Professional Documents
Culture Documents
00077277
00077277
Friedrich Kiessling
Siemens AG, T r a n s p o r t a t i o n and P u b l i c A u t h o r i t i e s D i v i s i o n , Dept. E 4 3 ,
Werner-von-Siemens-StraBe 50
D-8520 Erlangen
Abstract OENMARK
S t a r t i n g w i t h a s h o r t review of t h e overhead
c a t e n a r y system employed f o r t h e new l i n e s and of t h e
new high-performance pantographs, t h e r e p o r t d e s c r i b e s
t h e c h a r a c t e r i s t i c d a t a of t h e t r i a l s e c t i o n . Up-
g r a d i n g of t h e c a t e n a r y and u s i n g a new pantograph
enabled t h e r e c o r d speed on rails. Advanced measuring
d e v i c e s were used t o s u p e r v i s e t h e r u n of t h e panto-
graph and t h e behaviour of t h e c a t e n a r y . The monitored
d a t a proved t h a t t h e t r a c t i v e power was r e l i a b l y
t r a n s m i t t e d t o t h e v e h i c l e even a t t h e a t t a i n e d peak
speed.
1. I n t r o d u c t i o n
I n o r d e r t o a c c e l e r a t e t r a f f i c on r a i l s Ger-
man F e d e r a l Railway (DB) s t a r t e d a program t o b u i l d
new high-speed l i n e s and t o upgrade t h e e x i s t i n g n e t .
T h i s program comprises a t o t a l of about 2300 km. The
f i r s t two completely new l i n e s c o n n e c t i n g Hanover and
Wiirzburg as w e l l as Mannheim and S t u t t g a r t a r e t o be
commissioned end of 1990. Parts of them have a l r e a d y
been t a k e n i n t o s e r v i c e . F i g . 1 shows t h e new l i n e s Fig. 1: High-speed lines within t h e German Railway
w i t h i n t h e German Railway system. The s o u t h e r n p a r t Of network
23 CH2749-0/89/0000-0023$1.OO @ 1989
I1 I
t h e Hanover -
Wiirzburg l i n e &s completed i n due time s u p p l y through t h e overhead c a t e n a r y and t h e panto-
t o be put i n t o s e r v i c e end of May 1988. graph t o t h e v e h i c l e is t h e d e c i s i v e f a c t o r i n a speed
r e c o r d a t t e m p t w i t h e l e c t r i c a l t r a c t i o n . The speed
I n p a r a l l e l t o c o n s t r u c t i o n of new l i n e s a which c o u l d be achieved i n t h e tests of SNCF i n 1981
p r o t o t y p e of t h e f u t u r e advanced i n t e r c i t y t r a i n s , t h e was l i m i t e d by the power supply through t h e overhead
ICE ( I n t e r c i t y Experimental), was developed and com- c a t e n a r y system L 5-/. These d i f f i c u l t i e s were e f f e c -
missioned end o f 1985. T h e r e f o r e , a v e h i c l e and a t i v e l y avoided by a n adequate a d a p t i o n of t h e overhead
s t r e t c h were a v a i l a b l e t o approach t h e l i m i t s of t h e c a t e n a r y i n t h e t r i a l s e c t i o n w i t h r e s p e c t t o t h e high
w h e e l - r a i l system, and DB's management decided t o speed and by t h e newly developed pantograph. There-
c a r r y o u t high-speed r u n s on t h e new l i n e . The r u n s f o r e , t h e power s u p p l y d i d n o t determine t h e maximum
s t a r t e d on A p r i l 22nd, 1988 and culminated w i t h a max- speed achieved.
i m u m speed of 406.9 km/h on May lst, 1988.
2. T r i a l S e c t i o n and Record Run
The r o u t e s of t h e new high-speed l i n e s L-3-7
have been surveyed t o a l l o w f o r speeds up t o 300 km/h The s t r e t c h where t h e ICE r a n w i t h t h e maxi-
and t o be s u i t a b l e f o r passenger as well a s f o r mum speed is p a r t of t h e new high-speed l i n e from
f r e i g h t t r a i n s . T h e r e f o r e , o n l y a maximum s l o p e of Hanover t o Wiirzburg and is a l l t o g e t h e r a b o u t 60 km
12.5 ' 1. was p e r m i t t e d as a g a i n s t 35 %. adopted f o r long. The t r i a l r u n s s t a r t e d i n t h e s t a t i o n of Wiirz-
SNCF's new P a r i s - Lyon l i n e . burg and ended i n t h e s e r v i c e s t a t i o n of Mottgers.
Fig. 3 shows t h e topography of t h e t r i a l s e c t i o n . The
The l i m i t a t i o n of t h e s l o p e and t h e a d v e r s e overhead c a t e n a r y had been upgraded between km 308 and
topography of h i l l y t e r r a i n encountered i n most p a r t s km 282 on a t o t a l l e n g t h of 26 km, because i n t h i s
of t h e new l i n e s as well as environmental a s p e c t s ne- s e c t i o n s p e e d s exceeding c o n s i d e r a b l y 300 km/h were
c e s s i t a t e d a huge number of t u n n e l s . Out of t h e 327 km expected.
l o n g s e c t i o n Hanover - Wiirzburg 1 2 1 km r u n i n a t o t a l
of 61 t u n n e l s , and o u t of t h e 99 km l o n g Mannheim - A t t h e beginning of t h i s s e c t i o n t h e l i n e
S t u t t g a r t s e c t i o n 30 km i n 15 t u n n e l s . A l l t u n n e l s s l i g h t l y ascends. Then it s l o p e s down t o t h e Main val-
must be passed w i t h m a x i m u m speed. l e y f o r about 10 km w i t h a n i n c l i n a t i o n of 12.5 %a. I n
f r o n t of t h e Einmalberg t u n n e l a s h o r t a s c e n t a l s o of
The ICE (Fig. 2 ) was developed as p r o t o t y p e 12.5 %f.o l l o w s and t h e n t h e l i n e s l o p e s down a g a i n t o
of D B ' s f u t u r e advanced high-speed i n t e r c i t y t r a i n s t h e S i n n v a l l e y with a n i n c l i n a t i o n of 8 %..The l a s t
which w i l l c i r c u l a t e on t h e new l i n e s and on t h e up- p a r t of t h e s e c t i o n is almost l e v e l . The smallest
graded p a r t s of t h e e x i s t i n g network s t a r t i n g i n 1991. curve r a d i i of t h e t r i a l s e c t i o n amount t o 5300 m with
T h i s p r o t o t y p e t r a i n was designed f o r a maximum speed a r a i l s u p e r e l e v a t i o n of 85 mm.
of 100 m / s (360 km/h) and intended t o t e s t advanced
r a i l r o a d - t r a c t i v e , c o n t r o l , running and braking tech- There are t h r e e t u n n e l s i n t h i s l i n e s e c t i o n :
nology 4-/. The t r a i n is composed of two e n g i n e s a t t h e Muhlberg t u n n e l , t h e Einmalberg t u n n e l and t h e
t h e head and t h e end and a v a r i a b l e number of unpow- Sinnberg t u n n e l . These t h r e e t u n n e l s are s i t u a t e d
e r e d i n t e r m e d i a t e cars i n between. The e n g i n e s have w i t h i n t h e p a r t where t h e peak speeds d u r i n g t h e t r i a l
been provided w i t h a power c a p a c i t y of 4200 kW each. r u n s had t o be expected. A t o t a l of 14 s w i t c h p o i n t s
They employ modern 3-phase equipment and are c o n t r o l - form p a r t of t h e t r i a l t r a c k ; two of them, s i t u a t e d i n
l e d d i g i t a l l y as f a r a s p o s s i b l e . t h e Miihlberg t u n n e l , had t o be passed w i t h t h e maximum
speed. No m o d i f i c a t i o n was made t o t h e t r a c k , includ-
A s a p p l i e s t o D B ' s e x i s t i n g network of elec- i n g t h e s w i t c h p o i n t s . The r e l a t i v e l y s m a l l r a d i i w i t h
t r i f i e d l i n e s , t h e new l i n e s a r e s u p p l i e d w i t h 15 kV/ l i m i t e d s u p e r e l e v a t i o n and t h e t u n n e l s do n o t c o n s t i -
16 2/3 Hz t r a c t i v e energy. For t h i s t y p e of power sup- t u t e optimum c o n d i t i o n s f o r high-speed runs. But s i n c e
p l y t h e l i n e ' s electric equipment proves t o be compar- i n p r i n c i p l e a l l o t h e r s e c t i o n s of t h e new l i n e do n o t
a t i v e l y simple. T h e r e f o r e , a c o n v e n t i o n a l c a t e n a r y o f f e r any b e t t e r c o n d i t i o n s , DB decided t o u s e t h e
was i n s t a l l e d on t h e new l i n e s . The f a i l s a f e power d e s c r i b e d s e c t i o n f o r t h e tests.
-- Rohrboch stotion
- 26_
. krn _ ~ ~ -,
_ _
Burgsinn station
_ _
I1 I 1
During t h e r e c o r d r u n t h e I C E a t t a i n e d a
speed of 365 km/h a t km 300, a c c e l e r a t e d t o 380 km/h
b e f o r e e n t e r i n g t h e Miihlberg t u n n e l and s u r p a s s e d
400 km/h a t km 292.7 j u s t b e f o r e t h e end of t h e Muhl-
berg t u n n e l . On t h e Main v a l l e y b r i d g e t h e speed in- truck center
c r e a s e d t o 405 km/h. On t h e s l o p e down t o t h e Sinn
v a l l e y t h e I C E c o u l d a c c e l e r a t e once a g a i n and reached
t h e t o p speed of 406.9 km/h a t km 288.0 i n t h e Sinn stitch wire Bzll 35mrn’ messenger wire Bzll 70rnm’
v a l l e y (Fig. 31, e x a c t l y a t 11.13 o ‘ c l o c k on May lst, F = 2.8 kN F=lSkN
1988. From km 292.7 t o lan 287.3, t h a t is t o s a y on a
l e n g t h of 5.4 km, t h e speed was above 400 km/h. De-
s p i t e t h e unfavourable topography of t h e r o u t e t h e I C E
achieved t h e a s s i g n e d t e s t o b j e c t i v e s i n a l l r e s p e c t s .
3. Overhead Catenarx
CWH=5.30m \, \
D B l s new l i n e s are equipped w i t h a newly i contact wire RIS 120115kN dropper B z l l 16mrn’
developed -catenary f o r t h e s e r v i c e speed of 250 km/h
-/ 6, 7, a-/, which is c a l l e d R e 250. The Re 250 is a VSO i
l i g h t c a t e n a r y w i t h a messenger and a c o n t a c t w i r e and
s t i t c h wires w i t h i n t h e r a n g e of t h e s u p p o r t s , a s i t 0.30 m track center
is commonly i n s t a l l e d on many o t h e r AGpowered rail-
ways. The v e r s i o n of t h e Re 250 i n t h e t u n n e l s e c t i o n s /
d i f f e r s from t h e t y p e i n t h e open s e c t i o n s by a re- support contact wire support
duced system h e i g h t and s h o r t e r span l e n g t h s .
Fig. 4: Catenary of t h e c o n t a c t l i n e system Re 250 on
The d e s i g n of t h e c a t e n a r y is of utmost im- open a i r s e c t i o n s
p o r t a n c e i n view of t h e very high speeds. Mechanical
r a t i n g of t h e Re 250 aimed a t reducing t h e e l a s t i c i t y The chosen span l e n g t h s and t h e t e n s i l e f o r c e
of t h e c a t e n a r y t o approximately 0.5 m/N. T h i s was of 15 kN i n t h e c o n t a c t and messenger wire r e s u l t e d i n
ensured by i n c r e a s e of t h e t e n s i l e f o r c e s i n t h e con- a mid-span e l a s t i c i t y of 0.6 m/N i n t h e open-air sec-
tact and messenger wire and by t h e l i m i t a t i o n of t h e t i o n s and 0.4 mm/N i n t h e t u n n e l s . Optimizing t h e
span l e n g t h s t o a maximum of 65 m i n t h e open s e c t i o n s l e n g t h and t h e t e n s i l e f o r c e s of t h e s t i t c h w i r e s re-
and 44 m i n t h e t u n n e l s , as a g a i n s t t h e d e s i g n h i t h - duced t h e non-uniformity t o 10 % i n t h e o p e n - a i r sec-
e r t o used by DB w i t h a maximm of 80 m. t i o n s and 6 % i n t h e t u n n e l s .
F i g . 4 shows t h e c a t e n a r y i n t h e open sec- 4. Pantograph
t i o n s . Table 1 lists t h e most i m p o r t a n t d a t a . The
copper c o n t a c t wire a l l o y e d w i t h 0.1 % o f s i l v e r h a s a Primary t e s t s w i t h speeds of 250 km/h proved
nominal s t r e n g t h of 350 N/m’ and a c c o r d i n g t o German t h a t D B l s s t a n d a r d pantograph would n o t be s u i t a b l e
Standard i t can be s t r u n g w i t h a maximm s t r e s s of f o r speeds of 250 km/h and above. T h e r e f o r e , new pan-
160 N/mmz. The chosen t e n s i l e f o r c e of 1 5 kk?, t h a t is t o g r a p h s had t o be developed.
t o s a y a stress of 125 N/m‘ f o r a new c o n t a c t wire,
t a k e s i n t o account p o s s i b l e wear and tear. The messen- The overhead c a t e n a r y t o g e t h e r w i t h t h e pan-
g e r wire, a bronze w i r e Bz I1 70, was a l s o s t r u n g w i t h tograph forms a system a b l e t o v i b r a t e ; i t s components
a t e n s i l e f o r c e of 15 kN. cannot be a s s e s s e d independent from each o t h e r . The
c o n t a c t f o r c e s form a c r i t e r i o n f o r t h e i n t e r a c t i o n
Table 1: T e c h n i c a l Data o f Contact Line Re 250 between pantograph and c a t e n a r y . To a d o p t t h i s crite-
r i o n i t is n e c e s s a r y t o measure t h e c o n t a c t f o r c e s
Contact w i r e CuAgRi 120 c o n t i n u o u s l y . For t h i s purpose D B l s r e s e a r c h and test
department develoEed an-equipment which has been i n
T e n s i l e f o r c e of c o n t a c t wire (kN) 15 u s e s i n c e 1981 9, lo-/. It r e c o r d s t h e p a t t e r n of
Messenger wire Bz I1 70 t h e f o r c e s under l i v e c o n d i t i o n s and e n a b l e s t o calcu-
l a t e t h e mean v a l u e , t h e minimum and maximum as w e l l
T e n s i l e f o r c e of messenger w i r e (kN) 15 a s t h e s t a n d a r d d e v i a t i o n . F i g . 11 and 14 show exam-
S t i t c h wire Bz I1 35 p l e s . According t o t h e Gaussian d i s t r i b u t i o n t h e con-
t a c t f o r c e s normally r e g i s t e r e d v a r y between t h e mean
T e n s i l e f o r c e of s t i t c h wire (kN) 2.8 v a l u e plus/minus t h r e e times t h e s t a n d a r d d e v i a t i o n .
Length of s t i t c h wire’) (m) 18/14 I n o r d e r t o keep t h e maximum c o n t a c t f o r c e below 200 N,
i t was s t i p u l a t e d t h a t
Current capacity2) (A) 670
- t h e mean c o n t a c t p r e s s u r e of t h e new pantograph is
Maximum span1) (m) 65/44 n o t t o exceed 120 N and
System h e i g h t (m) 1.8/1.1
- t h e s t a n d a r d d e v i a t i o n s h a l l be a t most 20 $ o f t h i s
v a l u e , t h a t is t o s a y o n l y 24 N .
Stagger (m) -+ 0.3
The t a r g e t (Fig. 5 ) for t h e s t a n d a r d devia-
Contact w i r e h e i g h t (m) 5.3 t i o n of t h e dynamic f o r c e s f o r new pantographs under
0.6/0.4 t h e overhead c a t e n a r y R e 250 was based on t h e s e v a l u e s
E l a s t i c i t y , mid span’) (mm/N ) which were r e l a t e d t o a speed of 300 h / h .
E l a s t i c i t y , s u p p o r t 1) (m/N 1 0.5/0.35
Non-uniformity 1) T h e o r e t i c a l - c a l c u l a t i o n s adopting-Finite E l e -
(X) 10/6
ments Method L U-/, wind t u n n e l t e s t s L 12-/, t r i a l
r u n s on v e h i c l e s and measurements on D B l s v i b r a t i o n
1) The second f i g u r e r e l a t e s t o t u n n e l s e c t i o n s
t e s t s t a n d ensured t h a t t h e newly designed pantographs
2 ) With a c o n t a c t w i r e worn o u t t o 8 0 % of its c r o s s - met t h e s t i p u l a t i o n s and proved s u i t a b l e f o r speeds
s e c t i o n , w i t h o u t p a r a l l e l f e e d e r s and w i t h o u t exceeding 400 km/h w i t h o u t any m o d i f i c a t i o n s . Fig. 6
t r a n s v e r s e c o u p l i n g of p a r a l l e l c a t e n a r i e s and 7 show new t y p e s of pantographs.
I1 I
35 -
pantograph SBS 65 under Re200 /
a c h i e v e d s t a n d a r d d e v i a t i o n s of t h e c o n t a c t f o r c e s on 3w
t h e overhead c a t e n a r y Re 250 between 16 N and 20 N , Re250 RiS120. F; =15kNc125N/rnrn'
which were c l e a r l y below t h e t a r g e t . SNCF Ril5C. ii =20kN:l33N/mm~
R e 2 5 0 V RiSl2O.F: =ZlkN~i75N/mm'.
5. P r e p a r a t i o n s f o r t h e Record Run 250
50
0
200 250 300 350 400 150
running speed v I km/hl 3
Fig. 8: L i f t of t h e c o n t a c t w i r e as a g a i n s t t h e run-
Fig. 6: Pantograph DSA 350, developed f o r high-speed n i n g speed f o r v a r i o u s overhead c a t e n a r y sys-
runs t ems
26
I1 I 1
v being t h e running speed i n m/s and c t h e p r o p a g a t i o n Table 2: Dynamic C h a r a c t e r i s t i c s of Contact L i n e s
v e l o c i t y of t r a n s v e r s e waves i n t h e c o n t a c t wire i n
d s . T h i s v e l o c i t y o f wave p r o p a g a t i o n r e s u l t s from
E E
R e 250 SNCF R e 250
reinforced
c = = i n m/s
C o n t a c t wire CuAgRi 120 C u R i 150 CuAgRi 120
mF being t h e mass per u n i t l e n g t h o f t h e c o n t a c t wire T e n s i l e f o r c e (kN) 15 20 21
i n kg/m, (JF t h e t e n s i l e stress of t h e c o n t a c t w i r e i n
N/mm2 and QF t h e c r o s s - s e c t i o n a l mass p e r u n i t l e n g t h Messenger wire Bz I1 70 Bz I1 65 Bz I1 70
of t h e c o n t a c t wire i n kg/m .
mm'. The v e l o c i t y of
wave p r o p a g a t i o n f o r t h e Re 250 amounts t o 426 km/h.
T e n s i l e f o r c e (kN) 15 14 15
T h i s was a l s o confirmed by tests. V e l o c i t y of wave
p r o p a g a t i o n (km/h) 426 440 504
The r e f l e c t i o n c o e f f i c i e n t Reflection c o e f f i c i e n t 0.433 0.363 0.392
27
I1 I
Doppler coefficient a omplificotion coefficient support no
287-39k 287-611 288 - 5k
I I I
Lo? tensile force 15kN
I / lift position
I 1
-c
neutml position
conloct wire height I m l overlap spon
560 I tensile force 2lkN I l i f t position 1
1 1 1
28
The p a t t e r n of t h e c o n t a c t force r e f l e c t s t h e
motion and t h e a c c e l e r a t i o n s of t h e overhead c a t e n a r y
and t h e pantograph. T h e r e f o r e , t h e c o n t a c t f o r c e is
t h e most i m p o r t a n t v a l u e f o r t h e a s s e s s m e n t of t h e
dynamic behaviour of t h e c a t e n a r y / p a n t o g r a p h system.
A high-speed r e m o t e - c o n t r o l l e d camera was in- Fig. 12: Monitoring the pantograph running with
s t a l l e d on t o p o f t h e measuring car i n o r d e r t o ob- 406 b / h
s e r v e d i r e c t l y t h e r u n of t h e pantograph. The p i c t u r e
is reproduced on a v i d e o s c r e e n ( F i g . 12) and recorded s t r e s s e d by a c o n s i d e r a b l e bending moment. On t h e
on a v i d e o t a p e a t a frame frequency of 200 p i c t u r e s p o i n t of t h e u p p e r arm s t r e s s e d mostly a c c o r d i n g t o
p e r second. The speed and t h e r o u t e i n f o r m a t i o n from c a l c u l a t i o n s of t h e m a n u f a c t u r e r , s t r a i n wire gauges
t h e EDP system are a l s o recorded. F o r t h e a n a l y s i s of were a t t a c h e d for m o n i t o r i n g purposes.
t h e pantograph behaviour t h e tape speed c a n be changed
d u r i n g r e p r o d u c t i o n of t h e p i c t u r e . A t s p e e d s above 330 km/h t h e h i g h aerodynamic
l o a d on t h e p a n t o g r a p h i n f l u e n c e s a l s o t h e v e r t i c a l
6.3 C o n t r o l o f C o n t a c t Force, S t r a i n Measurement on c o n t a c t f o r c e which should n o t exceed 180 N. I n o r d e r
t o keep t h e c o n t a c t f o r c e w i t h i n t h e s p e c i f i e d l i m i t s ,
t h e Pantograph a system f o r a semiautomatic c o n t r o l of t h e f o r c e ' s
mean v a l u e was developed. An e x p e r t e n g i n e e r was re-
A i r f l o w s p e e d s of 450 t o 500 h / h a c t i n g on s p o n s i b l e for t h e comparison of t h e d e s i r e d and t h e
t h e pantograph were expected when e n t e r i n g t h e t u n n e l a c t u a l v a l u e s and t h e c o n t r o l of t h e c o n t a c t f o r c e .
w i t h r u n n i n g s p e e d s of 400 km/h. Computer c a l c u l a - The c o n t a c t f o r c e f o r t h e pantograph DSA 350 is ad-
t i o n s on t h e b a s i s of aerodynamic l o a d s measured on j u s t e d p n e u m a t i c a l l y w i t h a i r bellows. T h e i r p r e s s u r e
t h e pantograph a t a speed of 300 h / h p r e d i c t e d an c o u l d be a d j u s t e d c o n t i n u o u s l y .
i n c r e a s e of t h e aerodynamic l o a d s to a b o u t 3000 N a t
500 W h . S i n c e t h e head of t h e pantograph is exposed 6.4 L i f t of t h e C o n t a c t Wire
t o 40 t o 50 5 of t h e t o t a l l o a d , t h e upper arm is
A s a l r e a d y mentioned under para 5 t h e abso-
l u t e l i f t of t h e c o n t a c t wire c a n become a c r i t i c a l
v a l u e a t h i g h speeds. S i n c e t h e r e is no method t o mea-
s u r e c o n t i n u o u s l y t h i s v a l u e , s t a t i o n a r y d e v i c e s were
developed which s e r v e d t o measure t h e l i f t of t h e con-
t a c t wire on t e n s u p p o r t s .
A s primary e l e m e n t s r e e l - t y p e p o t e n t i o m e t e r s ,
on e a r t h p o t e n t i a l , were a r r a n g e d on t h e p o l e s (Fig.
1 1 3 ) . The p o t e n t i o m e t e r was connected by a p l a s t i c - c l a d
steel w i r e v i a a n a b o u t 1 m l o n g i n s u l a t i n g i n t e r c o n -
29
r I
n e c t i n g p i e c e made of K e v l a r to t h e c o n t a c t wire clamp
on t h e s t e a d y a r m , o v e r a g u i d e p u l l e y n h i c h is f i x e d -
t o t h e c r o s s a m . P r e l i m i n a r y tests confirmed t h a t t h e 200 ~
e x p e c t e d v e r t i c a l a c c e l e r a t i o n s of t h e c o n t a c t wire
were c o r r e c t l y p r o c e s s e d by t h e measuring system. The l o o f
measuring i n s t r u m e n t s were i n s t a l l e d i n cars on t h e
adjacent track.
7. High-speed Runs
7.1 Schedule
30
TT I
n i n g speeds above 380 km/h t h i s l o a d became a c r i t i c a l approaching t h e wave propagation v e l o c i t y i n t h e con-
v a l u e when l e a v i n g t h e t u n n e l s . The f a t i g u e s t r e n g t h t a c t wire, a l s o worked p e r f e c t l y .
was exceeded r e p e a t e d l y and t h e s p e c i f i e d l i m i t i n g
v a l u e of 140 N/mm* was a l m o s t reached a t 400 h / h . The d e s i g n speed of t h e Re 250 c a t e n a r y was
When l e a v i n g a t u n n e l t h e Kind f o r c e s a c t i n g on t h e 250 h / h . Tests c a r r i e d o u t under t h e c a t e n a r y and t h e
upper arm suddenly d e c r e a s e and e x c i t e v i b r a t i o n s of high-speed r u n s demonstrated t h e e f f e c t i v e n e s s of t h e
t h e pantograph, whose f i r s t amplitude c a u s e s high d e s i g n and t h e c o n s i d e r a t i o n s behind it. They proved
bending l o a d s . T h i s v i b r a t i o n , however, r a p i d l y f a d e s t h a t i n r e g u l a r s e r v i c e speeds up t o 300 h / h w i l l n o t
away. c a u s e any r e d u c t i o n s of t h e q u a l i t y of c o n t a c t between
pantograph and overhead c a t e n a r y .
The pantograph was equipped with a i r b a f f l e s
which up t o a speed of 300 h / h allowed f o r a s l i g h t The t e s t s made c l e a r t h e utmost importance of
i n c r e a s e of t h e c o n t a c t f o r c e i n o r d e r t h a t t h e re- t h e t e n s i l e stress i n t h e c o n t a c t wire. I n c r e a s e of
q u i r e d ffiean v a l u e of 120 N is n o t exceeded. t h i s t e n s i l e stress is an e s s e n t i a l pre-condition f o r
t h e f u r t h e r i n c r e a s e of t h e running speed w i t h elec-
During t h e r u n s i t became e v i d e n t t h a t above t r i c t r a c t i o n i n normal s e r v i c e .
330 km/h t h e c o n t a c t f o r c e d i d n o t i n c r e a s e any more
continuously. An e x t r a p o l a t i o n t o 400 km/h r e s u l t e d The p o i n t s of d i s c o n t i n u i t y i n t h e overhead
i n a mean v a l u e of t h e c o n t a c t f o r c e s which exceeded c a t e n a r y : t h e o v e r l a p s , t h e mid p o i n t s and t h e s w i t c h
200 N c o n s i d e r a b l y . T h e r e f o r e , t h e manual c o n t r o l of p o i n t s o f t e n cause peaks of c o n t a c t f o r c e s , which be-
t h e c o n t a c t f o r c e of t h e pantograph appeared t o be t h e come more e v i d e n t a t i n c r e a s e d running speeds. The
remedy w i t h o u t which t h e peak speed would h a r d l y chosen d e s i g n of t h e s e e l e m e n t s , e s p e c i a l l y of t h e
have been achieved. o v e r l a p s , proved i t s worth a l s o a t maximum speeds.
31
1 I
-/-12-7 E. Pfizenmaier, W.F. King and D. Christ, Unter- -/-15-7 K.-H. Bauer, R. Bucksch, F. Lerner, R. Mahrt
suchungen zur aerodynamischen und aeroakusti- and F. Schneider, Dynamische Kriterien fiir die
schen Optimierung eines Stromabnehmers fiir den Auslegung von Fahrleitungen. ZEV-Glasers Anna-
-
ICE. AET, vol. 40, 1985. len, vol. 103, pp. 365-370, 1979.
-/-13-7 J. Daffos and M. Gardou, Les 6tudes rhcentes de -/-16-7 DIN VDE 0115, Part 3, Rail-borne and trackless
antographes 5 la SNCF. Revue Gknhrale des vehicles; Particular requirements for station-
:hemins de Fer, vol. 105, pp. 521-528, 1986. ary installations, June 1982.
-/-14-7 R. Gabler, Aufnahme des Versuchsbetriebs auf -117-7 N.N., Die Regelfahrleitung der Deutschen Bun-
dem Teilabschnitt Burgsinn - tfberleitstelle desbahn. Elektrische Bahnen, vol. 77, pp. 175-
Hohe Wart der Neubaustrecke Hannover - Wiirzburg. 180, pp. 207-208, 1979.
Elektrische Bahnen, vol. 84, pp. 307-312, 1986.
-n 8 - 7 M. Ostermeyer, Ein neues Me& und Auswertekon-
zept fiir Versuche mit Eisenbahnfahrzeugen, vor-
gestellt am ICE. ZEV-Glasers Annalen, vol. 110,
pp. 360-366, 1986.
32
Ii I