Professional Documents
Culture Documents
Module 2 Lesson 5
Module 2 Lesson 5
Contents
Microsoft may have patents, patent applications, trademarks, copyrights, or other intellectual
property rights covering subject matter in this document. Except as expressly provided in any
written license agreement from Microsoft, the furnishing of this document does not give you any
license to these patents, trademarks, copyrights, or other intellectual property.
The names of actual companies and products mentioned herein may be the trademarks of their
respective owners.
Module 2.5 97
1. Create a Master Project with two inserted projects. Insert one project
that is stored in the same directory as the master project, and insert the
other from a location at the root.
2. Save all projects and close Microsoft Project 2000.
3. Save all projects to a floppy disk.
4. Choose a partner and exchange floppy disks.
5. Copy the files from the disk you received to the desktop.
6. Open the master project.
Resource Pools
On the surface, Resource Pools have not changed in Microsoft Project 2000.
The user interface and overall usage remains the same. Below the surface,
however, there are a few significant changes in the way Resource Pools work.
Let’s take a look at dialog box changes first.
The first option, “Open resource pool to see assignments across all sharer files”
opens the resource pool read only, along with the file. The second option, “Do
not open other files” corresponds to the third option in the Microsoft Project 98
dialog box, which reads, “Do not open resource pool.” It opens only the file
being opened.
Note
The second option found in the Microsoft Project 98 dialog box, “Open
Resource Pool Read-Write…” has not been removed from
Microsoft Project 2000. It is still found in the dialog box launched when
opening the resource pool directly. This option can also be accessed via
Microsoft® Visual Basic® for Applications (VBA).
Opening Master Projects with Multiple Inserted Projects
Attached to a Resource Pool
In Microsoft Project 98, when you open a master project with multiple inserted
projects, each attached to a resource pool, you would receive the following
dialog box for each inserted project.
In Microsoft Project 2000, you receive the new dialog with only two options as
shown below.
This dialog appears only once and the selection will be applied to all inserted
projects attached to a resource pool, even if each is attached to a different
resource pool.
Module 2.5 103
Similarly, you will no longer be prompted to update the resource pool multiple
times when saving or closing a master project. Instead you will receive the
following dialog only once and the selection will apply to all inserted projects.
Note
You will still be prompted to save each individual project unless you choose
“Yes to all” or “No to all.” But you will not be asked if you want to update the
resource pool for each individual project.
The Link (not the file) Takes Precedence
Dialog boxes are not the only change to Resource Pools. In
Microsoft Project 98, sharing resources made your project dependent on that
particular file. In Microsoft Project 2000, it is the link (not the file) that takes
precedence. Because of this, you can replace the resource pool file with another
file, simply by putting it directly where the old pool resided.
1. Create a new project with 3 tasks. Save the project as Project1.mpp, but
leave it open.
2. Create a resource pool with three resources named R1, R2, and R3.
3. Save the file as RP.mpp and leave it open.
4. Have Project1.mpp use RP.mpp as a resource pool.
5. Assign each resource to one task each.
6. In the resource sheet of Project1.mpp, add a new resource named R4.
7. Save both the files and close them.
8. Open Project1.mpp. When prompted, choose do not open other files
and click OK.
Data may be overwritten if using a resource pool and sharers of different versions
and one of the files uses features new to Microsoft Project 2000. This is because
Microsoft Project 2000 features will not be saved in a Microsoft Project 98 files.
Thus when files are saved, the data between the resource pool and the sharer become
out of sync. When they are re-opened together, one or the other may overwrite the
other. Which overwrites which is determined by the precedence setting found in the
Share Resources dialog box titled “On conflict with calendar or resource
information.”
For assignment data, the sharer will always take precedence. For resource data,
the precedence setting determines which file will overwrite which. For
example, in Scenario 3 where a Microsoft Project 2000 sharer uses a new
feature like Task Calendars or Estimated Durations, data for these features does
not get saved to the resource pool (which is saved in the Microsoft Project 98
format.) When the files are next opened together, all assignment information
from the sharer file overwrites the assignment information in the resource pool.
Thus estimated duration information will be copied over. However, resource
data from the resource pool may overwrite that in the sharer if “Pool takes
precedence” is set. Thus data for any new features used in the sharer (that is,
Material Resources or Resource Availability) will be overwritten and lost.