage-augmented hybrid microgrid considering battery aging costs, J. Clean. Prod.
[43] J. Sachs, O. Sawodny, Multi-objective three stage design optimization for island 188 (2018) 638–654.
microgrids, Appl. Energy 165 (2016) 789–800. [50] A.A. El-Fergany, A.Y. Abdelaziz, Capacitor allocations in radial distribution net-
[44] A. Jose-Garcia, W. Gómez-Flores, Automatic clustering using nature-inspired me- works using cuckoo search algorithm, IET Gen. Transm. Distrib. 8 (2) (2014)
taheuristics: a survey, Appl. Soft Comput. 41 (2016) 192–213. 223–232.
[45] O.K. Erol, I. Eksin, A new optimization method: big bang–big crunch, Adv. Eng.
24