2.

Fire Detection and Alarm System for FM 200 System

A). Detection, Alarm and Actuation.


B). Stand-By Power Supply.
C). Battery Test

A. Detection, Alarm And Actuation

Check and Write o.k. if normal x if not.

a). All detectors are to be checked for proper


alarm, supervision and trouble functions.

*Photo/Thermal Smoke Detectors ( )


*Photoelectric Smoke Detectors ( )
*Alarm Bells /Sirens ( )
*Strobe Lights ( )

b). Test cross-zones detection system

*Zone 1 Detectors ( )
Alarm Bells ( )
A/C & Dampers ( )
Shutdown

*Zone 2 Detectors ( )

Continuous Siren/Light ( )
Actuator must be in
DISCHARGE position
after time delay
Discharge signal on Novec
System status indicator.
Continuous Audio signal
shall change to Intermittent.
c). Operate Dual Action Manual Release to simulate
agent release. The actuating controls must move to
DISCHARGE position.

*Alarm Bells ( )
*Siren/Strobe Light ( )
*Siren/Strobe Light ( )
*HVAC & Dampers shutdown ( )
*Actuator must be in ( )
Discharge Position.

(If any of the devices are found to be


malfunctioning the devices must be
changed).

B. STAND-BY POWER SUPPLY

a). Disconnect the Battery

*Trouble signal observed ( )


*Charger with 24 V dc Output ( )
*Battery Voltage 24V dc ( )

(If the voltage output of the charger are


found to be less than 24 V DC or not
charging, the System must be serviced or
changed).

b). Reconnect Battery


* Trouble signal disappear ( )

C. BATTERY TEST

a). Disconnect the AC power for 48 ( )


hours and simulate alarm for 30 minutes
using battery only.
NOTE:
Battery Test shall be conducted separately.
Comments:

_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________

Approval Status:

Accepted

Rejected and Retest

Client : Saline water conversion corporation


Contractor : Saudi Sicli Company

1.0. Date of Fire alarm Testing: ___________________

2.0. Client’s Engr. Name & Signature: ____________________

3.0. Contractor’s Engr. Name & Signature: ____________________