CWDS Project
CWDS Cost Management Plan July 2018
Revision History
Revision / Date of Author Summary of Changes
Version # Release
2
CWDS Project
CWDS Cost Management Plan July 2018
Table of Contents
1. EXECUTIVE SUMMARY .................................................................................................................. 0
2. INTRODUCTION .............................................................................................................................. 0
2.1. PURPOSE ................................................................................................................................. 0
2.2. COST MANAGEMENT PLAN SCOPE ............................................................................................ 1
2.3. DOCUMENT DEVELOPMENT AND MAINTENANCE.......................................................................... 2
3. ORGANIZATIONAL STRUCTURE .................................................................................................. 3
3.1. KEY STAKEHOLDERS ................................................................................................................ 3
3.2. ROLES AND RESPONSIBILITIES .................................................................................................. 4
3.2.1. Project Sponsor/ELT ....................................................................................................... 4
3
CWDS Project
CWDS Cost Management Plan July 2018
List of Tables
TABLE 2-1 STAKEHOLDER MATRIX.............................................................................................................. 3
TABLE 3-1 FUNDING DOCUMENT THRESHOLDS .........................................................................................10
TABLE 4-1 SUCCESS CRITERIA/MEASURES ...............................................................................................16
4
CWDS Project
CWDS Cost Management Plan July 2018
5
CWDS Project
CWDS Cost Management January 2017
1. EXECUTIVE SUMMARY
The purpose of this Cost Management Plan is to document the processes and
guidelines for ensuring the project is completed within budget and adheres to all
applicable State and federal regulations pertaining to cost management. This plan has
the following objectives:
• Define the roles and responsibilities of project stakeholders involved in the cost
management process.
• Define the cost management approach.
• Define cost management success criteria and measurements.
1. Plan Cost Management – This process establishes the policies, procedures and
documentation for planning, managing, expending, and controlling project costs.
The development of this plan will assist with this effort.
2. Estimate Costs – This process estimates the project costs of the CWS-NS
solution and involves developing an approximation of the monetary resources
needed to complete all project activities.
3. Determine Budget – This process develops the project budget with the
estimated costs of the CWS-NS effort and involves aggregating estimated costs
from project control documents and developing the project baseline budget via
the State and federal budgeting process.
4. Control Costs - The last step is to control project costs to ensure there are no
cost overages.
2. INTRODUCTION
2.1. Purpose
The purpose of this Cost Management Plan (hereafter called the “plan”) is to document
the processes and guidelines for ensuring the Child Welfare Digital Services (CWDS),
Child Welfare Services - New System (CWS-NS) Project (hereafter called the “Project”)
is completed within budget and adheres to all applicable State and federal regulations
pertaining to cost management.
0
CWDS Project
CWDS Cost Management January 2017
• Define the roles and responsibilities of project stakeholders involved in the cost
management process.
• Define the cost management approach.
• Define cost management success criteria and measurements.
Estimate Costs
This second step is to estimate the project costs of the CWS-NS solution. This process
involves developing an approximation of the monetary resources needed to complete all
project activities.
Determine Budget
The third step is to develop the project budget with the estimated costs of the CWS-NS
effort. This process involves aggregating estimated costs from project control
documents and developing the project baseline budget via the State and federal
budgeting process. This process establishes a baseline budget against which project
performance can be monitored and controlled.
Control Costs
The last step is to control project costs to ensure there are no cost overages. This
process will provide the means to recognize cost management variance from this plan
and take corrective action when necessary to minimize risk.
Adhering to these core processes will help ensure that the Project is completed within
the cost parameters identified in the Project’s latest approval documents.
1
CWDS Project
CWDS Cost Management January 2017
2
CWDS Project
CWDS Cost Management January 2017
3. ORGANIZATIONAL STRUCTURE
The Project organization is an integrated team consisting of staff from the Office of
Systems Integration (OSI), the California Department of Social Services (CDSS),
counties, consultants, and other stakeholders. The OSI project management provides
assistance to ensure State and federal requirements are met and the Project is
completed according to scope, schedule and budget. The Project is sponsored by
CDSS who retains ultimate ownership and responsibility of the Project. Material
changes to scope, schedule or budget must be reviewed and approved by the Project
Sponsor prior to initiation.
The Project is supported by both OSI and CDSS centralized services (Human
Resources for hiring staff, fiscal for all budgetary concerns, Information Security Officer
for security concerns, Acquisition Contracting Services Division (ACSD) for acquisitions,
Information Technology Office of IT support, executive management for project
direction, etc.) and consultant services.
Sections 2.1 and 2.2 discuss the CWS-NS Project key stakeholders and their roles and
responsibilities respectively.
3
CWDS Project
CWDS Cost Management January 2017
4
CWDS Project
CWDS Cost Management January 2017
• Tracks and reconciles project budget in accordance with State processes and
policies.
• Reviews and validates Financial Information Systems of California (FI$Cal)
reports match records of expenditure approvals.
• Works with the OSI Accounting Office to resolve any FI$Cal discrepancies.
• Provides oversight of the project cost management activities and reports to the
Project sponsor.
• Submits an Independent Project Oversight Report (IPOR) monthly that includes a
summary of the Project’s current budget status and provides an assessment of
whether the Project is projected to be within budget based on the metrics defined
in the IPOR.
• Approves or denies project approval documents.
• Identifies risks to the budget.
• Validates the Project is adhering to this plan.
5
CWDS Project
CWDS Cost Management January 2017
3.2.7. Legislature
The DOF has the following responsibilities within the cost management process:
3.2.8. Counties
Responsible for submitting requests for reimbursement of staff time for participation in
application and organizational change management (OCM) training, travel expenditures
and other allowable costs.
6
CWDS Project
CWDS Cost Management January 2017
• Scope: The Project estimate will be based on other State projects of similar size
and complexity.
• Schedule: The schedule will be used to estimate the time it takes to complete
project activities and will drive the cost of the Project.
• Department of General Services (DGS) Leverage Procurement Agreements
(LPA): The DGS LPAs will be used to estimate the prevailing wages for
consultant services.
7
CWDS Project
CWDS Cost Management January 2017
• Office of Technology (OTech) Service Catalog: The OTech Service Catalog will
be used to calculate future data center services costs and service requests.
• State Staff
• County Staff
• Consultant Staff
8
CWDS Project
CWDS Cost Management January 2017
9
CWDS Project
CWDS Cost Management January 2017
DEVELOPMENT SUBMITTAL
DOCUMENT FEDERAL/STATE
THRESHOLD TIMEFRAME
APD Federal Generally when Varies
funding is projected
to expire within 60
calendar days
BCP/SFL State Any change to Annually in
baseline budget September (BCP) or
January (SFL)
Premise State Changes to Local Annually during the
Assistance budget November
Subvention Process
and May Revise
Process
APD – An APD is a document used to obtain federal approval and FFP for project
activities. All APDs must conform to the regulations identified in 45 CRF 95 and any
other requirements stipulated by ACYF. APDs are submitted to the ACYF for review and
approval.
Note: There are several types of APDs that the Project will be required to submit to
ACYF. The type of APD is contingent on several factors including project phase,
urgency and timing. All required APDs are defined in 45 CRF 95.
BCP/SFL –The BCP or SFL is the traditional decision document which proposes a
change to the existing budget level.
Note: The difference between a BCP and SFL is the timing of the document. The BCP
is developed during the November Subvention process prior to release of the
Governor’s Budget, while the SFL is developed during the May Revise process.
10
CWDS Project
CWDS Cost Management January 2017
Note: Although OSI’s CWS-NS’ budget resides in the CDSS Local Assistance budget,
this budget is converted to State Operations dollars upon reimbursement from CDSS,
therefore any baseline changes to OSI’s spending authority requires a BCP or SFL.
Both OSI and CDSS are responsible for developing any change proposals in
coordination with their respective centralized budget offices. Once the change proposal
is completed by the Project, the budget offices are responsible for coordinating final
approval and submitting the document to DOF. Once at DOF, the budget office acts as
the liaison between the Project and DOF for any questions or inquiries.
After completion of budget hearings, each subcommittee votes on the change proposal
and submits a report to the full committee. The full budget committee may accept the
change proposal or amend it. The revisions are incorporated into the budget bill and
sent to the full membership of each house for consideration. Each house discussed and
then votes on its version of the budget bill. If there are differences between the
Assembly and Senate versions, these are worked out in the joint budget conference
committee. If there is no delta between the Assembly and Senate versions, the change
is incorporated into the Revised Governor’s Budget and sent to the Governor (as part of
the Budget Act) for signature and enactment.
Once the Budget is enacted, the Project must review the Budget Act to ensure there is
no delta between the change proposal and what was included in the Budget Act. If there
is a difference, the Project must adjust the budget to match the Budget Act. It is
important to note that the approved budget may not be equivalent to the cost estimates
11
CWDS Project
CWDS Cost Management January 2017
provided in the approval documents since the Administration and Legislature can modify
the budget requested by the Project. This process occurs after approval of the SPR and
these documents will not have to be updated unless the changes meet reporting
requirements identified in the SAM.
1. Expenditure Tracking and Reporting – This identifies the approach the Project
uses to track and report costs.
2. Cost Variance – This identifies the approach of managing variances to the
Project budget.
3. Project Acquisitions – This defines the approach of procuring goods and services
to support project activities.
4. Consultant Costs – This defines the approach of managing consultant contract
budgets to ensure they remain within budget.
5. County Costs – This defines the approach of managing county costs associated
with county staff time and OCM.
6. Annual Cost Closeout – This defines the approach of reconciling annual project
costs.
7. Project Cost Closeout – This defines the approach of reconciling project costs at
project closure.
8. Budget Issue/Risk – All budget risks or issues will follow the project risk and
issue management process.
1. CDSS State Operations Budget – Personnel services costs and OE&E for CDSS
staff.
2. OSI Spending Authority Budget – A portion of the CDSS Local Assistance budget
in which OSI has authority to spend. This budget funds all OSI personnel, OE&E
and consultant services costs.
12
CWDS Project
CWDS Cost Management January 2017
3. CDSS Local Assistance Budget – Local Assistance costs for CWS-NS effort.
This budget includes all CDSS consultant services and county costs for training
and OCM activities.
The Project currently tracks expenditures using Microsoft Excel spreadsheets. CDSS is
responsible for tracking and managing the CDSS State Operations and their Local
Assistance costs, while OSI is responsible for tracking and managing the OSI spending
authority costs. However, OSI has the responsibility for reporting all project costs,
inclusive of OSI and CDSS, to control agencies in monthly reports.
Actual expenditures are provided monthly via FI$Cal reports to both OSI and CDSS.
Once these reports are received, the OSI and CDSS Fiscal Analysts will validate all
expenditures in the report and record them into the expenditures report. In the event
that there are any discrepancies between approved invoices and actual expenditures
reported in FI$Cal, they will work with their accounting offices to resolve and correct any
problems.
Once all costs are received and validated, they are reported monthly to CDT via the
Project Status Report (PSR). The PSR is due to the OSI Budget Office by the fifth of
each month for transmittal to CDT. This report indicates the Project’s current level of
spending and provides cost overrun projections.
On an annual basis, as directed under Government Code Section 11546.2 and SAM
Sections 4903.2, the Statewide Information Management Manual (SIMM) 55 requires
actual and projected IT costs be reported to CDT. This process assists the Project and
CDT in ensuring costs are being properly tracked and managed.
13
CWDS Project
CWDS Cost Management January 2017
Once the purchase order for goods or services has been issues to the vendor, the
Fiscal Analyst encumbers the funding in the expenditures report. This process ensures
that sufficient funding will be available for all project acquisitions.
The Fiscal Analyst processes the invoices and coordinates their review. This process
must be expeditious as the invoice must be approved by the Project within five days and
sent back to the accounting offices for payment. This will ensure there is sufficient time
to dispute an invoice if necessary. The Fiscal Analyst tracks the approved invoices and
compares this to the annual encumbrance. Using previously approved invoices, the
Fiscal Analyst can project whether a contract is expected to exceed the budget. The
Fiscal Analyst reports this information to the Contract Manager who then works with the
Functional Manager and consultant to update the TAP to ensure there are sufficient
hours to complete scheduled tasks. Should a consultant exhaust their annual allotted
hours or budget, the Project can either move hours or contract dollars from a future
fiscal year to use in the current year if this is permitted in the contract language. It is
important to note that if future contract dollars are moved to a different fiscal year, the
existing project budget must be able to absorb those additional costs because unless
there is an associated change proposal and As-Needed APDU, the baseline budget
cannot be changed. Moving funding between fiscal years cannot result in an increase to
the total contract cost unless there is an associated contract amendment. The Project
must work with their respective accounting and acquisition offices when adjusting
encumbrance dollars.
Once the Systems Integrator contract is awarded, this plan will be updated to document
the process for tracking those costs.
14
CWDS Project
CWDS Cost Management January 2017
implementation of the CWS-NS solution. Once this process is established this plan will
be updated.
Upon acceptance of a candidate risk, the Project may be required to report a change to
State and federal control agencies if reporting thresholds are met. The Project should
refer to reporting requirements identified in SAM section 4819.36 and 45 CFR 95 for
State and federal requirements, respectively. Once the reporting document has been
approved, the Project may need to develop a budget request to modifying the Project
baseline budget accordingly.
15
CWDS Project
CWDS Cost Management January 2017
SUCCESS
PHASE DESCRIPTION MEASURE BOUNDARY
CRITERIA
This plan has
been approved
Project cost and identified
Approval of this
management processes have None
plan.
approach defined. been
successfully
executed.
SPRs and
APDs have
been
developed and SPR and APD
Project costs are
approved in have all been None
estimated.
time for state approved.
and federal
budget
process.
All BCPs or SFLs
and APDs have
been Continued
developed and project funding
Project budget is
approved in is included in None
established.
time for state State and
and federal Federal budget.
budget
process.
Project
expenditures
Project PIER
does not
Project is indicates project
exceed
executed within remained within None
estimated
budget. estimated
budget in
budget.
approval
documents
16
CWDS Project
CWDS Cost Management January 2017
5.2. Reporting
Project costs are reported monthly in PSR and IV&V reports. The Project is required to
develop annual APDUs and As-Needed APDUs (if reporting thresholds are met) to
report on project status and costs.
5.3. Assumptions
The following assumptions pertain to this plan:
5.4. Constraints
The effectiveness of this plan depends upon the following:
• The general fiscal health of the State and federal governments allow the
availability of continued funding.
17