Subject: Activation & Response Test of Automatic Frequency Control at the Anwara 300 MW HFO
Based Power Plant.
Dear Sir,
As per the decision of FGMO Committee, we sent you the required settings in accordance with the
guideline of Electricity Grid Code-2019 (vide above mentioned reference) in order to activate FGMO in
your plant. Later on you requested for three weeks time to activate your plant in a meeting with BPDB
and PGCB. The three weeks time has so far been over.
Therefore, we are again requesting you to activate your plant as per the settings/ guidelines sent and do
the needful for a FGMO response test.