Professional Documents
Culture Documents
INTERNATIONAL
NIGERIA LIMITED
GENERIC HYDROTESTING
PROCEDURE
ITEM PAGE
1.0 Scope 3
2.0 References 3
3.0 Definitions and Abbreviations 3
4.0 Responsibilities 3
4.1 Technical Manager 3
4.2 Project Manager 3
4.3 Foreman 4
4.4 Quality Control Department 4
4.5 Safety and Cashes Manager 4
5.0 Pressure Testing Procedure
5.1 Preparation 4
5.2 Flushing 5
5.3 Hydrostatic Testing 5
5.4 Hydrotesting 5
5.5 Filling 6
5.6 De-Watering and Drying 6
5.7 System Re-instatement 6
5.8 Hydrostatic Test Acceptance Criteria 7
5.9 Test equipment Requirements 7
5.10 Quality Control Inspection 8
5.11 Test Pressure 8
5.12 Test duration 8
5.13 Safety 8
2.0 REFERENCES:
Project Drawings
API-5L
ASME B31.3
ASME B31.4
ASME B31.8
API-RP-1110
API-1104
4.0 RESPONSIBILITIES:
The Implementation of this Procedure is carried out by the Technical Manager, Project Manager,
Construction Manager, the Quality Control Department/ Representative and the Safety/ CASHES
Manager/ designee.
4.1 TECHNICAL MANAGER:
Shall review the drawings and draw up plan for the execution of the Project Scope of Work.
Draw up Plan for the Hydro-test based on Project Schedule.
4.3 FOREMAN:
Responsible for assuring that the work activities are performed within the specified
requirements.
5.2 FLUSHING :
All facilities to be tested shall be flushed with potable water prior to hydrostatic testing at full
volume to clear any debris and to ensure that there are no restrictions.
Flushing of system will be performed with one pump. Preferably should be a variable head
pump allowing high flow rate.
5.4 HYDROTESTING:
The Quality control department shall ensure that the preparation of the test package is done in
accordance with AFC drawings, relevant Codes and Client Specifications by the Construction
Manager/ Superintendent or his designee. Verification has to be made to guarantee that all NDT’s
has been carried out. Fill system with water, when filling is completed, Pressurizing will begin as
outlined in what follows. Pressure will be brought up to approximately twenty five (25%) of test
pressure and held for a period of time to check for leakage and pressure equalization/
stabilization. If no indication of leakage is detected, the medium will be pressured up to fifty (50%)
of the test pressure and checked for leakage, stabilization is also carried out. The medium can then
be pressured up to the test Pressure. The system will be monitored periodically during the test. If
the pressure falls below the minimum test Pressure during the test, the cause of fluctuation shall
be ascertained and rectified. The hold duration must be maintained only for test pressure that is
stable. If the rate and magnitude of the pressure drop can be accounted for by a corresponding
change in temperature, the test will continue after re-pressurization, taking into consideration the
elapsed test time prior to falling below the minimum test pressure. If leaks are found during test,
the leaks shall be repaired and the system is retested as per Client specification.
If the Pressure begins to rise due to thermal expansion, the Pressure will be adjusted so that over-
pressurization does not occur and this adjustment will be noted on the Recorder Chart.
Test medium shall be clean potable water not less than 60F temperature.
Pressure gauges and recorders shall be used for the test and gauges will be located at highest and
lowest elevations of the test system. The test pump shall be disconnected from the system as soon
as the test pressure is attained.
5.5 FILLING:
The system to be tested shall be filled with potable Water. All air shall be bled from vents and high
Points after filling. All valves, which will not be Isolated, shall undergo the pressure Test in the
full open position.
The test shall be accepted if, all pressure containing components in the test section maintain their
integrity and no leaks are found. Any reduction in pressure outside the limits specified, or
KANTAS International Nigeria Limited Page 5
QMS-QP-22: Hydro-test Procedure
variation in temperature which cannot be accounted for shall result in test failure, such as loose
bolts and/fittings, leaking gaskets, test pump failure, air entrapment or weld failure, shall be
located and rectified. The Client Representative and KANTAS QC Personnel shall certify the test
report.
Calibration certificates shall be issued Calibrated Instruments. Calibrated Instrument shall be valid
for a period of 6 months. Pressure indicators used for testing shall preferably have dials graduated
on a range at least 11/2 times the intended maximum test Pressure.
When inspection reveals unacceptable items, these will be entered into the Inspection Log for
tracking if these can be brought back into compliance with the applicable contract documents,
specifications or codes. When corrective action will not bring these items back into compliance,
non-conformance Report shall be generated.
5.13 SAFETY:
Considering the inherent dangers involved with Hydrostatic Pneumatic Testing, Safety shall be
the major concern. The following steps shall be minimum precautions before and when any
system is under Pressure:
Job safety Analysis.
Warning sign shall be posted at suitable Location shall be barricaded to prevent access by all
non-essential personnel.
No attempt to repair leaks shall be made while the system is under Pressure.
High Pressure Test hoses shall be inspected by Test Personnel before use and shall be
KANTAS International Nigeria Limited Page 6
QMS-QP-22: Hydro-test Procedure
installed and routed to avoid possible tripping hazards.