INTRODUCTION:

Fabrication work of different items is gaining importance with industrialization and


modernization of human civilization. Various steel fabricated items such as almirahs, racks, book-
cases, parts of almirahs such as monogram, locker plates, locker pullers handle its base, etc. are having
very good prospects at this moment and being used in daily life of middle class and upper middleclass
people. It is also used in Govt. offices, private companies, etc. Steel furniture is being preferred over
wood furniture due to its long durability, lightness in weight, portability, safety, economy in space
utilization, cleanliness etc.

The past performance of the unit can be seen at Annexure-A. this experience will definitely be
helpful to him to promote new unit with additional items of manufacture. Asked on his market survey
for different fabricated items the proposed unit will manufacture almirah and other fabricated items
as per local demand. Besides fabricated items, it is proposed to manufacture some almirah parts such
as Locker plate, Monogram, locker puller, etc. for which there is very good demand as there are many
fabrication units for almirah etc. Presently these units procure these parts from outside market.
Proposed unit will be able to meet their requirements and can be managed successfully by the
promoter of the unit.

MARKET POTENTIAL:

Demand for fabricated items such as almirah, racks, etc. is increasing with increasing of
population and urbanization. Almirah is almost used in every house, office, Govt. and private
organizations etc. it has vast potential of marketing within the state and outside the state. There are
many local fabricators of almirah in the state particularly in Rourkela, Cuttack, Bhubaneswar,
Sambalpur, etc. Still there is a good scope for setting new unit in such location like Tangi, Khordha
where hardly few such unit exist. Demand for almirah parts is almost every corner of the state for the
manufacture of steel almirah. Presently the fabricators are procuring parts from Calcutta and other
neighboring states. The proposed unit will be in position to meet the growing demand of these items
in the state.

BASIS OF PRESUMPTION:

1. The scheme is based on single shift basis and 300 working days per annum.
2. The prices of machinery etc. are taken as those which are prevailing at the time of preparing
scheme which may differ time to time and location to location.

3. Full capacity utilization of the unit may start after four years.

4. Interest rate @12%P.A. on total investment taken into consideration.

5. Payback period- 5years.

6. 5% of total investment will be contributed by the entrepreneur itself as margin money.

7. Land and building are Owned.


IMPLEMENTATION SCHEDULE:

Preparation of project report 3 months

Selection of site 1\2 months

Arrangement of finance 4 months

Registration and clearance from various authorities 1\2 month

Procurement of machinery 2 1\2 months

Recruitment of staff 1\2 month

11months

TECHNICAL ASPECTS:

1) Process of fabrication of steel almirah etc. mainly involved first pressing sheet, cutting,
bending, welding, joining of parts, finishing, painting etc. First desired sheets are pressed
then desired size and gauge sheet are cut with the help of cutting machinery. Then sheets
are bend with the help of cutting machinery. Then sheets are bent with the help of
bending machine welded. Parts are fitted and finally finishing and painting work done.
Other parts are made with the help of tool and jogs, After proper checking finished
products are made ready for dispatch.
2) Quality control: As per customers satisfaction.
3) Production capacity(Per Annum): Turnover (Per Annum)

Sl Item Value (Rs.)


No.
01 Sale of Almirah (General) 1,20,,00,000/-
02 Sale of Almirah (Special & Design) 65,50,000/-
03 Alena 10,50,000/-
04 Rack 14,00,000/-
Total Rs. 2,10,00,000/-

4) Approx. Motive Power : 25KWH.

5) Polution Control:

There is not much pollution in this type of unit. However, proper arrangement of
inventories are required and waste materials are to be disposed properly. Werkmen,
especially welders and cutters are to be provided with protective mouthpiece, hand
gloves etc.

6) Energy Conservation:
There is not much scope of energy conservation in such unit. However, unnecessary use
of lights, fans etc. has to be avoided inorder to save energy.