Professional Documents
Culture Documents
Section 1: Overview
1.1 Rigid Pavement Types
Different pavement types use different types of joints and reinforcement to control
the forces acting on the concrete pavement. These forces include drying shrinkage
of the concrete, environment changes, and traffic loads. Forces due to shrinkage
and environment changes are large enough in the concrete pavement to cause
cracks to form without any traffic loading.
The designer can select the location where the joints will be placed and,
consequently, where the cracks will form. Joints may be thought of as “controlled
cracks” that will reduce the stresses the concrete will experience during its life and
greatly increase the life of the concrete pavement. Through the use of
reinforcement, the location and spacing of cracks can also be controlled.
CRCP contains both longitudinal and transverse steel. CRCP does not contain
transverse joints except at construction joints. Figure 8-1 shows the typical
reinforcing steel layout for CRCP.
The function of the longitudinal steel is not to strengthen the concrete slab, but to
control concrete volume changes due to temperature and moisture variations and
to keep transverse cracks tightly closed. The function of the transverse steel is to
keep longitudinal joints and cracks closed. If the steel serves its proper function and
keeps cracks from widening, aggregate interlock is preserved and concrete
stresses in the concrete slab due to traffic loading are reduced.
The CRCP thickness design is detailed in Section 2, Approved Design Method, and
Section 3, Rigid Pavement Design Process for CRCP. Steel reinforcement and
other design details are governed by the CRCP standards. The latest CRCP
standards can be obtained from the department’s internet website at the following
address: http://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/standard/rdwylse.
htm.
CPCD has transverse joints spaced at regular intervals. The transverse joints are
used to control temperature-induced contraction and expansion in the concrete.
Smooth dowel bars are used at the transverse joints for load transfer. The
transverse joints are spaced at 15 ft. intervals. Longitudinal joints are used to
control random longitudinal cracking. Longitudinal joints are tied together with tie
bars. Figure 8-2 shows the typical layout for CPCD.
For frontage roads where CRCP is difficult to construct due to numerous leave-
out sections,
Factors Where/When
> 40 million ESALS
Material Sources Use Local Coarse Aggregates with High COTE for Traffic Levels with ≤ 40 mill
Rigid pavement types other than CRCP and CPCD may be appropriate for a wide
variety of situations. Refer to Section 7, “Bonded and Unbonded Concrete
Overlays,” and Section 8, “Thin Concrete Pavement Overlay (Thin Whitetopping),”
for a description of other rigid pavement applications.
PCC shoulders should be tied to the main lane pavement by tie bars or by the main
lane's transverse steel. The PCC shoulder must have the same thickness and the
same base layers as the main lane pavement. This will allow traffic to be routed on
the shoulder during future maintenance and construction while reducing the
chances of structurally damaging the shoulder. It will also facilitate the construction
sequence, in most cases.
Tied or monolithic curb and gutter help in reducing edge stresses and serve as a
barrier that discourages traffic from riding too close to the edge of the pavement
structure. Although tied curb and gutter sections usually contain tie bars, the tie
bars are too small in either size or number to transfer load stresses effectively by
themselves. Construction joints usually exist between tied curb and gutter and the
concrete pavement. This means no aggregate interlock exists. Since the number of
edge stresses in the pavement are much less for monolithic curb sections than for
tied curb and gutter sections, the use of monolithic curb is recommended when
practical.
Section 2: Approved Design Method
2.1 Introduction
The TxCRCP-ME design program and the AASHTO DARWin® 3.1 program are
available to department personnel through the district pavement engineer.
Consultants may obtain the TxCRCP-ME program from the district pavement
engineer or the Pavement Asset Management Section of the Maintenance Division.
The AASHTO Guide also contains design procedures for rehabilitation of rigid
pavements, including asphalt concrete overlays or Portland cement concrete (PCC)
overlays of existing rigid pavements. Contact the district pavement engineer or
MNT – Pavement Asset Management for further assistance.
The department has used the AASHTO 93 Guide for the design of CRCP, and it has
served the department well for the design of CRCP, despite its limitations. In March
2004, the NCHRP 1-37 report and the mechanistic-empirical pavement design guide
software (MEPDG) were released. In 2005, the department initiated Research
Project 0-4714-1 to evaluate the MEPDG for potential implementation. The study
recommended, for various reasons, not to implement the MEPDG as a replacement
for the design methods used at that time.
The district is the only required input in this section. By selecting the district, the
program will determine the environmental conditions for this pavement design. All
other information is not required to complete the thickness design, but they are
required for the final design submittal.
For rigid pavements, the initial pavement structure shall be designed and analyzed
for a performance period of 30 yr. A performance period other than 30 yr. may be
utilized with justifications.
3.2.3 Number of Punchouts per Mile
Provide a number of punchouts per mile that is considered the terminal condition of
CRCP you are designing. Traditionally, 10 per mile has been the number used for
CRCP design. For a higher class of highway where the number of punchouts may
be minimized, contact MNT – Pavement Asset Management for further assistance.
The traffic projections for a highway project (in terms of ADT and one-way total 18-
kip ESALs) are obtained from the traffic analysis report provided by the
Transportation Planning and Programming Division (TPP). This report is requested
during the design phase of a project and, upon receipt, should be evaluated for
reasonableness.
Input the one-way total 18-kip ESALs from the TPP traffic analysis report into the
design worksheet. The worksheet will calculate the design lane ESALs based on
inputted number of lanes in one direction.
Input a trial concrete slab thickness; the worksheet will predict number of punchouts
per mile for the design life. Adjust the slab thickness or other inputs until the
predicted number of punchouts per mile meets the requirement in “B. Design
Parameters.” Input the trial thickness in 1/2-in. increments.
The Modulus of Rupture (Mr) of concrete is a measure of the flexural strength of the
concrete as determined by breaking concrete beam test specimens. Use a 28-day
Mr of 570 psi. If the engineer selects an alternate value for Mr, it must be
documented with an explanation. Also, if a higher Mr is used, it should be required in
the plan to use a higher concrete strength than what is required in Item 360.
Soil Description Soil Classification System
USCS
Gravel GW or GP
Coarse
Coarse Sand SW
Grained Soils
Fine Sand SP
Silty Gravel
GM
Silty Sandy Gravel
Clayey Sand SC
Clayey Gravelly Sand
Silt ML or OL
Silt / Sand / Gravel Mix
Select the soil classification of subgrade from Unified Soil Classification system in
Table 8-2. Selecting the appropriate soil classification will assist in determining the
composite k-value of the support layers.
3.2.8 Base Layer Requirements
Select ATB for asphalt treated base, HMA for hot-mix asphalt, or CTB for cement
treated base.
Field performance evaluations of concrete pavement have revealed that the use of a
durable, stabilized, and non-erodable base is essential to the long-term performance
of concrete pavement. If the base underneath the concrete slab does not provide
good support, long-term pavement performance will be severely compromised,
regardless of the concrete slab thickness.
The department recognized this and requires one of the following base layer
combinations for concrete slab support:
a minimum 1 in. hot-mix asphalt bond breaker over 6 in. of a cement treated
base; use Item 276, Class L.
Approval from the Pavement Analysis & Design Branch of MNT – Pavement Asset
Management is required for use of base layers other than those listed above.
The subgrade/base must be designed 2 ft. wider than the concrete slab on each
side to accommodate slipform pavement equipment.
If the engineer elects to use a "drainable base," then coordination with the
Geotechnical, Soils and Aggregates Branch of CST personnel is required. Refer to
Chapter 2, Section 7, for an example of a typical drainable base system.
Input the proposed base layer thickness. For cement treated bases, ignore the 1-in.
thick bond breaker.
Input the modulus of elasticity of the base layer. Typical values of ATB vary from
100 ksi to 400 ksi. Use a value of 400 ksi for HMA and ATB.
The modulus of elasticity for cement treated bases (CTB) varies from 100 ksi to 700
ksi. Use a modulus of 500 ksi for cement treated bases.
2. A factorial was developed for various subgrade k and base modulus of elasticity
and thickness. Concrete stress was estimated for each cell of the 106 factorial
(specific combination of subgrade k and base modulus).
3. For each cell, the “equivalent” k value was derived from FEM analysis that would
provide the same concrete stresses.
For a factorial mentioned in step 2 above, the following levels were selected:
1. Subgrade k: 7 levels (25, 50, 100, 150, 200, 250, and 300 psi/in.).
3. Base modulus: 34 levels (50 ksi to 100 ksi with 10 ksi increment, 100 ksi to
1,000 ksi with 50 ksi increment, 1,000 ksi to 2,000 ksi with 100 ksi increment).
A total of 1,190 combinations were analyzed, and the k-Table was developed.
Section 4: Rigid Pavement Design Process for CPCD
4.1 Introduction
The following Figure 8-4 summarizes the CPCD design process.
Figure 8-4. CPCD Pavement Design Process.
A k-value of 300 psi/in. should be used in the CPCD design procedure with one of
the stabilized base layer combinations listed below.
Field performance evaluations of concrete pavement have revealed that the use of
a durable, stabilized, and non-erodable base is essential to the long-term
performance of concrete pavement. If the base underneath the concrete slab does
not provide good support, long-term pavement performance will be severely
compromised, regardless of the concrete slab thickness.
The department recognized this and requires one of the following base layer
combinations for concrete slab support:
a minimum 1 in. hot-mix asphalt bond breaker over 6 in. of a cement treated
base. Use Item 276, Class L.
Approval from the Pavement Analysis & Design Branch of MNT – Pavement Asset
Management Section is required for use of base layers other than those listed
above.
A bond breaker should always be used between concrete pavement and cement
treated base. There have been several instances across Texas where excessive
cracking and premature failures occurred when a concrete slab was placed directly
on cement treated base. These problems occur because concrete slabs tend to
bond directly to cement treated bases. This increases the chances for cracks in the
base to reflect through the overlying slab. This also increases tensile stresses in the
concrete slab due to temperature and moisture changes, resulting in higher
chances of additional cracking.
The subgrade/base should be designed 2 ft. wider than the concrete slab on each
side to accommodate slipform pavement equipment.
The department requires the use of tied concrete shoulders, tied curb and gutter, or
a widened lane, and the use of load transfer devices, so the load transfer coefficient
to be used for CPCD design is 2.9.
The department has not had much experience with positive drainage systems. As
stated in Chapter 2, the department’s philosophy on this issue is to prevent water
intrusion and pumping by using bases that are dense-graded, non-erosive, and
stabilized. The department has had good performance with such bases, and it is
believed that the bases recommended earlier in this section provide performance
equivalent to the AASHTO ‘fair’ level of drainage.
Currently, drainage coefficients in Texas for non-erosive stabilized bases are based
on the anticipated exposure of the pavement structure to water. “Table 8-3
Drainage Coefficients” shows the recommended drainage coefficients for Texas.
The coefficients are selected based on the annual rainfall in the project area.
48 – 40 0.96 - 1.00
38 – 30 1.01 - 1.05
28 – 20 1.06 - 1.10
18 – 8 1.11 - 1.16
NOTE: Higher drainage coefficients decrease the pavement thickness in the AASHTO procedure.
4.2.8 Reliability, %
The reliability value represents a "safety factor" with higher reliabilities representing
pavement structures with less chance of failure. The AASHTO Guide recommends
values ranging from 50% to 99.9%, depending on the functional classification and
the location (urban vs. rural) of the roadway. Based on TxDOT's experience, a
reliability of 95% should be used for rigid pavement with more than 5 million design
ESALs; a reliability of 90% should be used for rigid pavement with 5 million or less
design ESALs. If the engineer decides to use a different value, then it must be
documented and justified.
The traffic projections for a highway project (in terms of ADT and one-way total 18-
kip ESALs) are obtained from the traffic analysis report provided by TPP. This
report is requested during the design phase of a project and, upon receipt, should
be evaluated for reasonableness using guidelines discussed in Chapter 2, Section
8.
The predicted 18-kip ESALs is multiplied by a lane distribution factor (LDF). Table
8-4 lists the lane distribution factors. This factor represents the percentage of the
total one-way 18-kip ESALs that could be expected in the design lane. The design
lane is the lane that will carry the most traffic. Usually, it is assumed that the outer
lane of a highway with two lanes in each direction carries the most traffic. For a
three-lane facility, the middle lane is assumed to carry the most traffic. Traffic
distribution in urban areas is somewhat more complex due to merging and exiting
operations, but the same assumptions could apply.
≤4 1.0
6 0.7
≥ 8* 0.6
For CPCD design, the computed concrete slab thickness should be rounded to the
nearest full or half inch. For example, use slab thickness of 11.5 in. for computed
thickness of 11.4 in., and use slab thickness of 10 in. for computed thickness of 10.24 in.
The minimum slab thickness for CPCD is 6 in., and the maximum thickness is 12 in. It is
recommended to use CRCP for sections where the CPCD design thickness is greater
than 12 in.
The basic premise of the expansion joint system is that the expansion joint width
will be able to absorb any concrete pavement expansion without transmitting the
compression forces to the bridge structure.
The wide-flange system is similar to the expansion system, except that the
expansion joints exist under the wide flange and are not seen from the pavement
surface. One advantage is that, since the joint is not exposed to the pavement
surface, joint maintenance is minimized.
An anchor lug system tries to contain the concrete movement at the interface
between bridge and pavement by providing five anchor lugs.The department has
investigated the movements of CRCP near bridges and the effectiveness of these
three terminal systems in Research project 0-6326, “Rational Use of Terminal
Anchorages in Portland Cement Concrete Pavements.”The research data has
shown that the anchor lug system is not effective. The stresses generated in soil
due to slab expansion at lug walls are large enough to result in permanent
deformations in soils. The soil does not retract with the lug when the pavement
contracts. The permanent deformations result in voids between soil and lug walls.
Field measurements have indicated that the base friction restrains slab movements
effectively. Using coarse-textured base such as HMA might be the most effective
tool to control slab movements. Simple expansion joint systems or wide-flange
systems are effective in accommodating slab movements. Expansion joint systems
should cost less than wide-flange systems and attain comparable performance.
The use of anchor lug systems is no longer allowed, and the standard TA(CP)-99
has been deleted. The transverse expansion joint details at bridge approaches are
shown in the concrete pavement standards.
The department maintains many miles of thin PCC pavement that have exceeded
their design traffic projection and are still in reasonably good condition. The use of
BCO is based on the fundamental design assumption that the old and new concrete
layers behave as a monolithic layer. Providing full bond is of the utmost importance.
During construction, specific steps are taken to enhance and ensure the full bond
between old and new concrete as discussed in Chapter 10.
Bonded concrete overlays over jointed concrete pavements are difficult to construct
because all joints must be matched. CRCP-bonded concrete overlays have been
constructed and have performed successfully in several districts but have not been
used widely throughout the state. Districts considering a bonded concrete overlay
can contact MNT – Pavement Asset Management, Pavement Analysis & Design
Branch, for assistance.
Unbonded CRCP concrete overlays may be used over CRCP, jointed concrete
pavement (CPCD), or jointed reinforced concrete pavement (JRCP). Unbonded
CRCP overlay uses the same design procedure as new CRCP pavements. This
use of unbonded CRCP overlay can be credited for contributing to the structural
capacity of the existing concrete pavement and results in a thinner concrete
pavement design than required for CRCP constructed on a new location.
Where:
The slab thickness, Df, is determined for the design traffic as if it were built as a new
pavement on the prepared base. Use the design procedure in Sections 3 or 4 for
the pertinent pavement type. Some existing pavements might not have stabilized
bases, and the k-value should be evaluated using FWD or DCP.
Where:
For BCO design, the condition of the existing pavement is one of the most
important factors. If the pavement condition is deteriorated in the form of punchouts
and deteriorated cracks, BCO may not be a good alternative.
3. the number of existing and new repairs prior to the overlay per mile,
Punchouts are the only structural distresses in CRCP; the number of punchouts per
mile is a good indication of the structural condition of the existing pavement. If there
are more than 12 punchouts per mile, then the pavement is in poor structural
condition and may not be a good candidate for BCO.
The number of deteriorated transverse cracks per mile is the next item to be
surveyed. Even though some transverse cracks may appear to be deteriorated,
quite often they are structurally in good condition. In Texas, it is rare to observe
deteriorated transverse cracks, except for spalled cracks. Most spalled cracks are
not necessarily structurally deficient. Based on the research findings, it is
recommended that only transverse cracks much wider than normal, along the entire
length of the transverse crack and across the entire lane width, should be counted
as “deteriorated transverse cracks.”
The number of patches per mile and evidence of pumping should be recorded. In
Texas’ old concrete pavements, typically, the base was not stabilized and pumping
resulted. Durability related problems, such as D-cracking and ASR cracking, should
be noted and their severity recorded. Overall, it has been quite rare to observe
durability-related problems in concrete pavement in Texas.
A deteriorated joint or slab will rapidly reflect through an overlay and contribute to
loss of serviceability. Therefore, full-depth repair is recommended on all
deteriorated cracks and any other major discontinuities in the existing pavement
prior to overlay. The target Fjc is 1.00.
If it is not possible to repair all the deteriorated areas, use the total number of
unrepaired deteriorated joints, cracks, punchouts, and other discontinuities per mile
in the design lane to determine the Fjc from Figure 8-5.
Figure 8-5. Joints and Cracks Adjustment Factor for Bonded Overlays, Fjc. Source:
AASHTO Guide for Design of Pavement Structures (1993)
Durability Adjustment
Factor, Fdur Historical Records and Condition Survey Data
1.00 No evidence or history of PCC durability problems.
Cracking and spalling exist (in these conditions, a bonded PCC overlay
0.88 – 0.95
is not recommended).
7.2.3 Fatigue Damage Adjustment Factor, Ffat
The Fatigue Damage Adjustment Factor, Ffat, adjusts for past fatigue damage in the
slab. It is determined by observing the extent of punchouts (CRCP) that may be
caused primarily by repeated loading. Table 8-6 shows the fatigue damage
adjustment factor.
Table 8-6: Fatigue Damage Adjustment Factor
Fatigue Damage
Adjustment Factor, Ffat Historical Records and Condition Survey Data
Few transverse cracks/punchouts exist (none caused by D-cracking or
0.97 – 1.00
reactive aggregate distress), < 4 punchouts per mile.
The design engineer will determine the reinforcement bar size and number of
longitudinal steel, tie bars, and transverse steel. The performance of CRCP
depends on the percentage of longitudinal steel. Failing to place longitudinal steel
in a BCO 4 in. or thicker will effectively reduce the percentage of longitudinal steel
in the combined slab, which could increase steel stresses and make transverse
crack widths larger. See the recommended reinforcing steel percentage and vertical
location in Table 8-7.
Table 8-7: Reinforcement Requirements
Where:
Deff = Fjcu * D
Where:
D = existing slab thickness, in. (Use 10 in. when existing D > 10 in.)
Fjcu adjusts for PSI loss due to unrepaired joints, cracks, and existing expansion
joints, exceptionally wide joints (> 1 in.), or AC full-depth patches.
Use the total number of unrepaired deteriorated joints, cracks, punchouts, and
other discontinuities per mile in the design lane to determine the Fjcu from Figure 8-
6.
Figure 8-6. Joints and Cracks Adjustment Factor for Unbonded Overlays, Fjcu
Source: AASHTO Guide for Design of Pavement Structures (1993)
The reinforcing steel placements are the same as new CRCP when unbonded
overlay is 7 in. or thicker. When unbonded overlay is less than 7 in., use
longitudinal reinforcement at about 0.6% of concrete cross-sectional area. The
design engineer will determine the steel bar size and quantities for longitudinal
bars, tie bars, and transverse bars, and consult with the Pavement Analysis &
Design Branch of MNT – Pavement Asset Management.
This rehabilitation technique purposely seeks to bond the concrete overlay to the
existing asphalt. The composite action significantly reduces the load-induced
stresses in the concrete overlay. Therefore, the concrete overlay can be
significantly thinner for the same loading as compared to a whitetopping section
with no bond to the underlying asphalt. TWT will significantly reduce time and
delays accompanying the frequent maintenance of an asphalt surface.
Designs for < 4 in. TWT were not included because the initial cost difference
between 4-in. slabs and those with less than 4 in. is negligible, and thinner slabs
require shorter joint spacing, often encroaching on the wheel path.
Designs for > 7 in. TWT were not included because our standard concrete
pavement designs should be used along with load transfer devices.
Contraction joint spacing is set at 6-ft. intervals to prevent edge loading and
reduce the costs for saw cutting. All sawed TWT panels shall be square except
as necessary in pavement width transitions.
Recommend milling the existing ACP to provide a better bond and remove
rutting ≥ 1/2 in.
The department has yet to establish when expansion joints are needed for wide
pavements.
The use of steel fibers is not recommended at locations where de-icing salts
may be used.
Use Table 8-8 as a general guide for determining proper TWT thickness. More
research will be conducted to improve the design procedure.
Table 8-8: Thin Whitetopping Thickness (in.) Design
250 4 4 4 4 5 5
300 4 4 4 5 5 5
350 4 4 5 5 5 5
400 4 5 5 5 5 5
450 5 5 5 5 5 6
500 5 5 5 5 6 6
600 5 5 5 6 6 6
700 5 5 6 6 7 7
800 5 6 6 7 7 7
900 6 6 6 7 7 n/a
The traffic data (in terms of ADT, Percent Directional Distribution, and Percent
Trucks) are obtained from the traffic analysis report provided by TPP.
Where:
ADT = average daily traffic for the first year of design period
PT = percent trucks
LDF = lane distribution factor; use 1.0 for 4 lanes or less, 0.7 for 6 lanes, and
0.6 for 8 lanes or more. The lane number is for both directions.
Example:
Design Life = 10 years, ADT = 13,500, PDD = 63%, PT = 3.0%, and 4 lanes
roadway, LDF =1.0
Trucks per Day per Lane = 13,500 × 0.63 × 0.03 ×1.0 = 255
For 255 trucks per day per lane and 10-yr. design, the required TWT thickness
is 5 in.