Professional Documents
Culture Documents
BY
MOHD NAJIB ABD RASHID
SITE POSSESSION
[Clause 38.1] No work under this contract shall commences unless and
until the Performance Bond stipulated in clause 13 and such
insurance policy specified under clauses 15 & 18 shall have been
deposited with the government, PROVIDED THAT for the purposes of
this clause only (but for no other), if the contractor shall produce to the
government cover note of the said insurance policy and the receipt of
premium paid, it shall be a sufficient discharge of his obligation under
this clause.
[clause 38.2] Unless the contract documents shall otherwise provide,
possession of the site as complete as may reasonably be possible but
not so as to constitute a tenancy, shall be given on or before the “date of
possession” stated in the letter of acceptance to the contractor who
shall thereupon and forthwith commence the works (subject to clause
38.1) and regularly and diligently proceed with and complete the works
on or before the date for completion as stated in appendix.
[Clause 38.3] the “date for completion” of the works as referred to
under clause 39 hereof shall be calculated from the said “date for
possession”. PROVIDED ALWAYS that the possession of site may be
given in section or in any part or any other restriction upon possession
of the site shall be stated in the appendix to these condition or in
contract documents.
DELAY OF SITE POSSESSION [clause 38.4, 38.5 & 38.6
PWD 2007]
[clause 38.4] in the event of any delay in giving possession of the site
from the “date of possession” as stated in letter of acceptance or delay
in giving any section or part of the site as provided in clause 38.3, the
S.O may issue instruction in regard to the revision of the “date for
possession and “date for completion” shall be appropriately
revised under clause 43.1(h) hereof, but the contractor shall not be
entitled to claim for any loss or damage caused by such delay in
giving possession of the site, nor shall he be entitled to terminate this
contract.
[clause 38.5] in the event that the giving of the possession of the whole
site is delayed beyond 90 days of the “date for possession” stated in the
letter of acceptance, the S.O shall give written notice to the contractor
of the causes of such delay. Upon the receipt of the said written notice
issued by the S.O the contractor may inform the S.O. in writing of its
decision within 14 days of receipt of the said notice either to:
a. Agreed to proceed with the works when the site is subsequently made
available, in which case clause 38.4 shall apply in particular, the
contractor shall not be entitled to claim for any loss or damage caused
by such delay in giving possession of the site or
b. Terminate this contract, without prejudice to any other rights or
remedies that the government and the contractor may have as a result
of the termination.
[clause 38.6] in the event that the giving of possession of any section or
part of the site (whether provided for in clause 38.3 or otherwise) is
delayed beyond 90 days from the date of possession stated in the
contract, then the S.O shall give written notice to the contractor to inform
the causes of such delay. Upon receipt of the said written notice, the
contractor may inform S.O in writing, within 14 days of receipt of the said
notice of its decision either to:
a. Agree to proceed with the works when the section or part of the site is
subsequently made available, in which case sub-clause 38.5(a) above
apply and in particular, the contractor shall not be entitled to claim for
any loss or damage caused by such delay as aforesaid or
b. request for S.O’s instruction to omit the relevant section or
part of the works from the contract. If the S.O agree to such request then
the relevant part of the works shall be duly omitted and deemed to be a
variation to the contract. Such variation shall not vitiate this contract. If
the S.O does not agree to such request as aforesaid, then the contractor
shall be entitled to claim for any loss/expenses caused by and in respect
of such delay beyond 90 days as aforesaid.
SITE POSSESSION [clause 21 PAM 2006]
Clause 21.3 [where there are different completion dates for sections of
the works stated in the contract documents, the architects shall issue a
certificate of sectional completion when the section of the works are
practically completed. These provision in the contract in regard to
practical completion and DLP under clause 22.0 and release of
retention fund under clause 30.6 shall apply with necessary changes as
if each section was separate and distinct contract.
Clause 21.4 [postponement or suspension of the work] the architect
may issue an AI in regard to the postponement or suspension of all or
any part of the works to be executed under the contract for a
continuous period not exceeding the period of delay stated in clause 19
& 20.(A), the contractor shall ensure full insurance covered by the
employer under clause 20(B) or 20(C), the employer shall ensure
similar insurance coverage.
CONDITION PRIOR CONSTRUCTION
a) PERFORMANCE BOND
BANK GUARANTEE
INSURANCE GUARANTEE
PERFORMANCE GUARANTEE SUM
b) PUBLIC LIABILITY INSURANCE
c) INSURANCE OF WORKS
d) WORKMEN COMPENSATION [ No Longer Needed in PWD]
e) SOCSO
f) WORK PROGRAMME
INSURANCE
DEFINITION:-
1. Insurance of works
Indemnity given by 3rd party as a protection to the client and contractor for
any disaster during construction project
2. Public liabilities insurance
Indemnity given by 3rd party as a protection towards client and contractor if
accident happened affect the public and public property on the construction
site as well as around the site.
3. Workmen compensation
Indemnity given by 3rd party as a protection towards client and contractor if
the accident occurred on the construction site affect the contractor and
subcontractor workers.
4. SOCSO
Indemnity given by 3rd party as a protection towards client and contractor if
the accident occurred on the construction site affect the contractor and
subcontractor workers.
THE IMPORTANCE OF INSURANCE
3. Site Possession to
Contractor All Risk Bil 1 & Bil 2 CMGD Bil 1 & Bil 2
(CAR)
4. Workmen Compensation Death and injuries of main and sub Site Possession to
contractor income > RM 3000.00 CMGD 10% from contract sum
Clause 18.1(a) stated that the contractor shall in the joint names of the
government and the contractor insure against loss and damages of the
construction site.
Scope of coverage:
1. Work that had been execute
2. Material on site
3. Professional fee
4. Cost of cleaning up the mess due to disaster
Risk of insure:
1. Fire
2. Lightning
3. Explosion
4. Storm
5. Tempest
6. Flood
7. Ground Subsidence
INSURANCE of WORK [clause 20.A PAM 2006]
Clause 20.A.1 stated that the contractor shall as a condition to the commencement of any
work under the contract, take out and maintain in the joint names of the Employer,
contractor, subcontractor and interested parties a CAR insurance policy.
Scope of coverage:
1. Work that had been execute
2. Material on site
3. Professional fee
4. Cost of cleaning up the mess due to disaster
Risk of insure:
1. Fire
2. Lightning
3. Explosion
4. Storm
5. Tempest
6. Flood
7. Ground Subsidence
CONTRACTOR’S ALL RISKS [CAR]