Professional Documents
Culture Documents
ii
PREFACE
SPECIAL INSPECTIONS - BEST PRACTICES: A Guide to Special Inspection Application,
Policy, and Enforcement has been developed to aid structural engineers, building officials, special
inspectors, and contractors involved in special inspection programs in South Carolina. This
document was authored by the Special Inspections Committee of the Structural Engineers
Association of South Carolina (SEA of SC) and approved by the membership on September 15,
2005.
The document contains two parts. Chapter 1.0 is titled Special Inspection Applications for
Structural Engineers and it is intended to serve as an overall guide to special inspections as
related to the field of structural engineering. In particular, this part contains an introduction to
special inspections, a commentary on special inspection requirements of Chapter 17 of the 2003
International Building Code, explanations of often misunderstood material specific requirements,
a comparison of requirements and procedures for state and private jobs, a summary of SEA of SC
concerns and recommendations, and SEA of SC recommended forms available for use by SEA of
SC membership. Chapter 2.0 is titled Special Inspection Policy and Enforcement and it presents
some of the “best practices” of special inspection programs throughout the United States.
Particular emphasis is placed on the special inspection program in place in Mecklenburg County,
NC under the direction of Eddie Prince, AIA, Esquire.
AKNOWLEDGEMENTS
The Special Inspection Committee of the Structural Engineers Association of South Carolina
would like to recognize The Citadel’s Timothy Wayne Mays, Ph.D., P.E. and John C. Ryan, P.E.
of Structural Engineering and Education Solutions, LLC for spearheading this effort. A special
thanks should also be given to Eddie Prince, AIA, Esquire for providing support and insight on
special inspection programs in Mecklenburg County, NC and for his willingness to present
aspects of their program to code enforcement officers in South Carolina.
iii
Table of Contents
1.0 Part I - Special Inspection Applications for Structural Engineers
iv
1.0 Special Inspection Applications for Structural Engineers
The South Carolina Building Codes Council has put together several drafts of a document
originally titled “Special Inspection Policy” which has been changed to “Special
Inspection Resource Supplement.” The document is intended to provide guidelines for
building officials establishing special inspection programs in their jurisdictions and it
contains minimum qualifications for individuals or firms offering special inspection
services. The document stresses that the owner or design professional on a specific job
can require more stringent qualifications than those recommended by the South Carolina
Building Codes Council or those enforced by a local jurisdiction. Except for engineers
and architects registered in South Carolina, recommended special inspector qualifications
(taken directly from the Building Code Council’s Special Inspection Resource
Supplement) include:
Steel Construction
Welding
Current American Welding Society (AWS) Certified Welding Inspector or
current AWS Certified Welding Educator or
current AWS Certified Welding Engineer or
Current American Welding Society/American Institute of Steel Construction (AWS/AISC)
Certified Steel Structure Inspector
1
Nondestructive Testing of Welds
Current Nondestructive Testing Level II or III (Magnetic Particle Testing, Liquid
Penetrate Testing, Ultrasonic Testing or Radiographic Testing)
(1) Level II personnel shall should be qualified in accordance with the American
Society of Nondestructive Testing (ASNT) document SNT-TC-IA (current edition). Level
II certification as determined by a Level III examiner is required for each categoryor
(2) Level III Examiner shall should be certified by ASNT unless all level II personnel
have a current ASNT Central Certification Program certification. Only then will should
in-house designation of Level III nondestructive testing personnel be permitted
High-Strength Bolting
Current ICC Structural Steel and Welding certificate with one year
of related experience or
Current AWS/AISC Certified Steel Structure Inspector
Concrete Construction
Reinforced Concrete
Current ICC Reinforced Concrete Special Inspector or
Current American Concrete Institute (ACI) Concrete Field Testing Technician - Grade 1
Certification or
South Carolina Engineer in Training (EIT) with one year related experience
2
IBC Table 1704.4 Item No. 2
Current AWS Certified Welding Inspector or
Current AWS Certified Welding Educator or
Current AWS Certified Welding Engineer or
Current AWS/AISC Certified Steel Structure Inspector
Masonry Construction
Current ICC Structural Masonry certificate and one year related experience or
South Carolina EIT with one year related experience
Wood Construction
Current ICC Building Inspector or
Current ICC Commercial Building Inspector or
Current ICC Commercial Combination Inspector or
Current ICC Combination Inspector or
Current ICC Residential Building Inspector or
Current ICC Residential Combination Inspector or
Current ICC Building Code Official or
Current ICC Certified Building Official or
Current ICC Master Code Professional or
South Carolina EIT with one year related experience
Soils
Site Preparation
Current National Institute for Certification in Engineering Technologies (NICET) Level II
certification in geotechnical engineering technology/construction or
South Carolina Registered Geologist or
South Carolina EIT with one year related experience or
South Carolina Geologist in Training (GIT) with one year related experience
Pile Foundations
Current NICET Level II certification in geotechnical engineering technology/construction
South Carolina Registered Geologist or
South Carolina EIT with one year related experience or
South Carolina GIT with one year related experience
3
Pier Foundations
Current NICET Level II certification in geotechnical engineering technology/construction
South Carolina Registered Geologist or
South Carolina EIT with one year related experience or
South Carolina GIT with one year related experience
The only drawback to these recommendations is that a licensed engineer or architect “with
appropriate experience” can serve as a special inspector without additional training or
certification. It is anticipated that most jurisdictions will accept engineers and architects
as special inspectors without requiring evidence of appropriate experience. It is also
expected that auditing of special inspection practices by building officials will not be
commonplace in South Carolina. Most licensed professionals do not have the experience
necessary to serve as a special inspector without some type of additional training.
Building officials and the building codes council are relying on the ethical standards of
design professionals to prohibit them from providing services outside their areas of
competency.
A major requirement for the State of South Carolina is that firms offering special
inspection services for projects or fabrications in SC must be licensed, registered, or
certified by one of the following: the SC Board of Architectural Examiners, the SC
Contractors Licensing Board, or the SC Board of Professional Engineers and Land
Surveyors. Hence, special inspection firms must be licensed, registered, or certified and
cannot simply be owned and operated by ICC certified inspectors with minimum
education and experience. Although this topic is being fought at the state level, it is
actually conservative relative to surrounding states (e.g., Georgia, North Carolina) which
require a licensed professional in charge of the inspection services.
Prefabricated Trusses
Current Truss Plate Institute Certification
4
1.2 Commentary on Special Inspection Requirements of the 2003 IBC
The 2003 International Building Code states that the permit applicant (i.e., owner or
owner’s representative) is responsible for hiring special inspectors needed to provide the
special inspections required in the code. There are few exceptions and only a small
percentage of buildings do not require special inspections. Buildings not requiring special
inspections include buildings of minor nature, buildings not requiring professional
engineering or architectural services, and most categories of one and two family
dwellings. Although not specifically stated, the obvious implication is that buildings not
requiring a permit do not require special inspections. In such cases, however, the
contractor should be made aware that they are not relieved from certain elements of
quality control as discussed in later sections of this document. As a final note, since the
contractor is sometimes the owner, it may be the case that the special inspectors are paid
directly by the contractor and a conflict of interest cannot be avoided.
Continuous inspections are the full-time observation of the work in question. For
example, all full and partial penetration welds on a jobsite require continuous inspection.
This means that if two full penetration welds are being performed simultaneously, the
special inspector must be in a location to inspect all weld passes at the same time or
several welding special inspectors must be used. North Carolina state jobs (SCO Special
Inspections Guidelines) provide a more liberal definition of continuous for this case.
Periodic inspections are the part time observation of the work in question. The term
periodic means that the continuous presence of a special inspector is not required. It does
not necessarily indicate that fewer than 100% of items marked for periodic inspection
require inspection. It is the responsibility of the EOR specifying a special inspection
schedule to define the maximum interval between inspections, as well as the percentage of
particular inspection items requiring periodic inspection. The most restrictive of all
applicable standards should be specified. For example, the North Carolina State
Construction Manual places an upper bound on periodic inspections of once per week.
5
1.2.2 Report Requirements
Special inspectors are required to submit interim and final inspection reports to the
building official and relevant design professional on a periodic basis. The submittal
frequency of interim reports is jurisdiction and project specific. Often interim report
frequency is controlled by the review capacity of the building official and is jurisdiction
dependant. In some cases, interim reports are waived entirely. Final inspection reports are
integral to the special inspection process and are required for all projects for which a
special inspection program is required.
Interim reports shall summarize the inspections performed since the previous report and
any discrepancies noted at that particular time. The special inspector should not wait until
the interim report is due to notify the contractor of discrepancies. In fact, the special
inspector is required to notify the contractor immediately after noting the discrepancy and
the building official and relevant design professional if the discrepancy is not corrected.
At the conclusion of the project, special inspectors must submit a final report documenting
all the required special inspections and all discrepancies and corrections that occurred
during the entire project. The relative due date for the final report is also jurisdiction
specific and can be material specific (i.e., special inspector specific) as well.
For steel construction, special inspection of the fabrication process is not required unless
the fabricator performs welding, thermal cutting, or heating operations of some kind as
part of the fabrication process. Since it is typical that some type of flame cutting be used
in the shop, structural steel fabricators in South Carolina have two options: (1) become
certified through a state recognized program such as AISC’s Conventional Steel Building
Systems or Complex Steel Building System certification programs or (2) submit a detailed
procedure outlining the fabricator’s material control practices that focuses on the
fabricator’s ability to keep suitable records for all fabricated main load-bearing elements.
These records include mill test reports and documentation that tracks material
specification and grade for all structural components throughout the fabrication
process to ensure that the fabricated items are in accordance with job specifications
and shop drawings.
Simply put, a quality assurance plan for seismic resistance is a list of structural items
designed to resist seismic forces, such as moment frames, shear walls, diaphragms, etc. In
general, the intent of a quality assurance plan is to communicate to the contractor the
6
critical nature of the seismic force resisting items in a high seismic zone, and to verify that
the contractor has the ability to exact quality control when constructing these items. The
contractor is required to acknowledge his awareness of the critical nature of the items
included in the quality assurance plan in the “Contractor’s Statement of Responsibility,”
per IBC, Section 1705.3.
The provisions of the code state that a schedule of special inspections, including the
frequency of such inspections, be included in the quality assurance plan. No additional
special inspection items are required as a result of a quality assurance plan. Therefore, it
is more logical to include the quality assurance plan as a part of a statement of special
inspections, which can be taken out where special inspections are required, but a quality
assurance plan is not. When a quality assurance plan is required, it can simply be included
with the statement of special inspections, which lists inspection requirements.
Similar to a quality assurance plan for seismic resistance, a quality assurance plan for wind
resistance is a list of structural items designed to resist wind forces. All additional
commentary in section 1.2.4 is applicable to a quality assurance plan for wind resistance.
7
are no conflicts of interest. The second major difference is who is performing the
inspections. Many uncertified technicians working on behalf of the contractor are being
replaced with approved inspectors that have appropriate qualifications to effectively
inspect structures. It is anticipated that a well established special inspection program will
significantly improve the quality of construction in South Carolina.
1.3.1 Steel
Section 1704.3 of the 2003 International Building Code covers special inspection
requirements for steel construction. The requirements can be divided into three categories:
high strength bolting, structural welding, and steel frame detailing.
1.3.1.1 Bolting
Not all bolt installations require special inspection. Only ASTM A325 and ASTM A490
(or equivalent) high strength bolts require installations to be inspected by a special
inspector. Section 1704.3.3 of the 2003 International Building Code requires bolts to be
inspected in accordance with “AISC specifications.” This is a key statement since Section
1704.3.3.1 goes on to present an inspection outline in accordance with the table of
contents of the AISC/RSCS Specification for Structural Joints Using ASTM A325 or A490
Bolts (note that adherence to this document is also required by Section J3.1 of the AISC
LRFD and Specifications for Structural Steel Buildings). Careful review of the
AISC/RSCS Specification for Structural Joints Using ASTM A325 or A490 Bolts manifests
that the special inspection requirements for high strength bolts are not new at all. In fact,
quality control practices have simply been replaced by the quality assurance program of
Chapter 17 of the 2003 International Building Code. The introduction to Chapter 9 of the
AISC/RSCS Specification for Structural Joints Using ASTM A325 or A490 Bolts reads:
The option of using inspectors working on behalf of the owner and his or her design team
were already in place for high strength bolting prior to the adoption of Chapter 17 of the
2003 International Building Code. Hence, there are really no new inspection requirements
for high strength bolting. Special inspection topics for bolting are listed in
Table 3.1 below.
8
Table 1704.3, RCSC 2 Material verification - markings
As indicated in Table 3.1, performing special inspections of high strength bolting is a lot
of work. The special inspector is responsible for ensuring that the contractor prepares for
installing and installs high strength bolts in accordance with the AISC/RSCS Specification
for Structural Joints Using ASTM A325 or A490 Bolts. For an exhaustive discussion on
special inspection requirements for bolting, the reader is referred to Chapters 1 through 9
of the AISC/RSCS Specification for Structural Joints Using ASTM A325 or A490 Bolts. A
general discussion is included here.
There are many requirements that the special inspector must periodically verify prior to
bolting. Manufacturer certifications for bolts and bolt components, and bolt and bolt
component markings must be checked. Bolts must be stored in closed containers on site,
and there are stringent requirements for bolt cleaning and bolt reuse. Bolt component lots
must be separated and galvanized bolts and nuts must be kept together. Appropriate
washer use and faying surfaces must be verified. If alternative-design fasteners are used,
they must be installed in accordance with the manufacturer’s installation instructions and
inspected using the manufacturer’s inspection instructions. The special inspector must
make sure bolt holes line up and that only acceptable burrs are present on faying surfaces.
For snug-tightened joints, the special inspector must ensure that a snug condition is
obtained. This can be done using a feeler gage or the end of a small tape measure for
removed interior bolts.
For fully tensioned bolts, the contractor’s preinstallation procedure must be periodically
monitored by the special inspector. The purpose of the bolt preinstallation procedure is to
ensure that installed bolts meet the minimum preinstallation values given in Table 8.1 of
the AISC/RSCS Specification for Structural Joints Using ASTM A325 or A490 Bolts.
9
1.3.1.2 Welding
Section 1704.3.1 of the 2003 International Building Code requires welds to be inspected
in accordance with AWS D1.1 (Structural Welding Code – Steel) and for welding
inspector qualifications to be in accordance with this document as well. Weld inspection
requirements (i.e., verification inspection, quality assurance) for special inspectors are
listed in Section 6 of AWS D1.1 and are purposefully indicated as being in addition to
contractor quality control requirements that are listed there as well. In contrast to bolting
inspection requirements discussed above, quality control practices for welding are not
replaced with the quality assurance requirements mandated by Chapter 17 of the 2003
International Building Code. Section 6.1.2 of AWS D1.1 reads:
The option of using inspectors working on behalf of the owner and his or her design team
were already in place for structural welding prior to the adoption of Chapter 17 of the
2003 International Building Code. Hence, there are really no new inspection requirements
for structural welding. Special inspection topics for welding are listed in Tables 3.2
through 3.4 below.
TABLE 3.2. WELD INSPECTION: PRIOR TO WELDING (ALL REFERENCE IBC 1704.3.1).
10
AWS 6.5.3,4, 5.5, 5.21 WPS followed
AWS 6.2, 5.3 Welding materials exposure
AWS 5.6 Minimum interpass temperature
AWS 5.12.1, 5.12.2 No change to environmental conditions
AWS 6.5.4, 5.21 Proper welding technique
AWS 6.5.4, 5.30.1 Interpass cleaning
AWS 6.5.4, 5.24 Interpass profiles
AWS 6.5.4, 6.9 Weld pass quality
TABLE 3.3. WELD INSPECTION: DURING WELDING (ALL REFERENCE IBC 1704.3.1).
There are many requirements that the special inspector must periodically verify prior to
welding. Welder qualifications must be reviewed by the special inspector to ensure that
they are in accordance with Section 4 of AWS D1.1. Welders are qualified for a specific
type of welding unless they do not engage in the type of welding for six months or the
special inspector questions the welder’s ability. It should be verified that welding
equipment is in good working condition and that electrodes meet the appropriate AWS
specifications. All electrodes should be appropriately stored when not in use. The special
11
inspector’s main objective is to ensure that all welds are performed in strict accordance
with welding procedure specifications made available by the contractor for all types of
welds being performed on the jobsite. Welding procedure specifications cover shielding
gas, voltage, current, preheat, and wire feed speeds for each weld. Fit up must be verified
and atmospheric conditions (temperature, wind speed, etc.) must meet AWS D1.1
requirements before welding is begun.
During welding, the special inspector must again monitor the welding process by focusing
on the welding procedure specification requirements for each particular weld. Not
adhering to a given welding procedure specification will likely lead to unacceptable final
welds. For multipass welds, interpass temperatures must be maintained in accordance
with the welding procedure specification and each pass must be appropriately cleaned.
The special inspector must verify that interpass profiles of fillet and groove welds are in
accordance with AWS D1.1. A visual inspection of the weld must also be performed for
each weld pass of all multipass welds.
After welding, all welds must be cleaned by the welder and visually examined by the
special inspector to verify that no discontinuities are present. The special inspector must
verify the length and size of all welds using appropriate gages.
The only “new” provisions presented in Chapter 17 of the 2003 International Building
Code for welding are in regards to inspection frequency. All welds must be inspected by
the special inspector, but only complete and partial penetration groove welds, multipass
welds, and single pass welds larger than 5/16 in. require continuous inspection. Periodic
inspection can be performed for all other welds since the final inspection of these welds
will reveal all weld discontinuities. Some discontinuities may be hidden for the larger
welds mentioned above.
Additional requirements for welding are listed in Tables 3.5 and 3.6. Cold formed steel
construction only requires periodic special inspection of welded studs when used as a
structural diaphragm and for welded sheet steel for cold-formed framing members to
include studs and joists. Floor and deck welds are covered in AWS D1.3 and the special
inspector must confirm that there are no cracks in the arc spot welds, a minimum
reinforcement of 1/32 in. is present, and undercut is not longer than 1/8 times the
circumference of the weld. Note that welder qualification is also covered in AWS D1.3
and not AWS D1.1. Weld spacing should be verified.
Stud welding is covered in Section 7 of AWS D1.1 and the special inspector must visually
inspect all studs welds by looking for 360 degree flash around the base of the stud. If the
flash is not present, the stud must be bent 15 degrees from the vertical and left bent if no
failure sign is present. A failure while bending indicates a poorly welded stud. There is
no ASTM standard for ring testing of studs (hitting with a 3 lb hammer), but some
inspectors may choose to inspect welds this way in addition to the visual inspection
mentioned above. The special inspector must verify size, location, and spacing of
shear studs.
AISC 341 (Seismic Provisions for Steel Buildings) often applies in South Carolina and
specific requirements for welding inspections are required when welds are part of the
seismic force resisting system. All complete joint penetration and partial joint penetration
welds subject to net tension must be examined using non destructive tests other than visual
12
inspection (can be reduced to visual inspection by structural engineer of record if approved
by building official). When welds from doubler plates or continuity plates are installed in
the k area of the column, non destructive testing procedures should be used to check base
metal in proximity to the welds (if required by the structural engineer of record). Section
1708.4 (Seismic Design Categories C, D, E, and F) requires base metal thicker than 1.5
inches and subject to through thickness weld shrinkage strains to be ultrasonically tested
behind and adjacent to all welds. It should also be noted that Section 1707.3 (Seismic
Design Categories C, D, E, and F) requires seismic force resisting system components of
cold formed steel framing (all welds and fastening components to include but not limited
to screw attachments, bolting, and anchoring; struts; braces; hold-downs) be installed with
periodic special inspections.
1.3.2 Concrete
Section 1704.4 of the 2003 IBC provides special inspection requirements for concrete
construction. IBC Table 1704.4 provides a nominal description of inspection items,
which are listed with broad references to ACI 318, IBC (Chapter 19), AWS, and ASTM.
This section provides comprehensive lists of actual inspection and verification tasks to be
13
require further clarification. In general, special inspection requirements for cast-in-place
concrete can be categorized by one of three stages of construction: inspections occurring
(1) prior to concrete placement, (2) during concrete placement, and (3) post-concrete
placement.
Verify type and grade of reinforcing and post-tensioning steel (Mill test reports are
required for SDC C, D, E, or F per IBC 1708.3)
Verify that reinforcing is free of dirt, oil, damage, and excessive rust
Verify that post-tensioning tendons are free from dirt, oil, damage excessive rust, pitting,
and are properly wrapped as required
Verify that reinforcing steel and post-tensioning steel is properly chaired, tied and
otherwise supported to prevent displacement during concrete placement
Verify proper minimum and maximum clearances between reinforcing and minimum
clearance between reinforcing and forms
Verify proper minimum and maximum clearances between post-tensioning tendons at
ends of member
Verify proper clear cover between reinforcing / post-tensioning and concrete surface
Verify size and placement of reinforcing per structural drawings
Verify location and proper drape of PT tendons per structural drawings
Verify reinforcing lap lengths, bends, hooks
Verify anchorage detail at live and dead end of PT
Verify detail of PT termination within slab or beam
The tasks listed above are self explanatory and detail verification items required to ensure
that the type, size, condition, and placement of reinforcing is as specified in the contract
documents. Tabulated references related to these items are sections in ACI-318 or IBC,
Chapter 19 design standards. Meeting the requirements of the referenced sections in the
form of code compliant contract documents, as always, is the responsibility of the EOR.
No inspections or tests are referenced directly for these items.
However, it should be noted that mill test reports may be required by IBC, Section 1708.3.
14
are necessary, continuous special inspections of welding of reinforcing is required.
Welding inspection requirements are detailed in AWS D1.4. A general discussion of
welding inspection requirements is given in 1.3.1.2 of this document, and is not
repeated here.
Since the inter-pass and preheat requirements for welding is highly dependant on the
chemical composition, and more specifically the carbon equivalence (C.E.), of the
reinforcing steel used, additional mill tests are required for reinforcing steel not meeting
the ASTM A706 specification. To avoid excessive preheat and inter-pass temperature
requirements, chemical analysis tests should be specified in the contract documents for
reinforcing steel to be welded which do not meet the A706 specification,. Verification of
proper preheat and inter-pass temperature specified in AWS D1.4, based on the C.E. of the
reinforcing steel, is the responsibility of the special inspector.
It should also be noted that CRSI, Manual of Standard Practice, also recommends that
reinforcing steel meeting the ASTM A996 specification not be welded under any
circumstances due to the difficulty in obtaining meaningful chemical analysis of the rail
and axle steel.
IBC Section 1912 provides guidance for design of ASTM A307 bolts to be used for
anchorage in concrete. The section is applicable only for allowable stress design, and
only for load combinations which do not include seismic effects. Sub-section 1904.4
provides for increasing the allowable tension capacity of Table 1912.2 for anchorages
designed using the provisions of this section.
Continuous special inspections of anchorages designed using the provisions of IBC Sub-
section 1904.4 is required. Otherwise, special inspections of such anchorages are not
specifically required.
Concrete source information and supporting data pertaining to the service history of the
concrete materials and independent laboratory conducted strength tests, necessary to
determine the minimum compressive strength of a concrete mix is typically submitted to
the EOR by the concrete supplier for preliminary approval. By approving a mix design,
the EOR is confirming that the above five items are consistent with the requirements of
the contract documents. The special inspector is not usually required to approve a
concrete mix design. It is the responsibility of the special inspector to complete the
15
inspections items above by obtaining a copy of the approved mix and approval
documentation, and subsequently verify that the concrete mix submitted for approval is
the concrete mix delivered to the job site.
Verify that the total water added does not exceed that of the specifications
Verify that a proper number of strength test cylinders are made
Verify proper preparation of cylinders
Verify proper performance of slump, air content, and temperature tests
Arrange for proper handling and curing of test specimens
General guidance for the verification items relating to mixing, conveying, and
consolidation of concrete is found in ACI 318, Sections 5.7-5.10, which reference the
following ACI subcommittee reports for more detailed guidance: ACI 304 – Guide for
Measuring, Mixing, Transporting, and Placing Concrete, ACI 309 – Guide for
Consolidation of Concrete. When authoring a statement of special inspections, the EOR
16
should require conformance to the applicable sub-committee recommendations.
A qualified special inspector has in-depth familiarity with these documents and is
responsible for verifying that concreting operations conform to the referenced report
recommendations.
In addition to verifying proper mixing, depositing, and consolidating concrete, the special
inspector is also responsible for verifying that the formwork will result in the specified
dimensions.
General guidance for general curing practices is found in ACI 318, Sections 5.11-5.13,
which reference the following ACI subcommittee reports for more detailed guidance: ACI
308 – Standard Practice for Curing Concrete, ACI 306 – Cold Weather Concreting, and
ACI 305 – Cold Weather Concreting.
Since it is not always possible for the EOR to know the exact conditions of construction,
the recommendations of these sub-committee reports should be referenced. It is the
responsibility of the special inspector to be familiar with general curing practices, as well
as hot and cold weather concreting requirements and to verify that they are being
followed properly.
1.3.3 Masonry
1.3.3.1 IBC 1704: Special Inspection Requirements for Masonry
Section 1704.5 of the 2003 IBC provides special inspection requirements for masonry
17
construction. IBC Table 1704.5.1 lists Level 1 testing and inspection requirements and
Table 1704.5.3 lists Level 2 testing and inspection requirements. The appropriate level of
inspection is determined based on the type of structure (essential or non-essential) and the
method of masonry design (empirical or engineered) as follows:
Method of Design
Building Type/Use
Empirically Specified, Glass
Engineered Design c.
Unit, Veneer b.
Notes:
a. Essential and non-essential facilities are defined in IBC, Table 1604.5 and Section 1616.2
b. Indicates masonry specified according to provisions in ACI-530, Chapters 5, 6, or 7
c. Indicates masonry designed according to provisions in ACI-530, Chapters 2, 3, or 4
Verify that mortar mix designs are proportioned in accordance with ASTM C270
Verify that grout mix designs are proportioned in accordance with ASTM C476 or that
grout strength tests per ASTM C1019 indicate adequate grout strength
Verify that constitutive mortar and grout materials conform to ASTM C270 and
C476 respectively
18
Verify that mortar mixing is performed in accordance with ASTM C270
Verify that grout mixing is performed in accordance with ASTM C476
Mortar mixing should be done in a mechanical batch mixer for 3 to 5 minutes. Any
mortar that stiffens or is not used within 2 ½ hours should be discarded.
Grout mixing can be performed on site or by a ready mix supplier. Grout mixing on site
should be done mechanically for a minimum of five minutes. Ready mix grout should
be mixed for approximately one minute after water is added. It is important to achieve a
workable slump (8-11 inches) for proper consolidation of grout.
Verify that block dimensions, and site tolerances are within permissible limits
Variation from a level condition at the top of elements and courses, variation from a plum
condition for walls, and variation of the in-plan location of elements must be verified to
be within site tolerances listed in ACI 530.1-Article 3.3 G, Item 2.
Verify that reinforcing type, size, and placement are in conformance with
contract documents
See Section 1.2.3.1 for commentary on the inspection of welded reinforcing steel.
Verify minimum anchor size and location per ACI 530, Section 1.2.2(e)
Verify proper anchorage type and embedment per contract documents
19
Prior to grouting, verify that cells are clear of debris and that cleanouts are
provided at bottom course of lifts exceeding five feet
Verify that grout locations are in conformance with contract documents
Verify that placement of grout is within time and lift limits specified in ACI 530.1,
Article 3.5 (Article 3.6 C for bonded prestressed masonry)
Two methods are available for evaluating the compliance of masonry construction with
specified strength requirements: unit strength method and prism tests. Each requires
sampling of materials during construction. It is the responsibility of the special inspector
to verify that the sampling and handling procedures are consistent with the appropriate
ASTM standards.
The unit strength method establishes a compressive strength of masonry based on its
constitutive parts: grout, block, and mortar. To determine the compressive strength of the
grout it must be sampled and tested in accordance with ASTM C1019. This is the only
field sampling requirement for the unit strength method. Concrete blocks are typically
certified by concrete suppliers as being in compliance with the ASTM standard specified
in the contract documents (typically ASTM C90). Therefore no sampling of block is
required during construction for the unit strength method. Mortar proportioning and
mixing is required to meet ASTM C270 standards for Type M, S, or N mortar. The
verification of proper proportions of materials and proper construction of mortar joints is
the best method for the quality control of mortar. It should be noted that the field mortar
cube test, specified in ASTM C780, is not required to demonstrate compliance with
ASTM C270, and is an inappropriate test for evaluating the strength of mortar in a wall.
Prism tests may yield higher values for the design compressive strength of masonry, but
are more costly and typically used for special cases only. The method required that
20
activity, not the sampling itself. IBC 1708.1 should be referenced for guidance regarding
the appropriate sampling frequency to be specified.
1.3.4 Timber
Section 1704.6 of the 2003 International Building Code provides general special
inspection requirements for timber construction. There are no specific requirements for
conventional wood frame construction. On the other hand, high-load diaphragms
designed using the strength values from Table 2306.2 of the 2003 International Building
Code must be installed with special inspections. For these panels, the special inspector
must verify the wood structural panel grade and thickness, nominal size of framing at
adjoining panel edges, the nail or staple diameter and length, number of fastener lines, and
spacing of all fasteners. It should also be noted that Section 1707.3 (Seismic Design
Categories C, D, E, and F) requires seismic force resisting system components of timber
construction (field gluing, nailing, bolting, anchoring, and other fastening; struts; braces;
hold-downs) be installed with periodic special inspections. Field gluing requires
continuous inspections, but all other inspections may be periodic. For lightly loaded shear
walls, there is an exception for shear panels and/or diaphragms with fastener spacings that
exceeds four inches on center.
Section 1704.7 provides special inspection requirements for site preparation, during fill
placement, and evaluation of in-place density when the placement of fill is at least 12 in.
deep. Special inspections are not required when the fill depth is less than 12 in. The
special inspector must verify that the site has been prepared in accordance with the
approved soils report. Although the preparation requirements are project specific, typical
requirements include the removal of all deleterious material and establishment of a proper
excavation depth. While the fill is being placed and compacted, the special inspector must
verify that the appropriate material is used and that a maximum lift thickness is not
exceeded. The special inspector must also verify that the achieved in-place dry density of
the compacted fill complies with the approved soils report.
Section 1704.8 provides special inspection requirements for pile foundations. Special
inspections for driven piles shall be performed in accordance with the inspection
requirements of the approved soils report. In general, the special inspector shall record
data from the pile installations of each pile and the results of all load tests. The cutoff and
tip elevation of each pile shall be recorded relative to a permanent reference. There is no
major impact of special inspections on pile installations in South Carolina since piles are
already inspected and tested in accordance with the approved soils report. Again, the
21
major differences are that technicians are being replaced with approved special inspectors
and the contractual relationship is required to be between the special inspector
and the owner.
Section 1704.9 states that special inspections are required for drilled pier foundations in
Seismic Design Categories C, D, E, and F. Since drilled piers are typically constructed
using reinforced concrete, they are also subject to the concrete special inspection
requirements presented above, but they are not exempted by the requirements of Section
1704.4 for these seismic design categories.
contractor to perform both inspections and South Carolina not requiring the contractor
to perform all the identical inspections required of the special inspector is warranted
22
at this time.
23
2.0 Special Inspection Policy and Enforcement
2.1 Special Inspection Programs - Best Practices
SEA of SC has reviewed special inspection programs in neighboring states and across the United
States to develop a summary of the best practices of special inspections. Instead of summarizing
how different states/jurisdictions are handling special inspections, this section highlights
components of certain programs that have proven to effective. SEA of SC applauds the efforts of
Mecklenburg County, NC and many of the recommendations in this section are based on the
highlights of their program and conversations with their program directors.
California has, by far, the most proactive policies regarding special inspections and enforcement is
stringent at the local level. The California Council of Testing and Enforcing Agencies (
HYPERLINK "http://www.cctia.org" www.cctia.org) is an organization that is dedicated to
“fostering, promoting, and encouraging through education, the practice and profession of materials
testing and inspection services.” SEA of SC’s Statement of Special Inspections Forms in
Microsoft Excel Format are similar in content to their Special Inspection Guidelines document
available from their website. The SEA of SC document is more comprehensive and in accordance
with the 2003 International Building Code. Hence, jurisdictions are encouraged to use it for
auditing and reviewing special inspection practices and reports. California is known for its
auditing practices and SEA of SC strongly encourages auditing of special inspectors, particularly
during the first few years of Chapter 17 enforcement. The City of San Diego has special
inspection requirements that help ensure that unqualified special inspectors do not slip through the
cracks ( HYPERLINK "http://www.sandiego.gov/development-services/industry/pdf/ds320b.pdf"
www.sandiego.gov/development-services/industry/pdf/ds320b.pdf). They use a point system
where 8 points must come from either education or experience. A three point minimum is
required for each category. This is in addition to demonstrating technical competence and an oral
interview with the city.
Fulton County, GA handles a large area with a small number of code enforcement officers; one.
SEA of SC does not recommend such a small staff for any jurisdiction in urban South Carolina. A
small staff requires the jurisdiction to rely too heavily on the special inspectors and no auditing can
be performed. On the other hand, Fulton County has put a lot of effort into their program’s
development and they do have good ideas not commonplace in the Southeastern United States.
They allow personnel in training to perform inspections similar to an engineer in training that is
designing a building. The certified special inspector is responsible, but can review the personnel
in training’s work as often as he or she deems necessary. Fulton County also has special inspector
qualifications that adhere to ASTM E329. Hence, the inspection firm must be under the direction
of a full time PE and there is a hierarchy of inspectors to include a field supervisor and inspectors
that work under this individual. All inspectors must have certification unless they are inspectors in
training as identified above.
The remaining portion of this section is devoted to the special inspection program in place in
Mecklenburg County, NC. SEA of SC believes that Mecklenburg County’s special inspection
program is the most organized and user friendly program that SEA of SC has reviewed in the
Eastern United States. A full summary of the program is presented here, and more information
can be obtained from the website ( HYPERLINK "http://www.meck-si.com" www.meck-si.com).
Mecklenburg County has spent hundreds of thousands of dollars developing a comprehensive,
self-running, paperless (i.e., web based) system for special inspections that allows their code
enforcement officers to focus their time on the departments other needs. The website is now
undergoing a public test.
24
The program can best be described by the fulfillment of 6 steps (modified from HYPERLINK
"http://www.meck-si.com" www.meck-si.com and used with permission).
Step 3 – Pre-Construction
Prior to any work being performed at the jobsite, the DSI shall download and complete the
Statement of Special Inspections (SSI) with the project information. The DSI does not create the
SSI, but types it into the system based on the contract documents provided by the DPIRC. Then
the DSI contacts the Building Inspector (by cell phone) to set up a meeting time and date
acceptable to both parties for the Pre-Construction Meeting. The DSI is to enter the Pre-
Construction Meeting information on the Statement of Special Inspections (SSI), complete the
form, upload it to meck-si.com, and contact the Building Inspector (by cell phone) to notify
him/her that it has been uploaded.
25
the Referenced Standard, or the Statement of Special Inspections (SSI). Any document uploaded
to meck-si.com containing information about Non-Conforming Work shall be electronically
tagged as containing Non-Conforming Work on meck-si.com. Any work deemed to be Non-
Conforming shall be immediately brought to the attention of the Contractor and registered Design
Professional in Responsible Charge (DPIRC) for correction. This information and all related
documents shall be uploaded to meck-si.com and tagged as Non-Conforming Work. If these
Discrepancies are not corrected by the completion of that phase of work the Discrepancies shall be
brought to the attention of the Building Inspector. The Designated Special Inspector (DSI) is
responsible for resolving or documenting the resolution of all Discrepancies. If structural
members are being fabricated off site, the Special Inspections Firm (SIF) shall verify that the
Fabricator conforms to the requirements set forth in the 2003 International Building Code. At the
conclusion of the Fabricator’s work, the Fabricator shall submit a Fabricator’s Certificate of
Compliance to the DSI.
Standard forms for the Statement of Special Inspections, Special Inspections Final Report, DPIRC
Checklist, and Pre-construction Meeting Checklist are available at HYPERLINK
"http://www.meck-si.com" www.meck-si.com. Mecklenburg County has also consulted with the
insurance industry and provided the following information to design professionals:
2) SC jurisdictions should consider making the best practices mentioned in Section 2.1 part of their
special inspection programs.
26
Eddie Prince, AIA, Esquire has agreed to present a summary of their program to South Carolina
Code Enforcement Officers at The Citadel at a date yet to be determined.
4) The State of South Carolina should perform an economic analysis and consider purchasing the
software program developed by Mecklenburg County for use in South Carolina. It is anticipated
that savings shall be a multiple of the fee paid for the program.
27