0% found this document useful (0 votes)
155 views303 pages

Process Integration @oildoc

The maximum possible heat recovery is 14MW. The minimum utility requirement is -12MW of cooling. PROCESS INTEGRATION www.ChemEng.ir ‫مهندسان شیمى تهران‬ Three-Stream Problem Stream Type Supply Temp Target Temp ∆H (MW) 1 Cold 40°C 100°C 10 2 Hot 150°C 50°C -8 3 Hot 120°C 80°C -6 PROCESS INTEGRATION www.ChemEng.ir ‫مهندس

Uploaded by

Amin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
155 views303 pages

Process Integration @oildoc

The maximum possible heat recovery is 14MW. The minimum utility requirement is -12MW of cooling. PROCESS INTEGRATION www.ChemEng.ir ‫مهندسان شیمى تهران‬ Three-Stream Problem Stream Type Supply Temp Target Temp ∆H (MW) 1 Cold 40°C 100°C 10 2 Hot 150°C 50°C -8 3 Hot 120°C 80°C -6 PROCESS INTEGRATION www.ChemEng.ir ‫مهندس

Uploaded by

Amin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

‫‪www.ChemEng.ir‬‬
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS
INTEGRATION

M.R. OMIDKHAH

TMU
CHEMICAL ENGINEERING
DEPARTMENT

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 1
Introduction

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

200°C

35°C
RECYCLE

R
TO COLUMN

200°C
Purge
190°C CW
153°C
35°C
141°C
40°C Design as usual
115.5°C 126°C ΣH=1722
128°C
ΣC=645
114°C
FEED 5°C
6 Exchanger Unit

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

200°C RECYCLE
35°C
Design with Targets:
R ΣH=1068
ΣC=0
200°C
4 Exchanger Units
PURGE

35°C

TO COLUMN 126°C
FEED 5°C

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

ΣH=-38%

REACTOR ΣC=-100%
RECYCLE REACTOR
UNITS=-33% RECYCLE

AREA=-15%

FEED
PRODUCT
PRODUCT BETTER
FEED PROCESS
BASE CASE
INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What is better process


integration all about?
 Better process design
 Reduction in utility costs
 Reduction in emissions
 Better utilization of capital

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 1
Cool 180°C
COND 1
CP=20
60°C R2
80°C
120°C
C1
Heat
3
CP=80 R1

REB 100°C
130°C 120°C
Cool Heat 4
2
CP=40 CP=36

40°C 30°C

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

SOLUTION 1

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 1
Target Heat
Supply
Stream No. Temperature Capacity
Temperature Flowrate
& Type
(ºC) (ºC) (KW/ºC)
1 Hot 180 80 20
2 Hot 130 40 40
3 Cold 60 100 80
4 Cold 30 120 36
∆Tmin=10ºC
Utilities: Steam at 200ºC, C.W. at 25ºC 30ºC
Design a network of steam heaters, water cooler
and exchangers.
Use heat recovery in preference to utilities.

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The Popular Favorite


100º 120º

H 1200
85º
180º 1 80º
2000

49º
130º 2 C 40º
3240 360

60º 3 30º 4

Cooling No. of
Steam
Water Units
1200 360 4

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Experience
Most people have a cup
of coffee once they have
found the “popular
favorite”

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The “Winner”(Strictly Speaking)


100º 120º

H 800 H 160
90º 116º
180º 1 80º
2000
60º

70º 43º
130º 2 C 40º
2400 1080 120

60º 3 30º 4

Steam Cooling No. of


Water Units
960 120 6

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The “Winner”(Morally)
100º 120º

H 978
2000
87.8 º
180º 1 80º

64.4º

74.4º
130º 2 C 40º
2222 1240 43.4º 138

60º 3 30º 4

Steam Cooling No. of


Water Units
978 138 5

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The “System Buster”(∆Tmin=6.6ºC)


100º 120º

H 840
2000
180º 1 80º
89.5º
64.4º

71º 1240
130º 2 40º
2360

60º 3 30º 4

Steam Cooling No. of


Water Units
840 0 4
www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 2
Setting Energy Targets

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

COND 180°C
2000
60°C R2

80°C
120°C
C1
H 1200
R1

REB 100°C
130°C 120°C
360
C 40°C
3240
30°C
Steam CW Units
1200 360 4
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

 Are
1200 units of steam
necessary?

 Whatis the minimum


energy requirement?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Let’s first look at the


concept of heat recovery

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The T-H Diagram


T

130º
2
=
P
C
=
CP
m

40º

H
∆H=180

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Two – Stream Heat Recovery


Problem

Supply
Target Temp
Stream Type Temp. ∆H(MW)
TT(ºC)
Ts(ºC)

1 Cold 40 110 14

2 Hot 160 40 -12

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Two-Stream Heat Recovery


Problem
T
180º
110º
160º

am 3MW
e
110º tr 95º 1MW
S
ot e am
160º
H r 40º
St 50º
∆Tmin=10º old 11MW
40º C
20º
40º

H
QCmin=1MW QHmin=3MW
QREC=11MW

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Streams can be shifted


T
horizontally
180º 110º
160º
m 4MW
ea
110º tr 90º 2MW
S
ot e am 160º 40º
H r
St 60º
∆Tmin=20º ld 10MW
Co
40º
20º 40º

H
QCmin=2MW QHmin=4MW
QREC=10MW

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What about several hot and


several cold streams?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem
H=27MW
FEED 2 H=-30MW
230º PRODUCT 2
140º REACTOR 2
200º 80º
REACTOR 1 250º
FEED 1 180º
OFF GAS
20º
H=32MW H=-31.5MW 40º

40º
PRODUCT 1
40º

A simple flowsheet with two hot streams


and two cold streams
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stream Data
Heat
Supply Target
capacity
Stream Type Temp. Temp ∆H(MW)
flowrate
Ts(ºC) TT(ºC)
CP(MWºC-1)
Reactor 1
Cold 20 180 0.2 32
feed
Reactor 1
Hot 250 40 0.15 -31.5
product
Reactor 2
Cold 140 230 0.3 27
feed
Reactor 2
Hot 200 80 0.25 -30
product

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Composite Curve
T T

5
250

.1
=0
CP
200
5

.4
.1

25
0
=0

P=
0.

C
=
CP

CP

15
80

0.
=
40 CP
H
H
31.5 30
61.5 6 48 7.5
61.5
(A) Hot streams (B) Hot Composite
plotted separately
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The cold streams can also be


combined to obtain a cold composite
T T

3
230

0.
=
3

CP
0.
=
180 P
C 0 .5
=
CP
140
2
0.
=

2
CP

0.
=
CP
20
H H
32 27 24 20 15
59 59
The cold streams can also be combined to
obtain a composite cold stream.
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Plotting the hot and cold composite curves


together gives the utility targets
Qhmin=7.5
T
250

Pinch
150
140
∆Tmin=10º

20
Qcmin=10
H
QREC=51.5
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Increasing ∆Tmin Increases hot and


cold utilities
T Qhmin=11.5
250

150 Pinch

∆Tmin=20º
=20

20
Qcmin=14
H
QREC=47.5

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Optimum ∆tmin Can be found by economic


trade-offs between energy and capital
T T

1 2

H H

COST TOTAL
ENERGY

CAPITAL

∆T min
1 2 OPT
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Summary
T QHmin
200

150
∆Tmin

20
Qcmin
H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stream data, ∆T min

Construct composite curve

Energy targets

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

A Very Important
Conclusion

We can set
TARGETS
Prior to design

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 3
The Problem Table
Algorithm
(Cascade Diagram)

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stream Data

“Composite Curves”

Energy Targets
But,Complicated
Better:

“The Problem Table”

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 2

COND COND
80º
100º
100º

C1 C2
135º Cold R1
Shot

Heat Heat
CP=2 CP=4 140º
REB REB

150º 170º
20º Cool Cool
CP=1.5 CP=3

30º 60º

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 2
Supply Target Heat capacity
Stream Type
Temp. Ts(ºC) Temp TT(ºC) flowrate CP(MWº/C)

1 Cold 20 135 2

2 Hot 170 60 3

3 Cold 80 140 4

4 Hot 150 30 1.5

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Scale ∆T min=10º Cold Scale


3
170º 160º
60
1.5
150º 140º
2.5
145º 135º
-82.5
90º 80º
4
75
60º 50º
-15
30º 20º
2

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Scale ∆T min=10º Cold Scale


170º 160º
60
150º 60 140º
2.5
145º 62.5 135º
20
-82.5
0
90º 80º
75
75
60º 50º
-15
30º 60
20º

60 To cold utility
QHmin = 20
90º HOT
QCmin = 60 Pinch Temp.
80º COLD
www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 4
The Heat Recovery
Pinch

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T

PINCH

Qcmin
H
The Pinch Sets Absolute Limits for
Process Heat Recovery

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T

PINCH
(HOT)
∆T min
PINCH
(COLD)

Qcmin
H
For a Practical ∆T min THOT ≠ TCOLD

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T

Heat
Source

∆T min Heat
PINCH Sink

Qcmin
H
The “pinch” divides the problem
into a heat source and heat sink

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T
PINCH
Heat Source

Heat Sink

Qcmin
H
Sink in heat balance with QHmin
Source in heat balance with Qcmin
zero cross-pinch transfer
www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What happens if we
transfer heat across
the pinch?

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T
Possible

∆T min

Qcmin
H

It is possible to transfer heat from


above the pinch to below the pinch.

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T

∆T min

Not Possible

Qcmin
H

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin+α
T
e
bov
A
α

low
Be

Qcmin+ α
H
If we transfer α units of heat across the pinch

QHmin and Qcmin are both increased by α


www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design Rules

 Do not use hot utility below

 Do not recover process heat across

 Do not use cold utility above

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

OR:
 Keep source (below) and sink (above) separate
 Use hot utility above and cold utility below
T QHmin

Se
p ar
at e

Qcmin
H

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 5
Heat Exchanger Network
Representation

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Conventional Flowsheet
Where is the PINCH?
R2
R1
D1

Feed

D2

Product

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The pinch is much more


clearly shown on:

“Grid Diagram”

Which only shows heat transfer


operations

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Typical Grid Diagram

Hot 1

Hot 2 C

Cold 1

H Cold 2

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Rules for construction


 Hot streams run left to right
 Cold streams run right to left
 Hot streams on top;cold streams on
bottom
 Hot utility= H
 Cold utility= C
 Heat exchanger between streams=

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot 1

Hot 2 C

Cold 1

H Cold 2

Where is the pinch?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Pinch is easily shown:

Pinch

100º 100º
Hot 1

100º 100º
Hot 2 C

90º 90º
Cold 1

90º 90º
H Cold 2

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot1

Hot2 C
“Allowed”
Cold1

H Cold2

Hot1 C

Hot2
“Forbidden”
H Cold1

Cold2

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 6
Minimum Number of
Units

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Back to Example Problem 2


Supply Target
Stream Type CP ∆H
Temp. Ts(ºC) Temp TT(ºC)

1 Cold 20 135 2 230

2 Hot 170 60 3 330

3 Cold 80 140 4 240

4 Hot 150 30 1.5 180

Qcmin= 60
QHmin=20

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Ut. Stream 2 Stream 4


Sources 20 330 180

110 120
20 60

220

Stream 1 Stream 3 Cold Ut.


Sinks
230 240 60

No. of Exchangers = No. of Streams + No. of Utilities - 1

5 = 4 + 2 - 1

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Ut. Stream 2 Stream 4


Sources 20 330 180

210 120
20 60
120

Stream 1 Stream 3 Cold Ut.


Sinks
230 240 60

No. of Exchangers = No. of Streams + No. of Utilities - 1

5 = 4 + 2 - 1

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Ut. Stream 2 Stream 4


Sources 20 330 180

20
100 120 60

230

Stream 1 Stream 3 Cold Ut.


Sinks
230 240 60

No. of Exchangers= No. of Streams + N0. of Utilities - 1

5 = 4 + 2 - 1

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Ut. Stream 2 Stream 4


Sources 60 330 180

60 230 100 180

Stream 1 Stream 3 Cold Ut.


Sinks
230 240 100

No. of Exchangers= No. of Streams + No. of Utilities


- Independent Systems

4 = 4 + 2 - 2

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Ut. Stream 2 Stream 4


Sources 20 330 180

220 120
10 10 60
110

Stream 1 Stream 3 Cold Ut.


Sinks
230 240 60

No. of Exchangers = No. of Streams + No. of Utilities


+ No. of Loops - Independent Systems
6 = 4 + 2 + 1 - 1

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 7
Heat Exchanger Network
Design for Maximum
Energy Recovery

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Rules so far:
No exchanger has a temperature
difference < ∆Tmin.

No process to process heat


transfer across the pinch

No heat transfer across the pinch


by inappropriate use of utilities

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 2

COND COND
80º
100º
100º

C1 C2
135º Cold R1
Shot

Heat Heat
CP=2 CP=4 140º
REB REB

150º 170º
20º Cool Cool
CP=1.5 CP=3

30º 60º
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example Problem 2
Heat capacity
Supply Temp. Target Temp.
Stream Type flowrate
Ts(ºC) TT(ºC)
CP(MW/ºC)

1 Cold 20 135 2

2 Hot 170 60 3

3 Cold 80 140 4

4 Hot 150 30 1.5

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Grid Presentation

Pinch
CP
90º 90º
170 2 60º 3

90º 90º 1.5


150 4 30º

80º 80º
135 1 20º 2

80º 4
140 3

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Above the Pinch Design

170º 2 90º

150º 4 90º

135º 1 80º

140º 3 80º

Which match?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design Rules
 Start from pinch and move away

 Observe FCpout ≥ FCpin for every


pinch match

 Tick off at least one stream with


each match

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Generally
Start with the biggest stream “In”
CP
170º 90º
2 3

150º 90º
4 1.5

135º 80º
1 2

140º 80º
3 4

This leaves one more pinch match to place

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Two Matches

90º
170 2

150 4 90º

80º
135 1

140 80º
3

Now, how much heat should


these matches transfer?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Maximise loads to “Tick Off” streams Next step: ”Fill in


(Keeps capital costs down) the rest”

∆H CP
170 90º 170 90º
240 2 3 2

150 90º 150 90º


90 4 1.5 4

125º 80º 1 125º 80º 1


110 135 2 135 H
90 20 90

80º 80º
240 140 3 4 140 3
240 240

QHmin=20
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Below the Pinch Design Place Pinch Match

CP
90º 90º 60º
2 60º 3 2

90º 90º 30º


4 30º 1.5 4

80º 20º 1 2
80º 20º
1

Cpout ≥ Cpin
Start with stream 1 Only 1 option!

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Maximise load to Fill in the rest(1)


“Tick off” stream

CP
90º 90º
2 60º 3 2 60º

90º 90º 70º


4 30º 1.5 4 30º

80º 35º 20º 1 2


80º 35º 20º 1
90 90 30

What next?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Fill in the rest

2 90º 60º

90º 70º
4 C 30º
60

80º 35º 20º


1
90 30

QCmin=60

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Above Below
PINCH

90º 90º
170 2 60º

90º 90º 70º


150 4 C 30º
60
125 80º 80º 35º
135 H 1 20º
20 90 90 30
80º
140 3
240
QHmin=20 QCmin=60

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Completed design

170º 90º
2 60º

150º 90º 70º


4 C 30º
60
135º
H
125º 80º 35º 20º
1
20 90 90 30
140º 80º
3
240

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

80°C

100°C 140°C

135°C
C1 C2
R1
20 H Cold
Shot
150°C
140°C 170°C
90
240

20°C 30 90
60 C
60°C
30°C
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design for Maximum Energy Recovery


Divide problem at the pinch
Start at the pinch and move away
Start with biggest streams “IN”
Observe CPout ≥ CPin for all pinch
matches
Maximize loads on each match
Fill in the rest

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LOOP

170º
2 60º

150º
4 C 30º
60
20º
135º H 1
20 90 90 30
80º
140º 3
240

PINCH

Each loop means you can reduce one exchanger.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

In order to break the loop and reduce the number of


exchangers remove the exchanger with the smallest heat
load in loop.
∆Tmin violation

170º 90º
2 60º

150º 70º
4 C 30º
60
65º 20º
135º H 1
20 125º 120 90

140º 80º
3
240 Path

Path ia a connection between hot and cold


utilities which passes from or near the
exchanger with violation
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

This should be changed to 75º

CP
170º 90º
2 60º 3

150º 70º
4 C 30º 1.5
60+X
65º 20º
135º H 1 2
20+X 125º 120-X 90

140º 80º 4
3
240

150 − (120 − X ) / 1.5 = 75


X = 7.5
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Final design with 5 exchanger


CP
170º 90º
2 60º 3

150º 75°
4 C 30º 1.5

67.5
121.25º 65º 20º
135º H 1 2
112.5 90
27.5

140º 80º 4
3
240

7.5 unit of hot and cold utilities are


sacrificed in order to reduce one exchanger

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

WORKING SESSION 7

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Exercise 1
Supply Temp. Target Temp. Heat capacity
Stream Type
Ts(ºC) TT(ºC) flowrate CP(MW/ºC)

1 Hot 180 80 20

2 Hot 130 40 40

3 Cold 60 100 80

4 Cold 30 120 36

∆T min=10ºC
Utilities:Steam at 200ºC, C.W. at 25ºC
Design a network for Maximum Energy
Recovery
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Temperature(ºC) QHmin=960 kw

70 ºC PINCH

60 ºC

QCmin=120 kw Enthalpy(kw)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Solution 7

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

CP
180º 80º
1 20

130º 70º 40º


2 40

100º 60º
3 80

120º 60º 30º


4 36

QHmin=960 kw QCmin=120kw

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

CP
180º 80º
1 20

130º 70º 43º 40º


2 C 40
120

100º 90º 60º


H 3 80
800 2400

120º 115.6º 60º 60º 30º


H 4 36

160 2000 1080

QHmin=960 kw QCmin=120kw

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 8
Stream Splitting

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Above the pinch: PINCH

100º
1

100º
2

100º
3

T>90º 90º
4

T>90º 90º
5

What do we do?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Split a cold stream PINCH

100º
1

100º
2

100º
3

90º
4

90º
5

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Rule:

Above the pinch, NH ≤ NC

 NH=Number of hot streams


 NC=Number of cold streams

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Below the pinch:


PINCH

100º T<100º
1

100º T<100º
2

90º
3

90º
4

90º
5

What do we do?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Split a hot stream:


PINCH

100º
1

100º
2

90º
3

90º
4

90º
5

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Rule:
Below the pinch, NH ≥ NC

 NH=Number of hot streams


 NC=Number of cold streams

General Rule:
always observe Nout ≥ Nin

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example problem:
NH ≥ NC
But no appropriate CP match
PINCH
CP
100º
1
5

100º
2 4

90º
3 7

No feasible match!
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Solution:
CPH ≥ CPC
NH ≥ NC

5 4
7
4 3
CP PINCH

100º
5 1

100º
4 2
4
7
3
3
90º

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What about?
CPH ≥ CPC
NH ≥ NC

5 3.5
7
4 3.5
Or:
CPH ≥ CPC
NH ≥ NC

5 4.5
4 2.5 7

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Branch flow rates =degree of


freedom in design

Finding the best choice=


optimization problem

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Summary Above the pinch:


Stream data at pinch

YES CPH ≤ CPC YES


For pinch matches?
NH ≤ NC

NO NO

Split cold stream

Split hot stream

Place Matches

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Summary Below the pinch:


Stream data at pinch

YES CPH ≥ CPC YES


For pinch matches? NH ≥ NC?

NO

NO Split Hot stream

Split Cold stream

Place Matches

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Working session 8

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Working session 8
Supply Temp. Target Temp. Heat capacity
Stream Type
Ts(ºC) TT(ºC) flowrate CP(MWºC-1)

1 HOT 750 350 0.045

2 HOT 550 250 0.04

3 COLD 300 900 0.043

4 COLD 200 550 0.02

∆T min=50 ºC
QHmin=9.2 Mw
QCmin=6.4 Mw
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Grid diagram:
PINCH CP

750º 550º 350º


1 0.045
0.

550º 250º
2 0.040
0.

900º 500º 300º


3 0.043

550º 500º 200º


4 0.020

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Solution 8

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PINCH CP
750º 550º 350º 0.045
1
550º 250º 0.04
2
900º 500º 300º 0.043
3
550º 500º 200º 0.02
4

0.4MW
750º 550º 350º
1 C

6MW 250º
550º
2 C

900º 500º 300º


H 3
9.2MW 8MW 8.6MW
550º 500º 200º
4
1MW 6MW

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 9
Area Targeting

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Ideal Exchanger: Counter-Current

T
Heat load

1 Q
A= ×
U ∆TLM
Q
Resistance Driving Force
H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Real Exchanger:Not Counter-Current

A>Amin

PROCESS INTEGRATION
H
www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Likewise
A B
A B

C
C

T A>Amin
T A=Amin A
A B
B

C
C

H
H
Non-Counter Current
Counter-Current(Vertical) (Criss-Cross)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

For uniform h-values


Temperature(ºC)

Enthalpy(kw)

The vertical model guarantees


A=Amin
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Counter current heat transfer in interval


Temperature(ºC)

Hot streams q1,q2,..

150º
Interval

120º 120º

100º Cold streams q1,q2,..

Enthalpy(kw)

Hot stream in each interval only matches


with Cold Stream in the same interval
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Spaghetti Design
CP
150º 30 T(ºC) Minimum Area
120º
36 Network
6

150º
10
12
2
120º
120º

15 100º
30
15
qh
9
Enthalpy(kw)
12 j
3 1 q

120º 100º
Ai = ( )
( ∆ T LM ) i Stream h
Temperature profile is the same for every match
And corresponds to that of the composite curves.
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Temperature(ºC)

5 6

3
2

Enthalpy(kw)
6 1 j
q 
Network Area: AMin = Σ( Ai ) = ∑  × ∑ ( )
int erval 
 ∆T LM Stream h 

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Experience:
Good practical designs are
within 10% of the area
target
This also accounts for the h-
value approximation

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Having area target,


how do we estimate capital cost of the network?

Let’s start with a single exchanger

An exchanger cost model can be presented as:

Ex. cost = a + bAc


a = cost constant due to installation
b = cost constant due to material of construction
c = cost constant due to type or pressure

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What about capital cost of the network?

If there is Nmin exchangers in the network


and the total minimum area of the whole
network is Amin then the cost can be found as:

  Amin 
C

Network cost = N min ×  a + b  
  N min  

What are the assumptions used in this cost model?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Homework 1

Following assignment (including


four problems) is due to be
returned in three weeks.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 10

Shell targeting

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Bowman et al.(1940):

Q=UA∆TLMFT 0<FT<1
FT=f(R,P)
P ≡ Thermal effectiveness
R ≡ Ratio of two heat cap. Flowrates
T Hi − T Ho C PH TCo − TCi
P = R= =
T Hi − T Ci C PC THi − THo
Rule of thumb:
Kern (1950): FT ≥ 0.75

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Taborek(1979,1983)&Liu et al.(1985)

(∂FT / ∂P) R = const.

Mitson (1984) gives the expression for


(∂FT / ∂P) R for 1-2 shell & tube exchanger:

FT (1 − P) FT2 β α
(∂FT / ∂P) R = [ ] −[ ][ − ]
P(1 − P) 2P (2 − β P) (2 − α P)

Where: α = 2 − 2
β = 2 + 2

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

A constant slop line for FT=0.75 at R=1


has (∂FT / ∂P) R = −2.8

An Alternative Approach

This approach is based upon


observation that for any value of “R”
there is a maximum asymptotic value
for P, say Pmax when FT tends to -∞

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Mitson (1984):
Pmax = 2 2
(R + 1 + R + 1)
at P=Pmax design will not be feasible P
should be less than PMax.

P=XPPMax
where: 0<XP<1

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design with Multiple 1-2 shells

The designer often encounters


situations where Ft is too low or the
design is too sensitive when using a
single 1-2 shell.
In such cases either different type of
exchanger or multiple 1-2 shell should
be considered.

Traditional Approach ⇒ Trial & Error

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Example:
410°C 110°C
360°C 0°C
410 − 110 360 − 0
P= = 0.73 R= = 1.2
410 − 0 410 − 110
Try one shell ⇒ infeasible (see graph 1-2)
Try two shells ⇒infeasible(see graph 2-4)
Try three shells ⇒FT=0.65(see graph 3-6)
Try four shells ⇒FT=0.8(see graph 4-8)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping-off Method (Bell & Liu et al.)

A conservative way of applying


this method which allows no
temperature cross, normally
gives more shells than required.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping - off
Temperature

410°°
3 4 5
360°°

1 2 110°°

0°°

∆H
5 Shells suggested
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping – off with Pre-Specified FT


The unknown temperatures for first step, Tho
and TCi ; can be calculated using equations:
FT=f(R,P)
R=(TCo – TCi)/(Thi-Tho)
P= (Thi – Tho)/(Thi-TCi)

Note that: R,FT ,Thi and Tco for first step are
known.
The next step will be found in the same way.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping-off for FT ≥ 0.75


Temperature
410°
3 4
360°
FT > 0.75

FT=0.75
1 2
110°

Heat Duty
4 Shells suggested
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping-off with Specified XP


If XP is specified then P can be found
using P=XPPmax
Since Pmax = 2 ( R + 1 + R 2 + 1 )
and R is known.
P1, 2 = ∆TH (∆T1 + ∆TC )
R = ∆TC ∆TH ⇒ P1, 2 = ∆TH (∆T1 + R∆TH )
∆TH = ∆T1[ P1, 2 (1 − RP1, 2 )]

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping-off for P1,2


Temperature
410°
∆T1 ∆TH
360°
∆TC

110°

∆TH = ∆T1[P1,2 (1− RP1,2)]


Heat Duty

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Since P1,2 is determined fully from


R and XP , the step slop given by
∆TH ultimately depends only on the
designer’s choice of XP.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Stepping-off for X=0.9


Temperature
410°
X=0.9 (I.e. FT=0.75)

354°
N=3.9 Shells
360°

285°
293°
201°
210°

110°
109°

Heat Duty
4 Shells suggested
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

An Analytical Procedure
 Bowman(1936):
PN , 2 N = f ( R, P1, 2 , N )
PN , 2 N = f ( R, X P P1, 2 max , N )
Since P1,2max is only function of R
PN,2N=f(R,XP,N)
−1
Invert the function ⇒N = f (R, XP, PN,2N )

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Ahmad (1985) has derived the


equations:
for R ≠ 1
N = ln[(1− RPN ,2 N ) /(1− PN ,2 N )] / lnW
Where:
2 2
W = (R +1+ R +1 −2XPR) /(R+1+ R +1 −2XP )
for R =1
N =[PN,2N /(1− PN,2N )][1+( 2 / 2) − XP ]/ XP
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Temperature

Heat Duty

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Estimation of Number of Shells


Required by Hot Streams

Starting with a hot stream supply


temperature drop a vertical line on the
balanced composite curve until it
intercepts the cold composite. From
this point draw a horizontal.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

 Repeat the procedure until the


horizontal line intercepts the hot
composite at or below the target
temperature of that hot stream.
 The number of horizontal lines will
be the number of shells which this
particular hot stream requires.
 Repeat the procedure for all the hot
streams.
 The sum of the number of shells for
all the hot streams will be the total
number of shells required by the hot
streams.
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Temperature

Heat Duty

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Estimate of Number of Shells


Required by Cold Streams
 Starting with a cold stream target
temperature a horizontal line is drawn
until it intercepts the hot composite curve.
From that point a vertical line is dropped
to the cold composite curve.
 Repeat the procedure until the vertical line
intercepts the cold composite at or below
the target temperature of that particular
stream.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The number of horizontal lines


will be the number of shells
which this particular cold stream
requires.
Repeat the procedure for all the
cold streams.
The sum of the number of shells
for all the cold streams is the
total number of shells required
by the cold streams.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Estimation of Number of Shells


Required by the Network
 The quasi-minimum number of shells
required in the network would be the
maximum of the total number of shells
required by the hot streams and the total
number of shells required by the cold
streams.
 If the total number of shells required by the
network which is found in the above method
is less than the minimum number of units
obtained from Euler’s equation,the minimum
number of shells will be equal to minimum
number of units.
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 11
Cost Targets for
Different Materials of
Construction
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Cost targets for different materials of


construction Cp h (KW/m2)
(KW/º C)
160º CS 100º
1
20 0.25
130º CS 40º
2 8 0.25
170º TI 52º
3
24 0.25
170º TI 60º
4 40 0.25

110º CS 25º
5 25 0.25

∆T min=10º
Utilities:
Steam@190°C; h=0.25kw/m2°C
Air@18°C; h=0.1kw/m2°C
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

One design could be


80º

1 CS
CS
2 C CS
CS/TI 117
CS
3 TI
CS/TI CS TI CS CS/TI
H 4 TI
1890 350 2160
672
5 CS
850 400 203
60º

Network Cost = $1871506

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Cost Data
Shell/Tube Exchangers

Carbon Steel (CS ), ($) = 30800 + 750 A 0.81

Titannium (TI ), ($) = 30800 + 4407 A 0.81

Stainless Steel (SS) , ($) = 30800 + 1644 A 0.81

CS/TI or TI/CS, ($) = 30800+ 3349A0.81

CS/SSor SS/CS,($) = 30800+ 1339A0.81

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Existing Capital Targeting Procedure


Units

Capital
Area Shells
Target

With this model of capital cost, we could assume,

a) All exchangers are made from Carbon Steel


capital cost =$689,737
63% less than actual
b) All exchangers are made from Titanium (TI)
capital cost =$2,851,567
52% higher than actual
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Objective is to find a new capital cost


target model in order to accommodate
for different materials of construction

Units Materials

Capital
Area Shells
Target

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Let’s start with just one exchanger,

200 °C 80 °C h = 1.0

150 °C 30 °C h = 2.0

Q = 6667
Area = 200 m2

With a very simplified cost model:

a) Carbon Steel (CS)


Cost($) = 450 * A = $ 90,000

b) Titanium (TI)
Cost($) = 1800 * A = $ 360,000

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

If we wanted to cost a TI exchanger using the


CS cost model, we could apply a correction
factor Ф within the area term.

Here is one way of doing it :

1 Q 
cost TI = 1800 ×  ×  = $ 360 ,000
(by TI cost model) 
U LMTD 

 1 Q 
cost TI = 450 ×  ×  = $ 360,000
(by CS cost model)
ΦU LMTD 

Ф = 0.25
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Now consider somewhat more realistic cost model


0.81
cost CS ($) = 30800 + 750 A
0.81
cost TI ($) = 30800 + 4407 A
T 200
h1 = 1.0
150

80 Q = 6667
h2 = 2.0 LMTD = 50

30

Q 1 1 ∆H
A= ×  +  = 200 m 2
LMTD  h1 h2 
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Let’s use Φ again


0.81
 6667  1 1 
Cost TI = 30800 + 4407  +  = $ 352,890
(by TI cost model)  50  1 2 

0.81
 6667  1 1 
Cost TI = 30800 + 750  + 
(by CS cost model)  50  1× 0.1123 2 × 0.1123 
= $ 352,890

With Ф=0.1123 , we get the correct result

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

We can always “fudge” Φ to fit any


specific case.
But, how can we predict Φ ?

Cost of base case exchanger = a1+b1(A)C1

Cost of special exchanger = a2+b2(A)C2

Cost of special exchanger = a1+b1[Afudge]C1


Afudge= f (Φ,A)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Now let us get the Φ

Step 1

a2 + b2 (A)C2 = a1 + b1(Afudge)C1

For simplicity, we assume a1= a2

 1
C2 
  b2  C1 −1
× A
A fudge =   ×A C1
 b1  
 

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 2

Q 1 1 
A=  + 
∆ TLM  h1 h2 
This with the Afudge equation develops into …

 1
C2 
1   bC1 −1
C1  1
=   × A
2
×
h fudge  b1   h
 
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 3

Simple idea:
Φ = hfudge / h

 1
C2 
  b  C1 1−
C1 
Φ =   × A
1
 b2  
 

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Remember the example?

T 200
h1 = 1.0
150
Q = 6667
80
h2 = 2.0 LMTD = 50

30 Area = 200 m2

∆H

Network cost = $ 352,890

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Now
0.81
Cost CS = a1 + b1(A)c1

30800 750

0.81
Cost TI = a2 + b2(A)c2

30800 4407

 1
C2   1

  b1  1−
C1
C1   750  0.81
Φ =   × A =    = 0.1123
 b2    4407 
   

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Cost TI
0.81
 6667  1 1 
= 30800 + 750  +  = $352,890
 50  0.1123×1 0.1123× 2 

Therefore, we can predict the Φ and get the right cost

Note 1:

Our cost models had c1 = c2 , but don’t worry

Φ still can be used when c1 ≠ c2 with good approximation

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Note 2:

Φ is applied to h-value of both


streams, therefore it can be easily
used for a mixed materials of
construction when Φ1 ≠ Φ2
h1 Φ1 h1

h2 Φ2 h2
c1
 Q  1 1 
Cost TI = a1 + b1   + 
 ∆TLM  Φ1h1 Φ2h2 
(by CS cost law)
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Summary

HEN Design : A

Cost CS = a1 + b1 Ac1 Cost TI = a2 + b2 Ac2

Having: A, a, b, c
Find Φ

Having A, Φ, a1, b1, c1


Find Cost TI

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

All very well for single exchanger,


what about whole network?

h1

h2

∆H

1  q1 q2  1  qj 
A=  +  Amin =∑ ∑ 
(∆TLM )  h1 h2  i (∆TLM ) i  j h j  i

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Using strong similarity we can write


1  qj 
( Amin ) fudge = ∑ ∑ 
i (∆TLM )i  j Φ j h j  i
Back to our example 80º

1 Streams 3 and 4 require TI


CS
2 C

CS/TI 117
CS
3
CS/TI CS TI CS CS/TI
H 4
1890 350 2160
672
5
850 400 203
60º
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Apply Φ to h-values of streams 3 and 4

 1

 750  0.81
Φ3 = Φ 4 =   = 0.1123
 4407  
 
Target Capital cost = $ 1,894,766

Actual Capital cost = $ 1,871,506

Error = +1.24%

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Another Example:
This time assume streams 1 and 4 require SS
80º
SS CS/SS
1
CS CS CS
2 C

CS/SS CS 117
3
CS/SS
H 4
1890 350 2160
672
5
850 400 203
60º

Network Cost = $ 928,724

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

 1

 750  0. 81
Φ1 = Φ 4 =   = 0.3795
 1644  
 

Target Capital Cost = $ 891,293

Actual Capital Cost = $ 928,724

Error = -4%

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Procedure
Stream Data including Materials

Select base case

Cost 1 = a1+b1Ac1 , Cost 2 = a2+b2Ac2

Determine Ф for special streams

1  qj 
( A min ) fudge = ∑ ∑
( ∆ T LM ) i  j Φ j h j

i  i

Capital Cost Target of Network in Mixed Materials


= f (a1, b1, c1, Amin, Nmin or Nshell)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Homework 2

Following assignment is due to


be returned in two weeks.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 12
Multiple Utilities

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

There are different utilities that can be used in


process such as:

Furnace
Steam at different levels, ( VLP, LP, MP, HP, VHP)
Hot oil circuit
Cooling water
Air
Refrigeration cycles

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot Utilities:
We want to USE at the LOWEST level
and GENERATE at the HIGHEST level

Cold Utilities:
We want to USE at the HIGHEST level
and GENERATE at the LOWEST level

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

We can show multiple steam levels on a T-H diagram:

T
HP

MP

LP

H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Steam generation

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot oil circuits


Treturn
Process Duty

Tsupply
Tsup
T

Tret
What is the minimum hot oil flowrate?

H
Qfuel
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Simple Furnace Model


Loss T0
T
T stack T TFT

Q Hmin
Tstack

∆H Fuel = Q Hmin + TFT


C
Loss
T0
Loss H
∆H Fuel

AIR

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

How do we target for the best mix of utilities?


T

QH

QC

H
Up to now, we use hottest hot utility and
coldest cold utility
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Composite curves with multiple utilities


T

HP

MP

LP
∆Tmin

∆Tmin

CW
H

The additional utility causes utility pinch


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

 Composite Curves are not ideal tool


for utility selection

 Let’s introduce Grand Composite


Curve (GCC)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Remember the Cascade Diagram?


QHmin = 20
Hot Scale Cold Scale
170º 160º 165º T*
20
60
150º 80 140º 145º 80

2.5
82.5
145º 135º 140º
82.5

-82.5
0
90º 80º 85º 0

75
75
60º 50º 55º
75
-15
30º 60
20º 25º
60
H
QCmin = 60

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

The Grand Composite Curve gives


the hot and cold utility requirements
of the process both in ENTHALPY
and TEMPERATURE

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Now we can easily place multiple utilities –Constant Temp.


T* T*
HP HP

MP

LP

H H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Placing variable temperature utilities

T* Tf T* Tf

FG
FG

LP

H H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 13
Process Utility
Interface

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Hot End Stream Data


CP
1000º 150º
1 0.7

540º 150º
2 1.0

500º 300º
3
2.25

500º 100º
4 1.4

100º 100º
5 ∆H=275

QHmin= 300

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 1

CP
1000º 950º 150º
1 0.7

540º 425º 150º


2 1.0

500º 366.7º 351º 300º


H 3 2.25
300 35 115
500º 100º
4 1.4
560
100º 100º
5 ∆H=275
275

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 2

CP
1000º 521.4º 150º
1 0.7

540º 425º 150º


2 1.0

500º 351º 300º


3
2.25
335 115
500º 100º
285.7º
H 4 1.4
300 260
100º 100º
5 ∆H=275
275

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

There seems little to choose


Until we think about the
utilities!

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 1

T
500º
Tf

367º
Ts= 417º
500°

417º
300

Q=300 H

Qfuel=415

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 2

T
Tf

500 º
500°
286º
Ts= 336º
336°
300

H
Q=300
Qfuel=371

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin has been achieved in both


MER designs, but the furnace
efficiency is different

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Use the Grand Composite Curve


T Q Hmin
T TFT =Theoretical Flame Temperature

in
m
CP

Pinch

H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Simple Furnace Model


Loss T0
T Q Hmin

T stack T TFT

in
m
Q Hmin

P
C
T stack
Pinch
∆H Fuel = Q Hmin + TFT
C
Loss
H
∆H Fuel
Loss

AIR
Now we understand what happened
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 2

T Q Hmin

T TFT
B A

in
m
P
C
A
T stack
Pinch

H
Q=300 371

Fuel = 371

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Design No. 1

T Q Hmin
B A
T TFT

in
B

m
P
C
A
T stack

Pinch

Q=300
H
415
Fuel = 415

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCEDURE
1. Draw Grand Composite Curve
2. Determine best utility mix
3. Draw “Balanced Grid”
4. Design “Balanced Network”
5. Convert into HEN + Utilities

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

3. Draw “Balanced Grid”


Hot Utility

Cold Utility

Umin = 5 U min= 4
(no further utility)
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

4. Design “Balanced Network”


CP
FG 0.22
1000º 150º
1 0.7

540º 150º
2 1.0

500º 300º
3 2.25

500º 100º
4 1.4

100º 100º
5 ∆H=275

These ‘exchangers” will later trun into furnace coils


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

5. Convert into HEN + Utilities


1

4
TS = 160º C = T corr.
5

Q = 300

Fuel = 336

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

For Comparison
T S = 417º T S = 366º

Q=300 Fuel = 415 Q=300 Fuel = 371

T S = 160º = T corr

Q=300
Fuel = 336

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

PROCEDURE
(Once again)
1. Draw Grand Composite Curve
2. Determine best utility mix
- choose between options (tariffs, load, etc.)
3. Draw “Balanced Composite Curves”
- utility pinches,”narrow regions”, etc.
4. Draw “Balanced Grid”
-usually no further utility
5. Design “Balanced Network”
-future utility exchangers are integrated
6. Convert into HEN + Utilities
7. Evolve (we always need to leave a door open)

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Grand Composite

Grand Composite Utility Mix

Balanced Composite

Check:
•Tight regions
•Utility pinches
•etc

Balanced Grid

Design the network

Evolve
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 14
Furnace

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Independent Degrees of Freedom


in a Furnace
TDEW

We choose :
Fuel flow
T TF Tair
Tair
Fuel
Excess Air
Air T0

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

TDEW

Case one
T TF
Tair Tair< TDEW
Fuel
Air T0

I.T I.T
T TF

TDEW
Utility GCC
Tair

T0

H H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

TDEW

Case Two
T TF
Tair Tair > TDEW
Fuel
Air T0

I.T I.T
T TF
Utility GCC
Flue
Flue Only
Tair
Flue and Air
TDEW
Air
Air only
T0

H H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Now let’s look again at our


problem (Tair>TDEW)

T T

H H
Utility GCC Process GCC

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Utility and Process together


T

Tf

Utility Pinch
Tair

TDEW

Load limit

H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

A. Vary Fuel Flow


T
Tf Tair = constant
High fuel
Excess air = constant
flow(2)

Low fuel
Tair flow(1)

TDEW

T0

∆H Fuel (1) H
∆H Fuel (0)
∆H Fuel (2)
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

B. Vary Tair
T'''' TF  Fuel flow = constant
T'''TF  Excess air = constant
T T''TF
T'TF
TTF
X

T''''air T FT = 1074 .39 + 0 .853 Tair


T'''air CP flue = CPair + CP fuel
T''air
TDEW CPair
= 0 . 853
T'air
CP flue

Tair
X
T0
H
∆H Fuel
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

C. Vary Excess Air


Lower
Excess Air
 Fuel Flow = constant
T  Tair = constant
Higher
Excess Air

Tair

TDEW
Higher
Excess Air

T0
Lower H
Excess Air ∆H Fuel
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

How can we use these DOF to


minimize fuel consumption?

A. Excess Air,
We have already seen that more excess air
will never reduce fuel consumption

Initialize
XS air= 0 or (XS air)min

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

B. Air Preheat
FL
Furnace GCC
Tair
FL+

TDEW AP Process GCC


AP

Fix Tair and “shrink” furnace GCC onto process GCC


(decrease fuel). One of two cases can occur :
Utility Pinch on AP or FL+AP
Utility Pinch on FL
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

First Case
Pinch on AP or FL+AP
T"TF
T'TF
T''air TTF

T'air
Tair
FL+
Pinch
TDEW AP

AP
T0
∆H Fuel

Increasing Tair has no effect on fuel flow


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Second Case
Pinch on FL T'TF
T'TF
FL
TTF
TTF
Tair
T'air
Tair Pinch
Tair

T0 T0
T0
∆H Fuel(1) ∆H Fuel(1)
∆H Fuel(1)
∆H Fuel(2)

Increasing Tair allows fuel to be decreased


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 1
Assume no Air preheat to identify (CPflue)initial
TTF (No Air Preheat)
T (CPflue)initial

Utility Pinch

(CPflue)initial = f (Most protruding “Candidate Pinch”)


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 2
Set (Tair)initial= Tutility pinch
(This will always be hot enough)
TTF (With Air Preheat)
T
(CPflue)initial TTF (no Air Preheat)

(Tair)initial

TDEW (This will always ≥ Requirement)

T0
H
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 3
Decrease fuel flow until PGCC is limiting
TTF (With Air Preheat)
T (CPflue)initial

(Tair)initial
Process GCC
TDEW

Load limit
T0
H

Minimum fuel flow now set


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Step 4
Back off from (Tair)initial
T TTF (With Air Preheat)

(Tair)initial
(Tair)min

TDEW

T0 Load limit
H

Tair = Minimum TairPROCESS


that INTEGRATION
allows minimum fuel flow
www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Homework 3

Following assignment is due to


be returned in two weeks.

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 15
Heat Engines

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Heat Engine Models


T  TC 
Source T H Wmax = Q1 1 − 
 TH 
Q1
 TC 
1 −  = Carnot efficiency
 TH 
H.E. W Real = W max × η m
W= Q1-Q2
η m = machine efficiency
Q2

Sink T C

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Common Heat Engines


 Steam Turbines
 Gas Turbines

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T A Q

? H. E. W

pinch

Q-W

?
B

How should we integrate a heat engine?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

If we integrate across the pinch


A+Q
T A Q

H.E. W

Q-W

B +Q-W
Waste of Capital and Energy
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate above the pinch


A+Q-(Q-W)=A+W
T A Q

H.E. W
Q-W

100% Conversion of Heat to Work


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate below the pinch


T
A

H.E. W

B - Q + (Q-W) =B -W Q-W

100% Conversion of Heat to Work


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Appropriate placement of
heat engine is

NOT ACROSS THE


PINCH

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

To target the thermal design, use


the process grand composite
curve and treat the heat engine
like a utility

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QLoss
HP Steam

T QHP W BOILER
QLP Condensate
water QFuel

QCmin Q Fuel = Q HP + Q LP + W + Q Loss

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

QHmin
T* QHP

W
QLP

QCmin
∆H

Integration of a steam turbine


with the process
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Q Hmin+W+Qloss
Q Hmin -(Qfuel -W- Qloss) Qfuel
Combustion Chamber
T*
W

Tex
Qfuel -W
Air -
PINCH

Qloss
Qfuel= Q Hmin+ W + Qloss
T0
Exhaust to Atmosphere
QCmin
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Tex*
T*

TP*

T0*
∆H
QLoss Q Fuel-W-QLOSS
Q Fuel-W

A gas turbine exhaust matched


with process (same as flue gas)
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T*

200º

∆H

Question : Which CHP Scheme?


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T*

200º

∆H

Answer : Steam Turbine!


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T*

200º

∆H

Question : Which CHP Scheme?


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T1 Fuel
T*

W
T1
T0
200º

∆H

Answer : Gas Turbine!


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 16
Heat pumps

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Heat Pump Model

T
Sink T H

Q1=Q2 + w

H.P.
W

Q2

Source T C

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Coefficient of Performance
TH
COPhp =
Q2 TH − TC
Sink T H COP =
W TC
Q1 Sink T H COPref =
TH − TC
Q1
QH
Large ∆T

Small ∆T W hp =
η m (COP )hp
W W
QC
Q2 W ref =
Q2 η m (COP )ref
Source T C

Source T C η m = machine efficiency

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T A

Q+W
?

H. P. W

?
Q
B

How should we integrate a Heat Pump?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate above the pinch


T A - (Q+W-Q) = A-W
Q+W

H. P.
W
Q

Power Heat
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate below the pinch


T A

Q+W

H. P.
W
B +(Q+W-Q)=B+W Q

Power more cooling water


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate across the pinch


T A - (Q+W)
Q+W

H. P.
W
Q

B- Q

Save Hot and Cold Utility


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Appropriate Placement
of Heat Pump is

ACROSS THE PINCH

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

To target the thermal design, use the


GRAND COMPOSITE CURVE
and treat the Heat Pump like a utility

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T St

Q2

H. P.
W

CW H

If the hot side of Heat Pump is limiting


Find cold side temperature by iteration

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T St

Q2

H. P.
W

If the cold side of Heat Pump is limiting,


Find hot side temperature by iteration

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

And now, Let’s get more


sophisticated…

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

CW

0º Fridge 1

Fridge 2
H
We can use cooling water as hot utility … but
can we do better still?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Let’s consider the fridge cycle

40º
70+W
Heat rejected to
CW at 40º

W
HP

Level 1 at - 35º
- 35º 30
Level 2 at - 65º
- 65º 40

Do we have to Pump the heat all the way up to


40ºC ?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

There is a nice Heat Sink


T available at 0º, but its
load is limited
70 So we need a Compressor
with two Discharge
Fcond (=W) pressure …
CW
or do we?
Fcond
W 0º

F-1

F-2
70

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T
70

CW
F cond

F-1

F-2
70
H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Do we ever integrate a heat


pump not across the pinch?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Consider the following case

T HP

HP = 15 $ / ton
LP = 4 $ / ton
LP

CW

H
Any case for heat pumping?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T HP

LP
W

CW
H
Answer : NO
COP is poor
LP steam is cheap anyway
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T HP

MP
W

LP

This could save a lot of money

CW
H
Note:
The Heat Pump may not be across the
process pinch, but across the utility pinch

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Question:
Have we just violated the appropriate
placement principle?

Answer:
No, we have placed a HEAT PUMP
across a UTILITY PINCH

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

LECTURE 17
Distillation

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Distillation Column
T

Reboiler
A

A,B

Condenser

B
H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Distillation Column Model


T
A
Q A,B

Reboiler
A
B
A,B
Condenser B

“ Separation Engine”
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

How Should We Integrate a


Distillation Column?
T
A
? Q
Reboiler

Condenser

? Q

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate across the pinch


A+Q

Q
Reboiler

Condenser

B+Q

Why Integrate?
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate above the pinch


A

T Q

Reboiler

Condenser
Q

A “Free Ride”!
B
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Integrate above the pinch


A
T

Reboiler

Condenser

B Q

A “Free Ride”!
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Appropriate Placement
of Columns :
NOT ACROSS THE PINCH

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

How can we integrate the


column with the process
appropriately?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Use the background process


grand composite curve and
treat the column as utility …

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

A
A,B

Will the column fit the process?


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

This column fits!


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

This one fits too!


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

What if the column does


not fit?

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Column Across the Pinch - does not fit


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Shift the Column (Change the Pressure)


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T T T

H H H

Process
CW CW
P
Steam
Process

CW
Steam P Steam
Process

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Appropriate Column
Placement And…

 Capital Cost

 Control

 Double Effect

 Vapor Recompression
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

1. Column across the Pinch

T T

Reboiler
Reboiler
Cond

Cond

H
H

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T T

Reboiler Reboiler
Cond Cond

H H

Increase pressure both


“condenser” and “ reboiler”
temperature increase
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

We have a useful diagram


T

C1

C2

C3

C4
C5

All columns are appropriately placed…


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Double - Effect

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

C1

P↓

C2 ↑
P↑

Stand-Alone Column Optimization


⇒ Double Effect
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T T

CA
C
CB

H H

Before After

In isolation, we have saved energy …


PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

But What if ?
T

Feasible H

T T

CA CA
CB
CB

H H
Not Feasible (product Not Favorable
decomposition) (refrigeration)
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Conclusion
Do not “optimize” your column
before you have understood
the process context

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Control

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T T

H H

This Fits But This is easier to control

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Control - Conclusion
In principle, it is enough to
integrate the reboiler OR
the condenser

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Vapor
Recompression

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

H.P W

Distillation Column

Stand Alone Column Optimization: Vapor Recompression

PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

T T
SEP

HP

Appropriate placement of heat pumps and


columns are incompatible.
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

There, only if the column HAS to be


inappropriately placed …
A
T

SEP HP W

Q-W
W

B+W

…. Will there be a case for


vapour recompression
PROCESS INTEGRATION

www.ChemEng.ir
‫ﻣﻬﻨﺪﺳﺎن ﺷﯿﻤﻰ ﺗﻬﺮان‬

Conclusion

Do not “optimize” your column


before you have understood
the process context

PROCESS INTEGRATION

www.ChemEng.ir

You might also like