Professional Documents
Culture Documents
In Clause 38.5 pointed out that, when delay of delivering whole site possession beyond (90)
days of the “Date of Possession”, S.O. shall notice contractor with written notice the causes
of delay. After receive notice from S.O. contractor shall notice S.O. by written notice his
decision within 14 days whether he agree to proceed the work when site available and not
entitled to claim for loss or damage cause by such delay of giving site possession. Or
contractor wanted to terminate the contract without affecting any other rights or remedies that
the government or the contractor may have as a result of the termination, terminate this
contract. In Clause 38.6 additionally specified that the S.O. must tell the contractor in writing
of the reason for any section of work delays in delivery of a site that last longer than 90 days.
After receiving written notice from S.O., contractor shall inform S.O. with written notice of
his decision within 14 days. If the contractor decides to continue the work after the site has
been delivered, he cannot claim for any loss and damages cause by the delay. Or contractor
can request S.O. to omit the relevant part of work from contract. If S.O agree, the appropriate
part of work will be omitted properly, and changes won’t make agreement invalid. The
contractor shall be entitled to claim for damages and expenses caused by and in respect of
such delay beyond ninety (90) days as mentioned if the S.O does not agree to such request.
Besides, in PAM 39.0 – Completion of Works, Clause 39.1 of PWD form stated that
contractor shall complete their work as in contract within or on “Date of Completion” subject
to clauses 38.3, 41 and 43. In Clause 39.2, stated that contractor shall notice S.O. in written
notice to determine his work had achieve practical completion. Clause 39.3 stated S.O. shall
carry out testing or inspection for the works within 14days after receipt notice from
contractor. S.O will decide whether issue Certificate of Practical Completion to contractor
and Defect Liability Period commence. Or S.O. will give instruction to the contractor to
rectify all the defective works before issuance of Certificate of Practical Completion. And in
Clause 39.4 stated that unless contractor done carry out and complete all the defective work
otherwise Certificate of Practical Completion will not be given. Clause 39.5 stated work
deemed to practically complete if work have been completed according to terms and
conditions of contract, fulfil government beneficial use of the works for their intended
purpose, work have passed commissioning tests, and fulfil all the essential services including
access roads, landscape, car parks, drains, sanitary, water and electricity installation and etc.
And clause 39.6 stated S.O. will certify the work practical completion when it satisfies S.O.
requirement and the date of such completion shall be the date of commencement of Defects
of Liability Period.
However, in PAM 2018 Nominated Sub-Contract, Clause 15.1 stated subcontractor must start
design work (if any, and fabrication work on the commencement date of the subcontract
according to work programme. Architect shall issue Certificate of Practical Completion.
Case Study
Title: Thamesa Designs Sdn Bhd & Ors v Kuching Hotels Sdn Bhd [1993]
Case Detail:
The problem of this case is whether the employer was authorised to impose liquidated
ascertained damages when it failed to deliver over the site to the contractor on time. In that
instance, the contract's extension of time clause does not cover late site handover. The
Supreme Court ruled that the employer is not authorised to impose liquidated determined
damages since the period was set "at large" by the employer's act of prevention.
Lesson Learnt
In the situation of works delay, if it’s not cause by contractor default and contractor had put
his effort and endeavour to carry out his work, employer have no right to determine his
employment and claim for liquidated damages according to clause 22.1 – Liquidated
Damages & certificated of non-completion. And architect not entitled to issue certificate of
non-completion to contractor. In the same moment, contractor are entitled to claim for
Extension of Time (EOT).
Compare and contrast the above provisions with P.W.D 203A Form of Contract
However, Clause 40.1 in PWD form, stated that the S.O shall issue Certificated of Non-
completion immediately to the contractor if contractor fails to complete the works before or
by the Completion date or extended granted pursuant to clause 43. And government have the
right to terminate the contract when S.O issues Certificate of Non-completion to the contract
in clause40.2. and Government entitled to recover Liquidated and Ascertained Damages from
contractor. S.O may must first write a notice to inform contractor for a deduction. Liquidated
and Ascertained damages must be calculated according to rate stated in Appendix 1 from the
date of issuance of Non-completion Certificate to the date of issuance Practical Completion
Certificate. At the end, S.O can deduct Liquidated and Ascertained Damages from any money
due or become due to the contractor if he is failing with such damages shall recovered from
Performance Bond. In clause 40.3 specified Liquidated and Ascertained Damages must be
reasonable amount of loss stated in contract which Government will suffer from the
contractor default to breach the contract. In clause 40.4 stated that contractor still need to
carry out his responsibilities to complete his works and liabilities under the contract even
though his payment or liquidated and ascertained damages.
From the other part, PAM Sub-contract ( Clause 16.1 – Failure of Sub-Contractor to complete
)specified that contractor may issue a Certificate of Non-completion (with a copy to Architect
and Consultant) when sub-contractor fails to complete his work by completion date, with
stating his opinion, sub-contract work ought reasonably to have been completed. After
apportioning responsibility where the delays may have also been caused by the Contractor
and other Nominated Sub-Contractors, the Contractor shall thereafter be entitled to set-off a
sum for any loss and/or expense suffered or spent by the Contractor. The contractor may
think about sharing responsibility for delays brought on by non-completion between himself
and other NSC and mitigating the losses he suffers as a result of non-completion in
accordance with Cl 26.13. The amount of losses incurred may alternatively be seen as the
specified LD amount that both parties have agreed upon.
Case study
Title: PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah
Case detail:
The plaintiffs purchased condos at the Skypark property in Cyberjaya (the project). The first
and third defendants were the project's developer and architect, respectively, while the second
defendant was the landowner. The plaintiffs claimed that the first and second defendants
failed to give unoccupied possession because they did not provide a legitimate certificate of
completion and compliance (CCC). While delivering vacant possession, they had issued form
F1 (a partial CCC) rather than form F (a full CCC). The plaintiff argued that to claimed
further liquidated ascertained damages (LAD) against defendant. (Liquidated Damages –
Second Bite of the Cherry? – Gan Partnership, 2022)
Court held:
Court help that the parties involve in the contract make a settlement agreement. Plaintiff had
claimed his compensation through settlement agreement. And it was also determined that the
plaintiffs were not permitted to revisit the issue of LAD because their claims had been settled
before the Housing Tribunal and they had not challenged the Housing Tribunal's judgement.
The Court further stated that the first defendant was responsible for delivering the property in
line with the SPA and that no claim could be brought against the second or third defendants.
Given the foregoing, the Court eventually dismissed the allegations against all three
defendants.
Lesson Learnt
Through this case, learn that the plaintiff who fail to receive an unoccupied vacant possession
have the right to claimed for liquidated damages as defendant fail to fulfil his promises. And
the defendant can said as breach the contract by late deliver the possession to the buyer due to
his default. .
Reference
1. Liquidated damages – second bite of the cherry? – Gan Partnership. (2022, June 14).
https://www.ganlaw.my/liquidated-damages-second-bite-of-the-cherry/?
utm_source=mondaq&utm_medium=syndication&utm_term=Real-Estate-and-
Construction&utm_content=articleoriginal&utm_campaign=article
2. Jenny, L.S.Y. (2012). THE PROFILE OF CONSTRUCTION DELAY CASES
JENNY LOO SHIH YEIN UNIVERSITI TEKNOLOGI MALAYSIA. [online]
Available at: https://bic.utm.my/files/2019/04/jennylooshihyeinmb111048d12ttt.pdf
[Accessed 11 April. 2023].