Gas Release Emergency Response Plan

1. The document outlines an emergency response plan for a construction camp in the event of a toxic or flammable gas release/explosion from well sites. 2. It details the actions to be taken, including informing safety administrators, activating an emergency siren, assembling at a muster point for a head count, activating gas rescue teams if needed, and relaying an all clear message when the incident is over. 3. It also includes radio channel allocations and an emergency contact list with titles, channels, phone numbers, and mobile numbers for key personnel.

Uploaded by

james thorn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
101 views2 pages

Gas Release Emergency Response Plan

1. The document outlines an emergency response plan for a construction camp in the event of a toxic or flammable gas release/explosion from well sites. 2. It details the actions to be taken, including informing safety administrators, activating an emergency siren, assembling at a muster point for a head count, activating gas rescue teams if needed, and relaying an all clear message when the incident is over. 3. It also includes radio channel allocations and an emergency contact list with titles, channels, phone numbers, and mobile numbers for key personnel.

Uploaded by

james thorn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD

PROJECT No 571500
CONSTRUCTION CAMP EMERGENCY RESPONSE PLAN

Emergency Scenario: Toxic/Flammable Gas Release/Explosion from well sites during


drilling/workover operations

Action Responsible Person

1. Inform PFD Safety Administrator on Channel TCO Emergency Operator


24 or TCO Channel 2 of emergency situation.

2. Inform TCO/PFD Construction Management of PFD Safety Administrator


incident.

3. Activate Emergency Muster siren. TCO/PFD Management Team

4. Proceed cross wind to Muster Point (Field All construction personnel


Facilities Laydown Area)

5. Assemble construction personnel and take Muster Wardens


‘head count’. Report numbers to PFD Site HSE
Co-ordinator.

6. Should muster count be incorrect, inform TCO PFD HSE Manager/Designate


Emergency Operator on 5555 or Radio Channel
2 with number of missing persons.

7. Activate gas rescue teams. TCO Emergency Operator

8. Direct gas rescue teams to last known location. PFD HSE Manager/Designate

9. When all clear is given, relay to construction TCO/PFD Management Team


personnel.

Radio Channel Allocation Chart

Channel # Allocated to:

2 TCO Emergency Operator

24 PFD Construction Activities

37 Field Construction

38 Field Operations

47 Rigs

Page 1 of 2
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT No 571500
CONSTRUCTION CAMP EMERGENCY RESPONSE PLAN
TCO / PFD Construction Emergency Contact List

Mobile
Title Channel Phone No
Number
Emergency Operator 2 5555 N/A
ERT Dispatcher
PFD Admin Assistant 12 4794
TCO Construction Manager 12 4081
PFD Site Project Director
PFD Construction Manager 12 4440 +73007139412
PFD HSE Manager
PFD HSE Administrator N/A
TCO Construction HSE Supervisor
PFD Construction Superintendent 12 4440 +730071122181
PFD HSE Co-ordinator 12 TBA
Muster Warden 12 N/A N/A
Fire Warden 12 N/A N/A

For night working, PFD Safety Officer shall:


 Sign in at site and list Radio Channel (12).
 Liaise with Consortium Shift Supervisor to understand what activities will take place during the night.
 Maintain radio contact with Contractor Personnel throughout the night.
 Contact the Construction Manager on 5278 in the event of emergency at night.
 Report each morning with his daily log to the HSE Construction Supervisor.

Page 2 of 2