Material

Material Volume Weight


Cement 1m3 1.40 tonnes (28 bags)
Sand 1m3 1.52 tonnes
Mixed stone 1m3 1.62 tonnes
Labour (Hand-mixed & Hand-lifted, Placed)

mixing - 2.00 hours/m3

Lift & Place

ITEM UNIT GENERAL LABOUR (HOUR)


Pad foundation m3 6.00
Lower ground m3
≤150mm thick 7.75
150mm-300mm thick 6.50
>300mm thick 5.00
Upper ground m3
≤150mm thick 9.25
150mm-300mm thick 7.50
>300mm thick 6.50
Wall m3
≤150mm thick 10.00
150mm-300mm thick 8.50
>300mm thick 7.50
Column and beam m3 8.00
Plants and machineries

Size No. Of Labour Output/Hour Diesel/Hour (litre) Lubricant Oil


(m3) (litre)
5/3.5 1 operator 1.25 1.1 0.04
1 general
7/5 1 operator 2.25 1.6 0.06
3 general
10/7 1 operator 3.35 1.8 0.07
4 general
14/10 1 operator 4.45 2.1 0.08
4 general
18/12 1 operator 5.25 2.4 0.10
6 general

Door

Output labour for fixing door

Types of doors 1 joiner/m2 (Hour)


40mm skeleton framed flush door 0.85
50mm solid flush door 1.00
50mm panel door 1.00
54 mm fire resistance door 1.25
Frame door Frame Window

Timbe size 1 joiner/ m2 (hour) Timbe size 1 hanging & fitting /m


(hr)
37mm x 150mm 0.18 37mm x 150mm 0.18
50mm x 150mm 0.20 50mm x 150mm 0.20
50mm x 175mm 0.22 50mm x 175mm 0.22

Labour for spread and leveled of screed

Type of finishes 1 Tiler & 1 General Worker (Hr/m2)

Cement render 0.30


Granolithic pavement 0.35

Screeded bed 0.25


Floated plywood 0.28

Troweled bed 0.30


Tiles

Tile Size No of tiles


100mm x 100mm 100
200mm x 200mm 25
250mm x 250mm 16
300mm x 300mm 11
Brick Wall

Description Mortar (m2) No of bricks (No.)


½ brick wall 0.025 63
1 brick wall 0.050 125
1½ brick wall 0.075 188
Labour for brick wall

Description Brick layer (hours/m2) General lab. (hours/m2)


½ brick wall in common brick 1.00 0.35
1 brick wall in common brick 1.75 0.70
½ brick wall in facing brick 2.00 0.50
1 brick wall in facing brick 3.50 1.00
Block wall

Blok size Mortar (m3) No of bricks (No.) Bricklayer General lab.


450mm x 150mm (hours/m2) (hours/m2)
100 mm thick 0.010 16 0.75 0.35
215mm thick 0.022 16 1.50 0.50

Plastering
Location 1 Plasterer & 1 General Worker (Hr/m2)

Wall 0.40

Ceiling 0.50

Tiles

1 tiler & 1 General Worker (Hr/m2)


Size of tiles
Floor Wall

≤ 150mm x 150mm 0.75 1.00

< 150mm x 150mm 1.90 1.25

Labour Output for installing the tile

1 tiler & 1 General Worker (Hr/m2)


Size of tiles
Floor

≤ 150mm x 150mm 0.75

< 150mm x 150mm 1.90

Labour output for installing vertical tiles

High of vertical tiles


1 tiler & 1 General Worker (Hr/m2)
(mm)

75 0.20

100 0.23

125 0.26

150 0.30

You might also like