Professional Documents
Culture Documents
VOLUME-1
Page-1
Signature of Contractor NBCC DWC LLC
Particular condition of contract
TABLE OF CONTENTS
Page-2
Signature of Contractor NBCC DWC LLC
Particular condition of contract
INSTRUCTIONS TO TENDERER
1.0 Introduction
1.1 The bidder are invited to submit a Technical Bid together with a Financial Bid. The
tender will be the basis for technical discussions/negotiations if required and
ultimately for a signed contract with the selected firm /agency.
1.2 The agency should familiarize themselves with local conditions and take them into
account in preparing their proposals. To obtain first-hand information on the
assignment and local conditions, agency/firm are desired to visit the site before
submitting a bid. Firms/ agency or his authorized representative should contact the
following regarding site specific information and site visit enquiry.
Contact : ………………………………………………………………
Address : ………………………………………………………………
Fascimile : ………………………………………………………………
Mobile : ………………………………………………………………
1.3 (a) NBCC DWC LLC will provide the inputs to the firms/ agency, if available. However,
NBCC DWC LLC does not assume any responsibility for any loss or financial damages
on account of use of such information by agency /firm are advised to collect their
own information for preparation, submission of bids & execution of services after
award of work.
1.3 (b) The agency /firms shall be responsible for obtaining licenses and permits to carry
out the services in Dubai, UAE.
1.4 The agency /firms shall bear all costs associated with the preparation and submission
of their proposals and contract negotiation, site visits etc. NBCC DWC LLC / Client is
not bound to accept any proposal, and reserves the right to annual the selection
process at any time prior to contract award, without thereby incurring any liability to
the firms/ agency.
1.5 Conflict of Interest
1.5.1 NBCC DWC LLC policy requires that agency /firms provides professional, objective,
and impartial advice and at all times hold NBCC DWC LLC’s interests paramount,
strictly avoid conflicts with other assignments or their own corporate interests and
act without any consideration for future work.
Page-3
Signature of Contractor NBCC DWC LLC
Particular condition of contract
1.5.2 (i) Without limitation on the generality of the foregoing, agency/firms, and any of
their affiliates, shall be considered to have a conflict of interest and shall not be
recruited, under any of the circumstances set forth below :
Conflicting of Assignments
(ii) The agency /firm (including its personnel and sub-contractor/firms) or any of its
affiliates shall not be hired for any assignment that, by its nature, may be in conflict
with another assignment of the agency /firm to be executed for the same or for
another employer.
Conflicting Relationship
(iii) agency /firm (including its personnel and sub- contractor/firms) that has a
business or family relationship with a member of NBCC DWC LLC’s staff who is
directly or indirectly involved in any part of (a) the preparation of the Terms of
Reference of the assignment, (b) the selection process for such assignment, or (c)
supervision of the Contract, may not be awarded a Contract, unless the conflict
stemming from this relationship has been resolved in a manner acceptable to NBCC
DWC LLC throughout the selection process and the execution of the contract.
1.5.3 agency /Firms have an obligation to disclose any situation of actual or potential
conflict that impacts their capacity to serve the best interest of NBCC DWC LLC, or
that may reasonably be perceived as having this effect. Failure to disclose said
situations may lead to the disqualification of the firm/ agency or the termination of
its contract any time, throughout currency of the work.
1.5.4 No agency of current employees of NBCC DWC LLC shall work as agency /firms.
Recruiting former employees of NBCC DWC LLC to work is acceptable provided no
conflict of interest exists.
1.6 Fraud and Corruption
1.6.1 NBCC DWC LLC requires that the agency /Firms participating in selection process
adhere to the highest ethical standards, both during the selection process and
throughout the execution of a contract. In pursuance of this policy, NBCC DWC LLC.
a) Defines, for the purpose of this paragraph, the terms set forth below :
Page-4
Signature of Contractor NBCC DWC LLC
Particular condition of contract
b) Will reject a proposal for award if it determines that the agency /Firms
recommended for award has, directly or through an agent, engaged in corrupt,
fraudulent, collusive or coercive practices in competing for the contract in
question; and
c) Will sanction an agency /Firms ineligible, either indefinitely or for a stated period
of time, for award of a contract if at any time determines that the agency /firm
has, directly or through an agent engaged in corrupt, fraudulent, collusive or
coercive practices in competing for, or in executing a contract.
1.7 The agency /Firms should be aware of the provisions on fraud and corruption
stated in the specific clauses in the General Conditions of Contract.
1.8 Only one Proposal
The agency /Firm shall only submit one proposal. If a agency /firm submits or
participates in more than one proposal, such proposals shall be disqualified.
However, this does not limit the participation of the same Sub-Contractor/Firm,
including individual experts, to more than one proposal.
1.9 Proposal Validity
The agency /Firm’s tender must remain valid for 150 days after the last date fixed for
submission of tender including the extension(s) given, if any.
1.10 Association of Sub- Contractor /Firms (for specialized work)
The agency/Firm may associate with sub Contractor /Firm(s) for specialized works.
Later date shall be provided to the eligible bidders on submitting the relevant
supporting documents.
Page-5
Signature of Contractor NBCC DWC LLC
Particular condition of contract
2.2 At any time before the submission of tender, NBCC DWC LLC may modify/amend
the bid document and extend the last date of submission / opening of the tender by
issuing a corrigendum(s)/addendum (s).
Any Corrigendum(s)/Addendum (s) thus issued shall form part of tender document
and shall be posted only on www.eprocure.gov.in and the agency/firms are thus
advised to update their information by using said website. To give the agency /firm
reasonable time to take a n amendment into account in their bids and on account of
any other reasonable circumstances, NBCC DWC LLC may at its discretion, extend the
deadline for the submission/ opening of the tender.
3.0 Preparation of Bid Proposal
3.1 In preparing their tender/ agency /firms are expected to examine in detail the tender
document. The tender shall contain technical & financial bids.
3.2 The bid proposals, all related correspondence exchanged by the agency /Firm &
NBCC DWC LLC and the contract to be signed with the winning agnecy/firm shall be
written in the English language.
3.3 Technical Bid Proposal
a) The technical bid shall not include any financial information. A Technical bid
containing financial information shall be declared non responsive/invalid.
b) The technical bid may be declared non responsive/invalid, if the bid is not
accompanied by the requisite documents as stipulated in tender document.
3.4 Financial Bid Proposal
The financial bid shall not include any commercial or technical condition /
information. Financial offer shall be submitted as per Bid Sheet in Volume-IV of the
tender documents.
4.0 Submission, Receipt and Opening of Bids
4.1 Mode of Submission of Tender :
The tender/bid shall be submitted as under :
Name of Work : “Designing , Supply, Installation, Testing & Commissioning of Fitouts
for Exhibition and curation works including detail design for the Exhibit and curated
spaces for AV works, Exhibit Finishes, MEP works & integration of spaces with the
existing services for India Pavilion at World Expo 2020, Dubai, UAE”.
Envelope / Cover – 1 :
Cost of Tender Document, EMD as per format given in Form E of NIT, Letter of
Acceptance – Annexure – II, Integrity Pact – Annexure – III, Forms A to I, Affidavit
Form – H, Power of Attorney.
Bidders credential/experience certificate for meeting qualifying criteria for
experience, financial eligibility criteria etc. asked in NIT and Tender Document.
Tender Documents consisting of NIT, Vol-I, Vol – III , Vol – IV & Corrigendum if any
issued for this tender.
Page-6
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Envelope/Cover-1, should be clearly marked with tender for “Name of Work” &
“Technical Proposal”.
If tenderer fails to submit any of the above documents their price bid may not be
opened.
Envelope / Cover – 2 :
All pages of Volume – II (BOQ & Bidding sheet) of Tender Documents duly filled and
stamped and signed on each page by authorized representative and Letter of Tender
duly stamped and signed by authorized representative.
All corrections must be signed and stamped by the tenderer. Any condition
mentioned in Cover -2 shall not be taken into account otherwise bid will be rejected.
Envelope/Cover-2, should be clearly marked with tender for “Name of Work” &
“Price Proposal”.
All the tender document should be signed and stamped on each page by the
tenderer. Cutting & overwriting, if any, should be signed & stamped by the person
signing the tender.
Envelope 1 & 2 to be placed in a 3rd Envelope and should clearly marked with tender
for “Name of Work” & name/address of Bidder.
The documents are to be submitted in the office of NBCC DWC – LLC before last date
& time of submission of tender as mentioned in the NIT.
The documents submitted shall be opened at 11.30 am on the same day. The
technical tender documents submitted by intending tenderers/bidders shall be
opened only of those tenderers/bidders, whose earnest money deposit and cost of
tender document and other documents placed in the envelope are found in order.
The date of opening of price tender shall be informed to the tenderer/bidder.
4.2 The original bids (Technical bid and Financial bid) shall contain no interlineations or
overwriting, except as necessary to correct errors made by the agency/firms
themselves. The person who signed tender documents must initial such corrections.
Letter for unconditional acceptance of tender condition should be submitted in the
prescribed format of Annexure-II of NIT.
4.3 An authorized representative of the agency/firm shall sign the Technical & Financial
bids. The authorization shall be in the form of a legally enforceable written power of
attorney executed on non-judicial stamp paper of appropriate value duly notarized
and shall be submitted along with bid.
4.4 NBCC DWC LLC shall open the Technical bid after the deadline for the submission of
original in hard form as per NIT. The financial bid shall remain securely stored.
4.5 The evaluation of bids shall be done as described in NIT.
5.0 Confidentiality
Information relating to evaluation of tenders and recommendations concerning
awards shall not be disclosed to the agency/firm who submitted the tender or to
Page-7
Signature of Contractor NBCC DWC LLC
Particular condition of contract
other persons not officially concerned with the process, until the publication of the
award of contract. The undue use by any agency/firm of confidential information
related to the process may result in the rejection of its tender and may be debarred
from participating in future tenders.
6.0 Earnest Money Deposit:
Earnest Money Deposit of amount as mentioned in “NIT of Tender” required to be
submitted along with the tender shall be in the form of Demand Draft payable at
place as mentioned in NIT in favour of NBCC DWC LLC from any UAE Bank. The Bank
Guarantee towards EMD is also acceptable (in the prescribed format as given) issued
from any UAE Bank. EMD shall be submitted in the prescribed proforma. The EMD
shall be valid for a minimum period of 180 (One Hundred eighty) days from the
original last day of submission of bid as per NIT. The EMD shall be submitted along
with tender documents within the period of bid submission and original should be
deposited in office of NBCC DWC LLC.
Page-8
Signature of Contractor NBCC DWC LLC
Particular condition of contract
ii) The tenderer/bidder does not submit all the documents (including VAT
registration) as stipulated in the tender document.
8.0 The tenders shall be strictly as per the conditions of contract. Tenders with any
additional condition(s)/modifications shall be rejected.
9.0 On acceptance of tender, the name of the accredited representative(s) of the
contractor who would be responsible for taking instructions from Engineer-in-
Charge/Employer’s Representative or its authorized representative shall be
intimated by the contractor within 07 days of issue date of letter of Awards by
NBCC DWC LLC.
10.0 The tender award, execution and completion of work shall be governed by tender
documents consisting of (but not limited to) Letter of Award/Letter of work
order, Special Conditions of Contract, General Conditions of Contract,
Specifications, Drawings. The tenderers/bidders shall be deemed to have gone
through the various conditions including W i n d l o a d , sub-soil water
conditions, topography of the land, drainage and accessibility etc. or any other
condition which in the opinion of contractor will affect his price/rates before
quoting their rates. No claim whatsoever against the foregoing shall be entertained.
11.0 The drawings with the tender documents are Tender Drawing and are indicative
only. Tenderers/ Bidders are requested to submit shop drawings for approval
before execution.
12.0 Addenda/Corrigenda to the tender documents may be issued prior to the date of
submission of the tender to clarify or effect modification in specification
and/or contract terms included in various tender documents. The tenderer/bidder
shall suitably take into consideration such Addenda/Corrigenda while
submitting his tender. The tenderer/bidder shall return such Addenda/
Corrigenda duly signed and stamped as confirmation of its receipt &
acceptance and submit along with the tender document. All addenda/
Corrigenda shall be signed and stamped on each page by the tenderer/bidder and
shall become part of the tender and contract documents.
13.0 SITE VISIT AND COLLECTING LOCAL INFORMATION: Before tendering, the
tenderers/bidders are advised to visit the site, its surroundings to assess and
satisfy themselves about the local conditions such as the working and other
constraints at site, approach roads to the site, availability of water & power
supply, application of taxes, duties and levies as applicable & any other relevant
information required by them to execute complete scope of work. The
Page-9
Signature of Contractor NBCC DWC LLC
Particular condition of contract
The Contractor should note that area for construction may be made available in
phases as per availability and in conjunction with pace of actual progress of work at
site. The work may be required to be carried out in constrained situations. The work
is to be carried out in such a way that the traffic, people movement, if any, is kept
operative and nothing extra shall be payable to the contractor due to this phasing /
sequencing of the work. The contractor is required to arrange the resources to
complete the entire project within total stipulated time. Traffic diversion, if
required, is to be done and maintained as per requirement of local traffic police
or/and as per specification, by the contractor at his own cost and the contractor
shall not be entitled for any extra payment, whatsoever, in this regard.
The efforts will be made by the NBCC DWC LLC to handover the site to the
Contractor free of encumbrances. However, in case of any delay in handing over of
the site to the Contractor, the NBCC DWC LLC shall only consider suitable extension
of time for the execution of the work. It should be clearly understood that the NBCC
DWC LLC shall not consider any revision in contract price or any other
compensation whatsoever viz. towards idleness of Contractor's labour, equipment
etc.
15.0 The contractor shall be responsible to obtain necessary approval from the
respective authorities. NBCC DWC LLC shall only assist the contractor for liasoning
in obtaining the approval from the concerned authorities.
16.0 The contractor will arrange 2 BHK fully furnished guest house with attendant &
cook for use of NBCC/Client for a period of 6 months from the issue of LOA as per
location/ Type decided by NBCC DWC LLC.
17.0 Any services affected by the works must be temporarily supported by the
contractor who must also take all measures reasonably required by the various
bodies to protect their services and property during the progress of works. It shall
be deemed to be the part of the contract and no extra payment shall be made to
the contractor for the same.
18.0 The scope of work covered in this tender shall be as per the Bill of Quantities, DBR,
Technical Specifications, Tender Drawings, instructions, orders issued to the
contractor from time to time during the pendency of work. The drawings for this
work, which may be referred for tendering, provide general idea only about the
work to be performed under the scope of this contract. These may not be the
final drawings and may not indicate the full range of the work under the scope of
this contract. The work will be executed according to the drawings to be
released as "GOOD FOR CONSTRUCTION" by the Contractor after duly approved by
Page-10
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-11
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works,
Exhibit Finishes, MEP works & integration of spaces with the existing services for India
Pavilion at World Expo 2020, Dubai, UAE
ANNEX 1 - PRESCRIBED FORM FOR TENDER SECURITY
In consideration of NBCC DWC LLC, having its Registered Office at NBCC DWC LLC, P.O. Box-
27661, Building A3, Office-425, Business Park, Dubai World Central, Dubai-UAE (hereinafter
called "NBCC DWC LLC" which expression shall unless repugnant to the subject or
context include its successors and assigns) having issued Notice Inviting Tender
No.......... and M/s............... having its Registered Head Office at.......... (hereinafter
called the "TENDERER") is to participate in the said tender for............. Whereas NBCC DWC
LLC, as a special case, has agreed to accept an irrevocable and unconditional Tender Bond
Guarantee for an amount of Rs....... valid upto........ from the tenderer in lieu of Cash
Deposit of Rs......... required to be made by the tenderer, as a condition precedent for
participation in the said tender. We the.........(hereinafter called the "BANK") having its
Registered, Office at......... and branch office at...... do hereby, unconditionally and
irrevocably undertake to pay to NBCC DWC LLC on demand in writing and without
demur/protest any amount but not exceeding Rs.......... Any such demand made by NBCC
DWC LLC shall be conclusive and binding on us irrespective of any dispute or differences
that may be raised by the tenderer. Any change in the constitution of the tenderer or the
Bank shall not discharge our liability under the guarantee.
We, the....... Bank, lastly undertake not to revoke this guarantee during its currency
without the prior consent of NBCC DWC LLC in writing and this guarantee shall remain valid
upto.......... upon expiry of which, we shall be relieved of our liability under this guarantee
thereafter.
DATED :
WITNESS.
1.
2.
Page-12
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works,
Exhibit Finishes, MEP works & integration of spaces with the existing services for India
Pavilion at World Expo 2020, Dubai, UAE
LETTER OF TENDER
The General Manager
NBCC DWC LLC
P.O. Box-27661, Building A3, Office-425, Business Park, Dubai World Central, Dubai-UAE.
Madam/Sir
We have examined this Letter of Tender including the Appendix to Tender, Instructions to
Tenderers, Conditions of Contract, Particular Conditions of Contract, DBR, Technical
Specifications, Bill of Quantities, Drawings and, if any, addenda for the execution of the
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works,
Exhibit Finishes, MEP works & integration of spaces with the existing services for India
Pavilion at World Expo 2020, Dubai, UAE (“Works”). We offer to execute and complete the
Works and remedy any defects therein in conformity with this Tender, which includes all
these documents, for the sum of
AED………………………..……………………………………………………………………………………………………………
…………………………………………….. (AED …………………………) or such other sums as may be
ascertained in accordance with the Conditions of Contract.
We agree to abide by this Tender for the period of 150 days from the date of opening of
Price Bid and it shall remain binding upon us and may be accepted at any time before that
date. We acknowledge that the Appendix to Tender forms part of this Letter of Tender.
If this offer is accepted, we will provide the specified Performance Security, commence the
Works immediately after the Commencement Date, and complete the Works in accordance
with the above-named documents within the Time for Completion.
We understand that you are not bound to accept the lowest or any tender you may
receive.
Unless and until a formal Agreement is prepared and executed this Letter of Tender,
together with your written acceptance thereof, shall constitute a binding contract between
us.
Signature ................................................... in the capacity of .........................................
duly authorized to sign tenders for and behalf of
…………................................................................
Address ..........................................................................................................................
..........................................................................................................................
Date .........................................................
Page-13
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works,
Exhibit Finishes, MEP works & integration of spaces with the existing services for India
Pavilion at World Expo 2020, Dubai, UAE
CONTRACT AGREEMENT
And
…………..……………………………….of …………………..……………………….…….. .(hereinafter called “the
Contractor”) of the other part
Whereas the Employer desires that the Works known as Designing, Supply, Installation,
Testing & Commissioning of Fitouts for Exhibition and curation works including detail
design for the Exhibit and curated spaces for AV works, Exhibit Finishes, MEP works &
integration of spaces with the existing services for India Pavilion at World Expo 2020,
Dubai, UAE should be executed by the Contractor, and has accepted a Tender by the
Contractor for the execution and completion of these Works and the remedying of any
defects therein.
The Employer and the Contractor agree as follows:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and be read and construed as part
of the Agreement:
(a) The Letter of Acceptance dated ………………….
(b) The Letter of Tender of ………………….. including the Appendix to Tender.
(c) The Addenda nos. ………………….
(d) The Particular Conditions of Contract (Vol – 1).
The General Conditions i.e FIDIC Conditions of Contract for Construction of Building
and Engineering Works Designed by the Employer (i.e Red Book), First Edition 1999
with Errata to the First Edition 1999, published by FIDIC (Federation International des
Ingenieur –Conseils). (Vol-2).
(e) Design Basis Report, Perspective view, layouts and Technical Specifications. (Vol
– 3).
(f) Bill of Quantities. (Vol-4).
(g) Quoting Sheet.
(h) The Performance Security Guarantees and Warrantees.
Page-14
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Design, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works,
Exhibit Finishes, MEP works for the integration of spaces with the existing services for
India Pavilion at World Expo 2020, Dubai, UAE
CONTRACT AGREEMENT
4. The Employer hereby agrees to pay the Contractor, in consideration of the execution
and completion of the Works and the remedying of defects therein, the Contract
Price at the times and in the manner set forth and prescribed by the Contract.
In Witness whereof the parties hereto have caused this Agreement to be executed the day
and year first before written in accordance with their respective laws. ………………………
Page-15
Signature of Contractor NBCC DWC LLC
Particular condition of contract
CONDITIONS OF CONTRACT
The Conditions of Contract governs the rights and obligations of the parties to the Contract.
The Conditions of Contract comprises of:
(a) The General Conditions, which are in the Conditions of Contract for Construction of
Building and Engineering Works Designed by the Employer, First Edition 1999 with
Errata to the First Edition 1999, published by FIDIC (Federation International des
Ingenieur –Conseils)
FIDIC Bookshop
Box 311-CH-1215 Geneva 15
Switzerland
Tel: +41-22-799 49 05
Fax: +41-22-799 49 01
Email: fidic.pub@fidic.org
Website: FIDIC.org/bookshop
(b) The Particular Conditions, which are amendments and additions to the General
Conditions.
The clause numbers in the Particular Conditions refer to the equivalent clauses in
the General Conditions.
The headings and marginal notes in the Particular Conditions below shall not be
deemed part thereof or be taken into consideration in the interpretation or
construction thereof or of the Contract.
(d) Any documents incorporated by reference in the General Conditions and the
Particular Conditions
Page-16
Signature of Contractor NBCC DWC LLC
Particular condition of contract
PARTICULAR CONDITIONS
1. General Provisions
1.1 Definitions
1.1.5.8 Works and Goods Add after the words “as appropriate” the following:
1.1.6.7 Other Definitions Add at the end of this Sub-Clause the following
paragraph:
1.5 Priority of Documents Delete all the words under this Sub-Clause and insert
the following:
Page-17
Signature of Contractor NBCC DWC LLC
Particular condition of contract
1.6 Contract Agreement Delete in line 5 the last word “Employer” and insert:
“Contractor”
1.9 Delayed Drawings or Delete the entire paragraph and insert “The Final
Instructions Detailed Design of Fitouts work is in the scope of the
Contractor as per requirement of Expo authorities.
Before submitting the final Design to the Expo
authorities, the contractor shall submit the final design
to the Employer’s representative/Engineer-in-charge
for approval by him and the Employer’s Consultant.
Page-18
Signature of Contractor NBCC DWC LLC
Particular condition of contract
1.10 Employer’s Use of Add at the end of this Sub-Clause the following
Contractor’s Documents paragraph:
1.12 Confidential Details Add at the end of this Sub-Clause the following
paragraph:
“The Contractor shall treat all the details of the
Contract as private and confidential, save in so far as
may be necessary for the purpose thereof, and shall
not publish or disclose the same or any particulars
thereof in any trade or technical paper or elsewhere
without the previous consent in writing of the
Employer/Employer’s representative. If any dispute
arises as to the necessity of any publication or
disclosure for the purpose of the Contract the same
shall be referred to the Employer/Employer’s
representative whose decision shall be final, binding
and conclusive on the Contractor.
The Contractor shall disclose all such confidential and
other information as the Employer/Employer’s
representative may reasonably require in order to
verify the Contractor’s compliance with the Contract.”
1.13 Compliance with Laws Add at the end of this Sub-Clause the following
paragraph:
2. The Employer
2.1 Right of Access to the Delete at the end of sub-paragraph (a) the words “,
Site and” and insert “.”
Page-19
Signature of Contractor NBCC DWC LLC
Particular condition of contract
2.2 Permits, Licenses or Delete all the content in sub para (a) entirely and Add
Approvals
“The Contractor shall obtain the Fitout Permit,
approval of the Design for the Fitout works and
related detailed design for the Fitout works for the AV
Equipments & AV works any other approval that may
be required for completing the awarded work
successfully.”
3.3 Instructions of the Add at line 3 after the word “Contract.” the following:
Engineer
“Engineer means the Engineer of Employer. Unless
otherwise instructed by the Engineer, the Contractor
shall execute and complete the Works using only
drawings marked ‘Good for Construction Drawings’ or
‘For Construction’ or instructions issued by the
Engineer.
Page-20
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.1 Contractor’s General Add after the fourth paragraph the following:
Obligations
“The Contractor to undertake/prepare Final Detailed
Design as per Requirements of Technical
Specifications, DBR, Perspective views etc given with
the tender documents and submit to the Expo
Authority for obtaining Exhibit design approval and
building/Fitout permit for starting the work at site.
Whenever the Contractor is required to submit to the
Engineer proposals, details, drawings, calculations,
information, literature, materials, test report and
certificates, the Engineer shall consider each
submission and, if appropriate, shall reply to the
Contractor in accordance with relevant provisions of
the Contract. Unless a defined period of time is stated
in the Contract, each submission shall be made by the
dates to be agreed with the Engineer having regard to
Page-21
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.2 Performance Security “The Contractor shall obtain (at his cost) and deliver to
the Employer, Performance security @ 3% of the
Accepted Contract Amount, in AED, within 21 days of
Contractor’s receipt of Letter of Acceptance”.
Page-24
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-26
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.7 Setting Out Add at line 2 after the first sentence the following:
4.11 Sufficiency of the Delete in sub-paragraph (b) after [Site Data] the words
Accepted Contract “.” and insert “, and”
Amount
Add the following sub-paragraph:
4.12 Unforeseeable Physical Delete in second paragraph, line 2 the words “as soon
Conditions as practicable” and insert “within 7 days”
Delete the sentence in para 3 in line 5 after “give.”
Page-29
Signature of Contractor NBCC DWC LLC
Particular condition of contract
And add”.”
Delete paragraph 4,5,6 & 7 entirely.
4.13 Rights of Way and Add in line 1 after the word “shall” the words “be
Facilities responsible, arrange and”.
4.15 Access Route Add in the first paragraph, line 3 after the word
“bridge” the words “or existing structures.”
“(d) The Contractor shall bear all the taxes and charges
such as Import duty, VAT etc for bringing the Goods
meant for successful completion of work/project at
Site or any other statutory fee required to be paid for
transport of Goods and no extra charge shall be
payable by the Employer in this regard”
4.18 Protection of the Add at the end of this Sub-Clause the following
Environment paragraphs:
Page-30
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.19 Electricity, water and Gas Delete this clause entirely and add:
“The Contractor shall be responsible for the provision
of all Power, water & Gas and other services he may
require for the execution of work and site
management. Any Coordination required to be done
with the main contractor for obtaining Electricity,
Water and Gas has to be done by the Fitout
Contractor.
Page-31
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.21 Progress Reports Delete all the word “monthly” in this Sub-Clause and
insert “Weekly”.
Page-32
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.23 Contractor’s Operations Add the following paragraph after the second
on Site paragraph:
4.26 Reinstatement and Add under this new Sub-Clause the following:
Compensation for
Damages to Existing “The Contractor shall, at his own cost, reinstate all
Persons and/or Property properties and site conditions whether public or
private, which are disturbed and/or damaged in
consequence of the construction and maintenance of
the Works by the Contractor or his Subcontractors, to
a condition at least equal to that existing before his
first entry on them. The Contractor shall not wait for
the completion of the project to re-instate but shall do
so whenever it is possible or required by the Engineer.
4.27 Protection of Existing Add under this new Sub-Clause the following:
Works and Services
“The Contractor shall acquaint himself with the
position of all existing services inside and outside the
Project, such as surface water drains, cables for
electricity and telephone, telephone and lighting
poles, water mains, and the like before commencing
any work likely to affect the existing services.
Page-34
Signature of Contractor NBCC DWC LLC
Particular condition of contract
4.28 Diversion of Existing Add under this new Sub-Clause the following:
Services
“The Contractor shall be responsible for making
arrangements for the moving of or alterations to
existing MEP services which may be affected by the
Works. The arrangements for such moving or
alteration shall be subject to the agreement of the
Engineer.
4.29 Protection of Beacons Add under this new Sub-Clause the following:
6.1 Engagement of Staff and Add at after completion of para, the following:
Labour
“The contractor shall follow all the rules and
regulations as laid down by concern Dubai authorities
for the Engagement of staff and labour and follow all
health and safety Guidelines issued time to time by
them.” In case any financial liability occurred on
principle employer due to default / contravention of
any regulations / applicable in Dubai in relation to staff
and labour, same will be recovered from the
contractor.”
Page-35
Signature of Contractor NBCC DWC LLC
Particular condition of contract
6.6 Facilities for Staff and Delete in first paragraph, line 1 and 4 the word
Labour “Specification” and insert “Contract”.
Page-36
Signature of Contractor NBCC DWC LLC
Particular condition of contract
6.10 Records of Contractor’s Delete in line 3, the words “calendar month” and
Personnel and insert “calendar fortnight”
Equipment
6.12 Foreign Contractor’s Add under this new Sub-Clause the following:
Personnel, Burial and
Repatriation “The Contractor may import any foreign Contractor’s
Personnel who are necessary for the execution of the
Works. The Contractor shall be fully responsible for
the imported foreign Contractor’s Personnel and:
Page-37
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-38
Signature of Contractor NBCC DWC LLC
Particular condition of contract
6.14 Records of Safety and Add under this new Sub-Clause the following:
Health
“The Contractor shall maintain such records and make
such records concerning safety, health and welfare of
persons and damage to property as per the health and
Safety guidelines of the Expo and other Dubai
authorities. All such records shall be made available to
the Employer Representative.”
6.15 Reporting of Incidents & Add under this new Sub-Clause the following:
Accidents
“The Contractor shall report to the Employer
Representative details of any incident and accident
immediately after its occurrence. In the case of any
fatality or serious accident, the Contractor shall, in
addition, notify the Employer Representative
immediately by the quickest available means and shall
make all required arrangements for the treatment of
the injured worker.”
6.17 Alcoholic Liquor or Drugs Add under this new Sub-Clause the following:
Page-39
Signature of Contractor NBCC DWC LLC
Particular condition of contract
6.18 Arms and Ammunition Add under this new Sub-Clause the following:
6.19 Festivals and Religious Add under this new Sub-Clause the following:
Customs
“The Contractor shall in all dealings with labour in his
employment have due regard to all recognized
festivals, days of rest as published yearly by the local
authority.
6.20 Observance by Sub Add under this new Sub-Clause the following:
contractors
“The Contractor shall be responsible for the
observance of all the provisions under this Clause 6 by
any Subcontractors/Specialized agency employed by
him in the execution of the Contract.”
Page-40
Signature of Contractor NBCC DWC LLC
Particular condition of contract
done.”
7.4 Testing Add at the end of the first paragraph the following
paragraph:
7.6 Remedial Work Add at the end of this Sub-Clause the following
paragraph:
7.9 Quality of Goods, and Add under this new Sub-Clause the following:
Ownership of Materials
Found on Site “The Contractor shall guarantee the strength and
quality of all Goods supplied by him and all
workmanship and he shall not be relieved of any of his
obligations with respect to the sufficiency of the
Goods and Works by reason of no objection having
been received from the Engineer or Employer’s
Personnel although the same may have been
inspected by them in regular course. The Contractor
shall furnish all information as to the quality, weight,
Page-41
Signature of Contractor NBCC DWC LLC
Particular condition of contract
7.10 Procurement of Goods Add under this new Sub-Clause the following:
8.3 Programme Delete in first paragraph, line 1 “28” and insert “7”.
extension of time.
8.4 Extension of Time for Delete this sub-clause entirely and Add the following
Completion
“The Contractor shall be entitled subject to Sub-Clause
20.1 [Contractor’s Claims] to an extension of the Time
for Completion if and to the extent as given by Expo
authorities to the Employer and subject to the
approval by the client of the Employer.
Page-44
Signature of Contractor NBCC DWC LLC
Particular condition of contract
paragraphs:
9.4 Failure to Pass Tests on Delete in the last Paragraph in line 4 of this sub-
Completion clause all the words “failure.” And Add “The
calculation of amount to be reduced/deducted from
the Contract Price in regard to this sub-clause shall
be solely calculated by the Employer’s
Representative and shall be acceptable to the
Contractor”
Page-45
Signature of Contractor NBCC DWC LLC
Particular condition of contract
10.1 Taking Over of the Works Add in the first paragraph, in line 4 after the words
and Sections “[Time for Completion]” the following:
10.3 Interference with Tests Replace “14 days” in line 1 by “30 days”.
on Completion
Delete at the end of sub-paragraph (a) the words “,
and” and insert “.”
11.1 Completion of Add under sub-paragraph (a) in line 2 after the words
Outstanding Work and “the Engineer” the words “or within the time set in
Remedying Defects any schedule attached with the Taking- Over
Page-46
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Certificate”
11.3 Extension of Defects Add in the second paragraph, line 2 after the words
Notification Period “[Suspension of Work]” the words “for a cause which
the Contractor was not responsible”.
12.3 Evaluation Add in the second paragraph after the first sentence
the following:
Page-47
Signature of Contractor NBCC DWC LLC
Particular condition of contract
client”
13.7 Adjustments for Changes Delete all the words under this Sub-Clause and insert:
in Legislation
“The Contract Price shall not be adjusted for any
subsequent changes in legislation or introduction of
new laws / legislation. Any rise or fall (as a result of
change in VAT) in input VAT not creditable under or by
virtue of the Value Added Tax Act of Dubai or any
amendment to the Act thereof shall also not be
entertained.
The Contract Price shall not be adjusted for any rise or
fall in the cost of labour, materials, fuel and any other
input to the Works that are subject to the control of
the Government, the National Remuneration Board,
the Ministry of Commerce & Industries, or any
Authorities by way of Legislation and Regulations.”
13.8 Adjustments for changes Delete all the words under this Sub-Clause and insert:
in cost
“No claim on account of any escalation on whatsoever
ground shall be entertained at any stage of works. All
rates as per Bill of Quantities quoted by contractor
shall be firm and fixed for entire contract period as
well as extended period for completion of the works.
No escalation shall be applicable on this Contract.”
14.1 The Contract Price Add All rates as per Bill of Quantities quoted by
contractor shall be firm and fixed for entire contract
period as well as extended period for completion of
the works. No escalation shall be applicable on this
Contract.
Page-48
Signature of Contractor NBCC DWC LLC
Particular condition of contract
14.2 Advance Payment Delete all the words under this Sub-Clause and insert
the following:
Page-49
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Tender.
14.3 Application for Interim Add at line 5 after the words “[Progress Reports]”, the
Payment Certificates following:
Page-52
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-53
Signature of Contractor NBCC DWC LLC
Particular condition of contract
14.5 Plant and Materials Delete all the words under this Sub-Clause and insert:
intended for the Works
“Unfixed Plant and Materials shall be payable to the
Contractor if all the following conditions are to the
satisfaction of the Engineer:
14.6 Issue of Interim Payment Add after the first paragraph, a new paragraph as
Certificates follows:
14.7 Payment Delete the whole of the last paragraph and insert “In
case payment is made directly into the Contractor’s
bank account in Dubai, all bank charges shall be for
the account of the Contractor.”
Page-55
Signature of Contractor NBCC DWC LLC
Particular condition of contract
or”.
18. Insurance
18.1 General Requirements Delete in the sixth paragraph, line 2 the words
for Insurances “(calculated from the Commencement Date)”.
Page-57
Signature of Contractor NBCC DWC LLC
Particular condition of contract
18.2 Insurance for Works and Add at the end of first paragraph, after the words
Contractor’s Equipment “Works.” the following:
19.1 Definition of Force Add in Sub-Clause 19.1 (v) after the word “volcanic
Majeure activity” the words “or cyclone warning class 3 (or
above) or Tsunami, pandemic”.
20.9 Engineer’s Decision Add under this new Sub-Clause the following:
20.10 Amicable Settlement Add under this new Sub-Clause the following:
20.12 Failure to Comply with Add under this new Sub- Clause the following:
Engineer’s Decision
In the event that:
“If applicable,
Page-62
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-65
Signature of Contractor NBCC DWC LLC
Particular condition of contract
29 Protection of public and Add under this new Clause the following:
private properties
“The Contractor shall protect, uphold and maintain all
existing public and private roads, live drainage and
services (water, power and telephone), streams,
canals and sea, whether on or off the Site, during the
execution of the Works.
30 Keeping Public and Add under this new Clause the following:
Private Roads Clean
“The Contractor shall keep the public roads, private
roads, parking and driveways used by him clear of all
mud, materials, rubbish, debris and the like.”
Page-66
Signature of Contractor NBCC DWC LLC
Particular condition of contract
32 Pumping and Dewatering Add under this new Clause the following:
33 Borrow Pits and Dump Add under this new Clause the following:
Areas
“The Contractor shall provide for all necessary
pumping and dewatering and for keeping all
excavations, the Site and the Works free from surface
water and underground water.”
Page-67
Signature of Contractor NBCC DWC LLC
Particular condition of contract
(c) Plant and Materials that are being shipped e.g. bill
of lading, Notice of Arrival and
38 Request for Information Add under this new Clause the following:
Schedule
“The Contractor shall within 7 days after receiving the
notice under Sub-Clause 8.1 submit to the Engineer a
list (RFI Schedule) showing all the information,
approvals, consents, instructions, nominations and
Employer’s supply Materials and Plant he requires and
the dates he requires them, to execute and complete
the Works without any delays, disruption and
Page-68
Signature of Contractor NBCC DWC LLC
Particular condition of contract
additional cost.
39 Meetings & Site Visits Add under this new Clause the following:
42 Rates and Prices in Bill of Add under this new Clause the following:
Quantities
Page-69
Signature of Contractor NBCC DWC LLC
Particular condition of contract
(c) Levy;
Page-70
Signature of Contractor NBCC DWC LLC
Particular condition of contract
(o) Permits;
Page-71
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Page-73
Signature of Contractor NBCC DWC LLC
Particular condition of contract
50 Cost for Complying with Add under this new Clause the following:
Conditions of Contract
“Unless otherwise stated, the Cost for complying with
all the conditions in the General Conditions and
Particular Conditions shall be deemed to be included
in the Contractor’s prices and rates, Accepted Contract
Amount and Contract Price.”
51 Checks for Mild Steel / Add under this new Clause the following:
Aluminium Works
“The Mild Steel/ Aluminium works including works of
bolting and welding should be as per the
corresponding codes such as ASTM standards
mentioned in Technical Specifications.
Page-75
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works, Exhibit
Finishes, MEP works & integration of spaces with the existing services for India Pavilion at
World Expo 2020, Dubai, UAE
ANNEX A - PRESCRIBED FORM FOR PERFORMANCE SECURITY
Project - Supplying, Installation, Testing & Commissioning of Audio Video works for Indian
Pavilion for World Expo 2020, Dubai, UAE
Madam/Sir
And Whereas the Contract requires the Contractor to obtain and submit to you a bank guarantee
for the sum specified in the Contract as security for compliance with his obligations under the
Contract;
And Whereas at the request of the Contractor, we, [name of Bank] ………………………………………
whose registered office is at …………………………………………………… have agreed to give you such a
bank guarantee.
By this guarantee, we hereby irrevocably undertake to pay you any sum or sums not exceeding in
total the amount of AED …………………………. (the “Guaranteed Amount”) upon receipt by us of
your first demand in writing and your written statement stating:
(a) that the Contractor is in breach of his obligation(s) under the Contract, and
Following our receipt of an authenticated copy of the Taking-Over Certificate for the whole of
the Works under clause 10 of the Conditions of Contract , such Guaranteed Amount shall be
reduced by 50% and we shall promptly notify you in writing that we have received such
certificate and have reduced the Guaranteed Amount accordingly.
Page-76
Signature of Contractor NBCC DWC LLC
Particular condition of contract
We have been informed that, in accordance with the Contract, the Contractor shall be required
to extend the validity period of this guarantee, if the Performance Certificate under the Contract
has not been issued by the date 56 days prior to the Expiry Date of this guarantee. We hereby
irrevocably undertake to pay you such Guaranteed Amount upon our receipt, within such period
of 56 days, of your first demand in writing and your written statement stating that the
Performance Certificate has not been issued and that this guarantee has not been extended as
required.
We agree that our obligations and liabilities shall not be discharged by any allowance of time or
other indulgence whatsoever on your part to the Contractor, or by any variation or suspension of
the works to be executed under the Contract, or by any amendments to the Contract or to yours
and the Contractor’s constitution, or by any other matters, whether with or without our
knowledge or consent.
Any demand for payment must contain your signature(s) which must be authenticated by your
bankers or by a notary public. The authenticated demand and statement must be received by us
at this office on or before [the date 91 days after the expected expiry of the Defects Notification
Period for the Works] …………………………….. (the ‘’Expiry Date’’ of this guarantee).
Payment under this guarantee shall only be made upon presentation of this original guarantee.
This guarantee shall inure to the benefit of your successors and assigns.
The validity of this guarantee automatically expires on …………………………. by the time of the
closure of banking business to the general public.
This guarantee shall be governed and construed in accordance with the laws of Dubai.
[Both bank guarantor and Contractor are to sign this guarantee and to insert below in their own
handwriting “Good for the sum of AED ……………………”]
…………………………………………………………………………………………
…………………………………………………………………………………………
Signature: ……………………………..
Seal: …………………………………..
Date: ………………………………….
Page-77
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and curation
works including detail design for the Exhibit and curated spaces for AV works, Exhibit Finishes,
MEP works & integration of spaces with the existing services for India Pavilion at World Expo
2020, Dubai, UAE
ANNEX B - PRESCRIBED FORM FOR ADVANCE PAYMENT GUARANTEE
Madam/Sir,
By this guarantee, we hereby irrevocably undertake to pay you any sum or sums not exceeding in
total the amount of AED …………………………. (the “Guaranteed Amount”) upon receipt by us of
your first demand in writing and your written statement stating:
(a) that the Contractor has not repaid you the advance payment in accordance with the
Contract, and
(b) the amount of the advance payment which the Contractor has not repaid you.
We have been informed that, in accordance with the Contract, the Contractor may be required
to extend the validity period of this guarantee if the advance payment has not been repaid to
you by the date 56 days prior to the Expiry Date of this guarantee. We hereby irrevocably
undertake to pay you the amount of the advance payment which the Contractor has not repaid
you upon our receipt, within such period of 56 days, of your authenticated first demand in
writing and your written statement stating that the advance payment has not been repaid to you
by the Contractor, the amount which the Contractor has not repaid you and that this guarantee
has not been extended as required.
Page-78
Signature of Contractor NBCC DWC LLC
Particular condition of contract
We agree that our obligations and liabilities shall not be discharged by any allowance of time or
other indulgence whatsoever on your part to the Contractor, or by any variation or suspension of
the works to be executed under the Contract, or by any amendments to the Contract or to yours
and the Contractor’s constitution, or by any other matters, whether with or without our
knowledge or consent.
This guarantee shall become effective upon the Contractor’s receipt of the advance payment and
such Guaranteed Amount shall be reduced by the amounts of the advance payment the
Contractor repaid to you.
Any demand for payment must contain your signature(s) which must be authenticated by your
bankers or by a notary public. The authenticated demand and statement must be received by us
at this office on or before [the Time for Completion] ……………………………………. (the “Expiry Date”
of this guarantee).
Payment under this guarantee shall only be made upon presentation of this original guarantee.
This guarantee shall inure to the benefit of your successors and assigns.
The validity of this guarantee automatically expires on ……………………………. by the time of the
closure of banking business to the general public.
This guarantee shall be governed and construed in accordance with the laws of Dubai.
[Bank guarantor is to sign this guarantee and to insert below in their own handwriting “Good
for the sum of AED ……………………………………………” ]
…………………………………………………………………………………………………
…………………………………………………………………………………………………
Date: ………………………………….
Page-79
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Project: Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and
curation works including detail design for the Exhibit and curated spaces for AV works, Exhibit
Finishes, MEP works & integration of spaces with the existing services for India Pavilion at
World Expo 2020, Dubai, UAE
I hereby cede, transfer and assign all the Cedent’s right, title and interest in and to the materials
and goods described in the attached List of Unfixed Materials unto and in favour of the
Employer, NBCC DWC LLC (hereinafter referred to as the “Cessionary”).
This cession shall become effective as soon as the Cedent receives payment for the materials and
goods from the Cessionary or from any other person on behalf of the Cessionary.
I certify that these materials are adequately stored and protected against weather and other
casualties, are covered by proper insurances, have been supplied without any suspensive
condition and are the Cedent’s bona fide property, ownership of which has passed to the Cedent
according to Law.
(In the event of the signatory hereto not being the proprietor or in the case of a Company a
director thereof, a valid Resolution of the Board of Directors of the Cedent is to be attached
hereto.)
Cedent: Witness:
Seal: ……………………………….......
Page-80
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and curation
works including detail design for the Exhibit and curated spaces for AV works, Exhibit Finishes,
MEP works & integration of spaces with the existing services for India Pavilion at World Expo
2020, Dubai, UAE
Signature……………………………………….…………...…………….………….……………….…
.………………….…………………………………………………………...………………………….
Address………………………………………………………………………………………………….
………………….…………………………………………………………...…………………………..
Witness ……………………….…………...…………...…….…………………………………………
………………….…………………………………………………………...................………………..
Designing, Supply, Installation, Testing & Commissioning of Fitouts for Exhibition and curation
works including detail design for the Exhibit and curated spaces for AV works, Exhibit Finishes,
MEP works & integration of spaces with the existing services for India Pavilion at World Expo
2020, Dubai, UAE
NBCC DWC LLC a company incorporated under the laws of Dubai and having its registered office
at NBCC DWC LLC P.O. Box-27661, Building A3, Office-425, Business Park, Dubai World Central,
Dubai-UAE duly represented for the present purpose by ……………………………………………(hereinafter
referred to as “the Employer”) and…..………………. a company incorporated under the laws of
................................... with business registration number ……………………….. and having its
registered office at …………………………………., duly represented for the present purpose by
………………………………………………(hereinafter referred to as “the Contractor”)
1. THE BASIS
1.1 The Contractor has been invited to submit an offer for the carrying out the design,
manufacture, supply and fix ……………………………………………………. for
……………………………………………………………. as more fully specified and defined in the
Contract hereafter referred to and which specification and definition are deemed to be
incorporated herein (hereinafter referred to as “the Contract works”) pursuant to the
terms of the Contract entered into by the Employer and the Contractor on
…………………………………………………………………………………………
2.1 This agreement shall come into force and be binding upon the Employer and the
Contractor only if and when the aforementioned Contract between the Employer and
the Contractor is concluded and signed, and until then it shall be of no force or effect.
2.2 As the responsibility for the design of the Contract and the selection of the materials is
that of the Contractor therefore:
2.2.1 the Contractor warrants and undertakes in favour of the Employer that:
Page-82
Signature of Contractor NBCC DWC LLC
Particular condition of contract
2.2.1.1 as the Contract works or any part of the Contract works has been or
will be designed by him, he will exercise reasonable due and proper
skill and care in such design and shall be responsible towards the
Employer for the proper design thereof; and
2.2.1.2 as the materials or goods for the Contract works has been or will be
selected by the Contractor, he will exercise due and proper skill and
care in such selection of materials or goods; and
2.2.1.3 the Contractor is suitably qualified and competent to carry out such
design work and selection of materials and goods;
2.2.1.4 the Contractor shall comply with and satisfy any performance
specification or requirement in so far as such performance
specification or requirement is included or referred to in the Contract;
and
2.2.2 the Contractor undertakes and shall be obliged to pay and make good to the
Employer all damages and losses which the Employer may suffer as a result of
his non-compliance with the warranties set out in Sub-Clause 2.2.1 above.
2.3 Without limiting any other warranty and/or undertaking by the Contractor in terms of
this agreement and, in addition thereto the Contractor does hereby warrant and
undertake in favour of the Employer that:
2.3.1 The Contract works shall, for a period of 10 years, reckoned from the date of the
issue by the Engineer under the Main Contract of a Taking-Over Certificate, be
free of any defects or damages, whether patent, latent or of whatsoever nature
resulting from and/or occasioned by:
2.3.2 The Contractor shall at his cost (without limit to the amount of such cost) and
without delay in each case, replace or repair the Contract works, or any part
thereof, which are found, during 10 years period referred to in 2.3.1 above to be
defective and/or damaged as a result of and/or occasioned by defective
workmanship, defective materials and/or defective or faulty design, as referred
to in 2.3.1 above; provided, however, that the undertaking and warranty set
forth in 2.3.1 and 2.3.2 above shall be subject to the following terms and
conditions.
Page-83
Signature of Contractor NBCC DWC LLC
Particular condition of contract
2.3.3 The Contractor’s liability under the warranty and undertaking as set forth in this
Clause 2.3 shall in addition to the obligation at his expense to repair or replace
the defective Contract works, as set forth in 2.3.2, and be also liable for any
consequential loss or damage whatever and however it might arise.
2.3.4 The Contractor shall at all times while he is liable to the Employer hereunder, be
afforded adequate and reasonably access to the Contract works and any fault or
defect which may have manifested itself therein.
2.3.5 The Contractor shall be entitled after consultation with the Employer and only
with the prior written consent of the Employer, in rectifying the defective
Contract works hereunder, to deviate from original design and/or method of
repair should such deviation prove to be more suitable and effective.
2.4 Except to the event set out herein, the parties hereto expressly agree that this
agreement contains the whole agreement between the parties and that there are no
representations, warranties or terms hereof which are not expressly set out herein.
3. EXECUTION
1. ……………………………………………………………………………………………
2. ……………………………………………………………………………………………
1. ……………………………………………………………………………………………
2. ……………………………………………………………………………………………
Page-84
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Project Name-
Dubai
(a) That the Principal has failed to carry out his obligation(s) to rectify certain defect(s)
for which he is responsible under the Contract, and
At any time, our liability under this guarantee shall not exceed the total amount of
retention money released to the Principal by you, as evidenced by your notices issued
under sub-clause 14.6 of the conditions of the Contract with a copy being passed to us.
Any demand for payment must contain your signature(s) which must be authenticated
by your bankers or by a notary public . The authenticated demand and statement must
be received by us at this office on or before (the date 70 days after the expected expiry
of the Time of Completion)……………….(the 'expiry date'), when this guarantee shall expire
and shall be returned to us.
We have been informed that the Beneficiary/employer may require the Principal to
extend this guarantee if the performance certificate under the Contract has not been
issued by the date 56 days prior to such expiry date. We undertake to pay you such
guaranteed amount upon receipt by us, within such period of 56 days, of your demand in
writing and your written statement that the performance certificate has not been issued,
and this guarantee has not been extended.
We agree that our obligations and liabilities shall not be discharged by any allowance of
time or other indulgence whatsoever on your part to the Contractor, or by any variation
or suspension of the works to be executed under the Contract, or by any amendments to
the Contract or to yours and the Contractor's constitution, or by any other matters,
whether with or without our knowledge or consent.
Page-85
Signature of Contractor NBCC DWC LLC
Particular condition of contract
Payment under this guarantee shall only be made upon presentation of this original
guarantee.
This guarantee shall inure to the benefit of your successors and assigns.
This guarantee shall be governed by the laws of Dubai and shall be subject to the
Uniform Rules for Demand Guarantees, published as number 458 by the International
Chamber of Commerce, except as stated above.
Date: ………………………….
Page-86
Signature of Contractor NBCC DWC LLC