MATERIAL SPECIFICATIONS:

2ND FLOOR BUILDING WEIGHT

2ND FLOOR TOTAL BUILDING WEIGHT (kN)


MATERIAL SPECIFICATIONS:

3RD FLOOR BUILDING WEIGHT

3RD FLOOR TOTAL BUILDING WEIGHT (kN)


MATERIAL SPECIFICATIONS:

4th FLOOR BUILDING WEIGHT

4TH FLOOR TOTAL BUILDING WEIGHT (kN)


MATERIAL SPECIFICATIONS:

ROOF DECK BUILDING WEIGHT

ROOF DECK TOTAL BUILDING WEIGHT (kN)


MATERIAL SPECIFICATIONS:

ROOF LEVEL BUILDING WEIGHT

ROOF LEVEL TOTAL BUILDING WEIGHT (kN)


SUMMARY:

LEVELS BULDING WEIGHT


2ND Floor 8019.29 𝑘𝑁
3RD Floor 6619.18 𝑘𝑁
4TH Floor 6026.11 𝑘𝑁
Roof Deck 4345.23 𝑘𝑁
Roof Level 387.99 𝑘𝑁
TOTAL 25397.79 𝑘𝑁