Professional Documents
Culture Documents
Joint Venture
The following are the minimum The following are the minimum
requirements that should be in place requirements for a Restricted Area
for an Exclusion Zone and should be and shall be considered on a risk based
communicated to all personnel entering approach taking due cognisance of the
the tunnel and considered on a risk prevailing conditions and methods.
based approach taking due cognisance This area should always be as safe as
of the prevailing conditions and reasonably practical with safe systems
methods: of work established for all activities
undertaken in this area.
• Defined minimum strength of the
last concrete sprayed before an • A visible barrier defining the
Exclusion Zone may be changed to boundary between the Restricted
a Restricted Area. This should be Area and the Normal access zone
demonstrated by calculation by the • A minimum length of the total
contractor’s designer, accepted by Restricted Area
the Crossrail Project Manager, and
shall not be less than 0.25MPa • A list of personnel entitled to be
within each Restricted Area
• Defined time before the strength
testing is first carried out by an • A maximum number of personnel
approved method normally expected to be within
each restricted area during spraying
• Defined minimum distance from operations
the working face or a defined
position at the face. For the • A maximum number of personnel
Crossrail project this shall not be normally expected to be within each
less than 2m restricted area during excavation
operations
• A physical barrier defining the
boundary between the Exclusion • Arrangements to be put in place
Zone and the Restricted Area at all to allow other personnel to enter a
times except during excavation restricted area for a special reason.
In some cases this will involve
stopping work or restricting plant
movement
Spraying Cycle:
Restriction Zone D: Restriction Zone C: Restriction Zone B: Restriction Zone A:
Access for personnel Access for essential Access for Nozzleman, No access to any
involved in the works. personnel only, Inspectors engineer & personnel who personnel. *
No access along blind & maintenance. Permission have only been authorised by
side of mixer truck. * must be recieved from the the nozzleman.
pump man.
2m from trailing
Walkway ends Chains edge at Axis
Restriction Zone D * Restriction Zone C * Is applicable when any part of the spray is above axis level. When spraying only below axis level
Escorted visitors Restriction Zone B extends to the face and there is no Exclusion Zone A.
may only enter
restriction zone D
only if deemed Restriction Zone A * Under no circumstances must this area be entered until checks on a panel have been carried
suitable and safe by out and entry agreed as per the General SCL Methodology WMS.
their escort.
PD Project Director
PM Project Manager
Phonetic alphabet