Professional Documents
Culture Documents
Spool Fabrication Procedure - Template
Spool Fabrication Procedure - Template
WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 1 of 14
PROCEDURE
WSM-PSFP-01
Revision Summary
INDEX
2 REFERENCE DOCUMMENT........................................................................................................5
3 DEFINITION AND ABBREVIATIONS............................................................................................5
4 RESPONSIBILITIES......................................................................................................................5
4.1 Production Engineering...........................................................................................................5
4.2 Supervisor................................................................................................................................5
4.3 Quality Control.........................................................................................................................5
5 PIPING SPOOL FABRICATION PROCEDURE................................................................................6
5.1 General.....................................................................................................................................6
5.2 Material Preparation...............................................................................................................6
5.3 Cutting and Marking.................................................................................................................6
5.4 Machining (Bevelling, Threading and Drilling).........................................................................6
5.5 Fit Up/Assembly.......................................................................................................................7
5.6 Dimensional Control/Fit Up Inspection....................................................................................7
5.7 Welding....................................................................................................................................8
5.8 Visual Weld Control.................................................................................................................8
5.9 Non Destructive Testing/X-Ray (If Required)...........................................................................8
5.10 Hydrostatic Test.....................................................................................................................9
5.11 Painting (If Required).............................................................................................................9
5.12 Other Treatment (If Required)...............................................................................................9
7 ATTACHMENT..........................................................................................................................13
7.1 Flow Chart of Piping fabrication process (Carbon Steel)........................................................13
7.2 Flow Chart of Piping fabrication process (Exotic Materials)..................................................14
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 5 of 14
2 REFERENCE DOCUMMENT
Piping Fabrication shall be in accordance with latest edition of the following international
codes and standards.
4 RESPONSIBILITIES
4.1 Production Engineering
Production Engineering is responsible to verify the completeness and correctness of the
piping isometric drawings and the spool drawing which should be used as a reference for the
fabrication operation. Production Engineering also responsible to issue out material take off for
material preparation purpose.
4.2 Supervisor
Supervisor is responsible ton ensure that all the piping fabrication activity are conducted
as per approved procedure, achieve desired quality as per required by spec/ client
expectation. Prepared and execute detailed schedule and manpower planning to achieve
master schedule by Planner.
Method for workshop progress tracking and material traceability other than above can be
used, such as using a work progress sheet and/or welding follow up sheet. Final record of
workshop progress reporting has to be compiled.
1. Check the sizes, obtain nominal diameter and schedule number (pipe, elbow,
tee, etc).
2. Check the bend radius (elbow).
3. Check the pressure rating and flange facing
(flange). 4. Record down the heat number (pipe)
5. Check for any defect: pitting, corrosion, buckling, flattening, ovality, etc.
H N (H e a t N u m b e r )
Material m a n sh ou l d b e ta k e care the marking from
any damage and replaced it if is unreadable.
5. To maintain material traceability, heat number of each material should be
written in the spool drawing for each pipes and fitting.
6. Bring cut pipe to worktables on machining/bevelling area.
7. The spool drawing should follow these materials to the next step of fabrication.
8. Pipe fitters fill the workshop progress sheet.
1. Pipe fitter done the cutting work should do the bevelling work, in any case where
the pipe fitter doing both work is different persons, the pipe fitter doing
bevelling work shall verify the name plate to obtain correct spool pieces
information.
2. If original material identification marking is to be cut or material divided into two
or more pieces, the heat no, and pipe item code no, shall be transferred to each
of the pieces prior to cutting.
3. Pipe fitter shall collect other fittings related to the cut pipe (elbow, tee, red, etc)
as per drawing necessary. These fitting should be placed on the same worktables
for the same pipes spool/spool drawing.
4. Do bevelling work with the help of machine vices. Use grinder (disc and straight)
if necessary. Bevel parameters should be followed and as per required by the
WPS for correct root and edge facing. For carbon steel pipes end result should
be bright metal finish.
5. Bevelled pipes and fitting should be moved to assembly/fit up box.
6. Pipe fitters fill the workshop progress sheet.
1. Pipe fitter done the bevelling work should do the assembly work, in any case
where the pipe fitter doing both work is different person. The pipe fitter doing
assembly work shall verify the name plate to obtain correct spool pieces
information.
2. Pace the pipes/fitting in the pipes jack, assemble other pipes/fitting as per spool
drawing.
3. Align the pipes and fitting using pipe clampers.
4. Check the alignment result with welding gauge for misalignment, root gap etc.
5. Tack weld on the pipes if necessary as per applicable tack weld.
6. Clean the pipes weld joint preparation.
7. Pipe fitters fill the workshop progress sheet.
This step may be done in the same assembly box where the pipe being assembled. In case
any fault/ discrepancies. Comments for repair work shall be directly given to the pipe fitter
team.
Pipe fitters/ piping supervisor need to check below parameters internally before request
for inspection to QC team:
1. The welding work will be carried out in the same box where the pipes being
assembled, the pipe fitter should back to the material preparation work/cutting
work for next spool.
2. Welder need to ensure that weld preparation joint are clean and free of all
extraneous matter such as grease, dirt, scale, rust, water, etc that may affect the
weld quality.
3. Conduct preheat (when required by WPS).
4. Conduct welding work as per WPS.
5. Fill workshop progress sheet.
6. Fill welding follow up sheet.
7. AwAfatietrin wg evlidsuinagl ,t seesnt,t N thDeT painpde h sypdorooltse tsot) s.
torage area (this is only storage area for
1. Bring the pipe spools from Fabrication area (after Visual result) to NDT area.
2. QC team arranges NDT work.
3. NDT result obtained.
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 9 of 14
4. When the weld joint are found failed during NDT(mark on row NDT is failed on
welding matrix) bring the pipes to assembly box or fabrication area, welding
supervisor and his team have to directly carried out repair work, fill wielding
follow up sheet and work progress sheet.
1. Bring the pipe spools from NDT area to Hydrotest area (usually the area is same
area).
2. Layup pipe spools on the hydrotest area.
3. Prepare the blank flange and other hydrotest equipment.
4. Conduct hydrotest work as per pressure required.
5. Obtain the hydrotest result.
6. When the result is leak during hydrotest (mark on row NDT is failed on welding
matrix) bring the pipes to assembly box or fabrication area. welding supervisor
and his team have to directly carried out repair work.
7. Depressurize the water and clean the water inside pipes with compressed air
blow.
8. Collect the pipe spools and sent to storage area(this storage area is means
collection of pipes passed the test and ready to paint or erection).
Methods for passivation are determined later as per project requirement (either acid bath
method or passivation gel method).
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 10 of 14
Prevent direct contact between pipe spools with ground or floor by using wood support.
Pipe spools should be storage with grid basis. This grid basis is a storage system that divided
the pipe spools base on installation sequence by pipe material (carbon and Exotic), location of
installation, isometric drawing numbers and spool drawing numbers, and separate storage
area between after fabricated to be inspection test and pipe spools has been passed the test
or painted. Material controller should be prepared Database on spreadsheet for monitoring
flow pipe spools (flow pipe spools is how many fabricated spools, storage area, passed test
spools or not, painted spools and include with spool numbers.)
Forklift, use for taking out pipe from rack (if any) or storage area, lifting
materials and transfer materials. Specially protection for the fork should be used
for
fabricated pipe spools and exotic materials.
Mobile crane/overhead crane and lifting equipment should be used nylon
slings,
for exotic materials separate set of slings should be used for each type of
materials.
Trailers should be used protection floor/crates/support for fabricated pipe
spools and exotic materials.
To minimized ferrous contamination following preparation should be taken for exotic material
pipe shop:
1. All handling equipment, such as sling of crane, fork of lift truck, hook of chain
block etc should be a non metallic material or protected by clean wood, cloth or
plastic buffer to avoid iron contact with exotic pipes material surface.
2. All working bench, working tools and working consumables such as machine
vices, pipes clamp, grinding disk etc should be a non iron material or be isolated
with the rubber, wood, a stainless steel plate etc.
3. Each equipment and tools as described above shall be used for one type of
material only. Storage are of equipment and tools shall be segregated. An
identification code system shall be established for above segregation.
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 11 of 14
4. Each pipe, pipe fittings, assembled pipe spools. Welded pipes spool shall not be
storage directly into the ground. These item should be storage on wooden bar
at least a 150mm from the ground or on a fully surface cover with wood.
5. Walking, stepping or placing any items above corrosion resistance piping items
strictly prohibited.
6. A clean room must be established on the exotic materials pipe shop. A ventilation
1. Use tools as designated, stainless steel cutting disk for stainless steel only,
stainless steel wire brush for stainless steel only so on.
2. Eliminated contact between ferrous tools with the exotic pipes. For example, use
insulator on the machine vices, stainless steel lining on the hammer head etc.
3. Worktables have to use wood protection on top of it.
4. Pipe jack, pipe fit up clamp and other tools in contact directly with the exotic
materials have to be insulated or made by same grade of the materials.
Large wood panel should be installed to guarantee welding segregation between different
type of exotic pipe materials.
1. When transport the pipe spools with forklift, the fork has to be protected by
wood crates or similar protection.
2. Carried out X-Ray as per procedure.
3. When NDT process has finished, material man shall install back protection cover
to the pipe spools.
4. Inform the supervisor after successful result, or not mark on row NDT is failed on
welding matrix and bring the pipes to assembly box or fabrication area.
6.7 Passivation
Passivation is a process to enhance the spontaneous formation of the protective passive
film on an anticorrosion material surface. Passivation process for this exotic material normally
consist of following step:
1. Descaling, removal of heavy, tightly adherent oxide films resulting from hot
forming, heat treatment, welding and other hot work operations. Descaling can
be done either using chemical descaling (acid pickling) or mechanical descaling
(abrasive blasting, power brushing etc)
2. Cleaning, all operation necessary for the removal of surface contaminates from
metal to ensure maximum corrosion resistance, prevention of product
contamination and achievement of desired appearance. Some of the methods
used to do cleaning area vapor degreasing, water jetting, acid cleaning, steam
cleaning and mechanical cleaning.
Selection of any method for detailed passivation process shall be determined during
project execution.
6.8 Preservation
To maintain the quality of anticorrosion properties of exotic pipes material and to prevent
the deterioration of pipes surface finish, a special care shall be given during pipe spools
storage and handling after fabrication.
1. All the pipes opening shall be sealed with air tight closures after passivation
process.
2. End closures shall be durables and securely attached to the pipes such they will
remain intact and in position during transfer, handling and storage.
3. Flange end connection can be sealed by wooden blank or plastic cap (similar
material), secured using wire or tightened with bolt and nut at least in 4 holes
bolt. Unflagged pipes and connection can be sealed by plastic cap or similar
material and wrapped with protecting tape 50mm around the pipe cap joint.
Threaded and connection, whenever possible, should be sealed by means of
threaded plastic or similar material so that the pipes thread will be protected.
4. Pipes cannot be directly storage in the ground, wooden support should be used.
5. When the pipe spools are storage in outdoor a method for covering with
tarpaulin
or similar material should be established.
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 13 of 14
7 ATTACHMENT
7.1 Flow Chart of Piping fabrication process (Carbon Steel)
Doc. No. WSM-PSFP-01
PIPING SPOOL FABRICATION Rev. 0 11/03/19
PROCEDURE Page 14 of 14