Professional Documents
Culture Documents
People
DismissDismiss
Join nowSign in
Dangling Activities issue is one of the most influential defects of time schedules, especially for
big projects. The reason behind that is due to lack of tools for detecting them from time schedule,
and accordingly, for fixing them. Just imagine that scheduling software like Primavera and MS
Project have no available filters to check dangling activities or extract them from the activity list.
Therefore, such activities have more probability to stay and distort the program with inattention
of the scheduler.
“Dangling activities plague many schedules, and their presence in an active schedule
causes inaccuracies which potentially result in wrong critical paths and incorrect
milestone and completion dates.” (F. Saddik, 2015)
A dangle activity is an activity has a predecessor and a successor but still dangling from at least
one end. It could be considered as a type of Open-Ended Activities, but it is more complicated
due to it is already linked with relations to other activities, with the fact that these relations do
not govern it. This allows Dangle Activity to act similar to Open-Ended activity in spite of
existed relationships.
I have created an Excel Macro in order to provide a solution for this issue in an easy way as
explaining below. But before proceeding, we have to clearly define the meaning of dangling
activities to ensure that we are talking about the same term.
It could have (SS) or (SF) relation with its successor such as activity (B1) in figure (2) but it is
still dangling start because no activity in the network controls its start. The concern here is about
the relation with the predecessors.
It could have (FF) or (SF) relation with its predecessors such as activity (E1) in figure (4) but it
is still dangling finish because it can finish anytime without affecting other activities in the
network. The concern here is about the relation with the successors.
As aforementioned, any delay or expedition for a Dangle End (finish or start) will not impact the
project because it is not linked to the workflow sequence, which will lead to fake results of the
expected project completion date and/or project critical path.
For more information about Dangling Activities and its impact on the project time schedule, you
may refer to the following link:
http://www.projectrisk.com/white_papers/The_Problem_with_Dangling_Acti
vities_in_Project_Schedules.pdf
http://www.saddikandassociates.com/articles/10142015_SchedulingBestPracticeRemedyDanglin
gActivities.pdf
2- Copy relationships from the exported worksheet and paste them in the sheet “Relationships”
in the “Dangling Activities Detector” file.
3- Press “Detect Dangling” icon in the upper-left of the sheet,
The macro will extract any dangling activities in the program and provide them in two new
sheets, one for dangling start and the other for dangling finish.
You may stop here and link these activities in your way to fix them.
5- If you want the macro to provide suggestions for relationships linking dangles, then press
“Link Dangling” icon.
6- The macro will provide new suggested relationships to link dangles in two new sheets as
previous. You have to check these new relations carefully to ensure they are in proper and
realistic order. You may modify or replace some of them.
7- Once you feel satisfied with the results, press “Add New Links” icon. The macro will add
these new links to the “Relationships” sheet.
8- Copy relationships from the sheet “Relationships” in the “Dangling Activities Detector” file
and paste them in the exported worksheet again.
9- Import this sheet again to Primavera and run schedule. Note That the project completion
date may be impacted by adding these new links, so you have to study activity sequence and
duration again to fix that.
You may save a copy of your project as a backup before re-importing relationships to primavera.
Finally, I hope you find this article and the attached sheet useful. And I appreciate receiving your
feedback.
ِAddendum:
The new versions of P6 have some filters that can be used for detecting Dangling Activities but
of course not to fix them.
If you need a copy of the "Dangling Activities Detector" Excel Macro, you may download it
from that link, if the link does not work, write your email in a comment and I will send it to you.
129 64 Comments
LikeCommentShare
wasim akhtar
Very nice piece of work, ihope you will continue in the same way to help the people in need and share
knowledge with others.
Like
Reply
1 Like
3mo
Sami Abu-Al-Heijaa
Thank you so much for the nice work dear Ahmed
Like
Reply
1 Like
11mo
Services
Industries
Projects
Insights
About
Locations
VDC Education
Contact
RESOURCES
The Defaults tab under project settings can save you a lot of time if
you need to add multiple activities with the same calendar,
duration type, percent complete type, activity type, cost account,
and/or even a given ID structure. In other words, there is a way
you can pre-assign a given value to each of these settings for all
new activities you insert into the schedule, eliminating the need to
edit them on a per-activity basis after you’ve added the new tasks.
You can use this command to quickly copy WBS and Activity Code
values (as well as almost any parameter that can be displayed as a
column in the Activity Table) from one activity into other activities
in the schedule. For instance, if you’d like to change the calendar
for multiple activities, you need to:
c) Highlight all the activities that you need to update calendars for.
Note that the activities you select don’t need to be listed
consecutively in the Activity Table (ie: gaps in the range are
allowed as well). Also, ensure that the cell containing the desired
calendar ID (ie: the value that will be copied onto the rest of the
activities in the highlighted range) is the first item in that
selection, as shown in image 4.2 below.
5 DISABLE AUTO-REORGANIZATION
There are several data fields and activity settings that can be
edited at once for all the activities in your schedule through P6’s
Global Change tool. In order to access this feature, click the Tools
menu, and select Global Change. You will be prompted to create or
modify an existing rule.
Next, click the Ok button and select “Apply Change”. You will see a
log with all the proposed changes, as shown in Figure 6.2 below.
Finally, click “Commit Changes” to update all parameter values to
the new values.
Figure 6.2 – Global Change Report
Note that you can add multiple rules and use two logic operators
(ie: apply changes if “any” or “all” of the rules created apply) to
customize the Global Change you’re trying to implement. In this
case of this tip, we only used a single rule; but the tool can clearly
be utilized to implement more intricate and complex changes to
the schedule.
In order to control the way in which these values are shown in the
system, you may click Edit>User Preferences and navigate
between the Time Units (Figure 7.1) and Dates (Figure 7.2) tabs on
the left-hand side of the User Preferences window. For instance,
this comes in handy when engaging in higher-precision scheduling
efforts, which could require tracking activities down to the hour.
Conversely, you could set units to weeks, months, or even years if
you’re working on less-detailed, higher-level schedules.
8 EXPORT TO EXCEL
Have you ever lost track of the changes made from one schedule
revision to another or needed to put together a comprehensive
variance report? In these cases, the Claim Digger utility that comes
with Primavera P6 can be particularly useful.
This simple yet useful tip will spare you the (quite recurrent) pain
of seeing your schedules printed on more than 1 page wide (ie:
“horizontally” split into 2 or more parts). To scale your project so
it doesn’t exceed a width of 1 page, click Print Preview>Page
Setup. Make sure you do this from the Activity List view (not EPS).
Then, select “Fit Timescale To” and make sure “1” is selected, as
shown in Figure 12.1. Similarly, you may choose the “Fit To”
option and enter the same value. In this case, however, you’ll also
be prompted to fit the schedule to a given number of pages tall.
Figure 12.1 – Page Setup
When developing the logic for your schedule, remember links can
be created in three ways, which you can use to expedite your
workflow:
1) Visually: by clicking and dragging your cursor from one bar to
another in the Gantt chart.
2) At the Activity Details level: by going to the predecessors and
successors tabs in the activity details window and adding activities
to each list.
3) At the Activity Table level: by highlighting the activities you
need to connect, right-clicking on the selection, and choosing the
“Link Activities” option.
d) Save the file. Make sure the extension remains as .XER and is
not changed to .TXT.
The last step is to have P6 display the calculated variances for you.
To do this, simply add columns to the activity table (right-click>
columns) and pick the variance-related fields that best suit your
reporting needs. Options include columns like “Variance – BL
Project Duration” and “Variance – BL Project Labor Cost”.
You may have noticed that P6 offers two criteria for determining
the critical path in your schedule (F9 hotkey>Schedule Options): i)
Total Float Less Than Or Equal To (typically zero) and ii) longest
path. While both can yield the same results under certain
conditions, most times critical paths can differ dramatically when
calculated under one criterion over the other. Below are a few
notes that will help you decide which of the 2 to use.
The intent of the Critical Path Method (CPM) is to allow you to
obtain the total project duration by finding the longest sequence
(ie: “path”) of activities from project start through completion. If
we’re working on a schedule baseline, then both methods will lead
to the same result. In other words, activities in the longest path
will also be those with zero total float (TF). This continues to hold
even when we add constraints to our baseline to account for
intermediate and final project deadlines (eg: building dried-in,
substantial completion, and final completion milestones); as by
definition, a baseline shows no delays and hence no negative float.
Now, let’s assume we update the schedule and find that there is a
delay relative to the original completion deadline, as well as some
of the intermediate milestones we incorporated earlier into the
baseline. As you may expect, these unsatisfied constraints generate
negative TF values. Evidently, each of the 2 critical path
calculation criteria will yield completely different results this time
around. The Total Float Less Than Or Equal To (zero) method will
include any activity with a negative TF value; while the Longest
Path method will continue to show the longest progression of
activities leading to project completion.
Similarly, when the recipients of the .plf file have already opened
the schedule, all they need to do is go to the same menu and select
“Import” this time (View>Layout>Open; Import). Once they’ve
imported it, it will be listed on the Open Layout list for them to
use.
20 EXPORT FILTERS
Once you’ve created a layout and a filter, open the Filters window.
This can be accessed by right-clicking on the activity table and
selecting Filters, pressing the funnel icon on the toolbar, or by
clicking View>Filter By>Customize. Once there, select the desired
(ie: previously created) filter from the list and press the Copy As
Layout button, as shown in Image 20.1 below. Now the filter will
be listed under “Layout Filters” and will be exported together with
the current layout (ie: the layout that you previously created and
which you wish to send to your project team).
Image 20.1 – Filters, Copy As Layout
If you’ve been faced with this dilemma, fortunately, you can get
the best of both worlds by using the Activity Steps feature. This
option allows you to create sub-tasks (namely, “steps”) for the
activities you need to track more closely without the need to break
them down into separate, smaller activities. In order to do this,
select the activity you need to create steps for. Then, go to the
Steps tab located in the Activity Details window and define the
sub-tasks required for this activity as shown in Figure 21.1.
As shown above, you can record progress under each Activity Step,
and even assign weights to drive overall activity progress
calculation. If the latter is the case and you’d like P6 to do this
automatically for you, make sure to activate the “Activity Percent
Complete Based on Activity Steps” setting. This option can be
found under the Calculations tab at the project-level settings, as
shown in Figure 21.2 below:
Contact Us
We would love to learn more about your needs and find out how
our firm can work with you. You can reach us via the form below,
email us at engineers@viatechnik.com or call us at our various
offices.
Submit
SOFTWARE COMPATIBILITY
With the abundance of software built for the AEC industry, it has always been a challenge to
figure out the compatibility between file types. VIATechnik reviewed various software packages
to …
Autodesk Revit is an indispensable tool for architects, engineers, designers, and contractors. Its
use as a Building Information Modeling (BIM) software is critical for those involved in Virtual
Design and …
If you need help with Primavera scheduling, our experienced team can quickly develop a
managing schedule for your project, whether large or small. Find out how a Primavera scheduler
at …
COMPANY
Projects
About
Contact
Careers
Resources
INSIGHTS
Insights
Blog
Conferences
Subscribe
Search
About
o Who We Are
o Our Clients
o Contact Us
Courses
o Primavera P6 Professional
o Advanced P6 Schedule Building
o Construction Planning & Scheduling
o Forensic Schedule Delay Analysis
o Analyze P6 Schedules with ScheduleReader
o All Courses
Solutions For
o Companies
Resources
o Blog
o Video Channel
o Webinars
o Guides & Templates
o Help Center
Login
Blog > Guides > Duration Percent Complete in Primavera P6 – the Missing Guide
Duration Percent Complete in
Primavera P6 – the Missing Guide
MAY 14, 2012 BY NADER KHORRAMI RAD 48 COMMENTS
Duration % Complete
Units % Complete
Physical % Complete
Activity % Complete
Performance % Complete
Percent Complete Type
Earned Value settings of the WBS Elements
I will explain Duration % Complete in this article. Other fields and settings
will be explained in future articles and we will finally have a complete
picture of the whole actual progressing system in Primavera P6.
Primavera P6’s 3 Types of Activity Percent
Complete
Each activity has three percent complete fields that are calculated all the
time:
1. Duration % Complete
2. Units % Complete
3. Physical % Complete
Only one of these values will be selected by the user as the activity’s
progress, even though all of them are calculated all the time. I will explain
how to choose the appropriate activity percent complete in future articles.
But this is not the P6 formula. Duration % Complete is calculated with this
formula:
This formula uses Original Duration, which may be different from the
current duration. We will check this on the following sample.
Sample: We have an activity with original duration of 20 days. 15 days
have passed and we estimate it to finish in 18 days (yes, it’s much longer
than we expected initially). The Original Duration does not change
automatically after activity’s start.
Original Duration: 20d
Actual Duration: 15d
Remaining Duration: 18d
The following figure shows the initial state of this sample activity (named
A1):
Let’s say that the activity has started in May 8th. We’ll check the Started
checkbox and enter the actual start date in its date box.
Learn Primavera P6 Duration Percent Complete
Suppose that it’s currently May 27th; we will reschedule the plan for this
data date.
The Actual Duration is automatically calculated based on Actual Start Date
and the Data Date, as follows:
[Actual Duration] = [Data Date] – [Actual Start] (P6 formula for in-progress
activities)
However, after the activity has started, Original Duration will not be
automatically calculated by Early Start and Early Finish, and you can
change it manually. The At Completion Duration represents our current
duration, calculated as:
If you would like to have the intuitive Duration % Complete (for any
reason), you can create a global change to set the Original Durations of in-
progress activities. The following figure shows the appropriate global
change setup.
This global change checks each activity’s status; if it’s “In Progress”, then
the At Completion Duration would be copied to the Original Duration. We
will then have the intuitive Duration % Completes for all activities.
Summary
This tutorial has demonstrated the internal calculations of Primavera P6’s
Duration Percent Complete field.
The most common problem in this area is that Primavera P6 does not use
the intuitive formula for Duration % Complete which confuses some
planners and project managers. We explained the Primavera P6
calculations and the intuitive formula side by side, to show the differences
and create a better understanding of the P6 method. Finally, if you
absolutely need to use the intuitive formula, try the Global Change
described above.
Subscribe
i am very much great ful to you , i have a great experience with your
subject,please guide the planners in the same manner so that the
planning world shuold be the ruler in the universe.
Reply
2. s.a. mallick says:
Your Comments
The above mention information is really very useful . Is it possible to
give information for physical percnt complete method also and also
about cost loading in detail considering i am very new in planning
job
Thanks and Regards
s.a.mallick
Reply
3. Behzad says:
Reply
4. Arun R says:
Dear Mr.Nader,
I can’t say what i feel reading your article. It’s very helpful & is
mentioned so simply. I like that. I am waiting for Performance %
Complete article. Plannertuts is one of the best websites I seen
which publishes great helpful article. I waiting for more article that
help me to grow.
Reply
Reply
5. Mohamed Khafagi says:
Reply
Dear Mohammad,
The most likely problem is that you did not define any costs for
activities. The calculation of Performance % Complete is
depended on them.
Reply
6. Shuvro says:
Dear Sir,
Great Post !
Shuvro.
Reply
Reply
8. hosna says:
Hi
I have some problem with my P6 i was wondering if you could help
me with that
In activities detail i want to set details but it is inactive so what can i
do? What can cause this Mather?
Bests
Hosna
Reply
o PlannerTuts says:
Reply
9. nafis says:
Hi
Reply
10. viju says:
Reply
Reply
12. manoj says:
Reply
o Kriss says:
Reply
Reply
Hi,
In our project progress, my project finish date is passing the
required finish date. Is there any way that I can assign a constraint
and remaining activity durations get smaller to hit the target finish
date? For example, my project finishes on 14-Jan-2014, but I want to
finish it on 28-Nov-2014. What should I set my activity type and
duration type and percent complete type for Primavera to auto
shorten the remaining durations but keeping the same budgeted
labor units. I sincerely appreciate any help.
Reply
Reply
16. cris benecio says:
Reply
Reply
18. Mamoun says:
Dear Sir
i have a problem and i can’t understand this case
in my project Duration % Complete is 71.76 %
& Performance % Complete is 100 %
BR
Reply
Reply
PlannerTuts says:
Is this helpful? https://www.planacademy.com/primavera-p6-
relationship-lines-baseline-bars/
Reply
Dear Nader,
found your article helpful, but wonder why some quest arises in
mind that
Scenario
1. OD= 10
2. AD= 10
3. RD= 10
3. % Compl= 0%
but still some quantity of work progressed and duration lapsed and
resource did some work. could u please explain.
Reply
Mohammed F…,
This kind of scenario will occur when your work is not evenly
distributed with time.
I would suggest that you use physical % complete type for tasks like
construction activities whose progress is often not distributed evenly
over the duration.
However if you feel duration % complete is right for you, you might
want to fiddle with your Original duration or your Remaining
duration.
Regards
Reply
Reply
22. Alexander says:
Good luck.
Reply
23. Aamer says:
Reply
o Michael Lepage says:
Aamer,
For Duration Type, stick to Fixed Duration & Units/Time – only
change this if you’re trying to have P6 calculate durations or
number of resources (in very special circumstances – like a
change request or scenario).
Most industries use Physical % Complete. Units is never used,
and Duration is the default but not ideal – stick to Physical. I
teach both of these subjects in great detail on PlannerTuts
Premium – our online training portal.
Michael
Reply
24. Aria says:
May 07, 2014 at 11:49 pm
I think “Suppose that it’s currently May 29th”; is correct . would you
check again?
Reply
25. SUNIL says:
Reply
26. Arul says:
Reply
27. Afsaneh says:
Reply
28. Amin says:
Reply
Reply
o de jong says:
Emmy,
Concerning the financial project performance:
In many projects the clocked manhours are in a different
software system , and primavera calculates the earned value
hours. The calculation of the earned value is done by %
complete times 1% of the baseline budget.
This means that it does not matter what kind of % kpl you use.
Reply
30. Rory says:
If you use a global change to change the original duration then you
are changing the durations that you planned therefore your as built
schedule will not be useful for estimating durations on future similar
projects. Therefore you will not able to review your planned
durations (original duration) against your actual durations. Using
your global change methosshould not be recommended in my
opinion.
Reply
Reply
o Michael Lepage says:
Reply
Reply
Reply
o Michael Lepage says:
HOME
BLOG
PMP
SOFTWARE TOOLS
EVENTS
MY ACCOUNT
Obalim Esedebe, April 18, 2021, Primavera P6, Software Tools, 2
A Sample Construction Project Schedule
Example in Primavera P6
A work schedule is required for any type of project regardless of whether it is small or large to
estimate the completion date of the project and the project tasks. Therefore, it is a good decision
to create a schedule before the beginning of a project. Oracle Primavera P6 and Microsoft Project
are scheduling tools that are used to create schedules to demonstrate what needs to be done, by
which resources, and when. In this tutorial, we will learn how to create a sample construction
project schedule in Primavera P6 with the help of an example.
We shall be using the schedule as shown in the table below for the purpose of this tutorial.
Activity ID Activities Duration Predecessor
Phase 1 Foundation
Phase 3 Finishing
Creating a Project
Creating WBS
Adding Activities
Inserting Relationships
Demonstrating Gantt Chart
Set Up
To create a new project in Primavera P6, you begin by first logging into the primavera P6
Software. Once you have logged in, you should have an interface like this below.
Once you are logged in there are different ways to create a new project. In this tutorial, we shall
be looking on at one of the different ways to create a new project. But first, let us understand the
interface.
The bar by the left-hand side of your screen is known as the Directory Bar. The bar by the right
is known as the Command Bar. The Bar at the top is known as the Tools Bar. Right above the
tools bar is the tabs or menu. Within the P6 interface, there are 3 major interfaces. The timeline
or table by the left, the Gantt by the right, and the detail view below. Within the table, you have
different columns.
One Way to Create a New Project
Begin by clicking on file the click on new.
The Create a project Wizard will appear. In the create a project wizard click next in the Project
ID enter 3 bed. In the Project Name enter 3 Bedroom Bungalow and click on finish.
Once we have created the new project it will appear in our Table under the project view.
Open our project – Right-click on the newly created project (3 Bedroom Bungalow) and click
open project.
Before to start inserting activities and activity relationships in this sample project for
construction, you need to create a Work Breakdown Structure (WBS) in Primavera P6. While
creating the WBS, keep in mind the key project deliverables.
Create WBS | Click on WBS in the directory bar, then click Add in the command bar and type
in foundation in the new WBS.
Move superstructure left one step. Note the move left button is in the command bar by your right
represented by an arrow facing the left direction.
Your WBS table should appear as below when you are done.
Go back to your activities view by clicking on activities in the directory bar or at the top of your
view. Once your activity page opens, hit F5 on your keyboard to refresh.
Adding Activities
Next step of our example Oracle Primavera P6 schedule is adding activities.
By default, Primavera P6 assigns a 5-day duration to each activity. If your bars are not showing
in the Gantt, simply double click on your Gantt view.
Now repeat the process for activities under Super Structure and Finishing.
By the time you are done your schedule will appear as below.
Enter the activity durations as contained in the table. Ensure you sort by activity ID. To do this,
click on the Activity ID column make sure the arrow on the column is pointing down.
Working with Columns
At this step of our sample construction schedule in Oracle Primavera P6, we will show how to
work with columns.
Right-click on anywhere within your table then click on columns in the window that appears.
Click available options and select find or simply do CTRL + F. In the find window type in
predecessors. Look for and select predecessors and click on add to list or simply double click.
Use the up and down arrow to position it after the remaining duration. Then click on close.
To assign predecessors, double click on digging activity in the predecessor column cell. The
assign predecessor’s window appears, select clearing in the window and click assign. Do not
close the window as we shall use it for all our assignments before we close it.
Next click on blinding in the timeline table, in the assign predecessors window click digging then
click assign.
You should be seeing the relationships show up in the predecessors’ column in the table as well
as the predecessors tab in the details view and also in the Gantt Chart as below.
Repeat same for other relationships as captured in the table. For activities that have more than
one predecessor simply do it repeatedly. Once you are done click on close, to close the assign
predecessor window.
Next is to schedule. Click on the schedule button on the toolbar then click schedule.
Oracle Primavera P6 Gantt Chart View of the
Sample Construction Schedule
Once you have done that, this example Primavera P6 schedule will appear like below.
Obalim Esedebe
I am a Project Management Professional (PMP) and a Certified Business Analysis Professional (CBAP). A
Trainer and CEO of Ciel Consulting, a company specializing in the training and development of individuals
and organizations.
My goal is to help you achieve your personal and business goals faster and easier than you ever imagined.
I have consulted for major companies and addressed more than 2,000 people in 100’s of talks and seminars
throughout Nigeria. As a Trainer and Senior Consultant, I address more than 2,000 people each year.
SHARE THIS
RELATED ARTICLES
+
Become a Primavera Project Planner (Scheduler)
How to Become a Primavera Project Planner There are many professionals working in
the project management field of different...
+
Primavera P6 Global Change Tool Explained
Primavera P6 Global Change Tool Explained In a large and complex project schedule, a
large number of changes and...
+
Must Know Excel Functions for Business Analysis
Must Know Excel Functions for Business Analysis You may use Excel for basic
calculations. But, have you ever taken...
+
Best Cloud ERP Systems to Try In 2022
Best Cloud ERP Systems to Try In 2022 Cloud ERP systems (such as Oracle Cloud ERP
systems) are enterprise...
+
Primavera P6 Tutorial for Beginners
Primavera P6 Tutorial for Beginners A few weeks ago one of our readers asked “How
long does it take...
+
Schedule Baseline and User Baseline in Primavera
P6
+
Oracle Primavera P6 Project, Activity and Resource
Codes
Oracle Primavera P6 Project, Activity and Resource Codes Unlike other software tools,
Oracle Primavera P6 enables to use project,...
+
Resource Leveling Feature of Primavera P6
The term resource leveling is widely used in project management to refer to resource
optimization and limitation. Resource leveling...
2 COMMENTS
1.
Ogude Oghenenyerhovwo3 months ago
Hello sir. How can I get sample project schedules for practice?
REPLY
2.
Gregory1 month ago
Leave a reply
Your email address will not be published. Required fields are marked *
Comment
Name *
Email *
Website
Save my name, email, and website in this browser for the next time I comment.
Post comment
This site uses Akismet to reduce spam. Learn how your comment data is processed.
Latest Articles
What is Incremental Backup in SQL Server? Why Should You Use it?January 5,
2022
Follow Us
About Us
ProjectCubicle.com provides practical solutions, tutorials, articles and templates to help you
manage your projects more successfully. It is a community, for experts in all industries.
admin@projectcubicle.com
Site Links
About Us
Contact Us
Subscribe
Licensing
Blog As Guest
Subscribe
Skip to content
PROJECT MANAGEMENT
O
O
O
O
AGILE METHODOLOGY
O
O
O
PMP NOTES
O
O
O
O
O
O
O
O
O
O
O
O
PRIMAVERA P6 DOWNLOAD
O
O
O
O
DOWNLOADS
PROJECT MANAGEMENT
O
O
O
O
AGILE METHODOLOGY
O
O
O
PMP NOTES
O
O
O
O
O
O
O
O
O
O
O
O
PRIMAVERA P6 DOWNLOAD
O
O
O
O
DOWNLOADS
Hello Together,
I have seen people looking for templates and stuff. That is the reason I dedicated this post to
putting all the stuff together.
Note: I took this material from different resources and did not own all of this.
If you find any material copyrighted or owned by you can inform me with proper links or any
other ownership proof at faris.ahmad.raza@gmail.com; I am happy to remove it or give
appropriate credit here. Please keep in mind; the sole purpose is to help others for learning
purposes.
Quick Navigation [show]
I also request you to contribute to sharing any stuff – send me the same email.
DOWNLOAD PRIMAVERA P6
Primavera P6 Download
For more templates, Books, etc., you can find below…
Make sure these are only for educational purposes and are collected from different online free
resources.
One Request, please send me (faris.ahmad.raza@gmail.com) any previous program in any format that
you think will be helpful for others. I will upload it here. Thanks
FEATURED POSTS
Download Primavera P6
To download and install Primavera P6 was never that easy as nowadays. By following these steps…
Download Primavera P6
What is PMP?
What does PMP stand for? You are here as you just have heard about PMP, or you know a little already
but have some …
What is PMP?
Stakeholer Engagement
A stakeholder is any individual, a group of people or an organization that can affect or be affected
positively….
Stakeholer Engagement
Work Breakdown Structure
Work Breakdown Structure is simply a tool that breaks the work down into a structure…
Project Management
Gantt Chart
A Gantt chart is also known as bar chart represents a project plan by making each task into a bar and …
Gantt Chart
Planning Engineer
Planning Engineer is considered the right-hand of a Project Manager as he floats the information about
project…
Planning Engineer
Team Development
Dr. Bruce W. Tuckman, a psychologist published a theory in 1965 called ‘Tuckman’s Stages of …
Team Development
Post navigation
← Previous Post
Next Post →
13 THOUGHTS ON “DOWNLOAD STUFF RELATED TO PROJECT
MANAGEMENT”
1.
TOM
OCTOBER 9, 2019 AT 7:18 AM
Thank you for Primavera P6 and extension of time stuff.
Reply
1.
PROJECT EDITOR
JANUARY 20, 2020 AT 2:18 PM
You are welcome Mr. Tom
Reply
2.
LIZA
OCTOBER 23, 2019 AT 6:40 PM
A complete guide on Primavera installation was required & you know you are the who
Reply
1.
PROJECT EDITOR
OCTOBER 23, 2019 AT 7:27 PM
Welcome, Liza
Reply
3.
SRINATH
JANUARY 16, 2020 AT 1:03 PM
Reply
1.
PROJECT EDITOR
JANUARY 16, 2020 AT 3:29 PM
You are welcome dear
Reply
4.
MEHBOOB
FEBRUARY 12, 2020 AT 7:04 PM
Thank you for primavera p6 and extension of time stuff.
Reply
1.
PROJECT EDITOR
FEBRUARY 13, 2020 AT 5:14 AM
You are welcome, Mehboob
Reply
5.
STEVE GILLESPIE
APRIL 30, 2020 AT 1:36 PM
Can Primavera be installed with an enterprise distribution package instead of individual
downloads for each install?
Reply
6.
VINOD DAVID
SEPTEMBER 6, 2020 AT 7:11 AM
Thank you for Primavera P6 and the download files. I’ll definitely share this website with
my friends and colleagues.
Reply
1.
PROJECT EDITOR
SEPTEMBER 10, 2020 AT 6:00 AM
Thanks Vinod, make sure to download Planning related stuff from
here https://project.pm/download-stuff-related-to-project-management/
Reply
7.
MOHAMMED MUKKRUM
SEPTEMBER 8, 2021 AT 2:10 PM
The interview questions prepared , are excellent & was really helpful. Take a bow !!!
Reply
1.
PROJECT EDITOR
SEPTEMBER 21, 2021 AT 8:12 AM
Thanks Mukkrum
Reply
LEAVE A COMMENT
Your email address will not be published. Required fields are marked *
Type here..
Name*
Email*
Website
Post Comment »
FEATURED POSTS
What is PMP?
WHAT IS RACI?
STAKEHOLDERS ENGAGEMENT
DOWNLOAD PRIMAVERA P6
INTERVIEW QUESTIONS
GANTT CHARTS
PROJECT BASELINE
S CURVES IN PROJECT
7 QUALITY TOOLS
PARETO CHART
PROJECT MANAGEMENT
CHANGE ORDERS
ESTIMATING TECHNIQUES
What is WBS?
Team Development Tuckman
7 Basic QC Tools
Estimation Techniques
Critical Path Method
Earned Value Management
EMV
Organizational Structure
Project Stakeholders
TCPI
Gantt Chart Importance
Change Orders
Interview Planning Engineer
What is Lead & Lag?
Lean Project Management
Network Diagrams
MS Project & P6
Parteo Charts
Project Cahrter
Crashing a Project
Planning Engineer
Download Primavera P6
PERT
Project Management
Project Baseline
Expeditor vs Coordinator
Kick Off Meeting
PM Life Cycle
S Curves in PM
What is 6 Sigma
Project PM
What is PMO?
What is PMP?
PM Techniques
What is PPM?
What is SOW?
RACI Model
Risk Management
Project Engineer
What is ROM?
Contact Us
Disclaimer
Cookies Policy
Scroll to Top
https://drive.google.com/drive/folders/1ge9H0n2Nwjge17_P3TQKNPhARbThoR3R