WORK PROGRAMME

PLANNED (IN GREEN) / ACTUAL (IN RED)


PROGRESS STATUS AT MONTH 35

SITE ACCESS DELAYED EARTHQUAKE
(THREE‐MONTH DELAY) (THREE‐MONTH DELAY) New Critical Path

Project planning

Construction

SUBSOIL PROBLEM 
(ADDITIONAL COST OF 
10%) Equipment supply

CUSTOMS DUTIES UNPAID BY THE 
EMPLOYER (TWO‐ MONTH DELAY) Equipment assembly

RAW WATER SUPPLY NOT  Commissioning
PROVIDED ON TIME 
RAW WATER SUPPLIED (10 
BY THE EMPLOYER
MONTH DELAY)
Defects Notification Period 
Time for completion

YEAR 1 YEAR 2 YEAR 3 MONTH 35