Professional Documents
Culture Documents
net/publication/245294224
CITATIONS READS
42 1,900
3 authors, including:
All content following this page was uploaded by V. Kontogianni on 30 June 2016.
Abstract: The Tymfristos tunnel, a 1,365 m long road tunnel with an 11 m section diameter, was excavated through the highly tectonized,
low strength Flysch formation of central Greece. About 1 year after the completion of the excavation in 1995, convergence of up to 20%
followed by failure of the support system was recorded. A 501 m long segment, in which the failure occurred, was reexcavated based on
a more detailed study of the ground conditions; however, this second phase was also followed by an up to 6% convergence. The detailed
geodetic study of the three-dimensional kinematics of the support shell in relation time, ring closure delays, and support measures reveals
an unusual time-history of convergence occasionally continuing even after the ring closure and a nonuniform distortion of the lining.
Furthermore, uncontrolled deformation of certain “weak” sections propagated bidirectionally to adjacent, previously stabilized sections
producing a “chain effect,” responsible for destabilization and resumed convergence of long (⬃90 m) segments.
DOI: 10.1061/(ASCE)1090-0241(2004)130:10(1004)
CE Database subject headings: Convergence; Deformation analysis; Tunnels; Failures; Greece.
Introduction mations were practically the same (Panet and Guenot 1982; Dal-
giç 2002a; Kontogianni and Stiros 2002). This indicates that the
Two types of failures can be recognized during tunnel excavation: geotechnical techniques adopted, approximate elastoplastic analy-
(1) local instability effects (sudden collapse, tunnel face slope sis and FEM (Hoek 1999; Özsan and Karpuz 2001) successfully
failure) and (2) extreme convergence (squeezing) reducing the describe the actual conditions of good quality rock mass during
initial section of the tunnel and occasionally leading to the sup- tunneling.
port shell failure. This last deformation mode occurs beyond the There are, however, a number of tunnels in which observed
deformation was several times higher than the predicted one and
elastic range, is usually time-dependent, and its rate gradually
exceeded the critical 2% strain boundary (Table 1). As these tun-
decreases until it reaches an equilibrium level or failure (Singh
nels were excavated in weak rocks and there was no evidence of
and Goel 1999; Fig. 1). In fact, such a process is fundamental in
great delays to the lining or stoppages to the face advance, two
the so-called “NATM” (new Austrian tunneling method): a lim-
likely reasons for such failures can be proposed; either the false
ited reduction of the tunnel diameter leads to relief of stresses in application of the geotechnical models and excavation techniques,
the surrounding rock mass and to a less stiff and less expensive or the inability of these models or techniques to assess the weak
support system (Kovari 1993). Sakurai (1983) and Chern et al. rock mass conditions. Since the number of tunnels excavated in
(1998) suggested that strain (tunnel convergence to tunnel diam- unfavorable rock conditions (“bad rocks;” Hoek 2001) has dra-
eter ratio) values of approximately 1 to 2% represent a boundary matically increased in the last years, it is necessary to study such
(critical strain) between successfully designed tunnels and tunnels cases and shed some light on the conditions which led to such
requiring additional support measures and/or changes in the ex- failures.
cavation process. If strain exceeds this boundary, significant in-
stability problems may occur, and if it exceeds the minimum
specified clearances, several sections have to be remined (Fig. 1),
which is a time-consuming and high-cost process.
An analysis of the deformation recorded during the excavation
of a number of tunnels in good quality rocks in Greece, Turkey,
and other countries revealed that predicted and observed defor-
1
PhD Candidate, Dept. of Civil Engineering, Patras Univ., Patras
26500, Greece. E-mail: vkont@civil.upatras.gr
2
Civil Engineer, Dept of Civil Engineering, Patras Univ., Patras
26500, Greece.
3
Associate Professor, Dept. of Civil Engineering, Patras Univ., Patras
26500, Greece. E-mail: stiros@upatras.gr
Note. Discussion open until March 1, 2005. Separate discussions must
be submitted for individual papers. To extend the closing date by one
month, a written request must be filed with the ASCE Managing Editor.
The manuscript for this paper was submitted for review and possible
publication on February 20, 2002; approved on December 30, 2003. This
Fig. 1. Idealized curves indicating various cases of time-dependent
paper is part of the Journal of Geotechnical and Geoenvironmental
deformation of tunnels during their excavation. Modified from Muir
Engineering, Vol. 130, No. 10, October 1, 2004. ©ASCE, ISSN 1090-
0241/2004/10-1004–1013/$18.00. Wood (1993).
In this paper, we analyze the deformation of the Tymfristos Geological and Geotechnical Conditions
tunnel, Greece, one of the first tunnels excavated in Flysch for-
mation. Extreme deformation and failure of the support shell The Tymfristos tunnel was excavated through a Flysch complex,
(convergence up to 20%) made necessary the reexcavation of a widespread in the Pindos Mt. Range, representing the alpine skel-
501 m long tunnel segment, while during the reexcavation an eton of Greece. Flysch is a high laterally heterogeneous formation
additional up to 6% convergence was observed. Due to this ex- and in the broader study area consists of claystone and slicken-
treme deformation this project was much delayed and its cost was sided argillaceous schist, intensely folded and tectonized. Details
approximately 10 times higher than initially estimated (Technical of the rock structure along the tunnel path are shown in Fig. 3 and
Chamber of Greece, Central Greece Section 2000). Our analysis Table 3. No swelling rocks, like those found in tunnels in Flysch
is based on detailed geodetic survey records describing not simply further north in the Metsovo area (Karapantelakis et al. 2001; for
length changes as is the case with most tunnels excavated in the location see Fig. 2), were, however, met in Tymfristos.
past, but absolute three-dimensional (3D) displacements relative Dripping underground water was systematically observed, but
to fixed stations outside the tunnel, and permits to propose an no substantial change to the water flow along the tunnel axis or
explanation for the tunnel failure. with time was reported. Laboratory testing on samples collected
from the site suggests that the uniaxial compressive strength of
the intact rock 共ci兲 practically ranges between the values 5 and
50 MPa (unpublished data).
Tymfristos Tunnel
Fig. 2. Longitudinal section of the Tymfristos tunnel. Letters A–F indicate segments discussed in the text. Numbers indicate overburden height.
Shaded is the reexcavated part. Inset: Location map, T stands for Tymfristos, K for Kallidromo, and M for Metsovo.
1. Sampling of the rock mass of the area through drilled bore- Deformation During the First Phase of Excavation
holes along the tunnel axis at a spacing of a few hundreds of
In 1996, approximately 1 year after the initial excavation (1992–
meters.
1995), in the framework of the new geotechnical study the whole
2. Determination of certain rockmass parameters (uniaxial com-
tunnel was surveyed using geodetic techniques. It was divided
pression strength, cohesion, friction angle, modulus of elas-
into sections with a spacing of ⬃20 m along the tunnel axis, and
ticity, and Poisson ratio) on the basis of laboratory tests of
9–14 points in each section, some of them targets for the conver-
selected samples.
gence control during the initial excavation of the tunnel, were
3. Determination of the suitable support system on the basis of
measured. Both the initial survey (during the first phase of the
empirical selection of the support measures, following the
excavation) and postdeformation survey were based on stable ref-
current practice at the time. Such system consisted of 40 cm
erence stations outside the tunnel and survey stations along the
thick shotcrete shell reinforced with two layers of wire mesh
tunnel axis, fixed on the invert. Consequently, absolute displace-
(T188), twin IPN 180 steel ribs placed at 0.80 m spacing,
ments of survey stations along the tunnel axis and of deformed
invert lining to counteract the ring closure effect, and 20 rock
sections of the tunnel were estimated with an accuracy of a few
bolts 6–9 m long in order to improve the rock mass strength.
centimeters (Kontogianni and Stiros 2001).
4. The excavated cross section of 120 m2 was subdivided into
Survey data from two different segments were available for
top-heading, bench, and invert parts [Fig. 4(a)] following the
our study: from segment D (part of the reexcavated tunnel length)
NATM (Kovari 1993) and using mechanical excavation from
and from segment B (see Fig. 2 for locations). Convergence mea-
both portals. No limitations had been set concerning the ad-
sured ⬃1 year after the initial excavation in segment B (overbur-
vance rate or the ring closure distance. The tunneling rate
den 50–90 m) was up to 9% (at Ch. 0⫹577 m) while in segment
and sequence was determined by the lowest-cost approach,
D reached 20% (at Ch. 0⫹920 m; overburden 128–143 m). Se-
excavation through the week and support installation during
lected deformed sections for these two segments, compiled on the
the weekends.
basis of the survey data, are shown in Fig. 6.
5. Monitoring was based on geodetic data as well as geotech-
According to Tsatsanifos et al. (1999) the excavation of the
nical instruments (extensometers, etc.). The details and re-
top-heading section during the first phase of construction was not
sults of this monitoring are not known.
followed by any significant section closure. The main portion of
The excavation proved, at least for a 501 m long section (Ch.
the recorded deformation and the cracking of the support shell,
0⫹810 m to Ch. 1⫹311 m unsuccessful, leading to high defor-
accompanied by characteristic sounds, occurred shortly after the
mation of the tunnel sections, failure of the support shell (Fig. 5),
bench and invert excavation (P. Mantziaras, personal communica-
breaching of the contract, and partial reexcavation of the tunnel
tion, 2001). In some cases, the tunnel floor heaved up to 1.5 m
following a new geotechnical study under a new contract.
and the extremely stiff invert concrete lining failed to withstand
Fig. 3. Typical cross section of the Flysch along the face of the
Tymfristos tunnel (Ch. 0⫹536 m). Rockmass consists of mudstone Fig. 4. Tunnel section areas during the first phase of excavation and
with dense intercalations of argillaceous schist. Triangle and solid the reexcavation. Arrows indicate positions of cracked shotcrete shell
circle indicate dripping and low pressure water flow, respectively. in Fig. 5. Reflectors position also indicated (solid dots).
the strain and cracked (Fig. 5). Detailed records, however, of the The failed lining was removed and a new support system, includ-
convergence history versus the tunnel face advance or versus time ing the use of lattice girders instead of ribs, was installed; the rest
are not available. of the support system remained almost the same as that of the first
phase (Table 2). In addition, the ring closure distance was set to 2
m and the face advance to 1 m. However, these last specifications
Second Phase of Excavation were not strictly followed because of the delay produced to the
construction schedule.
During the second construction phase (1997 to 1998) under a new
contract, the section was widened to 130 m2, and the top-heading
Deformation during the Second Phase of Excavation
height was increased to 6.5 m high (instead of 6.0 m) in order to
provide the necessary net height even in the case of high defor- Geodetic monitoring of tunnel deformation was more systematic
mation [Fig. 4(b)]. Bench and invert parts were also remined to during the second phase of excavation. Deformation monitoring
the design dimensions. The excavation operation, following the sections were established at narrow (⬃15 m) spacing and three
NATM, started from both sides of the remined tunnel segment. reflectors were established in each section; two at the sides and
Fig. 5. Tymfristos tunnel, 1 year after the first excavation. (a) Maximum convergence reached 20% and the support system was destroyed; (b)
longitudinal cracks at the top-heading footings. Position of shotcrete cracking along the tunnel axis are indicated by arrows in Fig. 4. After
Kavvadas (1999).
one at the crown of the primary support of the tunnel [see Fig. Fig. 7. Recorded displacements and distortion of the support shell for
7(a)]. Measurements were made with a total station instrument representative sections of the Tymfristos tunnel (Section S13, a and
relative to fixed stations outside the tunnel, daily for approxi- b) and the Kallidromo tunnel (c and d). Arrows in (a) and (c) indicate
1
mately 1 2 months, until deformation stopped (i.e., until the tunnel horizontal and vertical components of displacement of geodetic con-
sections were stabilized). During this period, horizontal and ver- trol points; arrows in (b) and (d) indicate qualitatively the sense of
tical convergence of up to 2.5 and 6%, respectively, was observed deformation of the support shell.
(Tsatsanifos et al. 1999). The available survey data set discussed
below permits one to model the 3D kinematics of the primary
support of the tunnel. downwards. However, in some sections the vertical movement of
In order to understand the rock mass behavior in relation to the the control point at the crown is smaller than the vertical move-
excavation technique and the support measures used, the available ment of the sidewalls [i.e., vertical component of displacement
geodetic monitoring data collected during the second excavation for Point 3 was larger than for Point 2 in Fig. 7(a)]. Thus the main
phase were analyzed as far as: (1) the distribution of deformation part of the deformation is localized to the invert and the bench
in the various tunnel sections, (2) the variation of maximum con- (vertical and horizontal convergence) while in the top-heading a
vergence along the tunnel axis, (3) the time history of deforma- horizontal contraction is combined with a vertical movement that
tion, and (4) the relationship between convergence and ring clo- seems to represent a generalized rotational distortion of the sup-
sure are concerned. port shell [Fig. 7(b)].
Distribution of Deformation in Tunnel Sections Variation of Maximum Convergence along the Tunnel
Axis
As can be deduced from Figs. 7(a and b), a main characteristic of
the observed deformation is that it does not correspond to a uni- The horizontal and vertical maximum section convergence along
form radial section closure, but the amplitude of radial displace- the tunnel axis is shown in Fig. 8. This figure shows that for the
ment is variable along the tunnel periphery. The vertical displace- major part of the reexcavated segment convergence did not ex-
ment records indicate that the whole top-heading section moved ceed the value of 2% for the vertical and 1% for the horizontal
Fig. 8. Vertical convergence and horizontal convergence of the reexcavated part of the Tymfristos tunnel from position Ch. 0⫹850 m to position
Ch. 1⫹270 m
Discussion
Fig. 12. Resumed deformation after a stabilization period (shaded areas) for selected sections of the Kallidromo tunnel, Greece (top) and the Bolu
tunnel, Turkey (bottom). Based on unpublished data and Dalgiç (2002b).
apparent deterioration of the rock mass quality at the two Sections during both the initial and the reexcavation phases.
S9 and S13 (Table 3), a local increase of stresses or even a slight Based on the experience of the Tymfristos tunnel failure, we
change of the excavation rate or sequence had probably induced may assume that the limitation of the strain levels below the
deformation beyond the critical threshold before the ring closure, critical level (2%) at the time of ring closure and an early [i.e.,
preventing stabilization of the section. when deformation is still within the “green stage” (Peck, 2003,
Concerning the second point, geodetic data indicate that, ex- oral presentation)] identification of a possible deformation propa-
cept for a “primary” deformation, certain segments even after gation process may prevent high convergence or even failure of
their stabilization were affected by “induced” deformation from future tunnels excavated in “bad” rocks.
neighboring, incompetent sections (Fig. 11). This has probably
evolved to a “chain effect,” i.e., to a deformation propagating
bilaterally until sections “resisting” to and free of induced defor- Acknowledgments
mation were met (Figs. 13 and 14). A process which may be
responsible for the “bulge-type” deformation observed in a num- This paper is a contribution to the Research Project PENED 2001
ber of tunnels examined in this paper (Fig. 15), and possibly for (GSRT). The writers are deeply indebted to Dr. C. Tsatsanifos and
the unusual deformation observed next to incompetent sections in ERGOSE S.A. for providing unpublished data, as well as to Dr. P.
other tunnels [Inntaltunnel, Austria, see Fig. 5 in Schubert and Mantziaras for information and discussions. Constructive com-
Steindorfer (1996)] and which may last for a few weeks or a few ments of three anonymous reviewers are acknowledged.
months (Karapantelakis 1991). Obviously, such behavior could
not have been predicted during the excavation of the Tymfristos
tunnel because it was one of the very first tunnels excavated in References
Flysch in Greece (Hoek and Marinos 2000).
Brown, E. T., Bray, J., Ladanyi, B., and Hoek, E. (1983). “Ground re-
sponse curves for rock tunnels.” J. Geotech. Eng., 109(1), 15–39.
Conclusions Brox, D., and Hagedorn, H. (1999).”Extreme deformation and damage
during the construction of large tunnels.” Tunn. Undergr. Space Tech-
The extreme deformation observed during the two-phase excava- nol., 14(1), 23–26.
tion of the Tymfristos tunnel is certainly not an extraordinary Chern, J. C., Yu, C. W., and Shiao, F. Y. (1998). “Tunneling in squeezing
effect. What is extraordinary with this tunnel is the available geo- ground and support estimation.” Proc., Regional Symp. on Sedimen-
detic record describing the 3D kinematic history of long segments tary Rock Engineering, Taipei, 192–202.
in which convergence (tens of centimeters to 2 m) was far beyond Dalgiç, S. (2002a). “A comparison of predicted and actual tunnel behav-
the measurements noise (a few centimeters). Such data reveal that iour in the Instabul Metro, Turkey.” Eng. Geol. (Amsterdam), 63(1–
2), 69–82.
the deformation of this tunnel only at a first approximation cor-
Dalgiç, S. (2002b). “Tunneling in Squeezing Rock, the Bolu Tunnel,
responds to uniform radial closure and that there is a trade-off Anatolian Motorway, Turkey.” Eng. Geol. (Amsterdam), 67(1–2), 73–
between strain level and delays in ring closure. Finally, the bidi- 96.
rectional propagation of deformation from “weak” sections to Dalgiç, S., and Simsek, O. (2002).”Settlement predictions in the Ano-
previously stabilized sections (i.e., a chain effect), seems to have taliam Motorway, Turkey.” Eng. Geol. (Amsterdam), 67(1–2), 185–
been the main cause of extreme deformation, or even of failure 199.