INTERNAL REPORT

consumption in the project PROJECT : TANK TYPE B-01/MCM


date : 04-07-21

INFORMATION GENERAL

Clossing date Tuesday, June 29, 2021 Status closed Y N


Start date Total duration a+16 day
Estim Dat to deliv Thursday, June 24, 2021 Delay 5 day

CONSUMPTIONS

Manpower Machine
Function Total Hours Name Total Hours
EXPAT FAB 118 ROULEUSE 30
EXPAT WEL 64 PILIEUSE 1
LOCAL FAB 36 RADIAL 4
LOCAL WEL 196 CISAILLEUR 4
EXPAT RUB 117 COMPRESSEUR 1
LOCAL RUB 148 A 0
LOCAL PNT 22 B 0
ELECTRICI C 0

Material
Consumable material Principal material
qty Designation Qty Designation
68 disque coupé 230 6 tole 8 dim1.5*6
17 disque coupé 125 1 tole 10 dim 1.5*6
3 disque melage 230 2 cornier 100*80
18 disque melage 125 1 tole 15 dim1*2
2 baget 2.5 1 pipe DN100
2 baget 3.2 1 Bride DN100
2 baget 4 1/2 S Penguard TC BASE A
1 bobine 1/2 S Penguard com B
1 gaze oxygene 1/2 S Penguard Primer RED A
1 gaze co2 4 RUBBER LINE 6mm R20m2
0 0 01-Jan RUBBER LINE 3mm R20m2
3 PRIMER PR 200 750g
Principal material 6 SOLVENT CF-R4 800ml
59 CEMENT SC 4000 700g
36 HARDENER E-40 30g