Professional Documents
Culture Documents
1 Academic N Classroom Lunglei - Edited
1 Academic N Classroom Lunglei - Edited
2 PCC Rs 1238061.56
3 RCC Rs 17423711.14
8 Flooring Rs Err:509
9 Plastering Rs 2627267.87
10 Painting Rs 2438423.04
Total Rs Err:509
1.4 2.17 Filling available excavated earth (excluding rock) in trenches, plinth, sides
of foundations etc. in layers not exceeding 20cm in depth, consolidating
each deposited layer by ramming and watering, lead up to 50 m and lift
upto 1.5 m.
Foundations
F1 32 1.8 1.8 1.7 176.26 cum
F2 10 1.4 1.4 1.7 33.32 cum
Plinth filling
Ground Floor 1 Area= 369.00 0.45 166.05 cum
S.Total= 375.63 cum
Deduct (Col. Upto G.L.)
Sqr. Columns
C1
n 32
b 0.45 m
d 0.35 m
h 1.70 m
Academic Building
2.1 4.03 Providing and laying in position cement concrete of specified grade
excluding cost of centering and shuttering - All work upto plinth level:
(a)1:3:6(1 cement :3 course sand :6 stone aggregate 20mm
nominal size)
Foundations
F1 32 1.80 1.80 0.10 10.37 cum
F2 10 1.40 1.40 0.10 1.96 cum
Plinth Retaining base
Ground Floor 10 6.00 0.40 0.10 2.40 cum
24 5.00 0.40 0.10 4.80 cum
3 4.00 0.40 0.10 0.48 cum
10 1.90 0.40 0.10 0.76 cum
Side drain 2 120.00 1.00 0.15 36.00 cum
Steps 3 4.00 0.30 0.10 0.36 cum
Apron 1 115.00 0.60 0.10 6.90 cum
Ground Floor 1 Area= 369.00 0.10 36.90 cum
Courtyard 1 45.00 15.00 0.10 67.50 cum
Total 168.43 cum 7350.60 1238061.56
3.1 5.28 Providing and laying in position machine batched, machine mixed and
5.30 a) machine vibrated design mix M-20 grade reinforced cement concrete
excluding cost of centering and shuttering and reinforcement in -
a) All work upto plinth level.
Foundations
Rectangular portions
F1 32 1.8 1.80 0.20 20.74 cum
F2 10 1.4 1.40 0.18 3.53 cum
Trapezoidal portions
F1
n 32
h 0.4
A1 1.80 1.80 3.24
A2 0.75 0.75 0.56
0.5(A1+A2)*h*n 24.32 cum
F2
Academic Building
Level 2 Beam
B1 (6.00m) 10 6.00 0.35 0.50 10.50 cum
B2 (5.0m) 14 5.00 0.35 0.45 11.03 cum
B2 (4.5m) 2 4.50 0.35 0.45 1.42 cum
B2 (4.0m) 2 4.00 0.35 0.45 1.26 cum
B3 (1.9m) 15 1.90 0.25 0.50 3.56 cum
B4 (5.0m) 15 5.00 0.25 0.45 8.44 cum
B4 (4.5m) 1 4.50 0.25 0.45 0.51 cum
B4 (4.0m) 1 4.00 0.25 0.45 0.45 cum
B5 (1.9m) 5 1.90 0.25 0.45 1.07 cum
B3 (1.5m) 4 1.90 0.25 0.45 0.86 cum
CB(1.25m) 8 1.25 0.35 0.45 1.58 cum
Level 3 Beam
B1 (6.00m) 10 6.00 0.35 0.50 10.50 cum
B2 (5.0m) 14 5.00 0.35 0.45 11.03 cum
B2 (4.5m) 2 4.50 0.35 0.45 1.42 cum
B2 (4.0m) 2 4.00 0.35 0.45 1.26 cum
B3 (1.9m) 15 1.90 0.25 0.50 3.56 cum
B4 (5.0m) 15 5.00 0.25 0.45 8.44 cum
B4 (4.5m) 1 4.50 0.25 0.45 0.51 cum
B4 (4.0m) 1 4.00 0.25 0.45 0.45 cum
B5 (1.9m) 5 1.90 0.25 0.45 1.07 cum
B3 (1.5m) 4 1.90 0.25 0.45 0.86 cum
CB(1.25m) 8 1.25 0.35 0.45 1.58 cum
Level 4 Beam
B1 (6.00m) 2 6.00 0.35 0.50 2.10 cum
B2 (5.0m) 8 5.00 0.35 0.45 6.30 cum
B3 (1.9m) 2 1.90 0.25 0.50 0.48 cum
Roof Beam
B1 (6.00m) 5 6.00 0.35 0.50 5.25 cum
B2 (5.0m) 9 5.00 0.35 0.45 7.09 cum
B2 (4.5m) 3 4.50 0.35 0.45 2.13 cum
B5 (1.9m) 5 1.90 0.25 0.45 1.07 cum
Mumty Beam
B1 (6.00m) 2 6.00 0.35 0.50 2.10 cum
B2 (4.0m) 3 4.00 0.35 0.45 1.89 cum
B2 (1.9m) 2 1.90 0.35 0.45 0.60 cum
Total 110.37 cum
Slab
Academic Building
3.2 5.18 Steel reinforcement for RCC work including straighthening, cutting,
bending, placing in position and binding all complete.
b) TMT bars of grade Fe-500 or more
Foundations @ 100.00 kg/cum 53.38 5338.00 kg
Columns @ 310.00 kg/cum 68.55 21250.50 kg
Beams @ 270.00 kg/cum 143.45 38731.50 kg
Slabs @ 100.00 kg/cum 234.30 23430.00 kg
Staircase @ 120.00 kg/cum 17.83 2139.60 kg
Chajjas @ 80.00 kg/cum 11.07 885.60 kg
Total Rebar= 91775.20 kg 101.60 9324360.32
3.3 5.10 Centering and shuttering including strutting,propping etc. And removal of
form for:
a) Foundations, footings, bases of columns etc. for mass concrete.
Foundations
A=n*(2L+2B)*t n L B t Area
F1 32 1.8 1.8 0.15 34.56 sqm
F2 10 1.4 1.4 0.15 8.40 sqm
Total 42.96 sqm 359.10 15426.94
3.4 5.13 Providing and fixing MS fan clamp 12mm dia HYSD bar bent to shape
with hooked end in RCC slabs during laying including painting the
exposed portion of loop complete.
1 40.00 40.00 no.
Total 40.00 no. 101.80 4072.00
4.1 6.06 Half brick masonry with first class brick in superstructure above plinth
level upto floor V level.
a) in cement moratar 1:3 ( 1 cement : 3 fine sand )
Ground Floor
10 6.00 3.30 198.00 sqm
16 5.00 3.30 264.00 sqm
2 4.50 3.30 29.70 sqm
3 4.00 3.30 39.60 sqm
4 1.90 3.30 25.08 sqm
8 1.20 3.30 31.68 sqm
15 1.50 3.30 74.25 sqm
4 1.93 2.50 19.30 sqm
2 1.63 2.50 8.15 sqm
First Floor
10 6.00 3.30 198.00 sqm
16 5.00 3.30 264.00 sqm
2 4.50 3.30 29.70 sqm
3 4.00 3.30 39.60 sqm
4 1.90 3.30 25.08 sqm
8 1.20 3.30 31.68 sqm
15 1.50 3.30 74.25 sqm
Second Floor
3 6.00 3.30 59.40 sqm
8 5.00 3.30 132.00 sqm
3 4.00 3.30 39.60 sqm
4 1.90 3.30 25.08 sqm
4 6.00 3.30 79.20 sqm
5 5.00 3.30 82.50 sqm
2 4.50 3.30 29.70 sqm
2 1.90 3.30 12.54 sqm
Parapet 2 19.80 1.20 47.52 sqm
2 8.30 1.20 19.92 sqm
Academic Building
4.2 6.07 Extra for providing and placing in position 2 nos 6mm dia. MS bars at
every third course of half brick masonry.
Quantity same as item no 4.1 1750.87 sqm
Total 1750.87 sqm 75.70 132540.86
5.1 7.08 Coursed masonry with rectangular sized hard stone in foundation upto
one storey above and below ground level including curing etc. complete
a) in cement mortar 1 : 3 ( 1cement : 3 fine sand)
Plinth Retaining 10 6.00 0.40 0.45 10.80 cum
24 5.00 0.40 1.45 69.60 cum
3 4.00 0.40 2.45 11.76 cum
10 1.90 0.40 3.45 26.22 cum
Steps 3 4.00 0.30 0.15 0.54 cum
Retaining Wall
1 68.78 0.92 3.17 200.59 cum
Total 319.51 cum 9190.40 2936424.70
6.1 9.05 Providing Ist class teak wood dressed in frames of chaukhat for doors,
windows, clerestory windows fixed in position.
Chaukhats
Doors
D1 20 2.00 0.10 0.10 0.40 cum
10 1.20 0.10 0.10 0.12 cum
D1a 30 2.00 0.10 0.10 0.60 cum
15 1.20 0.10 0.10 0.18 cum
D2 32 2.00 0.10 0.10 0.64 cum
16 0.80 0.10 0.10 0.13 cum
D3 2 2.00 0.10 0.10 0.04 cum
Academic Building
6.2 9.11 Providing and fixing 1st class local wood panelled shutters for doors etc.
including M.S. butt hinges with necessary screws, etc. complete.
a)40 mm thick.
D1 10 1.2 2 24 sqm
D1a 15 1.2 2 36 sqm
D2 16 0.8 2 25.6 sqm
D3 1 1.5 2 3 sqm
Total 88.60 sqm 3323.60 294470.96
6.3 9.48 Providing and fixing wooden pelmet with 25mm dia wooden curtain
rod and bracket including wooden plugs etc. complete (to be fixed
on masonry or concrete work)
(B)1st class local wood
a) 12mm thick 100mm wide pelmet.
Doors
L=(W + (0.2*2))*n n W
D1 10 1.20 16.00 rm
D1a 15 1.20 24.00 rm
D2 16 0.80 19.20 rm
D3 1 1.50 1.90 rm
Windows
W1 16 1.2 19.2 rm
W2 13 1.2 15.6 rm
AW 21 1 21 rm
V1 34 0.8 27.2 rm
Total 144.10 rm 305.10 43964.91
7.1 14.28 Providing and fixing brass sliding door bolts (aldrops) bright finished with
nuts and screws etc. complete.
a) 300 x 16 mm
D1 10 1 10.00 no
D1a 15 1 15.00 no
D2 16 1 16.00 no
D3 1 1 1.00 no
Total 42.00 no 1213.70 50975.40
7.2 14.29 Providing and fixing Brass Tower Bolts (Socket Bolts) bright finished with
necessary screws etc. complete.
a) 300 mm
Doors
D1 10 4.00 40.00 no
D1a 15 4.00 60.00 no
D2 16 4.00 64.00 no
D3 1 4.00 4.00 no
Total 168.00 no 403.50 67788.00
Academic Building
a) 150 mm
Doors
D1 10 4.00 40.00 no
D1a 15 4.00 60.00 no
D2 16 5.00 80.00 no
D3 1 6.00 6.00 no
Total 186.00 no 287.10 53400.60
7.3 9.54 Providing and fixing dressed & chamfered 1st class teak wood door and
window architrave of size fixed with
b) 75x12mm
L=n*(mb+4h) n b m h L
D1 10 1.20 2 2.00 104.00 m
D1a 15 0.80 2 2.00 144.00 m
D2 16 0.80 2 2.00 153.60 m
D3 1 0.80 2 2.00 9.60 m
Total 411.20 m 222.68 91566.02
7.4 9.56 Factory made PVC door shutters made of styles and rails of a uPVC
hollow section of size 59x24 mm and wall thickness 2 mm with inbuilt
edging on both sides etc.
b) 30mm thick shutter
D3 14 0.80 2.00 112.00 sqm
Total 112.00 sqm 3697.30 414097.60
7.5 9.56 Providing 40 x 5mm flat iron hold fast 40 cm long including fixing to frame
with 10mm dia. bolts, nuts and wooden plugs and embeddings in cement
concrete block 30 x 10 x 15cm 1:3:6 mix (1 cement : 3 sand : 6 well
graded stone aggregate 20 mm nominal size)
D1 10 4 40.00 no
D1a 15 4 60.00 no
D2 16 4 64.00 no
D3 1 4 4.00 no
Total 168.00 no 2219.80 372926.40
7.6 14.36 Providing and fixing bright finished brass hanging type floor door stopper
with necessary screws, etc. complete.
27 1.00 27.00 no
Total 27.00 no 284.30 7676.10
8.2 20.21 15mm cement plaster 1 : 3 (1 cement : 3 fine sand) finished with a
floating coat of neat cement.
Academic Building
9.1 20.65 Applying one coat of cement distemper primer of approved brand and
manufacture on wall surface.
Qtty vide 20mm plaster area 3357.74 sqm
Qtty vide 15mm plaster area 890.21 sqm
Qtty vide 6mm plaster area 2967.48 sqm
Total 7215.43 sqm 127.20 917802.70
9.2 20.67 Distempering with 1st quality acrylic washable distemper of approved
brand and manufacture and of required shade and colour to give an even
shade on new work (two or more coats).
Qtty vide Distemper Primer area 7215.43 sqm
Total 7215.43 sqm 159.50 1150861.09
9.4 20.68 Finishing walls with water proofing cement paint of approved brand and
manufacture and of required shade on new work (three or more coats) to
give an even shade.
Qtty vide 20mm plaster area 3357.74 sqm
Total 3357.74 sqm 102.10 342825.25
9.5 20.51
Applying priming coat with ready mixed pink or Grey primer of approved
brand and manufacture on wood work and plywood complete.
a) Ready mix pink/grey primer.
Qtty vide Panel Door area 88.60 sqm
Total 88.60 sqm 74.40 6591.84
9.6 20.72 Painting with synthetic enamel paint of approved brand and manufacture
in all shades on new work (two or more coats).
b) High gloss
Qtty vide Wood Primer Areas 88.60 sqm
Total 88.60 sqm 142.90 12660.94
9.7 20.76 Varnishing with varnish of approved brand and manufacture on new
work (two or more coats) of glue sizing over an under coat of flatting
varnish.
Academic Building
10.1 12.12
Providing & laying vitrified floor tiles in different sizes (thickness to be
specified by the manufacture) with water adsorption less than 0.08% and
conforming to IS:15622, of approved make, in all colours nd shades, laid
on bed of 20mm thick cement mortar 1 : 4 (1 cement : 4 course sand),
including the joints with white cement and matching pigments etc.
complete as per design colours.
c) Double Charge)
Ground Floor Area= 460.00 sqm
First Floor Area= 466.68 sqm
Second Floor Area= 461.00 sqm
Toilet Block Area= 115.20 sqm
Total 1502.88 sqm 2588.40 3890054.59
10.2 12.13 Providing & laying vitrified floor tiles in different sizes (thickness to be
specified by the manufacture) with water adsorption less than 0.08% and
conforming to IS:15622, of approved make, in all colours nd shades,in
skirting/dado,riser of steps, laid with cement based high polymer
modified quik set tile adhesive(water) based conforming to IS:15477, in
average 6mm thickness, including grouting of joints (payment for grouting
of joints to be made seperately)colours.
c) Double Charge)
Ground Floor Area= 47.64 sqm
First Floor Area= 47.64 sqm
Second Floor Area= 37.20 sqm
Toilet block Area= 182.70 sqm
Total 315.18 sqm 2595.70 818112.73
10.3 12.14
Providing & laying vitrified floor tiles in different sizes (thickness to be
specified by the manufacture) with water adsorption less than 0.08% and
conforming to IS:15622, of approved make, in all colours nd shades, in
skirting/dado, riser of steps, over 12mm thick bed of cement mortar 1:3
(1cement:3 course sand), including the joints with white cement and
matching pigments etc. complete.
d) Digital( Marble look)
Landing Area= 30.83 sqm
Tread Area= 39.94 sqm
Riser Area= 22.26 sqm
Total 93.03 sqm 2907.60 270494.03
11.1 10.16 Steel work welded in built up sections/framed work including cutting,
hoisting, fixing in position and applying a priming coat of approved steel
primer using structural steel etc. as required.
Academic Building
11.2 10.09 Supplying and fixing M.S. decorative railing 80cm high in staircase
consisting of 25mm alluminium square sections inserted into 20mm dia.
M.S. bars @ 30 cm centres 60 x 60 x 4mm thick plate at the base fixed
with wooden wedge by I.W. screws to receive the wooden handrails
12.5cm x 10cm including cost of polishing the wooden rail.
11.3 10.08
Steel work in built up tubular ( round, aquare or rectangular hollow tubes
etc.) trusses etc., including cutting, hoisting, fixing in position and
applying a priming coat of approved steel primer, including welding and
bolted with special shaped washers etc. complete.
Roof Truss
Tie
ISNB 65M 9 12.00 108.00 m
Total 108.00 m
@ 6.53 kg/m 705.24 kg
Rafter
ISNB 65M 18 7.00 126.00 m
Total 126.00 m
@ 6.53 kg/m 822.78 kg
Strut
ISNB 50M 9 2.60 23.40 m
Total 23.40 m
@ 5.10 kg/m 119.34 kg
18 1.80 32.40 m
Total 32.40 m
@ 5.10 kg/m 165.24 kg
18 1.90 34.20 m
Academic Building
12.1 11.01 Providing and fixing anodised aluminium work for doors, windows,
ventilators and partitions with extruded built up standard sections/ other
sections of approved make conforming to IS : 733 and IS : 1285 fixing
with dash fasteners of required dia and size, including necessary filling up
of gaps at junctions, at top, bottom and sides with required PVC/
neoprene gaskets etc. Aluminium sections shall be smooth, rust free,
straight, mitred and jointed mechanically wherever required including
cleat angle, aluminium snap beading for glazing /panelling, CP brass
/stainless steel screws all complete including fixing of glasses but
excluding cost of glasses.
13.1 15.17
Providing and fixing recessed ceiling with 12.5mm tapered Gypboard
which includes providing and fixing G.I perimeter funnels with nylon
sleeves and screws intermediate channels fixed to GI seat and steel
expansion fastener etc. all complete including rounding, filling and
finishing the tapered and square of the board with jointing compound and
two coats of primer suitable to Gypboard.
CL1 1 30.00 13.0 390 sqm
Total 390.00 sqm 2383.30 929487.00
14.1 16.11 Providing Trapezoidal Polyester Coated Galvanised Steel Sheets Roofing
of any colour of 1.06m width at all levels including fitting and fixing
ridging with self drilling , self tapping screws, EPDM washers etc.
complete excluding the cost of purlin, rafter and trusses.
Total Rs 44458210.78
S Total Rs 44458210.78
Internal Water Supply & Sanitary Installation (Estimate attached) Rs 2222900.00
Internal Electrification (Estimate attached) Rs 5557200.00
Add External Services (5% of internal) Rs 389005.00
Fire Fighting (Wet riser system) @ Rs 768.4 per sqm of floor area (870.4sqm) Rs 668815.36
Total Rs 53296131.14
G Total Rs 53296131.14
Say Rs 53296000.00
(Rupees Five crore thirty two lakhs ninety six thousand only)
REBAR QUANTITY
BLOCK A
Particular No Length Dia. w/m Quantity (kg) Quantity (Qtl)
FOOTING
F1 264 1.8 12 0.888 421.9776 4.22
F2 460 1.5 12 0.888 612.72 6.13
S.TOTAL= 1034.70 10.35
Adding 10% as wastage, lapping etc.= 103.47 1.04
S.TOTAL= 1138.17 11.39
COLUMN
C1
FDN TO 2F 112 8.85 20 2.466 2444.2992 24.44
2F TO ROOF 24 3.30 20 2.466 195.3072 1.95
2F TO ROOF 24 3.30 16 1.579 125.0568 1.25
C2
FDN TO 1F 24 5.55 20 2.466 328.4712 3.28
FDN TO 1F 12 5.55 16 1.579 105.1614 1.05
FDN TO 1F 12 5.55 12 0.888 59.1408 0.59
1F TO ROOF 24 3.30 20 2.466 195.3072 1.95
1F TO ROOF 12 3.30 16 1.579 62.5284 0.63
C3
FDN TO ROOF 56 5.55 16 1.579 490.7532 4.91
FDN TO ROOF 56 5.55 12 0.888 275.9904 2.76
COLUMN STIRRUP
C1
FDN TO 2F 72 8.85 8 0.395 541.4976 5.41
14 1.36
2ND TO ROOF 25 3.00 8 0.395 188.02 1.88
14 1.36
C2
FDN TO 2F 72 8.85 8 0.395 197.9424 1.98
6 1.16
C3
FDN TO 2F 45 5.55 8 0.395 288.666 2.89
14 1.16
S.TOTAL= 5498.14 54.97
Adding 10% as wastage, lapping etc.= 549.81 5.50
S.TOTAL= 6047.95 60.47
BEAM
GF
PB 30 6.1 16 1.579 288.957 2.89
55 6.00 16 1.579 521.07 5.21
160 5.00 16 1.579 1263.2 12.63
10 3.50 16 1.579 55.265 0.55
10 2.80 16 1.579 44.212 0.44
FF
B1 (6.1m SPAN) 30 6.10 20 2.466 451.278 4.51
12 6.10 16 1.579 115.5828 1.16
B1 (6m SPAN) 15 6.00 20 2.466 221.94 2.22
6 6.00 16 1.579 56.844 0.57
B2 (5m SPAN) 95 5.00 20 2.466 1171.35 11.71
B2 (2.8m SPAN) 10 2.80 20 2.466 69.048 0.69
B3 (6m SPAN) 48 6.00 16 1.579 454.752 4.55
B4 (5m SPAN) 65 5.00 16 1.579 513.175 5.13
B4 (3.5m SPAN) 10 3.50 16 1.579 55.265 0.55
SF
B1 (6.1m SPAN) 10 6.10 20 2.466 150.426 1.50
4 6.10 16 1.579 38.5276 0.39
B2 (5m SPAN) 30 5.00 20 2.466 369.9 3.70
B2 (2.8m SPAN) 10 2.80 20 2.466 69.048 0.69
B3 (6m SPAN) 18 6.00 16 1.579 170.532 1.71
B3 (6.1m SPAN) 24 6.10 16 1.579 231.1656 2.31
B4 (5m SPAN) 65 5.00 16 1.579 513.175 5.13
ROOF
B3 (6.1m SPAN) 10 6.10 16 1.579 96.319 0.96
B4 (5m SPAN) 15 5.00 16 1.579 118.425 1.18
B4 (2.8m SPAN) 10 2.80 16 1.579 44.212 0.44
STAIR SUPPORT
B4 (3m SPAN) 5 3.00 16 1.579 23.685 0.24
B4 (2.8m SPAN) 10 2.80 16 1.579 44.212 0.44
S.TOTAL= 7151.57 71.50
GF STIRRUP
PB 50 6.1 8 0.395 30.81 0.31
3 0.52
31 3.9 8 0.395 50.9392 0.51
4 1.04
S.TOTAL= 0.82
ROOF
RB 15 5 16 1.58 118.5 1.19
20 3.9 16 1.58 123.24 1.23
S.TOTAL= 2.42
ROOF STIRRUP
RB 40 5 8 0.395 54.036 0.54
3 1.14
31 3.9 8 0.395 61.7148 0.62
4 1.26
S.TOTAL= 1.16
SLAB
GF
BOTTOM 49 9.1 10 0.616 274.6744 2.75
70 6.38 10 0.616 275.1056 2.75
TOP1 49 5.46 10 0.616 164.8046 1.65
42 6.38 10 0.616 165.0634 1.65
TOP2 70 3.83 10 0.616 165.1496 1.65
29 9.1 10 0.616 162.5624 1.63
S.TOTAL= 12.08
G.TOTAL= 5575.44
adding 5% as wastage , splice etc. 278.77
TOTAL= 5854.21
8 0.395
10 0.616
12 0.888
16 1.579
20 2.466
8 0.395
12 0.888
16 1.579
20 2.466
REQUIREMENT OF BUILDING MATERIALS FOR CONSTRUCTION OF ____
Sl. No. Name of items Quantity Required Local Rate Amount (Rs)
1 Cement 3 bags
2 Balu 0.35 cum
3 Rawra 0.00 cum
4 Rebar ( Rod) 20mm 0.00 qntls
5 Rebar ( Rod) 16mm 0.00 qntls
6 Rebar ( Rod) 12mm 0.00 qntls
7 Rebar ( Rod) 10mm 0.00 qntls
8 Rebar ( Rod) 8mm 0.00 qntls
9 Stones 1.37 cum
10 Bricks 57 nos.
TOTAL=
Note: Qty Calculations are based on MPWD SOR Co-efficients for computation of unit requirements
Quantity Calculator as per MPWD SOR coeefic
Rebar 20mm
No. of bars in Section
Lengt of Section
No. of same length section
Anchorage
Splicing/Lap
Total Length(m)
kg/m of bar
Total (kg)
Total (Quintal)
Rebar 16mm
No. of bars in Section
Lengt of Section
No. of same length section
Anchorage
Splicing/Lap
Total Length(m)
kg/m of bar
Total (kg)
Total (Quintal)
Rebar 12mm
No. of bars in Section
Lengt of Section
No. of same length section
Anchorage
Splicing/Lap
Total Length(m)
kg/m of bar
Total (kg)
Total (Quintal)
Rebar 10mm
No. of bars in Section
Lengt of Section
No. of same length section
Anchorage
Splicing/Lap
Total Length(m)
kg/m of bar
Total (kg)
Total (Quintal)
Rebar 8mm
No
Lateral ties
Total Length(m)
kg/m of bar
Total (kg)
Total (Quintal)
MPWD SOR coeeficients Cement
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
2.466 2.466 2.466 2.466 2.466 2.466 2.466 2.466
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1.579 1.579 1.579 1.579 1.579 1.579 1.579 1.579
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0.888 0.888 0.888 0.888 0.888 0.888 0.888 0.888
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0.616 0.616 0.616 0.616 0.616 0.616 0.616 0.616
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0.395 0.395 0.395 0.395 0.395 0.395 0.395 0.395
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Cement
bag
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.2856
0
0
0
3.06
0
0
0
0
0
9 10 11 12 13 14 15
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
2.466 2.466 2.466 2.466 2.466 2.466 2.466
0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 10 11 12 13 14 15
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
1.579 1.579 1.579 1.579 1.579 1.579 1.579
0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 10 11 12 13 14 15
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0.888 0.888 0.888 0.888 0.888 0.888 0.888
0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 10 11 12 13 14 15
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0.616 0.616 0.616 0.616 0.616 0.616 0.616
0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 10 11 12 13 14 15
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0.395 0.395 0.395 0.395 0.395 0.395 0.395
0 0 0 0 0 0 0
0 0 0 0 0 0 0