You are on page 1of 1198

Schedule -M / MORTH-1 Date:-25.02.

2021
List for Approved Rates of Construction Materials for the Preparation of Schedule of Rates for year 2021-22 only by the
State Level Schedule Rate Committee
Sl. No. (Materials
Description Should confirm to relevant B.I.S.,
of Materials UnitMoRDApproved
and MoRT&H
RatesSpecifications).
Royality
inclusive of included in
Royalty for SOR col.4
2021 (Rs) (Rs)

1 2 3 4 5
M-001 Stone Boulder of size 150 mm and below at Crusher Plant Cum 351.36 150.00
M-002 Supply of quarried Stone 150-200 mm size for Hand Broken at site Cum 351.36 150.00

M-003 Boulder with minimum size of 300 mm for Pitching at Site Cum 351.36 150.00
M-004 Coarse sand i) at source Quarry Koliwar/Sone sand Cum 175.80 75.00
M-005* Coarse sand ii) Equivalent to Koliwar / Cum 175.80 75.00
Sone Sand*
M-006 Fine sand at Site Cum 141.85 75.00
M-007 Moorum at Site Cum 158.35 83.00
M-008 Gravel/Quarry spall at Site Cum 351.36 150.00
M-009 Granular Material or hard murum for GSB Cum 163.53 83.00
works at site
M-010 Fly ash conforming to IS:3812 (Part II & I) at HMP Plant/Batching Cum 0.00 0
Plant/Crushing Plant
M-011 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 504.46 150.00

M-012 Close graded Granular sub-base Material 53 mm to 9.5 mm/4.75mm Cum 610.74 150.00

M-013 Close graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 587.31 150.00
M-014 Close graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 647.19 150.00
M-015 Close graded Granular sub-base Material 9.5 mm to 4.75 mm Cum 625.53 150.00
M-016 Close graded Granular sub-base Material 9.5 mm to 2.36mm Cum 506.92 150.00
M-017 Close graded Granular sub-base Material 4.75mm to 2.36mm Cum 301.05 150.00
M-018 Close graded Granular sub-base Material 4.75mm to 75 micron Cum 286.72 150.00
M-019 Close graded Granular sub-base Material 2.36 mm & below Cum 286.72 150.00
M-020 Stone crusher dust finer than 3 mm with not more than 10% passing Cum 117.23 30.00
0.075 sieve.
M-021 Coarse graded Granular sub-base Material 2.36 mm & below Cum 234.89 150.00
M-022 Coarse graded Granular sub-base Material 4.75 mm to 75 micron Cum 234.89 150.00
M-023 Coarse graded Granular sub-base Material 4.75mm to 2.36 mm Cum 249.22 150.00

M-024 Coarse graded Granular sub-base Material 9.5mm to 4.75 mm Cum 573.71 150.00
M-025 Coarse graded Granular sub-base Material 26.5mm to 4.75 mm Cum 544.89 150.00
M-026 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 595.36 150.00
M-027 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 535.48 150.00
M-028 Coarse graded Granular sub-base Material 53 mm to 26.5 mm Cum 503.85 150.00
M-029 Aggregates below 5.6 mm at Quarry Cum 249.22 150.00
M-030 Aggregates 22.4 mm to 2.36 mm at Quarry Cum 572.92 150.00
M-031 Aggregates 22.4 mm to 5.6 mm at Quarry Cum 572.92 150.00
M-032 Aggregates 45 mm to 2.8 mm at Quarry Cum 516.41 150.00
M-033 Aggregates 45 mm to 22.4 mm at Quarry Cum 524.49 150.00
M-034 Aggregates 53 mm to 2.8 mm at Quarry Cum 516.41 150.00
M-035 Aggregates 53 mm to 22.4 mm(Grade III) at Quarry Cum 503.85 150.00
M-036 Aggregates 63 mm to 2.8 mm at Quarry Cum 473.80 150.00
M-037 Aggregates 63 mm to 45 mm (Grade II) Cum 473.70 150.00
M-038 at Quarry 90 mm to 45mm(GradeI)
Aggregates Cum 442.63 150.00
M-039 at Quarry 10 mm to 5 mm at Quarry
Aggregates Cum 573.71 150.00
M-040 Aggregates 11.2 mm to 0.09 mm Cum 392.53 150.00
(Key aggregate Type B)

file:///conversion/tmp/activity_task_scratch/572445281.xlsx
M-041 Aggregates 13.2 mm to 0.09 mm Cum 515.53 150.00
M-042 (Key aggregate
Aggregates 13.2Type A) 5.6 mm at Quarry
mm to Cum 657.91 150.00
M-043 Aggregates 13.2 mm to 10 mm at Quarry Cum 686.05 150.00
M-044 Aggregates 20 mm to 10 mm at Quarry Cum 686.05 150.00
M-045 Aggregates 25 mm to10 mm at Quarry Cum 656.34 150.00
M-046 Aggregates 19 mm to 6 mm at Quarry Cum 572.92 150.00
M-047 Aggregates 37.5 mm to 19 mm at Quarry Cum 524.49 150.00
M-048 Aggregates 37.5 mm to 25 at Quarry Cum 524.49 150.00
M-049 Aggregates 6 mm nominal size at Quarry Cum 454.98 150.00
M-050 Aggregates 10 mm nominal size at Quarry Cum 657.91 150.00
M-051 Aggregates 13.2/12.5 mm nominal size Cum 686.05 150.00
M-052 at Quarry 20 mm nominal size at Quarry
Aggregates Cum 595.36 150.00
M-053 Aggregates 25 mm nominal size at Quarry Cum 570.13 150.00
M-054 Aggregates 40 mm nominal size at Quarry Cum 486.92 150.00
M-055 Crushing of Stone aggregates (GSB Crusher Run) Cum 481.13 150.00

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr &lg& vfHk;ark
izeq[k Hkou fuekZ.k foHkkx] izeq[k xzkeh.k dk;Z foHkkx] izeq[k y?kq ty lalk/ku foHkx
fcgkj] iVukA fcgkj] iVukA fcgkj iVukA

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr &lg&eq[; vfHk;ark fu/kZkj.k lfefr &lg&eq[; vfHk;ark fu/kZkj.k lfefr &lg& vfHk;ark
¼vlS½ fcgkj LVsV ikoj gksfYMx ¼fo/kqr½ Hkou fuekZ.k foHkkx] izeq[k rduhdh ijh{kd dks"kkax fuxjkuh
dEiuh fy] fcgkj] iVukA fcgkj] iVukA foHkkx ]fcgkj iVukA

lnL;] lnL;] la;kstd]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr &lg&vfHk;ark izeq[k] fu/kZkj.k lfefr &lg& vfHk;ark
izeq[k yksd LokLF; vfHk;a=.k] ¼eq[;ky;½] ty lalk/ku foHkkx] izeq[k ¼eq[;ky;½ iFk fuekZ.k
foHkkx] fcgkj] iVukA fcgkj] iVukA foHkkx fcgkj] iVukA
fcgkj] iVukA

file:///conversion/tmp/activity_task_scratch/572445281.xlsx
Schedule-M/MORTH-1A Date 25.02.2021
List of Approved Rates of Construction Materials for the Preparation of Schedule of Rates for year 2021-
22 only by the State Level Schedule Rate Committee (Materials Should conform to relevant B.I.S., MoRD
and MoRT&H Specifications). The rates are inclusive of Royalty but exclusive of all taxes,
G.S.T.,Overhead, Seigniorage fee and Contractor's profit. " Rates are at Source"

Unit Approved Rates Royality


inclusive of (Rs)
Royalty for SOR
2021 ) (Rs)

1 2 3 4 7
M-056 AC pipe 100 mm dia metre 42.54
M-057 Acrylic polymer bonding coat litre 119.78
M-058 Alluminium Paint litre 113.26
M-059 Aluminium alloy plate 2mm Thick sqm 7980.04
M-060 Aluminium alloy/galvanised steel tonne 31920.15
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting including 2% towards lettering, cost
M-061 sqm 7846.87
of angle iron, cost of drilling holes, nuts, bolts etc.and
signs as applicable
Road Aluminium Stud with Micro Prismatic lens
M-062 each 169.19
reflectors (with shank) 100 X 100 mm
M-063 Barbed wire kg 57.95
M-064 Bearing (Cost of parts) nos INPUT
Bearing (Cast steel rocker bearing assembly of 250
M-065 nos 81589.38
tonne )
Bearing (Elastomeric bearing assembly consisting of 7
internal layers of elastomer bonded to 6 nos. internal
cubic cm 0.59
reinforcing steel laminates by the process of
M-066 vulcanisation)
Taking elastomeric bearing of size 500 X 400 X 96mm,
Overall volume=19200 cubic cm @Rs 0.59/cucm= Rs nos 11328.00
11328
M-067 Bearing (Forged steel roller bearing of 250 tonne) nos 45479.26
Bearing (Pot type bearing assembly consisting of a
metal piston supported by a disc, PTFE pads providing
sliding surfaces against stainless steel mating together
M-068 MT 136.66
with cast steel assemblies/ fabricated structural steel
assemblies duly painted with all components
output=250 tonne)
Do nos 34165.00
(a) Fixed POT-PTFE Bearing MT 136.66
(b) Free POT-PTFE Bearing MT 146.43
(c) Guide Slide (L) POT-PTFE Bearing MT 156.19
(d) Guide Slide (T) POT-PTFE Bearing MT 151.31
Bearing (PTFE sliding plate bearing assembly of 80
M-069 nos 12104.94
tonnes )
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 10933.11
M-071 Bentonite kg 3.63
M-072 Binding wire kg 58.95
Bitumen ( Cationic Emulsion ) Ex- Patna (R.S1)
M-073 tonne 44306.00
Packed
M-074 Bitumen (60-70 grade) Packed Ex- Barauni tonne 43502.00
M-075 Bitumen (80-100 grade ) Packed Ex- Barauni tonne 42702.00
M-076 Bitumen (Cutback ) Packed Ex- Barauni . tonne 43502.00
M-077 Bitumen (emulsion) Packed Ex- Patna (SS1) tonne 46509.00
Bitumen (modified graded) Packed Ex - Barauni
M-078 tonne 44632.00
(CRMB - 55)
M-079 Brick 100A for - Patna Urban each 6.075 0.045
M-080 C.I. shoes for the pile kg 44.25
M-081 Cement - OPC 43 Grade at Patna tonne 4844.00
M-082 CGI Sheet 0.8 mm thick Kg 73.84
Cold twisted bars (HYSD Bars) - Fe 500 D Av. of M-
M-083 tonne 46824.00
10A
M-084 Coller (RCC) for joints 300 mm dia nos 55.00
M-085 Compressible Fibre Board (20mm thick) sqm 930.96
M-086 Connectors / Staples each 7.44
M-087 Copper Plate (12m long x 250mm wide) kg 749.21
M-088 Corrosion resistant Structural steel tonne 43845.55
Corrugated sheet, 3 mm thick, "Thrie" beam section
M-089 kg 47.35
railing
Credit for excavated rock found suitable for use (add
M-090 cum 139.07 32.09
Royality @ 30% of Rate)
M-091 Curing compound litre 123.05
Delineators from ISI certified firm as per the standard
M-092 each 794.08
drawing given in IRC - 79
Earth Cost or compensation for earth taken from
M-093 cum 34.82 33.00
private land
Elastomeric slab seal expansion joint assembly
manufactured by using chloroprene, elastomer for
M-094 metre 27202.73
elastomeric slab unit conforming to clause 915.1 of
IRC: 83 (part II)
Epoxy compound with accessories for preparing epoxy
M-095 kg 557.50
mortar
M-096 Epoxy mortar kg 738.29
M-097 Epoxy primer kg 114.14
M-098 Epoxy resin-hardner mix for prime coat kg 676.96
M-099 Flag of red color cloth 600 x 600 mm each 51.91
M-100 Flowering Plants each 6.00
M-101 Galvanised MS flat clamp nos 14.53
Galvanised steel wire crates of mesh size 100 mm x 100
M-102 mm woven with 4mm dia. GI wire in rolls of required sqm 94.65
size.
Galvanised structural steel plate 200 mm wide, 6 mm
M-103 kg 42.70
thick, 24 m long
M-104 Geo grids sqm 86.74
M-105 Geomembrane sqm 45.00
M-106 Geonets sqm 105.11
M-107 Geotextile sqm 82.17
M-108 Geotextile filter fabric sqm 82.17
M-109 GI bolt 10 mm Dia nos 15.96
M-110 Spherical Dome Nut nos INPUT
M-111 Grass (Doob) kg 4.48
M-112 Grass (Fine) kg 4.48
M-113 HDPE pipes 75mm dia metre 200.52
M-114 HDPE pipes 90mm dia metre 200.52
M-115 Hedge plants each 15.00
M-116 Helical pipes 600mm diameter metre INPUT
Hot applied thermoplastic compound (Sp. Gravity -
M-117 litre 183.25
2.10)
M-118 HTS strand tonne 68410.22
M-119 Joint Sealant Compound kg 24.61
Jute netting, open weave, 2.5 cm square opening for
M-120 sqm 36.94
seeding and Mulching
M-121 LDO for steam curing litre INPUT
M-122 M.S. Clamps nos 34.06
M-123 M.S. Clamps kg 61.64
M-124 M.S.shoes @ 35 Kg per pile of 15 m kg 23.57
M-125 Mild Steel bars (Av-M6) tonne 50325.00

Modular strip/box seal expansion joint including


anchorage catering to a horizontal movement beyond 70
mm and upto 140mm assembly comprising of edge
M-126 beams, central beam, 2 modules chloroprene seal, metre 29978.49
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative

Modular strip/box seal expansion joint catering to a


horizontal movement beyond 140mm and upto 210mm
box/box seal joint assembly containing 3 modules/cells
and comprising of edge beams, two central beams,
M-127 metre 29978.49
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative

M-128 Nipples 12mm,300mm long nos 40.00


M-129 Nuts and bolts kg 61.74
M-130 Paint litre 224.02
M-131 Pavement Marking Paint litre 224.02
M-132 Paving Fabric sqm 76.89
M-133 Perforated geosynthetic pipe 150 mm dia metre 26.51
M-134 Perforated pipe of cement concrete, internal dia 100 mm metre 109.54
M-135 Pesticide kg 77.86
M-136 Pipes 200 mm dia, 2.5 m long for drainage metre 160.18
M-137 Plastic sheath, 1.25 mm thick for dowel bars sqm 15.02
M-138 Plastic tubes 50 mm dia, 1.2 m high nos INPUT
M-139 Polymer braids metre INPUT
Pre moulded Joint filler, 25 mm thick for expansion
M-140 sqm 961.32
joint.
M-141 Pre-coated stone chips of 13.2 mm nominal size cum 634.05 150.00
Preformed continuous chloroprene elastomer or closed
cell foam sealing element with high tear strength,
M-142 metre INPUT
vulcanised in a single operation for the full length of a
joint to ensure water tightness.
M-143 Pre-moulded asphalt filler board sqm 961.32
Pre-packed cement based polymer concrete of strength
M-144 kg INPUT
45 Mpa at 28 days
M-145 Primer (Wall) kg 70.48
M-146 Quick setting compound kg INPUT
M-147 Random Rubble Stone cum 336.55 150.00
RCC Pipe NP 4 heavy duty non presure pipe 1000 mm
M-148 metre 5565.00
dia with spigot
RCC Pipe NP 4 heavy duty non presure pipe 1200 mm
M-149 metre 6510.00
dia with spigot
RCC Pipe NP 4 heavy duty non presure pipe 900 mm
M-150 metre 4494.00
dia with spigot
RCC Pipe NP 4 heavy duty non presure pipe 600 mm
M-151 metre 2310.00
dia with spigot
RCC Pipe NP 4 heavy duty non presure pipe 300 mm
M-152 metre 516.74
dia
M-153 Reflectorising glass beads kg 65.04
Reinforcement strips 60 mm wide 5 mm thick as per
M-154 metre INPUT
clause 3102. (Copper Strips)
Reinforcement strips 60 mm wide 5 mm thick as per
M-155 metre INPUT
clause 3102. (Galvanised carbon steel strips)
Reinforcement strips 60 mm wide 5 mm thick as per
M-156 clause 3102. (Glass reinforced polymer/fibre reinforced metre INPUT
polymer/polymeric strips)
Reinforcement strips 60 mm wide 5 mm thick as per
M-157 metre INPUT
clause 3102. (Stainless steel strips)
Reinforcement strips 60 mm wide 5 mm thick as per
M-158 metre INPUT
clause 3102. (Aluminium strips)
M-159 Rivets each 8.11
M-160 Sand bags (Cost of sand and Empty cement bag) nos 8.48 2.59
M-161 Sapling 2 m high 25 mm dia each 23.08
M-162 Scrap tyres of size 900 x 20 nos 76.91
M-163 Seeds kg 34.61
Selected earth (Including royalty @ `33.0 per cum &
M-164 cum 34.82 33.00
compensation @ `1.81 per cum)
Separation Membrane of impermeable plastic sheeting
M-165 sqm 14.07
125 micron thick
M-166 Sheathing duct metre 84.61
M-167 Shrubs each/ (sqft) 2.50

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at


M-168 cum 552.00
site of work for turfing
M-169 Sodium vapour lamp (70 watt) each 170.68
M-170 Square Rubble Coursed Stone cum 336.54 150.00
Steel circular hollow pole of standard specification for
M-171 street lighting to mount light at 5 m height above deck each INPUT
level
Steel circular hollow pole of standard specification for
M-172 street lighting to mount light at 9 m height above road each INPUT
level
Steel drum 300 mm dia 1.2 m high/empty bitumen
M-173 nos 123.71
drum
Steel helmet and cushion block on top of pile head
M-174 kg 40.01
during driving.
M-175 Steel pipe 25 mm external dia as per IS:1239 metre 123.62
M-176 Steel pipe 50 mm external dia as per IS:1239 metre 221.22
M-177 Steel pipe 100 mm external dia as per IS:1239 metre INPUT
M-178 Steel wire rope 20 mm kg 42.65
M-179 Steel wire rope 40 mm kg 42.65
M-180 Strip seal expansion joint metre 8439.38
M-181 Structural Steel (Av. of M6, M8 & M9) tonne 46658.00
M-182 Super plastisizer admixture IS marked as per 9103-1999 kg 159.51

Synthetic Geogrids as per clause 3102.8 and approved


M-183 sqm 182.60
design and specifications.
M-184 Through and bond stone each 10.35
M-185 Tie rods 20mm diameter (500mm length) @2.47 kg/m nos 57.80
M-186 Tiles size 300 x 300 mm and 25 mm thick each 38.93
M-187 Timber cum 41951.09
M-188 Traffic cones with 150 mm reflective sleeve nos INPUT
Tube anchorage set complete with bearing plate,
M-189 nos 46.14
permanent wedges etc
M-190 Unslaked lime tonne 3637.51
Sub Analysis
M-191 Water KL 73.60
21.22
M-192 Water based cement paint litre 114.01
M-193 Welded steel wire fabric kg 41.34
M-194 Wire mesh 50mm x 50mm size of 3mm wire kg 40.58
M-195 Wooden ballies 2" Dia for bracing (Sal) each 20.85
M-196 Wooden ballies 8" Dia and 9 m long each 504.19
M-197 Wooden packing cum INPUT
Wooden staff for fastening of flag 25 mm dia, 1.0 m
M-198 each 26.06
long
M-199 Silica fume kg 32.00
Synthetic Geogrids Ultimate tensile Strength
M-200 Sqm 182.60
100kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-201 Sqm 200.87
150kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-202 Sqm 273.91
200kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-203 Sqm 301.30
250kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-204 Sqm 319.56
300kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-205 Sqm 356.08
350kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-206 Sqm 383.47
400kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-207 Sqm 456.52
500kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-208 Sqm 502.17
600kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-209 Sqm 593.48
700kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-210 Sqm 646.43
800kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-211 Sqm 767.87
900kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-212 Sqm 867.39
1000kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-213 Sqm 913.04
1100kN/Metre.
Synthetic Geogrids Ultimate tensile Strength
M-214 Sqm 993.39
1200kN/Metre.
M-215 Explosive for blasting(Gelatine80%) Kg 879.47
M-216 Delay Detonators Nos INPUT
Electric Detonators @1 detonator for 1/2 gelatin stick
M-217 Nos 5.77
of 125 gms each
M-218 Detonation Fuse coil Meter INPUT
M-219 3.7 mlong extension rod boom Hydraulic Drill jumbo Nos INPUT
M-220 32 mm coupling sleeve boom Hydraulic Drill jumbo Nos INPUT
M-221 Difter rod boom Hydraulic Drill jumbo Nos INPUT
M-222 R32 sank adapter boom Hydraulic Drill jumbo Nos INPUT
M-223 45 mm Dia Button Bit boom Hydraulic Drill jumbo Nos INPUT
M-224 51 mm Dia Button Bit Hydraulic Drill Jumbo Nos INPUT
M-225 Steel Fiber tonne INPUT
M-226 Microsilica Kg 32.00
M-227 Accelerator Kg INPUT
M-228 Wire mesh Kg 40.58
17.75
Bamboos (i) 75mmDia 6m to 8m long
18.95
(ii) 100mm Dia 6m to 8m long
M-229 Meter 11.85
(iii) 50mm Dia Hill Bamboo

M-230 Live Stake Stump Meter INPUT


M-231 Hard wood sticks Meter INPUT
M-232 Live Sods(0.6m Length) Nos INPUT
M-233 Live Sods(2.0 m Length) Nos INPUT
M-234 Coal Tar Epoxy Kg INPUT
M-235 Binding Material Meter INPUT
M-236 Spring post 700mm each INPUT
M-237 Spring post 450 mm each INPUT
Water Filled Barricades Work zone sheeting
M-238 (Trapezoidal Shape 800mmto 1000mm in each INPUT
length,700mm in height
M-239 GI Pipe 100 mm Dia Meter 522.42
M-240 Bracket for G.I Pipe fixing Kg INPUT
M-241 Flange for G.I Pipe fixing Kg INPUT
M-242 Neem Cake Quintal 4000.00
M-243 Supplying sludge Cum 552.00
M-244 Contol Center Server Nos INPUT
M-245 Hot Standby Backup Server Nos INPUT
M-246 NAS Video Server with storage Minimum 70 TB Nos INPUT
M-247 Backup Video (Only Incidents) Server. Nos INPUT
M-248 Graphic Display(70'' LED DLP IN 3X2 matrix) Set INPUT
Graphic Display Controller and software including
M-249 Set INPUT
Video Switches
M-250 CCTV Monitoring Workstation Nos INPUT
M-251 Emergengy Telephone (1033)Console. Nos INPUT
M-252 VIDS-Workstation. Nos INPUT
M-253 Administrative Workstation Nos INPUT
M-254 ATMS Operator Workstation Nos INPUT
M-255 CCTV joystick Nos INPUT
M-256 Operations Laser Printer(Colour) Nos INPUT
M-257 Operations Laser Printer(Black) Nos INPUT
M-258 Rack 19'' Nos INPUT
ATMS Control Room Software(integrated with
M-259 Ls INPUT
VIDS,ATCC,VMS,MOS)

M-260 Video Management Software with atleast 150 VMS Lic Ls INPUT
M-261 Facility Monitoring System Controller Software Ls INPUT
M-262 Server & Database license Ls INPUT
M-263 Antivirus license Ls INPUT
M-264 PTZ Camera (including CCTV Controller) Set INPUT
Solar System with UPS, battery & 12mm Pole &
M-265 Set INPUT
Cabinet
M-266 VIDS Camera (including image Prossesing unit) Set INPUT
Warning amber lights with hooters, 72 Hrs solar
M-267 Set INPUT
backup,5m poles and foundation
M-268 Cabinet Nos INPUT
M-269 12 m Pole (including manufacturing and galvanizing) Nos INPUT
M-270 Solar System with UPS & batteries Set INPUT
Equipment,Sensor unit, Processing unit, Solar power
M-271 Set INPUT
supply and civil works for 4 Lanes
M-272 Solar System with UPS , batteries. Set INPUT
M-273 VMS (Variable Message Sine-Mtype) Nos INPUT
M-274 Gantry(including Manufacturing and galvanizing) Nos INPUT
Solar System with UPS, battery and Cabinet for M type
M-275 Set INPUT
VMS
Uninterruptible Power supply (UPS)for Server
M-276 Set INPUT
Rack(10KVA)
Uninterruptible Power supply (UPS) for TMC
M-277 Set INPUT
(30KVA)

M-278 Power Distribution Board (Essential & CriticalSupply) Set INPUT


M-279 MOS sensor Equipment (including MOS Controller) Set INPUT
M-280 Cabinet Nos INPUT
M-281 Pole Nos INPUT
M-282 Steel fence for protection Set INPUT
M-283 24 CoreArmoured OFC + all accessories Meter INPUT
40 mm PLB HDPE duct as per latest TSEC
M-284 Meter INPUT
specification +all accessories
Trenching of 1.8 meters,Laying & Back filling for PLB
M-285 Meter INPUT
HDPE duct
Bi- Axial Extruded Geogrids of Minimum Tensile
M-286 sqm 86.74
Strengh 15kN/m
Bi- Axial Extruded Geogrids of Minimum Tensile
M-287 sqm 99.52
Strengh 20kN/m
Bi- Axial Extruded Geogrids of Minimum Tensile
M-288 sqm 162.52
Strengh 30kN/m
Bi- Axial Extruded Geogrids of Minimum Tensile
M-289 sqm 237.39
Strengh 40kN/m
Geosynthetic Drainage composite (tensile strength of 18
M-290 sqm 460.17
Kn/m)
Geosynthetic Drainage composite (tensile strength of
M-291 sqm 547.82
13.5 Kn/m)
M-292 Waste Plastic (as per IRC:SP:98-2013) tonne 14580.00
RCC Pipe NP 4 heavy duty non presure pipe 1500 mm
M293 meter 6510.00
dia
M294 Acrylic noise barrier sheet Sqm INPUT
M295 Silt Fence Sheet Sqm INPUT
Fully Threaded Hot Dip galvanised geotechnical bars
M296 Lm INPUT
with casing'
M297 Centralizer No INPUT
M298 Bearing Plate 200mm x 200mm x 10mm No INPUT
M299 Spherical dome nut Nos. INPUT
M300 Fibre Reinforcement tonne INPUT
M301 Geotextile Sqm 82.17
M302 Polyvinyl Chloride Pipe (PVC)-90 mm meter 70.00
M303 Polyvinyl Chloride Pipe (PVC)-110 mm meter 130.00
M304 Polyvinyl Chloride Pipe (PVC)-135 mm meter 130.00
M305 Steel/Iron Scraps Kg. INPUT
Aluminium sheeting fixed with encapsulated lens type
M306 reflective sheeting including 2% towards lettering sqm INPUT
(Class-C Type XI- 2mm thick)
M307 Geocell sqm 86.74
M308 Geosynthetics mat sqm 45.00
M309 Natural geotextile sqm 82.17
M310 Fabric Form mattress sqm 82.17
M311 Non-Woven Geotextile sqm 82.17
Sr. Road Safety/Auditor/ Team Leader for Road Safety
M312 Month INPUT
Audit
M313 Traffic Planner for Road Safety Audit Month INPUT
Boarding & Loading and Per Diem for Site Visits
M314 Days INPUT
(During Road Safety Audit)
Transportation at site and Head Office (During Road
M315 No. of Trip INPUT
Safety Audit)
M316 Duty travel to Site (During Road Safety Audit) Days INPUT
Collection of Road accident data and analysis of fatal
No. of
M317 and grievously injured accident with black spot INPUT
Copies
identification (During Road Safety Audit)
No. of
M318 Submission of GAP report (For Road Safety Audit) INPUT
Copies
Road Safety Audit Reports on all activities which were
No. of
M319 planned, actually executed and planned for the next INPUT
Copies
quarter.
Submission of Audit Report of work zone safety (for No. of
M320 INPUT
Road Safety Audit) Copies
No. of
M321 Workshop Report for Road Safety Audit INPUT
Copies
No. of
M322 Final Safety Report (for road safety Audit) INPUT
Copies
Cement Fly Ash Brick (Conforming to IS 12894, size=
230 X 110 X 70 mm, weight of one brick= 3Kg,
M-323 each 5.008
composition: Fly ash= 60%, Coarse sand= 30%,
Cement= 10%) including carriage of sand
Paver Block (Excluding GST )
(i) M -35 Grade and 60 mm thickness (a) White sqm 506.66
(b) Red sqm 515.69
M-324 (C) Yelliw sqm 531.88
(ii) M-40 Grade and 80mm thickness (a) White sqm 581.43
(b) Red sqm 596.64
(C) Yellow sqm 615.88
Kerb-Stone Block- M30 Grade (Size 375mm x 300mm
M-325 each 79.00
x150mm ) inclusive of OH & CP
M-326 Autoclaved Aerated Concrete (AAC) Block cum 2457.20
M-327 Bitumen grade VG 40 (30/40) packed Ex Fatuha. MT 44525.00
Construction of restaurant, workshop, first aid room,
MR01 shop etc. in truck parking area complete as per drg. and Sqm INPUT
direction of the Engineer.
Providing Telephone booth complete as per
MR02 Nos. INPUT
specifications and direction of Engineer.
Providing & fixing tube well, complete as per drawing
MR03 Nr. INPUT
and additional specifictions.
Providing a Drinking Water Kiosk complete as per
MR04 Nr. INPUT
drawing & specification.
Providing and fixing of litter bins in Truck lay Bye
MR05 locations complete as per drawing or as directed by the Nr. INPUT
engineer.
Construction of toilet block provided with fittings and
MR06 fixtures complete in truck parking area complete as per Nr. INPUT
drg. and direction of the Engineer.
Construction of Open lined U - Drain in truck laybye
MR07 area complete as shown in drawing and technical Meter INPUT
specification clause 309.
Providing shelters for bus passengers as per drawing
MR08 and MORT&H Specifications section 300, 1500, 1600 Nr. INPUT
and 1700.

Providing & fixing guard railing with tubular steel


sections at foot path / medians / islands etc including
MR09 foundation concrete and painting with approved paint Meter INPUT
etc. all complete as per drawing & MORT&H
Specifications Clauses 808, 300, 1500, 1700 & 1900.

MR10 Toll Booth at Tollplaza Nr. INPUT


MR11 Barrier gates at Tollplaza For 3.2 m wide toll lane Nr. INPUT
MR12 Barrier gates at Tollplaza For 4.5 m wide toll lane Nr. INPUT
MR13 Canopy Sqm INPUT
MR14 Canopy Lights Halide lamps 150 watt Nr. INPUT
MR15 Canopy Lights Halogen lamps 1000 watt Nr. INPUT
MR16 Loading Unloading Platform Sqm INPUT
MR17 Traffic Aid Post at Toll Plaza Nr. INPUT
MR18 Medical Aid Post at Toll Plaza Nr. INPUT
MR19 Vehicle Rescue Post at Toll Plaza Nr. INPUT
MR20 Ambulances at Toll Plaza Nr. INPUT
MR21 Cranesat Toll Plaza Nr. INPUT
MR22 Electronic Toll Connection (ETC lanes) at Toll Plaza Nr. INPUT
MR23 Intercom facility at Toll Plaza Nr. INPUT
MR24 Weigh Bridge Nr. INPUT
MR25 Car Parking area Sqm INPUT
MR26 Generator room Sqm INPUT
MR27 Base Maintainance Camp Sqm INPUT
MR28 Toll plaza equipment Lane INPUT
Electrification And Air conditioning for toll Booth and
MR29 LS INPUT
toll Plaza
MR30 Bull nose crash barrier Nr. INPUT
MR31 Standby Generator at Toll Plaza Nr. INPUT
MR32 CCTV camera installed at each booth Nr. INPUT
MR33 T1 for Toll Road Start Nr. INPUT
MR34 T2 for Toll Gate 1 Km Nr. INPUT
MR35 T3 for Toll Gate 500 m and toll rates Nr. INPUT
MR36 T4 for exempt vehicles at Toll Plaza Nr. INPUT
MR37 T5 for pictorial description of toll rates Nr. INPUT
MR38 T6 for over size vehicle lane direction sign at Toll Plaza Nr. INPUT

T7 near the Toll booths displaying Toll Rates, exempt


MR39 Nr. INPUT
vehicles and complaint telephone number & address
MR40 T8 for Toll Road End Nr. INPUT
MR41 Picnic Area at Rest Area Sqm INPUT
MR42 Petrol Pump & Pepairing Shop at Rest Area Sqm INPUT
MR43 Buffer Zone at Rest Area Sqm INPUT
MR44 Traffic blinker Signal (L.E.D.) Nr INPUT
MR45 PVC Roof Sheet at FOB Sqm INPUT
MR46 Cost of Water Quality Monitoring Nos. INPUT
MR47 Cost of Soil Quality Monitoring Nos. INPUT
MR48 Cost of Ambient Air Quality Nos. INPUT
MR49 Cost of Ambient Noise Monitoring 24 hour continuous Nos. INPUT
MR50 Consent to Establish (CTE) Nos. INPUT
MR51 Consent to Operate (CTO) Nos. INPUT
MR52 Compliance submission for Consent to Establish (CTE) Nos. INPUT

MR53 Compliance submission for Consent to Operate (CTO) Nos. INPUT


MR54 Cost of Environmental Workshop Nos. INPUT

lnL;] lnL;]
jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj lnL;]
fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr &lg&vfHk;ark jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr&lg&vfHk;ark izeq[k]
izeq[k Hkou fuekZ.k foHkkx izeq[k xzkeh.k dk;Z
y?kq ty lalk/ku foHkkx]
foHkkx fcgkj]iVukA
]fcgkj] iVukA ]fcgkj] iVukA

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr &lg&eq[; vfHk;ark fu/kZkj.k lfefr &lg&eq[; fu/kZkj.k lfefr&lg&vfHk;ark izeq[k]
vfHk;ark ]rduhdh ijh{kd dks"kkax fuxjkuh foHkkx]
¼vlSñ½ fcgkj LVsV ikoj gksfYMx ¼ fo/kqr½ Hkou fcgkj]iVukA
fuekZ.k foHkkx dEiuh fyñfcgkj iVukA fcgkj]iVukA
]

lnL;] lnL;] la;kstd]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr &lg&vfHk;ark fu/kZkj.k lfefr&lg&vfHk;ark izeq[k
izeq[k yksd LokLF; vfHk;a=.k izeq[k] eq[;ky;]ty lalk/ku ¼eq[;ky;½ iFk fuekZ.k foHkkx]
foHkkx] fcgkj] iVukA foHkkx ]fcgkj] iVukA fcgkj]iVukA
42.54
119.78
113.26
7980.04
31920.15

7846.87

169.19
57.95

81589.38

0.59

11328.00

45479.26

136.66

34165.00
136.66
146.43
159.19
151.31
12104.94
10933.11
3.63
58.95
44306.00
43502.00
42702.00
43502.00
46509.00
44632.00
6.08
44.25
4844.00
73.84
46824.00
55.00
930.96
7.44
749.21
43845.55
47.35

139.07
123.05
794.08

34.82

27202.73

557.5
738.29
114.14
676.96
51.91
6.00
14.53

94.65

42.70
86.74
45.00
105.11
82.17
82.17
15.96

4.48
4.48
200.52
200.52
15.00
183.25
68410.22
24.61
36.94

34.06
61.64
23.57
50325.00

29978.49

29978.49

40.00
61.74
224.02
224.02
76.89
26.51
109.54
77.86
160.18
15.02

961.32
634.05

961.32

70.48

336.55
5565.00

6510.00

4494.00

2310.00

516.74
65.04

8.11
8.48
23.08
76.91
34.61
34.82

14.07
84.61
2.50

552.00
170.68
336.54

123.71

40.01
123.62
121.22

42.65
42.65
8439.38
46658.00
159.51

182.60
10.35
57.80
38.93
41951.09

46.14
3637.51

259.54

114.01
41.34
40.58
20.85
504.19

26.06
32.00
182.60

200.87

273.91

301.30

319.56

356.08

383.47

456.52

502.17

593.48

646.43

767.87

867.39

913.04
993.39
879.47

5.77

32.00

40.58
17.75
18.95
11.85

522.42

4000.00
552.00
86.74

99.52

162.52

237.39

460.17

547.82
14580.00
6510.00
82.17

86.74
45.00
82.17
82.17
82.17

5.008

506.66
515.69
531.88
581.43
596.64
615.88
79.00
2457.20
44525.00
Schedule- P & M / MORTH - 1A Date :- 25.02.2021
Approved Usages rate of Plants & Machinery for preparation of Schedule of rate 2021-22 including
all charges ,cost of repair,maintaintance,tyre- replacement,running and operating charges such as
fuel lubricant,labour etc but excluding GST,Overhead and Contractor's profit.

Sl.No. Code Description Unit Approved Remarks


Rate
1 PM1001 Dozer - 240 HP Hour 6,461.00
2 PM1002 Dozer - 175 HP Hour 4,930.00
3 PM1003 Dozer - 90 HP Hour 3,274.00
4 PM2001 Motor Grader 4.3 metre blade Hour 5,900.00
5 PM2002 Motor Grader 3.7 metre blade Hour 5,398.00
6 PM2003 Motor Grader 3.35 metre blade Hour 2982
7 PM3003 Hydraulic Excavator of 1.2 cum bucket Hour 3,388.00
8 PM3004 Hydraulic Excavator of 1.1 cum bucket Hour 3,021.00
9 PM3005 Hydraulic Excavator of 0.9 cum bucket Hour 2,702.00
10 PM4001 Jack Hammer (attachment of Hydraulic Excavator) Hour 206.00
11 PM5001 Front End loader 3.1 cum bucket capacity Hour 4,255.00
12 PM5002 Front End loader 2.1 cum bucket capacity Hour 2,588.00
13 PM5003 Backhoe-loader 1 cum bucket capacity Hour 1594
14 PM6001 Tipper-18 Cum Hour 2772
15 PM6002 Tipper-14 Cum Hour 2415
16 PM6003 Tipper-10 Cum Hour 2121
17 PM6004 Tipper-5.5 Cum Hour 1183
18 PM7001 Vibratory Soil Compactor (10 tonne) Hour 2156
19 PM8001 Smooth Wheeled Roller 8 tonne Hour 901
20 PM9001 Tandem Roller Hour 2,357.00
21 PM9002 Mini Tandem Roller hour 1,210.00
22 PM10001 Pneumatic Road Roller Hour 2338 Vibratory
road Roller
23 PM11001 Water Tanker (16 KL) Hour 1,426.00
24 PM11002 Water Tanker (12 KL) Hour 1,252.00
25 PM11003 Water Tanker (6 KL) Hour 907.00
26 PM12001 Tractor-Trolly Hour 612.00
27 PM13001 Rotavator Hour 17.00
28 PM14001 Ripper Hour 21.00
29 PM15001 Air Compressor -250 cfm Hour 416.00
30 PM15002 Air Compressor -500 cfm Hour 2,848.00
31 PM16001 Integrated Stone Crusher Stone (3 Stage) 250 TPH Hour 13,431.00
32 PM17001 Wet Mix Plant - 250 TPH Capacity Hour 642.00
33 PM17002 Wet Mix Plant - 200 TPH Capacity Hour 348.00
34 PM17003 Wet Mix Plant - 100 TPH Capacity Hour 322.00
35 PM18001 Hotmix Plant - 200 TPH Capacity Hour 14,810.00
36 PM18002 Hotmix Plant - 160 TPH Capacity Hour 10,450.00
37 PM18003 Hotmix Plant - 120 TPH capacity Hour 8309.00
38 PM19001 Batching and Mixing Plant - 240 cum Capacity Hour 5670.00
39 PM19002 Batching and Mixing Plant - 120 cum Capacity Hour 3627.00
40 PM20001 Mobile Concrete Batching / Mixing Plant Hour 735.00
41 PM21001 Concrete Mixer - 0.4/0.28 cum Hour 286.00
42 PM21002 Concrete Mixer - 1 cum Hour 344.00
43 PM22001 Generator 725 KVA Hour 13,148.00
44 PM22002 Generator 500 KVA Hour 9,075.00
45 PM22003 Generator 400 KVA Hour 7,303.00
46 PM22004 Generator 250 KVA Hour 4359.00
47 PM22005 Generator 125 KVA Hour 2653.00
48 PM22006 Generator 100 KVA Hour 2251.00
49 PM22007 Generator 62.5 KVA Hour 1,421.00
50 PM22008 Generator 33 KVA Hour 783.00
51 PM22009 Generator 15 KVA Hour 410.00
52 PM23001 Mechanical Broom Hydraulic Hour 642.00
53 PM24001 Bitumen Pressure Distributor Hour 1,645.00
54 PM25001 Emulsion Pressure Distributor Hour 1,645.00
55 PM26001 Bitumen Boiler Oil Fired Hour 606.00
56 PM27001 Mastic Cooker Hour 461.00
57 PM28001 Paver Finisher Mechanical Hour 1583.00
58 PM29001 Paver Finisher Hydrostatic with sensor control -240 HP Hour 8710.00
59 PM29002 Paver Finisher Hydrostatic with sensor control -170 HP Hour 6808.00
60 PM30001 Paver Finisher Concrete with 300 HP Motor Hour 26752.00
61 PM30002 Paver Finisher Concrete with 241 HP Motor Hour 17252.00
62 PM30003 Paver Finisher Concrete with 118 HP Motor Hour 4,082.00
63 PM31001 Texture Curing Machine (TCM) - upto 18 m Hour 4,470.00
64 PM31002 Texture Curing Machine (TCM) - upto 9 m Hour 3,497.00
65 PM32001 Hydraulic Chip Spreader Hour 2,146.00
66 PM33001 Pot-Hole Repair Machine Hour 1,718.00
67 PM34001 Transit Mixer - 6 Cum Hour 2,218.00
68 PM35001 Concrete Pump Hour 1,050.00
69 PM36001 Boom Placer Hour 4,052.00
70 PM37001 Kerb Casting Machine Hour 1,590.00
71 PM38001 Piling Rig with Bentonite Pump Hour 19,622.00
72 PM39001 Pneumatic Sinking Plant Hour 7,055.00
73 PM40001 Road marking machine Hour 1,965.00
74 PM41001 Mobile Slurry Seal Equipment Hour 3,619.00
75 PM42001 Joint Cutting Machine Hour 317.00
76 PM43001 Bar Bending & Cutting Machine Hour 334.00
77 PM44001 Needle Vibrator Hour 347.00
78 PM45001 Jack Hammer for air compressor Hour 11.00
79 PM46001 Plate Compactor Hour 352.00
80 PM47001 Milling Machine with 1 meter Drum Width Hour 4,448.00
81 PM47002 Milling Machine with 1.2 meter Drum Width Hour 5,276.00
82 PM47003 Milling Machine With 1.3 meter Drum Width Hour 7,711.00
83 PM47004 Milling Machine With 2 meter Drum Width Hour 11,192.00
84 PM48001 Cold in Situ recycling of bitumen's pavement with foam Hour 28,850.00
bitumen technology
85 PM49001 In situ stabilisation of WMM/GSB/Sub grade Hour 25,715.00
86 PM50001 Cement spreader Hour 7,872.00
87 PM51001 Mobile cold recycling mixing plant Hour 21,242.00
88 PM52001 Hot in place recycling Hour 103,416.00
89 PM53001 Pre heater unit for hot in place recycling Hour 902.00
90 PM54001 Single boom Hydraulic Drill Jumbo Hour 4,513.00
91 PM55001 Two boom Hydraulic Drill Jumbo Hour 6,857.00
92 PM56001 Three boom Hydraulic Drill Jumbo Hour 10,022.00
93 PM57001 Hydraulic Rock bolt drill Hour 6,711.00
94 PM58001 Rotating Telehandlers Hour 1,075.00
95 PM59001 Shotcrete Machine Hour 1,433.00
96 PM60001 Grouting machine Hour 521.00
97 PM61001 Dewatering Pump 10 HP Hour 260.00
98 PM61002 Concrete cutting machine Hour 175.00
99 PM62001 Crawler mounted Crane 35 tonne capacity Hour 6,082.00
100 PM62002 Crawler mounted Crane 80 tonne capacity Hour 6,403.00
101 PM62003 Crawler mounted Crane 100 tonne capacity Hour 9,736.00
102 PM63001 Mobile Hydraulic Crane 3 tonne capacity Hour 862.00
PM63002 Mobile Hydraulic Crane 5 tonne capacity Hour 909.00
104 PM63003 Mobile Hydraulic Crane 10 tonne capacity Hour 1,019.00
105 PM63004 Mobile Hydraulic Crane 15 tonne capacity Hour 1,057.00
106 PM63005 Mobile Hydraulic Crane 20 tonne capacity Hour 1,466.00
107 PM63006 Mobile Hydraulic Crane 35 toone capacity Hour 2,337.00
108 PM64001 Concrete Bucket Hour 83.00
109 PM65001 Prestressing Jack with Pump & Access Hour 406.00
110 PM66001 Boat to carry atleast 20 persons hour 773.00
111 PM67001 Crane with grab 0.75 cum capacity hour 871.00
112 PM68001 Epoxy Injection gun hour 241.00
113 PM6900 Induction, deinduction and erection of plant and hour 9,688.00
1 equipment including all components and accessories for
pneumatic method of well sinking.

114 PM7000 Jack for Lifting 40 tonne lifting capacity. hour 232.00
115 1
PM7100 Vibrating Pile driving hammer complete with power unit hour 18,501.00
1 and accessories.
116 PM7200 Tipper 18 Cum ( Surface Road) Per 5.94 As per
1 Tonn Carriage Rate
e Km.

117 PM7200 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH t.km 7.22 Do
2 & CP
118 PM7200 Tipper-18 Cum (Katcha Track) excluding OH & CP t.km 14.44 Do
119 3
PM7300 Tipper -14 Cum (Surface Road) excluding OH & CP t.km 6.63 Do
120 1
PM7300 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding t.km 8.05 Do
2 OH & CP
121 PM7300 Tipper -14 Cum (Katcha Track) excluding OH & CP t.km 16.10 Do
122 3
PM7400 Tipper -10 Cum (Surface Road) excluding OH & CP t.km 8.08 Do
123 1
PM7400 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding t.km 9.82 Do
2 OH & CP
124 PM7400 Tipper -10 Cum (Katcha Track) excluding OH & CP t.km 19.64 Do
125 3
PM7500 Tipper- 5.5 Cum (Surface Road) excluding OH & CP t.km 8.12 Do
126 1
PM7500 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding t.km 9.85 Do
2 OH & CP
127 PM7500 Tipper- 5.5 Cum (Katcha Track) excluding OH & CP t.km 19.72 Do
128 3
PM76001 Transit Mixer - 6 Cum excluding OH & CP t.km 12.32 Do
129 PM77001 Loading and unloading of stone boulder / stone cum 90.96 Do
aggregates / sand / kanker / moorum (Using by 18 cum
capacity Tipper & 3.1 Cum capacity Loader) excluding OH
& CP

130 PM77002 Loading and unloading of stone boulder / stone cum 89.34 Do
aggregates / sand / kanker / moorum (Using by 14 cum
capacity Tipper & 2.1 Cum capacity Loader) excluding OH
& CP

131 PM77003 Loading and unloading of stone boulder / stone cum 118.14 Do
aggregates / sand / kanker / moorum (Using by 10 cum
capacity Tipper & 1.0 Cum capacity Loader) excluding OH
& CP
132 PM77004 Loading and unloading of stone boulder / stone cum 114.61 Do
aggregates / sand / kanker / moorum (Using by 5 cum
capacity Tipper & 1.0 Cum capacity Loader) excluding OH
& CP

133 PM77005 Loading and Unloading of Cement or Steel by Manual tonne 485.08 Do
Means and Stacking
134 PM78001 Centrifugal water pump Hour 329.00
135 PM79001 Shredding Machine Hour 416.00
136 PM80001 Mobile Bridge Inspection Unit (MBIU) hour 6,887.00
137 PM81001 Network Survey Vehicle (NSV) With SUV hour 6,287.00
138 PM82001 Falling weight deflectometer (FWD) Equipment With SUV hour 3,128.00
139 PM83001 Retroreflectometer testing equipment with Vehicle With S hour 1,709.00
140 PM84001 Sport utility vehicle (SUV) hour 1,221.00
141 PM85001 Automatic Vehicle Counter Classifier (ATCC) System hour 74.00
142 PM90001 WMM Paver finisher hour 1810.00
143 PM90002 6.5 KVA Generator set hour 304.00
144 PM90003 Sensor Paver Finisher(158 BHP) hour 3958.00

lnL; lnL; lnL;


]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k
lfefr &lg&vfHk;ark izeq[k lfefr &lg&vfHk;ark izeq[k lfefr &lg&vfHk;ark izeq[k
Hkou fuekZ.k foHkkx xzkeh.k dk;Z foHkkx y/kq ty lalk/ku foHkkx
fcgkj]iVukA fcgkj]iVukA fcgkj]iVukA

lnL; lnL; lnL;


]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k
lfefr &lg&eq[;vfHk;ark ¼vlSñ½ lfefr &lg&eq[;vfHk;ark ¼fo/kqr½ lfefr &lg&vfHk;ark izeq[k
fcgkj LVsV ikoj gksfYMx dEiuh fyñ Hkou fuekZ.k foHkkx rduhdh ijh{kd dks"kakx] fuxjkuh
fcgkj]iVukA fcgkj]iVukA foHkkx]
fcgkj]iVukA

lnL; lnL; la;kstd]


]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k ]jkT; Lrjh; vuqlwfpr nj fu/kZkj.k
lfefr &lg&vfHk;ark izeq[k lfefr &lg&vfHk;ark izeq[k ¼ eq[;ky;½ lfefr &lg&vfHk;ark izeq[k
yksd LokLF; vfHk;a=.k ty lalk/ku foHkkx ¼eq[;ky;½
foHkkx] fcgkj]iVukA fcgkj]iVukA iFk fuekZ.k foHkkx]
fcgkj]iVukA
APPROVED CARRIAGE RATE OF MATERIALS (By TIPPER) Meeting Date 25.02.2021
Sl.No Ref.to Description Unit Quantity as per Project Categor Rate Amount Input_Re
M. f
Large Medium Small Large Medium Small
Loading and unloading of stone boulder / stone
1.01 A aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with
front end loader, dumping, turning for return
trip, excluding time for haulage and return trip

Unit = cum
A.Taking output = 5.5 Cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 6.633 6.633 6.633
capacity
iii) Maneuvering, reversing, dumping and Min 2.000 2.000 2.000
turning for return
iv) Waiting time, unforeseen contingencies Min 4.000 4.000 4.000
etc
Total Min 13.633 13.633 13.633
a) Machinery
Tipper-5.5 Cum capacity Hour 0.227 0.227 0.227 1,183.00 268.541 268.541 268.541 PM6004
Front end -loader 1 cum bucket capacity Hour 0.227 0.227 0.227 1,594.00 361.838 361.838 361.838 PM5003
Total Cost Excluding OH & CP 630.379 630.379 630.379
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 50.430 63.038 75.645
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 68.081 69.342 70.602
Total Cost for 5.5 cum = (a+b+c) Including OH 748.890 762.759 776.627
& CP
Unit Cost= (a+b+c)/5.5 Including OH & CP 136.162 138.683 141.205

Note : Unloading will be by tipping. Say 136.200 138.700 141.200


1.01 B Loading and unloading of stone boulder /
stone aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with
front end loader, dumping, turning for return
trip, excluding time for haulage and return trip

Unit = cum
Taking Output = 10.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 12.060 12.060 12.060
capacity
iii) Maneuvering, reversing, dumping and Min 2.000 2.000 2.000
turning for return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000

Total Min 19.060 19.060 19.060


a) Machinery
Tipper-10 Cum capacity Hour 0.318 0.318 0.318 2,121.00 674.478 674.478 674.478 PM6003
Front end-loder 1 cum bucket capacity Hour 0.318 0.318 0.318 1,594.00 506.892 506.892 506.892 PM5003
Total Cost Excluding OH & CP 1,181.37 1,181.37 1,181.37
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 94.510 118.137 141.764
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 127.588 129.951 132.313
Total Cost for 10 cum = (a+b+c)Including OH & 1403.468 1429.458 1455.448
CP
Unit Cost= (a+b+c)/10 Including OH & CP 140.347 142.946 145.545

Note : Unloading will be by tipping. Say 140.300 142.900 145.500


1.01 C. Loading and unloading of stone boulder /
stone aggregates / sand / kanker / moorum.

Placing tipper at loading point, loading with


front end loader, dumping, turning for return
trip, excluding time for haulage and return trip

Unit = cum
Taking Output = 14.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 2.1 cum bucket ca Min 8.029 8.029 8.029
iii) Maneuvering, reversing, dumping and Min 2.000 2.000 2.000
turning for return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 15.029 15.029 15.029
a) Machinery
Tipper-14 Cum capacity Hour 0.250 0.250 0.250 2415.000 603.750 603.750 603.750 PM6002
Front End loader 2.1 cum bucket capacity Hour 0.250 0.250 0.250 2588.000 647.000 647.000 647.000 PM5002
Total Cost Excluding OH & CP 1,250.750 1,250.750 1,250.750
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 100.060 125.075 150.090
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 135.081 137.583 140.084
Total Cost for 14 cum = (a+b+c)Including OH & 1,485.891 1,513.408 1,540.924
CP
Unit Cost= (a+b+c)/14 Including OH & CP 106.135 108.101 110.066

Note : Unloading will be by tipping. Say 106.100 108.100 110.100


1.01 D Loading and unloading of stone boulder /
stone aggregates / sand / kanker / moorum.

Placing tipper at loading point, loading with


front end loader, dumping, turning for return
trip, excluding time for haulage and return trip

Unit = cum
Taking Output = 18.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 3.1 cum bucket Min 6.996 6.996 6.996
capacity
iii) Maneuvering, reversing, dumping and Min 2.000 2.000 2.000
turning for return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000

Total Min 13.996 13.996 13.996


a) Machinery
Tipper-18 Cum capacity. Hour 0.233 0.233 0.233 2,772.00 645.876 645.876 645.876 PM6001
Front End loader 3.1 cum bucket capacity Hour 0.233 0.233 0.233 4,255.00 991.415 991.415 991.415 PM5001
Total Cost Excluding OH & CP 1,637.291 1,637.291 1,637.291
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 130.983 163.729 196.475
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 176.827 180.102 183.377
Total Cost for 18 cum = (a+b+c)Including OH & 1,945.102 1,981.122 2,017.143
CP
Unit Cost= (a+b+c)/18 Including OH & CP 108.061 110.062 112.063

Note : Unloading will be by tipping. Say 108.100 110.100 112.100


1.02 Ref. Loading and Unloading of Boulders by
to Manual Means
Morth. Unit = cum
Taking output = 10 Cum
a) Labour
Mate day 0.055 0.055 0.055 310.000 17.050 17.050 17.050 L-12
Mazdoor day 1.364 1.364 1.364 292.000 398.288 398.288 398.288 L-13
b) Machinery
Tipper-10 Cum capacity Hour 1.364 1.364 1.364 2,121.00 2893.044 2893.044 2893.044 PM6003
Total Cost Excluding OH & CP 3,308.38 3,308.38 3,308.38
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 264.671 330.838 397.006
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 357.305 363.922 370.539
Total Cost for10 cum=(a+b+c+d)Including OH 3930.358 4003.142 4075.927
& CP
Unit Cost=(a+b+c+d)/10 Including OH & CP 393.036 400.314 407.593

Note : Unloading will be by tipping. Say 393 400.3 407.6


1.03 Ref.to Loading and Unloading of Cement or Steel by
M. Manual Means and Stacking.
Unit = tonne
Taking Output = 18.00 tonne
a) Labour
Mate day 0.144 0.144 0.144 310.000 44.640 44.640 44.640 L-12
Mazdoor day 3.600 3.600 3.600 292.000 1051.200 1051.200 1051.200 L-13
b) Machinery
Truck-18 tonne capacity. Hour 3.600 3.600 3.600 2,121.00 7635.600 7635.600 7635.600 PM6003
Total Cost Excluding OH & CP 8731.440 8731.440 8731.440
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 698.515 873.144 1,047.773
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 942.996 960.458 977.921
Total Cost for 18 tonnes=(a+b+c+d)Including 10,372.951 10,565.042 10,757.134
OH & CP
Unit Cost=(a+b+c+d)/18 Including OH & CP 576.275 586.947 597.619

Say 576.300 586.900 597.600


Cost of Haulage Excluding Loading and
1.04 (i) A Unloading
i) A.Case-I : Surfaced Road.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load and lead 10
km=100. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 1,183.00 473.200 473.200 473.200 PM6004
Time taken for empty return trip. Hour 0.286 0.286 0.286 1,183.00 338.338 338.338 338.338 PM6004
Total Cost Excluding OH & CP 811.538 811.538 811.538
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 64.923 81.154 97.385
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 87.646 89.269 90.892
Total Cost for100 t.km = (a+b+c)Including OH 964.107 981.961 999.815
& CP
Rate per t.km= (a+b+c)/100 Including OH & 9.641 9.820 9.998
CP
Say 9.600 9.800 10.000
Cost of Haulage Excluding Loading and
Unloading

B i) Case-I : Surfaced Road .


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output =18tonnes load and lead10
km=180. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 18 tonne capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2121.000 848.400 848.400 848.400 PM6003
Time taken for empty return trip. Hour 0.286 0.286 0.286 2121.000 606.606 606.606 606.606 PM6003
Total Cost Excluding OH & CP 1,455.006 1,455.006 1,455.006
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 116.400 145.501 174.601
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 157.141 160.051 162.961
Total Cost for180 t.km = (a+b+c)Including OH 1,728.547 1,760.557 1,792.567
& CP
Rate per t.km= (a+b+c)/180 Including OH &
CP 9.603 9.781 9.959
Say 9.600 9.800 10.000
C Case-I : Surfaced Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output = 25 tonne load and lead
10km=250.t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 25 tonnes capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2415.000 966.000 966.000 966.000 PM6002
Time taken for empty return trip. Hour 0.286 0.286 0.286 2415.000 690.690 690.690 690.690 PM6002
Total Cost Excluding OH & CP 1656.690 1656.690 1656.690
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 132.535 165.669 198.803
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 178.923 182.236 185.549
Total Cost for250 t.km = (a+b+c)Including OH 1968.148 2004.595 2041.042
& CP
Rate per t.km= (a+b+c)/250 Including OH & 7.873 8.018 8.164
CP
Say 7.900 8.000 8.200
D Case-I : Surfaced Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output =32tonnes load and lead10km=
320. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 32 tonne capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2,772.00 1108.8 1108.8 1108.8 PM6001
Time taken for empty return trip. Hour 0.286 0.286 0.286 2,772.00 792.792 792.792 792.792 PM6001
Total Cost Excluding OH & CP 1,901.592 1,901.592 1,901.592
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 152.127 190.159 228.191
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 205.372 209.175 212.978
Total Cost for320 t.km = (a+b+c)Including OH 2,259.091 2,300.926 2,342.761
& CP
Rate per t.km= (a+b+c)/320 Including OH & 7.060 7.190 7.321
CP
Say 7.100 7.200 7.300
1.04 (ii) A .Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10 km=
100 t.km
Speed with load: 20 km/hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 1183.000 591.500 591.500 591.500 PM6004
Time taken for empty return trip. Hour 0.333 0.333 0.333 1183.000 393.939 393.939 393.939 PM6004
Total Cost Excluding OH & CP 985.439 985.439 985.439
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 78.835 98.544 118.253
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 106.427 108.398 110.369
Total Cost for100 t.km = (a+b+c)Including OH 1,170.702 1,192.381 1,214.061
& CP
Rate per t.km= (a+b+c)/100 Including OH & 11.707 11.924 12.141
CP
Say 11.700 11.900 12.100
1.04 (ii) B Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 18 tonnes load & lead10
km=180.t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage with load. Hour 0.500 0.500 0.500 2,121.00 1060.500 1060.500 1060.500 PM6003
Time taken for empty return trip. Hour 0.333 0.333 0.333 2,121.00 706.293 706.293 706.293 PM6003
Total Cost Excluding OH & CP 1,766.793 1,766.793 1,766.793
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 141.343 176.679 212.015
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 190.814 194.347 197.881
Total Cost for180 t.km = (a+b+c)Including OH 2,098.950 2,137.820 2,176.689
& CP
Rate per t.km= (a+b+c)/180 Including OH & 11.661 11.877 12.093
CP
Say 11.700 11.900 12.100
1.04 (ii) C Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 25 tonnes load & lead10 km
=250. t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 25 tonnes capacity.
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2,415.00 1207.500 1207.500 1207.500 PM6002
Time taken for empty return trip. Hour 0.333 0.333 0.333 2,415.00 804.195 804.195 804.195 PM6002
Total Cost Excluding OH & CP 2,011.695 2,011.695 2,011.695
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 160.936 201.170 241.403
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 217.263 221.286 225.310
Total Cost for250 t.km = (a+b+c)Including OH 2389.894 2434.151 2478.408
& CP
Rate per t.km= (a+b+c)/250 Including OH & 9.560 9.737 9.914
CP
Say 9.600 9.700 9.900
1.04 (ii) D Case-II : Unsurfaced Gravelled Road.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 32tonnes load & lead 10 km=
320. t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2,772.00 1386 1386 1386 PM6001
Time taken for empty return trip. Hour 0.333 0.333 0.333 2,772.00 923.076 923.076 923.076 PM6002
Total Cost Excluding OH & CP 2,309.076 2,309.076 2,309.076
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 184.726 230.908 277.089
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 249.380 253.998 258.617
Total Cost for320 t.km = (a+b+c)Including OH 2,743.182 2,793.982 2,844.782
& CP
Rate per t.km= (a+b+c)/320 Including OH & 8.572 8.731 8.890
CP
Say 8.600 8.700 8.900
1.04 (iii) A Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10km= 100
t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 1.000 1.000 1.000 1,183.00 1183.000 1183.000 1183.000 PM6004
Time taken for empty return trip. Hour 0.667 0.667 0.667 1,183.00 789.061 789.061 789.061 PM6004
Total Cost Excluding OH & CP 1,972.061 1,972.061 1,972.061
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 157.765 197.206 236.647
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 212.983 216.927 220.871
Total Cost for100 t.km = (a+b+c)Including OH 2,342.808 2,386.194 2,429.579
& CP
Rate per t.km= (a+b+c)/100 Including OH & 23.428 23.862 24.296
CP
Say 23.400 23.900 24.300
1.04 (iii) B iii) B.Case-III : Katcha Track and Track in river
bed / nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output18 tonnes load
&lead10km=180.00 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2,121.00 2121.000 2121.000 2121.000 PM6003
Time taken for empty return trip. Hour 0.667 0.667 0.667 2,121.00 1414.707 1414.707 1414.707 PM6003
Total Cost Excluding OH & CP 3,535.707 3,535.707 3,535.707
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 282.857 353.571 424.285
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 381.856 388.928 395.999
Total Cost for180 t.km = (a+b+c)Including OH 4,200.420 4,278.205 4,355.991
& CP
Rate per t.km= (a+b+c)/180 Including OH & 23.336 23.768 24.200
CP
Say 23.300 23.800 24.200
1.04 (iii) C Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output25Tonnes load &lead10
km=250.t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 25 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2,415.00 2415.000 2415.000 2415.000 PM6002
Time taken for empty return trip. Hour 0.667 0.667 0.667 2,415.00 1610.805 1610.805 1610.805 PM6002
Total Cost Excluding OH & CP 4,025.805 4,025.805 4,025.805
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 322.064 402.581 483.097
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 434.787 442.839 450.890
Total Cost for250 t.km = (a+b+c)Including OH 4,782.656 4,871.224 4,959.792
& CP
Rate per t.km= (a+b+c)/250 Including OH & 19.131 19.485 19.839
CP
Say 19.100 19.500 19.800
1.04 (iii) D Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output32 tonnes load &lead 1 km= 320.
t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2772.000 2772.000 2772.000 2772.000 PM6001
Time taken for empty return trip Hour 0.667 0.667 0.667 2772.000 1848.924 1848.924 1848.924 PM6001
Total Cost Excluding OH & CP 4,620.924 4,620.924 4,620.924
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 369.674 462.092 554.511
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 499.060 508.302 517.543
Total Cost for320 t.km = (a+b+c)Including OH 5489.658 5591.318 5692.978
& CP
Rate per t.km= (a+b+c)/320 Including OH & 17.155 17.473 17.791
CP
Say 17.200 17.500 17.800
1.04 (iv) Case-IV : Katcha Track in hilly area.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10km=
100. t.km
Speed with load: 5 km / hour
Speed while returning empty: 7 km / hour
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 2.000 2.000 2.000 1,183.00 2366.000 2366.000 2366.000 PM6004
Time taken for empty return trip. Hour 1.429 1.429 1.429 1,183.00 1690.507 1690.507 1690.507 PM6004
Total Cost Excluding OH & CP 4,056.507 4,056.507 4,056.507
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 324.52056 405.6507 486.78084
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 438.102756 446.21577 454.328784
Total Cost for100 t.km = (a+b+c)Including OH 4,819.130 4,908.373 4,997.617
& CP
Rate per t.km= (a+b+c)/100 Including OH & 48.191 49.084 49.976
CP
Say 48.200 49.100 50.000
1.04 (v) Case-V : Transit Mixture
Haulage of Concrete by transit mixture
excluding cost of loading, unloading and
stacking.
Unit = t.km
Taking Output 15Tonnes load & lead 10km=
150 t.km
Speed with load : 20 km / hour
Speed while returning empty: 30 km / hour
a) Machinery
i) Transit Mixture 6 cum capacity.
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2,218.00 1109.000 1109.000 1109.000 PM34001

Hour 0.333 0.333 0.333 2,218.00 738.594 738.594 738.594 PM34001


Time taken for empty return trip.
Total Cost Excluding OH & CP 1,847.594 1,847.594 1,847.594
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 147.80752 184.7594 221.71128
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 199.540152 203.23534 206.930528
Total Cost for150 t.km = (a+b+c)Including OH 2,194.942 2,235.589 2,276.236
& CP
Rate per t.km= (a+b+c)/150 Including OH & 14.633 14.904 15.175
CP
Say 14.600 14.900 15.200
1.05 Hand Broken Stone Aggregates 63 mm
nominal size
Supply of quarried stone, hand breaking into
coarse aggregate 63 mm nominal size (passing
80 mm and retained on 50 mm sieve) and
stacking as directed

Unit = cum
Taking Output = 1.00 cum
a) Labour
Mate day 0.0600 0.0600 0.0600 310.000 18.600 18.600 18.600 L-12
Mazdoor day 1.500 1.500 1.500 292.000 438.000 438.000 438.000 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.1000 1.1000 1.1000 351.360 386.496 386.496 386.496 M-001
Total Cost Excluding OH & CP 843.096 843.096 843.096
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 67.448 84.310 101.172
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 91.054 92.741 94.427
Total Cost for1cum = (a+b+c+d)Including OH & 1,001.598 1,020.146 1,038.694
CP
Rate per cum= (a+b+c+d) Including OH & CP Say 1,001.600 1,020.100 1,038.700

Crushing of stone aggregates (Nominal size)


1.06
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and
secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of
different nominal size.

(i) 1.Crushing Pattern 40 mm (tonne)- Cost


Distribution 28.98 %
Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.000 99.200 99.200 99.200 L-12
Mazdoor(Skilled) day 2.000 2.000 2.000 370.000 740.000 740.000 740.000 L-15
Mazdoor day 6.000 6.000 6.000 292.000 1752.000 1752.000 1752.000 L-13
b) Material
Stone Boulder of size 150 mm and below at cum 750.000 750.000 750.000 351.36 263520.000 263520.000 263520.000 M-001
Cruser Plant
c) Machinery
Integrated stone crusher of 250 TPH including Hour 6.000 6.000 6.000 13,431.00 80586.000 80586.000 80586.000 PM16001
belt conveyor and vibrating screens
Generator 725 KVA Hour 6.000 6.000 6.000 13,148.00 78888.000 78888.000 78888.000 PM22001

Front end loader 3.1 cum bucket capacity at Hour 5.515 5.515 5.515 4,255.00 23466.325 23466.325 23466.325 PM5001
quarry and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,415.00 13318.725 13318.725 13318.725 PM6002

Tipper 14 cum capacity for transportation within t.km 1,125.000 1,125.000 1,125.000 6.63 7455.105 7455.105 7455.105 1.04(i) C
1 km
d) Total Cost for 750 cum(Excluding OH & 469,825.36 469,825.36
CP)
e) Crushing pattern 40mm(tonne) tonne 22.71% 22.71% 22.71% 255.488
f) % Cost distribution={(d)x(f)/e)x1.5} cum 28.98% 28.98% 28.98% 0.2898 #VALUE! 799.38 799.38
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #VALUE! 79.938 95.926
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #VALUE! 87.932 89.531
i) Total Cost for1cum = (f+g+h) Including OH & #VALUE! 967.255 984.841
CP
Rate per cum= (f+g+h) Including OH & CP Say #VALUE! 967.300 984.800

(ii) Crushing of stone aggregates (Nominal size)

2.Crushing Pattern 20 mm (tonne)- Cost


Distribution 31.95 %
d) Total Cost for 750 cum(Excluding OH & 469,825.36 469,825.36
CP)
e) Crushing pattern 20mm(tonne) tonne 23.00% 258.75
f) % Cost distribution={(d)x(f)/e)x1.5} cum 31.95% 0.3195 #VALUE! 870.20 870.20
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #VALUE! 87.020 104.424
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #VALUE! 95.722 97.462
i)Total Cost for1cum =(f+g+h)Including OH& #VALUE! 1,052.940 1,072.084
CP
Rate per cum= (f+g+h) Including OH & CP Say #VALUE! 1,052.900 1,072.100

Crushing of stone aggregates (Nominal size)


(iii)
3.Crushing Pattern 10 mm (tonne)- Cost
Distribution 30.75 %
d) Total Cost for 750 cum(Excluding OH & 469,825.36 469,825.36
CP)
e) Crushing pattern 20mm(tonne) tonne 25.86% 290.925
f) % Cost distribution={(d)x(f)/e)x1.5} cum 30.75% 0.3075 #VALUE! 744.89 744.89
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #VALUE! 74.489 89.387
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #VALUE! 81.938 83.428
i) Total Cost for1cum = (f+g+h)Including OH & #VALUE! 901.316 917.704
CP
Rate per cum= (f+g+h) Including OH & CP #VALUE! 901.300 917.700

Crushing of stone aggregates (Nominal size)


(iv)
4 Crushing Pattern dust (tonne)- Cost
Distribution 08.32 %
d) Total Cost for 750 cum(Excluding OH & 469,825.36 469,825.36
CP)
e) Crushing pattern dust (tonne) tonne 28.43% 319.838
f) % Cost distribution={(d)x(f)/e)x1.5} cum 8.32% 0.0832 #VALUE! 183.32 183.32
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #VALUE! 18.332 21.999
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #VALUE! 20.166 20.532
i) Total Cost for1cum = (f+g+h)Including OH & #VALUE! 221.823 225.856
CP
Rate per cum= (f+g+h) Including OH & CP #VALUE! 221.800 225.900

Note: The average density of 1.5 tonne/cum is only a reference density in this Data Book.
1.07 Crushing of stone aggregates (GSB Crusher
Run)
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and
secondary crushing units, belt conveyor and
vibrating screens to obtain crusher run (all in
aggregate) for GSB.

Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.000 99.200 99.200 99.200 L-12
Mazdoor (Skilled) day 2.000 2.000 2.000 370.000 740.000 740.000 740.000 L-15
Mazdoor day 6.000 6.000 6.000 292.000 1752.000 1752.000 1752.000 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750 750 750 351.36 263520.000 263520.000 263520.000 M-001
c) Machinery
Integrated stone crusher of 250 TPH including Hour 4.615 4.615 4.615 13,431.00 61984.065 61984.065 61984.065 PM16001
belt conveyor and vibrating screens (for
producing crusher run production capacity will
increas by 30%)

Generator 725 KVA Hour 4.615 4.615 4.615 13,148.00 60678.020 60678.020 60678.020 PM22001

Front end loader 3.1 cum bucket capacity at Hour 5.515 5.515 5.515 4,255.00 23466.325 23466.325 23466.325 PM5001
quarry and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,415.00 13318.725 13318.725 13318.725 PM6002
Tipper 14 cum capacity for transportation within t.km 1,125.00 1,125.00 1,125.00 6.63 7455.105 7455.105 7455.105 1.04(i) C
1 km
Total Cost Excluding OH & CP 433,013.440 433,013.440 433,013.440
d) Overheadson (a+b+c) (@ 8%) (@ 10%) (@ 12%) 34641.075 43301.344 51961.613
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 46,765.45 47,631.48 48,497.51
Cost for 900 cum =(a+b+c+d+e) 514,419.97 523,946.26 533,472.56
Rate per cum =(a+b+c+d+e)/900( Including Say 571.60 582.20 592.70
OH & CP)
Note: Considering Crushed volume will be 1.2 times the volume of boulder.
Note:-1. For local transportation , carriage rate will be given as per provision of different Capacity of vehicle in Large/Medium/Small Projects in
rate analysis of particular item of any Chapter.

Note:-2.
Except Note 1, for transportation/carriage of Stone Aggregate/Stone Boulder/Moorum/Bitumen/Steel/Cement and Other
Construction Materials,Loading-Unloading charges&Haulage charges will be allowed by 18 Cum Capacity tipper(18 tonne
Capacity Truck in case of loading-unloading of Cement /Steel / Bitumen by manual means) and 32 tonne Capacity tipper
respectively only for all types of Projects(Large/Medium/Small) except in cases / circumstances where any limitation/restriction
regarding capacity of Vehicle has been imposed by competent Authority(District/State). Incase of restriction, rate of allowed
capacity of vehicle will be given.
Note:-3. In case of Loading &Unloading of Boulders by Manual means, loading-unloading charges will be allowed by 10Cum
Capacity tipper.
Note:-4. Carriage of material will be done by shortest rout.

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k
lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k
Hkou fuekZ.k foHkkx] xzkeh. dk;Z foHkkx] y?kq ty lalk/ku foHkkx]
fcgkj]iVukA fcgkj]iVukA fcgkj]iVukA

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuwlwfpr nj fu/kZkj.k
lfefr&lg&eq[; vfHk;ark ¼vlSñ½ lfefr&lg&eq[; vfHk;ark ¼fo/kqr½] lfefr&lg&vfHk;ark izeq[k rduhdh
fcgkj LVsV ikoj gksfYMx Hkou fuekZ.k foHkkx] ijh{kd dks"kkax] fuxjkuh foHkkx]
dEiuh fyñ] fcgkj]iVukA fcgkj]iVukA fcgkj] iVukA
lnL;] lnL;] la;kstd]
jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuwlwfpr nj fu/kZkj.k
lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k ¼eq[;ky;½ lfefr&lg&vfHk;ark izeq[k¼eq[;ky;½
yksd LokLF; vfHk;a=.k foHkkx] ty lalk/ku foHkkx iFk fuekZ.k foHkkx
fcgkj]iVukA fcgkj]iVukA fcgkj] iVukA

APPROVED CARRIAGE RATE OF MATERIALS (By TRACTOR) Date 25.02.2021


Sr. Ref.
No. to
Rate Amount Remarks/
MoR Description Unit Quantity as per Project Category
(Rs`) (Rs) Input ref.
TH
Spec.
1.1 Loading and Unloading of Stone Boulder/ cum
Stone aggregates/Sand /Kanker/Moorum Large Medium Small Large Medium Small

Placing Tractor at loading point, loading with


front end loader, dumping, turning for return
trip, excluding time for haulage and return trip
Unit = cum
Taking output = 2.25 cum
Time required for
i) Positioning of Tractor at loading point 1 Min
ii) Loading by front end loader 1 cum 5 Min
bucket capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and 0 Min
turning for return
iv) Waiting time, unforeseen 0 Min
contingencies etc
Total 6 Min
a) Labour
Mate day 0.050 0.050 0.050 310.00 15.500 15.500 15.500 L-12
Mazdoor for loading and unloading day 0.310 0.310 0.310 292.00 90.520 90.520 90.520 L-13
b) Machinery
Tractor 3.60 tonnes capacity hour 0.100 0.100 0.100 612.00 61.200 61.200 61.200 PM120
01
Front end-loader 1 cum bucket capacity hour 0.083 0.083 0.083 1594.00 132.302 132.302 132.302 PM500
3
Total Cost Excluding OH & CP 299.52 299.52 299.52
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 23.962 29.952 35.943
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 32.348 32.947 33.546
Total Cost for2.25 cum = (a+b+c+d)Including 355.832 362.422 369.011
OH & CP
Rate per cum= (a+b+c+d)/2.25 Including OH 158.148 161.076 164.005
& CP
Note Unloading will be done manually. say 158.100 161.100 164.000
1.2 Loading and Unloading of Boulders by
Manual Means
Unit = cum
Taking output = 2.25 cum
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.300 9.300 9.300 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.240 210.240 210.240 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.310 0.310 0.310 612.00 189.720 189.720 189.720 PM120
01
Total Cost Excluding OH & CP 409.260 409.260 409.260
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 32.741 40.926 49.111
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 44.200 45.019 45.837
Total Cost for2.25 cum = (a+b+c+d)Including 486.201 495.205 504.208
OH & CP
Rate per cum= (a+b+c+d)/2.25 Including OH 216.089 220.091 224.093
& CP
Say 216.100 220.100 224.100
Note Unloading will be done manually.
1.3 Loading and Unloading of Cement or Steel by
Manual Means and Stacking.
Unit = tonne
Taking output = 3.60 tonnes
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.300 9.300 9.300 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.240 210.240 210.240 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.720 0.720 0.720 612.00 440.640 440.640 440.640 #REF!
Total Cost Excluding OH & CP 660.180 660.180 660.180
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 52.814 66.018 79.222
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 71.299 72.620 73.940
Total Cost for3.6 tonnes= (a+b+c+d)Including 784.294 798.818 813.342
OH & CP
Rate per tonne= (a+b+c+d)/3.6 Including OH 217.859 221.894 225.928
& CP
say 217.900 221.900 225.900
1.4 (i) Cost of Haulage Excluding Loading and
Unloading
Haulage of materials by Tractor excluding cost
of loading, unloading and stacking.
Unit = t.km
Taking output 3.60 tonnes load and lead 10 km
= 36.0 t.km
Surfaced Road
Speed with load : 15 km / hour.
Speed while Returning empty :25 km / hour.
a) Machinery.
Tractor 3.6 tonne capacity
Time taken for onward haulage with load hour 0.667 0.667 0.667 612.00 408.204 408.204 408.204 PM12001

Time taken for empty return trip. hour 0.400 0.400 0.400 612.00 244.800 244.800 244.800 PM12001

Total Cost Excluding OH & CP 653.004 653.004 653.004


b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 52.240 65.300 78.360
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 70.524 71.830 73.136
Total Cost for36 t.km = (a+b+c)Including OH & 775.769 790.135 804.501
CP
Rate per t.km= (a+b+c)/36 Including OH & 21.549 21.948 22.347
CP

say 21.500 21.900 22.300


(ii) Unsurfaced Graveled Road
Speed with load: 12 km / hour
Speed for empty return trip :20 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage with load hour 0.833 0.833 0.833 612.00 509.796 509.796 509.796 PM12001
Time taken for empty return trip hour 0.500 0.500 0.500 612.00 306.000 306.000 306.000 PM12001
Total Cost Excluding OH & CP 815.80 815.80 815.80
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 65.264 81.580 97.896
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 88.106 89.738 91.369
Total Cost for36 t.km = (a+b+c)Including OH & 969.166 987.113 1,005.061
CP
Rate per t.km= (a+b+c)/36 Including OH & 26.921 27.420 27.918
CP
26.90 27.40 27.90
1.4 (iii) Katcha Track and Track in River Bed/Nallah
Bed and Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage hour 1.000 1.000 1.000 612.00 612.000 612.000 612.000 PM12001
Time taken for empty return trip hour 0.667 0.667 0.667 612.00 408.204 408.204 408.204 PM12001
Total Cost Excluding OH & CP 1020.20 1020.20 1020.20
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 81.616 102.020 122.424
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 110.182 112.222 114.263
Total Cost for36 t.km = (a+b+c)Including OH & 1,212.002 1,234.447 1,256.891
CP
Rate per t.km= (a+b+c)/36 Including OH & 33.667 34.290 34.914
CP
say 33.700 34.300 34.900
oSls LFky tgk¡ ij Truck ,oa Tipper ds }kjk <qykbZ fd;k tkuk laHko ugha gS rFkk Tractor ls <qykbZ economical gks dsoy oSls gh
Note:- LFkyksa ds fy, Tractor ls <qykbZ dk izko/kku fd;k tk;A

lnL;] lnL;]
lnL;] jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k
jkT; Lrjh; vuqlwfpr nj fu/kZkj.k lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k
lfefr&lg&vfHk;ark izeq[k xzkeh. dk;Z foHkkx] y?kq ty lalk/ku foHkkx]
Hkou fuekZ.k foHkkx] fcgkj]iVukA fcgkj]iVukA
fcgkj]iVukA

lnL;]
jkT; Lrjh; vuqlwfpr nj fu/kZkj.k lnL;] lnL;]
lfefr&lg&eq[; vfHk;ark ¼vlSñ½ jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuwlwfpr nj fu/kZkj.k
fcgkj LVsV ikoj gksfYMx lfefr&lg&eq[; vfHk;ark ¼fo/kqr½] lfefr&lg&vfHk;ark izeq[k rduhdh
dEiuh fyñ] fcgkj]iVukA Hkou fuekZ.k foHkkx] ijh{kd dks"kkax] fuxjkuh foHkkx]
fcgkj]iVukA fcgkj] iVukA

lnL;]
jkT; Lrjh; vuqlwfpr nj fu/kZkj.k lnL;] la;kstd]
lfefr&lg&vfHk;ark izeq[k jkT; Lrjh; vuqlwfpr nj fu/kZkj.k jkT; Lrjh; vuwlwfpr nj fu/kZkj.k
yksd LokLF; vfHk;a=.k foHkkx] lfefr&lg&vfHk;ark izeq[k ¼eq[;ky;½ lfefr&lg&vfHk;ark izeq[k¼eq[;ky;½
fcgkj]iVukA ty lalk/ku foHkkx iFk fuekZ.k foHkkx
fcgkj]iVukA fcgkj] iVukA
114.61
118.14
89.34
90.96
485.08

8.12
8.08

6.63
5.94

5.94

9.85
9.82
8.05

7.22
19.72

19.64
16.10

14.44
12.32
Approved Input of Labour wages, Overhead &Lead for the preparation of Schedule of Rate2021-
2022 in prescribed format of updated MORT&H Standard Data Book 2019
(2nd Revision) Date :-25.02.2021
S.No. Description of Labour Unit Approved Rate
1 2 3 4
L-01 Blacksmith (IInd class) day 351
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 394
L-03 Blaster (Stone cutter) day 485
L-04 Carpenter I Class day 394
L-05 Chiseller (Head Mazdoor) day 451
L-06 Driller (Jumper) day 304
L-07 Diver day 451
L-08 Fitter day 351
L-09 Mali day 304
L-10 Mason (IInd class) day 351
L-11 Mason (Ist class) day 394
L-12 Mate / Supervisor day 310
L-13 Mazdoor day 292
L-14 Mazdoor/Dresser (Semi Skilled) day 304
L-15 Mazdoor/Dresser/Sinker (Skilled) day 370
L-16 Medical Officer day 451
L-17 Operator(grouting) day 451
L-18 Painter I class day 373
L-19 Para medical personnel day 451
L-20 Heavy Plant Operator day 451
L-21 Light Plant Operator. day 370
L-22 Heavy Vehicle Driver. day 420
L-23 Light Vehicle Driver. day 370
L-24 Helper day 292
L-25 Black smith day 351
Overhead
Overheads for Road Works(Large) 0.08 (@ 8%)
Overheads for Road Works(Medium) 0.10 (@ 10%)
Overheads for Road Works (Small) 0.12 (@ 12%)
Contractor's profit for Road Works 0.10 (@ 10%)
Overheads for New / Widening of Bridge/Structure
0.20 (@ 20%)
Works
Overheads for Rehabilitation of Bridge /Structure 0.30 (@ 30%)
Contractor's profit for Bridge Works 0.10 (@ 10%)
Over heads for Road Tunnel Works 0.25 (@ 25%)
Contractor's profit for Tunnel Works 0.10 (@ 10%)
Lead
L1 Lead from Mixing Plant to working site 1.0 km
L2 Lead for E/W borrow area to site 1.0 km

lnL;] lnL;]
lnL;]
jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj
jkT;Lrjk; vuqlwfpr nj fu/kZkj.k
fu/kZkj.k lfefr&lg&vfHk;ark fu/kZkj.k
lfefr&lg&vfHk;ark izeq[k
lfefr&lg&vfHk;ark
y?kq ty lalk/ku foHkkx]
izeq[k]Hkou fuekZ.k foHkkx] izeq[k]xzkeh.k dk;Z
fcgkj]iVukA
foHkkx]
fcgkj]iVukA fcgkj]iVukA

lnL;] lnL;] lnL;]


jkT; Lrjh; vuqlwfpr nj jkT; Lrjh; vuqlwfpr nj jkT;Lrjh; vuqlwfpr nj fu/kZkj.k
fu/kkZj.k lfefr&lg&eq[; vfHk;ark fu/kkZj.k lfefr&lg&vfHk;ark izeq[k
lfefr&lg&eq[; rduhdh
¼vlSñ½fcgkj LVsV ikoj gksfYMax vfHk;ark ijh{kd dks"kkax]fuxjkuh
¼fo/kqr½]Hkou fuekZ.k foHkkx]
dEiuh fyñ fcgkj]iVukA foHkkx]fcgkj]iVukA fcgkj]iVukA

lnL;] lnL;]
jkT;Lrjh; vuqlwfpr nj jkT;Lrjh; vuqlwfpr nj
fu/kZj.k lfefr&lg vfHk;ark fu/kZkj.k lfefr
la;kstd]
&lg&vfHk;ark
jkT;Lrjh; vuqlwfpr nj fu/kZkj.k
izeq[k yksd LokLF; vfHk;a=.k izeq[k]eq[;ky;]ty
lfefr&lg&vfHk;ark izeq[k
lalk/ku
¼eq[;ky;½ iFkfuekZ.k foHkkx]
foHkkx] fcgkj]iVukA foHkkx] fcgkj]iVukA
fcgkj]iVukA
Proposed Input of Labour wages, Overhead &Lead for the preparation of Schedule of Rate2021-
2022 in prescribed format of updated MORT&H Standard Data Book 2019
(2nd Revision)
S.No. Description of Labour Unit Proposed Rate

1 2 3 4
L-01 Blacksmith (IInd class) day 351
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 394
L-03 Blaster (Stone cutter) day 485

L-04 Carpenter I Class day 394

L-05 Chiseller (Head Mazdoor) day 451


L-06 Driller (Jumper) day 304
L-07 Diver day 451
L-08 Fitter day 351
L-09 Mali day 304
L-10 Mason (IInd class) day 351
L-11 Mason (Ist class) day 394
L-12 Mate / Supervisor day 310

L-13 Mazdoor day 292

L-14 Mazdoor/Dresser (Semi Skilled) day 304


L-15 Mazdoor/Dresser/Sinker (Skilled) day 370
L-16 Medical Officer day 451
L-17 Operator(grouting) day 451
L-18 Painter I class day 373
L-19 Para medical personnel day 451
L-20 Heavy Plant Operator day 451
L-21 Light Plant Operator. day 370
L-22 Heavy Vehicle Driver. day 420

L-23 Light Vehicle Driver. day 370


L-24 Helper day 292
L-25 Black smith day 351
Overhead
Overheads for Road Works(Large) 0.08 (@ 8%)
Overheads for Road Works(Medium) 0.10 (@ 10%)
Overheads for Road Works (Small) 0.12 (@ 12%)
Contractor's profit for Road Works 0.10 (@ 10%)
Overheads for New / Widening of Bridge/Structure
0.20 (@ 20%)
Works

Overheads for Rehabilitation of Bridge /Structure 0.30 (@ 30%)


Contractor's profit for Bridge Works 0.10 (@ 10%)
Over heads for Road Tunnel Works 0.25 (@ 25%)
Contractor's profit for Tunnel Works 0.10 (@ 10%)
Lead
L1 Lead from Mixing Plant to working site 1.0 km
L2 Lead for E/W borrow area to site 1.0 km
mDr INPUT dks State Level SOR dfeVh dh cSBd esa fopkj&foe'Zk gsrq j[kk tk kdrk gSA

A.E. E.E. S.E.


Remarks

6
Similar to Blacksmith,Sl.No-23
Similar to Head Blacksmith,Sl.No-24
Similar to Blaster,Sl.No-54.

Similar to Head Carpenter, ,Sl.No-18.

Similar to Highly Skilled,Sl.No-72.


Similar to Semi Skilled,Sl.No-70.
Similar to Highly Skilled,Sl.No-72.
Similar to Fitter Grade II,Sl.No-08.
Similar to Semi Skilled,Sl.No-70.
Similar to Mason,Sl.No-30.
Similar to Head Mason,Sl.No-31.
Similar to Mate Sl.No-63.

Similar to Unskilled Labour,Sl.No-01.

Similar to Semi Skilled,Sl.No-70.


Similar to Skilled,Sl.No-71.
Similar to Highly Skilled,Sl.No-72.
Similar to Highly Skilled,Sl.No-72.
Similar to Painter Gr-I,Sl.No-55.
Similar to Highly Skilled,Sl.No-72.
Similar to Highly Skilled,Sl.No-72.
Similar to Skilled,Sl.No-71.
Similar to Truck Driver ,Sl.No-L-49.

Similar to Car Jeep Driver ,Sl.No L-50.


Similar to Helper.No-05.
Similar to Blacksmith,Sl.No-23.
Additional Hire & running charges for shifting of hour 3.000 3.000 3.000 871.00 2613.00 2613.00 2613.00 PM67001
crane (rock breaking time) with grab bucket of
0.75 cum capacity and accessories.

c) Overhead charges @ on (a+b) (@ 20%) (@ 20%) (@ 20%) 39589.65 39589.65 39589.65


d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 23753.79 23753.79 23753.79
Rate per metre = (a+b+c+d) 261291.67 261291.67 261291.67
Say 261291.70 261291.70 261291.70
12.19 1200 Sinking of Twin D Type well (other than
pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per
drawing and technical specifications. Depth of
sinking is reckoned from bed level.

Unit=Running Meter.
Taking output=1m
Dimensions of well-12m.
Overall length=12m
Overall width=6m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/ hour.
a) Labour
Mate day 0.200 0.200 0.200 310.00 62.00 62.00 62.00 L-12
Sinker ( skilled ) day 1.250 1.250 1.250 370.00 462.50 462.50 462.50 L-15
Sinking helper ( semi-skilled ) day 3.750 3.750 3.750 304.00 1140.00 1140.00 1140.00 L-14
b) Machinery
Hire & running charges of crane with grab hour 5.500 5.500 5.500
bucket of 0.75 cum capacity and
accessories.
871.00 4790.50 4790.50 4790.50 PM67001
Consumables in sinking @10 percent of
(b)
479.05 479.05 479.05
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%) (@ 20%) 1386.81 1386.81 1386.81
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 832.09 832.09 832.09
Rate per metre = (a+b+c+d) 9152.95 9152.95 9152.95
Summary of Analysis
CHAPTER 1
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Rate as per Project Category.
M Large Medium Small
1.01 A Loading and unloading of stone boulder / stone aggregates /
sand / kanker / moorum.
(Tipper-5.5cum capacity)
Placing tipper at loading point, loading with front end loader, cum 136.20 138.70 141.20
dumping, turning for return trip, excluding time for haulage and
return trip

1.01 B Loading and unloading of stone boulder / stone aggregates /


sand / kanker / moorum.
(Tipper-10.00 cum capacity)
Placing tipper at loading point, loading with front end loader, cum 140.30 142.90 145.50
dumping, turning for return trip, excluding time for haulage and
return trip

1.01 C. Loading and unloading of stone boulder / stone aggregates /


sand / kanker / moorum.
(Tipper-14.00 cum capacity)
Placing tipper at loading point, loading with front end loader, cum 106.10 108.10 110.10
dumping, turning for return trip, excluding time for haulage and
return trip

1.01 D Loading and unloading of stone boulder / stone aggregates /


sand / kanker / moorum.
(Tipper-18.00 cum capacity)
Placing tipper at loading point, loading with front end loader, cum 108.10 110.10 112.10
dumping, turning for return trip, excluding time for haulage and
return trip

1.02 Ref.to Loading and Unloading of Boulders by Manual Means .


M. (Tipper-10 cum capacity.) cum 393.00 400.30 407.60

1.03 Ref.to Loading and Unloading of Cement or Steel by Manual


M. Means and Stacking. tonne 576.30 586.90 597.60
(Truck- 10 Tonne capacity.)

1.04 (i) A Cost of Haulage Excluding Loading


and Unloading
i) A.Case-I : Surfaced Road.
Haulage of materials by tipper (10 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 9.60 9.80 10.00

B i) Case-I : Surfaced Road .


Haulage of materials by tipper (18 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 9.60 9.80 10.00

C Case-I : Surfaced Road .


Haulage of materials by tipper (25 tonne capacity) excluding
cost of loading, unloading and stacking. t.km 7.90 8.00 8.20
Summary of Analysis
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Rate as per Project Category.
M Large Medium Small
D Case-I : Surfaced Road .
Haulage of materials by tipper (32 tonne capacity ) excluding
cost of loading, unloading and stacking. t.km 7.10 7.20 7.30

1.04 (ii) A .Case-II : Unsurfaced Gravelled Road .


Haulage of materials by tipper(10 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 11.70 11.90 12.10

1.04 (ii) B Case-II : Unsurfaced Gravelled Road .


Haulage of materials by tipper (18 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 11.70 11.90 12.10

1.04 (ii) C Case-II : Unsurfaced Gravelled Road .


Haulage of materials by tipper (25 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 9.60 9.70 9.90

1.04 (ii) D Case-II : Unsurfaced Gravelled Road.


Haulage of materials by tipper(32 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 8.60 8.70 8.90

1.04 (iii) A Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper(10 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 23.40 23.90 24.30

1.04 (iii) B .Case-III : Katcha Track and Track in river bed / nallah
bed and choe bed.
Haulage of materials by tipper (18 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 23.30 23.80 24.20

1.04 (iii) C Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper(25 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 19.10 19.50 19.80

1.04 (iii) D Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper(32 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 17.20 17.50 17.80

1.04 (iv) Case-IV : Katcha Track in hilly area.


Haulage of materials by tipper (10 tonne capacity) excluding
cost of loading, unloading and stacking. t.km. 48.20 49.10 50.00

1.04 (v) Case-V : Transit Mixture


Haulage of Concrete by Transit mixture (6.cum capacity)
excluding cost of loading, unloading and stacking. t.km. 14.60 14.90 15.20
Summary of Analysis
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Rate as per Project Category.
M Large Medium Small
1.05 Hand Broken Stone Aggregates 63 mm
nominal size
Supply of quarried stone, hand breaking into coarse aggregate
63 mm nominal size (passing 80 mm and retained on 50 mm cum 1001.60 1020.10 1038.70
sieve) and stacking as directed

1.06 Crushing of stone aggregates (Nominal size)


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 250 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of different
nominal size.

(i) 1. Crushing Pattern 40 mm (tonne)- Cost Distribution 28.98


cum 949.70 967.30 984.80
%

(ii) Crushing of stone aggregates (Nominal size)


2. Crushing Pattern 20 mm (tonne)- Cost Distribution 31.95
cum 1033.80 1052.90 1072.10
%

(iii) Crushing of stone aggregates (Nominal size)


3. Crushing Pattern 10 mm (tonne)- Cost Distribution 30.75
cum 884.90 901.30 917.70
%

(iv) Crushing of stone aggregates (Nominal size)


4. Crushing Pattern dust (tonne)- Cost Distribution 08.32
cum 217.80 221.80 225.90
%

1.07 Crushing of stone aggregates (GSB Crusher Run)


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 250 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and cum 571.60 582.20 592.80
vibrating screens to obtain crusher run (all in aggregate) for
GSB.
Summary of Analysis
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Rate as per Project Category.
M Large Medium Small
Summary of Analysis
Summary of Analysis
Summary of Analysis
Summary of Analysis
CHAPTER 1

CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Loading and unloading of stone boulder / stone aggregates /
sand / kanker / moorum.
1.01 A
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time for
haulage and return trip

Unit = cum
A.Taking output = 5.5 Cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket capacity Min 6.633 6.633 6.633
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.633 13.633 13.633
a) Machinery
Tipper-5.5 Cum capacity Hour 0.227 0.227 0.227 1,183.00 268.54 268.54 268.54 PM6004
Front end -loader 1 cum bucket capacity Hour 0.227 0.227 0.227 1,594.00 361.84 361.84 361.84 PM5003
Total Cost Excluding OH & CP 630.38 630.38 630.38
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 50.43 63.04 75.65
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 68.08 69.34 70.60
Total Cost for 5.5 cum = (a+b+c) Including OH & CP 748.89 762.76 776.63
Unit Cost= (a+b+c)/5.5 Including OH & CP 136.16 138.68 141.20

Note : Unloading will be by tipping. Say 136.20 138.70 141.20


CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


1.01 B Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.

Placing tipper at loading point, loading with front end


loader, dumping, turning for return trip, excluding time for
haulage and return trip

Unit = cum
Taking Output = 10.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket capacity Min 12.060 12.060 12.060
iii) Maneuvering, reversing, dumping and turning for return Min 2.000 2.000 2.000
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 19.060 19.060 19.060
a) Machinery
Tipper-10 Cum capacity Hour 0.318 0.318 0.318 2,121.00 674.48 674.48 674.48 PM6003
Front end-loder 1 cum bucket capacity Hour 0.318 0.318 0.318 1,594.00 506.89 506.89 506.89 PM5003
Total Cost Excluding OH & CP 1181.37 1181.37 1181.37
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 94.51 118.14 141.76
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 127.59 129.95 132.31
Total Cost for 10 cum = (a+b+c)Including OH & CP 1403.47 1429.46 1455.45
Unit Cost= (a+b+c)/10 Including OH & CP 140.35 142.95 145.54

Note : Unloading will be by tipping. Say 140.30 142.90 145.50


1.01 C. Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time for
haulage and return trip

Unit = cum
Taking Output = 14.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 2.1 cum bucket capacity Min 8.029 8.029 8.029
iii) Maneuvering, reversing, dumping and turning for return Min 2.000 2.000 2.000
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 15.029 15.029 15.029
a) Machinery
Tipper-14 Cum capacity Hour 0.250 0.250 0.250 2415.00 603.75 603.75 603.75 PM6002
Front End loader 2.1 cum bucket capacity Hour 0.250 0.250 0.250 2588.00 647.00 647.00 647.00 PM5002
Total Cost Excluding OH & CP 1250.75 1250.75 1250.75
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 100.06 125.08 150.09
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 135.08 137.58 140.08
Total Cost for 14 cum = (a+b+c)Including OH & CP 1485.89 1513.41 1540.92
Unit Cost= (a+b+c)/14 Including OH & CP 106.14 108.10 110.07

Note : Unloading will be by tipping. Say 106.10 108.10 110.10


1.01 D Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time for
haulage and return trip
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Unit = cum
Taking Output = 18.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 3.1 cum bucket capacity Min 6.996 6.996 6.996
iii) Maneuvering, reversing, dumping and turning for return Min 2.000 2.000 2.000
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.996 13.996 13.996
a) Machinery
Tipper-18 Cum capacity. Hour 0.233 0.233 0.233 2,772.0 645.9 645.9 645.9 PM6001
Front End loader 3.1 cum bucket capacity Hour 0.233 0.233 0.233 4,255.0 991.4 991.4 991.4 PM5001
Total Cost Excluding OH & CP 1,637.3 1,637.3 1,637.3
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 131.0 163.7 196.5
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 176.8 180.1 183.4
Total Cost for 18 cum = (a+b+c)Including OH & CP 1,945.1 1,981.1 2,017.1
Unit Cost= (a+b+c)/18 Including OH & CP 108.1 110.1 112.1

Note : Unloading will be by tipping. Say 108.1 110.1 112.1


1.02 Ref.to Loading and Unloading of Boulders by Manual Means
M.

Unit = cum
Taking output = 10 Cum

a) Labour
Mate / Supervisor day 0.055 0.055 0.055 310.00 17.05 17.05 17.05 L-12
Mazdoor for loading and unloading. day 1.364 1.364 1.364 292.00 398.29 398.29 398.29 L-13
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


b) Machinery
Tipper-10 Cum capacity Hour 1.364 1.364 1.364 2,121.00 2893.04 2893.04 2893.04 PM6003
Total Cost Excluding OH & CP 3308.38 3308.38 3308.38
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 264.67 330.84 397.01
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 357.31 363.92 370.54
Total Cost for10 cum=(a+b+c+d)Including OH & CP 3930.36 4003.14 4075.93
Unit Cost=(a+b+c+d)/10 Including OH & CP 393.04 400.31 407.59

Note : Unloading will be by tipping. Say 393.00 400.30 407.60


1.03 Ref.to Loading and Unloading of Cement or Steel by Manual
M. Means and Stacking.

Unit = tonne
Taking Output = 18.00 tonne
a) Labour
Mate day 0.144 0.144 0.144 310.00 44.64 44.64 44.64 L-12
Mazdoor day 3.600 3.600 3.600 292.00 1051.20 1051.20 1051.20 L-13
b) Machinery
Truck-18 tonne capacity. Hour 3.600 3.600 3.600 2121.00 7635.60 7635.60 7635.60 PM6003
Total Cost Excluding OH & CP 8731.44 8731.44 8731.44
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 698.52 873.14 1047.77
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 943.00 960.46 977.92
Total Cost for 18 tonnes=(a+b+c+d)Including OH & CP 10372.95 10565.04 10757.13
Unit Cost=(a+b+c+d)/18 Including OH & CP 576.28 586.95 597.62
Say 576.30 586.90 597.60
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Cost of Haulage Excluding Loading and
Unloading
1.04 (i) A
i) A.Case-I : Surfaced Road.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load and lead 10 km=100. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 1,183.0 473.2 473.2 473.2 PM6004

Time taken for empty return trip. Hour 0.286 0.286 0.286 1,183.0 338.3 338.3 338.3 PM6004
Total Cost Excluding OH & CP 811.54 811.54 811.54
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 64.92 81.15 97.38
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 87.65 89.27 90.89
Total Cost for100 t.km = (a+b+c)Including OH & CP 964.11 981.96 999.81
Rate per t.km= (a+b+c)/100 Including OH & CP 9.64 9.82 10.00
Say 9.60 9.80 10.00
Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

B i) Case-I : Surfaced Road .


CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking Output =18tonnes load and lead10 km=180. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 18 tonne capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2121.00 848.40 848.40 848.40 PM6003

Time taken for empty return trip. Hour 0.286 0.286 0.286 2121.00 606.61 606.61 606.61 PM6003
Total Cost Excluding OH & CP 1455.01 1455.01 1455.01
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 116.40 145.50 174.60
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 157.14 160.05 162.96
Total Cost for180 t.km = (a+b+c)Including OH & CP 1728.55 1760.56 1792.57
Rate per t.km= (a+b+c)/180 Including OH & CP 9.60 9.78 9.96
Say 9.60 9.80 10.00

C Case-I : Surfaced Road .


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output = 25 tonne load and lead 10km=250.t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


i) Tipper 25 tonnes capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2415.00 966.00 966.00 966.00 PM6002

Time taken for empty return trip. Hour 0.286 0.286 0.286 2415.00 690.69 690.69 690.69 PM6002
Total Cost Excluding OH & CP 1656.69 1656.69 1656.69
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 132.54 165.67 198.80
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 178.92 182.24 185.55
Total Cost for250 t.km = (a+b+c)Including OH & CP 1968.15 2004.59 2041.04
Rate per t.km= (a+b+c)/250 Including OH & CP 7.87 8.02 8.16
Say 7.90 8.00 8.20
D Case-I : Surfaced Road .
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output =32tonnes load and lead10km= 320. t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 32 tonne capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 2772.00 1108.80 1108.80 1108.80 PM6001

Time taken for empty return trip. Hour 0.286 0.286 0.286 2772.00 792.79 792.79 792.79 PM6001
Total Cost Excluding OH & CP 1901.59 1901.59 1901.59
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 152.13 190.16 228.19
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 205.37 209.18 212.98
Total Cost for320 t.km = (a+b+c)Including OH & CP 2259.09 2300.93 2342.76
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Rate per t.km= (a+b+c)/320 Including OH & CP 7.06 7.19 7.32
Say 7.10 7.20 7.30
1.04 (ii) A .Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output 10 tonnes load & lead 10 km= 100 t.km
Speed with load: 20 km/hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 1183.00 591.50 591.50 591.50 PM6004
Time taken for empty return trip. Hour 0.333 0.333 0.333 1183.00 393.94 393.94 393.94 PM6004
Total Cost Excluding OH & CP 985.44 985.44 985.44
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 78.84 98.54 118.25
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 106.43 108.40 110.37
Total Cost for100 t.km = (a+b+c)Including OH & CP 1170.70 1192.38 1214.06
Rate per t.km= (a+b+c)/100 Including OH & CP 11.71 11.92 12.14
Say 11.70 11.90 12.10
1.04 (ii) B Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output 18 tonnes load & lead10 km=180.t.km
Speed with load : 20 km / hour
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage with load. Hour 0.500 0.500 0.500 2121.00 1060.50 1060.50 1060.50 PM6003

Time taken for empty return trip. Hour 0.333 0.333 0.333 2121.00 706.29 706.29 706.29 PM6003
Total Cost Excluding OH & CP 1766.79 1766.79 1766.79
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 141.34 176.68 212.02
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 190.81 194.35 197.88
Total Cost for180 t.km = (a+b+c)Including OH & CP 2098.95 2137.82 2176.69
Rate per t.km= (a+b+c)/180 Including OH & CP 11.66 11.88 12.09
Say 11.70 11.90 12.10

1.04 (ii) C Case-II : Unsurfaced Gravelled Road .


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output 25 tonnes load & lead10 km =250. t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 25 tonnes capacity.
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2415.00 1207.50 1207.50 1207.50 PM6002

Time taken for empty return trip. Hour 0.333 0.333 0.333 2415.00 804.20 804.20 804.20 PM6002
Total Cost Excluding OH & CP 2011.70 2011.70 2011.70
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 160.94 201.17 241.40
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 217.26 221.29 225.31
Total Cost for250 t.km = (a+b+c)Including OH & CP 2389.89 2434.15 2478.41
Rate per t.km= (a+b+c)/250 Including OH & CP 9.56 9.74 9.91
Say 9.60 9.70 9.90
1.04 (ii) D Case-II : Unsurfaced Gravelled Road.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output 32tonnes load & lead 10 km= 320. t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2772.00 1386.00 1386.00 1386.00 PM6001

Time taken for empty return trip. Hour 0.333 0.333 0.333 2772.00 923.08 923.08 923.08 PM6001
Total Cost Excluding OH & CP 2309.08 2309.08 2309.08
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 184.73 230.91 277.09
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 249.38 254.00 258.62
Total Cost for320 t.km = (a+b+c)Including OH & CP 2743.18 2793.98 2844.78
Rate per t.km= (a+b+c)/320 Including OH & CP 8.57 8.73 8.89
Say 8.60 8.70 8.90
1.04 (iii) A Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Unit = t.km
Taking Output 10 tonnes load & lead 10km= 100 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 1.000 1.000 1.000 1183.00 1183.00 1183.00 1183.00 PM6004

Time taken for empty return trip. Hour 0.667 0.667 0.667 1183.00 789.06 789.06 789.06 PM6004
Total Cost Excluding OH & CP 1972.06 1972.06 1972.06
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 157.76 197.21 236.65
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 212.98 216.93 220.87
Total Cost for100 t.km = (a+b+c)Including OH & CP 2342.81 2386.19 2429.58
Rate per t.km= (a+b+c)/100 Including OH & CP 23.43 23.86 24.30
Say 23.40 23.90 24.30
1.04 (iii) B .Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output18 tonnes load &lead10km=180.00 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2121.00 2121.00 2121.00 2121.00 PM6003
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small

Time taken for empty return trip. Hour 0.667 0.667 0.667 2121.00 1414.71 1414.71 1414.71 PM6003
Total Cost Excluding OH & CP 3535.71 3535.71 3535.71
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 282.86 353.57 424.28
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 381.86 388.93 396.00
Total Cost for180 t.km = (a+b+c)Including OH & CP 4200.42 4278.21 4355.99
Rate per t.km= (a+b+c)/180 Including OH & CP 23.34 23.77 24.20
Say 23.30 23.80 24.20
1.04 (iii) C Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking Output25Tonnes load &lead10 km=250.t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 25 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2415.00 2415.00 2415.00 2415.00 PM6002

Time taken for empty return trip. Hour 0.667 0.667 0.667 2415.00 1610.81 1610.81 1610.81 PM6002
Total Cost Excluding OH & CP 4025.81 4025.81 4025.81
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 322.06 402.58 483.10
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 434.79 442.84 450.89
Total Cost for250 t.km = (a+b+c)Including OH & CP 4782.66 4871.22 4959.79
Rate per t.km= (a+b+c)/250 Including OH & CP 19.13 19.48 19.84
Say 19.10 19.50 19.80
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


1.04 (iii) D Case-III : Katcha Track and Track in river bed / nallah bed
and choe bed.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output32 tonnes load &lead 10 km= 320. t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 2772.00 2772.00 2772.00 2772.00 PM6001

Time taken for empty return trip Hour 0.667 0.667 0.667 2772.00 1848.92 1848.92 1848.92 PM6001
Total Cost Excluding OH & CP 4620.92 4620.92 4620.92
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 369.67 462.09 554.51
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 499.06 508.30 517.54
Total Cost for320 t.km = (a+b+c)Including OH & CP 5489.66 5591.32 5692.98
Rate per t.km= (a+b+c)/320 Including OH & CP 17.16 17.47 17.79
Say 17.20 17.50 17.80
1.04 (iv) Case-IV : Katcha Track in hilly area.
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.

Unit = t.km
Taking Output 10 tonnes load & lead 10km= 100. t.km
Speed with load: 5 km / hour
Speed while returning empty: 7 km / hour
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 2.000 2.000 2.000 1183.00 2366.00 2366.00 2366.00 PM6004

Time taken for empty return trip. Hour 1.429 1.429 1.429 1183.00 1690.51 1690.51 1690.51 PM6004
Total Cost Excluding OH & CP 4056.51 4056.51 4056.51
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 324.52 405.65 486.78
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 438.10 446.22 454.33
Total Cost for100 t.km = (a+b+c)Including OH & CP 4819.13 4908.37 4997.62
Rate per t.km= (a+b+c)/100 Including OH & CP 48.19 49.08 49.98

Say 48.20 49.10 50.00


1.04 (v) Case-V : Transit Mixture
Haulage of Concrete by Transit mixture excluding cost of
loading, unloading and stacking.

Unit = t.km
Taking Output 15Tonnes load & lead 10km= 150 t.km
Speed with load : 20 km / hour
Speed while returning empty: 30 km / hour
a) Machinery
i) Transit Mixture 6 cum capacity.
Time taken for onward haulage with load Hour 0.500 0.500 0.500 2218.00 1109.00 1109.00 1109.00 PM34001

Time taken for empty return trip. Hour 0.333 0.333 0.333 2218.00 738.59 738.59 738.59 PM34001
Total Cost Excluding OH & CP 1847.59 1847.59 1847.59
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 147.81 184.76 221.71
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 199.54 203.24 206.93
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Total Cost for150 t.km = (a+b+c)Including OH & CP 2194.94 2235.59 2276.24
Rate per t.km= (a+b+c)/150 Including OH & CP 14.63 14.90 15.17
Say 14.60 14.90 15.20
1.05 Hand Broken Stone Aggregates 63 mm nominal size

Supply of quarried stone, hand breaking into coarse


aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as directed

Unit = cum
Taking Output = 1.00 cum
a) Labour
Mate day 0.0600 0.0600 0.0600 310.00 18.60 18.60 18.60 L-12
Mazdoor day 1.500 1.500 1.500 292.00 438.00 438.00 438.00 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.1000 1.1000 1.1000 351.36 386.50 386.50 386.50 M-002
Total Cost Excluding OH & CP 843.10 843.10 843.10
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 67.45 84.31 101.17
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 91.05 92.74 94.43
Total Cost for1cum = (a+b+c+d)Including OH & CP 1001.60 1020.15 1038.69
Rate per cum= (a+b+c+d) Including OH & CP 1001.60 1020.15 1038.69
Say 1001.60 1020.10 1038.70

1.06 Crushing of stone aggregates (Nominal size)


CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 250 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of different nominal size.

(i) 1.Crushing Pattern 40 mm (tonne)- Cost Distribution


28.98 %
Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.00 99.20 99.20 99.20 L-12
Mazdoor(Skilled) day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
b) Material
Stone Boulder of size 150 mm and below . cum 750.000 750.000 750.000 351.36 263520.00 263520.00 263520.00 M-001

c) Machinery
Integrated stone crusher of 250 TPH including belt Hour 6.000 6.000 6.000 13431.00 80586.00 80586.00 80586.00 PM16001
conveyor and vibrating screens
Generator 725 KVA Hour 6.000 6.000 6.000 13148.00 78888.00 78888.00 78888.00 PM22001
Front end loader 3.1 cum bucket capacity at quarry and Hour 5.515 5.515 5.515 4255.00 23466.33 23466.33 23466.33 PM5001
crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2415.00 13318.73 13318.73 13318.73 PM6002
Tipper 14 cum capacity for transportation within 1 km t.km 1,125.000 1,125.000 1,125.000 6.63 7458.75 7458.75 7458.75 PM73001
d) Total Cost for 750 cum(a+b+c) 469829.00 469829.00 469829.00
(Excluding OH & CP)
e) Crushing pattern 40mm(tonne) tonne 22.71% 22.71% 22.71% 255.49
f) % Cost distribution={(d)x(f)/e)x1.5} cum 28.98% 28.98% 28.98% 0.29 799.39 799.39 799.39
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) 63.95 79.94 95.93
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) 86.33 87.93 89.53
i) Total Cost for1cum = (f+g+h) Including OH & CP 949.68 967.26 984.85
Rate per cum= (f+g+h) Including OH & CP 949.68 967.26 984.85
Say 949.70 967.30 984.80

(ii) Crushing of stone aggregates (Nominal size)


2.Crushing Pattern 20 mm (tonne)- Cost Distribution
31.95 %
d) Total Cost for 750 cum(Excluding OH & CP) 469829.00 469829.00 469829.00
e) Crushing pattern 20mm(tonne) tonne 23.00% 23.00% 23.00% 258.75
f) % Cost distribution={(d)x(f)/e)x1.5} cum 31.95% 31.95% 31.95% 0.32 870.21 870.21 870.21
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) 69.62 87.02 104.42
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) 93.98 95.72 97.46
i) Total Cost for1cum = (f+g+h)Including OH & CP 1033.80 1052.95 1072.09
Rate per cum= (f+g+h) Including OH & CP Say 1033.80 1052.90 1072.10

(iii) Crushing of stone aggregates (Nominal size)


3.Crushing Pattern 10 mm (tonne)- Cost Distribution
30.75 %

d) Total Cost for 750 cum(Excluding OH & CP) 469829.00 469829.00 469829.00
e) Crushing pattern 10 mm(tonne) tonne 25.86% 25.86% 25.86% 290.9250
f) % Cost distribution={(d)x(f)/e)x1.5} cum 30.75% 30.75% 30.75% 0.3075 744.90 744.90 744.90
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) 59.59 74.49 89.39
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) 80.45 81.94 83.43
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


i) Total Cost for1cum = (f+g+h)Including OH & CP 884.94 901.32 917.71
Rate per cum= (f+g+h) Including OH & CP 884.90 901.30 917.70

(iv) Crushing of stone aggregates (Nominal size)


4 Crushing Pattern dust (tonne)- Cost Distribution
08.32 %

d) Total Cost for 750 cum(Excluding OH & CP) 469829.00 469829.00 469829.00
e) Crushing pattern dust (tonne) tonne 28.43% 28.43% 28.43% 319.84
f) % Cost distribution={(d)x(f)/e)x1.5} cum 8.32% 8.32% 8.32% 0.08 183.33 183.33 183.33
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) 14.67 18.33 22.00
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) 19.80 20.17 20.53
i) Total Cost for1cum = (f+g+h)Including OH & CP 217.79 221.82 225.86
Rate per cum= (f+g+h) Including OH & CP 217.80 221.80 225.90

1.07 Crushing of stone aggregates (GSB Crusher Run)


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 250 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain crusher run (all in
aggregate) for GSB.

Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.00 99.20 99.20 99.20 L-12
Mazdoor (Skilled) day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750 750 750 351.36 263520.00 263520.00 263520.00 M-001
c) Machinery
Integrated stone crusher of 250 TPH including belt Hour 4.615 4.615 4.615 13431.00 61984.07 61984.07 61984.07 PM16001
conveyor and vibrating screens (for producing crusher run
production capacity will increas by 30%)

Generator 725 KVA Hour 4.615 4.615 4.615 13148.00 60678.02 60678.02 60678.02 PM22001
Front end loader 3.1 cum bucket capacity at quarry and Hour 5.515 5.515 5.515 4255.00 23466.33 23466.33 23466.33 PM5001
crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2415.00 13318.73 13318.73 13318.73 PM6002
Tipper 14 cum capacity for transportation within 1 km t.km 1,125.00 1,125.00 1,125.00 6.63 7458.75 7458.75 7458.75 PM73001
Total Cost Excluding OH & CP 433017.09 433017.09 433017.09 481.13009
d) Overheadson (a+b+c) (@ 8%) (@ 10%) (@ 12%) 34641.37 43301.71 51962.05
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 46765.85 47631.88 48497.91

Cost for 900 cum =(a+b+c+d+e) 514424.30 523950.67 533477.05


Rate per cum =(a+b+c+d+e)/900( Including OH & CP) Say 571.60 582.20 592.80

Note: Considering Crushed volume will be 1.2 times the volume of boulder.
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small

Schedule :- CARRIAGE OF MATERIALS (By TRACTOR)


Ref.
to
Sr. Rate Remarks/
MoR Description Unit Quantity as per Project Category Amount
No. (Rs`) Input ref.
TH
Spec.
1.1 Loading and Unloading of Stone Boulder/ Stone cum
aggregates/Sand /Kanker/Moorum Large Medium Small Large Medium Small

Placing Tractor at loading point, loading with front end


loader, dumping, turning for return trip, excluding time for
haulage and return trip

Unit = cum
Taking output = 2.25 cum
Time required for
i) Positioning of Tractor at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 5 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 0 Min
return
iv) Waiting time, unforeseen contingencies etc 0 Min
Total 6 Min
a) Labour
Mate day 0.050 0.050 0.050 310.00 15.50 15.50 15.50 L-12
Mazdoor for loading and unloading day 0.310 0.310 0.310 292.00 90.52 90.52 90.52 L-13
b) Machinery
Tractor 3.60 tonnes capacity hour 0.100 0.100 0.100 612.00 61.20 61.20 61.20 PM120
01
Front end-loader 1 cum bucket capacity hour 0.083 0.083 0.083 1594.00 132.30 132.30 132.30 PM500
3
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Total Cost Excluding OH & CP 299.52 299.52 299.52
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 23.96 29.95 35.94
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 32.35 32.95 33.55
Total Cost for2.5 cum = (a+b+c+d)Including OH & CP 355.83 362.42 369.01
Rate per cum= (a+b+c+d)/2.5 Including OH & CP 142.33 144.97 147.60
Note Unloading will be done manually. say 142.30 145.00 147.60

1.2 Loading and Unloading of Boulders by Manual Means

Unit = cum
Taking output = 2.25 cum
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.30 9.30 9.30 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.24 210.24 210.24 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.310 0.310 0.310 612.00 189.72 189.72 189.72 PM120
01
Total Cost Excluding OH & CP 409.26 409.26 409.26
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 32.74 40.93 49.11
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 44.20 45.02 45.84
Total Cost for2.25 cum = (a+b+c+d)Including OH & CP 486.20 495.20 504.21
Rate per cum= (a+b+c+d)/2.25 Including OH & CP 216.09 220.09 224.09
say 216.10 220.10 224.10
Note Unloading will be done manually.
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Unit = tonne
Taking output = 3.60 tonnes
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.30 9.30 9.30 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.24 210.24 210.24 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.720 0.720 0.720 612.00 440.64 440.64 440.64 PM12001
Total Cost Excluding OH & CP 660.18 660.18 660.18
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 52.81 66.02 79.22
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 71.30 72.62 73.94
Total Cost for3.6 cum = (a+b+c+d)Including OH & CP 784.29 798.82 813.34
Rate per cum= (a+b+c+d)/3.6 Including OH & CP 217.86 221.89 225.93
say 217.90 221.90 225.90
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by Tractor excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 3.60 tonnes load and lead 10 km = 36.0
t.km

Surfaced Road
Speed with load : 15 km / hour.
Speed while Returning empty :25 km / hour.
a) Machinery.
Tractor 3.6 tonne capacity
Time taken for onward haulage with load hour 0.667 0.667 0.667 612.00 408.20 408.20 408.20 PM12001
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Time taken for empty return trip. hour 0.400 0.400 0.400 612.00 244.80 244.80 244.80 PM12001
Total Cost Excluding OH & CP 653.00 653.00 653.00
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 52.24 65.30 78.36
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 70.52 71.83 73.14
Total Cost for36 t.km = (a+b+c)Including OH & CP 775.77 790.13 804.50
Rate per t.km= (a+b+c)/36 Including OH & CP 21.55 21.95 22.35
say 21.50 21.90 22.30

1.4 (ii) Unsurfaced Graveled Road


Speed with load: 12 km / hour
Speed for empty return trip :20 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage with load hour 0.833 0.833 0.833 612.00 509.80 509.80 509.80 PM12001
Time taken for empty return trip hour 0.500 0.500 0.500 612.00 306.00 306.00 306.00 PM12001
Total Cost Excluding OH & CP 815.80 815.80 815.80
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 65.26 81.58 97.90
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 88.11 89.74 91.37
Total Cost for36 t.km = (a+b+c)Including OH & CP 969.17 987.11 1005.06
Rate per t.km= (a+b+c)/36 Including OH & CP 26.92 27.42 27.92
say 26.90 27.40 27.90

1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :10 km / hour
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount Input_Re
M. f

Large Medium Small Large Medium Small


Speed while returning empty:15 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage hour 1.000 1.000 1.000 612.00 612.00 612.00 612.00 PM12001
Time taken for empty return trip hour 0.667 0.667 0.667 612.00 408.20 408.20 408.20 PM12001
Total Cost Excluding OH & CP 1020.20 1020.20 1020.20
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 81.62 102.02 122.42
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 110.18 112.22 114.26
Total Cost for36 t.km = (a+b+c)Including OH & CP 1212.00 1234.45 1256.89
Rate per t.km= (a+b+c)/36 Including OH & CP 33.67 34.29 34.91
say 33.70 34.30 34.90

oSls LFky tgk¡ ij Truck ,oa Tipper ds }kjk <qykbZ fd;k tkuk laHko ugha gS rFkk Tractor ls <qykbZ economical gks dsoy oSls gh LFkyksa ds fy, Tractor ls
Note:-
<qykbZ dk izko/kku fd;k tk;A
114.6144
118.14
89.34
90.96061
330.8382

485.08 485.08
8.12
8.08 8.083367
6.63

5.942475
CHAPTER -2
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Cutting of trees, excluding removal of stumps and
2.01 201 A
roots of trees
Cutting of trees stacking of serviceble material with
all lifts and up to a lead of 1000 metres.
(i) Girth from 300mm to 600mm Each 350.90 369.30 401.50
(ii) Girth from 600mm to 900mm Each 493.40 529.60 667.50
(iii) Girth from 900mm to 1800mm Each 895.10 938.90 1084.20
(iv) Girth above 1800mm Each 1735.50 1853.30 2168.40

Removal of stumps and roots including


2.01 201 B backfillinbg with suitable material to required
compaction
Removal of stumps, roots, staking of serviceable
material with all lifts up to a lead of 1000 metres and
earth filling in the depression/ pit.
(i) Girth from 300mm to 600mm Each 572.00 584.90 637.40
(ii) Girth from 600mm to 900mm Each 765.20 779.80 864.40
(iii) Girth from 900mm to 1800mm Each 919.30 935.80 1034.30
(iv) Girth above 1800mm Each 1141.90 1169.80 1287.30
2.02 201 Clearing Grass and Removal of Rubish

Clearing grass and removal of rubbish up to a distance


of 50 metres outside the periphery of the area

By Manual Means Hectare 18081.40 18416.20 18751.00

2.03 201 Clearing and Grubbing road land


Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, sapling and
tress girth upto 300 mm, removal of stumps of tree cut
earlier and disposal of unserviceable materials and
stacking of sericeable material to be used of
auctioned, up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding
150mm in thickness.

(i) By Manual means:-


A In area of light jungle Hectare 143106.30 145756.40 148406.60
B In area of thorny jungle Hectare 161187.70 164172.60 167157.60
(ii) By Mechanical means using dozer
A In area of light jungle Hectare 165054.40 166756.60 217252.60
2.03 B In area of thorny jungle Hectare 176475.80 178227.90 231257.10

2.03 (iii) By Mechanical Means using Motor grader


A In area of light jungle Hectare 147268.30 152272.80 180778.50

2.03 B In area of thorny Jungle Hectare 154333.60 160215.20 185760.20

2.04 202 Dismantling of Structures


SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small

Dismantling of existing structures like culverts,


bridges, retaining walls and other structure comprising
of masonry, cement concree, wood work, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with allk lifts and lead of 1000 metres

(i) Lime/ Cement concrete


I By Manual means
Lime concrete, cement concrete grade M-10 and
A cum 463.20 471.80 480.40
below
2.04 B Cement concrete Grade M-15 & M-20 cum 535.50 545.50 555.40
Prestressed/ Reinforced cement concrete grade M- cum
2.04 C 1248.40 1271.50 1294.60
20 & above

2.04 II By Mechanical means


A Cement Concrete Grade M-15 & M-20 cum 755.10 768.40 820.50
Prestressed/ Reinforced cement concrete grade M- cum 957.00 974.00 1029.90
2.04 B
20 & above

2.04 (ii) Dismantling Brick/ tile work


By Manual means
A In lime mortar cum 294.10 299.60 305.00
2.04 B In cement mortar cum 366.50 373.20 380.00
2.04 C In Mud mortar cum 265.20 270.10 275.00
2.04 D Dry brick pitching or brick soling cum 250.70 255.40 260.00

2.04 (iii) Dismantling stone masonry


I By Manual means
A rubble stone masonry in lime mortar cum 323.10 329.00 335.00
2.04 B Rubble stone masonry in cement mortar cum 366.50 373.20 380.00
2.04 C Rubble stone masonry in mud mortar cum 294.10 299.60 305.00
2.04 D Dry rubble masonry cum 279.70 284.80 290.00
2.04 E Dismantling stone pitching/dry stone spalls. cum 265.20 270.10 275.00
Dismantling boulders laid in wire crates including
2.04 F opening of crates and stacking dismantled cum 294.10 299.60 305.00
materials.

2.04 II By Mechanical means


Dismantling Brick/ Tile work/ rubble
A cum 205.60 214.00 269.10
masonary/pitching/ etc. by mechanical means

Wood work wrought framed and fixed in frames of cum


2.04 (iv) 631.90 643.60 655.30
trussess upto a height of 5m above plinth level

Steel work in all types of sections upto a height of


2.04 (v)
5m above plinth level excluding cutting of rivet.

A Including dismembring tonne 1458.60 1485.60 1512.60


2.04 B Excluding dismembering tonne 1052.00 1071.50 1091.00
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small

2.04 C Extra over item no (v) A and (v)B for cutting rivets Each 10.30 10.50 10.70

Scrapping of bricks dismantled from brick work


2.04 (vi)
including stacking
A In Lime/Cement mortar Nos 1.30 1.30 1.30
2.04 B In mud mortar 0.50 0.50 0.50

2.04 (vii) Scraping of stone from dismantled stone masonry

A In Cement and lime mortar cum 506.30 515.70 525.00


2.04 B In Mud mortar 108.50 110.50 112.50

Scraping plaster in lime or cement mortar from


2.04 (viii) sqm 16.70 17.00 17.30
Brick/Stone Masonry

Removing all type of Hume pipes and stacking


2.04 (ix) within a lead of 1000 metres including Earthwork
and Dismantling of Masonry Works.

A Upto 600mm dia metre 1122.90 1248.20 1355.60


B Above 600mm to 900mm dia metre 1372.90 1473.60 1559.90
C Above 900mm metre 1622.90 1699.00 1968.60
2.05 202 Dismantling of flexible pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
(i) By Manual means
A Bituminous courses cum 663.90 676.20 688.40
2.05 B Granular courses cum 483.00 492.00 500.90

Dismantling of flexible pavements and disposal of


dismantled materials upto a leadof 1000 metres,
2.05 202
stacking serviceable and unserviceable materials
separately
(ii) By Mechanical means
A Bituminous courses cum 500.40 518.20 593.30
B Granular Courses cum 63.50 68.00 86.20

2.06 202 Dismantling of cement concrete pavement

Dismantling of cement concrete pavement by


mechanical means using pneumatic tools, breaking to
pieces not exceeding 0.02 cum in volume and stock
piling at designated locations and disposal of cum 730.70 776.80 858.50
dismantled materials up to a alead of 1000 metres,
stackiung serviceable and unserviceable materials
separately

2.07 202 Dismantling of guard rails


SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Dismantling of guard rails by manual means and
disposal of dismantled material with all lifts and up to metre 58.60 59.70 60.80
a lead of 1000 metres, stacking serviceable materials
and unserviceable materials separately

2.08 202 Dismantling of kerb stone


Dismantling kerb stone by manual means and disposal
of dismantled material with all lifts and up to a lead of metre 15.50 15.80 16.10
1000 metres

2.09 202 Dismantling of kerb stone channel


Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to metre 20.50 20.90 21.30
a lead of 1000 metres

2.10 202 Dismantling of kilometre stone


Dismantling of kilometre stone including cutting of
earth , foundation and disposal of dismantled material
with all lifts and lead up to 1000 metres and back
filling of pit
A 5th KM stone Each 380.30 387.30 394.40
B Ordinary KM Stone Each 253.50 258.20 262.90
C Hectometre Stone Each 50.70 51.60 52.60

2.11 202 Dismantling of fencing


Dismantling of barbed wire fencing/ wire mesh
fencing including posts, foundation concrete, back
filling of pit by manual means including disposal of metre 50.60 51.50 52.50
dismantled materials with all lifts and up to a lead of
1000 metres stacking serviceable material and
unserviceable material separately.

2.12 202 Dismantling of CI Water Pipe Line


Dismantling of CI Water Pipe Line 600mm dia.
Including disposal with all lifts and lead upto 1000
metres and stacking of serviceable material and metre 170.40 173.50 176.70
unserviceable material separately under supervision of
concerned department

2.13 202 Removal of cement concrete Pipe of sewer Gutter

Removal of cement concrete pipe of sewer gutter 1500


mm dia under the supervision of concerned
department including disposal with all lifts and up to a metre 263.30 268.20 273.10
lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth
excavation and dismantling of masonry works.

2.14 202 Removal of telephone/ Electric Poles and Lines


SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small

Removal of telephone/ Electric poles including


excavation and dismantling of foundation concrete
and lines under the supervision of concerned Each 189.10 192.60 196.10
department , disposal with all lifts and up to a lead of
1000 metres and stacking the serviceable and
unserviceable material separately

CHAPTER -3
EARTH WORK, EROSION CONTROL AND DRAINAGE.
Unit Rate as per Project Category
Ref. to
Sr No Description
M.
3.01 301 Exacavation in Soil by Manual Means. Large Medium Small
cum 243.80 248.30 252.80
Exacavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto 1000
metres.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Note In case there is a situation where the cross-section is
of cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted

3.02 301 Exacavation in Ordinary Rock by Manual Means.


cum 319.10 325.00 330.90
Exacavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres.
Note In case there is a situation where the cross-section is
of cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted

Excavation in soil with Dozer with lead upto 1000


3.03 301
metres
Excation for road way in soil by mechanical means cum 177.40 185.40 231.80
including cutting and transporting the earth to site of
embankment /dumping area with lead upto 1000
metres, including trimming bottom and side slopes in
accordance with requirements of lines, grades and
cross sections.

3.04 301 Excavation in ordinary rock with Dozer with lead


upto 1000 metres
cum 267.80 282.80 343.90
Excavation for roadway in ordinary rock by deploying
a dozer, including cutting and transporting the earth
to site of embankment /dumping area with lead upto
1000 metres, trimming bottom and side slopes in
accordance with the requirements of lines, grades
and cross sections.

301 & Excavation in Hard Rock (requiring


3.05
302 blasting) with disposal upto 1000 metres
cum #VALUE! #VALUE! #VALUE!
Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking,
trimming of bottom and side slopes in accordance
with requirements of lines, grades and cross
sections, loading and disposal of cut road with in all
lifts and leads upto 1000 metres

Note 1. The quantity and availability of rock shall be checked before affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall be
reduced/ restricted to that extent.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Excavation in Soil using Hydraulic Excavator and
3.06 301 Tippers with Disposal upto 1000 metres.

Excavation for road work in soil with hydraulic cum 93.70 107.50 123.30
excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
tranporting to the embankment location within all
lifts and lead upto 1000 m

Excavation in Ordinary Rock using


3.07 301 Hydraulic Excavator and Tippers with
Disposal upto 1000 metres
cum 646.70 686.50 721.90
Excavation for roadwork in Ordinary
Rock with hydraulic excavator including
cutting and loading in tippers, trimming
bottom and side slopes, in accordance
with requirements of lines, grades and
cross sections, and transporting to the
embankment location within all lifts and
lead upto 1000m

Excavation in Hard Rock (blasting


3.08 301
prohibited)
Excavation for roadwork in Hard Rock
(blasting prohibited) with hydraulic
excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all
lifts and lead upto 1000m

A Mechanical Method cum 797.10 837.50 898.40


3.08 B Manual Method cum 1386.50 1412.20 1437.90
Note 1. Credit is considered for 50 percent of quantity of work.
2. Loading for disposal will be done manually, being small quantity.
3. In case some rock is issued to contractor at site, the item of carriage shall
be omitted to the extent of quantity issued to the contractor

cum #VALUE! #VALUE! #VALUE!


3.09 301 & 302 Excavation in Hard Rock (controlled
blasting) with disposal upto 1000 metres
1. The quantity and availability of rock shall be checked before affording
Note
credit.
2. In case some rock is issued to the contractor at site, the item of carriage
shall be reduced/ restricted to that extent.

Excavation in Marshy Soil using


3.10 301 Hydraulic Excavator and Tippers with
Disposal upto 1000 metres
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Excavation for roadwork in Marshy Soil cum 203.20 211.40 266.50
with hydraulic excavator including cutting and loading
in tippers, trimming bottom and side slopes, in
accordance with
requirements of lines, grades and cross
sections, and transporting to the embankment
location within all lifts and lead upto 1000m

3.11 301 Removal of Unserviceable Soil with


Disposal upto 1000 metres
Removal of unserviceable soil including excavation, cum 95.60 100.00 125.80
loading and disposal upto 1000 metres lead but
excluding replacement by suitable soil which shall be
paid separately as per clause 305.

3.12 303
Presplitting of Rock Excavation Slopes sqm #VALUE! #VALUE! #VALUE!
Carrying out excavation in hard rock to
achieve a specified slope of the rock face by
controlled use of explosives and blasting accessories
in properly aligned and spaced drill holes, collection
of the excavated rock by a dozer, loading in tipper by
a front end loader and disposing of the material with
all lifts and lead upto 1000 m, all as specified in clause
No. 303

Note 1. The quantity and availability of rock shall be checked before affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall be
reduced/ restricted to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures
as per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom, backfilling the
excavation earth to the extent required a nd utilising
the remaining earth locally for road work.

(i) Ordinary Soil


A Manual Means ( Depth upto 3 m) cum 289.30 294.70 300.00
Cost of dewatering may be added where required upto 10 percent of labour cost
Note
Assesment for dewatering shall be made as per site conditions.
3.13 B Mechanical Means (Depth upto 3 m) cum 87.90 91.60 113.80

3.13 (ii) (ii) Ordinary Rock (not requiring blasting)


A Manual Means ( Depth upto 3m) cum 361.60 368.30 375.00
Cost of dewatering upto 10 percent of labour cost may be added where required.
Note
Assesment for dewatering shall be made as per site conditions.
3.13 (ii) B Mechanical Means cum 664.00 708.50 735.90
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small

3.13 302 & (iii) Mechanical Means


303
A Carrying out excavation in hard rock to achieve a cum #VALUE! #VALUE! #VALUE!
specified slope of the rock face by controlled use of
explosives and blasting accessories in property
alighed and spaced drill holes , collection of the
excavated rock by a dozer, loading in tipper by a front
end loader and disposing of the material with all lifts
and lead upto 1000 m, all as specified in clasue No.
303.

3.13 (iv) Hard Rock ( Blasting Priohibited) cum 1212.60 1300.30 1462.50

3.13 (v) Marshy soil


A Manual means ( upto 3m depth) cum 576.40 587.10 597.80

Note 1. Cost of dewatering @ 30 percent of (a), may be added where required Assesment for
dewatering shall be made as per site conditions.
2. Shoring & Strutting 20 percent of (a), where required may be added.
3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper
excavation below 3 m depth, refer analysis in item (i) to (iv) for ordinary soil.
3.13 B Mechanical Means cum 332.20 345.20 429.10

Scarifying the existing bituminous road surface to a


depth of 50 mm and disposal of scarified material
3.14 305.4.3 with in all lifts and lead upto 1000 metres.

Scarifying Existing Grannular Surface to a depth of 50 sqm 30.20 30.80 31.30


(i)
mm by Manual Means
In case material is to be reused at site, transportation cost catered above for disposal
Note
shall be deleted.

3.14 305.4.3 (ii) By Mechanaical Means using Hydraulic excavator sqm 6.00 6.30 7.90

3.14 305.4.3 (iii) By Mechanaical Means using Motor Grader sqm 7.90 8.20 9.40

Note In case material is to be reused at site, transportation cost catered above for disposal
shall be deleted.

Scarifying the existing bituminous surface too a


3.15 305.4.3 depth of 50 mm and disposal of scarified material
within all the lifts and leads upto 1000 metres.

(i) By Mechanaical Means using Hydraulic excavator sqm 7.20 7.50 9.50

3.15 305.4.3 (ii) By Mechanaical Means using Motor Grader sqm 8.00 8.30 9.50

Construction of Embankment with Material obtained


3.16 305 from Borrow pits.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
cum 194.90 205.50 220.30
Construction of Embankment with approved material
obtained from Borrow pits with approved material
obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required
slope and compacting to meet requirement of Table
300-2.

Note Compensation for earth will vary from place to place and will have to be assessed
realistically as per particular ground situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is required to be clearly stated
in the cost estimate.

Construction of Embankment with


3.17 305 Material Deposited from Roadway
Cutting
cum 92.40 97.80 86.40
Construction of Embankment with
approved materials deposited at site from roadway
cutting and excavation from drain and foundation of
other structures graded and compacted to meet
requirement of Table 300-2.

Construction of Subgrade and Earthen


3.18 305
Shoulders
Construction of sub-grade and earthen shoulders with cum 197.00 207.90 223.20
approved material obtained from Borrow pits with
approved material obtained from borrow pits with all
lifts and leads, transporting to site, spreading, grading
to required slope and compacting to meet
requirement of Table 300-2.

Construction of Subgrade and Earthen


3.19 305 Shoulders with Material Deposited from Roadway
Cutting

cum 93.40 98.90 87.70


Construction of Embankment with
Material Deposited from Roadway
Construction of embankment with approved
materials deposited at site from roadway cutting and
excavation from drain and foundation of other
structures graded and compacted to meet
requirement of Table 300-2.

3.20 305.3.4 Compacting Original ground


Case-I Compacting Original ground supporting sub-grade
cum 93.80 103.10 74.30
Loosening of the ground upto a level of 500 mm
below the sub-grade level, watered, graded and
compacted in layers to meet requirement of Table
300-2 for sub-grade construction.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small

Case-II Compacting Original ground supporting embankment


Loosening, leveling and compacting orinal ground cum 107.70 118.90 85.60
supporting embankment to facilitate placement of
first layer of embankment , scarified to a depth of 150
mm, mixed with water at OMC and then compacted
by rolling so as to achieve minimum dry density as
given in Table 300-2 for emabakment construction.

3.21 305 Stripping and Storing Top Soil


Stripping, Storing of Top Soil by road side at 15 m cum 117.40 125.70 126.90
internal and re-application on embankment slopes,
cut slopes and other areas in localities where the
available embankment material is not conducive to
plant growth.

3.22 305 Stripping, Storing and Re-laying Top Soil


from Borrow Areas in Agriculture Fields.

cum 213.00 222.60 256.30


Stripping of top Soil from Borrow areas located in
agriculture fields, storing at a suitable place,
spreading and re-laying after taking the borrow earth
to maintain fertility of the agricultural field, finishing
it to the required levels and satisfaction of the
farmer.

3.23 307 A Turfing with Sods


Furnishing and laying of the live sods of perennial turf cum 39.90 42.40 48.70
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of
sods and watering.

3.24 308 Seeding and Mulching


sqm 151.80 160.90 183.50
Preparation of seed bed on previously laid top soil,
firnishing and placing of seeds, fertilizer, mulching
material, applying bituminous emulssion at the rate
of 0.23 litres per sqm and laying and fixing jute
netting, including cost of watering for 3 months all as
per clause 308.

3.25 309 Surface Drains in Soil


metre 55.80 56.80 57.90
Construction of unlined surface drains of average
cross sectional area 0.40 sqm in soil to specified lines,
grades, levels and dimensions to the reuirement of
clause 301 and 309. Excavated material to be used in
embankment within a lead of 1000 metres

3.25 B Manual means metre 132.10 134.50 137.00


SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
Note Where lining of drain is provided, quanity shall be worked out based on approved design
and drawing and priced on rate of cement concrete of approved grade or stone/ brick
masonry as the case may be.

3.26 309 Surface Drains in Ordinary Rock

Construction of unlined surface drain of average cross


sectional area 0.4 sqm in ordinary rock to specified
lines, grades, levels and dimensions as per approved
design and to the reuirement of clause 301 and 309.
Excavated material to be used in embankment at site
within a lead of 1000 metres

A Mechanical means metre 73.40 74.80 76.20


B Manual means metre 184.40 187.80 191.20

3.27 309 Surface Drains in Hard Rock

Rate per metre may be worked out bsed on quantity


of hard rock as per desig. For rate of hard rock
cutting, refer relevent item in this chapter

3.28 309 Sub-Surface Drains with Perforated Pipe


metre 344.80 351.20 357.60

Construction of subsurface drain with perforated pipe


of 100 mm internal diameter of metal/ asbestos
cement/ Cement concrete/ PVC, closely jointed,
perforations ranging from 3mm to 6mm depending
upto size of material surrounding the pipe, with 150
mm bedding below the pipe and 300mm cushion
above the pipe, cross section of excavation 450 x 550
mm. Excavated material to be utilised in roadway at
site

Note Type of pipe may be modified depending upon provision in design.

3.29 309 Aggregate Sub-Surface Drains


metre 135.10 137.70 140.20
Construction of aggregate sub surface drain 300 mm
x 450 mm with aggregates conforming to Table 300-4,
excavated material to be utilised in roadway.

3.30 309 Underground Drain at Edge of pavement


metre 3281.23 3350.18 3456.80
Construction of an underground drain 1m x 1m
(inside dimensions) lined with RCC-20 cm thick and
covered with RCC slab 10 cm in thickness on urban
roads.

Rates for these items may be taken from chapters on


earth work and culvert respectively.

3.31 310 Preparation and Surface Treatment of Formation


SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
sqm 3.70 3.80 4.20
Preparation and Surface treatment of formation by
removing mud and slurry, watering to the extent
needed to maintain the desired moisture content,
trimming to the required line, grade, profile and
rolling with smooth wheeled roller,complete as per
clause 310.

Construction of Rock fill Embankment with all lifts


3.32 313
and lead upto 5 km
Construction of Rock fill Embankment from roadway cum 132.60 141.00 170.00
excavation with broken hard rock fragments of size
not exceeding 300 mm laid in layers not exceeding
500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material,
rolled with vibratory road roller, all complete as per
clause 313.

Note It is assumed that rock is available locally at site from roadway cutting. In case,portion of
the rock requires breaking to acceptable size of 300mm, beaking charges will have to be
added.

3.33 Work in Urban Roads


The cost of earth work in urban roads inhabited area will be comparatively higher due to
following reasons:
a) There is mixed traffic on urban roads like slow moving hand and animal driven carts,
riskshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be in the range of 10-15
percent

c) Cost of living in urban areas is comparatively more resulting into higher wages.
d) At times, work is executed during night time due to heavy traffic during day time. This
involves extra expenditure by way of making arrangement for lighting and special
transport for working parties due to odd hour.

In the light of above, the authorities engaged in preparing the cost estimates may
exercise their judgement and cater for the additional cost to the extent of 2 to3
percent,keeping in view the severity of factors mentioned above. Supporting details for
the extra cost based on the actual conditions in specific cases will have to give in
justification.

3.34 Suggestive Embankment Construction with Fly ash/Pond ash


available from coal or lignite burning Thermal Plants
as waste material.
86.00 92.60 86.20
Construction of embankment with fly ash conforming
to Table 1 of IRC: SP:58 obtained from coal or lignite
burning thermal power stations as waste material,
spread and compacted in layers at OMC, all as
specified in IRC: SP: 58 and as per approved plans.
Considering soil blanketing of 2m either side for 4
lane section

Note 1. As Fly Ash is available free of cost as waste material from Thermal Plants, cost of
materials has not been added.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
2. The Earth cover on sides and intermidiate layers of earth sandwitching the Fly Ash has
been included in this analysis.
SITE CLEARANCE
Ref. to Unit Rate as per Project Category
Sr No Description
M.
Large Medium Small
CHAPTER -2
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small

Cutting of trees, excluding removal of stumps and


2.01 201 A
roots of trees

Cutting of trees stacking of serviceble material with


all lifts and up to a lead of 1000 metres.

(i) Girth from 300mm to 600mm


Unit=Each
Taking output= 40nos.
a) Labour
Mate day 0.960 0.960 0.960 310 297.60 297.60 297.60 L-12
Mazdoors day 24.000 24.000 24.000 292 7008.00 7008.00 7008.00 L-13
7305.60 7305.60 7305.60
b) Machinery
Tipper
(i) 18 cum capacity hour 1.600 2772.000 4435.20 PM6001
(ii) 14 cum capacity hour 2.000 2415.000 4830.00 PM6002
(iii) 10 cum capacity hour 2.667 2121.000 5656.71 PM6003
Sundries @1% of labour cost (a) 73.06 73.06 73.06
Total cost without (OH&CP) 11813.86 12208.66 13035.36
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 945.11 1220.87 1564.24
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 1275.90 1342.95 1459.96
Rate for each tree = (a+b+c+d)/40 350.87 369.31 401.49
Say 350.90 369.30 401.50
(ii) Girth from 600mm to 900mm
Unit= Each
Taking output= 30nos
a) Labour
Mate day 1.080 1.080 1.080 310.000 334.80 334.80 334.80
Mazdoors day 27.000 27.000 27.000 292.000 7884.00 7884.00 7884.00
b) Machinery 8218.80 8218.80 8218.80
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Tipper
(i) 18 cum capacity hour 1.500 2772.000 4158.00 PM6001
(ii) 14 cum capacity hour 2.000 2415.000 4830.00 PM6002
(iii) 10 cum capacity hour 3.750 2121.000 7953.75 PM6003
Sundries @1% of labour cost (a) 82.19 82.19 82.19
Total cost without (OH&CP) 12458.99 13130.99 16254.74
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 996.72 1313.10 1950.57
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 1345.57 1444.41 1820.53
Rate for each tree = (a+b+c+d)/30 493.38 529.62 667.53
Say 493.40 529.60 667.50
(iii) Girth from 900mm to 1800mm
Unit= Each
Taking output= 25nos
a) Labour
Mate day 2.000 2.000 2.000 310.000 620.00 620.00 620.00 L-12
Mazdoors day 50.000 50.000 50.000 292.000 14600.00 14600.00 14600.00 L-13
15220.00 15220.00 15220.00
b) Machinery
Tipper
(i) 18 cum capacity hour 1.250 2772.000 3465.00 PM6001
(ii) 14 cum capacity hour 1.667 2415.000 4025.81 PM6002
(iii) 10 cum capacity hour 3.125 2121.000 6628.13 PM6003
Sundries @1% of labour cost (a) 152.20 152.20 152.20
Total cost without (OH&CP) 18837.20 19398.01 22000.33
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1506.98 1939.80 2640.04
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2034.42 2133.78 2464.04
Rate for each tree = (a+b+c+d)/25 895.14 938.86 1084.18
Say 895.10 938.90 1084.20
(iv) Girth above 1800mm
Unit= Each
Taking output= 20nos
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
a) Labour
Mate day 3.200 3.200 3.200 310.000 992.00 992.00 992.00 L-12
Mazdoors day 80.000 80.000 80.000 292.000 23360.00 23360.00 23360.00 L-13
b) Machinery 24352.00 24352.00 24352.00
Tipper
hour 1.667 2772.000 4620.92 PM6001
(ii) 14 cum capacity hour 2.500 2415.000 6037.50 PM6002
(iii) 10 cum capacity hour 5.000 2121.000 10605.00 PM6003
Sundries @1% of labour cost (a) 243.52 243.52 243.52
Total cost without (OH&CP) 29216.44 30633.02 35200.52
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 2337.32 3063.30 4224.06
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3155.38 3369.63 3942.46
Rate for each tree = (a+b+c+d)/20 1735.46 1853.30 2168.35
Say 1735.50 1853.30 2168.40

Note: All the serviceable material rsulting from tree cutting would be handed over to the employer. for the
all above items.

Removal of stumps and roots including


2.01 201 B backfillinbg with suitable material to required
compaction
Removal of stumps, roots, staking of serviceable
material with all lifts up to a lead of 1000 metres and
earth filling in the depression/ pit.
(i) Girth from 300mm to 600mm
Unit= Each
Taking output=40nos.
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery 304.40 304.40 304.40
Hydraulic Excavator
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
(i) 1.2 cum bucket capacity hour 5.000 3388.000 16940.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.500 3021.000 16615.50 PM3004
(iii) 0.9 cum bucket capacity hour 6.500 2702.000 17563.00 PM3005
Tipper
(i) 18 cum capacity hour 0.727 2772.000 2015.24 PM6001
(ii) 14 cum capacity hour 1.000 2415.000 2415.00 PM6002
(iii) 10 cum capacity hour 1.333 2121.000 2827.29 PM6003
19259.64 19334.90 20694.69
Total cost without (OH&CP)
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1540.77 1933.49 2483.36
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2080.04 2126.84 2317.81
Rate for each tree = (a+b+c+d)/40 572.01 584.88 637.40
Say 572.00 584.90 637.40
(ii) Girth from 600mm to 900mm
Unit= Each
Taking output=30nos.
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery 304.40 304.40 304.40
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3388.000 16940.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.500 3021.000 16615.50 PM3004
(iii) 0.9 cum bucket capacity hour 6.500 2702.000 17563.00 PM3005
Tipper
(i) 18 cum capacity hour 0.750 2772.000 2079.00 PM6001
(ii) 14 cum capacity hour 1.000 2415.000 2415.00 PM6002
(iii) 10 cum capacity hour 1.500 2121.000 3181.50 PM6003
Total cost without (OH&CP) 19323.40 19334.90 21048.90
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1545.87 1933.49 2525.87
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2086.93 2126.84 2357.48
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Rate for each tree = (a+b+c+d)/30 765.21 779.84 864.41
Say 765.20 779.80 864.40
(iii) Girth from 900mm to 1800mm
Unit= Each
Taking output=25nos.
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery 304.40 304.40 304.40
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3388.000 16940.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.500 3021.000 16615.50 PM3004
(iii) 0.9 cum bucket capacity hour 6.500 2702.000 17563.00 PM3005
Tipper
(i) 18 cum capacity hour 0.758 2772.000 2101.18 PM6001
(ii) 14 cum capacity hour 1.000 2415.000 2415.00 PM6002
(iii) 10 cum capacity hour 1.471 2121.000 3119.99 PM6003
Total cost without (OH&CP) 19345.58 19334.90 20987.39
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1547.65 1933.49 2518.49
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2089.32 2126.84 2350.59
Rate for each tree = (a+b+c+d)/25 919.30 935.81 1034.26
Say 919.30 935.80 1034.30
(iv) Girth above 1800mm
Unit= Each
Taking output=20nos.
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3388.000 16940.00 PM3003
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
(ii) 1.1 cum bucket capacity hour 5.500 3021.000 16615.50 PM3004
(iii) 0.9 cum bucket capacity hour 6.500 2702.000 17563.00 PM3005
Tipper
(i) 18 cum capacity hour 0.714 2772.000 1979.21 PM6001
(ii) 14 cum capacity hour 1.000 2415.000 2415.00 PM6002
(iii) 10 cum capacity hour 1.429 2121.000 3030.91 PM6003
Total cost without (OH&CP) 19223.61 19334.90 20898.31
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1537.89 1933.49 2507.80
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2076.15 2126.84 2340.61
Rate for each tree = (a+b+c+d)/20 1141.88 1169.76 1287.34
1141.90 1169.80 1287.30
Note: All the serviceable material resulting from girth removal would be handed over to the employer for
the all above items.

2.02 201 Clearing Grass and Removal of Rubish

Clearing grass and removal of rubbish up to a distance


of 50 metres outside the periphery of the area

By Manual Means
Unit = Hectare
Taking output= 1 Hectare
a) Labour
Mate day 2.000 2.000 2.000 310.000 620.00 620.00 620.00 L-12
Mazdoor day 50.000 50.000 50.000 292.000 14600.00 14600.00 14600.00 L-13
Total cost without (OH&CP) 15220.00 15220.00 15220.00
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 1217.60 1522.00 1826.40
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 1643.76 1674.20 1704.64
Rate per Hectare = (a+b+c) 18081.36 18416.20 18751.04
18081.40 18416.20 18751.00
2.03 201 Clearing and Grubbing road land
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, sapling and
tress girth upto 300 mm, removal of stumps of tree cut
earlier and disposal of unserviceable materials and
stacking of sericeable material to be used of auctioned,
up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150mm in
thickness.

Unit= Hectare
Taking output= 1 Hectare
(i) By Manual means:-
A In area of light jungle
a) Labour
Mate day 6.000 6.000 6.000 310.000 1860.00 1860.00 1860.00 L-12
Mazdoor day 150.000 150.000 150.000 292.000 43800.00 43800.00 43800.00 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 612.000 74799.86 74799.86 74799.86 PM12001
Total cost without (OH&CP) 120459.86 120459.86 120459.86
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 9636.79 12045.99 14455.18
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 13009.67 13250.59 13491.50
Rate per Hectare= a+b+c+d 143106.32 145756.44 148406.55
Say 143106.30 145756.40 148406.60
B In area of thorny jungle
a) Labour
Mate day 8.000 8.000 8.000 310.000 2480.00 2480.00 2480.00 L-12
Mazdoor day 200.000 200.000 200.000 292.000 58400.00 58400.00 58400.00 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 612.000 74799.86 74799.86 74799.86 PM12001
Total cost without (OH&CP) 135679.86 135679.86 135679.86
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 10854.39 13567.99 16281.58
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 14653.43 14924.79 15196.14
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Rate per Hectare = (a+b+c+d) 161187.68 164172.64 167157.59
(ii) By Mechanical means using dozer Say 161187.70 164172.60 167157.60
A In area of light jungle
a) Labour
Mate day 0.080 0.080 0.080 310.000 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.000 584.00 584.00 584.00 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 5.952 6461 38455.87 PM1001
(ii) Dozer (175 HP) hour 7.692 4930 37921.56 PM1002
(iii) Dozer (90 Hp) hour 13.889 3274 45472.59 PM1003
Tipper
For tranportation to dumping yard considering lead @ 1km
(i) 18 cum capacity t.km 1500.000 5.940 8910.00 PM72001
(ii) 14 cum capacity t.km 1500.000 6.630 9945.00 PM73001
(iii) 10 cum capacity t.km 1500.000 8.080 12120.00 PM74001
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1000.000 90.960 90960.00 0.00 0.00 PM77001
capacity loader
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1000.000 89.34 0.00 89340.00 0.00 PM77002
capacity loader.
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1000.000 118.140 0.00 0.00 118140.00 PM77003
capacity loader.
Total cost without (OH&CP) 138934.67 137815.36 176341.39
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 11114.77 13781.54 21160.97
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 15004.94 15159.69 19750.24
Rate per Hectare = (a+b+c+d) 165054.39 166756.59 217252.59
Say 165054.40 166756.60 217252.60
2.03 B In area of thorny jungle
a) Labour
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Mate day 0.080 0.080 0.080 310.000 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.000 584.00 584.00 584.00 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 7.440 6461 48069.84 0.00 0.00 PM1001
(ii) Dozer (175 HP) hour 9.615 4930 0.00 47401.95 0.00 PM1002
(iii) Dozer (90 Hp) hour 17.361 3274 0.00 0.00 56839.91 PM1003
Tipper
For tranportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 1500.000 5.940 8910.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1500.000 6.630 0.00 9945.00 0.00 PM73001
(iii) 10 cum capacity t.km 1500.000 8.080 0.00 0.00 12120.00 PM74001
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1000.000 90.960 90960.00 0.00 0.00 PM77001
capacity loader
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1000.000 89.34 0.00 89340.00 0.00 PM77002
capacity loader
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1000.000 118.140 0.00 0.00 118140.00 PM77003
capacity loader
Total cost without (OH&CP) 148548.64 147295.75 187708.71
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 11883.89 14729.58 22525.05
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 16043.25 16202.53 21023.38
Rate per Hectare = (a+b+c+d) 176475.78 178227.86 231257.14
Say 176475.80 178227.90 231257.10
2.03 (iii) By Mechanical Means using Motor grader
A In area of light jungle
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
b) Machinery
Motor Grader
(i) Motor grader 4.3 metre blade hour 4.032 5900.000 23788.80 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 4.864 5398.000 0.00 26255.87 0.00 PM2002
(iii) motor grader 3.35 metre blade hour 5.423 2982.000 0.00 0.00 16171.39 PM2003
Tipper
For tranportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 1500.000 5.940 8910.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1500.000 6.630 0.00 9945.00 0.00 PM73001
(iii) 10 cum capacity t.km 1500.000 8.080 0.00 0.00 12120.00 PM74001
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1000.000 90960.00 0.00 0.00 PM77001
capacity loader 90.960
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1000.000 0.00 89340.00 0.00 PM77002
capacity loader 89.34
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1000.000 0.00 0.00 118140.00 PM77003
capacity loader 118.140
Total cost without (OH&CP) 123963.20 125845.27 146735.79
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 9917.06 12584.53 17608.29
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 13388.03 13842.98 16434.41
Rate per Hectare = (a+b+c+d) 147268.28 152272.78 180778.49
Say 147268.30 152272.80 180778.50
2.03 B In area of thorny Jungle
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.3 metre blade hour 5.040 5900.000 29736.00 0.00 0.00 PM2001
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
(ii) Motor grader 3.70 metre blade hour 6.080 5398.000 0.00 32819.84 0.00 PM2002
(iii) motor grader 3.35 metre blade hour 6.779 2982.000 0.00 0.00 20214.98 PM2003
Tipper
For tranportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1500.000 5.940 8910.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1500.000 6.630 0.00 9945.00 0.00 PM73001
(iii) 10 cum capacity t.km 1500.000 8.080 0.00 0.00 12120.00 PM74001
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1000.000 90960.00 0.00 0.00 PM77001
capacity loader 90.960
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1000.000 0.00 89340.00 0.00 PM77002
capacity loader 89.34
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1000.000 0.00 0.00 118140.00 PM77003
capacity loader 118.140
Total cost without (OH&CP) 129910.40 132409.24 150779.38
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 10392.83 13240.92 18093.53
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 14030.32 14565.02 16887.29
Rate per Hectare = (a+b+c+d) 154333.56 160215.18 185760.19
Say 154333.60 160215.20 185760.20
2.04 202 Dismantling of Structures

Dismantling of existing structures like culverts,


bridges, retaining walls and other structure comprising
of masonry, cement concree, wood work, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with allk lifts and lead of 1000 metres

Unit- cum
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Taking output-=1.25 cum
(i) Lime/ Cement concrete
I By Manual means
Lime concrete, cement concrete grade M-10 and
A
below
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoor for dismantling and loading day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery
Tractor- trolley (considering 15 min loading
hour 0.299 0.299 0.299 612.000 182.99 182.99 182.99 PM12001
time)
Total cost without (OH&CP) 487.39 487.39 487.39
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 38.99 48.74 58.49
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 52.64 53.61 54.59
Rate for 1.25 cum = (a+b+c+d) 579.02 589.74 600.46
Rate per cum= (a+b+c+d)/1.25 463.21 471.79 480.37
Say 463.20 471.80 480.40
2.04 B Cement concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 0.050 0.050 310.000 15.50 15.50 15.50 L-12
Mazdoor for dismantling and loading day 1.250 1.250 1.250 292.000 365.00 365.00 365.00 L-13
b) Machinery
Tractor- trolley (considering 15 min loading
hour 0.299 0.299 0.299 612.000 182.99 182.99 182.99 PM12001
time)
Total cost without (OH&CP) 563.49 563.49 563.49
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 45.08 56.35 67.62
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 60.86 61.98 63.11
Cost for 1.25 cum = (a+b+c+d) 669.42 681.82 694.22
Rate per cum= (a+b+c+d)/1.25 535.54 545.46 555.37
Say 535.50 545.50 555.40
Prestressed/ Reinforced cement concrete grade M-
2.04 C
20 & above
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
a) Labour
Mate day 0.150 0.150 0.150 310.000 46.50 46.50 46.50 L-12
Blacksmith day 0.250 0.250 0.250 351.000 87.75 87.75 87.75 L-25
Mazdoor for dismantling and loading day 3.500 3.500 3.500 292.000 1022.00 1022.00 1022.00 L-13
b) Machinery
Tractor- trolley (considering 15 min loading
hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
time)
Total cost without (OH&CP) 1313.53 1313.53 1313.53
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 105.08 131.35 157.62
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 141.86 144.49 147.12
Cost for 1.25 cum = (a+b+c+d) 1560.48 1589.38 1618.27
Rate per cum= (a+b+c+d)/1.25 1248.38 1271.50 1294.62
Say 1248.40 1271.50 1294.60
2.04 II By Mechanical means
A Cement Concrete Grade M-15 & M-20
Unit= cum
Taking output= 1.25 cum
a) Labour
Mate day 0.020 0.020 0.020 310.000 6.20 6.20 6.20 L-12
Mazdoor for loading and unloading &
day 0.500 0.500 0.500 292.000 146.00 146.00 146.00 L-13
pneumatic breaker
b) Machinery
Air compressor 250cfm hour 0.625 0.625 0.625 416.000 260.00 260.00 260.00 PM15001
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.000 257.50 257.50 257.50 PM4001
Tipper
For tranportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1.875 5.940 11.14 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1.875 6.630 0.00 12.43 0.00 PM73001
(iii) 10 cum capacity t.km 1.875 8.080 0.00 0.00 15.15 PM74001
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Loading & unloading charges for disposed of
material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1.250 113.70 0.00 0.00 PM77001
capacity loader 90.960
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1.250 0.00 111.68 0.00 PM77002
capacity loader 89.34
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1.250 0.00 0.00 147.68 PM77003
capacity loader 118.140
Total cost without (OH&CP) 794.54 793.81 832.53
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 63.56 79.38 99.90
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 85.81 87.32 93.24
Cost for 1.25 cum = (a+b+c+d) 943.91 960.51 1025.67
Rate per cum = (a+b+c+d)/1.25 755.13 768.40 820.54
Say 755.10 768.40 820.50
Prestressed/ Reinforced cement concrete grade M-
2.04 II B
20 & above
Unit= cum
Taking output= 1.25 cum
a) Labour
Mate day 0.036 0.036 0.036 310.000 11.16 11.16 11.16 L-12
Mazdoor with Pneumatic breaker and for
day 0.910 0.910 0.910 292.000 265.72 265.72 265.72 L-13
loading and unloading .
Blacksmith day 0.250 0.250 0.250 351.000 87.75 87.75 87.75 L-25
b) Machinery
Air compressor 250cfm hour 0.625 0.625 0.625 416.000 260.00 260.00 260.00 PM15001
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.000 257.50 257.50 257.50 PM4001
Tipper
For tranportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1.875 5.940 11.14 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1.875 6.630 0.00 12.43 0.00 PM73001
(iii) 10 cum capacity t.km 1.875 8.080 0.00 0.00 15.15 PM74001
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Loading & unloading charges for disposed of
material
(i) Using by 18 cum capacity Tipper & 3.1 cum
cum 1.250 113.70 0.00 0.00 PM77001
capacity loader 90.960
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 1.250 0.00 111.68 0.00 PM77002
capacity loader 89.34
(iii) Using by 10 cum capacity tipper & 1 cum
cum 1.250 0.00 0.00 147.68 PM77003
capacity loader 118.140
Total cost without (OH&CP) 1006.97 1006.24 1044.96
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 80.56 100.62 125.39
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 108.75 110.69 117.03
Cost for 1.25 cum = (a+b+c+d) 1196.28 1217.55 1287.38
Rate per cum = (a+b+c+d)/1.25 957.02 974.04 1029.91
Say 957.00 974.00 1029.90
2.04 (ii) Dismantling Brick/ tile work
By Manual means
A In lime mortar
a) Labour
Mate day 0.020 0.020 0.020 310.000 6.20 6.20 6.20 L-12
Mazdoor for dismantling and loading day 0.500 0.500 0.500 292.000 146.00 146.00 146.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 309.48 309.48 309.48
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 24.76 30.95 37.14
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 33.42 34.04 34.66
Cost for 1.25 cum = (a+b+c+d) 367.67 374.48 381.28
Rate per cum= (a+b+c+d)/1.25 294.13 299.58 305.03
Say 294.10 299.60 305.00
2.04 B In cement mortar
a) Labour
Mate day 0.030 0.030 0.030 310.000 9.30 9.30 9.30 L-12
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small

Mazdoor for dismantling and loading-unloading day 0.750 0.750 0.750 292.000 219.00 219.00 219.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 385.58 385.58 385.58
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 30.85 38.56 46.27
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 41.64 42.41 43.19
Cost for 1.25 cum = (a+b+c+d) 458.07 466.56 475.04
Rate per cum= (a+b+c+d)/1.25 366.46 373.25 380.03
Say 366.50 373.20 380.00
2.04 C In Mud mortar
a) Labour
Mate day 0.016 0.016 0.016 310.000 4.96 4.96 4.96 L-12
Mazdoor for dismantling , loading and unloading. day 0.400 0.400 0.400 292.000 116.80 116.80 116.80 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 279.04 279.04 279.04
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 22.32 27.90 33.49
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 30.14 30.69 31.25
Cost for 1.25 cum = (a+b+c+d) 331.50 337.64 343.78
Rate per cum= (a+b+c+d)/1.25 265.20 270.11 275.03
Say 265.20 270.10 275.00
2.04 D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 0.014 0.014 310.000 4.34 4.34 4.34 L-12
Mazdoor for dismantling, loadingand -unloading. day 0.350 0.350 0.350 292.000 102.20 102.20 102.20 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 263.82 263.82 263.82
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 21.11 26.38 31.66
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 28.49 29.02 29.55
Cost for 1.25 cum = (a+b+c+d) 313.42 319.23 325.03
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Rate per cum= (a+b+c+d)/1.25 250.74 255.38 260.02
Say 250.70 255.40 260.00
2.04 (iii) Dismantling stone masonry
I By Manual means
A rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 0.024 0.024 310.000 7.44 7.44 7.44 L-12
Mazdoor for dismantling , loading and -unloading day 0.600 0.600 0.600 292.000 175.20 175.20 175.20 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 339.92 339.92 339.92
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 27.19 33.99 40.79
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 36.71 37.39 38.07
Cost for 1.25 cum = (a+b+c+d) 403.83 411.31 418.79
Rate per cum= (a+b+c+d)/1.25 323.06 329.05 335.03
Say 323.10 329.00 335.00
2.04 B Rubble stone masonry in cement mortar
a) Labour
Mate day 0.030 0.030 0.030 310.000 9.30 9.30 9.30 L-12
Mazdoor for dismantling , loading and -unloading day 0.750 0.750 0.750 292.000 219.00 219.00 219.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 385.58 385.58 385.58
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 30.85 38.56 46.27
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 41.64 42.41 43.19
Cost for 1.25 cum = (a+b+c+d) 458.07 466.56 475.04
Rate per cum= (a+b+c+d)/1.25 366.46 373.25 380.03
Say 366.50 373.20 380.00
2.04 C Rubble stone masonry in mud mortar
a) Labour
Mate day 0.020 0.020 0.020 310.000 6.20 6.20 6.20 L-12
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Mazdoor for dismantling ,loading and -unloading day 0.500 0.500 0.500 292.000 146.00 146.00 146.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 309.48 309.48 309.48
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 24.76 30.95 37.14
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 33.42 34.04 34.66
Cost for 1.25 cum = (a+b+c+d) 367.67 374.48 381.28
Rate per cum= (a+b+c+d)/1.25 294.13 299.58 305.03
Say 294.10 299.60 305.00
2.04 D Dry rubble masonry
a) Labour
Mate day 0.018 0.018 0.018 310.000 5.58 5.58 5.58 L-12
Mazdoor for dismantling ,loading and -unloading day 0.450 0.450 0.450 292.000 131.40 131.40 131.40 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 294.26 294.26 294.26
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 23.54 29.43 35.31
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 31.78 32.37 32.96
Cost for 1.25 cum = (a+b+c+d) 349.59 356.06 362.53
Rate per cum= (a+b+c+d)/1.25 279.67 284.85 290.03
Say 279.70 284.80 290.00
2.04 E Dismantling stone pitching/dry stone spalls.
a) Labour
Mate day 0.016 0.016 0.016 310.000 4.96 4.96 4.96 L-12
Mazdoor for dismantling ,loading and -unloading day 0.400 0.400 0.400 292.000 116.80 116.80 116.80 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 279.04 279.04 279.04
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 22.32 27.90 33.49
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 30.14 30.69 31.25
Cost for 1.25 cum = (a+b+c+d) 331.50 337.64 343.78
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Rate per cum= (a+b+c+d)/1.25 265.20 270.11 275.03
Say 265.20 270.10 275.00
Dismantling boulders laid in wire crates including
2.04 F opening of crates and stacking dismantled
materials.
a) Labour
Mate day 0.020 0.020 0.020 310.000 6.20 6.20 6.20 L-12
Mazdoor for dismantling ,loading and -unloading day 0.500 0.500 0.500 292.000 146.00 146.00 146.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 309.48 309.48 309.48
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 24.76 30.95 37.14
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 33.42 34.04 34.66
Cost for 1.25 cum = (a+b+c+d) 367.67 374.48 381.28
Rate per cum= (a+b+c+d)/1.25 294.13 299.58 305.03
Say 294.10 299.60 305.00
2.04 II By Mechanical means
Dismantling Brick/ Tile work/ rubble
A
masonary/pitching/ etc. by mechanical means
Unit=cum
Taking output=20cum
a) Labour
Mate day 0.008 0.008 0.008 310.000 2.48 2.48 2.48 L-12
Mazdoor day 0.200 0.200 0.200 292.000 58.40 58.40 58.40 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.523 3388.000 1771.92 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 0.603 3021.000 0.00 1821.66 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 0.843 2702.000 0.00 0.00 2277.79 PM3005
Tipper
For transprtation to dumping yard considering
lead @ 1km
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
(i) 18 cum capacity t.km 30.000 5.940 178.20 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 30.000 6.630 0.00 198.90 0.00 PM73001
(iii) 10 cum capacity t.km 30.000 8.080 0.00 0.00 242.40 PM74001
Loading and unloading time
(i) 18 cum capacity hour 0.523 2772.000 1449.76 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.603 2415.000 0.00 1456.25 0.00 PM6002
(iii) 10 cum capacity hour 0.843 2121.000 0.00 0.00 1788.00 PM6003
Total cost without (OH&CP) 3460.76 3537.69 4369.07
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 276.86 353.77 524.29
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 373.76 389.15 489.34
Rate for 20 Cum = (a+b+c+d) 4111.38 4280.60 5382.69
Rate per cum= (a+b+c+d)/20 205.57 214.03 269.13
Say 205.60 214.00 269.10

Wood work wrought framed and fixed in frames of


2.04 (iv)
trussess upto a height of 5m above plinth level

Unit=cum
Taking output=1.25 cum
a) Labour
Mate day 0.060 0.060 0.060 310.000 18.60 18.60 18.60 L-12
Carpenter day 0.500 0.500 0.500 394.000 197.00 197.00 197.00 L-04
Mazdoor for dismantling, loading and unloading day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery
Tractor- trolley hour 0.257 0.257 0.257 612.000 157.28 157.28 157.28 PM12001
Total cost without (OH&CP) 664.88 664.88 664.88
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 53.19 66.49 79.79
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 71.81 73.14 74.47
Rate for1.25 Cum = (a+b+c+d) 789.88 804.51 819.14
Rate per cum= (a+b+c+d)/1.25 631.91 643.61 655.31
Say 631.90 643.60 655.30
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small

Steel work in all types of sections upto a height of


2.04 (v)
5m above plinth level excluding cutting of rivet.

Unit=tonne
Taking output=1 tonne
A Including dismembring
a) Labour
Mate day 0.140 0.140 0.140 310.000 43.40 43.40 43.40 L-12
Blacksmith day 1.000 1.000 1.000 351.000 351.00 351.00 351.00 L-25
Mazdoor for dismantling, loading and unloading day 2.500 2.500 2.500 292.000 730.00 730.00 730.00 L-13
Add 2.5 percent of cost of labour for gas cutting,
28.11 28.11 28.11
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 612.000 75.28 75.28 75.28 PM12001
Total cost without (OH&CP) 1227.79 1227.79 1227.79
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 98.22 122.78 147.33
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 132.60 135.06 137.51
Rate per tonne = (a+b+c+d) 1458.61 1485.62 1512.63
Say 1458.60 1485.60 1512.60
2.04 B Excluding dismembering
a) Labour
Mate day 0.100 0.100 0.100 310.000 31.00 31.00 31.00 L-12
Blacksmith day 0.500 0.500 0.500 351.000 175.50 175.50 175.50 L-25
Mazdoor for dismantling, loading and unloading day 2.000 2.000 2.000 292.000 584.00 584.00 584.00 L-13
Add 2.5 percent of cost of labour for gas cutting,
19.76 19.76 19.76
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 612.000 75.28 75.28 75.28 PM12001
Total cost without (OH&CP) 885.54 885.54 885.54
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 70.84 88.55 106.26
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 95.64 97.41 99.18
Rate per tonne = (a+b+c+d) 1052.02 1071.50 1090.98
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Say 1052.00 1071.50 1091.00
2.04 C Extra over item no (v) A and (v)B for cutting rivets
Unit=each
Taking output=10 rivets
a) Labour
Mate day 0.010 0.010 0.010 310.000 3.10 3.10 3.10
Blacksmith day 0.130 0.130 0.130 351.000 45.63 45.63 45.63
Mazdoor day 0.130 0.130 0.130 292.000 37.96 37.96 37.96
Total cost without (OH&CP) 86.69 86.69 86.69
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 6.94 8.67 10.40
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 9.36 9.54 9.71
Rate for 10 rivets = (a+b+c) 102.99 104.89 106.80
Rate for each rivet =(a+b+c)/10 10.30 10.49 10.68
Say 10.30 10.50 10.70
Scrapping of bricks dismantled from brick work
2.04 (vi)
including stacking
Unit= numbers
Taking output= 1000 numbers
A In Lime/Cement mortar
a) Labour
Mate day 0.140 0.140 0.140 310.000 43.40 43.40 43.40 L-12
Mazdoor day 3.500 3.500 3.500 292.000 1022.00 1022.00 1022.00 L-13
Total cost without (OH&CP) 1065.40 1065.40 1065.40
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 85.23 106.54 127.85
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 115.06 117.19 119.32
Rate for 1000 Nos = (a+b+c) 1265.70 1289.13 1312.57
Rate for each rivet =(a+b+c)/1000 1.27 1.29 1.31
2.04 B In mud mortar Say 1.30 1.30 1.30
a) Labour
Mate day 0.050 0.050 0.050 310.000 15.50 15.50 15.50 L-12
Mazdoor day 1.250 1.250 1.250 292.000 365.00 365.00 365.00 L-13
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Total cost without (OH&CP) 380.50 380.50 380.50
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 30.44 38.05 45.66
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 41.09 41.86 42.62
Rate for 1000 Nos = (a+b+c) 452.03 460.41 468.78
Rate for each rivet =(a+b+c)/1000 0.45 0.46 0.47
2.04 (vii) Scraping of stone from dismantled stone masonry Say 0.50 0.50 0.50
Unit=cum
Taking output=1 cum
A In Cement and lime mortar
a) Labour
Mate day 0.056 0.056 0.056 310.000 17.36 17.36 17.36 L-12
Mazdoor day 1.400 1.400 1.400 292.000 408.80 408.80 408.80 L-13
Total cost without (OH&CP) 426.16 426.16 426.16
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 34.09 42.62 51.14
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 46.03 46.88 47.73
Rate per Cum = (a+b+c) 506.28 515.65 525.03
Say 506.30 515.70 525.00
2.04 B In Mud mortar
a) Labour
Mate day 0.012 0.012 0.012 310.000 3.72 3.72 3.72 L-12
Mazdoor day 0.300 0.300 0.300 292.000 87.60 87.60 87.60 L-13
Total cost without (OH&CP) 91.32 91.32 91.32
b) Overhead charges on(a) (@ 8%) (@ 10%) (@ 12%) 7.31 9.13 10.96
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 9.86 10.05 10.23
Rate per Cum = (a+b+c) 108.49 110.50 112.51
Say 108.50 110.50 112.50
Scraping plaster in lime or cement mortar from
2.04 (viii)
Brick/Stone Masonry
Unit=sqm
Taking output= 100sqm
a) Labour
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Mate day 0.160 0.160 0.160 310.000 49.60 49.60 49.60 L-12
Mazdoor for scraping and loading day 4.000 4.000 4.000 292.000 1168.00 1168.00 1168.00 L-13
b) Machinery
Tractor-trolley hour 0.308 0.308 0.308 612.000 188.50 188.50 188.50 PM12001
Total cost without (OH&CP) 1406.10 1406.10 1406.10
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 112.49 140.61 168.73
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 151.86 154.67 157.48
Rate per sqm= (a+b+c+d)/100 16.70 17.01 17.32
Say 16.70 17.00 17.30

Removing all type of Hume pipes and stacking


2.04 (ix) within a lead of 1000 metres including Earthwork
and Dismantling of Masonry Works.

A Upto 600mm dia


Unit= metre
Taking output= 15 metre
a) Labour
Mate day 0.084 0.094 0.105 310.000 26.04 29.14 32.55 L-12
Mazdoor day 2.088 2.346 2.617 292.000 609.70 685.03 764.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.176 3388.000 7372.29 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 2.693 3021.000 0.00 8135.55 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 3.235 2702.000 0.00 0.00 8740.97 PM3005
Tipper
For loading & unloading time & for transportation of
excess material to dumping yard considering lead @
1km
(i) 18 cum capacity hour 2.226 2772.000 6170.47 0.00 0.00 PM6001
(ii) 14 cum capacity hour 2.743 2415.000 0.00 6624.35 0.00 PM6002
(iii) 10 cum capacity hour 3.285 2121.000 0.00 0.00 6967.49 PM6003
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Total cost without (OH&CP) 14178.50 15474.07 16505.17
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1134.28 1547.41 1980.62
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 1531.28 1702.15 1848.58
Rate for 15 meter = (a+b+c+d) 16844.05 18723.62 20334.37
Rate per metre= (a+b+c+d)/15 1122.94 1248.24 1355.62
Say 1122.90 1248.20 1355.60
B Above 600mm to 900mm dia
Unit= metre
Taking output= 15 metre
a) Labour
Mate day 0.094 0.104 0.115 310.000 29.14 32.24 35.65 L-12
Mazdoor day 2.338 2.596 2.867 292.000 682.70 758.03 837.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.676 3388.000 9066.29 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 3.193 3021.000 0.00 9646.05 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 3.735 2702.000 0.00 0.00 10091.97 PM3005
Tipper for loading & unloading.
For loading & unloading time & for transportation of
excess nmaterial to dumping yard considering lead @
1km
(i) 18 cum capacity hour 2.726 2772.000 7556.47 0.00 0.00 PM6001
(ii) 14 cum capacity hour 3.243 2415.000 0.00 7831.85 0.00 PM6002
(iii) 10 cum capacity hour 3.785 2121.000 0.00 0.00 8027.99 PM6003
Total cost without (OH&CP) 17334.60 18268.17 18992.77
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1386.77 1826.82 2279.13
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 1872.14 2009.50 2127.19
Rate for 15 metre = (a+b+c+d) 20593.50 22104.49 23399.09
Rate per metre= (a+b+c+d)/15 1372.90 1473.63 1559.94
Say 1372.90 1473.60 1559.90
C Above 900mm
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Unit= metre
Taking output= 15 metre
a) Labour
Mate day 0.104 0.114 0.135 310.000 32.24 35.34 41.85 L-12
Mazdoor day 2.588 2.846 3.367 292.000 755.70 831.03 983.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.176 3388.000 10760.29 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 3.693 3021.000 0.00 11156.55 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 4.735 2702.000 0.00 0.00 12793.97 PM3005
Tipper for loading & unloading.
For loading & unloading time & for
transportation of excess nmaterial to dumping
yard considering lead @ 1km
(i) 18 cum capacity hour 3.226 2772.000 8942.47 0.00 0.00 PM6001
(ii) 14 cum capacity hour 3.743 2415.000 0.00 9039.35 0.00 PM6002
(iii) 10 cum capacity hour 4.785 2121.000 0.00 0.00 10148.99 PM6003
Total cost without (OH&CP) 20490.70 21062.27 23967.97
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1639.26 2106.23 2876.16
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2213.00 2316.85 2684.41
Rate for 15metre = (a+b+c+d) 24342.95 25485.35 29528.54
Rate per metre= (a+b+c+d)/15 1622.86 1699.02 1968.57
Say 1622.90 1699.00 1968.60
1. The excavation of earth, dismantling of stone masonry work in head walls and protection work is
Note
not included which is to be measured and paid separately.

2. Credit for retrieved stone from masonry work may be taken as per actual availability.

2.05 202 Dismantling of flexible pavements


SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
Unit=cum
Taking output= 1 cum
(i) By Manual means
A Bituminous courses
a) Labour
Mate day 0.060 0.060 0.060 310.000 18.60 18.60 18.60 L-12
Mazdoor for dismantling, loading and unloading day 1.500 1.500 1.500 292.000 438.00 438.00 438.00 L-13
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 612.000 102.20 102.20 102.20 PM12001
Total cost without (OH&CP) 558.80 558.80 558.80
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 44.70 55.88 67.06
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 60.35 61.47 62.59
Rate per cum = (a+b+c+d) 663.86 676.15 688.45
2.05 B Granular courses Say 663.90 676.20 688.40
a) Labour
Mate day 0.040 0.040 0.040 310.000 12.40 12.40 12.40 L-12
Mazdoor for dismantling, loading and unloading day 1.000 1.000 1.000 292.000 292.00 292.00 292.00 L-13
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 612.000 102.20 102.20 102.20 PM12001
Total cost without (OH&CP) 406.60 406.60 406.60
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 32.53 40.66 48.79
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 43.91 44.73 45.54
Rate per cum = (a+b+c+d) 483.05 491.99 500.94
Say 483.00 492.00 500.90
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Dismantling of flexible pavements and disposal of
dismantled materials upto a leadof 1000 metres,
2.05 202
stacking serviceable and unserviceable materials
separately
(ii) By Mechanical means
A Bituminous courses
Unit=cum
Taking output= 20cum
a) Labour
Mate day 0.024 0.027 0.033 310.000 7.44 8.37 10.23 L-12
Mazdoor for dismantling, loading and unloading day 0.588 0.667 0.833 292.000 171.70 194.76 243.24 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity considering output
hour 2.353 3388.000 7971.96 0.00 0.00 PM3003
85 sqm/8.5 cum per hour
(ii) 1.1 cum bucket capacity considering output
hour 2.667 3021.000 0.00 8057.01 0.00 PM3004
75 sqm/7.5 cum per hour
(iii) 0.9 cum bucket capacity considering output
hour 3.333 2702.000 0.00 0.00 9005.77 PM3005
60 sqm/6 cum per hour
Tipper for transportation
(i) 18 cum capacity t.km 46.000 5.940 273.24 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 46.000 6.630 0.00 304.98 0.00 PM73001
(iii) 10 cum capacity t.km 46.000 8.080 0.00 0.00 371.68 PM74001
Total cost without (OH&CP) 8424.34 8565.12 9630.91
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 673.95 856.51 1155.71
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 909.83 942.16 1078.66
Ratefor 20 cum = (a+b+c+d) 10008.12 10363.80 11865.28
Rate per cum= (a+b+c+d)/20 500.41 518.19 593.26
Say 500.40 518.20 593.30
B Granular Courses
Unit=cum
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Taking output= 250cum
a) Labour
Mate day 0.029 0.033 0.046 310.000 8.99 10.23 14.26 L-12

Mazdoor for dismantling, loading and unloading day 0.718 0.827 1.156 292.000 209.66 241.48 337.55 L-13

b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.873 3388.000 9733.72 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 3.308 3021.000 0.00 9993.47 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 4.625 2702.000 0.00 0.00 12496.75 PM3005
Tipper for transportation
(i) 18 cum capacity t.km 575.000 5.940 3415.50 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 575.000 6.630 0.00 3812.25 0.00 PM73001
(iii) 10 cum capacity t.km 575.000 8.080 0.00 0.00 4646.00 PM74001
Total cost without (OH&CP) 13367.87 14057.43 17494.56
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 1069.43 1405.74 2099.35
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 1443.73 1546.32 1959.39
Rate for 250 cum = (a+b+c+d) 15881.03 17009.49 21553.30
Rate per cum = (a+b+c+d)/250 63.52 68.04 86.21
Say 63.50 68.00 86.20
2.06 202 Dismantling of cement concrete pavement

Dismantling of cement concrete pavement by


mechanical means using pneumatic tools, breaking to
pieces not exceeding 0.02 cum in volume and stock
piling at designated locations and disposal of
dismantled materials up to a alead of 1000 metres,
stackiung serviceable and unserviceable materials
separately

Unit=cum
Taking output=60cum
a) Labour
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Mate day 0.120 0.120 0.120 310.000 37.20 37.20 37.20 L-12
Mazdoor day 3.000 3.000 3.000 292.000 876.00 876.00 876.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 6.841 3388.000 23177.31 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 8.048 3021.000 0.00 24313.01 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 9.121 2702.000 0.00 0.00 24644.94 PM3005
Jack hammer hour 6.841 9.146 12.162 206.000 1409.25 1884.08 2505.37 PM4001
Air compressor 250 cfm with 2 leads of pneumatic
hour 2.880 2.880 2.880 416.000 1198.08 1198.08 1198.08 PM15001
breaker @1 cum per hour
Pneumatic breaker hour 5.760 5.760 5.760 206.000 1186.56 1186.56 1186.56 PM4001
Concrete joint cutting machine hour 8.000 8.000 8.000 175.000 1400.00 1400.00 1400.00 PM61002
Tipper
for transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t.km 180.000 5.940 1069.20 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 180.000 6.630 0.00 1193.40 0.00 PM73001
(iii) 10 cum capacity t.km 180.000 8.080 0.00 0.00 1454.40 PM74001
For loading and unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity tipper & 3.1 cum
cum 72.000 6549.12 0.00 0.00 PM77001
capacity loader 90.960
(ii) Using by 14 cum capacity tipper & 2.1 cum
cum 72.000 0.00 6432.48 0.00 PM77002
capacity loader 89.34
(i) Using by 10 cum capacity tipper & 1 cum capacity
cum 72.000 0.00 0.00 8506.08 PM77003
loader 118.140
Total cost without (OH&CP) 36902.71 38520.80 41808.63
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 2952.22 3852.08 5017.04
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3985.49 4237.29 4682.57
Cost for 60 cum = (a+b+c+d) 43840.42 46610.17 51508.24
Rate per cum= (a+b+c+d)/60 730.67 776.84 858.47
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Say 730.70 776.80 858.50
2.07 202 Dismantling of guard rails

Dismantling of guard rails by manual means and


disposal of dismantled material with all lifts and up to
a lead of 1000 metres, stacking serviceable materials
and unserviceable materials separately

Unit= running metre


Takng output= 1 metre
a) Labour
Mate day 0.006 0.006 0.006 310.000 1.86 1.86 1.86 L-12
Mazdoor including loading and unloading day 0.150 0.150 0.150 292.000 43.80 43.80 43.80 L-13
b) Machinery
Tractor- trolley hour 0.006 0.006 0.006 612.000 3.67 3.67 3.67 PM12001
Total cost without (OH&CP) 49.33 49.33 49.33
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 3.95 4.93 5.92
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 5.33 5.43 5.53
Rate per metre = (a+b+c+d) 58.61 59.69 60.78
Say 58.60 59.70 60.80
2.08 202 Dismantling of kerb stone
Dismantling kerb stone by manual means and disposal
of dismantled material with all lifts and up to a lead of
1000 metres
Unit= running metre
Takng output= 10 metre
a) Labour
Mate day 0.006 0.006 0.006 310.000 1.86 1.86 1.86 L-12
Mazdoor including loading and unloading day 0.150 0.150 0.150 292.000 43.80 43.80 43.80 L-13
b) Machinery
Tractor- trolley hour 0.139 0.139 0.139 612.000 85.07 85.07 85.07 PM12001
Total cost without (OH&CP) 130.73 130.73 130.73
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 10.46 13.07 15.69
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 14.12 14.38 14.64
Cost for 10 meter = (a+b+c+d) 155.30 158.18 161.06
Rate per metre =(a+b+c+d)/10 15.53 15.82 16.11
Say 15.50 15.80 16.10
2.09 202 Dismantling of kerb stone channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to
a lead of 1000 metres
Unit= running metre
Takng output= 10 metre
a) Labour
Mate day 0.009 0.009 0.009 310.000 2.79 2.79 2.79 L-12
Mazdoor including loading and unloading day 0.225 0.225 0.225 292.000 65.70 65.70 65.70 L-13
b) Machinery
Tractor- trolley hour 0.170 0.170 0.170 612.000 104.04 104.04 104.04 PM12001
Total cost without (OH&CP) 172.53 172.53 172.53
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 13.80 17.25 20.70
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 18.63 18.98 19.32
Cost for 10 meter = (a+b+c+d) 204.97 208.76 212.56
Rate per metre =(a+b+c+d)/10 20.50 20.88 21.26
Say 20.50 20.90 21.30
2.10 202 Dismantling of kilometre stone
Dismantling of kilometre stone including cutting of
earth , foundation and disposal of dismantled material
with all lifts and lead up to 1000 metres and back
filling of pit
Unit= each
Takng output= one KM stone
A 5th KM stone
Quantity of cement concrete= 0.392
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
a) Labour
Mate day 0.030 0.030 0.030 310.000 9.30 9.30 9.30 L-12
Mazdoor day 0.750 0.750 0.750 292.000 219.00 219.00 219.00 L-13
b) Machinery
Tractor- trolley hour 0.150 0.150 0.150 612.000 91.80 91.80 91.80 PM12001
Total cost without (OH&CP) 320.10 320.10 320.10
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 25.61 32.01 38.41
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 34.57 35.21 35.85
Rate for one 5th KM Stone = (a+b+c+d) 380.28 387.32 394.36
Say 380.30 387.30 394.40
B Ordinary KM Stone
Quantity of cement concrete=0.269 cum
a) Labour
Mate day 0.020 0.020 0.020 310.000 6.20 6.20 6.20 L-12
Mazdoor day 0.500 0.500 0.500 292.000 146.00 146.00 146.00 L-13
b) Machinery
Tractor- trolley hour 0.100 0.100 0.100 612.000 61.20 61.20 61.20 PM12001
Total cost without (OH&CP) 213.40 213.40 213.40
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 17.07 21.34 25.61
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 23.05 23.47 23.90
Rate for 1 ordinary km stone = (a+b+c+d) 253.52 258.21 262.91
Say 253.50 258.20 262.90
C Hectometre Stone
Quantity of cement concrete=0.048 cum
a) Labour
Mate day 0.004 0.004 0.004 310.000 1.24 1.24 1.24 L-12
Mazdoor day 0.100 0.100 0.100 292.000 29.20 29.20 29.20 L-13
b) Machinery
Tractor- trolley hour 0.020 0.020 0.020 612.000 12.24 12.24 12.24 PM12001
Total cost without (OH&CP) 42.68 42.68 42.68
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 3.41 4.27 5.12
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 4.61 4.69 4.78
Rate for 1 Hectometre stone = (a+b+c+d) 50.70 51.64 52.58
Say 50.70 51.60 52.60
2.11 202 Dismantling of fencing
Dismantling of barbed wire fencing/ wire mesh
fencing including posts, foundation concrete, back
filling of pit by manual means including disposal of
dismantled materials with all lifts and up to a lead of
1000 metres stacking serviceable material and
unserviceable material separately.

Unit=running metre
Taking output= 30 metres
a) Labour
Mate day 0.150 0.150 0.150 310.000 46.50 46.50 46.50 L-12
Mazdoor including loading and unloading day 3.000 3.000 3.000 292.000 876.00 876.00 876.00 L-13
Blacksmith day 0.750 0.750 0.750 351.000 263.25 263.25 263.25 L-25
b) Machinery
Tractor- trolley hour 0.150 0.150 0.150 612.000 91.80 91.80 91.80 PM12001
Total cost without (OH&CP) 1277.55 1277.55 1277.55
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 102.20 127.76 153.31
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 137.98 140.53 143.09
Cost for 30 metres = (a+b+c+d) 1517.73 1545.84 1573.94
Rate per metre= (a+b+c+d)/30 say 50.60 51.50 52.50

2.12 202 Dismantling of CI Water Pipe Line


Dismantling of CI Water Pipe Line 600mm dia.
Including disposal with all lifts and lead upto 1000
metres and stacking of serviceable material and
unserviceable material separately under supervision of
concerned department
Unit= running metre
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Taking output=10 metres
a) Labour
Mate day 0.080 0.080 0.080 310.000 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.000 584.00 584.00 584.00 L-13
Plumber day 0.250 0.250 0.250 394.000 98.50 98.50 98.50 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 0.250 0.250 1183.000 295.75 295.75 295.75 PM6004
Light crane 3 tonne capacity hour 0.500 0.500 0.500 862.000 431.00 431.00 431.00 PM63001
Total cost without (OH&CP) 1434.05 1434.05 1434.05
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 114.72 143.41 172.09
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 154.88 157.75 160.61
Cost for 10 metres = (a+b+c+d) 1703.65 1735.20 1766.75
Rate per metre= (a+b+c+d)/10 170.40 173.50 176.70
The rate analysis does not include any excavation in earth or dismantling of masonry works which
Note
are to be measured and paid separately.

2.13 202 Removal of cement concrete Pipe of sewer Gutter

Removal of cement concrete pipe of sewer gutter 1500


mm dia under the supervision of concerned
department including disposal with all lifts and up to a
lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth
excavation and dismantling of masonry works.

Unit= running metre


Taking output= 10 metres
a) Labour
Mate day 0.100 0.100 0.100 310.000 31.00 31.00 31.00 L-12
Mazdoor day 2.500 2.500 2.500 292.000 730.00 730.00 730.00 L-13
b) Machinery
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Crane 5 tonne cpacity hour 0.300 0.300 0.300 909.000 272.70 272.70 272.70 PM63002
Truck flat body 10 tonne hour 1.000 1.000 1.000 1183.00 1183.00 1183.00 1183.00 PM6004
Total cost without (OH&CP) 2216.70 2216.70 2216.70
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 177.34 221.67 266.00
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 239.40 243.84 248.27
Cost for 10 metres = (a+b+c+d) 2633.44 2682.21 2730.97
Rate per metre= (a+b+c+d)/10 263.30 268.20 273.10
The rate analysis does not include any excavation in earth or dismantling of masonry works which
Note
are to be measured and paid separately.

2.14 202 Removal of telephone/ Electric Poles and Lines


Removal of telephone/ Electric poles including
excavation and dismantling of foundation concrete and
lines under the supervision of concerned department ,
disposal with all lifts and up to a lead of 1000 metres
and stacking the serviceable and unserviceable
material separately
Unit= Each
Taking Output= 30 nos.
a) Labour
Mate day 0.480 0.480 0.480 310.000 148.80 148.80 148.80 L-12
Mazdoor day 10.000 10.000 10.000 292.000 2920.00 2920.00 2920.00 L-13
Electrician/ Lineman day 2.000 2.000 2.000 394.000 788.00 788.00 788.00 L-02
b) Machinery
Tractor-trolley hour 1.500 1.500 1.500 612.000 918.00 918.00 918.00 PM12001
Total cost without (OH&CP) 4774.80 4774.80 4774.80
c) Overhead charges on(a+b) (@ 8%) (@ 10%) (@ 12%) 381.98 477.48 572.98
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 515.68 525.23 534.78
Cost for 30 Pole = (a+b+c+d) 5672.46 5777.51 5882.55
Rate per pole= (a+b+c+d)/30 189.08 192.58 196.09
Say 189.10 192.60 196.10
SITE CLEARANCE
Ref. Quantity as per peroject
Rate (Rs) Amount Input_Ref
Sr No to Description Unit category
M. Large Medium Small Large Medium Small
Note All the serviceables material resulting from removal of telephone / Electric poles and lines
would be handed over to the employer.
0 0 0
Summary of Rate Analysis.
CHAPTER -3
EARTH WORK, EROSION CONTROL AND DRAINAGE.
Ref.
Sr No Description Unit Rate as per Project Category
to M.
Large Medium Small
3.01 301 Exacavation in Soil by Manual Means.
Exacavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to cum 243.80 248.30 252.80
embankment site with all lifts and lead upto 1000 metres.

3.02 301 Exacavation in Ordinary Rock by Manual Means.


Exacavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
cum 319.10 325.00 330.90
material to embankment site with in all lifts and leads
upto 1000 metres.

3.03 301 Excavation in soil with Dozer with lead upto 1000 metres
Excavation for road way in soil by mechanical means
including cutting and transporting the earth to site of
embankment /dumping area with lead upto 1000 metres,
including trimming bottom and side slopes in accordance cum 177.40 185.40 231.80
with requirements of lines, grades and cross sections.

Excavation in ordinary rock with Dozer with lead upto


3.04 301
1000 metres

Excavation for roadway in ordinary rock by deploying a


dozer, including cutting and transporting the earth to site
of embankment /dumping area with lead upto 1000 cum 267.80 282.80 343.90
metres, trimming bottom and side slopes in accordance
with the requirements of lines, grades and cross sections.

301 & Excavation in Hard Rock (requiring


3.05 blasting) with disposal upto 1000 metres
302

Excavation for roadway in hard rock


(requiring blasting) by drilling, blasting and breaking,
trimming of bottom and side slopes in accordance with cum #VALUE! #VALUE! #VALUE!
requirements of lines, grades and cross sections, loading
and disposal of cut road with in all lifts and leads upto
1000 metres

Excavation in Soil using Hydraulic Excavator and Tippers


3.06 301 with Disposal upto 1000 metres.

Excavation for road work in soil with hydraulic excavator


including cutting and loading in tippers, trimming bottom
and side slopes, in accordance with requirements of cum 93.70 107.50 123.30
lines, grades and cross sections, and tranporting to the
embankment location within all lifts and lead upto 1000 m
Excavation in Ordinary Rock using
3.07 301 Hydraulic Excavator and Tippers with
Disposal upto 1000 metres

Excavation for roadwork in Ordinary Rock with hydraulic


excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
cum 646.70 686.50 721.90
requirements of lines, grades and
cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m

Excavation in Hard Rock (blasting


3.08 301
prohibited)

Excavation for roadwork in Hard Rock


(blasting prohibited) with hydraulic
excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts
and lead upto 1000m

A Mechanical Method cum 797.10 837.50 898.40


3.08 B Manual Method cum 1386.50 1412.20 1437.90

Excavation in Hard Rock (controlled


3.09 301 & 302 cum #VALUE! #VALUE! #VALUE!
blasting) with disposal upto 1000 metres
Excavation for road way in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of
lines,grades and cross sections,loading and disposal of cut
road within all lifts and leads upto 1000 metres.

3.10 301 Excavation in Marshy Soil using


Hydraulic Excavator and Tippers with
Disposal upto 1000 metres
Excavation for roadwork in Marshy Soil with hydraulic
excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts cum 203.20 211.40 266.50
and lead upto 1000m

3.11 301 Removal of Unserviceable Soil with


Disposal upto 1000 metres
Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid cum 95.60 100.00 125.80
separately as per clause 305.

3.12 303
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and sqm #VALUE! #VALUE! #VALUE!
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified
in clause No. 303

3.13 304 Excavation for Structures


Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting
out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of sides
and bottom, backfilling the excavation earth to the extent
required a nd utilising the remaining earth locally for road
work.

(i) Ordinary Soil


A Manual Means ( Depth upto 3 m) cum 289.30 294.70 300.00
3.13 B Mechanical Means (Depth upto 3 m) cum 87.90 91.60 113.80
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means ( Depth upto 3m) cum 361.60 368.30 375.00
3.13 B Mechanical Means cum 664.00 708.50 735.90

3.13 302 & (iii) Mechanical Means


303
A Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in property alighed and spaced drill
holes , collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as cum #VALUE! #VALUE! #VALUE!
specified in clasue No. 303.

3.13 (iv) Hard Rock ( Blasting Priohibited) cum 1212.60 1300.30 1462.50
3.13 (v) Marshy soil
A Manual means ( upto 3m depth) cum 576.40 587.10 597.80
3.13 B Mechanical Means cum 332.20 345.20 429.10

Scarifying the existing bituminous road surface to a


3.14 305.4.3 depth of 50 mm and disposal of scarified material with in
all lifts and lead upto 1000 metres.

(i) Scarifying Existing Grannular Surface to a depth of 50 mm sqm 30.20 30.80 31.30
by Manual Means
3.14 305.4.3 (ii) By Mechanaical Means using Hydraulic excavator sqm 6.00 6.30 7.90
3.14 305.4.3 (iii) By Mechanaical Means using Motor Grader sqm 7.90 8.20 9.40

Scarifying the existing bituminous surface to a depth of


3.15 305.4.3 50 mm and disposal of scarified material within all the
lifts and leads upto 1000 metres.
(i) By Mechanaical Means using Hydraulic excavator sqm 7.20 7.50 9.50
3.15 305.4.3 (ii) By Mechanaical Means using Motor Grader sqm 8.00 8.30 9.50
Construction of Embankment with Material obtained
3.16 305 from Borrow pits.

Construction of Embankment with approved material


obtained from Borrow pits with approved material
obtained from borrow pits with all lifts and leads, cum 194.90 205.50 220.30
transporting to site, spreading, grading to required slope
and compacting to meet requirement of Table 300-2.

Construction of Embankment with Material Deposited


3.17 305
from Roadway Cutting.
Construction of Embankment with approved materials
deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and
compacted to meet requirement of Table 300-2. cum 59.40 64.80 53.40

Rate per cum after adding royalty@Rs 33.00/cum cum 92.40 97.80 86.40

Construction of Subgrade and Earthen


3.18 305
Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from Borrow pits with
approved material obtained from borrow pits with all lifts
and leads, transporting to site, spreading, grading to cum 197.00 207.90 223.20
required slope and compacting to meet requirement of
Table 300-2.

3.19 305 Construction of Subgrade and Earthen Shoulders with


Material Deposited from Roadway Cutting

Construction of Embankment with Material Deposited


from Roadway Construction of embankment with
approved materials deposited at site from roadway
cum 60.40 65.90 54.70
cutting and excavation from drain and foundation of other
structures graded and compacted to meet requirement of
Table 300-2.

Rate per cum after adding royalty@Rs 33.00/cum cum 93.40 98.90 87.70

3.20 305.3.4 Compacting Original ground


Case-I Compacting Original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below
the sub-grade level, watered, graded and compacted in
cum 93.80 103.10 74.30
layers to meet requirement of Table 300-2 for sub-grade
construction.

Case-II Compacting Original ground supporting embankment


Loosening, leveling and compacting orinal ground
supporting embankment to facilitate placement of first
layer of embankment , scarified to a depth of 150 mm,
mixed with water at OMC and then compacted by rolling
so as to achieve minimum dry density as given in Table cum 107.70 118.90 85.60
300-2 for emabakment construction.

3.21 305 Stripping and Storing Top Soil


Stripping, Storing of Top Soil by road side at 15 m internal
and re-application on embankment slopes, cut slopes and
other areas in localities where the available embankment
material is not conducive to plant growth. cum 117.40 125.70 126.90

3.22 305 Stripping, Storing and Re-laying Top Soil


from Borrow Areas in Agriculture Fields.

Stripping of top Soil from Borrow areas located in


agriculture fields, storing at a suitable place, spreading
and re-laying after taking the borrow earth to maintain
fertility of the agricultural field, finishing it to the required cum 213.00 222.60 256.30
levels and satisfaction of the farmer.

3.23 307 A Turfing with Sods


Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods cum 39.90 42.40 48.70
and watering.

3.24 308 Seeding and Mulching

Preparation of seed bed on previously laid top soil,


firnishing and placing of seeds, fertilizer, mulching
material, applying bituminous emulssion at the rate of
sqm 151.80 160.90 183.50
0.23 litres per sqm and laying and fixing jute netting,
including cost of watering for 3 months all as per clause
308.

3.25 309 Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301
and 309. Excavated material to be used in embankment
within a lead of 1000 metres

A Mechanical means metre 55.80 56.80 57.90


3.25 B Manual means metre 132.10 134.50 137.00

3.26 309 Surface Drains in Ordinary Rock

Construction of unlined surface drain of average cross


sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the reuirement of clause 301 and 309. Excavated
material to be used in embankment at site within a lead of
1000 metres

A Mechanical means metre 73.40 74.80 76.20


B Manual means metre 184.40 187.80 191.20

3.27 309 Surface Drains in Hard Rock


Rate per metre may be worked out bsed on quantity of
hard rock as per design. For rate of hard rock cutting,
refer relevent item in this chapter
3.28 309 Sub-Surface Drains with Perforated Pipe

Construction of subsurface drain with perforated pipe of


100 mm internal diameter of metal/ asbestos cement/
Cement concrete/ PVC, closely jointed, perforations
ranging from 3mm to 6mm depending upto size of
metre 344.80 351.20 357.60
material surrounding the pipe, with 150 mm bedding
below the pipe and 300mm cushion above the pipe, cross
section of excavation 450 x 550 mm. Excavated material
to be utilised in roadway at site

3.29 309 Aggregate Sub-Surface Drains

Construction of aggregate sub surface drain 300 mm x 450


mm with aggregates conforming to Table 300-4, metre 135.10 137.70 140.20
excavated material to be utilised in roadway.

3.30 309 Underground Drain at Edge of pavement


Construction of an underground drain 1m x 1m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab 10 cm in thickness on urban roads. metre 3281.23 3350.18 3456.80

Rates for these items may be taken from chapters on


earth work and culvert respectively.
3.31 310 Preparation and Surface Treatment of Formation

Preparation and Surface treatment of formation by


removing mud and slurry, watering to the extent needed
to maintain the desired moisture content, trimming to the sqm 3.70 3.80 4.20
required line, grade, profile and rolling with smooth
wheeled roller,complete as per clause 310.

Construction of Rock fill Embankment with all lifts and


3.32 313
lead upto 5 km
Construction of Rock fill Embankment from roadway
excavation with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm
thick including filling of surface voids with stone spalls,
blinding top layer with granular material, rolled with cum 132.60 141.00 170.00
vibratory road roller, all complete as per clause 313.

3.33 Work in Urban Roads

The cost of earth work in urban roads inhabited area will


be comparatively higher due to following reasons:

a) There is mixed traffic on urban roads like slow moving


hand and animal driven carts, riskshaws, cycles, two/
three wheeler apart from the usual vehicular traffic
resulting into traffic jams. This causes loss of working
time which may be in the range of 10-15 percent

b) There is considerable disruption of traffic adversely


affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the-road
side encroachment by the shopkeepers and local shops
who make use of the berms of the road in front of these
shops and unauthorised conversion of road berms into
mini local market. The output of Manpower and machines
is substantially reduced due to factors mentioned above.
c) Cost of living in urban areas is comparatively more
resulting into higher wages.
d) At times, work is executed during night time due to
heavy traffic during day time. This involves extra
expenditure by way of making arrangement for lighting
and special transport for working parties due to odd hour.

In the light of above, the authorities engaged in preparing


the cost estimates may exercise their judgement and
cater for the additional cost to the extent of 2 to3
percent,keeping in view the severity of factors mentioned
above. Supporting details for the extra cost based on the
actual conditions in specific cases will have to give in
justification.

3.34 Suggestive Embankment Construction with Fly ash/Pond ash


available from coal or lignite burning Thermal Plants as
waste material.

Construction of embankment with fly ash conforming to


Table 1 of IRC: SP:58 obtained from coal or lignite burning
thermal power stations as waste material, spread and
86.00 92.60 86.20
compacted in layers at OMC, all as specified in IRC: SP: 58
and as per approved plans. Considering soil blanketing of
2m either side for 4 lane section
CHAPTER 3

EARTHWORK,EROSION CONTROL AND DRAINAGE.


Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
3.01 301 Exacavation in Soil by Manual Means.

Exacavation for roadway in soil using manual means


including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto 1000 metres.

Unit=cum
Taking output=120 cum
a) Labour
Mate day 1.800 1.800 1.800 310.00 558.00 558.00 558.00 L-12
Mazdoors day 45.000 45.000 45.000 292.00 13140.00 13140.00 13140.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1183.00 10926.19 10926.19 10926.19 PM6004
Total cost( Without O.H&C.P.) 24624.19 24624.19 24624.19
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 1969.94 2462.42 2954.90
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 2659.41 2708.66 2757.91
Cost of 120 cum= a+b+c+d 29253.54 29795.27 30337.00
Rate per cum= (a+b+c+d)/120(With OH.&C.P.) 243.78 248.29 252.81
Say 243.80 248.30 252.80
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted

3.02 301 Exacavation in Ordinary Rock by Manual Means.


Exacavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres.
Unit=cum
Taking output=120 cum
a) Labour
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Mate day 2.800 2.800 2.800 310.00 868.00 868.00 868.00 L-12
Mazdoors day 70.000 70.000 70.000 292.00 20440.00 20440.00 20440.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1183.00 10926.19 10926.19 10926.19 PM6004
Total cost( Without O.H&C.P.) 32234.19 32234.19 32234.19
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 2578.74 3223.42 3868.10
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 3481.29 3545.76 3610.23
Cost of 120 cum= a+b+c+d 38294.22 39003.37 39712.52
Rate per cum= (a+b+c+d)/120(With OH.&C.P.) 319.12 325.03 330.94
Say 319.10 325.00 330.90
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted

Excavation in soil with Dozer with lead upto 1000


3.03 301
metres
Excavation for road way in soil by mechanical means
including cutting and transporting the earth to site of
embankment /dumping area with lead upto 1000
metres, including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.

Unit=cum
Taking output= 500 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6461.00 24105.99 0.00 0.00 PM1001
Dozer (175HP) hour 5.342 4930.00 0.00 26336.06 0.00 PM1002
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Dozer (90HP) hour 8.621 3274.00 0.00 0.00 28225.15 PM1003
Tipper
(i) 18 cum capacity t.km 800.000 5.94 4752.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 800.000 6.63 0.00 5304.00 0.00 PM73001
(iii) 10 cum capacity t.km 800.000 8.08 0.00 0.00 6464.00 PM74001
Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 500.000 90.96 45480.00 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 500.000 89.34 0.00 44670.00 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 500.000 118.14 0.00 0.00 59070.00 PM77003
Total cost( Without O.H&C.P.) 74642.39 76614.46 94063.55
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 5971.39 7661.45 11287.63
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 8061.38 8427.59 10535.12
Cost for 500 cum= a+b+c+d 88675.16 92703.50 115886.30
Rate per cum= (a+b+c+d)/500(With OH.&C.P.) 177.35 185.41 231.77
Say 177.40 185.40 231.80
Excavation in ordinary rock with Dozer with lead upto
3.04 301
1000 metres

Excavation for roadway in ordinary rock by deploying a


dozer, including cutting and transporting the earth to site
of embankment /dumping area with lead upto 1000
metres, trimming bottom and side slopes in accordance
with the requirements of lines, grades and cross
sections.

Unit=cum
Taking output= 300 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Dozer
Dozer (240HP) hour 4.688 6461.00 30289.17 0.00 0.00 PM1001
Dozer (175HP) hour 6.667 4930.00 0.00 32868.31 0.00 PM1002
Dozer (90HP) hour 10.714 3274.00 0.00 0.00 35077.64 PM1003
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 720.000 5.94 4276.80 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 720.000 6.63 0.00 4773.60 0.00 PM73001
(iii) 10 cum capacity t.km 720.000 8.08 0.00 0.00 5817.60 PM74001
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 360.000 90.96 32745.60 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 360.000 89.34 0.00 32162.40 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 360.000 118.14 0.00 0.00 42530.40 PM77003
Total cost( Without O.H&C.P.) 67615.97 70108.71 83730.04
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 5409.28 7010.87 10047.60
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 7302.52 7711.96 9377.76
Cost for 300 cum= a+b+c+d 80327.77 84831.54 103155.40
Rate per cum= (a+b+c+d)/300 (With OH.&C.P.) 267.76 282.77 343.85
Say 267.80 282.80 343.90
3.05 301 & Excavation in Hard Rock (requiring
302 blasting) with disposal upto 1000 metres

Excavation for roadway in hard rock


(requiring blasting) by drilling, blasting and breaking,
trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross sections, loading
and disposal of cut road with in all lifts and leads upto
1000 metres

Unit = cum
Taking output= 180 cum
a) Labour
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Mate day 0.210 0.210 0.210 310.00 65.10 65.10 65.10 L-12
Mazdoors day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
Driller day 2.000 2.000 2.000 304.00 608.00 608.00 608.00 L-06
Blaster day 0.250 0.250 0.250 485.00 121.25 121.25 121.25 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 416.00 11440.00 11440.00 11440.00 PM15001
Pneumatic breaker for driling holes hour 55.000 55.000 55.000 206.00 11330.00 11330.00 11330.00 PM4001
(@ 4.5 m per hour)
Dozer
Dozer (240HP) hour 3.375 6461.00 21805.88 0.00 0.00 PM1001
Dozer (175HP) hour 4.800 4930.00 0.00 23664.00 0.00 PM1002
Dozer (90HP) hour 7.714 3274.00 0.00 0.00 25255.64 PM1003
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 360.000 5.94 2138.40 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 360.000 6.63 0.00 2386.80 0.00 PM73001
(iii) 10 cum capacity t.km 360.000 8.08 0.00 0.00 2908.80 PM74001
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 216.000 90.96 19647.36 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 216.000 89.34 0.00 19297.44 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 216.000 118.14 0.00 0.00 25518.24 PM77003
c) Materials
Small dia Explosive at 0.40kg/cum for 180 cum (180 x
0.40) Explosive at 0.20 kg/cum for secondary blast @5% kg 73.800 73.800 73.800 879.47 64904.89 64904.89 64904.89 M-215
of the total volume (180 x 0.2x5%)
Electric detonators at 1 per hole for main blast holes
( 21x3+20x2)= 103 nos
no 103.000 103.000 103.000 5.77 594.31 594.31 594.31 M-217

Ordinary detonators @ 1 per hole for 10 secondary holes


(required for 5% of the total quantity @ 0.6 m per hole no 10.000 10.000 10.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
for 1 cum)
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Detonating Fuse coil m 320.000 320.000 320.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
Credit for excavated rock found suitable for use @ 50
percent quantity blasted
cum 90.000 90.000 90.000 139.07 -12516.30 -12516.30 -12516.30 M-090

Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for 180 cum = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per cum=(a+b+c+d+e)/180(with OH.&C.P) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
Note 1. The quantity and availability of rock shall be checked before affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced/ restricted to that extent.
Excavation in Soil using Hydraulic Excavator and Tippers
3.06 301 with Disposal upto 1000 metres.

Excavation for road work in soil with hydraulic excavator


including cutting and loading in tippers, trimming
bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
tranporting to the embankment location within all lifts
and lead upto 1000 m

Unit = cum
Taking output= 350 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.926 3388.00 13301.29 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.024 3021.00 0.00 15177.50 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 6.321 2702.00 0.00 0.00 17079.34 PM3005
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 525.000 5.94 3118.50 0.00 0.00 PM72001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(ii) 14 cum capacity t.km 525.000 6.63 0.00 3480.75 0.00 PM73001
(iii) 10 cum capacity t.km 525.000 8.08 0.00 0.00 4242.00 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 3.926 2772.00 10882.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 5.024 2415.00 0.00 12132.96 0.00 PM6002
(iii) 10 cum capacity hour 6.321 2121.00 0.00 0.00 13406.84 PM6003
Total cost( Without O.H&C.P.) 27607.06 31095.61 35032.58
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 2208.56 3109.56 4203.91
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 2981.56 3420.52 3923.65
Cost for 350 cum= a+b+c+d 32797.19 37625.69 43160.14
Rate per cum= (a+b+c+d)/350 (With OH.&C.P.) 93.71 107.50 123.31
Say 93.70 107.50 123.30
Excavation in Ordinary Rock using
3.07 301 Hydraulic Excavator and Tippers with
Disposal upto 1000 metres

Excavation for roadwork in Ordinary


Rock with hydraulic excavator including
cutting and loading in tippers, trimming
bottom and side slopes, in accordance
with requirements of lines, grades and
cross sections, and transporting to the
embankment location within all lifts and
lead upto 1000m

Unit = cum
Taking output= 60 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 6.982 3388.00 23655.02 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 8.214 3021.00 0.00 24814.49 0.00 PM3004
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(iii) 0.9 cum bucket capacity hour 8.727 2702.00 0.00 0.00 23580.35 PM3005
Jack Hammer hour 6.982 8.214 8.727 206.00 1438.29 1692.08 1797.76 PM4001
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 120.000 5.94 712.80 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 120.000 6.63 0.00 795.60 0.00 PM73001
(iii) 10 cum capacity t.km 120.000 8.08 0.00 0.00 969.60 PM74001
For Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 72.000 90.96 6549.12 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 72.000 89.34 0.00 6432.48 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 72.000 118.14 0.00 0.00 8506.08 PM77003
Total cost( Without O.H&C.P.) 32659.63 34039.06 35158.20
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 2612.77 3403.91 4218.98
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 3527.24 3744.30 3937.72
Cost for 60 cum= a+b+c+d 38799.64 41187.26 43314.90
Rate per cum= (a+b+c+d)/ 60 (With OH.&C.P.) 646.66 686.45 721.91
Say 646.70 686.50 721.90
Excavation in Hard Rock (blasting
3.08 301
prohibited)

Excavation for roadwork in Hard Rock


(blasting prohibited) with hydraulic
excavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts
and lead upto 1000m

A Mechanical Method
Unit = cum
Taking output= 50 cum
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 8.533 3388.00 28909.80 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 10.039 3021.00 0.00 30327.82 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 11.378 2702.00 0.00 0.00 30743.36 PM3005
Jack Hammer hour 8.533 10.039 11.378 206.00 1757.80 2068.03 2343.87 PM4001
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 100.000 5.94 594.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 100.000 6.63 0.00 663.00 0.00 PM73001
(iii) 10 cum capacity t.km 100.000 8.08 0.00 0.00 808.00 PM74001
For Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 60.000 90.96 5457.60 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 60.000 89.34 0.00 5360.40 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 60.000 118.14 0.00 0.00 7088.40 PM77003

Credit for excavated rock found suitable for use @ 50


percent of excavated .
cum 25.000 25.000 25.000 139.07 -3476.75 -3476.75 -3476.75 M-090

Total cost( Without O.H&C.P.) 33546.85 35246.90 37811.27


c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 2683.75 2819.75 3024.90
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 3623.06 3806.67 4083.62
Cost for 50 cum= a+b+c+d 39853.66 41873.32 44919.79
Rate per cum= (a+b+c+d)/ 50 (With OH.&C.P.) 797.07 837.47 898.40
Say 797.10 837.50 898.40
3.08 B Manual Method
Unit = cum
Taking output= 16 cum
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
a) Labour
Mate day 1.640 1.640 1.640 310.00 508.40 508.40 508.40 L-12
Mazdoor including loading in truck day 16.000 16.000 16.000 292.00 4672.00 4672.00 4672.00 L-13
Chiseller day 24.000 24.000 24.000 451.00 10824.00 10824.00 10824.00 L-05
Blacksmith (Iind class) day 1.000 1.000 1.000 351.00 351.00 351.00 351.00 L-01
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour hour 2.900 2.900 2.900 1183.00 3430.70 3430.70 3430.70 PM6004
Credit for excavated rock found suitable for use @ 50
cum 8.000 8.000 8.000 139.07 -1112.56 -1112.56 -1112.56 M-090
percent quantity blasted
Total cost( Without O.H&C.P.) 18673.54 18673.54 18673.54
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 1493.88 1867.35 2240.82
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 2016.74 2054.09 2091.44
Cost for 16 cum= a+b+c+d 22184.17 22594.98 23005.80
Rate per cum= (a+b+c+d)/ 16 (With OH.&C.P.) 1386.51 1412.19 1437.86
Say 1386.50 1412.20 1437.90
Note 1. Credit is considered for 50 percent of quantity of work.
2. Loading for disposal will be done manually, being small quantity.
3. In case some rock is issued to contractor at site, the item of carriage shall be omitted to the extent of quantity
issued to the contractor

Excavation in Hard Rock (controlled


3.09 301 & 302 blasting) with disposal upto 1000 metres

Excavation for road way in hard rock (requiring blasting)


by drilling, blasting and breaking, trimming of bottom
and side slopes in accordance with requirements of
lines,grades and cross sections,loading and disposal of
cut road within all lifts and leads upto 1000 metres.

Unit = cum
Taking output= 180 cum
a) Labour
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Mate day 0.210 0.210 0.210 310.00 65.10 65.10 65.10 L-12
Mazdoors day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
Driller day 2.000 2.000 2.000 304.00 608.00 608.00 608.00 L-06
Blaster day 0.250 0.250 0.250 485.00 121.25 121.25 121.25 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 416.00 11440.00 11440.00 11440.00 PM15001
Pneumatic breaker for driling holes hour 55.000 55.000 55.000 206.00 11330.00 11330.00 11330.00 PM4001
(@ 4.5 m per hour)
Dozer
Dozer (240HP) hour 3.375 6461.00 21805.88 0.00 0.00 PM1001
Dozer (175HP) hour 4.320 4930.00 0.00 21297.60 0.00 PM1002
Dozer (90HP) hour 7.714 3274.00 0.00 0.00 25255.64 PM1003
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 360.000 5.94 2138.40 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 360.000 6.63 0.00 2386.80 0.00 PM73001
(iii) 10 cum capacity t.km 360.000 8.08 0.00 0.00 2908.80 PM74001
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 216.000 90.96 19647.36 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 216.000 89.34 0.00 19297.44 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 216.000 118.14 0.00 0.00 25518.24 PM77003
c) Materials
Small dia Explosive at 0.40kg/cum for 180 cum (180 x
0.40) Explosive at 0.20 kg/cum for secondary blast @5% kg 73.800 73.800 73.800 879.47 64904.89 64904.89 64904.89 M-215
of the total volume (180 x 0.2x5%)
Electric detonators at 1 per hole for main blast holes
(21x3+20x2)= 103 nos
no 103.000 103.000 103.000 5.77 594.31 594.31 594.31 M-217

Ordinary detonators @ 1 per hole for 10 secondary holes


(required for 5% of the total quantity @ 0.6 m per hole no 10.000 10.000 10.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
for 1 cum)
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Detonating Fuse coil m 320.000 320.000 320.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
Credit for excavated rock found suitable for use @ 50
percent quantity blasted
cum 90.000 90.000 90.000 139.07 -12516.54 -12516.54 -12516.54 M-090

#VALUE! #VALUE! #VALUE!


Add 5 percent of cost of a+b+c towards muffling
arrangements to guard agaainst any rock fly off during #VALUE! #VALUE! #VALUE!
blasting

Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for 180 cum = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per cum=(a+b+c+d+e)/180(with OH.&C.P) #VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!
Note 1. The quantity and availability of rock shall be checked before affording credit.

2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced/ restricted to that extent.

Excavation in Marshy Soil using


3.10 301 Hydraulic Excavator and Tippers with
Disposal upto 1000 metres

Excavation for roadwork in Marshy Soil


with hydraulic excavator including cutting and loading in
tippers, trimming bottom and side slopes, in accordance
with
requirements of lines, grades and cross
sections, and transporting to the embankment location
within all lifts and lead upto 1000m

Unit = cum
Taking output= 325 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3388.00 28818.33 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 9.796 3021.00 0.00 29593.72 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 13.695 2702.00 0.00 0.00 37003.89 PM3005
Tipper
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 487.500 5.94 2895.75 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 487.500 6.63 0.00 3232.13 0.00 PM73001
(iii) 10 cum capacity t.km 487.500 8.08 0.00 0.00 3939.00 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 8.506 2772.00 23578.63 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.796 2415.00 0.00 23657.34 0.00 PM6002
(iii) 10 cum capacity hour 13.695 2121.00 0.00 0.00 29047.10 PM6003
Total cost( Without O.H&C.P.) 55597.11 56787.58 70294.39
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 4447.77 5678.76 8435.33
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 6004.49 6246.63 7872.97
Cost of 325 cum= a+b+c+d 66049.37 68712.97 86602.68
Rate per cum= (a+b+c+d)/325 (With OH.&C.P.) 203.23 211.42 266.47
Say 203.20 211.40 266.50

3.11 301 Removal of Unserviceable Soil with


Disposal upto 1000 metres
Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but
excluding replacement by suitable soil which shall be
paid separately as per clause 305.

Unit = cum
Taking output= 415 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.769 3388.00 16157.37 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.492 3021.00 0.00 16591.33 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 7.678 2702.00 0.00 0.00 20745.96 PM3005
Tipper
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 622.500 5.94 3697.65 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 622.500 6.63 0.00 4127.18 0.00 PM73001
(iii) 10 cum capacity t.km 622.500 8.08 0.00 0.00 5029.80 PM74001
Loading and unloading time
(i) 18 cum capacity hour 4.769 2772.00 13219.67 0.00 0.00
(ii) 14 cum capacity hour 5.492 2415.00 0.00 13263.18 0.00
(iii) 10 cum capacity hour 7.678 2121.00 0.00 0.00 16285.04
Total cost( Without O.H&C.P.) 33379.09 34286.09 42365.19
c) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 2670.33 3428.61 5083.82
d) Contractor's profit on(a+b+c) (@ 10%) (@ 10%) (@ 10%) 3604.94 3771.47 4744.90
Cost of 415 cum= a+b+c+d 39654.36 41486.17 52193.92
Rate per cum= (a+b+c+d)/415 (With OH.&C.P.) 95.55 99.97 125.77
Say 95.60 100.00 125.80
3.12 303
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to
achieve a specified slope of the rock face by controlled
use of explosives and blasting accessories in properly
aligned and spaced drill holes, collection of the
excavated rock by a dozer, loading in tipper by a front
end loader and disposing of the material with all lifts and
lead upto 1000 m, all as specified in clause No. 303

Unit = Sqm
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Taking output= 400 Sqm
(120 cum considering 300mm average depth of
excavation over the existing rock face)
a) Labour
Mate day 0.210 0.210 0.210 310.00 65.10 65.10 65.10 L-12
Mazdoors day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
Driller day 2.000 2.000 2.000 304.00 608.00 608.00 608.00 L-06
Blaster day 0.250 0.250 0.250 485.00 121.25 121.25 121.25 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 416.00 7072.00 7072.00 7072.00 PM15001
Pneumatic breaker for driling holes hour 34.000 34.000 34.000 206.00 7004.00 7004.00 7004.00 PM4001
(@ 4.5 m per hour)
Dozer
(i) Dozer (240HP) hour 1.875 6461.00 12114.38 0.00 0.00 PM1001
(ii) Dozer (175HP) hour 2.400 4930.00 0.00 11832.00 0.00 PM1002
(iii) Dozer (90HP) hour 4.286 3274.00 0.00 0.00 14032.36 PM1003
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 240.000 5.94 1425.60 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 240.000 6.63 0.00 1591.20 0.00 PM73001
(iii) 10 cum capacity t.km 240.000 8.08 0.00 0.00 1939.20 PM74001
Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 144.000 90.96 13098.24 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 144.000 89.34 0.00 12864.96 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 144.000 118.14 0.00 0.00 17012.16 PM77003
c) Materials
Small dia Explosive at 0.40kg/cum for 400 cum (400 x
0.40) Explosive at 0.20 kg/cum for secondary blast @5% kg 49.200 49.200 49.200 879.47 43269.92 43269.92 43269.92 M-215
of the total volume (400 x 0.2x5%)
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Electric detonators at 1 per hole for main blast holes
(21x3+20x2)= 103 nos
no 69.000 69.000 69.000 5.77 398.13 398.13 398.13 M-217

Ordinary detonators @ 1 per hole for 10 secondary holes


(required for 5% of the total quantity @ 0.6 m per hole no 7.000 7.000 7.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
for 1 cum)
Detonating Fuse coil m 213.000 213.000 213.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
Credit for excavated rock found suitable for use @ 50
percent quantity blasted
cum 60.000 60.000 60.000 139.07 -8344.36 -8344.36 -8344.36 M-090

Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for 400 sqm = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per sqm=(a+b+c+d+e)/400(with OH.&C.P) #VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!
Note 1. The quantity and availability of rock shall be checked before affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced/ restricted to that extent.

3.13 304 Excavation for Structures


Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting
out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of sides
and bottom, backfilling the excavation earth to the
extent required a nd utilising the remaining earth locally
for road work.

(i) (i) Ordinary Soil


Unit=cum
Taking output=10 cum
A Manual Means ( Depth upto 3 m)
a) Labour
Mate day 0.320 0.320 0.320 310.00 99.20 99.20 99.20 L-12
Mazdoors day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
Total cost( Without O.H&C.P.) 2435.20 2435.20 2435.20
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
b) Overhead charges on (a) (@ 8%) (@ 10%) (@ 12%) 194.82 243.52 292.22
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 263.00 267.87 272.74
Cost for 10 cum = a+b+c 2893.02 2946.59 3000.17
Rate per cum=(a+b+c)/10(with OH.&C.P) 289.30 294.66 300.02
Say 289.30 294.70 300.00
Note Cost of dewatering may be added where required upto 10 percent of labour cost Assesment for dewatering shall be made as per site conditions.

3.13 B Mechanical Means (Depth upto 3 m)


Unit= Cum
Taking output= 330 cum
a) Labour
Mate day 0.320 0.320 0.320 310.00 99.20 99.20 99.20 L-12
Mazdoor day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
b) Machinery
Hydraulic Excavator
For excavation & backfill
(i) 1.2 cum bucket capacity hour 4.627 3388.00 15676.28 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.329 3021.00 0.00 16098.91 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 7.450 2702.00 0.00 0.00 20129.90 PM3005
Tipper
For transportation of excess material to dumping yard
considering lead @1 km
(i) 18 cum capacity t.km 198.000 5.94 1176.12 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 198.000 6.63 0.00 1312.74 0.00 PM73001
(iii) 10 cum capacity t.km 198.000 8.08 0.00 0.00 1599.84 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 1.851 2772.00 5130.97 0.00 0.00 PM6001
(ii) 14 cum capacity hour 2.131 2415.00 0.00 5146.37 0.00 PM6002
(iii) 10 cum capacity hour 2.980 2121.00 0.00 0.00 6320.58 PM6003
Total cost( Without O.H&C.P.) 24418.57 24993.21 30485.52
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 1953.49 2499.32 3658.26
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2637.21 2749.25 3414.38
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Cost for 330 cum= a+b+c+d 29009.26 30241.79 37558.16
Rate per cum= (a+b+c+d)/330 87.91 91.64 113.81
Say 87.90 91.60 113.80
3.13 (ii) (ii) Ordinary Rock (not requiring blasting)
A Manual Means ( Depth upto 3m)
Unit=cum
Taking output=10 cum
a) Labour
Mate day 0.400 0.400 0.400 310.00 124.00 124.00 124.00 L-12
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
Total cost( Without O.H&C.P.) 3044.00 3044.00 3044.00
b) Overhead charges on (a) (@ 8%) (@ 10%) (@ 12%) 243.52 304.40 365.28
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 328.75 334.84 340.93
Cost for 10 cum = a+b+c 3616.27 3683.24 3750.21
361.63 368.32 375.02
Rate per cum=(a+b+c)/10(with OH.&C.P) Say 361.60 368.30 375.00

Note Cost of dewatering upto 10 percent of labour cost may be added where required. Assesment for dewatering shall be made as per site conditions.
3.13 B Mechanical Means
Unit= Cum
Taking output= 50 cum
a) Labour
Mate day 0.120 0.120 0.120 310.00 37.20 37.20 37.20 L-12
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
b) Machinery
Hydraulic Excavator
For excavation, backfill & loading
(i) 1.2 cum bucket capacity hour 7.127 3388.00 24146.28 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 8.352 3021.00 0.00 25231.39 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 9.380 2702.00 0.00 0.00 25344.76 PM3005
Jack Hammer hour 5.818 6.845 7.273 206.00 1198.51 1410.07 1498.24 PM4001
Tipper
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 40.000 5.94 237.60 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 40.000 6.63 0.00 265.20 0.00 PM73001
(iii) 10 cum capacity t.km 40.000 8.08 0.00 0.00 323.20 PM74001
Loading and unloading time
(i) 18 cum capacity hour 0.523 2772.00 1449.76 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.603 2415.00 0.00 1456.25 0.00 PM6002
(iii) 10 cum capacity hour 0.843 2121.00 0.00 0.00 1788.00 PM6003
Total cost( Without O.H&C.P.) 27945.34 29276.11 29867.40
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 2235.63 2927.61 3584.09
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3018.10 3220.37 3345.15
Cost for 50 cum= a+b+c+d 33199.06 35424.09 36796.64
Rate per cum= (a+b+c+d)/50 663.98 708.48 735.93
Say 664.00 708.50 735.90

3.13 302 & (iii) Mechanical Means


303
A Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of
explosives and blasting accessories in property alighed
and spaced drill holes , collection of the excavated rock
by a dozer, loading in tipper by a front end loader and
disposing of the material with all lifts and lead upto
1000 m, all as specified in clasue No. 303.

Unit = cum
Taking output= 120 cum
a) Labour
Mate day 0.210 0.210 0.210 310.00 65.10 65.10 65.10 L-12
Mazdoors day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
Driller day 2.000 2.000 2.000 304.00 608.00 608.00 608.00 L-06
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Blaster day 0.250 0.250 0.250 485.00 121.25 121.25 121.25 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 416.00 7072.00 7072.00 7072.00 PM15001
Pneumatic breaker for driling holes hour 34.000 34.000 34.000 206.00 7004.00 7004.00 7004.00 PM4001
(@ 4.5 m per hour)
Hydraulic Excavator for Jack Hammer & backfilling,
loading
(i) 1.2 cum bucket capacity hour 3.537 3388.00 11983.36 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 4.174 3021.00 0.00 12609.65 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 5.411 2702.00 0.00 0.00 14620.52 PM3005
Jack Hammer (considering 5% of the volume for
hour 1.024 1.280 1.365 206.00 210.94 263.68 281.19 PM4001
dressing)
Tipper
For transportation considering lead @1 km
(i) 18 cum capacity t.km 96.000 5.94 570.24 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 96.000 6.63 0.00 636.48 0.00 PM73001
(iii) 10 cum capacity t.km 96.000 8.08 0.00 0.00 775.68 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 1.005 2772.00 2785.86 0.00 0.00 PM6001
(ii) 14 cum capacity hour 1.157 2415.00 0.00 2794.16 0.00 PM6002
(iii) 10 cum capacity hour 1.618 2121.00 0.00 0.00 3431.78 PM6003
c) Materials
Small dia Explosive at 0.40kg/cum for 120 cum (120 x
0.40) Explosive at 0.20 kg/cum for secondary blast @5% kg 49.200 49.200 49.200 879.47 43269.92 43269.92 43269.92 M-215
of the total volume (120 x 0.2x5%)
Electric detonators at 1 per hole for main blast holes
(21x3+20x2)= 103 nos
no 69.000 69.000 69.000 5.77 398.13 398.13 398.13 M-217

Ordinary detonators @ 1 per hole for 10 secondary holes


(required for 5% of the total quantity @ 0.6 m per hole no 7.000 7.000 7.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
for 1 cum)
Detonating Fuse coil m 213.000 213.000 213.000 INPUT #VALUE! #VALUE! #VALUE! #REF!
Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for120 cum = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per cum=(a+b+c+d+e)/120(with OH.&C.P) #VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!
3.13 (iv) Hard Rock ( Blasting Priohibited)
Unit= Cum
Taking output= 35 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery

Hydraulic Excavator used for Jack Hammer & loading

(i) 1.2 cum bucket capacity hour 9.571 3388.00 32426.55 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 11.244 3021.00 0.00 33968.12 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 13.783 2702.00 0.00 0.00 37241.67 PM3005
Jack Hammer hour 8.960 10.541 12.800 206.00 1845.76 2171.45 2636.80 PM4001
Tipper
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 28.000 5.94 166.32 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 28.000 6.63 0.00 185.64 0.00 PM73001
(iii) 10 cum capacity t.km 28.000 8.08 0.00 0.00 226.24 PM74001
Loading and unloading time
(i) 18 cum capacity hour 0.244 2772.00 676.37 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.281 2415.00 0.00 678.62 0.00 PM6002
(iii) 10 cum capacity hour 0.393 2121.00 0.00 0.00 833.55 PM6003
Total cost( Without O.H&C.P.) 35723.80 37612.63 41547.06
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 2857.90 3761.26 4985.65
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3858.17 4137.39 4653.27
Cost for 35cum= a+b+c+d 42439.87 45511.28 51185.98
Rate per cum= (a+b+c+d)/35 1212.57 1300.32 1462.46
Say 1212.60 1300.30 1462.50
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
3.13 (v) Marshy soil
Unit=cum
Taking output=10 cum
A Manual means ( upto 3m depth)
a) Labour
Mate day 0.400 0.400 0.400 310.00 124.00 124.00 124.00 L-12
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
b) Machinery
Tractor- Trolley hour 2.670 2.670 2.670 612.00 1634.04 1634.04 1634.04 PM12001
c) Material
Selected earth for refilling cum 5.000 5.000 5.000 34.82 174.10 174.10 174.10 M-164
Total cost( Without O.H&C.P.) 4852.14 4852.14 4852.14
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 388.17 485.21 582.26
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 524.03 533.74 543.44
Cost for 10 cum= a+b+c+d 5764.34 5871.09 5977.84
Rate per cum= (a+b+c+d)/10 576.43 587.11 597.78
say 576.40 587.10 597.80
Note 1. Cost of dewatering @ 30 percent of (a), may be added where required Assesment for dewatering shall be made as per site conditions.
2. Shoring & Strutting 20 percent of (a), where required may be added.

3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item (i) to (iv) for ordinary soil.

3.13 B Mechanical Means


Unit= Cum
Taking output= 260 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 10.256 3388.00 34747.33 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 11.811 3021.00 0.00 35681.03 0.00 PM3004
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(iii) 0.9 cum bucket capacity hour 16.513 2702.00 0.00 0.00 44618.13 PM3005
Tipper
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 639.600 5.94 3799.22 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 639.600 6.63 0.00 4240.55 0.00 PM73001
(iii) 10 cum capacity t.km 639.600 8.08 0.00 0.00 5167.97 PM74001
For Loading and unloading
(i) 18 cum capacity hour 10.256 2772.00 28429.63 0.00 0.00 PM6001
(ii) 14 cum capacity hour 11.811 2415.00 0.00 28523.57 0.00 PM6002
(iii) 10 cum capacity hour 16.513 2121.00 0.00 0.00 35024.07 PM6003
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 34.82 5431.92 5431.92 5431.92 M-164
Total cost( Without O.H&C.P.) 72712.50 74181.46 90546.49
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 5817.00 7418.15 10865.58
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 7852.95 8159.96 10141.21
Cost for260 cum = a+b+c+d+e 86382.45 89759.57 111553.27
Rate per cum=(a+b+c+d+e)/260 (with OH.&C.P) 332.24 345.23 429.05
Say 332.20 345.20 429.10
Scarifying the existing bituminous road surface to a
3.14 305.4.3 depth of 50 mm and disposal of scarified material with
in all lifts and lead upto 1000 metres.

(i) Scarifying Existing Grannular Surface to a depth of 50


mm by Manual Means
Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.200 0.200 0.200 310.00 62.00 62.00 62.00 L-12
Mazdoor including loading and unloading day 5.000 5.000 5.000 292.00 1460.00 1460.00 1460.00 L-13
b) Machinery
Tractor- Trolley hour 1.670 1.670 1.670 612.00 1022.04 1022.04 1022.04 PM12001
Total cost( Without O.H&C.P.) 2544.04 2544.04 2544.04
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 203.52 254.40 305.28
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 274.76 279.84 284.93
Cost for 100 sqm = a+b+c+d 3022.32 3078.29 3134.26
Rate per sqm= (a+b+c+d)/100 30.22 30.78 31.34
Say 30.20 30.80 31.30
Note In case material is to be reused at site, transportation cost catered above for disposal shall be deleted.

3.14 305.4.3 (ii) By Mechanaical Means using Hydraulic excavator


Unit= sqm
Taking output= 6000 sqm
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.309 3388.00 14598.89 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 4.962 3021.00 0.00 14990.20 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 6.938 2702.00 0.00 0.00 18746.48 PM3005
Tipper
For transportation to dumping yard considering lead @1 km
(i) 18 cum capacity t.km 600.000 5.94 3564.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 600.000 6.63 0.00 3978.00 0.00 PM73001
(iii) 10 cum capacity t.km 600.000 8.08 0.00 0.00 4848.00 PM74001
For Loading and unloading
(i) 18 cum capacity hour 4.309 2772.00 11944.55 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.962 2415.00 0.00 11983.23 0.00 PM6002
(iii) 10 cum capacity hour 6.938 2121.00 0.00 0.00 14715.50 PM6003
Total cost( Without O.H&C.P.) 30411.84 31255.83 38614.37
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 2432.95 3125.58 4633.72
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3284.48 3438.14 4324.81
Cost for 6000 sqm = a+b+c+d 36129.27 37819.56 47572.91
Rate per sqm= (a+b+c+d)/6000 6.02 6.30 7.93
6.00 6.30 7.90
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
3.14 305.4.3 (iii) By Mechanaical Means using Motor Grader
Unit= sqm
Taking output= 12500 sqm
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 3.064 5900.00 18077.60 0.00 0.00 PM2001
(i) Motor grader 3.70 metre blade hour 3.676 5398.00 0.00 19843.05 0.00 PM2002
(i) Motor grader 3.35 metre blade hour 3.720 2982.00 0.00 0.00 11093.04 PM2003
Tipper
For transportation to dumping yard considering lead @1 km
(i) 18 cum capacity t.km 1250.000 5.94 7425.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1250.000 6.63 0.00 8287.50 0.00 PM73001
(iii) 10 cum capacity t.km 1250.000 8.08 0.00 0.00 10100.00 PM74001
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 625.000 90.96 56850.00 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 625.000 89.34 0.00 55837.50 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 625.000 118.14 0.00 0.00 73837.50 PM77003
Total cost( Without O.H&C.P.) 82657.00 84272.45 95334.94
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 6612.56 8427.24 11440.19
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 8926.96 9269.97 10677.51
Cost for12500 sqm = a+b+c+d 98196.52 101969.66 117452.65
Rate per sqm= (a+b+c+d)/12500 7.86 8.16 9.40
Say 7.90 8.20 9.40

In case material is to be reused at site, transportation


Note
cost catered above for disposal shall be deleted.
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Scarifying the existing bituminous surface to a depth of
50 mm and disposal of scarified material within all the
3.15 305.4.3 lifts and leads upto 1000 metres.

(i) By Mechanaical Means using Hydraulic excavator


Unit= sqm
Taking output= 6000 sqm
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.196 3388.00 17604.05 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.984 3021.00 0.00 18077.66 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 8.366 2702.00 0.00 0.00 22604.93 PM3005
Tipper
For transportation to dumping yard considering lead
@1 km
(i) 18 cum capacity t.km 690.000 5.94 4098.60 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 690.000 6.63 0.00 4574.70 0.00 PM73001
(iii) 10 cum capacity t.km 690.000 8.08 0.00 0.00 5575.20 PM74001
For Loading and unloading
(i) 18 cum capacity hour 5.196 2772.00 14403.31 0.00 0.00 PM6001
(ii) 14 cum capacity hour 5.984 2415.00 0.00 14451.36 0.00 PM6002
(iii) 10 cum capacity hour 8.366 2121.00 0.00 0.00 17744.29 PM6003
Total cost( Without O.H&C.P.) 36410.36 37408.12 46228.82
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 2912.83 3740.81 5547.46
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 3932.32 4114.89 5177.63
Cost for 6000 sqm = a+b+c+d 43255.51 45263.83 56953.90
Rate per sqm= (a+b+c+d)/6000 7.21 7.54 9.49
Say 7.20 7.50 9.50
3.15 305.4.3 (ii) By Mechanaical Means using Motor Grader
Unit= sqm
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Taking output= 12500 sqm
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 3.064 5900.00 18077.60 0.00 0.00 PM2001
(i) Motor grader 3.70 metre blade hour 3.676 5398.00 0.00 19843.05 0.00 PM2002
(i) Motor grader 3.35 metre blade hour 3.720 2982.00 0.00 0.00 11093.04 PM2003
Tipper
For transportation to dumping yard considering lead @1 km
(i) 18 cum capacity t.km 1437.500 5.94 8538.75 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 1437.500 6.63 0.00 9530.63 0.00 PM73001
(iii) 10 cum capacity t.km 1437.500 8.08 0.00 0.00 11615.00 PM74001
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 625.000 90.96 56850.00 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 625.000 89.34 0.00 55837.50 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 625.000 118.14 0.00 0.00 73837.50 PM77003
Total cost( Without O.H&C.P.) 83770.75 85515.57 96849.94
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 6701.66 8551.56 11621.99
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 9047.24 9406.71 10847.19
Cost for 12500 sqm = a+b+c+d 99519.65 103473.84 119319.13
Rate per sqm= (a+b+c+d)/12500 7.96 8.28 9.55
Say 8.00 8.30 9.50
Construction of Embankment with Material obtained
3.16 305 from Borrow pits.
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small

Construction of Embankment with approved material


obtained from Borrow pits with approved material
obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope
and compacting to meet requirement of Table 300-2.

Unit= cum
Taking output= 450 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3388.00 17102.62 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.813 3021.00 0.00 17561.07 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 8.127 2702.00 0.00 0.00 21959.15 PM3005
Tipper
For transportation
(i) 18 cum capacity t.km 450x1.6xL2 5.94 4276.80 PM72001
(ii) 14 cum capacity t.km 450x1.6xL2 6.63 4773.60 PM73001
(iii) 10 cum capacity t.km 450x1.6xL2 8.08 5817.60 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 5.048 2772.00 13993.06 0.00 0.00 PM6001
(ii) 14 cum capacity hour 5.813 2415.00 0.00 14038.40 0.00 PM6002
(iii) 10 cum capacity hour 8.127 2121.00 0.00 0.00 17237.37 PM6003
Motor grader
(i) Motor grader 4.30 metre blade hour 2.177 5900.00 12844.30 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.626 5398.00 0.00 14175.15 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.929 2982.00 0.00 0.00 8734.28 PM2003
Water tanker (Speed @ km/hr and return speed @ hour
20km/hr and spreading speed @ 2.5 km/hr
0.25XL1+0.
(i) 16 KL Capacity hour
864
1426.00 1588.56 PM11001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
0.333XL1+
(ii) 12 KL capacity hour
1.152
1252.00 1859.22 PM11002

0.667XL1+2
(iii) 6 KL Capacity hour
.304
907.00 2694.70 PM11003

Vibratory roller hour 2.184 2.184 2.184 2338.00 5106.19 5106.19 5106.19 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 36.000 36.000 36.000 73.60 2649.60 2649.60 2649.60 M-191

Compensation for Earth taken from private land cum 450.000 450.000 450.000 34.82 15669.00 15669.00 15669.00 M-093
Total cost( Without O.H&C.P.) 73838.94 76441.03 80476.69
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 5907.11 7644.10 9657.20
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 7974.61 8408.51 9013.39
Cost for450 cum = a+b+c+d+e 87720.66 92493.64 99147.28
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 194.93 205.54 220.33
194.90 205.50 220.30
Note Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from
Govt. land, compensation for earth will not be required. The position is required to be clearly stated in the cost estimate.

Construction of Embankment with Material Deposited


3.17 305
from Roadway Cutting

Construction of Embankment with approved materials


deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded
and compacted to meet requirement of Table 300-2.

Unit= cum
Taking output= 450 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Motor Grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5900.00 12844.30 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.626 5398.00 0.00 14175.15 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.929 2982.00 0.00 0.00 8734.28 PM2003
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5 hour
km/hr
0.25XL1+0.
(i) 16 KL Capacity hour
864
1426.00 1588.56 PM11001

0.333XL1+
(ii) 12 KL capacity hour
1.152
1252.00 1859.22 PM11002

0.667XL1+2
(iii) 6 KL Capacity hour
.304
907.00 2694.70 PM11003

Vibratory roller hour 2.184 2.184 2.184 2338.00 5106.19 5106.19 5106.19 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 36.000 36.000 36.000 73.60 2649.60 2649.60 2649.60 M-191

Total cost( Without O.H&C.P.) 22493.06 24094.56 19489.17


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 1799.44 2409.46 2338.70
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 2429.25 2650.40 2182.79
Cost for450 cum = a+b+c+d+e 26721.75 29154.42 24010.65
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 59.40 64.80 53.40
Rate per cum after adding royalty@Rs 33.00/cum 92.40 97.80 86.40
3.18 305 Construction of Subgrade and Earthen
Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from Borrow pits with
approved material obtained from borrow pits with all
lifts and leads, transporting to site, spreading, grading to
required slope and compacting to meet requirement of
Table 300-2.

Unit= cum
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Taking output= 450 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3388.00 17102.62 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 5.813 3021.00 0.00 17561.07 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 8.127 2702.00 0.00 0.00 21959.15 PM3005
Tipper
For transportation
450x1.75xL
(i) 18 cum capacity t.km
2 5.94 4677.75 PM72001

450x1.75x
(ii) 14 cum capacity t.km
L2 6.63 5221.13 PM73001

450x1.75xL
(iii) 10 cum capacity t.km
2 8.08 6363.00 PM74001
For Loading and unloading time
(i) 18 cum capacity hour 5.048 2772.00 13993.06 0.00 0.00 PM6001
(ii) 14 cum capacity hour 5.813 2415.00 0.00 14038.40 0.00 PM6002
(iii) 10 cum capacity hour 8.127 2121.00 0.00 0.00 17237.37 PM6003
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5900.00 12844.30 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.626 5398.00 0.00 14175.15 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.929 2982.00 0.00 0.00 8734.28 PM2003
Water tanker (Speed @ km/hr and return speed @
20km/hr and spreading speed @ 2.5 km/hr)
0.273XL1+0
(i) 16 KL Capacity hour
.945
1426.00 1736.87 PM11001

0.365XL1+
(ii) 12 KL capacity hour
1.26
1252.00 2034.50 PM11002

0.729XL1+2
(iii) 6 KL Capacity hour
.52
907.00 2946.84 PM11003
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Vibratory roller 12 tonne hour 2.184 2.184 2.184 2338.00 5106.19 5106.19 5106.19 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 39.375 39.375 39.375 73.60 2898.00 2898.00 2898.00 M-191

Compensation for Earth taken from private land cum 450.000 450.000 450.000 34.82 15669.00 15669.00 15669.00 M-093
Total cost( Without O.H&C.P.) 74636.59 77312.23 81522.63
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 5970.93 7731.22 9782.72
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 8060.75 8504.35 9130.54
Cost for450 cum = a+b+c+d+e 88668.27 93547.80 100435.89
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 197.04 207.88 223.19
Say 197.00 207.90 223.20

Construction of Subgrade and Earthen Shoulders with


3.19 305 Material Deposited from Roadway Cutting

Construction of Embankment with


Material Deposited from Roadway
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded
and compacted to meet requirement of Table 300-2.

Unit= cum
Taking output= 450 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5900.00 12844.30 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.626 5398.00 0.00 14175.15 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.929 2982.00 0.00 0.00 8734.28 PM2003
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.273XL1+0
(i) 16 KL Capacity hour
.945
1426.00 1736.87 PM11001

0.365XL1+
(ii) 12 KL capacity hour
1.26
1252.00 2034.50 PM11002

0.729XL1+2
(iii) 6 KL Capacity hour
.52
907.00 2946.84 PM11003

Vibratory roller hour 2.184 2.184 2.184 2338.00 5106.19 5106.19 5106.19 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 39.375 39.375 39.375 73.60 2898.00 2898.00 2898.00 M-191

Total cost( Without O.H&C.P.) 22889.76 24518.24 19989.71


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 1831.18 2451.82 2398.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 2472.09 2697.01 2238.85
Cost for450 cum = a+b+c+d+e 27193.03 29667.07 24627.33
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 60.40 65.90 54.70
Rate per cum after adding royalty@Rs 33.00/cum 93.40 98.90 87.70
3.20 305.3.4 Compacting Original ground
Case-I Compacting Original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below
the sub-grade level, watered, graded and compacted in
layers to meet requirement of Table 300-2 for sub-grade
construction.
Unit= cum
Taking output= 225 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor grader for ripping (in two layers) & grading
(i) Motor grader 4.30 metre blade hour 2.192 5900.00 12932.80 0.00 0.00 PM2001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(ii) Motor grader 3.70 metre blade hour 2.637 5398.00 0.00 14234.53 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.804 2982.00 0.00 0.00 8361.53 PM2003
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.137XL1+0
(i) 16 KL Capacity hour
.236
1426.00 531.90 PM11001

0.182XL1+
(ii) 12 KL capacity hour
0.315
1252.00 622.24 PM11002

0.365XL1+0
(iii) 6 KL Capacity hour
.63
907.00 902.47 PM11003

Vibratory roller hour 1.092 1.092 1.092 2338.00 2553.10 2553.10 2553.10 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 19.688 19.688 19.688 73.60 1449.04 1449.04 1449.04 M-191

Total cost( Without O.H&C.P.) 17771.23 19163.30 13570.53


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 1421.70 1916.33 1628.46
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 1919.29 2107.96 1519.90
Cost for 225 cum = a+b+c+d+e 21112.22 23187.60 16718.89
Rate per cum=(a+b+c+d+e)/225(with OH.&C.P) 93.83 103.06 74.31
Say 93.80 103.10 74.30
Case-II Compacting Original ground supporting embankment
Loosening, leveling and compacting original ground
supporting embankment to facilitate placement of first
layer of embankment , scarified to a depth of 150 mm,
mixed with water at OMC and then compacted by rolling
so as to achieve minimum dry density as given in Table
300-2 for emabakment construction.

Unit= cum
Taking output= 300 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader for ripping & grading
(i) Motor grader 4.30 metre blade hour 3.487 5900.00 20573.30 0.00 0.00 PM2001
(i) Motor grader 3.70 metre blade hour 4.197 5398.00 0.00 22655.41 0.00 PM2002
(i) Motor grader 3.35 metre blade hour 4.497 2982.00 0.00 0.00 13410.05 PM2003
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5 hour
km/hr)
0.167xL1+0
(i) 16 KL Capacity hour
.64
1426.00 1150.78 PM11001

0.222XL1+
(ii) 12 KL capacity hour
0.853
1252.00 1345.90 PM11002

0.444XL1+1
(iii) 6 KL Capacity hour
.707
907.00 1950.96 PM11003

Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 24.000 24.000 24.000 73.60 1766.40 1766.40 1766.40 M-191

Total cost( Without O.H&C.P.) 27199.01 29476.23 20835.94


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 2175.92 2947.62 2500.31
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 2937.49 3242.39 2333.63
Cost for 300 cum = a+b+c+d+e 32312.42 35666.24 25669.88
Rate per cum=(a+b+c+d+e)/300(with OH.&C.P) 107.71 118.89 85.57
Say 107.70 118.90 85.60
3.21 305 Stripping and Storing Top Soil
Stripping, Storing of Top Soil by road side at 15 m
internal and re-application on embankment slopes, cut
slopes and other areas in localities where the available
embankment material is not conducive to plant growth.

Unit= cum
Taking output= 250 cum
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 1.680 5900.00 9912.00 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.027 5398.00 0.00 10941.75 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.260 2982.00 0.00 0.00 6739.32 PM2003
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3388.00 9499.95 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 3.230 3021.00 0.00 9757.83 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 4.515 2702.00 0.00 0.00 12199.53 PM3005
Tipper
For transportation considering lead @ 1 km (20% of the
material needs to be transported)
(i) 18 cum capacity t.km 75.000 5.94 445.50 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 75.000 6.63 0.00 497.25 0.00 PM73001
(iii) 10 cum capacity t.km 75.000 8.08 0.00 0.00 606.00 PM74001
For Loading (20% of the material needs to be
transported)
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 50.000 90.96 4548.00 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 50.000 89.34 0.00 4467.00 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 50.000 118.14 0.00 0.00 5907.00 PM77003
Total cost( Without O.H&C.P.) 24709.85 25968.23 25756.25
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 1976.79 2596.82 3090.75
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 2668.66 2856.50 2884.70
Cost for 250 cum = a+b+c+d 29355.30 31421.55 31731.70
Rate per cum= (a+b+c+d)/250 117.42 125.69 126.93
Say 117.40 125.70 126.90
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small

3.22 305 Stripping, Storing and Re-laying Top Soil


from Borrow Areas in Agriculture Fields.

Stripping of top Soil from Borrow areas located in


agriculture fields, storing at a suitable place, spreading
and re-laying after taking the borrow earth to maintain
fertility of the agricultural field, finishing it to the
required levels and satisfaction of the farmer.

Unit= cum
Taking output= 250 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 1.680 5900.00 9912.00 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.027 5398.00 0.00 10941.75 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.260 2982.00 0.00 0.00 6739.32 PM2003
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3388.00 9499.95 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 3.230 3021.00 0.00 9757.83 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 4.515 2702.00 0.00 0.00 12199.53 PM3005
Tipper
For transportation
250x1.60xL
(i) 18 cum capacity t.km
2 5.94 2376.00 PM72001

250x1.60x
(ii) 14 cum capacity t.km
L2 6.63 2652.00 PM73001

250x1.60xL
(iii) 10 cum capacity t.km
2 8.08 3232.00 PM74001
For Loading & unloading
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(i) Using by 18 cum capacity Tipper & 3.1 cum capacity
loader
cum 250.000 90.96 22740.00 0.00 0.00 PM77001

(ii) Using by 14 cum capacity tipper & 2.1 cum capacity


loader
cum 250.000 89.34 0.00 22335.00 0.00 PM77002

(iii) Using by 10 cum capacity tipper & 1 cum capacity


loader
cum 250.000 118.14 0.00 0.00 29535.00 PM77003
Total cost( Without O.H&C.P.) 44832.35 45990.98 52010.25
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 3586.59 4599.10 6241.23
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 4841.89 5059.01 5825.15
Cost for 250 cum = a+b+c+d 53260.83 55649.08 64076.63
Rate per cum= (a+b+c+d)/250 213.04 222.60 256.31
Say 213.00 222.60 256.30
3.23 307 A Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of
sods and watering.

Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 310.00 37.20 37.20 37.20 L-12

Mazdoor for prparation of ground and fetching of sods day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.5XL1+0.0
(i) 16 KL Capacity hour
96
1426.00 849.90 PM11001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
0.667XL1+
(ii) 12 KL capacity hour
0.128
1252.00 995.34 PM11002

1.333XL1+0
(iii) 6 KL Capacity hour
.256
907.00 1441.22 PM11003

Tactor- trolley hour 1.000 1.000 1.000 612.00 612.00 612.00 612.00 PM12001
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
cum 0.180 0.180 0.180 552.00 99.36 99.36 99.36 M-168

Cost of water KL 12.000 12.000 12.000 73.60 883.20 883.20 883.20 M-191
Total cost( Without O.H&C.P.) 3357.66 3503.10 3948.98
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 268.61 350.31 473.88
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 362.63 385.34 442.29
Cost for100 sqm = a+b+c+d+e 3988.90 4238.75 4865.15
Rate per Sqm=(a+b+c+d+e)/100 (with OH.&C.P) 39.89 42.39 48.65
Say 39.90 42.40 48.70
3.24 308 Seeding and Mulching

Preparation of seed bed on previously laid top soil,


firnishing and placing of seeds, fertilizer, mulching
material, applying bituminous emulssion at the rate of
0.23 litres per sqm and laying and fixing jute netting,
including cost of watering for 3 months all as per clause
308.

Unit= sqm
Taking output= 240 sqm
a) Labour
Mate day 0.400 0.400 0.400 310.00 124.00 124.00 124.00 L-12
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
3.5XL1+1.6
(i) 16 KL Capacity hour
13
1426.00 7291.14 PM11001

4.667XL1+
(ii) 12 KL capacity hour
2.15
1252.00 8534.88 PM11002

9.333XL1+4
(iii) 6 KL Capacity hour
.301
907.00 12366.04 PM 11003

Tactor- trolley hour 2.400 2.400 2.400 612.00 1468.80 1468.80 1468.80 PM12001
c) Material 0.00 0.00 0.00
Seeds kg 3.600 3.600 3.600 34.61 124.60 124.60 124.60 M-163
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 0.430 0.430 552.00 237.36 237.36 237.36 M-168
Bitumen emulsion litre 55.200 55.200 55.200 46.51 2567.30 2567.30 2567.30 M-077
Jute netting, open weave, 2.5 cm square opening sqm 264.000 264.000 264.000 36.94 9752.16 9752.16 9752.16 M-120
Cost of water for 3 months KL 84.000 84.000 84.000 73.60 6182.40 6182.40 6182.40 M-191
Total cost( Without O.H&C.P.) 30667.75 31911.50 35742.65
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 2453.42 3191.15 4289.12
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 3312.12 3510.26 4003.18
Cost for240 sqm = a+b+c+d+e 36433.29 38612.91 44034.95
Rate per sqm=(a+b+c+d+e)/240 (with OH.&C.P) 151.81 160.89 183.48
Say 151.80 160.90 183.50
3.25 309 Surface Drains in Soil

Construction of unlined surface drains of average cross


sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301
and 309. Excavated material to be used in embankment
within a lead of 1000 metres

Unit= metre
Taking output = 10 metre
A Mechanical means
a) Labour
Mate day 0.010 0.010 0.010 310.00 3.10 3.10 3.10 L-12
Mazdoor for dressing of bed and side of drain day 0.250 0.250 0.250 292.00 73.00 73.00 73.00 L-13
b) Machinery
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Hydraulic Excavator 0.9 cum bucket capacity hour 0.090 0.090 0.090 2702.00 243.18 243.18 243.18 PM3005
Tactor- trolley
Tactor- Trolley for transportation & for loading & un
loading Time
hour 0.246 0.246 0.246 612.00 150.55 150.55 150.55 PM12001
Total cost( Without O.H&C.P.) 469.83 469.83 469.83
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 37.59 46.98 56.38
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 50.74 51.68 52.62
Cost for 10 meter = a+b+c+d 558.16 568.50 578.83
Rate per meter= (a+b+c+d)/10 55.82 56.85 57.88
Say 55.80 56.80 57.90
3.25 B Manual means
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Tactor- trolley
Tactor- trolley for transportation & for loading & un
loading Time
hour 0.822 0.822 0.822 612.00 503.06 503.06 503.06 PM12001
Total cost( Without O.H&C.P.) 1111.86 1111.86 1111.86
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 88.95 111.19 133.42
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 120.08 122.31 124.53
Cost for 10 meter = a+b+c+d 1320.89 1345.36 1369.82
Rate per meter= (a+b+c+d)/10 132.09 134.54 136.98
Say 132.10 134.50 137.00
Note Where lining of drain is provided, quanity shall be
worked out based on approved design and drawing and
priced on rate of cement concrete of approved grade or
stone/ brick masonry as the case may be.

3.26 309 Surface Drains in Ordinary Rock


EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small

Construction of unlined surface drain of average cross


sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design
and to the reuirement of clause 301 and 309. Excavated
material to be used in embankment at site within a lead
of 1000 metres

Unit= metre
Taking output = 10 metre
A Mechanical means
a) Labour
Mate day 0.020 0.020 0.020 310.00 6.20 6.20 6.20 L-12
Mazdoor for dressing of bed and side of drain day 0.500 0.500 0.500 292.00 146.00 146.00 146.00 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.112 0.112 0.112 2702.00 302.62 302.62 302.62 PM3005
Tactor- trolley
Tactor- trolley for transportation & for loading & un
loading Time
hour 0.267 0.267 0.267 612.00 163.40 163.40 163.40 PM12001
Total cost( Without O.H&C.P.) 618.23 618.23 618.23
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 49.46 61.82 74.19
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 66.77 68.01 69.24
Cost for 10 meter = a+b+c+d 734.45 748.06 761.66
Rate per meter= (a+b+c+d)/10 73.45 74.81 76.17
Say 73.40 74.80 76.20
B Manual means
a) Labour
Mate day 0.120 0.120 0.120 310.00 37.20 37.20 37.20 L-12
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
b) Machinery
Tactor- trolley
Tactor- trolley for transportation & for loading & un
loading Time
hour 1.044 1.044 1.044 612.00 638.93 638.93 638.93 PM12001
Total cost( Without O.H&C.P.) 1552.13 1552.13 1552.13
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 124.17 155.21 186.26
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 167.63 170.73 173.84
1843.93 1878.07 1912.22
Rate per meter= (a+b+c+d)/10 184.39 187.81 191.22
Say 184.40 187.80 191.20
3.27 309 Surface Drains in Hard Rock

Rate per metre may be worked out bsed on quantity of


hard rock as per design. For rate of hard rock cutting,
refer relevent item in this chapter

3.28 309 Sub-Surface Drains with Perforated Pipe

Construction of subsurface drain with perforated pipe of


100 mm internal diameter of metal/ asbestos cement/
Cement concrete/ PVC, closely jointed, perforations
ranging from 3mm to 6mm depending upto size of
material surrounding the pipe, with 150 mm bedding
below the pipe and 300mm cushion above the pipe,
cross section of excavation 450 x 550 mm. Excavated
material to be utilised in roadway at site

Unit= metre
Taking output = 10 metre
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoor for excavation and back filling day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Material

Perforated pipe of cement contrete, internal dia 100 mm metre 10.000 10.000 10.000 109.54 1095.40 1095.40 1095.40 M-134

Crushed stone as per table 300-3 cum 2.400 2.400 2.400 504.46 1210.70 1210.70 1210.70 M-011
Total cost( Without O.H&C.P.) 2902.50 2902.50 2902.50
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 232.20 290.25 348.30
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 313.47 319.28 325.08
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Cost for 10 meter = a+b+c+d 3448.17 3512.03 3575.88
Rate per meter= (a+b+c+d)/10 344.82 351.20 357.59
Say 344.80 351.20 357.60
Note Type of pipe may be modified depending upon provision in design.

3.29 309 Aggregate Sub-Surface Drains

Construction of aggregate sub surface drain 300 mm x


450 mm with aggregates conforming to Table 300-4,
excavated material to be utilised in roadway.

Unit= metre
Taking output = 10 metre
a) Labour
Mate day 0.060 0.060 0.060 310.00 18.60 18.60 18.60 L-12

Mazdoor for excavation and back filling with aggregates day 1.500 1.500 1.500 292.00 438.00 438.00 438.00 L-13
b) Material
Crushed stone as per table 300-3 cum 1.350 1.350 1.350 504.46 681.02 681.02 681.02 M-011
Total cost( Without O.H&C.P.) 1137.62 1137.62 1137.62
c) Overhead charges(a+b) (@ 8%) (@ 10%) (@ 12%) 91.01 113.76 136.51
d) Contractor's profit (a+b+c) (@ 10%) (@ 10%) (@ 10%) 122.86 125.14 127.41
Cost for 10 meter = a+b+c+d 1351.49 1376.52 1401.55
Rate per meter= (a+b+c+d)/10 135.15 137.65 140.15
Say 135.10 137.70 140.20
3.30 309 Underground Drain at Edge of pavement

Construction of an underground drain 1m x 1m (inside


dimensions) lined with RCC-20 cm thick and covered
with RCC slab 10 cm in thickness on urban roads.

Unit= Running metre


Taking output= One metre
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
87.90
a) Earthwork in soil ( Rate taken from Item No. - 3.13
cum 1.500 1.500 1.500 91.60 131.85 137.40 170.70
including OH & CP)
113.80

3916.40
b) RCC work M-20 ( Rate taken from Item No. - 9.06 C
cum 0.495 0.495 0.495 3997.20 1938.62 1978.61 2027.37
Case-ll including OH & CP)
4095.70

60538.00
c) Reinforcement ( Rate taken from Item No. - 9.07
tonne 0.020 0.020 0.020 61708.20 1210.76 1234.16 1258.73
including OH & CP)
62936.60
Rate per metre= (a+b+c) 3281.23 3350.18 3456.80
Rates for these items may be taken from chapters on
earth work and culvert respectively.

3.31 310 Preparation and Surface Treatment of Formation

Preparation and Surface treatment of formation by


removing mud and slurry, watering to the extent needed
to maintain the desired moisture content, trimming to
the required line, grade, profile and rolling with smooth
wheeled roller,complete as per clause 310.

Unit= sqm
Taking output= 3500 sqm
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
b) Machinery
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.125xL1+0
(i) 16 KL Capacity hour
.84
1426.00 1376.09 PM11001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
0.167XL1+
(ii) 12 KL capacity hour
1.12
1252.00 1611.32 PM11002

0.333XL1+2
(iii) 6 KL Capacity hour
.24
907.00 2333.71 PM11003

Vibratory roller hour 2.549 2.549 2.549 2338.00 5959.56 5959.56 5959.56 PM10001
c) Material
Cost of water KL 18.000 18.000 18.000 73.60 1324.80 1324.80 1324.80 M-191
Total cost( Without O.H&C.P.) 10869.25 11104.49 11826.87
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 869.54 1110.45 1419.22
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 1173.88 1221.49 1324.61
Cost for3500 sqm = a+b+c+d+e 12912.67 13436.43 14570.71
Rate per sqm=(a+b+c+d+e)/3500(with OH.&C.P) 3.69 3.84 4.16
Say 3.70 3.80 4.20
Construction of Rock fill Embankment with all lifts and
3.32 313
lead upto 5 km
Construction of Rock fill Embankment from roadway
excavation with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm
thick including filling of surface voids with stone spalls,
blinding top layer with granular material, rolled with
vibratory road roller, all complete as per clause 313.

Unit = cum
Taking output= 500 cum
a) Labour
Mate day 0.040 0.040 0.040 310.00 12.40 12.40 12.40 L-12
Mazdoors day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6461.00 24105.99 0.00 0.00 PM1001
Dozer (175HP) hour 4.808 4930.00 0.00 23703.44 0.00 PM1002
Dozer (90HP) hour 8.621 3274.00 0.00 0.00 28225.15 PM1003
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Tipper for transportation of rock considering lead @5
km
(i) 18 cum capacity t.km 4000.000 5.94 23760.00 0.00 0.00 PM72001
(ii) 14 cum capacity t.km 4000.000 6.63 0.00 26520.00 0.00 PM73001
(iii) 10 cum capacity t.km 4000.000 8.08 0.00 0.00 32320.00 PM74001
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.111xL1+0
(i) 16 KL Capacity hour
.427
1426.00 767.19 PM11001

0.148XL1+
(ii) 12 KL capacity hour
0.569
1252.00 897.68 PM11002

0.296XL1+1
(iii) 6 KL Capacity hour
.138
907.00 1300.64 PM11003

Vibratory roller hour 2.427 2.427 2.427 2338.00 5674.33 5674.33 5674.33 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 16.000 16.000 16.000 73.60 1177.60 1177.60 1177.60 M-191

Total cost( Without O.H&C.P.) 55789.51 58277.45 69002.12


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 4463.16 5827.75 8280.25
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 6025.27 6410.52 7728.24
Cost for500 cum = a+b+c+d+e 66277.93 70515.71 85010.61
Rate per cum=(a+b+c+d+e)/500 (with OH.&C.P) 132.56 141.03 170.02
Say 132.60 141.00 170.00
Note It is assumed that rock is available locally at site from roadway cutting. In case,portion of the rock requires breaking to acceptable size of 300mm, breaking
charges will have to be added.

3.33 Work in Urban Roads

The cost of earth work in urban roads inhabited area will


be comparatively higher due to following reasons:
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small

a) There is mixed traffic on urban roads like slow moving


hand and animal driven carts, rickshaws, cycles, two/
three wheeler apart from the usual vehicular traffic
resulting into traffic jams. This causes loss of working
time which may be in the range of 10-15 percent

b) There is considerable disruption of traffic adversely


affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the-road
side encroachment by the shopkeepers and local shops
who make use of the berms of the road in front of these
shops and unauthorised conversion of road berms into
mini local market. The output of Manpower and
machines is substantially reduced due to factors
mentioned above.

c) Cost of living in urban areas is comparatively more


resulting into higher wages.

d) At times, work is executed during night time due to


heavy traffic during day time. This involves extra
expenditure by way of making arrangement for lighting
and special transport for working parties due to odd
hour.

In the light of above, the authorities engaged in


preparing the cost estimates may exercise their
judgement and cater for the additional cost to the extent
of 2 to3 percent,keeping in view the severity of factors
mentioned above. Supporting details for the extra cost
based on the actual conditions in specific cases will have
to give in justification.
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
Embankment Construction with Fly ash/Pond ash
3.34 Suggestive available from coal or lignite burning Thermal Plants as
waste material.

Construction of embankment with fly ash conforming to


Table 1 of IRC: SP:58 obtained from coal or lignite
burning thermal power stations as waste material,
spread and compacted in layers at OMC, all as specified
in IRC: SP: 58 and as per approved plans. Considering soil
blanketing of 2m either side for 4 lane section

Unit= cum
Taking output= 450 cum
a) Labour
Mate
Mazdoor day 0.120 0.120 0.120 310.00 37.20 37.20 37.20 L-12
b) Machinery day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
Hydraulic Excavator
(i) 1.2 cum bucket capacity 0.757 3388.00 2564.72 0.00 0.00 PM3003
(ii) 1.1 cum bucket capacity hour 0.872 3021.00 0.00 2634.31 0.00 PM3004
(iii) 0.9 cum bucket capacity hour 1.219 2702.00 0.00 0.00 3293.74 PM3005
Tipper hour
Transportation of borrow area soil
67.5X1.6XL
(i) 18 cum capacity t.km
2 5.94 641.52 PM72001

67.5X1.6XL
(ii) 14 cum capacity t.km
2 6.63 716.04 PM73001

67.5X1.6XL
(iii) 10 cum capacity t.km
2 8.08 872.64 PM74001
Transportation of Fly ash
To be supplied by the thermal power plant including
loading and unloading
Loading and unloading
(i) 18 cum capacity hour 0.757 2772.00 2098.40 0.00 0.00 PM6001
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
(ii) 14 cum capacity hour 0.872 2415.00 0.00 2105.88 0.00 PM6002
(iii) 10 cum capacity hour 1.219 2121.00 0.00 0.00 2585.50 PM6003
Motor Grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5900.00 12844.30 0.00 0.00 PM2001
(ii) Motor grader 3.70 metre blade hour 2.626 5398.00 0.00 14175.15 0.00 PM2002
(iii) Motor grader 3.35 metre blade hour 2.929 2982.00 0.00 0.00 8734.28 PM2003
Water tanker (Speed @ water tanker speed km/hr and
return speed @ 20km/hr and spreading speed @ 2.5
km/hr
0.356XL1+1
(i) 16 KL Capacity hour
.231
1426.00 2263.06 PM11001

0.475XL1+
(ii) 12 KL capacity hour
1.642
1252.00 2650.48 PM11002

0.95XL1+3.
(iii) 6 KL Capacity hour
283
907.00 3839.33 PM11003

Vibratory roller hour 2.184 2.184 2.184 2338.00 5106.19 5106.19 5106.19 PM10001
c) Material
Cost of water (considering 5% additional moisture
required)
KL 51.300 51.300 51.300 73.60 3775.68 3775.68 3775.68 M-191

Compensation for Earth taken from private land cum 67.5 67.5 67.5 34.82 2350.35 2350.35 2350.35 M-093
Total cost( Without O.H&C.P.) 32557.42 34427.29 31470.91
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 2604.59 3442.73 3776.51
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 3516.20 3787.00 3524.74
Cost for 450 cum = a+b+c+d+e 38678.22 41657.02 38772.16
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 85.95 92.57 86.16
Say 86.00 92.60 86.20
Note 1. As Fly Ash is available free of cost as waste material from Thermal Plants, cost of materials has not been added.

2. The Earth cover on sides and intermidiate layers of earth sandwitching the Fly Ash has been included in this analysis.
EARTHWORK,EROSION CONTROL AND DRAINAGE.
Ref. to Quantity as per peroject category Rate (Rs) Amount (Rs) Input_Ref
Sr No Description Unit
M. Large Medium Small Large Medium Small
CHAPTER - 4
SUB-BASES, BASES ( NON - BITUMINOUS) AND SHOULDERS
Ref. to Unit Rate as per Project Category
Sr. No. Description
M.
4.01 401 Large Medium Small
A Granular Sub-Base with Graded Material (Table:-
400-1)
Plant Mix Method
4.01A (i) Construction of granular sub-base by providing close cum 1044.80 1062.20 1139.50
graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in
uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the
desired density, complete as per clause 401.
4.01A (ii) Rate per cum for grading-II Material cum 1034.90 1052.10 1129.20
4.01A (iii) Rate per cum for grading-III Material cum 1222.40 1243.10 1323.70
4.01A (iV) Rate per cum for grading-IV Material cum 1193.90 1214.10 1294.20
4.01A (V) Rate per cum for grading-V Material cum 1058.30 1076.00 1153.50
4.01A (VI) Rate per cum for grading-VI Material cum 1060.40 1078.20 1155.70

4.01 401 B By Mix in Place Method


Construction of granular sub-base by providing close
graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method
with front end loader at OMC, and compacting with
vibratory roller to achieve the desired density, complete as
per clause 401.
4.01B (i) Rate per cum for grading-I Material cum 930.80 945.70 967.20
4.01B (ii) Rate per cum for grading-II Material cum 920.90 935.60 957.00
4.01B (iii) Rate per cum for grading-III Material cum 1108.40 1126.60 1151.40
4.01B (iv) Rate per cum for grading-IV Material cum 1079.90 1097.60 1121.90
4.01B (v) Rate per cum for grading-V Material cum 944.30 959.50 981.30
4.01B (vi) Rate per cum for grading-VI Material cum 946.40 961.60 983.40

4.01 401&4 C Using Crusher Run


07
Construction of granular sub-base using crusher run
,spreading in uniform layers with mator grader on prepared
surface ,mixing by mix in place method with rotovator at
OMC, and compating with vibratory roller to achieve the
desired density, complete as per clause 401

4.01C (i) Rate per cum for grading-I Material cum 992.10 1022.10 1055.20
4.01C (ii) Rate per cum for grading-II Material cum 1037.60 1068.40 1102.50
4.01C (iii) Rate per cum for grading-III Material cum 1037.60 1068.40 1102.50
4.01C (iv) Rate per cum for grading-IV Material cum 1037.60 1068.40 1102.50
4.01C (v) Rate per cum for grading-V Material cum 992.10 1022.10 1055.20
4.01C (vi) Rate per cum for grading-VI Material cum 992.10 1022.10 1055.20

4.02A 402 Lime Stabilisation for Improving Sub-grade


Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent slaked
lime having minimum content of 70 per cent of CaO,
grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of
improved sub grade.

A By Manual Means cum 406.40 423.80 433.90


4.02B 402 (i) Lime Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 percent
slaked lime using Binder spreader Machine having
minimum content of 70 per cent of CaO, grading with
motor grader and compacting with the road roller at OMC
to the desired density to form a layer of improved sub
grade.

A By Mechanical Means cum 749.60 773.30 789.80


4.02B 402 (ii) Lime Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stablizer with 2 percent
slaked lime manually spread having minimum content of
70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade.

A By Mechanical Means cum 674.90 697.20 712.30


4.03 402 A Cement Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent
cement , grading with motor grader and compacting with
the road roller at OMC to the desired density to form a
layer of improved sub grade.
A By Manual Means cum 456.60 474.90 485.90
4.03 402 B Cement Stabilisation for Improving Sub-grade
(i) Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil stabilizer with 2 per cent
cement using Binder spreader Machine grading with motor
grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade.

By Mechanical Means cum 799.80 824.40 841.80


4.03B 402 (ii) Cement Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a cum 725.10 748.30 764.30
prepared surface, pulverising, mixing the spread soil in
place with Soil Stablizer with 2 percent cement
manually spread, grading with motor grader and
compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade.
4.04 402 Lime Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent slaked
lime having minimum content of 70 per cent of CaO,
grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of
improved sub grade.

A By Manual Means cum 380.60 397.50 407.10


4.04B 402 (i) Lime Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per cent
slaked limeusing Binder Spreader Machine having
minimum content of 70 per cent of CaO, grading with
motor grader and compacting with the road roller at OMC
to the desired density to form a layer of improved sub
grade.

A By Manual Means cum 723.80 747.10 763.00

4.04B 402 (ii) Lime Stabilisation in Embankment


Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per cent
slaked lime manually spread having minimum content of 70
per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade.

By Mechanical Means cum 649.10 671.00 685.60


4.04B 403 (iii) Cement Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per cent
cement using Binder Spreader machine, grading with
motor grader and compacting with the road roller at OMC
to the desired density to form a layer of improved sub
grade.

By Mechanical Means cum 766.80 790.90 807.60


4.04B 403 (iv) Cement Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-
grade on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per cent
cement manually spread, grading with motor grader and
compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade.
By Mechanical Means cum 692.10 714.80 730.20
4.05 402 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared sub
grade, pulverising, mixing the spread soil in place with
rotavator with 3 per cent slaked lime with minimum
content of 70 per cent of CaO, grading with motor grader cum 619.60 642.80 684.60
and compacting with the road roller at OMC to achieve at
least 98 per cent of the max dry density to form a layer of
sub base.

4.06 403 CementTreated Soil for Sub- Base /Base


Providing, laying and spreading soil on a prepared sub cum 795.60 822.00 867.00
grade, pulverising,adding the designed quantity of cement
to the spread soil mixing in place with rotavator , grading
with motor grader and compacting with the road roller at
OMC to achieve the desired unconfined compressive
strength and to form a layer of sub base /base

4.07 403 Cement Treated Crushed Rock or combination as per


clause 403 and Table 400-4 in sub base /Base
Providing, laying and spreading Material on a prepared
sub grade, pulverising,adding the designed quantity of
cement to the spread Material mixing in place with
rotavator , grading with motor grader and compacting with
the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub base
/base
4.07 (I) For Sub -Base course cum 1362.50 1394.80 1398.60
4.07 (II) For Base course 1182.40 1211.30 1211.80
4.08 403 A Cement Treated Crushed stone Sub base
Plant Mix Method
Construction of granular sub-base by providing graded
Material, mixing with cement in a mechanical mix plant at
OMC, carriage of mixed Material to work site, spreading in
uniform layers with mechanical paver on prepared surface
and compacting with vibratory power roller to achieve the
desired density, complete as per clause 401.

(i) Rate per cum for Grading -III Material cum 1564.40 1593.60 1705.30
(i) Rate per cum for Grading -IV Material cum 1536.00 1564.60 1675.80
4.08 403 Cement Treated Crushed stone Sub base
B By Mix Place Method
Construction of granular sub-base by providing graded
Material, mixing , carriage of mixed Material to work site,
spreading in uniform layers with motor grader on prepared
surface mixing with cement at OMC and compacting with
vibratory power roller to achieve the desired density,
complete as per clause 401.
(i) Rate per cum for Grading -III Material cum 1765.90 1796.40 1833.30
4.09 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450
to the center line of the road and at one metre interval in
the existing thin bituminous wearing coarse including
sweeping and disposal of excavated material within 1000
metres lead,
(i) 25mm deep furrow cutting sqm 4.10 4.20 4.30
(ii) 50mm deep furrow cutting sqm 8.30 8.40 8.60
4.10 404.3.2 Inverted Choke
Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse sand
of specified grade in uniform layer on a prepared surface
with motor grader and compacting with power roller etc.
cum 367.90 381.20 364.90
4.11 404 Water Bound Macadam
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with 3 wheeled steel/ vibratory roller
in stages to proper grade and camber, applying and
brooming requisite type of screening/ binding Materials to
fill up the interstices of coarse aggregate, watering and
compacting to the required density.

A By Manual Means
4.11A(i) (a) Using Screening Crushable type such as
Moorum or Gravel. cum 1062.80 1083.40 1105.80
4.11A(i) (b) Using Screening Type-A (13.2mm agg.) cum 1104.90 1126.30 1149.50
4.11A(i) (c) Using Screening Type-B (11.2mm agg.) cum 1119.50 1141.10 1164.60
4.11A(ii) (a) Using Screening Crushable type such as
Moorum or Gravel. cum 1106.10 1127.50 1150.70
4.11A(ii) (b) Using Screening Type-B (11.2mm agg.)
cum 1162.90 1185.30 1209.60
4.11 B By Mechanical Means
4.11B(i) (a) Using Screening Crushable type such as
Moorum or Gravel. cum 973.50 988.90 1009.90
4.11B(i) (b) Using Screening Type-A (13.2mm agg.) cum 1016.30 1032.50 1054.30
4.11B(i) (c) Using Screening Type-B (11.2mm agg.) cum 1030.30 1046.70 1068.80
4.11B (ii) Grading-II
4.11B(ii (a) Using Screening Crushable type such as
) Moorum or Gravel. cum 1016.90 1033.00 1054.90
4.11B(ii (b) Using Screening Type-B (11.2mm agg.)
) cum 1073.60 1090.80 1113.70
4.12 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not
exceeding 75 mm as specified in Table 400-9 transporting
the aggregates obtained from breaking of cement concrete
slabs at a lead of L1 km., laying and compacting the same
as sub base/ base course, constructed as WBM to clause
404 except the use of screening or binding Material.
cum 288.80 304.90 322.60
4.13 405.2 Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates
at the rate of 0.13 cum per 10 sqm by a mechanical gritter
and rolling the surface as per clause 506.3.8.
cum 16.10 16.40 16.70
4.14 406 A Wet Mix Macadam (Plant Mix Method)
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical
mix plant carriage of mixed Material by tipper to site, laying
in uniform layers with paver in sub- base / base course on
well prepared surface and compacting with vibratory roller
to achieve the desired density.
cum 1068.70 1094.60 1173.20
4.14 406 B Wet Mix Macadam (Plant Mix Method)
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical
mix plant carriage of mixed Material by tipper to site, laying
in uniform layers with grader in sub- base / base course on
well prepared surface and compacting with vibratory roller
to achieve the desired density.
cum 1066.30 1083.50 1144.90
4.15 406 Cement Treated Crushed Stone Base(Plant Mix Method)

Providing, laying, spreading and compacting graded stone


aggregate mixed with cement to crushed stone treated
base specification including pre mixing the material with
water at OMC. in Mechanical mix plant carriage of mixed
Material by tipper to site ,laying in uniform layers with paver
in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired
density.
cum 1605.90 1623.50 1719.70
4.16 408 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting
and excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 408
cum 319.60 340.50 393.70
4.17 408 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 408 cum 459.20 504.60 626.30
4.18 408 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be
adopted as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers
of pavement depending upon approved design of paved
shoulders.
4.19 410 Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25
mm thick cement concrete grade M15, over laid with pre-
cast concrete tiles in cement mortar 1:3 including provision
of all drainage arrangements but excluding kerb channel..
cum 795.40 811.20 829.20
4.20 407 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting with
a vibratory roller to clause 407 to form a layer of sub-
base/Base.
A By Mix in Place Method
4.20A (i) For 53 mm maximum size cum 884.90 898.50 918.00
4.20A (ii) For 37.5 mm maximum size cum 938.60 953.30 973.70
4.20 B By Mixing Plant :
4.20B (i) For 53 mm maximum size cum 928.90 944.90 1000.20
4.20B (ii) For 37.5 mm maximum size cum 926.60 942.50 997.80
4.21 Suggestive Lime, Flyash Stabilised Soil Sub-Base
Construction of Sub-base using lime - Flyash admixture
with granular soil, free from organic matter/ deleterious
material or clayey silts and low plasticity clays having PI
between 5 and 20 and liquid limit less than 25 and
commercial dry lime, slaked at site or pre-slaked with CaO
content not less than 50 per cent, Flyash to conform to
gradation as per clause 4.3 of IRC: 88-1984, lime + Flyash
content ranging between 10 to 30 per cent, the minimum
un-confined compressive strength and CBR value after 28
days curing and 4 days soaking to be 7.5kg/sq, cm and 25
per cent respectively, all as specified in IRC: 88.

cum 470.80 487.20 494.50


4.22 Suggestive Granular crack relief layer
Granular crack relief layer laying Using Mechanical Paver
(Providing, laying ,spreading and compacting graded stone
aggregate to Granular crack relief layer as per IRC SP -37
including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper
to site, laying in uniform layers with paver over base course
on well prepared surface and compacting with vibratory
roller to achieve the desired density.)

Unit:= Cum
Note Rate shall be taken from item no- 4.14 A.
CHAPTER - 4
SUB-BASES, BASES ( NON - BITUMINOUS) AND SHOULDERS
Ref. to Remarks/
Sr. No. Description Unit Quantity as per Project Category Rate Amount
M. Input ref.
4.01 401 Granular Sub-Base with Graded Material (Table:- 400-1) Large Medium Small Large Medium Small

A Plant Mix Method


Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per
clause 401.
Unit = cum
Taking output = 400 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
686.80 686.80 686.80
b) Machinery
Wet mix plant
(i)250 tonne per hour hour 4.480 642.00 2876.16 PM17001
(ii)200 tonne per hour hour 5.600 348.00 1948.80 PM17002
(iii)100 tonne per hour hour 11.200 322.00 3606.40 PM17003
Electric generator
(i)125 KVA hour 4.480 2653.00 11885.44 PM22005
(ii)100 KVA hour 5.600 2251.00 12605.60 PM22006
(iii)62.5 KVA hour 11.200 1421.00 15915.20 PM22007
Front end loader
(I)3.1 cum capacity hour 9.502 4255.00 40431.01 PM5001
(ii) 2.1 cum capacity hour 14.047 2588.00 36353.64 PM5002
(iii) 1 cum capacity hour 29.371 1594.00 46817.37 PM5003
Tipper
for transportation
(I)18 cum capacity t.km 840xL1 5.94 4989.60 L1=1km &
PM72001
(ii) 14 cum capacity t.km 840xL1 6.63 5569.20 L1=1km
&PM73001
(iii) 10 cum capacity t.km 840xL1 8.08 6787.20 L1=1 km
&PM74001
For loading and unloading Time
(I)18 cum capacity hour 4.480 2772.00 12418.56 PM6001
(ii) 14 cum capacity hour 5.600 2415.00 13524.00 PM6002
(iii) 10 cum capacity hour 11.200 2121.00 23755.20 PM6003
Motor grader
(i)Motor grader 4.30 metre blade hour 3.226 5900.00 19033.40 PM2001
(ii)Motor grader 3.70 metre blade hour 3.891 5398.00 21003.62 PM2002
(iii)Motor grader 3.35 metre blade hour 4.339 2982.00 12938.90 PM2003
Vibratory roller hour 2.589 2.589 2.589 2338.00 6053.08 6053.08 6053.08 PM10001
97687.25 97057.94 115873.35
c) Material
Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 26.5 mm @ 27.5 per cent cum 148.077 148.077 148.077 503.85 74608.60 74608.60 74608.60 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 647.19 78409.66 78409.66 78409.66 M-014
9.5 mm to 4.75 below @ 10% cum 53.846 53.846 53.846 625.53 33682.29 33682.29 33682.29 M-015
4.75mm below @40 percent cum 215.385 215.385 215.385 286.72 61755.19 61755.19 61755.19 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
253401.65 253401.65 253401.65
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 188.462 188.462 188.462 647.19 121970.72 121970.72 121970.72 M-014
9.5 mm to 4.75 mm @12.5 % cum 67.308 67.308 67.308 625.53 42103.17 42103.17 42103.17 M-015
4.75 mm below @ 52.5 percent cum 282.692 282.692 282.692 286.72 81053.45 81053.45 81053.45 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
250073.27 250073.27 250073.27
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 366.154 366.154 366.154 647.19 236971.21 236971.21 236971.21 M-014
9.5 mm to 4.75 mm @12% per cent cum 64.615 64.615 64.615 625.53 40418.62 40418.62 40418.62 M-015
4.75 mm below @ 20 percent cum 107.692 107.692 107.692 286.72 30877.45 30877.45 30877.45 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
313213.20 313213.20 313213.20
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 344.615 344.615 344.615 647.19 223031.38 223031.38 223031.38 M-014
9.5 mm to 4.75 mm @11% cum 59.231 59.231 59.231 625.53 37050.77 37050.77 37050.77 M-015
4.75 mm below @ 25 percent cum 134.615 134.615 134.615 286.72 38596.81 38596.81 38596.81 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
303624.88 303624.88 303624.88
OR
For Grading-V Material
53 mm to 26.5 mm @ 27.5 per cent cum 148.077 148.077 148.077 503.85 74608.60 74608.60 74608.60 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 647.19 78409.66 78409.66 78409.66 M-014
9.5 mm to 4.75 below @ 12.50 percent cum 67.308 67.308 67.308 625.53 42103.17 42103.17 42103.17 M-015
4.75mm below @ 37.5 percent cum 201.923 201.923 201.923 286.72 57895.36 57895.36 57895.36 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
257962.71 257962.71 257962.71
OR
For Grading-VI Material
53 mm to 26.5 mm @ 12.5 per cent cum 67.308 67.308 67.308 503.85 33913.14 33913.14 33913.14 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 647.19 78409.66 78409.66 78409.66 M-014
9.5 mm to 4.75 below @ 22.50 percent cum 121.154 121.154 121.154 625.53 75785.46 75785.46 75785.46 M-015
4.75mm below @ 42.5 percent cum 228.846 228.846 228.846 286.72 65614.73 65614.73 65614.73 M-018
Cost of water KL 67.200 67.200 67.200 73.60 4945.92 4945.92 4945.92 M-191
258668.90 258668.90 258668.90
4.01A (i) Rate per cum for grading-I Material
Total cost (Without O.H.& C.P.) 351775.70 351146.39 369961.80
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 28142.06 35114.64 44395.42
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 37991.78 38626.10 41435.72
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 417909.53 424887.13 455792.94
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1044.77 1062.22 1139.48
say 1044.80 1062.20 1139.50
4.01A (ii) Rate per cum for grading-II Material
Total cost (Without O.H.& C.P.) 348447.32 347818.00 366633.42
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 27875.79 34781.80 43996.01
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 37632.31 38259.98 41062.94
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 413955.41 420859.78 451692.37
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1034.89 1052.15 1129.23
say 1034.90 1052.10 1129.20
4.01A (iii) Rate per cum for grading-III Material
Total cost (Without O.H.& C.P.) 411587.25 410957.93 429773.35
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 32926.98 41095.79 51572.80
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 44451.42 45205.37 48134.62
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 488965.65 497259.10 529480.77
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1222.41 1243.15 1323.70
say 1222.40 1243.10 1323.70
4.01A (iV) Rate per cum for grading-IV Material
Total cost (Without O.H.& C.P.) 401998.93 401369.62 420185.04
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 32159.91 40136.96 50422.20
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 43415.88 44150.66 47060.72
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 477574.73 485657.24 517667.96
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1193.94 1214.14 1294.17
say 1193.90 1214.10 1294.20
4.01A (V) Rate per cum for grading-V Material
Total cost (Without O.H.& C.P.) 356336.76 355707.45 374522.86
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 28506.94 35570.74 44942.74
e) Contractor's profit on(a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 38484.37 39127.82 41946.56
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 423328.07 430406.01 461412.17
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1058.32 1076.02 1153.53
say 1058.30 1076.00 1153.50
4.01A (VI) Rate per cum for grading-VI Material
Total cost (Without O.H.& C.P.) 357042.95 356413.64 375229.05
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 28563.44 35641.36 45027.49
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 38560.64 39205.50 42025.65
Cost for 400 cum = a+b+c+d+e (With O.H. & C.P.) 424167.03 431260.50 462282.19
Rate per cum = (a+b+c+d+e)/400 (With O.H. & C.P.) 1060.42 1078.15 1155.71
say 1060.40 1078.20 1155.70
Note Any one of the grading for material may be adopted as per
design.
4.01 401 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with front end
loader at OMC, and compacting with vibratory roller to achieve
the desired density, complete as per clause 401.
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
1295.60 1295.60 1295.60
b) Machinery
Front end loader for Mixing at stock pile location.
(I)3.1 cum capacity hour 4.464 4255.00 18994.32 PM5001
(ii) 2.1 cum capacity hour 6.579 2588.00 17026.45 PM5002
(iii) 1 cum capacity hour 13.889 1594.00 22139.07 PM5003
Water tanker (speed@20km / hr and return speed @30km / hr
and spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.292xL1+0. 1426.00 1525.82 L1=1km &
778 PM11001
(ii)12 KL capacity hour 0.389xL1+1. 1252.00 1785.35 L1=1km &
037 PM11002
(iii)6 KL capacity hour 0.778xL1+2. 907.00 2586.76 L1=1km &
074 PM11003
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.016 5900.00 11894.40 PM2001
(ii)Motor grader 3.70 metre blade hour 2.432 5398.00 13127.94 PM2002
(iii)Motor grader 3.35 metre blade hour 2.712 2982.00 8087.18 PM2003
Vibratory roller hour 1.618 1.618 1.618 2338.00 3782.88 3782.88 3782.88 PM10001
36197.42 35722.62 36595.90
c) Material
Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 26.5 mm @ 27.5 per cent cum 92.548 92.548 92.548 503.85 46630.31 46630.31 46630.31 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 75.721 75.721 75.721 647.19 49005.87 49005.87 49005.87 M-014
9.5 mm to 4.75mm @10 percent cum 33.654 33.654 33.654 625.53 21051.59 21051.59 21051.59 M-015
4.75mm below @ 40 percent cum 134.615 134.615 134.615 286.72 38596.81 38596.81 38596.81 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
158375.78 158375.78 158375.78
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 117.788 117.788 117.788 647.19 76231.22 76231.22 76231.22 M-014
9.5 mm to 4.75 mm @12.5 % cum 42.067 42.067 42.067 625.53 26314.17 26314.17 26314.17 M-015
4.75 mm below @ 52.5 percent cum 176.683 176.683 176.683 286.72 50658.55 50658.55 50658.55 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
156295.14 156295.14 156295.14
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 228.846 228.846 228.846 647.19 148106.84 148106.84 148106.84 M-014
9.5 mm to 4.75 mm @12 % cum 40.385 40.385 40.385 625.53 25262.03 25262.03 25262.03 M-015
4.75 mm below @ 20 percent cum 67.308 67.308 67.308 286.72 19298.55 19298.55 19298.55 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
195758.62 195758.62 195758.62
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 215.385 215.385 215.385 647.19 139395.02 139395.02 139395.02 M-014
9.5 mm to 4.75 mm @11 per cent cum 37.019 37.019 37.019 625.53 23156.50 23156.50 23156.50 M-015
4.75 mm below @ 25 percent cum 84.135 84.135 84.135 286.72 24123.19 24123.19 24123.19 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
189765.90 189765.90 189765.90
OR
For Grading-V Material
53 mm to 26.5 mm @ 27.5 per cent cum 92.548 92.548 92.548 503.85 46630.31 46630.31 46630.31 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 75.721 75.721 75.721 647.19 49005.87 49005.87 49005.87 M-014
9.5 mm to 4.75mm @ 12.50 percent cum 42.067 42.067 42.067 625.53 26314.17 26314.17 26314.17 M-015
4.75mm below @ 37.5 percent cum 126.202 126.202 126.202 286.72 36184.64 36184.64 36184.64 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
161226.19 161226.19 161226.19
OR
For Grading-VI Material
53 mm to 26.5 mm @ 12.5 per cent cum 42.067 42.067 42.067 503.85 21195.46 21195.46 21195.46 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 75.721 75.721 75.721 647.19 49005.87 49005.87 49005.87 M-014
9.5 mm to 4.75mm @ 22.50 percent cum 75.721 75.721 75.721 625.53 47365.76 47365.76 47365.76 M-015
4.75mm below @ 42.5 percent cum 143.029 143.029 143.029 286.72 41009.27 41009.27 41009.27 M-018
Cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
161667.56 161667.56 161667.56
4.01B (i) Rate per cum for grading-I Material
Total cost (Without O.H.& C.P.) 195868.81 195394.01 196267.28
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15669.50 19539.40 23552.07
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21153.83 21493.34 21981.94
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 232692.14 236426.75 241801.29
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 930.77 945.71 967.21
say 930.80 945.70 967.20
4.01B (ii) Rate per cum for grading-II Material
Total cost (Without O.H.& C.P.) 193788.16 193313.36 194186.63
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15503.05 19331.34 23302.40
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20929.12 21264.47 21748.90
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 230220.33 233909.17 239237.93
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 920.88 935.64 956.95
say 920.90 935.60 957.00
4.01B (iii) Rate per cum for grading-III Material
Total cost (Without O.H.& C.P.) 233251.65 232776.85 233650.12
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 18660.13 23277.68 28038.01
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 25191.18 25605.45 26168.81
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 277102.95 281659.98 287856.95
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1108.41 1126.64 1151.43
say 1108.40 1126.60 1151.40
4.01B (iv) Rate per cum for grading-IV Material
Total cost (Without O.H.& C.P.) 227258.92 226784.12 227657.40
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 18180.71 22678.41 27318.89
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 24543.96 24946.25 25497.63
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 269983.60 274408.79 280473.91
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1079.93 1097.64 1121.90
say 1079.90 1097.60 1121.90
4.01B (v) Rate per cum for grading-V Material
Total cost (Without O.H.& C.P.) 198719.22 198244.42 199117.69
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15897.54 19824.44 23894.12
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21461.68 21806.89 22301.18
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 236078.43 239875.74 245312.99
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 944.31 959.50 981.25
say 944.30 959.50 981.30
4.01B (vi) Rate per cum for grading-VI Material
Total cost (Without O.H.& C.P.) 199160.59 198685.79 199559.06
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15932.85 19868.58 23947.09
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21509.34 21855.44 22350.61
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 236602.78 240409.80 245856.76
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 946.41 961.64 983.43
say 946.40 961.60 983.40
Note Any one of the grading for material may be adopted as per
design.
4.01 401&40 C Using Crusher Run
7
Construction of granular sub-base using crusher run ,spreading in
uniform layers with mator grader on prepared surface ,mixing by
mix in place method with rotovator at OMC, and compating with
vibratory roller to achieve the desired density, complete as per
clause 401
Unit=cum
Taking output=250 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
686.80 686.80 686.80
b) Machinery
Front end loader for loading to Tipper
(I)3.1 cum capacity hour 1.548 4255.00 6586.74 PM5001
(ii) 2.1 cum capacity hour 2.283 2588.00 5908.40 PM5002
(iii) 1 cum capacity hour 4.808 1594.00 7663.95 PM5003
Tipper
for transportation
(I)18 cum capacity t.km 525xL1 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL1 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL1 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 1.548 2772.00 4291.06 PM6001
(ii) 14 cum capacity hour 2.283 2415.00 5513.45 PM6002
(iii) 10 cum capacity hour 4.808 2121.00 10197.77 PM6003
Water tanker (speed@20km /hr and return speed @30 km / hr
and spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.292xL1+0. 1426.00 1525.82 L1=1km &
778 PM11001
(ii)12 KL capacity hour 0.389xL1+1. 1252.00 1785.35 L1=1km &
037 PM11002
(iii)6 KL capacity hour 0.778xL1+2. 907.00 2586.76 L1=1km &
074 PM11003
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.016 5900.00 11894.40 PM2001
(ii)Motor grader 3.70 metre blade hour 2.432 5398.00 13127.94 PM2002
(iii)Motor grader 3.35 metre blade hour 2.712 2982.00 8087.18 PM2003
Vibratory roller hour 1.618 1.618 1.618 2338.00 3782.88 3782.88 3782.88 PM10001
31199.40 33598.77 36560.55
c) Material
Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 516.41 173791.59 173791.59 173791.59 M-034
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
176882.79 176882.79 176882.79
OR
For Grading-II Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 544.89 183376.19 183376.19 183376.19 M-025
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
186467.39 186467.39 186467.39
OR
For Grading-III Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 544.89 183376.19 183376.19 183376.19 M-025
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
186467.39 186467.39 186467.39
OR
For Grading-IV Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 544.89 183376.19 183376.19 183376.19 M-025
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
186467.39 186467.39 186467.39
OR
For Grading-V Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 516.41 173791.59 173791.59 173791.59 M-034
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
176882.79 176882.79 176882.79
OR
For Grading-VI Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 516.41 173791.59 173791.59 173791.59 M-034
cost of water KL 42.000 42.000 42.000 73.60 3091.20 3091.20 3091.20 M-191
176882.79 176882.79 176882.79
4.01C (i) Rate per cum for grading-I Material
Total cost (Without O.H.& C.P.) 208768.99 211168.36 214130.14
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16701.52 21116.84 25695.62
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 22547.05 23228.52 23982.58
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 248017.56 255513.72 263808.33
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 992.07 1022.05 1055.23
say 992.10 1022.10 1055.20
4.01C (ii) Rate per cum for grading-II Material
Total cost (Without O.H.& C.P.) 218353.59 220752.96 223714.74
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 17468.29 22075.30 26845.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 23582.19 24282.83 25056.05
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 259404.07 267111.08 275616.56
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1037.62 1068.44 1102.47
say 1037.60 1068.40 1102.50
4.01C (iii) Rate per cum for grading-III Material
Total cost (Without O.H.& C.P.) 218353.59 220752.96 223714.74
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 17468.29 22075.30 26845.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 23582.19 24282.83 25056.05
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 259404.07 267111.08 275616.56
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1037.62 1068.44 1102.47
say 1037.60 1068.40 1102.50
4.01C (iv) Rate per cum for grading-IV Material
Total cost (Without O.H.& C.P.) 218353.59 220752.96 223714.74
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 17468.29 22075.30 26845.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 23582.19 24282.83 25056.05
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 259404.07 267111.08 275616.56
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1037.62 1068.44 1102.47
say 1037.60 1068.40 1102.50
4.01C (v) Rate per cum for grading-V Material
Total cost (Without O.H.& C.P.) 208768.99 211168.36 214130.14
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16701.52 21116.84 25695.62
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 22547.05 23228.52 23982.58
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 248017.56 255513.72 263808.33
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 992.07 1022.05 1055.23
say 992.10 1022.10 1055.20
4.01C (vi) Rate per cum for grading-VI Material
Total cost (Without O.H.& C.P.) 208768.99 211168.36 214130.14
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16701.52 21116.84 25695.62
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 22547.05 23228.52 23982.58
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 248017.56 255513.72 263808.33
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 992.07 1022.05 1055.23
say 992.10 1022.10 1055.20
Note Any one of the grading for material may be adopted as per
design.

4.02A 402 Lime Stabilisation for Improving Sub-grade


Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with rotavator with 2 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density to
form a layer of improved sub grade.
Unit = cum
Taking output = 300 cum
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Tractor with ripper and rotavator
attachments @250 cum per hour for mixing hour 1.200 1.200 1.200 650 780.00 780.00 780.00 PM
(12001+130
01+14001)

Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii) 6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
43828.95 46266.09 46847.33
c) Material
Lime at site tonne 10.500 10.500 10.500 3637.51 38193.86 38193.86 38193.86 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
55981.46 55981.46 55981.46
Total cost (Without O.H.& C.P.) 102628.00 105065.15 105646.39
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 8210.24 10506.51 12677.57
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 11083.82 11557.17 11832.40
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 121922.07 127128.83 130156.35
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 406.41 423.76 433.85
say 406.40 423.80 433.90
4.02B 402 (i) Lime Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stabilizer with 2 percent slaked lime using Binder
spreader Machine having minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved
sub grade.

Unit = cum
Taking output = 300 cum
A By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
686.80 686.80 686.80
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabilizer for mixing and pulverising with capacity 1000 m2 hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
per hour
Binder Spreader hour 2.667 2.667 2.667 7872.00 20994.62 20994.62 20994.62 PM50001
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/ hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii)6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
132625.48 135062.62 135643.86
c) Material
Lime at site tonne 10.500 10.500 10.500 3637.51 38193.86 38193.86 38193.86 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.00 300.00 300.00 34.82 10446.00 10446.00 10446.00 M-093
55981.46 55981.46 55981.46
Total cost (Without O.H.& C.P.) 189293.73 191730.88 192312.12
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15143.50 19173.09 23077.45
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20443.72 21090.40 21538.96
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 224880.95 231994.36 236928.53
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 749.60 773.31 789.76
say 749.60 773.30 789.80
4.02B 402 (ii) Lime Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stablizer with 2 percent slaked lime manually spread
having minimum content of 70 per cent of CaO, grading with
motor grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade.

Unit = cum
Taking output = 300 cum
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for sprying lime day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavtor
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabiliser for mixing and pulversing with capacity1000 m2 hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM77004
per hour
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/ hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii)6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
111630.85 114068.00 114649.24
c) Material
Lime at site tonne 10.500 10.500 10.500 3637.51 38193.86 38193.86 38193.86 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
55981.46 55981.46 55981.46
Total cost (Without O.H.& C.P.) 170429.91 172867.05 173448.29
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 13634.39 17286.71 20813.80
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 18406.43 19015.38 19426.21
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 202470.73 209169.14 213688.30
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 674.90 697.23 712.29
say 674.90 697.20 712.30
4.03 402 A Cement Stabilisation for Improving Sub-grade
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with rotavator with 2 per cent cement , grading with motor
grader and compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade.
Unit = cum
Taking output = 300 cum
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying cement day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Tractor with ripper and rotavator
attachments @250 cum per hour for mixing hour 1.200 1.200 1.200 650 780.00 780.00 780.00 PM
(12001+130
01+14001)

Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 hr/km and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii)6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
43828.95 46266.09 46847.33
c) Material
cement at site tonne 10.500 10.500 10.500 4844.00 50862.00 50862.00 50862.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
68649.60 68649.60 68649.60
Total cost (Without O.H.& C.P.) 115296.15 117733.29 118314.53
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 9223.69 11773.33 14197.74
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 12451.98 12950.66 13251.23
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 136971.82 142457.29 145763.51
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 456.57 474.86 485.88
say 456.60 474.90 485.90
4.03 402 B Cement Stabilisation for Improving Sub-grade
(i) Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil stabilizer with 2 per cent cement using Binder
spreader Machine grading with motor grader and compacting with
the road roller at OMC to the desired density to form a layer of
improved sub grade.
Unit = cum
Taking output = 300 cum
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying cement day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
686.80 686.80 686.80
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil stabilizer for mixing and pulverising with capacity 1000 m2 hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
per hour
Binder Spreader hour 2.667 2.667 2.667 7872.00 20994.62 20994.62 20994.62 PM50001
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader3.7metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/ hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii)6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
132625.48 135062.62 135643.86
c) Material
cement at site tonne 10.500 10.500 10.500 4844.00 50862.00 50862.00 50862.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
68649.60 68649.60 68649.60
Total cost (Without O.H.& C.P.) 201961.88 204399.02 204980.26
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16156.95 20439.90 24597.63
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21811.88 22483.89 22957.79
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 239930.71 247322.82 252535.68
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 799.77 824.41 841.79
say 799.80 824.40 841.80
4.03B 402 (ii) Cement Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place with
Soil Stablizer with 2 percent cement manually spread, grading
with motor grader and compacting with the road roller at OMC to
the desired density to form a layer of improved sub grade.

Unit = cum
Taking output = 300 cum

a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for sprying cement day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavtor
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabiliser for mixing and pulversing with capacity1000 m2 hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
per hour
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/ hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+2. 1426.00 1525.82 L1=1km &
217 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
956 PM11002
(iii) 6 KL capacity hour 1.847xL1+5. 907.00 2586.76 L1=1km &
911 PM11003
111630.85 114068.00 114649.24
c) Material
Cement at site tonne 10.500 10.500 10.500 4844.00 50862.00 50862.00 50862.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
68649.60 68649.60 68649.60
Total cost (Without O.H.& C.P.) 183098.05 185535.20 186116.44
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 14647.84 18553.52 22333.97
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 19774.59 20408.87 20845.04
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 217520.49 224497.59 229295.45
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 725.07 748.33 764.32
say 725.10 748.30 764.30
4.04 402 Lime Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with rotavator with 2 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density to
form a layer of improved sub grade.
Unit = cum
Taking output = 300 cum
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Tractor with ripper and rotavator
attachments @250 cum per hour for mixing hour 1.200 1.200 1.200 650.00 780.00 780.00 780.00 #VALUE!
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader3.35metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.594xL1+1. 1426.00 1525.82 L1=1km &
9 PM11001
(ii)12 KL capacity hour 0.792xL1+2. 1252.00 1785.35 L1=1km &
533 PM11002
(iii)6 KL capacity hour 1.583xL1+5. 907.00 2586.76 L1=1km &
067 PM11003
43828.95 46266.09 46847.33
c) Material
Lime at site tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 73.60 6292.80 6292.80 6292.80 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
49476.39 49476.39 49476.39
Total cost (Without O.H.& C.P.) 96122.94 98560.08 99141.32
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 7689.84 9856.01 11896.96
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 10381.28 10841.61 11103.83
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 114194.05 119257.70 122142.11
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 380.65 397.53 407.14
say 380.60 397.50 407.10
4.04B 402 (i) Lime Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stabilizer with 2 per cent slaked limeusing Binder
Spreader Machine having minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved
sub grade.

Unit = cum
Taking output = 300 cum
A By Manual Means
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
686.80 686.80 686.80
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabilizer for mixing and pulverising with capacity hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
1000m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7872.00 20994.62 20994.62 20994.62 PM50001
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km/ hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.594xL1+1. 1426.00 1525.82 L1=1km &
9 PM11001
(ii)12 KL capacity hour 0.792xL1+2. 1252.00 1785.35 L1=1km &
533 PM11002
(iii)6 KL capacity hour 1.583xL1+5. 907.00 2586.76 L1=1km &
067 PM11003
132625.48 135062.62 135643.86
c) Material
Lime at site tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 73.60 6292.80 6292.80 6292.80 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
49476.39 49476.39 49476.39
Total cost (Without O.H.& C.P.) 182788.67 185225.81 185807.05
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 14623.09 18522.58 22296.85
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 19741.18 20374.84 20810.39
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 217152.94 224123.23 228914.29
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 723.84 747.08 763.05
say 723.80 747.10 763.00
4.04B 402 (ii) Lime Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stabilizer with 2 per cent slaked lime manually spread
having minimum content of 70 per cent of CaO, grading with
motor grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade.

Unit = cum
Taking output = 300 cum
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabilizer for mixing and pulverising with capacity hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
1000m2 per hour
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 hr/ and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.594xL1+1. 1426.00 1525.82 L1=1km &
9 PM11001
(ii)12 KL capacity hour 0.792xL1+2. 1252.00 1785.35 L1=1km &
533 PM11002
(iii)6 KL capacity hour 1.583xL1+5. 907.00 2586.76 L1=1km &
067 PM11003
111630.85 114068.00 114649.24
c) Material
Lime at site tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 73.60 6292.80 6292.80 6292.80 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
49476.39 49476.39 49476.39
Total cost (Without O.H.& C.P.) 163924.84 166361.99 166943.23
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 13113.99 16636.20 20033.19
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 17703.88 18299.82 18697.64
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 194742.71 201298.01 205674.06
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 649.14 670.99 685.58
say 649.10 671.00 685.60
4.04B 403 (iii) Cement Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stabilizer with 2 per cent cement using Binder Spreader
machine, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved
sub grade.
Unit = cum
Taking output = 300 cum
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying cement day 1.000 1.000 1.000 292.00 292.00 292.00 292.00 L-13
b) Machinery 686.80 686.80 686.80
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabilizer for mixing and pulverising with capacity hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
1000m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7872.00 20994.62 20994.62 20994.62 PM50001
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 hr/ and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.594xL1+1. 1426.00 1525.82 L1=1km &
9 PM11001
(ii)12 KL capacity hour 0.792xL1+2. 1252.00 1785.35 L1=1km &
533 PM11002
(iii)6 KL capacity hour 1.583xL1+5. 907.00 2586.76 L1=1km &
067 PM11003
132625.48 135062.62 135643.86
c) Material
cement at site tonne 9.000 9.000 9.000 4844.00 43596.00 43596.00 43596.00 M-081
Cost of water including water for curing KL 85.500 85.500 85.500 73.60 6292.80 6292.80 6292.80 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
60334.80 60334.80 60334.80
Total cost (Without O.H.& C.P.) 193647.08 196084.22 196665.46
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15491.77 19608.42 23599.86
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20913.88 21569.26 22026.53
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 230052.73 237261.91 242291.85
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 766.84 790.87 807.64
say 766.80 790.90 807.60
4.04B 403 (iv) Cement Stabilisation in Embankment
Providing,laying and spreading available soil in the sub-grade on
a prepared surface, pulverising, mixing the spread soil in place
with Soil Stabilizer with 2 per cent cement manually spread,
grading with motor grader and compacting with the road roller at
OMC to the desired density to form a layer of improved sub
grade.
Unit = cum
Taking output = 300 cum
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor for spraying cement day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
2817.60 2817.60 2817.60
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 3.365 3388.00 11400.62 PM3003
(ii)1.1 cum bucket capacity hour 3.875 3021.00 11706.38 PM3004
(iii)0.9 cum bucket capacity hour 5.418 2702.00 14639.44 PM3005
Tipper for transportation
(I)18 cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 3.365 2772.00 9327.78 PM6001
(ii) 14 cum capacity hour 3.875 2415.00 9358.13 PM6002
(iii) 10 cum capacity hour 5.418 2121.00 11491.58 PM6003
Soil Stabilizer for mixing and pulverising with capacity hour 2.667 2.667 2.667 25715.00 68581.91 68581.91 68581.91 PM49001
1000m2 per hour
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Water tanker (speed@20km /hr and return speed @30 km /hr and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.594xL1+1. 1426.00 1525.82 L1=1km &
900 PM11001
(ii)12 KL capacity hour 0.792xL1+2. 1252.00 1785.35 L1=1km &
533 PM11002
(iii)6 KL capacity hour 1.583xL1+5. 907.00 2586.76 L1=1km &
067 PM11003
111630.85 114068.00 114649.24
c) Material
cement at site tonne 9.000 9.000 9.000 4844.00 43596.00 43596.00 43596.00 M-081
Cost of water including water for curing KL 85.500 85.500 85.500 73.60 6292.80 6292.80 6292.80 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 34.82 10446.00 10446.00 10446.00 M-093
60334.80 60334.80 60334.80
Total cost (Without O.H.& C.P.) 174783.25 177220.40 177801.64
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 13982.66 17722.04 21336.20
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 18876.59 19494.24 19913.78
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 207642.50 214436.68 219051.62
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 692.14 714.79 730.17
say 692.10 714.80 730.20
4.05 402 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with 3
per cent slaked lime with minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road
roller at OMC to achieve at least 98 per cent of the max dry
density to form a layer of sub base.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
3808.80 3808.80 3808.80
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 7.852 3388.00 26602.58 PM3003
(ii)1.1 cum bucket capacity hour 9.043 3021.00 27318.90 PM3004
(iii)0.9 cum bucket capacity hour 12.642 2702.00 34158.68 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 7.852 2772.00 21765.74 PM6001
(ii) 14 cum capacity hour 9.043 2415.00 21838.85 PM6002
(iii) 10 cum capacity hour 12.642 2121.00 26813.68 PM6003
Motor Grader for grading
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Tractor with ripper and rotovator
attachments @ 250 cum per hour for mixing hour 1.200 1.200 1.200 650 780.00 780.00 780.00 PM
(12001+130
01+14001)

Water tanker (speed@20km /hr and return speed @30 km / hr


and spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.365xL1+1. 1426.00 1525.82 L1=1km &
167 PM11001
(ii)12 KL capacity hour 0.486xL1+1. 1252.00 1785.35 L1=1km &
556 PM11002
(iii)6 KL capacity hour 0.972xL1+3. 907.00 2586.76 L1=1km &
111 PM11003
71468.87 74359.34 81688.69
c) Material
Lime at site tonne 15.750 15.750 15.750 3637.51 57290.78 57290.78 57290.78 M-190
Compensation for earth taken from private land cum 300.000 300.000 300.000 73.60 22080.00 22080.00 22080.00 M-191
Cost of water KL 52.500 52.500 52.500 34.82 1828.05 1828.05 1828.05 M-093
81198.83 81198.83 81198.83
Total cost (Without O.H.& C.P.) 156476.50 159366.97 166696.32
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 12518.12 15936.70 20003.56
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 16899.46 17530.37 18669.99
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 185894.08 192834.04 205369.86
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 619.65 642.78 684.57
say 619.60 642.80 684.60
4.06 403 CementTreated Soil for Sub- Base /Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising,adding the designed quantity of cement to the spread
soil mixing in place with rotavator , grading with motor grader and
compacting with the road roller at OMC to achieve the desired
unconfined compressive strength and to form a layer of sub base
/base
Unit = cum
Taking output = 300 cum for 4 percent quantity of cement by
weight of soil
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
3808.80 3808.80 3808.80
b) Machinery
Hydraulic Excavator
(i)1.2 cum bucket capacity hour 7.852 3388.00 26602.58 PM3003
(ii)1.1 cum bucket capacity hour 9.043 3021.00 27318.90 PM3004
(iii)0.9 cum bucket capacity hour 12.642 2702.00 34158.68 PM3005
Tipper
for transportation
(I)18 cum capacity t.km 525xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 cum capacity t.km 525xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 cum capacity t.km 525xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading Time
(I)18 cum capacity hour 7.852 2772.00 21765.74 PM6001
(ii) 14 cum capacity hour 9.043 2415.00 21838.85 PM6002
(iii) 10 cum capacity hour 12.642 2121.00 26813.68 PM6003
Motor Grader for grading
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Tractor with ripper and rotovator
attachments @ 250 cum per hour for mixing hour 1.200 1.200 1.200 650.00 780.00 780.00 780.00 #VALUE!
Water tanker (speed@20km /hr and return speed @30 hr/ and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.365xL1+1. 1426.00 1525.82 L1=1km &
167 PM11001
(ii)12 KL capacity hour 0.486xL1+1. 1252.00 1785.35 L1=1km &
556 PM11002
(iii)6 KL capacity hour 0.972xL1+3. 907.00 2586.76 L1=1km &
111 PM11003
71468.87 74359.34 81688.69
c) Material
cement at site( @4 percent of 525 tonne) tonne 21.000 21.000 21.000 4844.00 101724.00 101724.00 101724.00 M-081
Compensation for earth taken from private land cum 300.000 300.000 300.000 73.60 22080.00 22080.00 22080.00 M-191
Cost of water KL 52.500 52.500 52.500 34.82 1828.05 1828.05 1828.05 M-093
125632.05 125632.05 125632.05
Total cost (Without O.H.& C.P.) 200909.72 203800.19 211129.54
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16072.78 20380.02 25335.54
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21698.25 22418.02 23646.51
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 238680.74 246598.23 260111.59
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 795.60 821.99 867.04
say 795.60 822.00 867.00
4.07 403 Cement Treated Crushed Rock or combination as per clause 403
and Table 400-4 in sub base /Base
Providing, laying and spreading Material on a prepared sub
grade, pulverising,adding the designed quantity of cement to the
spread Material mixing in place with rotavator , grading with
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub base /base
Unit = cum
Taking output = 300 cum
Quantity of cement assumed as 4 percent of quantity of crushed
rock by weight
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
3808.80 3808.80 3808.80
b) Machinery
Motor Grader for grading
(i)Motor grader 4.30 metre blade hour 2.419 5900.00 14272.10 PM2001
(ii)Motor grader 3.70 metre blade hour 2.918 5398.00 15751.36 PM2002
(iii)Motor grader 3.35 metre blade hour 3.254 2982.00 9703.43 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
Tractor with ripper and rotovator
attachments @ 250 cum per hour for mixing hour 1.200 1.200 1.200 650 780.00 780.00 780.00 PM
(12001+130
01+14001)

Water tanker (speed@20km /hr and return speed @30 km / hr


and spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.417xL1+1. 1426.00 1525.82 L1=1km &
333 PM11001
(ii)12 KL capacity hour 0.556xL1+1. 1252.00 1785.35 L1=1km &
778 PM11002
(iii)6 KL capacity hour 1.111xL1+3. 907.00 2586.76 L1=1km &
556 PM11003
19982.05 21720.84 16474.32
c) Material
cement at site @4 percent by weight of crushed tonne 24.000 24.000 24.000 4844.00 116256.00 116256.00 116256.00 M-081
aggregate ( 600 tonne)
Grading of material for sub-base course
37.5mm to 9.5mm @ 55 percent cum 211.200 211.200 211.200 587.31 124039.87 124039.87 124039.87 M-013
9.5mm to 4.75mm @ 20 percent cum 76.800 76.800 76.800 625.53 48040.70 48040.70 48040.70 M-015
4.75mm to 75 micron @ 25 percent cum 96.000 96.000 96.000 286.72 27525.12 27525.12 27525.12 M-018
Cost of water kL 60.000 60.000 60.000 73.60 4416.00 4416.00 4416.00 M-191
204021.70 204021.70 204021.70
or
Grading of material for Base course
37.5 mm to 9.5mm @ 32.5 percent cum 124.800 124.800 124.800 587.31 73296.29 73296.29 73296.29 M-013
9.5mm to 4.75mm @ 5 percent cum 19.200 19.200 19.200 625.53 12010.18 12010.18 12010.18 M-015
4.75mm to 75 micron @ 62.5 percent cum 240.000 240.000 240.000 286.72 68812.80 68812.80 68812.80 M-018
Cost of water kL 60.000 60.000 60.000 73.60 4416.00 4416.00 4416.00 M-191
158535.26 158535.26 158535.26
4.07 (I) For Sub -Base course
Total cost (Without O.H.& C.P.) 344068.54 345807.34 340560.82
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 27525.48 34580.73 40867.30
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 37159.40 38038.81 38142.81
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 408753.43 418426.88 419570.93
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 1362.51 1394.76 1398.57
say 1362.50 1394.80 1398.60
4.07 (II) For Base course
Total cost (Without O.H.& C.P.) 298582.11 300320.91 295074.38
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 23886.57 30032.09 35408.93
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 32246.87 33035.30 33048.33
Cost for 300 cum = a+b+c+d+e (With O.H. & C.P.) 354715.55 363388.30 363531.64
Rate per cum = (a+b+c+d+e)/300 (With O.H. & C.P.) 1182.39 1211.29 1211.77
say 1182.40 1211.30 1211.80
Note Quantities of aggregate provide under 'c' above are uncompacted
quantities

4.08 403 A Cement Treated Crushed stone Sub base


Plant Mix Method
Construction of granular sub-base by providing graded Material,
mixing with cement in a mechanical mix plant at OMC, carriage
of mixed Material to work site, spreading in uniform layers with
mechanical paver on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete as
per clause 401.
Laying Using Mechanical Paver
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
1295.60 1295.60 1295.60
b) Machinery
Wet mix plant
(i)250 tonne per hoour hour 2.800 642.00 1797.60 PM17001
(ii)200 tonne per hoour hour 3.500 348.00 1218.00 PM17002
(iii)100 tonne per hoour hour 7.000 322.00 2254.00 PM17003
Electric generator
(i) 125 KVA hour 2.800 2653.00 7428.40 PM22005
(ii)100KVA hour 3.500 2251.00 7878.50 PM22006
(iii)62.5 KVA hour 7.000 1421.00 9947.00 PM22007
Front end loader for loading to Tipper
(i) 3.1Cum capacity hour 5.939 4255.00 25270.45 PM5001
(ii)2.1 Cum capacity hour 8.779 2588.00 22720.05 PM5002
PM2200 (iii)1 Cum Capacity hour 18.357 1594.00 29261.06 PM5003
6
Tipper For Transportation
(i) 18Cum capacity t.km 525xL1 5.94 3118.50 L1=1km&P
M72001
(ii)14 Cum capacity t.km 525xL1 6.63 3480.75 L1=1km&P
M73001
(iii)10 Cum Capacity t.km 525xL1 8.08 4242.00 L1=1km&P
M74001
For loading &unloading time
(i) 18Cum capacity hour 5.600 2772.00 15523.20 PM6001
(ii)14 Cum capacity hour 6.300 2415.00 15214.50 PM6002
(iii)10 Cum Capacity hour 9.800 2121.00 20785.80 PM6003
Mechanical paver finisher hour 2.800 3.500 3.500 1583.00 4432.40 5540.50 5540.50 PM28001
Vibratory roller hour 2.240 2.800 2.800 2338.00 5237.12 6546.40 6546.40 PM10001
Water tanker (speed@20km /hr and return speed @30 hr/ and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.328xL1+0. 1426.00 1525.82 L1=1km &
875 PM11001
(ii)12 KL capacity hour 0.4375xL1+ 1252.00 1785.35 L1=1km &
1.167 PM11002
(iii)6 KL capacity hour 0.875xL1+2. 907.00 2586.76 L1=1km &
333 PM11003
64333.49 64384.05 81163.52
c) Material
cement at site tonne 13.125 13.125 13.125 4844.00 63577.50 63577.50 63577.50 M-081
cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
70919.10 70919.10 70919.10
(i)For Grading -III Material
26.5mm to 9.5mm @ 68 percent cum 228.846 228.846 228.846 647.19 148106.84 148106.84 148106.84 M-014
9.5mm to 4.75mm @ 12 percent cum 40.385 40.385 40.385 625.53 25262.03 25262.03 25262.03 M-015
4.75mm below @ 20 percent cum 67.308 67.308 67.308 286.72 19298.55 19298.55 19298.55 M-018
192667.42 192667.42 192667.42
OR
(i)For Grading -IV Material
26.5 mm to 9.5mm @ 64 percent cum 215.385 215.385 215.385 647.19 139395.02 139395.02 139395.02 M-014
9.5mm to 4.75mm @ 11 percent cum 37.019 37.019 37.019 625.53 23156.50 23156.50 23156.50 M-015
4.75mm below@25 percent cum 84.135 84.135 84.135 286.72 24123.19 24123.19 24123.19 M-018
186674.70 186674.70 186674.70
(i) Rate per cum for Grading -III Material
Total cost (Without O.H.& C.P.) 329215.61 329266.18 346045.64
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 26337.25 32926.62 41525.48
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 35555.29 36219.28 38757.11
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 391108.14 398412.07 426328.23
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1564.43 1593.65 1705.31
say 1564.40 1593.60 1705.30
(i) Rate per cum for Grading -IV Material
Total cost (Without O.H.& C.P.) 323222.89 323273.45 340052.92
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 25857.83 32327.35 40806.35
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 34908.07 35560.08 38085.93
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 383988.79 391160.88 418945.20
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1535.96 1564.64 1675.78
say 1536.00 1564.60 1675.80
4.08 403 Cement Treated Crushed stone Sub base
B By Mix Place Method
Construction of granular sub-base by providing graded Material,
mixing , carriage of mixed Material to work site, spreading in
uniform layers with motor grader on prepared surface mixing with
cement at OMC and compacting with vibratory power roller to
achieve the desired density, complete as per clause 401.

Unit = cum
Taking output = 250cum
By mechanical means
a) Labour
Mate day 0.400 0.400 0.400 310.00 124.00 124.00 124.00 L-12
Skilled mazdoor for alignment and geometrics day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor for spraying cement day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
3200.00 3200.00 3200.00
b) Machinery
Front end loader for Mixing at stock pile location.
(I)3.1 cum capacity hour 4.464 4255.00 18994.32 PM5001
(ii) 2.1 cum capacity hour 6.579 2588.00 17026.45 PM5002
(iii) 1 cum capacity hour 13.889 1594.00 22139.07 PM5003
Water tanker (speed@20km /hr and return speed @30 hr/ and
spreading speed@3.0 km /hr )
(i)16 KL capacity hour 0.693xL1+1. 1426.00 1525.82 L1=1km &
847 PM11001
(ii)12 KL capacity hour 0.924xL1+2. 1252.00 1785.35 L1=1km &
463 PM11002
(iii)6 KL capacity hour 1.847xL1+4. 907.00 2586.76 L1=1km &
926 PM11003
Soil Stabilizer for mixing and pulverising with capacity hour 2.222 2.222 2.222 25715.00 57138.73 57138.73 57138.73 PM49001
1000m2 per hour
Binder Spreader hour 2.222 2.222 2.222 7872.00 17491.58 17491.58 17491.58 PM50001
Motor Grader
(i)Motor grader 4.30 metre blade hour 2.016 5900.00 11894.40 PM2001
(ii)Motor grader 3.70 metre blade hour 2.432 5398.00 13127.94 PM2002
(iii)Motor grader 3.35 metre blade hour 2.712 2982.00 8087.18 PM2003
Vibratory roller hour 1.618 1.618 1.618 2338.00 3782.88 3782.88 3782.88 PM10001
110827.74 110352.94 111226.21
c) Material
cement at site tonne 13.125 13.125 13.125 4844.00 63577.50 63577.50 63577.50 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 73.60 7341.60 7341.60 7341.60 M-191
70919.10 70919.10 70919.10
For Grading -III Material
26.5mm to 9.5mm @ 68 percent cum 228.846 228.846 228.846 647.19 148106.84 148106.84 148106.84 M-014
9.5mm to 4.75mm @ 12 percent cum 40.385 40.385 40.385 625.53 25262.03 25262.03 25262.03 M-015
4.75mm below@ 20 percent cum 67.308 67.308 67.308 286.72 19298.55 19298.55 19298.55 M-018
192667.42 192667.42 192667.42
OR
For Grading -IV Material
26.5 mm to 9.5mm @ 64 percent cum 215.385 215.385 215.385 647.19 139395.02 139395.02 139395.02 M-014
9.5mm to 4.75mm @ 11 percent cum 37.019 37.019 37.019 625.53 23156.50 23156.50 23156.50 M-015
4.75mm below@ 25 percent cum 84.135 84.135 84.135 286.72 24123.19 24123.19 24123.19 M-018
186674.70 186674.70 186674.70
(i) Rate per cum for Grading -III Material
Total cost (Without O.H.& C.P.) 377614.26 377139.46 378012.73
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 30209.14 37713.95 45361.53
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 40782.34 41485.34 42337.43
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 448605.74 456338.75 465711.69
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1794.42 1825.35 1862.85
say 1794.40 1825.40 1862.80
(ii) Rate per cum for Grading -IV Material
Total cost (Without O.H.& C.P.) 371621.54 371146.74 372020.01
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 29729.72 37114.67 44642.40
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 40135.13 40826.14 41666.24
Cost for 250 cum = a+b+c+d+e (With O.H. & C.P.) 441486.39 449087.55 458328.66
Rate per cum = (a+b+c+d+e)/250 (With O.H. & C.P.) 1765.95 1796.35 1833.31
say 1765.90 1796.40 1833.30
4.09 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the
center line of the road and at one metre interval in the existing
thin bituminous wearing coarse including sweeping and disposal
of excavated material within 1000 metres lead,
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
608.80 608.80 608.80
b) Machinery
Tractor-trolley hour 0.200 0.200 0.200 612.00 122.40 122.40 122.40 PM12001
Total cost (Without O.H.& C.P.) 731.20 731.20 731.20
d) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 58.50 73.12 87.74
e) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 78.97 80.43 81.89
Cost for 210 sqm = a+b+c+d (With O.H. & C.P.) 868.67 884.75 900.84
Rate per sqm = (a+b+c+d)/210 (With O.H. & C.P.) 4.14 4.21 4.29
say 4.10 4.20 4.30
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
1217.60 1217.60 1217.60
b) Machinery
Tractor-trolley hour 0.400 0.400 0.400 612.00 244.80 244.80 244.80 PM12001
Total cost (Without O.H.& C.P.) 1462.40 1462.40 1462.40
d) Overhead charges on (a+b) (@ 8%) (@ 10%) (@ 12%) 116.99 146.24 175.49
e) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 157.94 160.86 163.79
Cost for 210 sqm= a+b+c+d (With O.H. & C.P.) 1737.33 1769.50 1801.68
Rate per sqm= (a+b+c+d)/210 (With O.H. & C.P.) 8.27 8.43 8.58
say 8.30 8.40 8.60
4.10 404.3.2 Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified grade
in uniform layer on a prepared surface with motor grader and
compacting with power roller etc.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 0.920 0.920 310.00 285.20 285.20 285.20 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 21.000 21.000 21.000 292.00 6132.00 6132.00 6132.00 L-13
7157.20 7157.20 7157.20
b) Machinery
(i)Motor Grader 4.30 meter blade. hour 4.839 5900.00 28550.10 PM2001
(ii)Motor Grader 3.70 meter blade. hour 5.837 5398.00 31508.13 PM2002
(iii)Motor Grader 3.35 meter blade. hour 6.508 2982.00 19406.86 PM2003
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 6.000 6.000 2338.00 14028.00 14028.00 14028.00 PM10001
Water tanker (speed @20km/hourand return speed@30
km/hourand spreading speed@ 3.0km/hour
(i) 16 KL capacity hour 0.75xL1+4.8 1426.00 1525.82 L1=1km &
PM11001
(ii) 12 KL capacity hour 1xL1+6.4 1252.00 1785.35 L1=1km &
PM11002
(iii) 6 KL capacity hour 2xL1+12.8 907.00 2586.76 L1=1km &
PM11003
44103.92 47321.48 36021.62
c) Material
Screening type 'B' or coarse sand cum 720.000 720.000 720.000 175.80 126576.00 126576.00 126576.00 M-005*
Cost of water KL 108.000 108.000 108.000 73.60 7948.80 7948.80 7948.80 M-191
134524.80 134524.80 134524.80
Total cost (Without O.H.& C.P.) 185785.92 189003.48 177703.62
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 14862.87 18900.35 21324.43
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20064.88 20790.38 19902.81
Cost for 600 cum = a+b+c+d+e (With O.H. & C.P.) 220713.67 228694.21 218930.86
Rate per cum = (a+b+c+d+e)/600 (With O.H. & C.P.) 367.86 381.16 364.88
say 367.90 381.20 364.90
4.11 404 Water Bound Macadam
Providing, laying, spreading and compacting stone aggregates of
specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with 3
wheeled steel/ vibratory roller in stages to proper grade and
camber, applying and brooming requisite type of screening/
binding Materials to fill up the interstices of coarse aggregate,
watering and compacting to the required density.

A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 10.080 10.080 310.00 3124.80 3124.80 3124.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 250.000 250.000 250.000 292.00 73000.00 73000.00 73000.00 L-13
76864.80 76864.80 76864.80
b) Machinery
Vibratory roller hour 2.330 2.330 2.330 2338.00 5447.54 5447.54 5447.54 PM10001
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 4.660 4.660 4.660 PM8001
Water tanker (speed @20km/hourand return speed@30
km/hourand spreading speed@ 3.0km/hour
(i) 16 KL capacity hour 1xL1+3.84 1426.00 1525.82 L1=1km &
PM11001
(ii) 12 KL capacity hour 1.333xL1+5. 1252.00 1785.35 L1=1km &
12 PM11002
(iii) 6 KL capacity hour 0.533xL1+1 907.00 2586.76 L1=1km &
0.24 PM11003
6973.36 7232.89 8034.30
C)Material (Refer table 400-8,9,10 & 11.)
4.11A (i) Grading-I
Aggregate
Grading-I 63 mm to 45 mm/ Grading II-53mm to cum 435.600 435.600 435.600 473.70 206343.72 206343.72 206343.72 M-037
22.4mm@ 0.91 cum per 10 sqm for compacted thickness
of 75 mm.
Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 sqm cum 57.200 57.200 57.200 515.53 29488.32 29488.32 29488.32 M-041
OR
Crushable type such as Moorum or Gravel for grading-I &II cum 105.590 105.590 105.590 158.35 16720.18 16720.18 16720.18 M-007
@ 0.22 cum per 10 sqm
OR
Type B 11.2 mm for grading-II @ 0.18 cum per 10 sqm Cum 86.400 86.400 86.400 392.53 33914.59 33914.59 33914.59 M-040
Binding material
Binding Material @ 0.06 cum per 10 sqm for grading I cum 28.800 28.800 28.800 158.35 4560.48 4560.48 4560.48 M-007
material
Cost of water KL 144.000 144.000 144.000 73.60 10598.40 10598.40 10598.40 M-191

4.11A(i) (a) Using Screening Crushable type such as Moorum or


Gravel.
Total cost (Without O.H.& C.P.) 322060.94 322320.47 323121.88
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 25764.87 32232.05 38774.63
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 34782.58 35455.25 36189.65
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 382608.39 390007.77 398086.16
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1062.80 1083.35 1105.79
say 1062.80 1083.40 1105.80
OR
4.11A(i) (b) Using Screening Type-A (13.2mm agg.)
Total cost (Without O.H.& C.P.) 334829.08 335088.61 335890.02
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 26786.33 33508.86 40306.80
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 36161.54 36859.75 37619.68
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 397776.94 405457.22 413816.50
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1104.94 1126.27 1149.49
say 1104.90 1126.30 1149.50
OR
4.11A(i) (c) Using Screening Type-B (11.2mm agg.)
Total cost (Without O.H.& C.P.) 339255.35 339514.88 340316.30
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 27140.43 33951.49 40837.96
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 36639.58 37346.64 38115.43
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 403035.36 410813.01 419269.68
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1119.54 1141.15 1164.64
say 1119.50 1141.10 1164.60
4.11A (ii) Grading-II
Aggregate
Grading-II 53 mm to22.4 mm @ 0.91 cum per 10 sqm for cum 435.600 435.600 435.600 503.85 219477.06 219477.06 219477.06 M-035
compacted thickness of 75 mm
Stone Screening
TypeB 11.2 mm for grading-II @ 0.18 cum per 10 sqm cum 86.400 86.400 86.400 392.53 33914.59 33914.59 33914.59 M-040
OR
Crushable type such as Moorum or Gravel for grading I&II cum 105.590 105.590 105.590 158.35 16720.18 16720.18 16720.18 M-007
@ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading I cum 28.800 28.800 28.800 158.35 4560.48 4560.48 4560.48 M-007
material
Cost of water KL 144.000 144.000 144.000 73.60 10598.40 10598.40 10598.40 M-191
4.11A(ii) (a) Using Screening Crushable type such as Moorum or
Gravel.
Total cost (Without O.H.& C.P.) 335194.28 335453.81 336255.22
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 26815.54 33545.38 40350.63
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 36200.98 36899.92 37660.58
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 398210.80 405899.11 414266.43
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1106.14 1127.50 1150.74
say 1106.10 1127.50 1150.70
OR
4.11A(ii) (b) Using Screening Type-B (11.2mm agg.)
Total cost (Without O.H.& C.P.) 352388.69 352648.22 353449.64
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 28191.10 35264.82 42413.96
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 38057.98 38791.30 39586.36
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 418637.77 426704.35 435449.95
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1162.88 1185.29 1209.58
say 1162.90 1185.30 1209.60
(Anyone of the aggregate grading, screening and binding material
may be used as per design.)
4.11 B By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 0.680 0.680 310.00 210.80 210.80 210.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 15.000 15.000 15.000 292.00 4380.00 4380.00 4380.00 L-13
5330.80 5330.80 5330.80
b) Machinery
Front end loader for Mixing at stock pile location.
(i) 3.1 Cum Capacity. hour 6.429 4255.00 27355.40 PM5001
(ii) 2.1 Cum Capacity. hour 9.474 2588.00 24518.71 PM5002
(iii) 1 Cum Capacity. hour 20.000 1594.00 31880.00 PM5003
Motor grader
(i) Moter grader 4.3 meter blade hour 2.903 5900.00 17127.70 PM2001
(ii) Moter grader 3.70 meter blade hour 3.502 5398.00 18903.80 PM2002
(iii) Moter grader3.35 meter blade hour 3.905 2982.00 11644.71 PM2003
Vibratory roller hour 2.330 2.330 2.330 2338.00 5447.54 5447.54 5447.54 PM10001
or
Smooth 3 wheeled steel roller. hour 4.660 4.660 4.660 PM8001
Water tanker (speed @20km/hourand return speed@30
km/hourand spreading speed@ 3.0km/hour
(i) 16 KL capacity hour 1xL1+3.84 1426.00 1525.82 L1=1km &
PM11001
(ii)12 KL.Capacity. hour 1.333xL1+5. 1252.00 1785.35 L1=1km &
12 PM11002
(iii)6 KL.Capacity. hour 2.667xL1+1 907.00 2586.76 L1=1km &
0.24 PM11003
51456.46 50655.40 51559.01
c) Material ( Refer table 400- 8,9,10&11 )
4.11B (i) Grading-I
Aggregate
Grading-I 63 mm to 45 mm/ Grading-II-53MM to22.4mm cum 435.600 435.600 435.600 473.70 206343.72 206343.72 206343.72 M-037
@ 0.91 cum per 10 sqm for compacted thickness of 75
mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 sqm cum 57.600 57.600 57.600 515.53 29694.53 29694.53 29694.53 M-041
OR
Crushable type such as Moorum or Gravel for grading-I&II cum 105.590 105.590 105.590 158.35 16720.18 16720.18 16720.18 M-007
@ 0.22 cum per 10 sqm
OR
Type B 11.2 mm for grading II-@0.18 cum per 10sqm cum 86.400 86.400 86.400 392.53 33914.59 33914.59 33914.59 M-040
Binding material
Binding Material @ 0.06 cum per 10 sqm for grading I cum 28.800 28.800 28.800 158.35 4560.48 4560.48 4560.48 M-007
material
Cost of water KL 144.000 144.000 144.000 73.60 10598.40 10598.40 10598.40 M-191
4.11B(i) (a) Using Screening Crushable type such as Moorum or
Gravel.
Total cost (Without O.H.& C.P.) 295010.03 294208.98 295112.59
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 23600.80 29420.90 35413.51
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 31861.08 32362.99 33052.61
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 350471.92 355992.86 363578.71
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 973.53 988.87 1009.94
say 973.50 988.90 1009.90
OR
4.11B(i) (b) Using Screening Type-A (13.2mm agg.)
Total cost (Without O.H.& C.P.) 307984.38 307183.33 308086.94
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 24638.75 30718.33 36970.43
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 33262.31 33790.17 34505.74
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 365885.45 371691.83 379563.11
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1016.35 1032.48 1054.34
say 1016.30 1032.50 1054.30
OR
4.11B(i) (c) Using Screening Type-B (11.2mm agg.)
Total cost (Without O.H.& C.P.) 312204.45 311403.39 312307.01
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 24976.36 31140.34 37476.84
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 33718.08 34254.37 34978.38
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 370898.88 376798.10 384762.23
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1030.27 1046.66 1068.78
say 1030.30 1046.70 1068.80

4.11B (ii) Grading-II


Aggregate
Grading-II 53 mm to 22.4 mm @ 0.91 cum per 10 sqm for cum 435.600 435.600 435.600 503.85 219477.06 219477.06 219477.06 M-035
compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for grading-II @ 0.18 cum per 10 sqm cum 86.400 86.400 86.400 392.53 33914.59 33914.59 33914.59 M-040
OR
Crushable type such as Moorum or Gravel for grading I &II cum 105.590 105.590 105.590 158.35 16720.18 16720.18 16720.18 M-007
@ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06 cum per 10 sqm for grading I cum 28.800 28.800 28.800 158.35 4560.48 4560.48 4560.48 M-007
material
Cost of water KL 144.000 144.000 144.000 73.60 10598.40 10598.40 10598.40 M-191
4.11B(ii (a) Using Screening Crushable type such as Moorum or
) Gravel.
Total cost (Without O.H.& C.P.) 308143.37 307342.32 308245.93
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 24651.47 30734.23 36989.51
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 33279.48 33807.65 34523.54
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 366074.33 371884.20 379758.99
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1016.87 1033.01 1054.89
say 1016.90 1033.00 1054.90
OR
4.11B(ii (b) Using Screening Type-B (11.2mm agg.)
)
Total cost (Without O.H.& C.P.) 325337.79 324536.73 325440.35
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 26027.02 32453.67 39052.84
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 35136.48 35699.04 36449.32
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 386501.29 392689.45 400942.51
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 1073.61 1090.80 1113.73
say 1073.60 1090.80 1113.70
4.12 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking damaged
cement concrete slabs to size range not exceeding 75 mm as
specified in Table 400-9 transporting the aggregates obtained
from breaking of cement concrete slabs at a lead of L1 km.,
laying and compacting the same as sub base/ base course,
constructed as WBM to clause 404 except the use of screening or
binding Material.

Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 4.160 4.160 310.00 1289.60 1289.60 1289.60 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor for crushing broken cement concrete day 102.000 102.000 102.000 292.00 29784.00 29784.00 29784.00 L-13
pavement/slabs into aggregate
31813.60 31813.60 31813.60
b) Machinery
Motor Grader for grading
(i) Moter grader 4.3 meter blade hour 2.903 5900.00 17127.70 PM2001
(ii) Moter grader 3.70 meter blade hour 3.502 5398.00 18903.80 PM2002
(iii) Moter grader3.35 meter blade hour 3.905 2982.00 11644.71 PM2003
Vibratory roller 8-10 tonne @ 60 Cum per hour hour 6.000 6.000 6.000 2338.00 14028.00 14028.00 14028.00 PM10001
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.00 12.00 12.00 PM8001
Front end loader for loading to Tipper
(i) 3.1Cum Capacity hour 2.229 4255.00 9484.40 PM5001
(ii) 2.1Cum Capacity hour 3.288 2588.00 8509.34 PM5002
(iii) 1Cum Capacity hour 6.923 1594.00 11035.26 PM5003
Tipper
ForTransportation
(i) 18 Cum Capacity tonne.km 720xL1 5.94 3118.50 L1=1km&P
M72001
(ii) 14 Cum Capacity tonne.km 720xL1 6.63 3480.75 L1=1km&P
M73001
(iii) 10 Cum Capacity tonne.km 720xL1 8.08 4242.00 L1=1km&P
M74001

For loading and unloading time


(i) 18 Cum Capacity hour 2.229 2772.00 6178.79 PM6001
(ii) 14 Cum Capacity hour 3.288 2415.00 7940.52 PM6002
(iii) 10 Cum Capacity hour 6.923 2121.00 14683.68 PM6003
Water tanker (speed @20km/hourand return speed@30
km/hourand spreading speed@ 3.0km/hour
(i) 16 KL capacity hour 0.4xL1+1.53 1426.00 1525.82 L1=1km &
6 PM11001
(ii)12 KL.Capacity. hour 0.533xL1+2. 1252.00 1785.35 L1=1km &
048 PM11002
(iii)6 KL.Capacity. hour 1.067xL1+4. 907.00 2586.76 L1=1km &
096 PM11003
51463.20 54647.76 58220.42
c) Material
Material available from dismantled concrete slab after crushing /
breaking and only carriage is required to be provided.
Cost of water KL 57.600 57.600 57.600 73.60 4239.36 4239.36 4239.36 M-191
Total cost (Without O.H.& C.P.) 87516.16 90700.72 94273.38
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 7001.29 9070.07 11312.81
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 9451.75 9977.08 10558.62
Cost for 360 cum = a+b+c+d+e (With O.H. & C.P.) 103969.20 109747.87 116144.80
Rate per cum = (a+b+c+d+e)/ 360 (With O.H. & C.P.) 288.80 304.86 322.62
say 288.80 304.90 322.60

Note 1. It is assumed that dismantling of concrete slab/pavement has


been considered separately. Hence same is not added in this
analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work site
has been provided with a lead of L1 km.
Note

2. In case of breaking of slabs is done locally without involvement


of transportation, the provision of tipper, front end loader and
loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use, the
same has been provided as an alternative.
4.13 405.2 Penetration Coat Over Top Layer of Crushed Cement Concrete
Base
Spraying of bitumen over cleaned dry surface of crushed cement
concrete base at the rate of 25 kg per 10 sqm by a bitumen
pressure distributor, spreading of key aggregates at the rate of
0.13 cum per 10 sqm by a mechanical gritter and rolling the
surface as per clause 506.3.8.
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 0.560 0.560 310.00 173.60 173.60 173.60 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 12.000 12.000 12.000 292.00 3504.00 3504.00 3504.00 L-13
4417.60 4417.60 4417.60
b) Machinery
Mechanical broom (2.1meter sweeping width) hour 2.232 2.232 2.232 642.00 1432.94 1432.94 1432.94 PM23001
Hydraulic self propelled chips spreader hour 5.140 5.140 5.140 2146.00 11030.44 11030.44 11030.44 PM32001
Front end loader 1 cum bucket capacity hour 6.000 6.000 6.000 1594.00 9564.00 9564.00 9564.00 PM5003
Tipper 10 tonne capacity hour 6.000 6.000 6.000 1183.00 7098.00 7098.00 7098.00 PM6004
Vibratory roller 8 -10 tonnes hour 5.140 5.140 5.140 2338.00 12017.32 12017.32 12017.32 PM10001
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 4.280 4.280 1645.00 7040.60 7040.60 7040.60 PM24001
48183.30 48183.30 48183.30
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 97.500 97.500 392.53 38271.68 38271.68 38271.68 M-040
Bitumen (60-70 grade) tonne 0.250 0.250 0.250 43502.00 10875.50 10875.50 10875.50 M-074
49147.18 49147.18 49147.18
Total cost (Without O.H.& C.P.) 101748.08 101748.08 101748.08
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 8139.85 10174.81 12209.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 10988.79 11192.29 11395.78
Cost for 7500 sqm = a+b+c+d+e (With O.H. & C.P.) 120876.72 123115.18 125353.63
Rate per sqm = (a+b+c+d+e)/ 7500 (With O.H. & C.P.) 16.12 16.42 16.71
say 16.10 16.40 16.70
4.14 406 A Wet Mix Macadam (Plant Mix Method)
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing
the Material with water at OMC in mechanical mix plant carriage
of mixed Material by tipper to site, laying in uniform layers with
paver in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.

Laying Using Mechanical Paver


Unit = cum
Taking output = 225 cum
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
1295.60 1295.60 1295.60
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 642.00 1694.88 PM17001
(ii) 200 tonne per hour hour 3.300 348.00 1148.40 PM17002
(iii) 100 tonne per hour hour 6.600 322.00 2125.20 PM17003
Electric generator
(i) 125 KVA hour 2.640 2653.00 7003.92 PM22005
(ii) 100 KVA hour 3.300 2251.00 7428.30 PM22006
(iii) 62.5 KVA hour 6.600 1421.00 9378.60 PM22007
Front end loader for loading to Tipper
(i) 3.1Cum Capacity hour 2.640 4255.00 11233.20 PM5001
(ii) 2.1Cum Capacity hour 3.300 2588.00 8540.40 PM5002
(iii) 1Cum Capacity hour 6.600 1594.00 10520.40 PM5003
Tipper for Transportation
(i) 18 Cum Capacity tonne.km 495xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 Cum Capacity tonne.km 495xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 Cum Capacity tonne.km 495xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading time
(i) 18 Cum Capacity hour 5.280 2772.00 14636.16 PM6001
(ii) 14 Cum Capacity hour 6.600 2415.00 15939.00 PM6002
(iii) 10 Cum Capacity hour 9.900 2121.00 20997.90 PM6003
Mechanical Paver finisher hour 2.640 3.300 3.300 1583.00 4179.12 5223.90 5223.90 PM28001
Vibratory roller hour 2.112 2.640 2.640 2338.00 4937.86 6172.32 6172.32 PM10001
46803.64 47933.07 58660.32
c) Material as per table 400-13
45 mm to 22.4 mm@ 30 percent Cum 95.192 95.192 95.192 524.49 49927.25 49927.25 49927.25 M-033
22.4 mm to 2.36 mm@ 40 percent Cum 126.923 126.923 126.923 572.92 72716.73 72716.73 72716.73 M-030
2.36 mm to 75 microm@ 30 percent Cum 95.192 95.192 95.192 286.72 27293.45 27293.45 27293.45 M-019
Cost of water KL 59.400 59.400 59.400 73.60 4371.84 4371.84 4371.84 M-191
154309.27 154309.27 154309.27
Rate per cum
Total cost (Without O.H.& C.P.) 202408.50 203537.94 214265.19
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16192.68 20353.79 25711.82
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21860.12 22389.17 23997.70
Cost for 225 cum = a+b+c+d+e (With O.H. & C.P.) 240461.30 246280.90 263974.71
Rate per cum= (a+b+c+d+e)/ 225 (With O.H. & C.P.) 1068.72 1094.58 1173.22
say 1068.70 1094.60 1173.20
4.14 406 B Wet Mix Macadam (Plant Mix Method)
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing
the Material with water at OMC in mechanical mix plant carriage
of mixed Material by tipper to site, laying in uniform layers with
grader in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.

Laying Using Grader


Unit = cum
Taking output = 225 cum
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
1295.60 1295.60 1295.60
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 642.00 1694.88 PM17001
(ii) 200 tonne per hour hour 3.300 348.00 1148.40 PM17002
(iii) 100 tonne per hour hour 6.600 322.00 2125.20 PM17003
Electric generator
(i) 125 KVA hour 2.640 2653.00 7003.92 PM22005
(ii)100 KVA hour 3.300 2251.00 7428.30 PM22006
(iii) 62.5 KVA hour 6.600 1421.00 9378.60 PM22007
Front end loader for loading to Tipper
(i) 3.1Cum Capacity hour 2.640 4255.00 11233.20 PM5001
(ii) 2.1Cum Capacity hour 3.300 2588.00 8540.40 PM5002
(iii) 1Cum Capacity hour 6.600 1594.00 10520.40 PM5003
Tipper
For Transportation
(i) 18 Cum Capacity tonne.km 495xL2 5.94 4989.60 L1=1km &
PM72001
(ii) 14 Cum Capacity tonne.km 495xL2 6.63 5569.20 L1=1km
&PM73001
(iii) 10 Cum Capacity tonne.km 495xL2 8.08 6787.20 L1=1 km
&PM74001
For loading and unloading time
(i) 18 Cum Capacity hour 2.640 2772.00 7318.08 PM6001
(ii) 14 Cum Capacity hour 3.300 2415.00 7969.50 PM6002
(iii) 10 Cum Capacity hour 6.600 2121.00 13998.60 PM6003
Motor grader
(i) Motor grader 4.3 meter blade hour 1.815 5900.00 10708.50 PM2001
(ii) Motor grader 3.70 meter blade hour 2.189 5398.00 11816.22 PM2002
(iii) Motor grader 3.35 meter blade hour 2.441 2982.00 7279.06 PM2003
Vibratory roller hour 1.456 1.456 1.456 2338.00 3404.13 3404.13 3404.13 PM10001
46352.31 45876.15 53493.19
c) Material
Material as per table 400-13
45 mm to 22.4 mm@ 30 percent Cum 95.192 95.192 95.192 524.49 49927.25 49927.25 49927.25 M-033
22.4 mm to 2.36 mm@ 40 percent Cum 126.923 126.923 126.923 572.92 72716.73 72716.73 72716.73 M-030
2.36 mm to 75 micron@ 30 percent Cum 95.192 95.192 95.192 286.72 27293.45 27293.45 27293.45 M-019
Cost of water KL 59.400 59.400 59.400 73.60 4371.84 4371.84 4371.84 M-191
154309.27 154309.27 154309.27
Rate per cum
Total cost (Without O.H.& C.P.) 201957.18 201481.02 209098.06
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16156.57 20148.10 25091.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21811.37 22162.91 23418.98
Cost for 225 cum = a+b+c+d+e (With O.H. & C.P.) 239925.12 243792.03 257608.81
Rate per cum= (a+b+c+d+e)/ 225 (With O.H. & C.P.) 1066.33 1083.52 1144.93
say 1066.30 1083.50 1144.90
4.15 406 Cement Treated Crushed Stone Base(Plant Mix Method)

Providing, laying, spreading and compacting graded stone


aggregate mixed with cement to crushed stone treated base
specification including pre mixing the material with water at OMC.
in Mechanical mix plant carriage of mixed Material by tipper to
site ,laying in uniform layers with paver in sub- base / base course
on well prepared surface and compacting with vibratory roller to
achieve the desired density.

Laying Using Mechanical Paver.


Unit = cum
Taking output = 225 cum
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
1295.60 1295.60 1295.60
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 642.00 1694.88 PM17001
(ii) 200 tonne per hour hour 3.300 348.00 1148.40 PM17002
(iii) 100 tonne per hour hour 6.600 322.00 2125.20 PM17003
Electric generator
(i)125 KVA hour 2.640 2653.00 7003.92 PM22005
(ii) 100 KVA hour 3.300 2251.00 7428.30 PM22006
(iii) 62.5 KVA hour 6.600 1421.00 9378.60 PM22007
Front end loader for loading to Tipper
(i) 3.1Cum Capacity hour 2.640 4255.00 11233.20 PM5001
(ii) 2.1Cum Capacity hour 3.300 2588.00 8540.40 PM5002
(iii) 1Cum Capacity hour 6.600 1594.00 10520.40 PM5003
Tipper For Transportation
(i) 18 Cum Capacity tonne.km 495xL2 5.94 4989.60 L1=1km &
PM72001
(ii) 14 Cum Capacity tonne.km 495xL2 6.63 5569.20 L1=1km
&PM73001
(iii) 10 Cum Capacity tonne.km 495xL2 8.08 6787.20 L1=1 km
&PM74001
For loading and unloading time
(i) 18 Cum Capacity hour 5.280 2772.00 14636.16 PM6001
(ii) 14 Cum Capacity hour 5.940 2415.00 14345.10 PM6002
(iii) 10 Cum Capacity hour 9.240 2121.00 19598.04 PM6003
Vibratory roller hour 2.112 2.112 2.112 2338.00 4937.86 4937.86 4937.86 PM10001
Mechanical Paver finisher hour 2.460 2.460 2.460 1583.00 3894.18 3894.18 3894.18 PM28001
Water tanker (speed @20km/hr and return speed@30
km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.722xL1+1. 1426.00 1525.82 L1=1km &
733 PM11001
(ii)12 KL.Capacity. hour 0.963xL1+2. 1252.00 1785.35 L1=1km &
31 PM11002
(iii)6 KL.Capacity. hour 1.925xL1+4. 907.00 2586.76 L1=1km &
62 PM11003
49915.62 47648.79 59828.24
c) Material
Material as per table 400-13
45 mm to 22.4 mm@ 30 percent Cum 95.192 95.192 95.192 524.49 49927.25 49927.25 49927.25 M-033
22.4 mm to 2.36 mm@ 40 percent Cum 126.923 126.923 126.923 572.92 72716.73 72716.73 72716.73 M-030
2.36 mm to 75 microm@ 30 percent Cum 95.192 95.192 95.192 234.89 22359.65 22359.65 22359.65 M-021

Cost of cement @4% Tonne. 19.800 19.800 19.800 4844.00 95911.20 95911.20 95911.20 M-081

Cost of water KL 163.350 163.350 163.350 73.60 12022.56 12022.56 12022.56 M-191
252937.39 252937.39 252937.39
Total cost (Without O.H.& C.P.) 304148.60 301881.77 314061.23
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 24331.89 30188.18 37687.35
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 32848.05 33207.00 35174.86
Cost for 225 cum = a+b+c+d+e (With O.H. & C.P.) 361328.54 365276.95 386923.43
Rate per cum= (a+b+c+d+e)/ 225 (With O.H. & C.P.) 1605.90 1623.45 1719.66
say 1605.90 1623.50 1719.70
4.16 408 Construction of Median and Island with Soil Taken from Roadway
Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 408
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 0.240 0.240 310.00 74.40 74.40 74.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
1826.40 1826.40 1826.40
b) Machinery

Water tanker (speed @20km/hr and return speed@30


km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.018xL1+0. 1426.00 1525.82 L1=1km &
004 PM11001
(ii)12 KL.Capacity. hour 0.023xL1+0. 1252.00 1785.35 L1=1km &
005 PM11002
(iii)6 KL.Capacity. hour 0.047xL1+0. 907.00 2586.76 L1=1km &
01 PM11003
Plate Compactor @ 3.5 cum per hour hour 6.000 6.000 6.000 352.00 2112.00 2112.00 2112.00 PM46001
3637.82 3897.35 4698.76
c) Material
Cost of water KL 2.520 2.520 2.520 73.60 185.47 185.47 185.47 M-191
Total cost (Without O.H.& C.P.) 5649.69 5909.22 6710.64
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 451.98 590.92 805.28
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 610.17 650.01 751.59
Cost for 21 cum = a+b+c+d+e (With O.H. & C.P.) 6711.83 7150.16 8267.50
Rate per cum= (a+b+c+d+e)/ 21 (With O.H. & C.P.) 319.61 340.48 393.69
say 319.60 340.50 393.70
Note This analysis provides for median and island with earthen top. In
case the surface is required to be turfed or planted with shrubs,
the same is required to be provided separately as per analysis
given in the chapter on horticulture. In case granular fill is
required to be paved, quantities of paving are required to be
calculated as per approved design and paid separately.
4.17 408 Construction of Median and Island with Soil Taken from Borrow
Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped and
compacted as per clause 408
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
608.80 608.80 608.80
b) Machinery
Hydraulic Excavator
(i) 1.2 Cum bucket Capacity hour 0.236 3388.00 799.57 PM3003
(ii) 1.1 Cum bucket Capacity hour 0.271 3021.00 818.69 PM3004
(iii) 0.9 Cum bucket Capacity hour 0.379 2702.00 1024.06 PM3005
Tipper
for Transportation
(i) 18 Cum Capacity t.km 31.5xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 Cum Capacity t.km 31.5xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 Cum Capacity t.km 31.5xL2 8.08 4242.00 L1=1km&P
M74001
For loading and unloading time
(i) 18 Cum Capacity hour 0.236 2772.00 654.19 PM6001
(ii) 14 Cum Capacity hour 0.271 2415.00 654.47 PM6002
(iii) 10 Cum Capacity hour 0.379 2121.00 803.86 PM6003
Water tanker (speed @20km/hr and return speed@30
km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.018xL1+0. 1426.00 1525.82 L1=1km &
002 PM11001
(ii)12 KL.Capacity. hour 0.023xL1+0. 1252.00 1785.35 L1=1km &
003 PM11002
(iii)6 KL.Capacity. hour 0.047xL1+0. 907.00 2586.76 L1=1km &
006 PM11003
Plate Compactor hour 1.400 1.400 1.400 352.00 492.80 492.80 492.80 PM46001
6590.88 7232.06 9149.48
c) Material
Compensation for earth taken from private Land cum 21.000 21.000 21.000 34.82 731.22 731.22 731.22 M-093
Cost of water KL 2.520 2.520 2.520 73.60 185.47 185.47 185.47 M-191
916.69 916.69 916.69
Total cost (Without O.H.& C.P.) 8116.37 8757.55 10674.97
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 649.31 875.76 1281.00
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 876.57 963.33 1195.60
Cost for 21 cum = a+b+c+d+e (With O.H. & C.P.) 9642.25 10596.64 13151.57
Rate per cum= (a+b+c+d+e)/ 21 (With O.H. & C.P.) 459.15 504.60 626.27
say 459.20 504.60 626.30
Note This analysis provides for median and island with earthen top. In
case the surface is required to be turfed or planted with shrubs,
the same is required to be provided separately as per analysis
given in the chapter on horticulture. In case surface finish is of
hard type, the same may be provided separately as per approved
design.
4.18 408 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted as
per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved shoulders.

4.19 410 Footpaths and Separators


Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm thick
cement concrete grade M15, over laid with pre-cast concrete tiles
in cement mortar 1:3 including provision of all drainage
arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 1.360 1.360 310.00 421.60 421.60 421.60 L-12
Mason day 4.000 4.000 4.000 351.00 1404.00 1404.00 1404.00 L-10
Mazdoor day 30.000 30.000 30.000 292.00 8760.00 8760.00 8760.00 L-13
10585.60 10585.60 10585.60
b) Machinery
Vibratory road roller hour 0.750 0.750 0.750 2338.00 1753.50 1753.50 1753.50 PM10001
Water tanker (speed @20km/hr and return speed@30
km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.083xL1+0. 1426.00 1525.82 L1=1km &
04 PM11001
(ii)12 KL.Capacity. hour 0.111xL1+0. 1252.00 1785.35 L1=1km &
053 PM11002
(iii)6 KL.Capacity. hour 0.222xL1+0. 907.00 2586.76 L1=1km &
107 PM11003
Concrete mixer 0.4/0.28 cum per hour hour 6.000 6.000 6.000 286.00 1716.00 1716.00 1716.00 PM21001
4995.32 5254.85 6056.26
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 20.790 20.790 503.85 10475.04 10475.04 10475.04 M-028
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 26.730 26.730 544.89 14564.91 14564.91 14564.91 M-025
2.36 mm below @ 20 per cent cum 11.880 11.880 11.880 286.72 3406.23 3406.23 3406.23 M-019

ii) For cement concrete grade M15 7.5 cum


Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 6.750 6.750 686.05 4630.84 4630.84 4630.84 M-051
Sand @ 0.45 cum/cum of concrete cum 3.380 3.380 3.380 175.80 594.20 594.20 594.20 M-005*
Cement tonne 1.880 1.880 1.880 4844.00 9106.72 9106.72 9106.72 M-081
iii) For cement plaster 1:3
Sand cum 3.840 3.840 3.840 175.80 675.07 675.07 675.07 M-005*
Cement tonne 1.830 1.830 1.830 4844.00 8864.52 8864.52 8864.52 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 3300.000 3300.000 38.93 128469.00 128469.00 128469.00 M-186
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 22.500 22.500 160.18 3604.05 3604.05 3604.05 M-136
vi) Cost of water KL 12.000 12.000 12.000 73.60 883.20 883.20 883.20 M-191
185273.79 185273.79 185273.79
Total cost (Without O.H.& C.P.) 200854.71 201114.24 201915.65
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 16068.38 20111.42 24229.88
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 21692.31 22122.57 22614.55
Cost for 300 sqm = a+b+c+d+e (With O.H. & C.P.) 238615.39 243348.23 248760.08
Rate per sqm = (a+b+c+d+e)/ 300 (With O.H. & C.P.) 795.38 811.16 829.20
say 795.40 811.20 829.20
4.20 407 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to clause
407 to form a layer of sub-base/Base.
Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
3808.80 3808.80 3808.80
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 12.000 12.000 629.00 7548.00 7548.00 7548.00 PM(12001+
13001)
Front end Loader for mixing at stock pile location.
(i) 3.1 Cum Capacity hour 6.429 4255.00 27355.40 PM5001
(ii) 2.1 Cum Capacity hour 9.474 2588.00 24518.71 PM5002
(iii)1 Cum Capacity hour 20.000 1594.00 31880.00 PM5003
Motor grader
(i) Motor grader 4.30 meter blade. hour 2.903 5900.00 17127.70 PM2001
(ii) Motor grader 3.70 meter blade. hour 3.502 5398.00 18903.80 PM2002
(iii) Motor grader 3.35 meter blade. hour 3.905 2982.00 11644.71 PM2003
Vibratory roller hour 2.330 2.330 2.330 2338.00 5447.54 5447.54 5447.54 PM10001
or
Smooth 3 Wheeled steel roller hour 4.660 4.660 4.660 PM8001
Water tanker (speed @20km / hr and return speed@30
km / hr and spreading speed@ 3.0km / hr
(i) 16 KL capacity hour 0.25xL1+0.9 1426.00 1525.82 L1=1km &
6 PM11001
(ii)12 KL.Capacity. hour 0.333xL1+1. 1252.00 1785.35 L1=1km &
28 PM11002
(iii)6 KL.Capacity. hour 0.667xL1+2. 907.00 2586.76 L1=1km &
56 PM11003
59004.46 58203.40 59107.01
C) Material
i) For 53 mm maximum size (Table- 400-14)
63 mm to 45 mm @ 33 per cent cum 157.460 157.460 157.460 473.70 74588.80 74588.80 74588.80 M-037
22.5 mm to 5.6 mm @ 32 per cent cum 151.060 151.060 151.060 572.92 86545.30 86545.30 86545.30 M-031
Below 5.6 mm @ 35 per cent cum 166.680 166.680 166.680 249.22 41539.99 41539.99 41539.99 M-029
Cost of water KL 36.000 36.000 36.000 73.60 2649.60 2649.60 2649.60 M-191
205323.69 205323.69 205323.69
Or
ii) For 37.5 mm maximum size (Table- 400-14)
37.5 mm to 22.5 mm @ 5 per cent cum 24.120 24.120 24.120 524.49 12650.70 12650.70 12650.70 M-047
22.4 mm to 5.6 mm @ 50 per cent cum 237.600 237.600 237.600 442.63 105168.89 105168.89 105168.89 M-038
Below 5.6 mm @ 45 per cent cum 213.480 213.480 213.480 473.80 101146.82 101146.82 101146.82 M-036
Cost of water KL 36.000 36.000 36.000 73.60 2649.60 2649.60 2649.60 M-191
221616.01 221616.01 221616.01
4.20A (i) For 53 mm maximum size
Total cost (Without O.H.& C.P.) 268136.94 267335.89 268239.50
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 21450.96 26733.59 32188.74
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 28958.79 29406.95 30042.82
Cost for 360.0 cum = a+b+c+d+e (With O.H. & C.P.) 318546.69 323476.42 330471.06
Rate per cum = (a+b+c+d+e)/ 360.0 (With O.H. & C.P.) 884.85 898.55 917.98
say 884.90 898.50 918.00
or
4.20A (ii) For 37.5 mm maximum size
Total cost (Without O.H.& C.P.) 284429.27 283628.21 284531.82
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 22754.34 28362.82 34143.82
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 30718.36 31199.10 31867.56
Cost for 360.0 cum = a+b+c+d+e (With O.H. & C.P.) 337901.97 343190.14 350543.21
Rate per cum = (a+b+c+d+e)/ 360.0 (With O.H. & C.P.) 938.62 953.31 973.73
say 938.60 953.30 973.70
Note Any one of the aggregate grading may be adopted.
4.20 B By Mixing Plant :
Unit = cum
Taking output = 225 cum
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
2208.80 2208.80 2208.80
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.400 642.00 1540.80 PM17001
(ii) 200 tonne per hour hour 3.000 348.00 1044.00 PM17002
(iii) 100 tonne per hour hour 6.000 322.00 1932.00 PM17003
Electric generator
(i) 125 KVA hour 2.400 2653.00 6367.20 PM22005
(ii) 100 KVA hour 3.000 2251.00 6753.00 PM22006
(iii) 62.5 KVA hour 6.000 1421.00 8526.00 PM22007
Front end loader for loading to tipper
(i) 3.1 Cum Capacity hour 2.400 4255.00 10212.00 PM5001
(ii) 2.10 Cum Capacity hour 3.000 2588.00 7764.00 PM5002
(iii) 1 Cum Capacity hour 6.000 1594.00 9564.00 PM5003
Motor grader
(i) Motor grader 4.3 meter blade. hour 1.815 5900.00 10708.50 PM2001
(ii) Motor grader 3.70 meter blade. hour 2.189 5398.00 11816.22 PM2002
(iii) Motor grader 3.35 meter blade. hour 2.441 2982.00 7279.06 PM2003
Vibratory roller hour 2.400 2.400 2.400 2338.00 5611.20 5611.20 5611.20 PM10001
Water tanker (speed @20km/hr and return speed@30
km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.125xL1+0. 1426.00 1525.82 L1=1km &
3 PM11001
(ii)12 KL.Capacity. hour 0.167xL1+0. 1252.00 1785.35 L1=1km &
4 PM11002
(iii)6 KL.Capacity. hour 0.333xL1+0. 907.00 2586.76 L1=1km &
8 PM11003
Tipper
ForTransportation
(i) 18 Cum capacity t.km 450xL2 5.94 3118.50 L1=1km&P
M72001
(ii) 14 Cum capacity t.km 450xL2 6.63 3480.75 L1=1km&P
M73001
(iii) 10 Cum capacity t.km 450xL2 8.08 4242.00 L1=1km&P
M74001
For loading & unloading time
(i) 18 Cum capacity hour 2.400 2772.00 6652.80 PM6001
(ii) 14 Cum capacity hour 3.000 2415.00 7245.00 PM6002
(iii) 10 Cum capacity hour 6.000 2121.00 12726.00 PM6003
45736.82 45499.52 52467.03
c) Material
Aggregate at site
i) For 53 mm maximum size (Table 400-14)
63 mm to 45 mm @ 33 per cent cum 98.400 98.400 98.400 473.70 46612.08 46612.08 46612.08 M-037
22.5 mm to 5.6 mm @ 32 per cent cum 94.410 94.410 94.410 572.92 54089.38 54089.38 54089.38 M-031
Below 5.6 mm @ 35 per cent cum 104.180 104.180 104.180 249.22 25963.74 25963.74 25963.74 M-029
Cost of water KL 18.000 18.000 18.000 73.60 1324.80 1324.80 1324.80 M-191
127990.00 127990.00 127990.00
Or
ii) For 37.5 mm maximum size (Table 400-14)
37.5 mm to 22.5 mm @ 5 per cent cum 15.060 15.060 15.060 524.49 7898.82 7898.82 7898.82 M-047
22.4 mm to 5.6 mm @ 50 per cent cum 148.500 148.500 148.500 572.92 85078.62 85078.62 85078.62 M-031
Below 5.6 mm @ 45 per cent cum 133.430 133.430 133.430 249.22 33253.42 33253.42 33253.42 M-029
Cost of water KL 18.000 18.000 18.000 73.60 1324.80 1324.80 1324.80 M-191
127555.66 127555.66 127555.66
4.20B (i) For 53 mm maximum size
Total cost (Without O.H.& C.P.) 175935.62 175698.32 182665.82
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 14074.85 17569.83 21919.90
e) Contractor's on profit (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 19001.05 19326.82 20458.57
Cost for 225 cum = a+b+c+d+e (With O.H. & C.P.) 209011.51 212594.97 225044.29
Rate per cum = (a+b+c+d+e)/ 225 (With O.H. & C.P.) 928.94 944.87 1000.20
say 928.90 944.90 1000.20
4.20B (ii) For 37.5 mm maximum size
Total cost (Without O.H.& C.P.) 175501.28 175263.99 182231.49
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 14040.10 17526.40 21867.78
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 18954.14 19279.04 20409.93
Cost for 225 cum = a+b+c+d+e (With O.H. & C.P.) 208495.53 212069.43 224509.20
Rate per cum = (a+b+c+d+e)/ 225 (With O.H. & C.P.) 926.65 942.53 997.82
say 926.60 942.50 997.80
4.21 Suggestive Lime, Flyash Stabilised Soil Sub-Base
Construction of Sub-base using lime - Flyash admixture with cum
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and 20
and liquid limit less than 25 and commercial dry lime, slaked at
site or pre-slaked with CaO content not less than 50 per cent,
Flyash to conform to gradation as per clause 4.3 of IRC: 88-1984,
lime + Flyash content ranging between 10 to 30 per cent, the
minimum un-confined compressive strength and CBR value after
28 days curing and 4 days soaking to be 7.5kg/sq, cm and 25 per
cent respectively, all as specified in IRC: 88.

Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)

Assumptions made
Total mass taken for analysis = 720 Tonne
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 Tonne

Soil = 720 -144 = 576 Tonne


576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 t
Flyash = 115 t

a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
2208.80 2208.80 2208.80
b) Machinery
Hydraulic Excavator
(i) 1.2 Cum bucket Capacity hour 4.038 3388.00 13680.74 PM3003
(ii) 1.1 Cum bucket Capacity hour 4.650 3021.00 14047.65 PM3004
(iii) 0.9 Cum bucket Capacity hour 6.502 2702.00 17568.40 PM3005
Tipper For transportation
(i) 18 Cum Capacity t.km 720xL1 5.94 3118.50 L1=1km&P
M72001
(ii) 14 Cum Capacity t.km 720xL1 6.63 3480.75 L1=1km&P
M73001
(iii) 10 Cum Capacity t.km 720xL1 8.08 4242.00 L1=1km&P
M74001
For loading & unloading time
(i) 18 Cum Capacity hour 4.038 2772.00 11193.34 PM6001
(ii) 14 Cum Capacity hour 4.650 2415.00 11229.75 PM6002
(iii) 10 Cum Capacity hour 6.502 2121.00 13790.74 PM6003
Tractor with disc harrow for pulverisation hour 6.000 6.000 6.000 633.00 3798.00 3798.00 3798.00 PM(12001+
Motor grader for grading 14001)
(i) Motor grader 4.3 meter blade. hour 3.302 5900.00 19481.80 PM2001
(ii) Motor grader 3.70 meter blade. hour 3.982 5398.00 21494.84 PM2002
(iii) Motor grader 3.35 meter blade. hour 4.441 2982.00 13243.06 PM2003
Vibratory Roller hour 6.000 6.000 6.000 2338.00 14028.00 14028.00 14028.00 PM10001
Water tanker (speed @20km/hr and return speed@30
km/hr and spreading speed@ 3.0km/hr
(i) 16 KL capacity hour 0.3xL1+1.57 1426.00 1525.82 L1=1km &
2 PM11001
(ii)12 KL.Capacity. hour 0.4xL1+2.09 1252.00 1785.35 L1=1km &
6 PM11002
(iii)6 KL.Capacity. hour 0.8xL1+4.19 907.00 2586.76 L1=1km &
2 PM11003
66826.20 69864.34 69256.97
c) Material
Slaked Lime tonne 29.000 29.000 29.000 3637.51 105487.79 105487.79 105487.79 M-190
Compensation for earth taken from private source cum 360.000 360.000 360.000 34.82 12535.20 12535.20 12535.20 M-093
Cost of water (considering 5% additional moisture KL 43.200 43.200 43.200 73.60 3179.52 3179.52 3179.52 M-191
required)
121202.51 121202.51 121202.51
Total cost (Without O.H.& C.P.) 190237.51 193275.65 192668.28
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15219.00 19327.56 23120.19
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20545.65 21260.32 21578.85
Cost for 480 cum = a+b+c+d+e (With O.H. & C.P.) 226002.16 233863.53 237367.32
Rate per cum = (a+b+c+d+e)/ 480 (With O.H. & C.P.) 470.84 487.22 494.52
say 470.80 487.20 494.50
Note 1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land, compensation
for earth will not be required. The position is required to be clearly
stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been provided.

3.Lime + Flyash has been taken as 20 per cent of total mass and
ratio of lime and Flyash as 1:4 for estimating purposes. Total
quantities will be as per approved design.
4.22 Suggestive Granular crack relief layer
Granular crack relief layer laying Using Mechanical Paver
(Providing, laying ,spreading and compacting graded stone
aggregate to Granular crack relief layer as per IRC SP -37
including premixing the Material with water at OMC in mechanical
mix plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver over base course on well prepared
surface and compacting with vibratory roller to achieve the
desired density.)

Unit:= Cum
Note Rate shall be taken from item no- 4.14 A.
CHAPTER -5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref.
Sr No Description Unit Rate as per Project Category
to M.

Large Medium Small


5.01 502 A Prime Coat over WMM/WBM
Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(i) sqm 40.00 40.80 41.60
primer at the rate of 0.70 kg/sqm using mechanical
means.

Providing and applying primer coat with cutback MC


30 bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(ii) sqm 32.30 33.00 33.60
primer at the rate of 0.60 kg/sqm using mechanical
means.

5.01 502 B Prime Coat over Stabilized soi bases/ Crusher


Run Macadam
Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(i) sqm 51.00 52.00 53.10
primer at the rate of 0.90 kg/sqm using mechanical
means.

Providing and applying primer coat with cutback MC


70 bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(ii) sqm 47.80 48.70 49.70
primer at the rate of 0.90 kg/sqm using mechanical
means.

5.02 503 (i) Tack Coat on Bituminous surfaces


Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.20 kg per sqm on the prepared bituminous sqm 12.10 12.30 12.50
surface cleaned with mechanical broom.

5.02 503 (ii) Tack Coat on Granular surfaces treated with


primer
Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.25 kg per sqm on the prepared bituminous sqm 14.80 15.10 15.40
surface cleaned with mechanical broom.

5.02 503 (iii) Tack Coat on Cement concrete pavement


Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.30 kg per sqm on the prepared bituminous sqm 17.60 17.90 18.20
surface cleaned with mechanical broom.

5.03 504 (i) Bituminous Macadam Grading- I


Providing and laying bituminous macadam with
higher capacity hot mix plant using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the cum 5563.90 5674.30 5819.50
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction.

5.03 504 (ii) Bituminous Macadam Grading-II


Providing and laying bituminous macadam with
higher capacity hot mix plant using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the cum 5750.60 5863.20 6015.20
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction.

Dense Graded Bituminous Macadam Grading-I


5.04 505 A
Providing and laying dense graded bituminous
macadam with higher capacity batch type HMP
using crushed aggregates of specified grading,
premixed with bituminous binder @ 4.0 per cent by
weight of total mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled, cum 6716.60 6847.40 7019.60
vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No.
505 complete in all respects.

5.04 505 B
Dense graded Bituminous Macadam Grading-II
Providing and laying dense graded bituminous
macadam with higher capacity batch type HMP
using crushed aggregates of specified grading,
premixed with bituminous binder @4.5 percent by
weight of total mix and filler, transporting the hot
mix to work site laying with a hydrostatic paver
finisher with sensor control to the required grade
level and alignment, rolling with smooth wheeled, cum 7374.00 7517.10 7701.30
vibratory and tandem rollers to achieve the desired
compaction as per MORT&H specification clause
no. 505 complete in all respects.

5.05 507 A Bituminous concrete Grading- I


Providing and laying bituminous concrete with
higher capacity batch type hot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @5.2 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment , rolling
with smooth wheeled, vibratory and tandem rollers cum 8463.40 8635.70 8856.20
to achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

5.05 507 B Bituminous concrete Grading- II


Providing and laying bituminous concrete with
higher capacity batch type hot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @5.4 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment , rolling
with smooth wheeled, vibratory and tandem rollers cum 8649.30 8825.00 9049.50
to achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

5.06 509 Surface Dressing


Providing and laying surface dressing as wearing
course in a single coat using crushed stone
aggregates of specified size on a layer of bituminous
binder laid on prepared surface and rolling with 8-10
tonne smooth wheeled steel roller

5.06 Case-I 19mm Nominal chipping size sqm 82.80 84.00 85.70
Case 13 mm Nominal size chipping
5.06 509 sqm 68.80 69.80 71.10
-II
5.07 510 Open-Graded Premix Surfacing
Providing, laying and rolling of open-graded pemix
surfacing of 20mm thickness composed of 13.2mm
to 5.6mm aggregates using viscosity grade bitumen
to required line, grade and level to serve as wearing
course on a previously prepared base, including
mixing in a suitable hot mix plant of appropriate
capcity not less than 200 tonnes/hour, laying and
rolling with a smooth wheeled roller finished to
required level and grades.

5.08 508 Close Graded Premix Surfacing/Mixed Seal


Surfacing
Providing, laying and rolling of open graded premix
surfacing of 20mm thickness composed of 11.2mm
to 0.09 mm (Type-a) or 13.2 mm to 0.09mm (Type-
b) aggregates using viscosity grade bitumen to
required line, grade and level to serve as wearing
course on a previously prepared base, including
mixing in a suitable hot mix plant of appropriate
capacity not less tha 200 tonnes/hour, laying and
rolling with a smooth wheeled roller, finished to
required level and grades.

Type-A sqm 148.00 151.80 155.40


Type-B sqm 136.40 140.00 143.50
5.09 511 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade
and cross fall using Type A and B Seal coats

(i) Case-I: Type A sqm 63.20 64.00 65.20


5.09 (ii) Case-II : Type B
Providing and laying of premix sand seal coat with
HMP of appropriate capacity not less than 200
tonnes/hours using crushed stone chipping 6.7mm sqm 42.50 43.30 44.30
size and penetration bitumen of suitable grade.

5.10 520
Supply of Stone aggregates for pavement course
Supply of stone aggregates from approved sources
conforming to physical requirement, specified in the
respective specefied clauses, including royalties ,
fees, rents, collection, transportaion, stacking and
testing and measured in cum as per clause 520

Competitive market rates to be ascertained.


Altenatively rates for stone crushing given in chapter
1 may be adopted, if found economical. In case for
supply of aggregates at site may be ascertained.
Loading and unloading charges and cost of carriage
may be added to the rates to arrive at the cost at site.

5.11 516 Mastic Asphalt


Providing and laying 25 mm thick mastic asphalt
wearing course with paving grade bitumen meeting
the requirements given in table 500-39, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine grained
hard stone chipping of 13.2 mm nominal size at the
rate of 0.005 cum per 10sqm and at an approximate
spacing of 10cm center to center in both directions, sqm 1387.90 1413.60 1439.30
pressed into surface when the temperature of
surfaces is not less tha 1000c, protruding 1mm to
4mm over mastic surface, all complete as per clause
516.

5.12 512 Slurry seal


Providing and laying slurry seal consisting of a
mixture of fine aggregates, portland cement filler,
bituminous emulsion and water on a road surface
including cleaning of surface, mixing of slurry seal
in a suitable mobile plant, laying and compacting to
provide even riding surface
(i) 2-3mm thickness (Type-i) sqm 44.50 45.30 46.20
5.12 (ii) 4-6mm thickness (Type-II) sqm 70.30 71.50 73.00
5.12 (iii) 6-8mm thickness (Type-III) sqm 84.80 86.30 88.10

5.13 519 Recycling of Bituminous Pavement with Central


Recycling Plant
Recycling pavement by cold milling of existing
bituminous layers, planning the surface after cold
milling, reclaiming excavated material to the extent
of 30 percent of the required quantity, hauling and
stock piling the reclaimed material near the central
recycling plant after carrying out necessary checks
and evaluation, adding fresh material including
rejuvenators as required , mixing in a hot mix plant,
transporting and laying at site and compacting tothe
required the grade , level and the thickness, all as
specified in clause 519.

A (i) Using by bituminous Macadam cum 5925.60 6145.70 6096.90


Grading I
A (ii) Using by bituminous Macadam cum 6029.40 6250.00 6206.80
Grading II
B cum 6678.60 6901.80 6844.20
(i) Using by Dense Graded bituminous macadam
Grading I
B (ii) Using by Dense Graded bituminous macadam
cum 7266.80 7510.60 7489.60

Grading II
C (i) Using bituminous concrete cum 8002.10 8259.60 8252.00
Grading I
C (ii) Using by bituminous concrete cum 8121.10 8380.90 8375.40
Grading II
Providing and applying low viscosity bitumen
emulsion for sealing cracks less than 3mm wide or
5.14 513 (i) sqm 42.50 43.30 44.10
incipient fretting or disintegration in an existing
bituminous surfacing

(ii) 1. In case it is decided by the engineer to blind the sqm 4.20 4.20 4.20
fog spray, the following may be added
5.15 518
Bituminous Cold mix (including gravel emulsion)
Providing laying and rolling of bituminous cold mix
on prepared base consisting of a mixture of unheated
mineral aggregate and emulsified or cutback
bitumen, including mixing in a plant of suitable type
and capacity , transporting , laying compacting and
finishing to specified grades and levels.

Using bitumen emulsion and 9.5mm or 13.2mm


(i) size aggregate cum 11750.90 11977.50 12257.50

(ii) Using bitumen emulsion and 19mm or 26.5mm cum 11686.00 11911.30 12190.10
nominal size aggregate
Using cutback bitumen and 9.5mm or 13.2mm
5.15 (iii) cum 7756.00 7902.30 8095.20
nominal size aggregate
Using cutback bitumen and 19mm or 26.5mm
5.15 (iv) cum 7672.20 7816.80 8008.20
nominal size aggregate
5.16 506 Sand asphalt /base course
Providing , laying and rolling sand-asphalt base
course compose of sand, mineral filler and
bitumnious binder on a prepared subgrade or sub-
base to the lines, levels, grades and cross sections as
per the drawing including mixing in a plant of cum 7230.10 7370.20 7549.90
suitable type and capacity, transporting, laying,
compacting and finishing.

5.17 517 (i) Crack prevention courses


Stress absorbing membrane (SAM) crack width
less than 6mm
Providng and laying of a stress absorbing membrane
over a cracked road surface, with crack width below
6 mm afer cleaning with a mechanical broom, using
modified binder complying with IRC:SP: 53, sprayed
at the rate of 9 kg per 10 sqm and spreading 5.6 mm
crushed stone aggregates @ 0.11 cum per 10 sqm
sqm 53.60 54.60 55.60
with hydraulic chip spreader, sweeping the surface
for uniform spread of aggregates and surface finished
to conform to clause 902.

5.17 (ii) Stress absorbing membrane (SAM) crack width


6mm to 9mm
Providng and laying of a stress absorbing membrane
over a cracked road surface, with crack width 6 mm
to 9mm afer cleaning with a mechanical broom,
using modified binder complying with IRC:SP: 53,
sprayed at the rate of 11 kg per 10 sqm and spreading
11.2 mm crushed stone aggregates @ 0.12 cum per
sqm 65.90 67.10 68.30
10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface
finished to conform to clause 902.

Stress absorbing membrane (SAM) crack width


(iii) above 9 mm and cracked area above 50 percent

Providng and laying of a stress absorbing membrane


over a cracked road surface, with crack width above
9mm and cracked area above 50 percent after
cleaning with a mechanical broom, using modified
binder complying with IRC:SP: 53, sprayed at the
rate of 15 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm sqm 88.10 89.80 91.40
with hydraulic chip spreader, sweeping the surface
for uniform spread of aggregates and surface finished
to conform to clause 902.

5.17 (iv) Case IV: bitumen impregnated geotextile


Providing and laying of premix of crushed stone
aggregates and emulsion binder, mixed in a batch
type cold mixing plant, laid over prepared surface, sqm 164.00 167.00 170.10
by paver finisher, rolled with a pneumatic tyred
roller initially and finished with a smooth steel wheel
roller, all as per clause 518.3
5.18 518.3 Recipe Cold mix
Providing and laying of premix crushed stone
aggregates and emulsion binder, mixed in a batch
type cold mixing plant, laid over prepared surface,
by paver finisher, rolled with a pneumatic tyred rolle cum 7332.70 7480.10 7675.70
initially and finished with a smooth steel wheel
roller, all as per clause 518.3

5.18 (ii) 40mm thickness cum 10659.30 10871.30 11131.40


5.18 (iii) 25mm thickness cum 12037.60 12277.00 12559.40

Sugg
5.19 A Bituminous Concrete Grading 1 using waste
estive
plastic
Providing and laying bituminous concrete with
higher capacity batch typehot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @ 5.2 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the the required grade, level and alignment ,
rolling with smooth wheeled, vibratory and tandem cum 8153.30 8319.90 8534.60
rollers to achieve the desired compaction as per
MORT&H specification clause no. 507 complete in
all respects.

Sugg
5.19 estive B Bituminous Concrete Grading 2 ( using waste
plastic)
Providing and laying bituminous concrete with
higher capacity batch typehot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @ 5.4 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the the required grade, level and alignment ,
rolling with smooth wheeled, vibratory and tandem cum 8303.60 8472.90 8691.00
rollers to achieve the desired compaction as per
MORT&H specification clause no. 507 complete in
all respects.

5.20 519 A Hot recycling in place of Bituminous Pavement


with bituminous concrete
Grading I

Providing and laying bitminous concrete with hot


recycling in place using crushed caggregates of
specified grading, with bituminous bindes @ 5.2
percent of mix filler, transporting the aggregate to
work site, laying with a hot recycling in plavce to the cum 3272.20 3320.50 3374.10
required grade, level and alignment rolling with
smoothed wheeled, vibratoey and tandem rollers to
achieve the desired compaction as per MORTH
specificationf clause No. 519 complete in all
respects.

5.20 519 B Hot recycling in place of Bituminous Pavement


with bituminous concrete
Grading II
Providing and laying bitminous concrete with hot
recycling in place using crushed caggregates of
specified grading, with bituminous bindes @ 5.4
percent of mix filler, transporting the aggregate to
work site, laying with a hot recycling in plavce to the
required grade, level and alignment rolling with
cum 3294.30 3343.00 3396.90
smoothed wheeled, vibratoey and tandem rollers to
achieve the desired compaction as per MORTH
specificationf clause No. 519 complete in all
respects.
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
5.01 502 A Prime Coat over WMM/WBM
Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(i)
primer at the rate of 0.70 kg/sqm using mechanical
means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour
1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001

Water tanker (Speed @ 20km/hr and return speed @


30km/hr and spreading speed. @ 4.0 km/hr. L1=1
(i) 16 KL Capacity hour 0.073xL1+0 1426.00 978.24 PM11001
.613
(ii) 12 KL capacity hour 0.097XL1+ 1252.00 1144.33 PM11002
0.817
(iii) 6 KL Capacity hour 0.194XL1+ 907.00 1657.09 PM11003
1.633
c) Material
SS1 grade Bitumen emulsion @ 0.70 Kg per sqm tonne 4.900 4.900 4.900 46509.00 227894.10 227894.10 227894.10 M-077
Cost of water KL 10.500 10.500 10.500 73.60 772.80 772.80 772.80 M-191
Total cost( Without O.H&C.P.) 235655.63 235821.72 236334.48
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 18852.45 23582.17 28360.14
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 25450.81 25940.39 26469.46
Cost for 7000 sqm = a+b+c+d+e 279958.89 285344.28 291164.08
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Rate per sqm = (a+b+c+d+e)/7000 39.99 40.76 41.59
Say 40.00 40.80 41.60
Bitumen primer has been provided @ 0.70 kg per
sqm as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between
Note this quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in
clause No. 502.4.3.

Providing and applying primer coat with cutback MC


30 bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(ii)
primer at the rate of 0.60 kg/sqm using mechanical
means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour
1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
Water tanker (Speed @ 20km/hr and return speed @
30km/hr and spreading speed @ 4.0 km/hr L1=1
(i) 16 KL Capacity hour 0.073xL1+0 1426.00 978.24 PM11001
.613
(ii) 12 KL capacity hour 0.097XL1+ 1252.00 1144.33 PM11002
0.817
(iii) 6 KL Capacity hour 0.194XL1+ 907.00 1657.09 PM11003
1.633
c) Material
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Cutback Bitumen MC 30 @ 0.60 Kg per sqm tonne 4.200 4.200 4.200 43502.00 182708.40 182708.40 182708.40 M-076
Cost of water KL 10.500 10.500 10.500 73.60 772.80 772.80 772.80 M-191
Total cost( Without O.H&C.P.) 190469.93 190636.02 191148.78
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 15237.59 19063.60 22937.85
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 20570.75 20969.96 21408.66
Cost for 7000 sqm = a+b+c+d+e 226278.28 230669.59 235495.30
Rate per sqm = (a+b+c+d+e)/7000 32.33 32.95 33.64
Say 32.30 33.00 33.60
Bitumen primer has been provided @ 0.60 kg per
sqm as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between
Note this quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in
clause No. 502.4.3.

5.01 502 B Prime Coat over Stabilized soi bases/ Crusher Run
Macadam
Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular
(i) Base including clearing of road surface and spraying
primer at the rate of 0.90 kg/sqm using mechanical
means.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour 1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
Water tanker (Speed @ 20km/hr and return speed @ L1=1
30km/hr and spreading speed @ 4.0 km/hr
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 16 KL Capacity hour 0.073xL1+0 1426.00 978.24 PM11001
.613
(ii) 12 KL capacity hour 0.097XL1+ 1252.00 1144.33 PM11002
0.817
(ii) 6 KL capacity hour 0.194XL1+ 907.00 1657.09 PM11003
1.633
c) Material
SS1 grade bitumen emulsion @ 0.9 kg/sqm tonne 6.300 6.300 6.300 46509.00 293006.70 293006.70 293006.70 M-077
Cost of water KL 10.500 10.500 10.500 73.60 772.80 772.80 772.80 M-191
Total cost( Without O.H&C.P.) 300768.23 300934.32 301447.08
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 24061.46 30093.43 36173.65
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 32482.97 33102.78 33762.07
Cost for 7000 sqm = a+b+c+d+e 357312.66 364130.53 371382.81
Rate per sqm = (a+b+c+d+e)/7000 51.04 52.02 53.05
Say 51.00 52.00 53.10
Bitumen primer has been provided @ 0.90 kg per
sqm as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between
Note this quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in
clause No. 502.4.3.

Providing and applying primer coat with cutback MC


70 bitumen emulsion on prepared surface of granular
Base including clearing of road surface and spraying
(ii)
primer at the rate of 0.90 kg/sqm using mechanical
means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour 1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
Water tanker (Speed @ 20km/hr and return speed @ L1=1
30km/hr and spreading speed @ 4.0 km/hr
(i) 16 KL Capacity hour 0.073xL1+0 1426.00 978.24 PM11001
.613
(ii) 12 KL capacity hour 0.097XL1+ 1252.00 1144.33 PM11002
0.817
(iii) 6 KL Capacity hour 0.194XL1+ 907.00 1657.09 PM11003
1.633
c) Material
Cutback Bitumen MC 70@ 0.90 Kg per sqm tonne 6.300 6.300 6.300 43502.00 274062.60 274062.60 274062.60 M-076
Cost of water KL 10.500 10.500 10.500 73.60 772.80 772.80 772.80 M-191
Total cost( Without O.H&C.P.) 281824.13 281990.22 282502.98
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 22545.93 28199.02 33900.36
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 30437.01 31018.92 31640.33
Cost for 7000 sqm = a+b+c+d+e 334807.07 341208.17 348043.68
Rate per sqm = (a+b+c+d+e)/7000 47.83 48.74 49.72
Say 47.80 48.70 49.70
Bitumen primer has been provided @ 0.90 kg per
sqm as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between
Note this quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in
clause No. 502.4.3.

5.02 503 (i) Tack Coat on Bituminous surfaces


Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.20 kg per sqm on the prepared bituminous
surface cleaned with mechanical broom.
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour 1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
c) Material
Bitumen emulsion @0.2 kg per sqm tonne 1.400 1.400 1.400 46509.00 65112.60 65112.60 65112.60 M-077
Total cost( Without O.H&C.P.) 71123.09 71123.09 71123.09
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 5689.85 7112.31 8534.77
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 7681.29 7823.54 7965.79
Cost for 7000 sqm = a+b+c+d+e 84494.24 86058.94 87623.65
Rate per sqm = (a+b+c+d+e)/7000 12.07 12.29 12.52
Say 12.10 12.30 12.50
Bitumen emulsion has been provided @ 0.20 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between
Note this quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in
clause No. 503.4.3.

5.02 503 (ii) Tack Coat on Granular surfaces treated with


primer
Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.25 kg per sqm on the prepared bituminous
surface cleaned with mechanical broom.

Unit = sqm
Taking output = 7000 sqm
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour 1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
c) Material
Bitumen emulsion @0.25 kg per sqm tonne 1.750 1.750 1.750 46509.00 81390.75 81390.75 81390.75 M-077
Total cost( Without O.H&C.P.) 87401.24 87401.24 87401.24
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 6992.10 8740.12 10488.15
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 9439.33 9614.14 9788.94
Cost for 7000 sqm = a+b+c+d+e 103832.68 105755.51 107678.33
Rate per sqm = (a+b+c+d+e)/7000 14.83 15.11 15.38
Say 14.80 15.10 15.40
1) Bitumen emulsion has been provided @ 0.25 kg
per sqm as per clause 503.8. Payment shall be made
with adjustment, plus or minus, for the variation
Note between this quantity and actual quantity approved
by the Engineer after the preliminary trials referred to
in clause No. 503.4.3.

2) An output of 7000 sqm has been considered in


case of prime coat and tack coat which can be
covered by bituminous courses on the same day

5.02 503 (iii) Tack Coat on Cement concrete pavement


Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.30 kg per sqm on the prepared bituminous
surface cleaned with mechanical broom.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 310.00 24.80 24.80 24.80 L-12
Mazdoor day 2.000 2.000 2.000 292.00 584.00 584.00 584.00 L-13
b) Machinery
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mechanical broom (2.1 m sweeping width) hour 2.083 2.083 2.083 642.00 1337.29 1337.29 1337.29 PM23001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Air compressor 250 cfm hour 2.083 2.083 2.083 416.00 866.53 866.53 866.53 PM15001
Bitumen pressure distributor (spraying width 4.5m) hour 1.944 1.944 1.944 1645.00 3197.88 3197.88 3197.88 PM24001
c) Material
Bitumen emulsion @0.30 kg per sqm tonne 2.100 2.100 2.100 46509.00 97668.90 97668.90 97668.90 M-077
Total cost( Without O.H&C.P.) 103679.39 103679.39 103679.39
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 8294.35 10367.94 12441.53
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 11197.37 11404.73 11612.09
Cost for 7000 sqm = a+b+c+d+e 123171.12 125452.07 127733.01
Rate per sqm = (a+b+c+d+e)/7000 17.60 17.92 18.25
Say 17.60 17.90 18.20
NOTE 1) Bitumen emulsion has been provided @ 0.30 kg
per sqm as per clause 503.8. Payment shall be made
with adjustment, plus or minus, for the variation
between this quantity and the actual quantity
approved by the Engineer after the preliminary trials
referred to in clause No. 503.4.3.

2) An output of 7000 sqm has been considered in


case of prime coat and tack coat which can be
covered by bituminous courses on the same day

5.03 504 (i) Bituminous Macadam Grading- I


Providing and laying bituminous macadam with
higher capacity hot mix plant using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction.

Unit=cum
Taking output=205cum
a) Labour
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Batch type hot mix plant
(i) HMP 200 TPH hour 3.007 14810.00 44533.67 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.758 10450.00 0.00 39271.10 0.00 PM18002
(iii) HMP 120 TPH hour 5.011 8309.00 0.00 0.00 41636.40 PM18003
Mechanical broom (2.1m sweeping width) hour 0.697 0.697 0.697 642.00 447.47 447.47 447.47 PM23001
Air compressor 250 cfm hour 0.697 0.697 0.697 416.00 289.95 289.95 289.95 PM15001
Paver finisher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240 HP) hour 3.007 8710.00 26190.97 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.758 8710.00 0.00 32732.18 0.00 PM29001
(iii) Paver (174 HP) hour 5.011 6808.00 0.00 0.00 34114.89 PM29002
Electric generator
(i) 500 KVA hour 3.007 9075.00 27288.53 0.00 0.00 PM22002
(ii) 400 KVA hour 3.758 7303.00 0.00 27444.67 0.00 PM22003
(iii) 250 KVA hour 5.011 4359.00 0.00 0.00 21842.95 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 4.618 4255.00 19649.59 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 6.826 2588.00 0.00 17665.69 0.00 PM5002
(iii) 1 Cum Capacity hour 14.273 1594.00 0.00 0.00 22751.16 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 451xL1 5.94 2678.94 PM72001
(ii) 14 cum Capacity t.km 451XL1 6.63 2990.13 PM73001
(iii) 10 Cum Capacity t.km 451XL1 8.08 3644.08 PM74001
For loading & Unloading time
(i) 18 cum Capacity hour 6.013 2772.00 16668.04 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.517 2415.00 0.00 18153.56 0.00 PM6002
(iii) 10 Cum Capacity hour 10.022 2121.00 0.00 0.00 21256.66 PM6003
Smooth steel wheeled tandem roller for static and hour 7.256 7.256 7.256 2357.00 17102.39 17102.39 17102.39 PM9001
vibratory passages
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
c) Material
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
i) Bitumen @ 3.3 percent of mix tonne 14.883 14.883 14.883 43502.00 647440.27 647440.27 647440.27 M-074
Weight of mix = 205 X 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451 tonnes
Weight of bitumen= 14.88 tonnes
Weight of aggregate = 436.12 tonnes
Taking density of aggregate= 1.5 tonne/ cum
*Grading I ( 40 mm nominal size)
37.5-25 mm 15 percent cum 43.612 43.612 43.612 524.49 22874.06 22874.06 22874.06 M-048
25- 10 mm 45 percent cum 130.835 130.835 130.835 656.34 85872.24 85872.24 85872.24 M-045
10-5mm 25 percent cum 72.686 72.686 72.686 573.71 41700.69 41700.69 41700.69 M-039
5mm and below 15 percent cum 14.537 14.537 14.537 249.22 3622.91 3622.91 3622.91 M-029
* Any one of the alternative may be adopted asper approved design
(i) for Grading I ( 40mm nominal size)
Total cost( Without O.H&C.P.) 960098.11 961345.71 968334.52
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 76807.85 96134.57 116200.14
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 103690.60 105748.03 108453.47
Cost for 205 cum = a+b+c+d+e 1140596.56 1163228.31 1192988.13
Rate per cum = (a+b+c+d+e)/205 5563.89 5674.28 5819.45
Say 5563.90 5674.30 5819.50
Note: 1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job
mix formula.
2. Labour for traffic control, watch and ward and
other miscellaneous duties at site including sundries
have been included in administrative overheads of the
contractor.

3. In case BM is laid over freshly laid tack coat,


provision of Mechanical broom and 2 mazdoors for
the same shall be deleted as the same has been
included in the cost of tack coat.
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
5.03 504 (ii) Bituminous Macadam Grading-II
Providing and laying bituminous macadam with
higher capacity hot mix plant using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction.

Unit=cum
Taking output=205cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Batch type hot mix plant
(i) HMP 200 TPH hour 3.007 14810.00 44533.67 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.758 10450.00 0.00 39271.10 0.00 PM18002
(iii) HMP 120 TPH hour 5.011 8309.00 0.00 0.00 41636.40 PM18003
Mechanical broom (2.1m sweeping width) hour 0.976 0.976 0.976 642.00 626.59 626.59 626.59 PM23001
Air compressor 250 cfm hour 0.976 0.976 0.976 416.00 406.02 406.02 406.02 PM15001
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.007 8710.00 26190.97 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.758 8710.00 0.00 32732.18 0.00 PM29001
(iii) Paver (174 HP) hour 5.011 6808.00 0.00 0.00 34114.89 PM29002
Electric generator
(i) 500 KVA hour 3.007 9075.00 27288.53 0.00 0.00 PM22002
(ii) 400 KVA hour 3.758 7303.00 0.00 27444.67 0.00 PM22003
(iii) 250 KVA hour 5.011 4359.00 0.00 0.00 21842.95 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 5.125 4255.00 21806.88 0.00 0.00 PM5001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(ii) 2.1 cum Capacity hour 7.577 2588.00 0.00 19609.28 0.00 PM5002
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) 1 Cum Capacity hour 15.842 1594.00 0.00 0.00 25252.15 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 451XL1 5.94 2678.94 PM72001
(ii) 14 cum Capacity t.km 451XL1 6.63 2990.13 PM73001
(iii) 10 Cum Capacity t.km 451XL1 8.08 3644.08 PM74001
Tipper for loading & Unloading time
(i) 18 cum Capacity hour 6.013 2772.00 16668.04 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.517 2415.00 0.00 18153.56 0.00 PM6002
(iii) 10 Cum Capacity hour 10.022 2121.00 0.00 0.00 21256.66 PM6003
Smooth steel wheeled tandem roller for static and hour 10.159 10.159 10.159 2357.00 23944.76 23944.76 23944.76 PM9001
vibratory passages
c) Material
i) Bitumen @ 3.4 percent of mix tonne 15.334 15.334 15.334 43502.00 667059.67 667059.67 667059.67 M-074
Weight of mix = 205 * 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451 tonnes
Weight of bitumen= 15.33 tonnes
Weight of aggregate = 435.67 tonnes
Taking density of aggregate= 1.5 tonne/ cum
Grading II ( 19 mm nominal size)
25-10 mm 40 percent cum 116.178 116.178 116.178 656.34 76252.27 76252.27 76252.27 M-045
10-5mm 40 percent cum 116.178 116.178 116.178 573.71 66652.48 66652.48 66652.48 M-039
5mm and below 20 percent cum 58.089 58.089 58.089 249.22 14476.94 14476.94 14476.94 M-029
* Any one of the alternative may be adopted asper approved design
(i) for grading II ( 19mm nominal size)
Total cost( Without O.H&C.P.) 992324.14 993358.04 1000904.25
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 79385.93 99335.80 120108.51
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 107171.01 109269.38 112101.28
1178881.08 1201963.23 1233114.04
Rate per cum = (a+b+c+d+e)/205 5750.64 5863.24 6015.19
Say 5750.60 5863.20 6015.20
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
NOTE *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job
mix formula.
2. Labour for traffic control, watch and ward and
other miscellaneous duties at site including sundries
have been included in administrative overheads of the
contractor.

3. In case BM is laid over freshly laid tack coat,


provision of Mechanical broom and 2 mazdoors for
the same shall be deleted as the same has been
included in the cost of tack coat.

Dense Graded Bituminous Macadam Grading-I


5.04 505 A

Providing and laying dense graded bituminous


macadam with higher capacity batch type HMP using
crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 per cent by weight of
total mix and filler, transporting the hot mix to work
site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction
as per MoRTH specification clause No. 505 complete
in all respects.

Unit = cum
Taking output = 195 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
H ot mix plant
(i) HMP 200 TPH hour 3.003 14810.00 44474.43 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.754 10450.00 0.00 39229.30 0.00 PM18002
(iii) HMP 120 TPH hour 5.005 8309.00 0.00 0.00 41586.55 PM18003
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 642.00 425.65 425.65 425.65 PM23001
Air compressor 250 cfm hour 0.663 0.663 0.663 416.00 275.81 275.81 275.81 PM15001
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.003 8710.00 26156.13 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.754 8710.00 0.00 32697.34 0.00 PM29001
(iii) Paver (174 HP) hour 5.005 6808.00 0.00 0.00 34074.04 PM29002
Electric generator
(i) 500 KVA hour 3.003 9075.00 27252.23 0.00 0.00 PM22002
(ii) 400 KVA hour 3.754 7303.00 0.00 27415.46 0.00 PM22003
(iii) 250 KVA hour 5.005 4359.00 0.00 0.00 21816.80 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 5.138 4255.00 21862.19 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.596 2588.00 0.00 19658.45 0.00 PM5002
(iii) 1 Cum Capacity hour 15.882 1594.00 0.00 0.00 25315.91 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 450.45XL1 5.94 2675.67 PM72001

(ii) 14 cum Capacity t.km 450.45XL1 6.63 2986.48 PM73001


(iii) 10 Cum Capacity t.km 450.45XL1 8.08 3639.64 PM74001
Tipper For loading & Unloading time
(i) 18 cum Capacity hour 6.006 2772.00 16648.63 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.508 2415.00 0.00 18131.82 0.00 PM6002
(iii) 10 Cum Capacity hour 10.010 2121.00 0.00 0.00 21231.21 PM6003
Smooth steel wheeled tandem roller for static and hour 9.663 9.663 9.663 2357.00 22775.69 22775.69 22775.69 PM9001
vibratory passages
c) Material
i) Bitumen @ 4 percent of mix tonne 18.018 18.018 18.018 43502.00 783819.04 783819.04 783819.04 M-074
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Weight of mix = 205 x 2.231 = 450.45 tonne
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen= 18.02 tonnes
Weight of aggregate = 432.43 tonnes
Taking density of aggregate= 1.5 tonne/ cum
Grading- I 37.5mm (Nominal size)
37.5-25mm 22 percent cum 63.423 63.423 63.423 524.49 33264.73 33264.73 33264.73 M-048
25-10 mm 13 percent cum 37.477 37.477 37.477 656.34 24597.65 24597.65 24597.65 M-045
10-4.75mm 19 percent cum 54.775 54.775 54.775 573.71 31424.97 31424.97 31424.97 M-039
4.75 mm and below 44 percent cum 126.847 126.847 126.847 249.22 31612.81 31612.81 31612.81 M-029
Filler @ 2percent of weight of aggregates tonne 8.649 8.649 8.649 3637.51 31460.82 31460.82 31460.82 M-190
* Any one of the alternative may be adopted asper approved design 1102464.84 1103514.42 1111059.70
Grading I 37.5mm (Nominal size)
Total cost( Without O.H&C.P.) 1102464.84 1103514.42 1111059.70
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 88197.19 110351.44 133327.16
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 119066.20 121386.59 124438.69
Cost for 195 cum = a+b+c+d+e 1309728.23 1335252.44 1368825.55
Rate per cum = (a+b+c+d+e)/195 6716.56 6847.45 7019.62
Say 6716.60 6847.40 7019.60

5.04 505 B
Dense graded Bituminous Macadam Grading-II
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providing and laying dense graded bituminous
macadam with higher capacity batch type HMP using
crushed aggregates of specified grading, premixed
with bituminous binder @4.5 percent by weight of
total mix and filler, transporting the hot mix to work
site laying with a hydrostatic paver finisher with
sensor control to the required grade level and
alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction
as per MORT&H specification clause no. 505
complete in all respects.

S
Unit= cum
Taking output= 195 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 3.003 14810.00 44474.43 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.754 10450.00 0.00 39229.30 0.00 PM18002
(iii) HMP 120 TPH hour 5.005 8309.00 0.00 0.00 41586.55 PM18003
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 642.00 425.65 425.65 425.65 PM23001
Air compressor 250 cfm hour 0.663 0.663 0.663 416.00 275.81 275.81 275.81 PM15001
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.003 8710.00 26156.13 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.754 8710.00 0.00 32697.34 0.00 PM29001
(iii) Paver (174 HP) hour 5.005 6808.00 0.00 0.00 34074.04 PM29002
Electric generator
(i) 500 KVA hour 3.003 9075.00 27252.23 0.00 0.00 PM22002
(ii) 400 KVA hour 3.754 7303.00 0.00 27415.46 0.00 PM22003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) 250 KVA hour 5.005 4359.00 0.00 0.00 21816.80 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 5.112 4255.00 21751.56 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.556 2588.00 0.00 19554.93 0.00 PM5002
(iii) 1 Cum Capacity hour 15.799 1594.00 0.00 0.00 25183.61 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 450.45XL1 5.94 2675.67 PM72001

(ii) 14 cum Capacity t.km 450.45XL1 6.63 2986.48 PM73001


450.45XL1
(iii) 10 Cum Capacity t.km 8.08 3639.64 PM74001

Tipper for loading & Unloading time


(i) 18 cum Capacity hour 6.006 2772.00 16648.63 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.508 2415.00 0.00 18131.82 0.00 PM6002
(iii) 10 Cum Capacity hour 10.010 2121.00 0.00 0.00 21231.21 PM6003
Smooth steel wheeled tandem roller for static and hour 9.663 9.663 9.663 2357.00 22775.69 22775.69 22775.69 PM9001
vibratory passages
c) Material
i) Bitumen @ 4.5 percent of mix tonne 20.270 20.270 20.270 43502.00 881785.54 881785.54 881785.54 M-074
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen= 20.27 tonnes
Weight of aggregate = 430.18 tonnes
Taking density of aggregate= 1.5 tonne/ cum
Grading-2, 26.5 mm (Nominal size)
25-10mm 30 percent cum 86.036 86.036 86.036 656.34 56468.87 56468.87 56468.87 M-045
10-5mm 28 percent cum 80.300 80.300 80.300 573.71 46068.91 46068.91 46068.91 M-039
5mm and below 40 percent cum 114.715 114.715 114.715 249.22 28589.27 28589.27 28589.27 M-029
Filler @2 percent of weight of aggregates tonne 8.604 8.604 8.604 3637.51 31297.14 31297.14 31297.14 M-190
* Any one of the alternative may be adopted asper approved design
Grading-2, 26.5mm (Nominal size)
Total cost( Without O.H&C.P.) 1210383.92 1211440.61 1218957.11
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 96830.71 121144.06 146274.85
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 130721.46 133258.47 136523.20
Cost for 195 cum = a+b+c+d+e 1437936.10 1465843.14 1501755.16
Rate per cum = (a+b+c+d+e)/195 7374.03 7517.14 7701.31
Say 7374.00 7517.10 7701.30
1.Quantity of Bitumen has been taken for analysis
Note purpose. The actual quantity will depend upon job
mix formula.
2. Labour for traffic control, watch and ward and
other miscellaneous duties at site including sundries
have been included in administrative overheads of the
contractor.

3. In case DBM is laid over freshly laid tack coat,


provision of Mechanical broom and 2 mazdoors shall
be deleted as the same has been included in the cost
of tack coat.

4. The average density of 1.5 tonne/cum is only a


refrence density in this data book.
5. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e.
excluding the weight of bitu,men. The weight of filler
will alo be 2 percent by weight of dry aggregates.

5.05 507 A Bituminous concrete Grading- I


BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providing and laying bituminous concrete with
higher capacity batch type hot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @5.2 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment , rolling
with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 3.005 14810.00 44504.05 0.00 0.00 PM18001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(ii) HMP 160 TPH hour 3.756 10450.00 0.00 39250.20 0.00 PM18002
(iii) HMP 120 TPH hour 5.008 8309.00 0.00 0.00 41611.47 PM18003
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 642.00 729.95 729.95 729.95 PM23001
Air compressor 250 cfm hour 1.137 1.137 1.137 416.00 472.99 472.99 472.99 PM15001
Paver finisher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240 HP) hour 3.005 8710.00 26173.55 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.756 8710.00 0.00 32714.76 0.00 PM29001
(iii) Paver (174 HP) hour 5.008 6808.00 0.00 0.00 34094.46 PM29002
Electric generator
(i) 500 KVA hour 3.005 9075.00 27270.38 0.00 0.00 PM22002
(ii) 400 KVA hour 3.756 7303.00 0.00 27430.07 0.00 PM22003
(iii) 250 KVA hour 5.008 4359.00 0.00 0.00 21829.87 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 5.078 4255.00 21606.89 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.506 2588.00 0.00 19425.53 0.00 PM5002
(iii) 1 Cum Capacity hour 15.694 1594.00 0.00 0.00 25016.24 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 450.76xL1 5.94 2677.51 PM72001
(ii) 14 cum Capacity t.km 450.76xL1 6.63 2988.54 PM73001
(iii) 10 Cum Capacity t.km 450.76xL1 8.08 3642.14 PM74001
Tipper for loading & Unloading time
(i) 18 cum Capacity hour 6.010 2772.00 16659.72 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.513 2415.00 0.00 18143.90 0.00 PM6002
(iii) 10 Cum Capacity hour 10.017 2121.00 0.00 0.00 21246.06 PM6003
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibratory passages

Pneumatic tyre roller hour 2.404 3.005 4.007 2338.00 5620.55 7025.69 9368.37 PM10001
c) Material
i) Bitumen @ 5.2 percent of mix tonne 23.440 23.440 23.440 43502.00 1019686.88 1019686.88 1019686.88 M-074
ii) Aggregate
Total weight of mix = 450.76tonnes
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Weight of bitumen= 23.44 tonnes
Weight of aggregate = 427.32 tonnes
Taking density of aggregate= 1.5 tonne/ cum
*Grading I 19mm (Nominal size)
20-10mm 38 percent cum 108.255 108.255 108.255 686.05 74268.34 74268.34 74268.34 M-044
10-5mm 17percent cum 48.430 48.430 48.430 573.71 27784.78 27784.78 27784.78 M-039
5mm and below 43 percent cum 122.499 122.499 122.499 249.22 30529.20 30529.20 30529.20 M-029
Filler @ 2percent of weight of aggregates tonne 8.546 8.546 8.546 3637.51 31086.16 31086.16 31086.16 M-190
* Any one of the alternative may be adopted asper
approved design
Total cost( Without O.H&C.P.) 1360695.02 1363161.05 1372990.98
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 108855.60 136316.11 164758.92
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 146955.06 149947.72 153774.99
Cost for 191 cum = a+b+c+d+e 1616505.69 1649424.87 1691524.89
Rate per cum = (a+b+c+d+e)/191 8463.38 8635.73 8856.15
Say 8463.40 8635.70 8856.20
5.05 507 B Bituminous concrete Grading- II
Providing and laying bituminous concrete with
higher capacity batch type hot mix plant using
crushed aggregates of specified grading, premixed
with bituminous binder @5.4 percent of mix and
filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment , rolling
with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 3.005 14810.00 44504.05 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.756 10450.00 0.00 39250.20 0.00 PM18002
(iii) HMP 120 TPH hour 5.008 8309.00 0.00 0.00 41611.47 PM18003
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 642.00 1042.61 1042.61 1042.61 PM23001
Air compressor 250 cfm hour 1.624 1.624 1.624 416.00 675.58 675.58 675.58 PM15001
Paver finisher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240 HP) hour 3.005 8710.00 26173.55 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.756 8710.00 0.00 32714.76 0.00 PM29001
(iii) Paver (174 HP) hour 5.008 6808.00 0.00 0.00 34094.46 PM29002
Electric generator
(i) 500 KVA hour 3.005 9075.00 27270.38 0.00 0.00 PM22002
(ii) 400 KVA hour 3.756 7303.00 0.00 27430.07 0.00 PM22003
(iii) 250 KVA hour 5.008 4359.00 0.00 0.00 21829.87 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 5.004 4255.00 21292.02 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.378 2588.00 0.00 19094.26 0.00 PM5002
(iii) 1 Cum Capacity hour 15.553 1594.00 0.00 0.00 24791.48 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 450.76xL1 5.94 2677.51 PM72001
(ii) 14 cum Capacity t.km 450.76xL1 6.63 2988.54 PM73001
(iii) 10 Cum Capacity t.km 450.76xL1 8.08 3642.14 PM74001
For loading & Unloading time
(i) 18 cum Capacity hour 6.010 2772.00 16659.72 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 7.513 2415.00 0.00 18143.90 0.00 PM6002
(iii) 10 Cum Capacity hour 10.017 2121.00 0.00 0.00 21246.06 PM6003
Smooth steel wheeled tandem roller for static and
hour 16.902 16.902 16.902 2357.00 39838.01 39838.01 39838.01 PM9001
vibratory passages
Pneumatic tyre roller hour 2.404 3.005 4.007 2338.00 5620.55 7025.69 9368.37 PM10001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
c) Material
i) Bitumen @ 5.4 percent of mix tonne 24.341 24.341 24.341 43502.00 1058882.18 1058882.18 1058882.18 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen= 24.34
Weight of aggregate = 426.42 tonnes
Taking density of aggregate= 1.5 tonne/ cum
*Grading II 13mm (Nominal size)
13.2mm-10 mm 21percent cum 59.699 59.699 59.699 686.05 40956.50 40956.50 40956.50 M-043
10-5mm 17percent cum 48.327 48.327 48.327 573.71 27725.68 27725.68 27725.68 M-039
5mm and below 60 percent cum 170.568 170.568 170.568 249.22 42508.96 42508.96 42508.96 M-029
Filler @ 2percent of weight of aggregates tonne 8.528 8.528 8.528 3637.51 31020.69 31020.69 31020.69 M-190
* Any one of the alternative may be adopted asper
approved design
Total cost( Without O.H&C.P.) 1390586.39 1393036.03 1402972.47
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 111246.91 139303.60 168356.70
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 150183.33 153233.96 157132.92
Cost for 191 cum = a+b+c+d+e 1652016.64 1685573.59 1728462.08
Rate per cum = (a+b+c+d+e)/191 8649.30 8824.99 9049.54
Say 8649.30 8825.00 9049.50
1.Quantity of Bitumen has been taken for analysis
Note purpose. The actual quantity will depend upon job
mix formula.
2. Labour for traffic control, watch and ward and
other miscellaneous duties at site including sundries
have been included in administrative overheads of the
contractor.

3. In case BC is laid over freshly laid tack coat,


provision of Mechanical broom and 2 mazdoors shall
be deleted as the same has been included in the cost
of tack coat.
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
4. The average density of 1.5 tonne/cum is only a
refrence density in this data book.
5. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e.
excluding the weight of bitumen. The weight of filler
will also be 2 percent by weight of dry aggregates.

5.06 509 Surface Dressing


Providing and laying surface dressing as wearing
course in a single coat using crushed stone aggregates
of specified size on a layer of bituminous binder laid
on prepared surface and rolling with 8-10 tonne
smooth wheeled steel roller

Unit=sqm
Taking output= 9000sqm
5.06 Case-I 19mm Nominal chipping size
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 9.000 9.000 9.000 292.00 2628.00 2628.00 2628.00 L-13
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 642.00 1719.92 1719.92 1719.92 PM23001
Air compressor 250 cfm hour 2.679 2.679 2.679 416.00 1114.46 1114.46 1114.46 PM15001
Bitumen pressure distributor (Spraying width 4.5m)
hour 1.250 1.250 1.250 1645.00 2056.25 2056.25 2056.25 PM24001

Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2146.00 15882.55 15882.55 15882.55 PM32001
Front end loader for feeding the plant
(i) 3.1 cum capacity hour 0.823 4255.00 3501.87 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 1.216 2588.00 0.00 3147.01 0.00 PM5002
(ii) 1 cum Capacity hour 2.547 1594.00 0.00 0.00 4059.92 PM5003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 202.5XL1 5.94 1202.85 PM72001
(ii) 14 cum capacity t.km 202.5XL1 6.63 1342.58 PM73001
(iii) 10 cum capacity t.km 202.5XL1 8.08 1636.20 PM74001
For loading and unloading time
(i) 18 cum Capacity hour 8.224 2772.00 22796.93 0.00 0.00 PM6001
(ii) 14 cum capacity hour 8.618 2415.00 0.00 20812.47 0.00 PM6002
(iii) 10 cum capacity hour 9.948 2121.00 0.00 0.00 21099.71 PM6003
Smooth steel wheeled tandem roller for static and
vibratory pasages 5.973 5.973 5.973 2357.00 14078.36 14078.36 14078.36 PM9001
hour
Pneumatic Tyre roller hour 5.973 5.973 5.973 2338.00 13964.87 13964.87 13964.87 PM10001
c) Material
Bitumen @1.2 kg per sqm tonne 10.800 10.800 10.800 43502.00 469821.60 469821.60 469821.60 M-074
Crushed stone chipping, 19mm nominal size @ 0.015
cum per sqm cum 135.000 135.000 135.000 572.92 77344.20 77344.20 77344.20 M-046

Total cost( Without O.H&C.P.) 626988.26 624788.67 626282.44


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 50159.06 62478.87 75153.89
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 67714.73 68726.75 70143.63
Cost for 9000 sqm= a+b+c+d+e 744862.05 755994.29 771579.96
Rate per sqm =(a+b+c+d+e)/9000 82.76 84.00 85.73
Say 82.80 84.00 85.70
5.06 509 Case-II 13 mm Nominal size chipping
Unit= sqm
Taking output= 9000sqm
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 9.000 9.000 9.000 292.00 2628.00 2628.00 2628.00 L-13
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 642.00 1719.92 1719.92 1719.92 PM23001
Air compressor 250 cfm hour 2.679 2.679 2.679 416.00 1114.46 1114.46 1114.46 PM15001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Bitumen pressure distributor (Spraying width 4.5m)
hour 1.250 1.250 1.250 1645.00 2056.25 2056.25 2056.25 PM24001
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2146.00 15882.55 15882.55 15882.55 PM32001
Front end loader for loading
(i) 3.1 cum capacity hour 0.544 4255.00 2314.72 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 0.804 2588.00 0.00 2080.75 0.00 PM5002
(ii) 1 cum Capacity hour 1.688 1594.00 0.00 0.00 2690.67 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 135XL1 5.94 801.90 PM72001
(ii) 14 cum capacity t.km 135XL1 6.63 895.05 PM73001
(iii) 10 cum capacity t.km 135XL1 8.08 1090.80 PM74001
For loading and unloading time
(i) 18 cum Capacity hour 7.946 2772.00 22026.31 0.00 0.00 PM6001
(ii) 14 cum capacity hour 8.205 2415.00 0.00 19815.08 0.00 PM6002
(iii) 10 cum capacity hour 9.089 2121.00 0.00 0.00 19277.77 PM6003
Smooth steel wheeled tandem roller for static and
vibratory pasages hour 3.982 3.982 3.982 2357.00 9385.57 9385.57 9385.57 PM9001

Pneumatic Tyre roller hour 3.982 3.982 3.982 2338.00 9309.92 9309.92 9309.92 PM10001
c) Material
Bitumen @1.2 kg per sqm tonne 9.000 9.000 9.000 43502.00 391518.00 391518.00 391518.00 M-074
Crushed stone chipping, 13mm nominal size @ 0.015
cum per sqm cum 90.000 90.000 90.000 686.05 61744.50 61744.50 61744.50 M-051

Total cost( Without O.H&C.P.) 521378.50 519026.45 519294.81


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 41710.28 51902.64 62315.38
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 56308.88 57092.91 58161.02
Cost for 9000 sqm= a+b+c+d+e 619397.66 628022.00 639771.20
Rate per sqm =(a+b+c+d+e)/9000 68.82 69.78 71.09
Say 68.80 69.80 71.10
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
1. Where the proposed aggregate fails to pass the
stripping test, an approved adhesion agent may be
added to the binder as per clause 510.2.4.
Note
Alternatively, chips may be precoated as per clause
510.2

2. Input for the second coat, where required, will be


the same as per the Ist coat mentioned above

5.07 510 Open-Graded Premix Surfacing


Providing, laying and rolling of open-graded pemix
surfacing of 20mm thickness composed of 13.2mm to
5.6mm aggregates using viscosity grade bitumen to
required line, grade and level to serve as wearing
course on a previously prepared base, including
mixing in a suitable hot mix plant of appropriate
capcity not less than 200 tonnes/hour, laying and
rolling with a smooth wheeled roller finished to
required level and grades.

Unit=sqm
Taking output= 10250 sqm
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 3.225 14810.00 47762.25 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 4.032 10450.00 0.00 42134.40 0.00 PM18002
(iii) HMP 120 TPH hour 5.376 8309.00 0.00 0.00 44669.18 PM18003
Mechanical broom (2.1m sweeping width) hour 1.220 1.220 1.220 642.00 783.24 783.24 783.24 PM23001
Air compressor 250 cfm hour 1.220 1.220 1.220 416.00 507.52 507.52 507.52 PM15001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.225 8710.00 28089.75 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 4.032 8710.00 0.00 35118.72 0.00 PM29001
(iii) Paver (174 HP) hour 5.376 6808.00 0.00 0.00 36599.81 PM29002
Electric generator
(i) 500 KVA hour 3.225 9075.00 29266.88 0.00 0.00 PM22002
(ii) 400 KVA hour 4.032 7303.00 0.00 29445.70 0.00 PM22003
(iii) 250 KVA hour 5.376 4359.00 0.00 0.00 23433.98 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 4.942 4255.00 21028.21 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.283 2588.00 0.00 18848.40 0.00 PM5002
(iii) 1 Cum Capacity hour 15.375 1594.00 0.00 0.00 24507.75 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 483.8XL1 5.94 2873.77 PM72001
(ii) 14 cum Capacity t.km 483.8XL1 6.63 3207.59 PM73001
(iii) 10 Cum Capacity t.km 483.8XL1 8.08 3909.10 PM74001
For loading & Unloading time
(i) 18 cum Capacity hour 6.451 2772.00 17882.17 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 8.063 2415.00 0.00 19472.15 0.00 PM6002
(iii) 10 Cum Capacity hour 10.751 2121.00 0.00 0.00 22802.87 PM6003
Smooth steel wheeled tandem roller for static and hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passages
c) Material
i) Bitumen @ 14.60 kg per 10 sqm tonne 14.965 14.965 14.965 43502.00 651007.43 651007.43 651007.43 M-074
Crushed stone chipping, 13.2mm to 5.6mm @ 0.27 cum 276.750 276.750 276.750 657.91 182076.59 182076.59 182076.59 M-042
cum per 10 sqm
* Any one of the alternative may be adopted asper
approved design
Total cost( Without O.H&C.P.) 1027774.55 1029098.48 1036794.22
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 82221.96 102909.85 124415.31
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 110999.65 113200.83 116120.95
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Cost for 10250 sqm = a+b+c+d+e 1220996.16 1245209.16 1277330.48
Rate per sqm = (a+b+c+d+e)/10250 119.12 121.48 124.62
Say 119.10 121.50 124.60
5.08 508 Close Graded Premix Surfacing/Mixed Seal
Surfacing
Providing, laying and rolling of open graded premix
surfacing of 20mm thickness composed of 11.2mm to
0.09 mm (Type-a) or 13.2 mm to 0.09mm (Type-b)
aggregates using viscosity grade bitumen to required
line, grade and level to serve as wearing course on a
previously prepared base, including mixing in a
suitable hot mix plant of appropriate capacity not less
tha 200 tonnes/hour, laying and rolling with a smooth
wheeled roller, finished to required level and grades.

Unit=sqm
Taking output=10250 sqm
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 3.225 14810.00 47762.25 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 4.032 10450.00 0.00 42134.40 0.00 PM18002
(iii) HMP 120 TPH hour 5.376 8309.00 0.00 0.00 44669.18 PM18003
Mechanical broom (2.1m sweeping width) hour 1.220 1.220 1.220 642.00 783.24 783.24 783.24 PM23001
Air compressor 250 cfm hour 1.220 1.220 1.220 416.00 507.52 507.52 507.52 PM15001
Paver finisher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240 HP) hour 3.225 8710.00 28089.75 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 4.032 8710.00 0.00 35118.72 0.00 PM29001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) Paver (174 HP) hour 5.376 6808.00 0.00 0.00 36599.81 PM29002
Electric generator
(i) 500 KVA hour 3.225 9075.00 29266.88 0.00 0.00 PM22002
(ii) 400 KVA hour 4.032 7303.00 0.00 29445.70 0.00 PM22003
(iii) 250 KVA hour 5.376 4359.00 0.00 0.00 23433.98 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 3.225 4255.00 13722.38 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.283 2588.00 0.00 18848.40 0.00 PM5002
(iii) 1 Cum Capacity hour 15.375 1594.00 0.00 0.00 24507.75 PM5003
Tipper for transportation L1=1
(i) 18 cum Capacity t.km 483.8XL1 5.94 2873.77 PM72001
(ii) 14 cum Capacity t.km 483.8XL1 6.63 3207.59 PM73001
(iii) 10 Cum Capacity t.km 483.8XL1 8.08 3909.10 PM74001
For loading & Unloading time
(i) 18 cum Capacity hour 6.451 2772.00 17882.17 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 8.063 2415.00 0.00 19472.15 0.00 PM6002
(iii) 10 Cum Capacity hour 10.751 2121.00 0.00 0.00 22802.87 PM6003
Smooth steel wheeled tandem roller for static and hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passages
c) Material
Type-A
* Bitumen @ 22kg per 10sqm tonne 22.550 22.550 22.550 43502.00 980970.10 980970.10 980970.10 M-074
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 276.750 276.750 392.53 108632.68 108632.68 108632.68 M-040
cum per 10sqm
or
Type-B
Bitumen @19 kg per 10 sqm tonne 19.475 19.475 19.475 43502.00 847201.45 847201.45 847201.45 M-074
Stone crushed aggregates 13.2mm to 0.09mm @ 0.27 cum 276.750 276.750 276.750 515.53 142672.93 142672.93 142672.93 M-041
cum per 10sqm
* Any one of the alternative may be adopted as per
approved design
Type-A
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Total cost( Without O.H&C.P.) 1276987.47 1285617.23 1293312.98
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 102159.00 128561.72 155197.56
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 137914.65 141417.90 144851.05
Cost for 10250 sqm = a+b+c+d+e 1517061.11 1555596.85 1593361.59
Rate per sqm = (a+b+c+d+e)/10250 148.01 151.77 155.45
Say 148.00 151.80 155.40
Type-B
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Total cost( Without O.H&C.P.) 1177259.07 1185888.83 1193584.58
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 94180.73 118588.88 143230.15
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 127143.98 130447.77 133681.47
Cost for 10250 sqm = a+b+c+d+e 1398583.77 1434925.49 1470496.20
Rate per sqm = (a+b+c+d+e)/10250 136.45 139.99 143.46
Say 136.40 140.00 143.50
5.09 511 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade
and cross fall using Type A and B Seal coats

(i) Case-I: Type A


Unit= sqm
Taking output= 10250sqm
a) Labour
Mate day 0.240 0.240 0.240 310.00 74.40 74.40 74.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.051 3.051 3.051 642.00 1958.74 1958.74 1958.74 PM23001
Air compressor 250 cfm hour 3.051 3.051 3.051 416.00 1269.22 1269.22 1269.22 PM15001
1645.00 4683.32 4683.32 4683.32 PM24001
Bitumen pressure distributor (spraying width 4.5m) hour 2.847 2.847 2.847
Hydraulic self propelled chip spreader hour 8.429 8.429 8.429 2146.00 18088.63 18088.63 18088.63 PM32001
Front end loader
(i) 3.1 cum Capacity hour 0.563 4255.00 2395.57 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 0.831 2588.00 0.00 2150.63 0.00 PM5002
(iii) 1 Cum Capacity hour 1.741 1594.00 0.00 0.00 2775.15 PM5003
Tipper
For loading time
(i) 18 cum Capacity hour 0.563 2772.00 1560.64 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 0.831 2415.00 0.00 2006.87 0.00 PM6002
(iii) 10 Cum Capacity hour 1.741 2121.00 0.00 0.00 3692.66 PM6003
For transportation L1=1
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 18 cum Capacity t.km 202.95XL1 5.94 1205.52 PM72001
(ii) 14 cum Capacity t.km 202.95XL1 6.63 1345.56 PM73001
(iii) 10 Cum Capacity t.km 202.95XL1 8.08 1639.84 PM74001
For Unloading time
(i) 18 cum Capacity hour 8.429 2772.00 23365.19 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 8.429 2415.00 0.00 20356.04 0.00 PM6002
(iii) 10 Cum Capacity hour 8.429 2121.00 0.00 0.00 17877.91 PM6003
Smooth steel wheeled tandem roller for static and hour 4.082 4.082 4.082 2357.00 9621.27 9621.27 9621.27 PM9001
vibratory passages
c) Material
i) Bitumen @ 9.80 kg per 10 sqm tonne 10.045 10.045 10.045 43502.00 436977.59 436977.59 436977.59 M-074
Crushed stone chipping of 6.7 mm size defined as 100
percent passing 11.2mm sieve and retained on cum 92.250 92.250 92.250 454.98 41971.91 41971.91 41971.91 M-049
2.36mm sieve applied @ 0.09 cum per 10 sqm

Total cost( Without O.H&C.P.) 544923.99 542256.16 542382.64


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 43593.92 54225.62 65085.92
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 58851.79 59648.18 60746.86
Cost for 10250 sqm= a+b+c+d+e 647369.70 656129.96 668215.41
Rate per sqm = (a+b+c+d+e)/10250 63.16 64.01 65.19
Say 63.20 64.00 65.20
Note Since seal coat is provided immediately over the bituminous layers, mechanical broom for cleaning has not been catered.
5.09 (ii) Case-II : Type B
Providing and laying of premix sand seal coat with
HMP of appropriate capacity not less than 200
tonnes/hours using crushed stone chipping 6.7mm
size and penetration bitumen of suitable grade.

Unit=sqm
Taking output= 7860 sqm
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
b) Machinery
Hot mix plant
(i) HMP 200 TPH hour 0.314 14810.00 4650.34 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 0.393 10450.00 0.00 4106.85 0.00 PM18002
(iii) HMP 120 TPH hour 0.524 8309.00 0.00 0.00 4353.92 PM18003
Mechanical broom (2.1m sweeping width) hour 2.339 2.339 2.339 642.00 1501.64 1501.64 1501.64 PM23001
Air compressor 250 cfm hour 2.339 2.339 2.339 416.00 973.02 973.02 973.02 PM15001
Paver finisher hydrostatic with sensor control
compatible with Hot mix plant
(i) Paver (240 HP) hour 0.314 8710.00 2734.94 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 0.393 8710.00 0.00 3423.03 0.00 PM29001
(iii) Paver (174 HP) hour 0.524 6808.00 0.00 0.00 3567.39 PM29002
Electric generator
(i) 500 KVA hour 0.314 9075.00 2849.55 0.00 0.00 PM22002
(ii) 400 KVA hour 0.393 7303.00 0.00 2870.08 0.00 PM22003
(iii) 250 KVA hour 0.524 4359.00 0.00 0.00 2284.12 PM22004
Front end loader for feeding the plant
(i) 3.1 cum Capacity hour 0.832 4255.00 3540.16 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 1.230 2588.00 0.00 3183.24 0.00 PM5002
(iii) 1 Cum Capacity hour 2.572 1594.00 0.00 0.00 4099.77 PM5003
Tipper for transportation L1=1
103.752XL
(i) 18 cum Capacity 5.94 616.29 PM72001
1
103.752XL
(ii) 14 cum Capacity t.km 6.63 687.88 PM73001
1
103.752XL
(iii) 10 Cum Capacity t.km 8.08 838.32 PM74001
1
For loading & Unloading time
(i) 18 cum Capacity hour 0.629 2772.00 1743.59 0.00 0.00 PM6001
(ii) 14 cum Capacity hour 0.786 2415.00 0.00 1898.19 0.00 PM6002
(iii) 10 Cum Capacity hour 1.048 2121.00 0.00 0.00 2222.81 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Smooth steel wheeled tandem roller for static and 2357.00 4919.06 4919.06 4919.06 PM9001
vibratory passages hour 2.087 2.087 2.087
c) Material
i) Bitumen @ 6.80 kg per 10 sqm tonne 5.345 5.345 5.345 43502.00 232518.19 232518.19 232518.19 M-074
Crushed stone chipping of 6.7mm size defined as
passing 11.2mm sieve and retained on 2.6mm sieve cum 47.160 47.160 47.160 454.98 21456.86 21456.86 21456.86 M-049
applied @0.06 cum per 10 sqm
* Any one of the alternative may be adopted asper
approved design
Total cost( Without O.H&C.P.) 281242.03 281276.43 282473.48
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 22499.36 28127.64 33896.82
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 30374.14 30940.41 31637.03
Cost for 7860 sqm = a+b+c+d+e 334115.53 340344.48 348007.33
Rate per sqm = (a+b+c+d+e)/7860 42.51 43.30 44.28
Say 42.50 43.30 44.30
5.10 520
Supply of Stone aggregates for pavement course
Supply of stone aggregates from approved sources
conforming to physical requirement, specified in the
respective specefied clauses, including royalties ,
fees, rents, collection, transportaion, stacking and
testing and measured in cum as per clause 520

Competitive market rates to be ascertained.


Altenatively rates for stone crushing given in chapter
1 may be adopted, if found economical. In case for
supply of aggregates at site may be ascertained.
Loading and unloading charges and cost of carriage
may be added to the rates to arrive at the cost at site.

5.11 516 Mastic Asphalt


BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providing and laying 25 mm thick mastic asphalt
wearing course with paving grade bitumen meeting
the requirements given in table 500-39, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine grained
hard stone chipping of 13.2 mm nominal size at the
rate of 0.005 cum per 10sqm and at an approximate
spacing of 10cm center to center in both directions,
pressed into surface when the temperature of surfaces
is not less tha 1000c, protruding 1mm to 4mm over
mastic surface, all complete as per clause 516.

Unit=sqm
Taking output=35 sqm
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 10.000 10.000 10.000 292.00 2920.00 2920.00 2920.00 L-13
Mazdoor skilled day 1.000 1.000 1.000 370.00 370.00 370.00 370.00 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.010 0.010 0.010 642.00 6.42 6.42 6.42 PM23001
Air compressor 250 cfm hour 0.010 0.010 0.010 416.00 4.16 4.16 4.16 PM15001
Mastic cooker 1 tonne capacity hour 3.000 3.000 3.000 461.00 1383.00 1383.00 1383.00 PM27001
Bitumen boiler 1500 litres capacity hour 3.000 3.000 3.000 606.00 1818.00 1818.00 1818.00 PM26001
Tractor for towing and positioning of mastic cooker hour 1.000 1.000 1.000 612.00 612.00 612.00 612.00 PM12001
and bitumen boiler
c) Material

Base mastic (without coarse aggregates)= 60 percent


Coarse aggregate (6.3mm to 13.2mm)= 40 percent

Proportion of material required for mastic asphalt


with coarse aggregates ( based on mix design by
CRRI for a specific case)
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
i) Bitumen 85/25 or 30/40 @10.2 percent by weight tonne 0.205 0.205 0.205 44525.00 9127.63 9127.63 9127.63 M-327
of mix. 2 X 10.2/100=0.204

ii) Fine aggregate passing 2.36mm and retained on cum 0.395 0.395 0.395 286.72 113.25 113.25 113.25 M-019
0.075mm sieve @31.9 percent by weight of mix = 2
X 31.9/100=0.638 tonnes= 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not
less than 80 percent by weight of mix = 2 X tonne 0.361 0.361 0.361 3637.51 1313.14 1313.14 1313.14 M-190
17.92/100=0.36
iv) Coarse aggregates 6.3mm to 13.2mm @ 40
percent by weight of mix = 2 X 40/100= 0.8 MT= 0.553 0.553 0.553 657.91 363.82 363.82 363.82 M-042
0.8/1.456= 0.55 cum
v) Pre-Coated stone chips of 13.2 mm nominal size cum 0.018 0.018 0.018 686.05 12.35 12.35 12.35
for skid resistance =35 X 0.005/10=0.018 M-051

vi) Bitumen for coating of chips @2 percent by kg 0.510 0.510 0.510 44525.00 22707.75 22707.75 22707.75 M-327
weight= 0.018 X 1.456 X 2/100 = 0.0005 MT= 0.5kg
Total cost( Without O.H&C.P.) 40887.92 40887.92 40887.92
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 3271.03 4088.79 4906.55
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 4415.90 4497.67 4579.45
Cost for 35 sqm = a+b+c+d+e 48574.85 49474.39 50373.92
Rate per sqm= (a+b+c+d+e)/35 1387.85 1413.55 1439.25
Say 1387.90 1413.60 1439.30
Note 1. The rates for 50mm and 40mm thick layers may be
worked out on pro-rata basis
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3. The quantities of binder, filler and aggregates are
for estimating purpose. Exact quantities shall be as
per mix design.
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small

4. This rate analysis is based on design made by


CRRI for a specific case and is meant estimating
purposes only. Actual design is required to be done
for each case.
5.12 512 Slurry seal

Providing and laying slurry seal consisting of a


mixture of fine aggregates, portland cement filler,
bituminous emulsion and water on a road surface
including cleaning of surface, mixing of slurry seal in
a suitable mobile plant, laying and compacting to
provide even riding surface

(i) 2-3mm thickness (Type-i)


Unit=sqm
Taking output= 24000 sqm (60cum)
Taking density of 2.2 tonnes per cum
a) Labour
Mate day 0.200 0.200 0.200 310.00 62.00 62.00 62.00 L-12
Mazdoor day 5.000 5.000 5.000 292.00 1460.00 1460.00 1460.00 L-13
b) Machinery
Machanical broom (2.1m sweeping width) hour 7.143 7.143 7.143 642.00 4585.81 4585.81 4585.81 PM23001
Air compressor 250 cfm hour 7.143 7.143 7.143 416.00 2971.49 2971.49 2971.49 PM15001
Mobile slurry seal equipment hour 6.579 6.579 6.579 3619.00 23809.40 23809.40 23809.40 PM41001
Front end loader
(i) 3.1 Cum Capacity hour 0.366 4255.00 1557.33 0.00 0.00 PM5001
(ii) 2.1 cum capacity hour 0.541 2588.00 0.00 1400.11 0.00 PM5002
(iii) 1 cum capacity hour 1.132 1594.00 0.00 0.00 1804.41 PM5003
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.366 2772.00 1014.55 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.541 2415.00 0.00 1306.52 0.00 PM6002
(iii) 10 cum capacity hour 1.132 2121.00 0.00 0.00 2400.97 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
For transportation L1=1
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 18 cum capacity t.km 132XL1 5.94 784.08 PM72001
(ii) 14 cum capacity t.km 132XL1 6.63 875.16 PM73001
(iii) 10 cum capacity t.km 132XL1 8.08 1066.56 PM74001
Tipper for unloading time
(i) 18 cum capacity hour 6.579 2772.00 18236.99 0.00 0.00 PM6001
(ii) 14 cum capacity hour 6.579 2415.00 0.00 15888.29 0.00 PM6002
(iii) 10 cum capacity hour 6.579 2121.00 0.00 0.00 13954.06 PM6003
Water tanker (speed @20km/hr and return speed
@30km/hr and spreading speed @3 km/hr) L1=1
0.083xL1+3
(i) 16kL capacity hour 1426.000 4681.558 PM11001
.2
0.111xL1+4
(ii) 12 kL capacity hour 1252.000 5481.256 PM11002
.267
0.222xL1+8
(iii) 6 kL capacity hour 907.000 7940.785 PM11003
.533
Pneumatic tyred roller with individual wheel load not 5.263 5.263 5.263 2338.00 12304.89 12304.89 12304.89 PM10001
exceeding 1.5 tonnes hour
c) Material
Residual binder @13 percent of mix = 60 X 2.2 X 17.160 17.160 17.160 46509.00 798094.44 798094.44 798094.44 M-077
0.13 tonne
Fine aggregate 3mm and below 85.5 percent of total
mix, 60X2.2X0.855=112.860 tonnes. Taking density 75.240 75.240 75.240 286.72 21572.81 21572.81 21572.81 M-019
1.5,= 112.860/1.5= 75.240 cum cum
Filler @1.5 percent of total mix= 60X2.2X0.015 tonne 1.980 1.980 1.980 3637.51 7202.27 7202.27 7202.27 M-190
Cost of water kL 12.000 12.000 12.000 73.60 883.20 883.20 883.20 M-191
Total cost( Without O.H&C.P.) 899220.82 897897.64 900113.10
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 71937.67 89789.76 108013.57
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 97115.85 98768.74 100812.67
Cost for 24000 sqm= a+b+c+d+e 1068274.33 1086456.14 1108939.33
Rate per sqm= (a+b+c+d+e)/24000 44.51 45.27 46.21
Say 44.50 45.30 46.20
5.12 (ii) 4-6mm thickness (Type-II)
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Unit=sqm
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Taking output= 16000 sqm (80cum)
a) Labour
Mate day 0.240 0.240 0.240 310.00 74.40 74.40 74.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
b) Machinery
Machanical broom (2.1m sweeping width) hour 4.762 4.762 4.762 642.00 3057.20 3057.20 3057.20 PM23001
Air compressor 250 cfm hour 4.762 4.762 4.762 416.00 1980.99 1980.99 1980.99 PM15001
Mobile slurry seal equipment hour 4.386 4.386 4.386 3619.00 15872.93 15872.93 15872.93 PM41001
Front end loader
(i) 3.1 Cum Capacity hour 0.488 4255.00 2076.44 0.00 0.00 PM5001
(ii) 2.1 cum capacity hour 0.721 2588.00 0.00 1865.95 0.00 PM5002
(iii) 1 cum capacity hour 1.509 1594.00 0.00 0.00 2405.35 PM5003
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.488 2772.00 1352.74 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.721 2415.00 0.00 1741.22 0.00 PM6002
(iii) 10 cum capacity hour 1.509 2121.00 0.00 0.00 3200.59 PM6003
For transportation L1=1
(i) 18 cum capacity t.km 176XL1 5.94 1045.44 PM72001
(ii) 14 cum capacity t.km 176XL1 6.63 1166.88 PM73001
(iii) 10 cum capacity t.km 176XL1 8.08 1422.08 PM74001
Tipper for unloading time
(i) 18 cum capacity hour 4.386 2772.00 12157.99 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.386 2415.00 0.00 10592.19 0.00 PM6002
(iii) 10 cum capacity hour 4.386 2121.00 0.00 0.00 9302.71 PM6003
Water tanker (speed @20km/hr and return speed
@30km/hr and spreading speed @3 km/hr) L1=1
0.083XL1+ 1426.000 3160.016 PM11001
(i) 16kL capacity hour 2.133
0.111XL1+ 1252.000 3699.660 PM11002
(ii) 12 kL capacity hour 2.844
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
0.222XL1+ 907.000 5361.277 PM11003
(iii) 6 kL capacity hour 5.689

Pneumatic tyred roller with individual wheel load not hour 3.509 3.509 3.509 2338.00 8204.04 8204.04 8204.04 PM10001
exceeding 1.5 tonnes
c) Material
Residual binder @10.5 percent of mix = 60 X 2.2 X tonne 18.480 18.480 18.480 46509.00 859486.32 859486.32 859486.32 M-077
0.105
Fine aggregate 4.75mm and below 88 percent of total
mix, 80 X 2.2 X 0.88 =154.88 tonnes. Taking density cum 103.253 103.253 103.253 249.22 25732.71 25732.71 25732.71 M-029
1.5,= 154.88/1.5= 103.253cum
Filler @1.5 percent of total mix= 80X2.2X0.015 tonne 2.640 2.640 2.640 3637.51 9603.03 9603.03 9603.03 M-190
Cost of water kL 12.000 12.000 12.000 73.60 883.20 883.20 883.20 M-191
Total cost( Without O.H&C.P.) 946439.46 945712.72 948338.83
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 75715.16 94571.27 113800.66
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 102215.46 104028.40 106213.95
Cost for 16000 sqm= a+b+c+d+e 1124370.07 1144312.40 1168353.44
Rate per sqm= (a+b+c+d+e)/16000 70.27 71.52 73.02
Say 70.30 71.50 73.00
5.12 (iii) 6-8mm thickness (Type-III)
Unit=sqm
Taking output= 12000 sqm (84cum)
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
b) Machinery
Machanical broom (2.1m sweeping width) hour 3.571 3.571 3.571 642.00 2292.58 2292.58 2292.58 PM23001
Air compressor 250 cfm hour 3.571 3.571 3.571 416.00 1485.54 1485.54 1485.54 PM15001
Mobile slurry seal equipment hour 3.289 3.289 3.289 3619.00 11902.89 11902.89 11902.89 PM41001
Front end loader
(i) 3.1 Cum Capacity hour 0.512 4255.00 2178.56 0.00 0.00 PM5001
(ii) 2.1 cum capacity hour 0.757 2588.00 0.00 1959.12 0.00 PM5002
(iii) 1 cum capacity hour 1.585 1594.00 0.00 0.00 2526.49 PM5003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.512 2772.00 1419.26 0.00 0.00 PM6001
(ii) 14 cum capacity hour 0.757 2415.00 0.00 1828.16 0.00 PM6002
(iii) 10 cum capacity hour 1.585 2121.00 0.00 0.00 3361.79 PM6003
For transportation L1=1
(i) 18 cum capacity t.km 184.8XL1 5.94 1097.71 PM72001
(ii) 14 cum capacity t.km 184.8XL1 6.63 1225.22 PM73001
(iii) 10 cum capacity t.km 184.8XL1 8.08 1493.18 PM74001
Tipper for unloading time
(i) 18 cum capacity hour 3.289 2772.00 9117.11 0.00 0.00 PM6001
(ii) 14 cum capacity hour 3.289 2415.00 0.00 7942.94 0.00 PM6002
(iii) 10 cum capacity hour 3.289 2121.00 0.00 0.00 6975.97 PM6003
Water tanker (speed @20km/hr and return speed
@30km/hr and spreading speed @3 km/hr) L1=1
0.083XL1+ 1426.000 2399.96 PM11001
(i) 16kL capacity hour 1.600
0.111XL1+ 1252.000 2809.488 PM11002
(ii) 12 kL capacity hour 2.133
0.222XL1+ 907.000 4071.523 PM11003
(iii) 6 kL capacity hour 4.267
Pneumatic tyred roller with individual wheel load not hour 2.632 2.632 2.632 2338.00 6153.62 6153.62 6153.62 PM10001
exceeding 1.5 tonnes
c) Material
tonne 16.632 16.632 16.632 46509.00 773537.69 773537.69 773537.69 M-077
Residual binder @9 percent of mix = 84 X 2.2 X 0.09
Fine aggregate 2.36mm and below 89.5 percent of
total mix, 84 X 2.2 X 0.895 =165.396 tonnes. Taking cum 110.264 110.264 110.264 286.72 31614.89 31614.89 31614.89 M-019
density 1.5,= 165.396/1.5= 110.264 cum
Filler @1.5 percent of total mix= 84X2.2X0.015 tonne 2.772 2.772 2.772 3637.51 10083.18 10083.18 10083.18 M-190
Cost of water kL 12.000 12.000 12.000 73.60 883.20 883.20 883.20 M-191
Total cost( Without O.H&C.P.) 856296.99 855849.30 858513.34
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 68503.76 85584.93 103021.60
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 92480.07 94143.42 96153.49
Cost for 12000 sqm= a+b+c+d+e 1017280.82 1035577.66 1057688.43
Rate per sqm= (a+b+c+d+e)/12000 84.77 86.30 88.14
Say 84.80 86.30 88.10
Tack coat, if required to be provided, before laying
Note slurry seal may be measured and paid separately

5.13 519 Recycling of Bituminous Pavement with Central


Recycling Plant
Recycling pavement by cold milling of existing
bituminous layers, planning the surface after cold
milling, reclaiming excavated material to the extent
of 30 percent of the required quantity, hauling and
stock piling the reclaimed material near the central
recycling plant after carrying out necessary checks
and evaluation, adding fresh material including
rejuvenators as required , mixing in a hot mix plant,
transporting and laying at site and compacting tothe
required the grade , level and the thickness, all as
specified in clause 519.

Unit= cum
Taking output = 120 cum
A (i) Using by bituminous Macadam
Grading I
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width hour 9.117 7711.00 0.00 70301.19 0.00 PM47003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Milling machine with 1.2 metre drum width hour 9.877 5276.00 0.00 0.00 52111.05 PM47002
Bitumen pressure distributor( Spraying width hour 0.667 0.667 0.667 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m)
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 0.00 PM18001
(ii) HMP 160 TPh hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with Hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the pant
(i) 3.1 Cum Capacity hour 1.868 4255.00 7948.34 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 2.762 2588.00 0.00 7148.06 0.00 PM5002
(iii) 1 Cum capacity hour 5.775 1594.00 0.00 0.00 9205.35 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003
For transportation of dismantle material site to plant L1=1
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
Smooth steel wheeled tandem roller for static and hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen

A bitumen content is 3.3 percent bitumen weight of


mix. For reclaimed material, fresh material will be
required to extent of 60 percent of normal
requiement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and
balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne
tonne 1.639 1.639 1.639 43502.00 71299.78 71299.78 71299.78 M-074
@60 percent= 82.8 X 0.60 X 0.033=1.639

Bitumen required for fresh mix of 193.2 tonnes= tonne 6.376 6.376 6.376 43502.00 277368.75 277368.75 277368.75 M-074
193.2 tonnes= 193.2 X 0.033= 6.376
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
Weight of fresh aggregate in the mix= 193.2 X
0.967= 186.824 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 124.550 cum
Size wise requirement of fresh aggregates
* Grading I ( 40 mm nominal size)
37.5-25 mm 15 percent cum 18.683 18.683 18.683 524.49 9799.05 9799.05 9799.05 M-048
25-10 mm 45 percent cum 56.048 56.048 56.048 656.34 36786.54 36786.54 36786.54 M-045
10-5mm 25 percent cum 31.138 31.138 31.138 573.71 17864.18 17864.18 17864.18 M-039
5mm and below 15 percent cum 18.683 18.683 18.683 249.22 4656.18 4656.18 4656.18 M-029
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Credit for milled material for use (70 percent),
Considering 20 percent cost as salvage value of above cum 124.550 124.550 124.550 500.94 -12478.42 -12478.42 -12478.42 J=0.2*F*I
average material rate of aggregate
* Any one of the alternative may be adopted as per
approved design
Total cost( Without O.H&C.P.) 598544.82 609491.64 593857.84
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 47883.59 60949.16 71262.94
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 64642.84 67044.08 66512.08
Cost for 120 cum= a+b+c+d+e 711071.25 737484.88 731632.86
Rate per cum= (a+b+c+d+e)/120 5925.59 6145.71 6096.94
Say 5925.60 6145.70 6096.90
A (ii) Using by bituminous Macadam
Grading II
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width 9.117 7711.00 0.00 70301.19 0.00 PM47003
Milling machine with 1.2 metre drum width 9.877 5276.00 0.00 0.00 52111.05 PM47002
Bitumen pressure distributor( Spraying width hour 0.667 0.667 0.667 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m)
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 0.00 PM18001
(ii) HMP 160 TPh hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the pant
(i) 3.1 Cum Capacity hour 2.196 4255.00 9343.98 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 3.246 2588.00 0.00 8400.65 0.00 PM5002
(iii) 1 Cum capacity hour 6.787 1594.00 0.00 0.00 10818.48 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003
For transportation of dismantle material site to plant
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
Smooth steel wheeled tandem roller for static and hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small

A bitumen content is 3.4 percent bitumen weight of


mix. For reclaimed material, fresh material will be
required to extent of 60percent ofnormal requiement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne tonne 1.689 1.689 1.689 43502.00 73474.88 73474.88 73474.88 M-074
@60 percent= 82.8 X 0.60 X 0.33=1.639
Bitumen required fro fresh mix of 193.2 tonnes= tonne 6.569 6.569 6.569 43502.00 285764.64 285764.64 285764.64 M-074
193.2 tonnes= 193.2 X 0.033= 6.376
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
Weight of fresh aggregate in the mix= 193.2 X
0.966= 186.631 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 124.421 cum
Size wise requirement of fresh aggregates
* Grading II ( 19 mm nominal size)
25-10 mm 40 percent cum 49.768 49.768 49.768 656.34 32664.73 32664.73 32664.73 M-045
10-5mm 40 percent cum 49.768 49.768 49.768 573.71 28552.40 28552.40 28552.40 M-039
5mm and below 20 percent cum 24.884 24.884 24.884 249.22 6201.59 6201.59 6201.59 M-029
Credit for milled material for use (70 percent),
Considering 20 percent cost as salvage value of above cum 124.421 124.421 124.421 493.09 -12270.15 -12270.15 -12270.15 J=0.2*F*I
averagematerial rate of aggregate
* Any one of the alternative may be adopted as per
approved design
Total cost( Without O.H&C.P.) 609032.48 619836.25 604562.99
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 48722.60 61983.63 72547.56
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 65775.51 68181.99 67711.06
Cost for 120 cum= a+b+c+d+e 723530.59 750001.86 744821.61
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Rate per cum= (a+b+c+d+e)/120 6029.42 6250.02 6206.85
Say 6029.40 6250.00 6206.80
B
(i) Using by Dense Graded bituminous macadam
Grading I
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width 9.117 7711.00 0.00 70301.19 0.00 PM47003
Milling machine with 1.2 metre drum width 9.877 5276.00 0.00 0.00 52111.05 PM47002
Bitumen pressure distributor( Spraying width 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m) hour 0.667 0.667 0.667
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 0.00 PM18001
(ii) HMP 160 TPh hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the pant
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 3.1 Cum Capacity hour 1.840 4255.00 7829.20 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 2.300 2588.00 0.00 5952.40 0.00 PM5002
(iii) 1 Cum capacity hour 3.642 1594.00 0.00 0.00 5805.35 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003
For transportation of dismantle material site to plant L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
Smooth steel wheeled tandem roller for static and hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen
A bitumen content is 4 percent bitumen weight of
mix. For reclaimed material, fresh bitumen will be
required to extent of 60 percent of normal
requiement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed an d


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne tonne 1.987 1.987 1.987 43502.00 86438.47 86438.47 86438.47 M-074
@60 percent= 82.8 X 0.60 X 0.04=1.987
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Bitumen required fro fresh mix of 193.2 tonnes= tonne 7.728 7.728 7.728 43502.00 336183.46 336183.46 336183.46 M-074
193.2 tonnes= 193.2 X 0.04= 7.728
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
Weight of fresh aggregate in the mix= 193.2 X 0.96=
185.472 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 123.648 cum
Size wise requirement of fresh aggregates
* Grading I ( 40mm nominal size)
37.5-25mm 22 percent cum 27.203 27.203 27.203 524.49 14267.70 14267.70 14267.70 M-048
25-10mm 13 percent cum 16.074 16.074 16.074 656.34 10550.01 10550.01 10550.01 M-045
10-4.75mm 19 percent cum 23.493 23.493 23.493 573.71 13478.17 13478.17 13478.17 M-039
4.75mm and below 44 percent cum 54.405 54.405 54.405 234.89 12779.19 12779.19 12779.19 M-022
Filler @2 % of weight of aggregates tonnes 5.520 5.520 5.520 3637.51 20079.06 20079.06 20079.06 M-190
Credit for milled material for use (70 percent),
Considering 20 percent cost as salvage value of above cum 123.648 123.648 123.648 497.36 -12299.45 -12299.45 -12299.45 J=0.2*F*I
averagematerial rate of aggregate

* Any one of the alternative may be adopted as per


approved design
Total cost( Without O.H&C.P.) 674606.22 684476.52 666638.38
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 53968.50 68447.65 79996.61
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 72857.47 75292.42 74663.50
Cost for 120 cum= a+b+c+d+e 801432.19 828216.59 821298.49
Rate per cum= (a+b+c+d+e)/120 6678.60 6901.80 6844.15
Say 6678.60 6901.80 6844.20
B (ii) Using by Dense Graded bituminous macadam
Grading II
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width 9.117 7711.00 0.00 70301.19 0.00 PM47003
Milling machine with 1.2 metre drum width 9.877 5276.00 0.00 0.00 52111.05 PM47002
Bitumen pressure distributor( Spraying width 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m) hour 0.667 0.667 0.667
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the pant
(i) 3.1 Cum Capacity hour 2.127 4255.00 9050.39 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 3.145 2588.00 0.00 8139.26 0.00 PM5002
(iii) 1 Cum capacity hour 6.575 1594.00 0.00 0.00 10480.55 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003

For transportation of dismantle material site to plant L1=1


(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
Smooth steel wheeled tandem roller for static and hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen
A bitumen content is 4.5 percent bitumen weight of
mix. For reclaimed material, fresh material will be
required to extent of 60percent of normal requiement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne
tonne 2.236 2.236 2.236 43502.00 97270.47 97270.47 97270.47 M-074
@60 percent= 82.8 X 0.60 X 0.045=1.689
Bitumen required for fresh mix of 193.2 tonnes=
tonne 8.694 8.694 8.694 43502.00 378206.39 378206.39 378206.39 M-074
193.2 tonnes= 193.2 X 0.045= 6.569
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Weight of fresh aggregate in the mix= 193.2 X
0.955= 184.506 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 123.004 cum
Size wise requirement of fresh aggregates
* Grading II ( 19mm nominal size)
25-10mm 30percent cum 36.901 36.901 36.901 656.34 24219.60 24219.60 24219.60 M-045
10-5mm 28 percent cum 34.441 34.441 34.441 573.71 19759.15 19759.15 19759.15 M-039
5mm and below 40 percent cum 49.202 49.202 49.202 249.22 12262.12 12262.12 12262.12 M-029
Filler @2 % of weight of aggregates tonnes 5.520 5.520 5.520 3637.51 20079.06 20079.06 20079.06 M-190

Credit for milled material for use (70 percent),


Considering 20 percent cost as salvage value of above cum 123.004 123.004 123.004 493.09 -12130.41 -12130.41 -12130.41 J=0.2*F*I
averagematerial rate of aggregate

* Any one of the alternative may be adopted as per


approved design
Total cost( Without O.H&C.P.) 734017.18 744853.16 729503.36
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 58721.37 74485.32 87540.40
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 79273.86 81933.85 81704.38
Cost for 120 cum= a+b+c+d+e 872012.41 901272.32 898748.14
Rate per cum= (a+b+c+d+e)/120 7266.77 7510.60 7489.57
Say 7266.80 7510.60 7489.60
C (i) Using bituminous concrete
Grading I
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width hour 9.117 7711.00 0.00 70301.19 0.00 PM47003
Milling machine with 1.2 metre drum width hour 9.877 5276.00 0.00 0.00 52111.05 PM47002
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Bitumen pressure distributor( Spraying width 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m) hour 0.667 0.667 0.667
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the pant
(i) 3.1 Cum Capacity hour 2.112 4255.00 8986.56 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 3.122 2588.00 0.00 8079.74 0.00 PM5002
(iii) 1 Cum capacity hour 6.527 1594.00 0.00 0.00 10404.04 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003

For transportation of dismantle material site to plant L1=1


BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
Smooth steel wheeled tandem roller for static and
hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen
A bitumen content is 5.2 percent bitumen weight of
mix. For reclaimed material, fresh material will be
required to extent of 60 percent of normal
requiement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed an d


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne
tonne 2.583 2.583 2.583 43502.00 112365.67 112365.67 112365.67 M-074
@60 percent= 82.8 X 0.60 X 0.052=2.583
Bitumen required for fresh mix of 193.2 tonnes =
tonne 10.046 10.046 10.046 43502.00 437021.09 437021.09 437021.09 M-074
193.2 X 0.052= 10.046
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
Weight of fresh aggregate in the mix= 193.2 X
0.948= 183.54 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 122.102cum
Size wise requirement of fresh aggregates
* Grading I ( 19mm nominal size)
20-10mm 38percent cum 46.399 46.399 46.399 686.05 31832.03 31832.03 31832.03 M-044
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
10-5mm 17 percent cum 20.757 20.757 20.757 573.71 11908.50 11908.50 11908.50 M-039
5mm and below 43 percent cum 52.504 52.504 52.504 249.22 13085.05 13085.05 13085.05 M-029
Filler @2 % of weight of aggregates tonnes 5.520 5.520 5.520 3637.51 20079.06 20079.06 20079.06 M-190

Credit for milled material for use (70 percent),


cum 122.102 122.102 122.102 502.99 -12283.30 -12283.30 -12283.30 J=0.2*F*I
Considering 20 percent cost as salvage value of above
averagematerial rate of aggregate
* Any one of the alternative may be adopted as per
approved design
Total cost( Without O.H&C.P.) 808295.07 819135.35 803768.56
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 64663.61 81913.53 96452.23
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 87295.87 90104.89 90022.08
Cost for 120 cum= a+b+c+d+e 960254.55 991153.77 990242.87
Rate per cum= (a+b+c+d+e)/120 8002.12 8259.61 8252.02
Say 8002.10 8259.60 8252.00
C (ii) Using by bituminous concrete
Grading II
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 3.000 3.000 3.000 370.00 1110.00 1110.00 1110.00 L-15
b) Machinery
Milling machine
Milling machine with 2 metre drum width hour 5.926 11192.00 66323.79 0.00 0.00 PM47004
Milling machine with 1.3 meter Drum width hour 9.117 7711.00 0.00 70301.19 0.00 PM47003
Milling machine with 1.2 metre drum width hour 9.877 5276.00 0.00 0.00 52111.05 PM47002
Bitumen pressure distributor( Spraying width hour 0.667 0.667 0.667 1645.00 1097.22 1097.22 1097.22 PM24001
4.5m)
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14810.00 27250.40 0.00 PM18001
(ii) HMP 160 TPH hour 2.300 10450.00 0.00 24035.00 0.00 PM18002
(iii) HMP 120 TPH hour 3.067 8309.00 0.00 0.00 25483.70 PM18003
Mechanical broom (2.1 m sweeping width) hour 0.571 0.571 0.571 642.00 366.58 366.58 366.58 PM23001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Air compressor 250 cfm hour 0.571 0.571 0.571 416.00 237.54 237.54 237.54 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 1.840 8710.00 16026.40 0.00 0.00 PM29001
(ii)Paver (240HP) hour 2.300 8710.00 0.00 20033.00 0.00 PM29001
(iii) Paver (174 HP) hour 3.067 6808.00 0.00 0.00 20880.14 PM29002
Electric generator
(i) 500 kVA hour 1.840 9075.00 16698.00 0.00 0.00 PM22002
(ii) 400 KVA hour 2.300 7303.00 0.00 16796.90 0.00 PM22003
(iii) 250 KVA hour 3.067 4359.00 0.00 0.00 13369.05 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.107 4255.00 8965.29 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 3.115 2588.00 0.00 8061.62 0.00 PM5002
(iii) 1 Cum capacity hour 6.513 1594.00 0.00 0.00 10381.72 PM5003
Tipper
For transportation plant to site L1=1
(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2772.00 10200.96 0.00 0.00 PM6001
(ii) 14 cum capacity hour 4.600 2415.00 0.00 11109.00 0.00 PM6002
(iii) 10 cum capacity hour 6.133 2121.00 0.00 0.00 13008.09 PM6003

For transportation of dismantle material site to plant L1=1


(i) 18 cum capacity t.km 276XL1 5.94 1639.44 PM72001
(ii) 14 cum capacity t.km 276XL1 6.63 1829.88 PM73001
(iii) 10 cum capacity t.km 276XL1 8.08 2230.08 PM74001
Tipper for loading time
(i) 18 cum capacity hour 5.926 2772.00 16426.87 0.00 0.00 PM6001
(ii) 14 cum capacity hour 9.117 2415.00 0.00 22017.56 0.00 PM6002
(iii) 10 cum capacity hour 9.877 2121.00 0.00 0.00 20949.12 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Smooth steel wheeled tandem roller for static and hour 10.619 10.619 10.619 2357.00 25028.98 25028.98 25028.98 PM9001
vibratory passaes
c) Material
i) Bitumen
A bitumen content is 5.4 percent bitumen weight of
mix. For reclaimed material, fresh material will be
required to extent of 60 percent ofnormal requiement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne tonne 2.683 2.683 2.683 43502.00 116715.87 116715.87 116715.87 M-074
@60 percent= 82.8 X 0.60 X 0.054=2.683
Bitumen required for fresh mix of 193.2 tonnes = tonne 10.433 10.433 10.433 43502.00 453856.37 453856.37 453856.37 M-074
193.2 X 0.054= 10.433
ii) Aggregates
Percentage of mix requiring fresh aggregates- 70
percent
Weight of fresh mix= 276 X 0.70= 193.2 tonne
Weight of fresh aggregate in the mix= 193.2 X
0.946= 182.767 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 121.845cum
Size wise requirement of fresh aggregates
* Grading II( 13mm nominal size)
13.2-10mm 21percent cum 25.587 25.587 25.587 686.05 17553.96 17553.96 17553.96 M-043
10-5mm 17 percent cum 20.714 20.714 20.714 573.71 11883.83 11883.83 11883.83 M-039
5mm and below 60 percent cum 73.107 73.107 73.107 249.22 18219.73 18219.73 18219.73 M-029
Filler @2 % of weight of aggregates tonnes 5.520 5.520 5.520 3637.51 20079.06 20079.06 20079.06 M-190
Credit for milled material for use (70 percent),
Considering 20 percent cost as salvage value of above cum 121.845 121.845 121.845 502.99 -12257.44 -12257.44 -12257.44 J=0.2*F*I
averagematerial rate of aggregate
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
* Any one of the alternative may be adopted as per
approved design
Total cost( Without O.H&C.P.) 820317.06 831160.50 815789.51
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 65625.37 83116.05 97894.74
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 88594.24 91427.65 91368.43
Cost for 120 cum= a+b+c+d+e 974536.67 1005704.20 1005052.68
Rate per cum= (a+b+c+d+e)/120 8121.14 8380.87 8375.44
Say 8121.10 8380.90 8375.40
Providing and applying low viscosity bitumen
emulsion for sealing cracks less than 3mm wide or
5.14 513 incipient fretting or disintegration in an existing
bituminous surfacing

Unit=sqm
Taking output=10500sqm
(i) a) Labour
Mate day 0.120 0.120 0.120 310.00 37.20 37.20 37.20 L-12
Mazdoor day 3.000 3.000 3.000 292.00 876.00 876.00 876.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 3.125 3.125 3.125 642.00 2006.25 2006.25 2006.25 PM23001
Air compressor 250cfm hour 3.125 3.125 3.125 416.00 1300.00 1300.00 1300.00 PM15001
tonne 2.917 2.917 2.917 1645.00 4798.47 4798.47 4798.47 PM24001
Bitumen pressure distributor ( spraying width 4.5m)
c) Material
Bitumn emulsion @ 0.75 kg/sqm tonne 7.880 7.880 7.880 46509.00 366490.92 366490.92 366490.92 M-077
Total cost( Without O.H&C.P.) 375508.84 375508.84 375508.84
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 30040.71 37550.88 45061.06
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 40554.95 41305.97 42056.99
Cost for 10500sqm= a+b+c+d+e 446104.50 454365.69 462626.88
Rate per sqm= (a+b+c+d+e)/10500 42.49 43.27 44.06
Say 42.50 43.30 44.10

(ii) 1. In case it is decided by the engineer to blind the fog


spray, the following may be added
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor for precoating of grit day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
b) Material
Crushed stone grit 3mm size @3.75kg / sqm cum 26.250 26.250 26.250 249.22 6542.03 6542.03 6542.03 M-029
Bitumen emulsion for precoating grit @2 percent of tonne 0.790 0.790 0.790 46509.00 36742.11 36742.11 36742.11 M-077
grit, 39.38 X 0.02
Cost for 10500 sqm= a+b 44501.74 44501.74 44501.74
Rate per sqm= (a+b)/10500 4.24 4.24 4.24
Say 4.20 4.20 4.20
5.15 518 Bituminous Cold mix (including gravel emulsion)

Providing laying and rolling of bituminous cold mix


on prepared base consisting of a mixture of unheated
mineral aggregate and emulsified or cutback bitumen,
including mixing in a plant of suitable type and
capacity , transporting , laying compacting and
finishing to specified grades and levels.

Unit=cum
Taking outpur=205cum
Using bitumen emulsion and 9.5mm or 13.2mm
(i) size aggregate

Composition of mix (450 tonne) is assumed to be as


under-:
Bitumen emulsion 8 percent by weight of total mix
Filler 2 percent
Total aggregates 90 percent
Proportion of aggregates
19mm to 9.5 mm 25 percent
9.5mm to 6mm 29 percent
6mm to 0.075mm 36 percent
a) Labour
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Mechanical broom (2.1 m sweeping width) hour 1.743 1.743 1.743 642.00 1119.01 1119.01 1119.01 PM23001
Air compressor 250 cfm hour 1.743 1.743 1.743 416.00 725.09 725.09 725.09 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii)Paver (240HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.852 4255.00 20645.26 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 6.923 2588.00 0.00 17916.72 0.00 PM5002
(iii) 1 Cum capacity hour 15.081 1594.00 0.00 0.00 24039.11 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Smooth steel wheeled tandem roller for static and hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passaes
Pneumatic Tyre roller hour 2.569 3.000 4.000 2338.00 6006.32 7014.00 9352.00 PM10001
c) Material
Bitumen emulsion @8percent tonne 36.000 36.000 36.000 46509.00 1674324.00 1674324.00 1674324.00 M-077
Filler (lime) @ 2percent tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Aggregates size 19 to 9.5mm- 450 X 0.25 X1/1.5 cum 75.000 75.000 75.000 686.05 51453.75 51453.75 51453.75 M-044
Aggregates size 9.5 to 6mm- 450 X 0.29 X 1/1.5 cum 87.000 87.000 87.000 573.71 49912.77 49912.77 49912.77 M-039
Aggregates size 6 to 0.075mm- 450 X 0.36 X 1/1.5 cum 108.000 108.000 108.000 249.22 26915.76 26915.76 26915.76 M-029
Total cost( Without O.H&C.P.) 2027730.68 2029252.08 2039606.22
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 162218.45 202925.21 244752.75
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 218994.91 223217.73 228435.90
Cost for 205 cum= a+b+c+d+e 2408944.05 2455395.01 2512794.86
Rate per cum= (a+b+c+d+e)/205 11750.95 11977.54 12257.54
Say 11750.90 11977.50 12257.50
(Applicable to cases I to IV)
Note 1. Density of aggregates has been assumed 1.5gms/cc

2. Tack coat where provided will be measured and


paid separately
(ii) Using bitumen emulsion and 19mm or 26.5mm
nominal size aggregate
Compostion of mix ( 450 tonne ) is assumed to be as
under-:
Bitumen emulsion - 8 percent
Filler - 2 percent
Total aggregates - 90 percent
Proportion of aggregates
37.5mm to 19 mm 25 percent
19mm to 6mm 30percent
6mm to 0.075mm 35 percent
a) Labour
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Mechanical broom (2.1 m sweeping width) hour 1.743 1.743 1.743 642.00 1119.01 1119.01 1119.01 PM23001
Air compressor 250 cfm hour 1.743 1.743 1.743 416.00 725.09 725.09 725.09 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii)Paver (240HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.852 4255.00 20645.26 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 6.923 2588.00 0.00 17916.72 0.00 PM5002
(iii) 1 Cum capacity hour 15.081 1594.00 0.00 0.00 24039.11 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Smooth steel wheeled tandem roller for static and
hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passaes
Pneumatic Tyre roller hour 2.569 3.000 4.000 2338.00 6006.32 7014.00 9352.00 PM47001
c) Material
Bitumen emulsion @8percent tonne 36.000 36.000 36.000 46509.00 1674324.00 1674324.00 1674324.00 M-077
Filler (lime) @ 2percent tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190

cum 75.000 75.000 75.000 524.49 39336.75 39336.75 39336.75 M-047


Aggregates size 37.5 to 19mm- 450 X 0.25 X1/1.5
Aggregates size 19 to 6mm- 450 X 0.3 X 1/1.5 cum 90.000 90.000 90.000 572.92 51562.80 51562.80 51562.80 M-046

Aggregates size 6 to 0.075mm- 450 X 0.35 X 1/1.5 cum 105.000 105.000 105.000 249.22 26168.10 26168.10 26168.10 M-029

Total cost( Without O.H&C.P.) 2016516.05 2018037.45 2028391.59


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 161321.28 201803.74 243406.99
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 217783.73 221984.12 227179.86
Cost for 205 cum= a+b+c+d+e 2395621.07 2441825.31 2498978.43
Rate per cum= (a+b+c+d+e)/205 11685.96 11911.34 12190.14
Say 11686.00 11911.30 12190.10
Note 1. Density of aggregates has been assumed 1.5gms/cc

2. Tack coat where provided will be measured and


paid separately

Using cutback bitumen and 9.5mm or 13.2mm


5.15 (iii) nominal size aggregate
Compostion of mix ( 450 tonne ) is assumed to be as
under-:
Bitumen emulsion - 5 percent
Filler - 2 percent
Total aggregates - 93 percent
Proportion of aggregates
19mm to 9.5mm 26 percent
9.5mm to 6mm 31percent
6mm to 0.075mm 36 percent
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Mechanical broom (2.1 m sweeping width) hour 1.743 1.743 1.743 642.00 1119.01 1119.01 1119.01 PM23001
Air compressor 250 cfm hour 1.743 1.743 1.743 416.00 725.09 725.09 725.09 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii)Paver (240HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.009 4255.00 21313.30 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.154 2588.00 0.00 18514.55 0.00 PM5002
(iii) 1 Cum capacity hour 15.568 1594.00 0.00 0.00 24815.39 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003

Smooth steel wheeled tandem roller for static and


hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passaes
Pneumatic tyre roller hour 2.569 2.569 2.569 2338.00 6006.32 6006.32 6006.32 PM10001
c) Material
Cutback bitumen @ 5percent tonne 22.500 22.500 22.500 43502.00 978795.00 978795.00 978795.00 M-076
Filler (lime) @ 2percent tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Aggregates size 19 to 9.5mm- 450 X 0.26 X1/1.5 cum 78.000 78.000 78.000 686.05 53511.90 53511.90 53511.90 M-044
Aggregates size 9.5 to 6 mm- 450 X 0.31 X 1/1.5 cum 93.000 93.000 93.000 573.71 53355.03 53355.03 53355.03 M-039

Aggregates size 6 to 0.075mm- 450 X 0.36 X 1/1.5 cum 108.000 108.000 108.000 249.22 26915.76 26915.76 26915.76 M-029

Total cost( Without O.H&C.P.) 1338370.13 1338813.64 1347008.23


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 107069.61 133881.36 161640.99
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 144543.97 147269.50 150864.92
Cost for 205 cum= a+b+c+d+e 1589983.71 1619964.50 1659514.13
Rate per cum= (a+b+c+d+e)/205 7756.02 7902.27 8095.19
Say 7756.00 7902.30 8095.20
Note 1. Density of aggregates has been assumed 1.5gms/cc

2. Tack coat where provided will be measured and


paid separately

5.15 (iv) Using cutback bitumen and 19mm or 26.5mm


nominal size aggregate

Compostion of mix ( 450 tonne ) is assumed to be as


under-:
Bitumen emulsion - 5 percent
Filler - 2 percent
Total aggregates - 93 percent
Proportion of aggregates
37.5mm to 19mm 25 percent
19mm to 6mm 30 percent
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
6mm tp 0.075mm 38 percent
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Mechanical broom (2.1 m sweeping width) hour 1.743 1.743 1.743 642.00 1119.01 1119.01 1119.01 PM23001
Air compressor 250 cfm hour 1.743 1.743 1.743 416.00 725.09 725.09 725.09 PM15001
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii)Paver (240HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.009 4255.00 21313.30 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.154 2588.00 0.00 18514.55 0.00 PM5002
(iii) 1 Cum capacity hour 15.568 1594.00 0.00 0.00 24815.39 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
Smooth steel wheeled tandem roller for static and hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passaes
Pneumatic tyre roller hour 2.569 2.569 2.569 2338.00 6006.32 6006.32 6006.32 PM10001
c) Material
Cutback bitumen @ 5percent tonne 22.500 22.500 22.500 43502.00 978795.00 978795.00 978795.00 M-076
Filler (lime) @ 2percent tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190

Aggregates size 37.5 to 19mm- 450 X 0.25 X1/1.5 cum 75.000 75.000 75.000 524.49 39336.75 39336.75 39336.75 M-047

Aggregates size 19 to 6 mm- 450 X 0.3 X 1/1.5 cum 90.000 90.000 90.000 572.92 51562.80 51562.80 51562.80 M-046
Aggregates size 6 to 0.075mm- 450 X 0.38 X 1/1.5 cum 114.000 114.000 114.000 249.22 28411.08 28411.08 28411.08 M-029

Total cost( Without O.H&C.P.) 1323898.07 1324341.58 1332536.17


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 105911.85 132434.16 159904.34
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 142980.99 145677.57 149244.05
Cost for 205 cum= a+b+c+d+e 1572790.90 1602453.31 1641684.56
Rate per cum= (a+b+c+d+e)/205 7672.15 7816.85 8008.22
Say 7672.20 7816.80 8008.20
Note 1. Density of aggregates has been assumed 1.5gms/cc

2. Tack coat where provided will be measured and


paid separately

5.16 506 Sand asphalt /base course


Providing , laying and rolling sand-asphalt base
course compose of sand, mineral filler and
bitumnious binder on a prepared subgrade or sub-base
to the lines, levels, grades and cross sections as per
the drawing including mixing in a plant of suitable
type and capacity, transporting, laying, compacting
and finishing.
Unit= cum
Taking output=205 cum
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Paver finsher hydrostatic with sensor control
compatible with hot mix plant
(i) Paver (240HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii)Paver (240HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.044 4255.00 21462.22 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.441 2588.00 0.00 19257.31 0.00 PM5002
(iii) 1 Cum capacity hour 15.664 1594.00 0.00 0.00 24968.42 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Smooth steel wheeled tandem roller for static and
hour 18.141 18.141 18.141 2357.00 42758.34 42758.34 42758.34 PM9001
vibratory passaes
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight 450 tonne
Bitumen 5 percent
Filler 2 percent
Sand of size 4.75 to 0.075mm 93 percent
Bitumen @ 5 percent tonne 22.500 22.500 22.500 43502.00 978795.00 978795.00 978795.00 M-074
Filler (lime) @ 2 percent tonne 9.000 9.000 9.000 3637.51 32737.59 32737.59 32737.59 M-190
Sand of size 4.75 to 0.075mm - 450 X 0.93 X 1/1.5 cum 288.620 288.620 288.620 175.80 50739.40 50739.40 50739.40 M-004
Total cost( Without O.H&C.P.) 1247625.34 1248662.68 1256267.54
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 99810.03 124866.27 150752.10
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 134743.54 137352.89 140701.96
Cost for 205 cum= a+b+c+d+e 1482178.91 1510881.84 1547721.61
Rate per cum = (a+b+c+d+e)/205 7230.14 7370.16 7549.86
Note:- Tack coat will be measured and paid separately Say 7230.10 7370.20 7549.90

5.17 517 (i) Crack prevention courses


Stress absorbing membrane (SAM) crack width
less than 6mm
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providng and laying of a stress absorbing membrane
over a cracked road surface, with crack width below 6
mm afer cleaning with a mechanical broom, using
modified binder complying with IRC:SP: 53, sprayed
at the rate of 9 kg per 10 sqm and spreading 5.6 mm
crushed stone aggregates @ 0.11 cum per 10 sqm
with hydraulic chip spreader, sweeping the surface
for uniform spread of aggregates and surface finished
to conform to clause 902.

Unit= sqm
Taking output= 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
B) Machinery
Mechanical broom (2.1 m sweeping width) hour 3.125 3.125 3.125 642.00 2006.25 2006.25 2006.25 PM23001
Air compressor 250cfm hour 3.125 3.125 3.125 416.00 1300.00 1300.00 1300.00 PM15001
Bitumen pressue distributor (spraying widh 4.5m) hour 2.917 2.917 2.917 1645.00 4798.47 4798.47 4798.47 PM24001
Hydraulic chip spreader hour 5.397 5.397 5.397 2146.00 11581.96 11581.96 11581.96 PM32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 901.00 4862.70 4862.70 4862.70 PM8001
c) Material
Modified binder tonne 9.450 9.450 9.450 44632.00 421772.40 421772.40 421772.40 M-078
Crushed stone aggregates 5.6mm size cum 105.000 105.000 105.000 249.22 26168.10 26168.10 26168.10 M-029
Total cost( Without O.H&C.P.) 473707.47 473707.47 473707.47
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 37896.60 47370.75 56844.90
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 51160.41 52107.82 53055.24
Cost for 10500 sqm= a+b+c+d+e 562764.48 573186.04 583607.61
Rate per sqm= (a+b+c+d+e)/10500 53.60 54.59 55.58
Say 53.60 54.60 55.60
5.17 (ii) Stress absorbing membrane (SAM) crack width
6mm to 9mm
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providng and laying of a stress absorbing membrane
over a cracked road surface, with crack width 6 mm
to 9mm afer cleaning with a mechanical broom, using
modified binder complying with IRC:SP: 53, sprayed
at the rate of 11 kg per 10 sqm and spreading 11.2
mm crushed stone aggregates @ 0.12 cum per 10 sqm
with hydraulic chip spreader, sweeping the surface
for uniform spread of aggregates and surface finished
to conform to clause 902.

Unit= sqm
Taking output= 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
B) Machinery
Mechanical broom (2.1 m sweeping width) hour 3.125 3.125 3.125 642.00 2006.25 2006.25 2006.25 PM23001
Air compressor 250cfm hour 3.125 3.125 3.125 416.00 1300.00 1300.00 1300.00 PM15001
Bitumen pressure distributor (spraying widh 4.5m) hour 2.917 2.917 2.917 1645.00 4798.47 4798.47 4798.47 PM24001

Hydraulic chip spreader hour 5.397 5.397 5.397 2146.00 11581.96 11581.96 11581.96 PM32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 901.00 4862.70 4862.70 4862.70 PM8001
c) Material
Modified binder tonne 11.550 11.550 11.550 44632.00 515499.60 515499.60 515499.60 M-078
Crushed stone aggregates 11.2mm size cum 105.000 105.000 105.000 392.53 41215.65 41215.65 41215.65 M-040
Total cost( Without O.H&C.P.) 582482.22 582482.22 582482.22
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 46598.58 58248.22 69897.87
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 62908.08 64073.04 65238.01
Cost for 10500 sqm= a+b+c+d+e 691988.88 704803.49 717618.10
Rate per sqm= (a+b+c+d+e)/10500 Say 65.90 67.12 68.34
65.90 67.10 68.30
Stress absorbing membrane (SAM) crack width
(iii) above 9 mm and cracked area above 50 percent
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providng and laying of a stress absorbing membrane
over a cracked road surface, with crack width above
9mm and cracked area above 50 percent after
cleaning with a mechanical broom, using modified
binder complying with IRC:SP: 53, sprayed at the
rate of 15 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm
with hydraulic chip spreader, sweeping the surface
for uniform spread of aggregates and surface finished
to conform to clause 902.

Unit= sqm
Taking output= 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 310.00 49.60 49.60 49.60 L-12
Mazdoor day 4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00 L-13
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
B) Machinery
Mechanical broom (2.1 m sweeping width) hour 3.125 3.125 3.125 642.00 2006.25 2006.25 2006.25 PM23001
Air compressor 250cfm hour 3.125 3.125 3.125 416.00 1300.00 1300.00 1300.00 PM15001

Bitumen pressure distributor (spraying widh 4.5m) hour 2.917 2.917 2.917 1645.00 4798.47 4798.47 4798.47 PM24001

Hydraulic chip spreader hour 5.397 5.397 5.397 2146.00 11581.96 11581.96 11581.96 PM32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 901.00 4862.70 4862.70 4862.70 PM8001
c) Material
Modified binder tonne 15.750 15.750 15.750 44632.00 702954.00 702954.00 702954.00 M-078
Crushed stone aggregates 11.2mm size cum 126.000 126.000 126.000 392.53 49458.78 49458.78 49458.78 M-040
Total cost( Without O.H&C.P.) 778919.75 778919.75 778919.75
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 62313.58 77891.98 93470.37
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 84123.33 85681.17 87239.01
Cost for 10500 sqm= a+b+c+d+e 925356.67 942492.90 959629.14
Rate per sqm= (a+b+c+d+e)/10500 88.13 89.76 91.39
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Say 88.10 89.80 91.40
In case 2nd coat is also required to be provided,
Note material provided for the 2nd coat shall be as per
Table 500-43

5.17 (iv) Case IV: bitumen impregnated geotextile

Providing and laying of premix of crushed stone


aggregates and emulsion binder, mixed in a batch
type cold mixing plant, laid over prepared surface, by
paver finisher, rolled with a pneumatic tyred roller
initially and finished with a smooth steel wheel roller,
all as per clause 518.3

Unit= sqm
Taking output= 10500 sqm
a) Labour
Mate day 0.280 0.280 0.280 310.00 86.80 86.80 86.80 L-12
Mazdoor day 5.000 5.000 5.000 292.00 1460.00 1460.00 1460.00 L-13
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00 L-15
B) Machinery
Mechanical broom (2.1 m sweeping width) hour 1.042 1.042 1.042 642.00 668.96 668.96 668.96 PM23001
Air compressor 250cfm hour 1.042 1.042 1.042 416.00 433.47 433.47 433.47 PM15001
Bitumen pressure distributor (spraying widh 4.5m) hour 0.972 0.972 0.972 1645.00 1598.94 1598.94 1598.94 PM24001

Pneumatic roller hour 2.000 2.000 2.000 2338.00 4676.00 4676.00 4676.00 PM10001
c) Material
Paving grade bitumen of 80-100 penetration @1.05 tonne 3.680 3.680 3.680 42702.00 157143.36 157143.36 157143.36 M-075
kg per sqm
Geotextile including 10 percent for overlaps sqm 3850.000 3850.000 3850.000 82.17 316354.50 316354.50 316354.50 M-108
Total cost( Without O.H&C.P.) 483162.04 483162.04 483162.04
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 38652.96 48316.20 57979.44
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 52181.50 53147.82 54114.15
Cost for 3500 sqm= a+b+c+d+e 573996.50 584626.06 595255.63
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Rate per sqm= (a+b+c+d+e)/3500 164.00 167.04 170.07
Say 164.00 167.00 170.10
Note As bitumen overlay construction shall follw closely
the fabric placement on the same day, an output of
3500 sqm only has been considered for the analysis
which will cover a length of 500m, of 7 m wide
carriageway. This can be conveniently overlaide by a
bituminous course in a day

5.18 518.3 Recipe Cold mix


Providing and laying of premix crushed stone
aggregates and emulsion binder, mixed in a batch
type cold mixing plant, laid over prepared surface, by
paver finisher, rolled with a pneumatic tyred rolle
initially and finished with a smooth steel wheel roller,
all as per clause 518.3

Unit= cum
Taking output=205cum
(i) 75mm thickness
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.400 4255.00 22977.00 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 8.027 2588.00 0.00 20773.88 0.00 PM5002
(iii) 1 Cum capacity hour 16.500 1594.00 0.00 0.00 26301.00 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibratory passaes
Pneumatic tyre roller hour 2.400 3.000 4.000 2338.00 5611.20 7014.00 9352.00 PM10001
Water tanker (speed @20km/hr and return speed
@30km/hr and spreading speed @3.0 km.hr) L1=1
0.42XL1+0. 1426.000 858.452 PM11001
(i) 16 KL capacity hour 182
0.056XL1+ 1252.000 374.348 PM11002
(ii) 12 KL capacity hour 0.243
0.111XL1+ 907.000 541.479 PM11003
(iii) 6 KL capacity hour 0.486
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 20.250 20.250 46509.00 941807.25 941807.25 941807.25 M-077
Crushed stone aggregates 40mm nominal size cum 297.000 297.000 297.000 486.92 144615.24 144615.24 144615.24 M-054
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Cost ofwater KL 6.000 6.000 6.000 73.60 441.60 441.60 441.60 M-191
Total cost( Without O.H&C.P.) 1265329.21 1267287.03 1277213.04
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 101226.34 126728.70 153265.56
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 136655.55 139401.57 143047.86
Cost for 205 cum= a+b+c+d+e 1503211.10 1533417.31 1573526.46
Rate per cum= (a+b+c+d+e)/205 7332.74 7480.08 7675.74
Note (Case (i) to (iii)) Say 7332.70 7480.10 7675.70
1. These mixes are considered suitable for minor
repair work and temporary road surface
improvements.
2. In case concrete mixtures are required to be used
for mixing, a number of these will be needed to match
the capacity of road rollers.

3. Tack coat, where provided, will be meaured and


paid separately.

5.18 (ii) 40mm thickness


a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.125 4255.00 21806.88 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.553 2588.00 0.00 19547.16 0.00 PM5002
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
(iii) 1 Cum capacity hour 15.944 1594.00 0.00 0.00 25414.74 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibratory passaes
Pneumatic tyre roller hour 2.400 3.000 4.000 2338.00 5611.20 7014.00 9352.00 PM10001
Water tanker (speed @20km/hr and return speed
@30km/hr and spreading speed @3.0 km.hr) L1=1
0.042XL1+ 1426.000 547.584 PM11001
(i) 16 KL capacity hour 0.342
0.056XL1+ 1252.000 641.024 PM11002
(ii) 12 KL capacity hour 0.456
0.111XL1+ 907.000 926.954 PM11003
(iii) 6 KL capacity hour 0.911
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 31.500 31.500 46509.00 1465033.50 1465033.50 1465033.50 M-077
Crushed stone aggregates 14mm nominal size cum 287.000 287.000 287.000 686.05 196896.35 196896.35 196896.35 M-051
Cost of water KL 6.000 6.000 6.000 73.60 441.60 441.60 441.60 M-191
Total cost( Without O.H&C.P.) 1839355.58 1841834.36 1852219.61
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 147148.45 184183.44 222266.35
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 198650.40 202601.78 207448.60
Cost for 205 cum= a+b+c+d+e 2185154.42 2228619.57 2281934.56
Rate per cum= (a+b+c+d+e)/205 10659.29 10871.31 11131.39
Say 10659.30 10871.30 11131.40
5.18 (iii) 25mm thickness
a) Labour
Mate day 0.480 0.480 0.480 310.00 148.80 148.80 148.80 L-12
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14810.00 44430.00 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.750 10450.00 0.00 39187.50 0.00 PM18002
(iii) HMP 120 TPH hour 5.000 8309.00 0.00 0.00 41545.00 PM18003
Electric generator
(i) 500 kVA hour 3.000 9075.00 27225.00 0.00 0.00 PM22002
(ii) 400 KVA hour 3.750 7303.00 0.00 27386.25 0.00 PM22003
(iii) 250 KVA hour 5.000 4359.00 0.00 0.00 21795.00 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.576 4255.00 19470.88 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 6.750 2588.00 0.00 17469.00 0.00 PM5002
(iii) 1 Cum capacity hour 14.211 1594.00 0.00 0.00 22652.33 PM5003
Tipper
For transportation L1=1
(i) 18 cum capacity t.km 450XL1 5.94 2673.00 PM72001
(ii) 14 cum capacity t.km 450XL1 6.63 2983.50 PM73001
(iii) 10 cum capacity t.km 450XL1 8.08 3636.00 PM74001
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2772.00 16632.00 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.500 2415.00 0.00 18112.50 0.00 PM6002
(iii) 10 cum capacity hour 10.000 2121.00 0.00 0.00 21210.00 PM6003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.000 8710.00 26130.00 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.750 8710.00 0.00 32662.50 0.00 PM29001
(iii) Paver (174 HP) hour 5.000 6808.00 0.00 0.00 34040.00 PM29002
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibratory passaes
Pneumatic tyre roller hour 2.400 3.000 4.000 2338.00 5611.20 7014.00 9352.00 PM10001

Water tanker (speed @20km/hr and return speed


@30km/hr and spreading speed @3.0 km.hr) L1=1
0.042XL1+
(i) 16 KL capacity hour 1426.000 839.914 PM11001
0.547
0.056XL1+
(ii) 12 KL capacity hour 1252.000 982.820 PM11002
0.729
0.111XL1+
(iii) 6 KL capacity hour 907.000 1423.083 PM11003
1.458
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 38.250 38.250 46509.00 1778969.25 1778969.25 1778969.25 M-077
Crushed stone aggregates 6mm nominal size cum 270.000 270.000 270.000 454.98 122844.60 122844.60 122844.60 M-049
Cost of water KL 6.000 6.000 6.000 73.60 441.60 441.60 441.60 M-191
Total cost( Without O.H&C.P.) 2077195.91 2079981.99 2089837.33
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 166175.67 207998.20 250780.48
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 224337.16 228798.02 234061.78
Cost for 205 cum= a+b+c+d+e 2467708.74 2516778.20 2574679.60
Rate per cum= (a+b+c+d+e)/205 12037.60 12276.97 12559.41
Say 12037.60 12277.00 12559.40
Sugges Bituminous Concrete Grading 1 using waste
5.19 A
tive plastic
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providing and laying bituminous concrete with higher
capacity batch typehot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.2 percent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
the required grade, level and alignment , rolling with
smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.400 0.400 0.400 310.00 124.00 124.00 124.00 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14810.00 44504.05 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.756 10450.00 0.00 39250.20 0.00 PM18002
(iii) HMP 120 TPH hour 5.008 8309.00 0.00 0.00 41611.47 PM18003
Mechanical broom ( 2.1m sweeping width) hour 1.137 1.137 1.137 642.00 729.95 729.95 729.95 PM23001
Air compressor 250cfm hour 1.137 1.137 1.137 416.00 472.99 472.99 472.99 PM15001
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.005 8710.00 26173.55 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.756 8710.00 0.00 32714.76 0.00 PM29001
(iii) Paver (174 HP) hour 5.008 6808.00 0.00 0.00 34094.46 PM29002
Electric generator
(i) 500 kVA hour 3.005 9075.00 27270.38 0.00 0.00 PM22002
(ii) 400 KVA hour 3.756 7303.00 0.00 27430.07 0.00 PM22003
(iii) 250 KVA hour 5.008 4359.00 0.00 0.00 21829.87 PM22004
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 4255.00 21606.89 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.506 2588.00 0.00 19425.53 0.00 PM5002
(iii) 1 Cum capacity hour 15.694 1594.00 0.00 0.00 25016.24 PM5003
Tipper
For transportation mix L1=1
(i) 18 cum capacity t.km 450.76XL1 5.94 2677.51 PM72001
(ii) 14 cum capacity t.km 450.76XL1 6.63 2988.54 PM73001
(iii) 10 cum capacity t.km 450.76XL1 8.08 3642.14 PM74001
Tipper for loading & unloading time for mix
(i) 18 cum capacity hour 6.010 2772.00 16659.72 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.513 2415.00 0.00 18143.90 0.00 PM6002
(iii) 10 cum capacity hour 10.017 2121.00 0.00 0.00 21246.06 PM6003
Smooth steel wheeled tandem roller for static and
11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibratory passages
hour
Pneumatic tyre roller hour 2.404 3.005 4.007 2338.00 5620.55 7025.69 9368.37 PM10001
Shredding Machine hour 1.250 1.250 1.250 416.00 520.00 520.00 520.00 PM79001
c) Material
i) Bitumen @4.78 percent of mix tonne 21.654 21.654 21.654 43502.00 941992.31 941992.31 941992.31 M-074
ii) Plastic @ 8 percent of mix tonne 1.875 1.875 1.875 14580.00 27337.50 27337.50 27337.50 M-292
iii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen=21.564 tonnes
Weight of Plastic= 1.875 tonnes
Weight of aggregate= 427.320 tonnes
Taking density of aggregate=1.5 ton/cum
* Grading-I 19mm(Nominal size)
20-10mm 38 percent cum 108.255 108.255 108.255 686.05 74268.34 74268.34 74268.34 M-044
10-5mm 17 percent cum 48.430 48.430 48.430 573.71 27784.78 27784.78 27784.78 M-039
5mm and below 43 percent cum 122.499 122.499 122.499 249.22 30529.20 30529.20 30529.20 M-029
Filler @2 percent of weight of aggregates cum 8.546 8.546 8.546 3637.51 31086.16 31086.16 31086.16 M-190
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
*Any one of the alternative may be adopted as per
approved design
* Grading I-19mm (Nominal size)
Total cost( Without O.H&C.P.) 1310845.55 1313311.58 1323141.51
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 104867.64 131331.16 158776.98
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 141571.32 144464.27 148191.85
Cost for 191 cum= a+b+c+d+e 1557284.52 1589107.01 1630110.34
Rate per cum=(a+b+c+d+e)/191 8153.32 8319.93 8534.61
Say 8153.30 8319.90 8534.60
Sugges
5.19 tive B Bituminous Concrete Grading 2 ( using waste
plastic)
Providing and laying bituminous concrete with higher
capacity batch typehot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 percent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
the required grade, level and alignment , rolling with
smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORT&H
specification clause no. 507 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40 L-12
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00 L-13
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14810.00 44504.05 0.00 0.00 PM18001
(ii) HMP 160 TPH hour 3.756 10450.00 0.00 39250.20 0.00 PM18002
(iii) HMP 120 TPH hour 5.008 8309.00 0.00 0.00 41611.47 PM18003
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Mechanical broom ( 2.1m sweeping width) hour 1.624 1.624 1.624 642.00 1042.61 1042.61 1042.61 PM23001
Air compressor 250cfm hour 1.624 1.624 1.624 416.00 675.58 675.58 675.58 PM15001
Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240 HP) hour 3.005 8710.00 26173.55 0.00 0.00 PM29001
(ii) Paver (240 HP) hour 3.756 8710.00 0.00 32714.76 0.00 PM29001
(iii) Paver (174 HP) hour 5.008 6808.00 0.00 0.00 34094.46 PM29002
Electric generator
(i) 500 kVA hour 3.005 9075.00 27270.38 0.00 0.00 PM22002
(ii) 400 KVA hour 3.756 7303.00 0.00 27430.07 0.00 PM22003
(iii) 250 KVA hour 5.008 4359.00 0.00 0.00 21829.87 PM22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.993 4255.00 21245.22 0.00 0.00 PM5001
(ii) 2.1 cum Capacity hour 7.362 2588.00 0.00 19052.86 0.00 PM5002
(iii) 1 Cum capacity hour 15.520 1594.00 0.00 0.00 24738.88 PM5003
Tipper
For transportation mix L1=1
(i) 18 cum capacity t.km 450.76XL1 5.94 2677.51 PM72001
(ii) 14 cum capacity t.km 450.76XL1 6.63 2988.54 PM73001
(iii) 10 cum capacity t.km 450.76XL1 8.08 3642.14 PM74001
Tipper for loading & unloading time for mix
(i) 18 cum capacity hour 6.010 2772.00 16659.72 0.00 0.00 PM6001
(ii) 14 cum capacity hour 7.513 2415.00 0.00 18143.90 0.00 PM6002
(iii) 10 cum capacity hour 10.017 2121.00 0.00 0.00 21246.06 PM6003
Smooth steel wheeled tandem roller for staic and
hour 16.902 16.902 16.902 2357.00 39838.01 39838.01 39838.01 PM9001
vibratory passages
Pneumatic tyre roller hour 2.404 3.005 4.007 2338.00 5620.55 7025.69 9368.37 PM10001
Shredding Machine hour 1.298 1.298 1.298 416.00 539.97 539.97 539.97 PM79001
c) Material
i) Bitumen @4.97 percent of mix tonne 22.394 22.394 22.394 43502.00 974183.79 974183.79 974183.79 M-074
ii) Plastic @ 8 percent of bitumen tonne 1.947 1.947 1.947 14580.00 28387.26 28387.26 28387.26 M-292
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
iii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen=22.39 tonnes
Weight of Plastic= 1.95 tonnes
Weight of aggregate= 426.42 tonnes
Taking density of aggregate=1.5 ton/cum
* Grading-II 13mm(Nominal size)
13.2-10mm 21 percent cum 59.825 59.825 59.825 686.05 41042.94 41042.94 41042.94 M-043
10-5mm 17 percent cum 48.430 48.430 48.430 573.71 27784.78 27784.78 27784.78 M-039
5mm and below 60 percent cum 170.928 170.928 170.928 249.22 42598.68 42598.68 42598.68 M-029
Filler @2 percent of weight of aggregates tonne 8.528 8.528 8.528 3637.51 31020.69 31020.69 31020.69 M-190
*Any one of the alternative may be adopted as per
approved design
* Grading II-13mm (Nominal size)
Total cost( Without O.H&C.P.) 1335003.68 1337458.71 1347383.95
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 106800.29 133745.87 161686.07
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 144180.40 147120.46 150907.00
Cost for 191 cum= a+b+c+d+e 1585984.37 1618325.04 1659977.03
Rate per cum=(a+b+c+d+e)/191 8303.58 8472.91 8690.98
Say 8303.60 8472.90 8691.00
Note *1. Quantity of bitumen & plastic has been taken for analysis purpose. The actual quantity will
depend upon job mix formula.
2 Labour for traffic control, watch and ward and other miscellaneous duties at site inclluding sundries
have beeen included in administrative overheads of the contractor.

3. The average density of 1.5 tonne/cum is only a refrence density in this data book
4. The individual percentage of aggregates should be calculated from the total weight of dry
aggregates i.e Excluding the weight of bitumen. The weight of filler will also be 2 percent by weight
of dry aggregates.

5.20 519 A Hot recycling in place of Bituminous Pavement


with bituminous concrete
Grading I
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small

Providing and laying bitminous concrete with hot


recycling in place using crushed caggregates of
specified grading, with bituminous bindes @ 5.2
percent of mix filler, transporting the aggregate to
work site, laying with a hot recycling in plavce to the
required grade, level and alignment rolling with
smoothed wheeled, vibratoey and tandem rollers to
achieve the desired compaction as per MORTH
specificationf clause No. 519 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.520 0.520 0.520 310.00 161.20 161.20 161.20 L-12
Mazdoor working with HMP, mechanical boom,
paver, roller, asphalt cutter and assistancew for day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
setting out lins, levels and layout of construction
Skilled mazdoor for checking lines and levels day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot in place recycling with pre heater unit for hot in
place recycling hour 6.000 6.000 6.000 902.00 5412.00 5412.00 5412.00 PM53001
Front end loader for feeding the plant
i) 3.1 cum capacity hour 1.200 4255.00 5106.00 0.00 0.00 PM5001
ii) 2.1 cum capacity hour 1.200 2588.00 0.00 3105.60 0.00 PM5002
iii) 1 cum capacity hour 1.200 1594.00 0.00 0.00 1912.80 PM5003
Tipper
For Transportation (Mix 20 % fresh material has been
considered) L1=1
90.152 X
i)18 cum capacity t.km 5.94 535.50 PM72001
L1
90.152 X
ii) 14 cum capacity t.km 6.63 597.71 PM73001
L1
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
90.152 X
iii) 10 cum capacity t.km 8.08 728.43 PM74001
L1
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibbratory passages
Pneumatic Tyre roller hour 4.800 4.800 4.800 2338.00 11222.40 11222.40 11222.40 PM10001
c) Material
i) Bitumen@5.2 percent of weight of mix (for 80% tonne 10.088 10.088 10.088 438848.18 438848.18 438848.18
recycled material @1.5%) 43502.00 M-074
ii) Aggregate
Total weight of mix= 450.76 tonnes
Weight of bitumen= 23.440 tonnes
Weight of aggregate=427.320 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading I -19mm (Nominal size)(only 20% fresh
material has been considered)
20-10 mm 38 percent cum 21.651 21.651 21.651 686.05 14853.67 14853.67 14853.67 M-044
10-5 mm 17 percent cum 9.686 9.686 9.686 573.71 5556.96 5556.96 5556.96 M-039
5 mm and below 43 percent cum 24.500 24.500 24.500 249.22 6105.89 6105.89 6105.89 M-029
Filler @2 percent of weight of aggregates tonne 1.709 1.709 1.709 3637.51 6216.50 6216.50 6216.50 M-190
* Any of the alternative may be adopted as per
approved design
* Grading I-19mm (Nominal size)
Total cost( Without O.H&C.P.) 526089.96 524151.77 523089.69
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 42087.20 52415.18 62770.76
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 56817.72 57656.69 58586.05
Cost for 191 cum = a+b+c+d+e 624994.88 634223.64 644446.50
Rate per cum= (a+b+c+d+e)/191 3272.22 3320.54 3374.07
Say 3272.20 3320.50 3374.10
5.20 519 B Hot recycling in place of Bituminous Pavement
with bituminous concrete
Grading II
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Providing and laying bitminous concrete with hot
recycling in place using crushed caggregates of
specified grading, with bituminous bindes @ 5.4
percent of mix filler, transporting the aggregate to
work site, laying with a hot recycling in plavce to the
required grade, level and alignment rolling with
smoothed wheeled, vibratoey and tandem rollers to
achieve the desired compaction as per MORTH
specificationf clause No. 519 complete in all respects.

Unit= cum
Taking output= 191 cum
a) Labour
Mate day 0.520 0.520 0.520 310.00 161.20 161.20 161.20 L-12
Mazdoor day 8.000 8.000 8.000 292.00 2336.00 2336.00 2336.00 L-13
Skilled mazdoor day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00 L-15
b) Machinery
Hot in place recycling with pre heater unit for hot in
place recycling hour 6.000 6.000 6.000 902.00 5412.00 5412.00 5412.00 PM53001
Front end loader for feeding the plant
i) 3.1 cum capacity hour 1.200 4255.00 5106.00 0.00 0.00 PM5001
ii) 2.1 cum capacity hour 1.200 2588.00 0.00 3105.60 0.00 PM5002
iii) 1 cum capacity hour 1.200 1594.00 0.00 0.00 1912.80 PM5003
Tipper
For Transportation L1=1
90.152 X 5.94 535.50 PM72001
i)18 cum capacity t.km L1
90.152 X 6.63 597.71 PM73001
ii) 14 cum capacity t.km L1
90.152 X
t.km 8.08 728.43 PM74001
iii) 10 cum capacity L1
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 2357.00 27885.67 27885.67 27885.67 PM9001
vibbratory passages
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
Pneumatic Tyre roller hour 4.800 4.800 4.800 2338.00 11222.40 11222.40 11222.40 PM10001
c) Material
i) Bitumen@5.4 percent of weight of mix (for 80% tonne 10.268 10.268 10.268 43502.00 446678.54 446678.54 446678.54 M-074
recycled material @1.5%)
ii) Aggregate
Total weight of mix= 450.76 tonnes
Weight of bitumen= 23.341 tonnes
Weight of aggregate=426.419 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading II -13mm (Nominal size)(only 20% fresh
material has been considered)
13.2-10 mm 21 percent cum 11.940 11.940 11.940 686.05 8191.44 8191.44 8191.44 M-043
10-5mm 17 percent cum 9.665 9.665 9.665 573.71 5544.91 5544.91 5544.91 M-039
5 mm and below 60 percent cum 34.114 34.114 34.114 249.22 8501.89 8501.89 8501.89 M-029
Filler @2 percent of weight of aggregates tonne 1.706 1.706 1.706 3637.51 6205.59 6205.59 6205.59 M-190
* Any of the alternative may be adopted as per
approved design
Total cost( Without O.H&C.P.) 529631.13 527692.94 526630.86
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 42370.49 52769.29 63195.70
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 57200.16 58046.22 58982.66
Cost for 191 cum = a+b+c+d+e 629201.79 638508.46 648809.22
Rate per cum= (a+b+c+d+e)/191 3294.25 3342.98 3396.91
Say 3294.30 3343.00 3396.90
Note
*1 Quantity of bitumen & plastic has been taken for
analysis purpose. The actual quantity will depend
upon job mix formula.
2. Labour for traffic control, watch and ward and
other miscellaneos duties at site including sundries
have been included in administrative overheads of the
contractors.
3.The average density of 1.5 tonne/cum is only
refrence density in this data book.
BASES AND SURFACE COURSES (BITUMINOUS)
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Ref. to
Sr No Description Unit
M. Large
Medium Small Large Medium Small
4. The individual percentage of aggregate should be
calculated from the total weight of dry aggregates i.e.
excluding the weight of bitumen. The weight of filler
will also be 2 percent by weight of dry aggregates.
CHAPTER -6
CEMENT CONCRETE PAVEMENT

Ref.
Sr No Description Unit Rate as per Project Category
to M.

Large Medium Small


6.01 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base
over a prepared sub-grade with coarse and fine
aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm, aggregate cement
ratio not to exceed 15:1, aggregate gradation after
blending to be as per table 600-1, cement content not
to be less than 150 kg/ cum, optimum moisture
content to be determined during trial length
construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported
to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller,
finishing and curing.

cum 2144.30 2191.50 2257.20

6.02 602 Cement Concrete Pavement


Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base
with approve grade cement @ 400 kg per cum, coarse
and fine aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25 mm, mixed
in a batching and mixing plant as per approved mix
design, transported to site, laid with a fixed form or
slip form paver, spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and longitudinal
joints, joint filler, separation membrane, sealant
primer, joint sealant, debonding strip, dowel bar, tie
rod, admixtures as approved, curing compound,
finishing to lines and grades as per drawing

cum 4922.80 5029.40 5151.00

6.03 Suggestive Transition Section between Rigid and Flexible


Pavement
Due to change in the properties of materials and type
of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid
any damage at the butting joint. After provision of an
expansion joint in the cement concrete slab, the
thickness of slab should be tapered to 10 cm over a
length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the
slab should be made up by the asphaltic layers.
The quantities of items should be worked out based on
the approved design and drawings and priced as per
rates given under respective clauses for cement
concrete and asphaltic work.
6.04 sugge Cement-Fly ash Dry Lean Cement Concrete Sub-
stive base

Construction of dry lean cement concrete sub-


base over a prepared sub-grade with coarse and
fine aggregate conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of 20
percent, aggregate cement ratio not to exceed
15:1,aggregate gradation after blending to be as
per table 600-1,cement content not to be less
than 129 kg/cum,optimum moisture content to
be determined during trial length
construction,concrete strength not to be less than
10 Mpa at 7 days, mixed in a batching plant,
transported to site, laid with a paver with
electronic sensor , compacting with 8-10 tonnes
vibratory roller, finishing and curing.

cum 2020.30 2065.20 2128.60

6.05 Suggestive Cement - Fly ash concrete pavement.


Construction reinforced-reinforced, dowel jointed,
plain cement concrete pavement over a prepared sub
base with approve grade cement @ 340 kg per cum,
coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25
mm,replacing cement by fly ash to the extent of 15
percent and sand by 10 percent,mixed in a batching
and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form
paver, spread, compacted and finished in a continuous
operation including provision of contraction,
expansion, construction and longitudinal joints, joint
filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing
to lines and grades as per drawing

cum 4501.00 4599.70 4661.00

6.06 Sugge Thin White topping


stive
Construction of thin white topping with plain cement
concrete pavement over existing surface with approve
grade cement @ 400 kg per cum and as per IRC SP-
76, coarse and fine aggregate conforming to IS 383,
maximum size of fine aggregate not exceeding 25
mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision
of contraction joint, joint filler, sealant primer, joint
sealant, admixtures as approved, curing compound,
finishing to lines etc.. and grades as per drawing.

cum #VALUE! #VALUE! #VALUE!

6.07 Suggestive Cement- Fly ash Thin White topping


Construction of thin white topping with plain cement
concrete pavement over exiting surface with approve
grade cement @ 340 kg per cum and Fly ash as per
IRC SP-76, coarse and fine aggregate conforming to
IS 383, maximum size of fine aggregate not exceeding
25mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision
of contraction joint, joint filler, sealent primer, joint
sealent, admixtures as approved, curing compound,
finishing to lines etc.. and grades as per drawing.

cum #VALUE! #VALUE! #VALUE!


CHAPTER -6
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
6.01 601 Dry Lean Cement Concrete Sub- base

Construction of dry lean cement concrete


Sub- base over a prepared sub-grade with
coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after
blending to be as per table 600-1, cement
content not to be less than 150 kg/ cum,
optimum moisture content to be determined
during trial length construction, concrete
strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site,
laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller,
finishing and curing.

Unit = cum
Taking output = 450 cum.
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00
b) Machinery
Paver with electronic senser
(i)Paver Finisher Concrete with 300HP
Motor hour 2.045 26752.00 54707.84 0.00 0.00
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii)Paver Finisher Concrete with 241HP
Motor hour 3.000 17252.00 0.00 51756.00 0.00
(iii)Paver Finisher Concrete with
118HP Motor hour 5.625 4082.00 0.00 0.00 22961.25

Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2338.00 4781.21 7014.00 13151.25
Tipper for Transportation
(i) 18 cum capacity t.km 990 x L1 5.94 5880.60
(ii) 14 cum capacity t.km 990 x L1 6.63 6563.70
(iii) 10 cum capacity t.km 990 x L1 8.08 7999.20
For loading& unloading
Time
(i) 18 cum capacity hour 4.545 2772.00 12598.74 0.00 0.00
(ii) 14 cum capacity hour 5.500 2415.00 0.00 13282.50 0.00
(iii) 10 cum capacity hour 10.625 2121.00 0.00 0.00 22535.63
Water tanker(speed@20km/hr and return
speed@30km/hr and spreading
speed@3.0km/hr)
(i) 16KL Capacity hour 1.509xL1+7. 1426.000 12483.20
245
(ii) 12KL Capacity 2.013xL1+9.6
hour 6 1252.000 14614.60

(iii)6KL Capacity hour 4.025xL1+19. 907.000 21173.92


32
(C) Material
Concrete from sub-analysis of concrete Rate

(i) Using Batching Plant 240 Cum Capacity cum 450.000 1562.00
(Rate taken from sub-analysis of concrete- 702900.00 0.00 0.00
21.18 A)
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii) Using Batching Plant 240 Cum Capacity cum 450.000 1562.00
(Rate taken from sub-analysis of concrete- 0.00 702900.00 0.00
21.18 A)
(iii)Using Batching Plant 120 Cum Capacity cum 450.000 1595.00
(Rate taken from sub-analysis of concrete- 0.00 0.00 717750.00
21.18 C)
cost of water (Curing) KL 217.350 217.350 217.350 73.60 15996.96 15996.96 15996.96
Total cost( Without O.H&C.P.) 812244.15 815023.36 824463.80
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 64979.53 81502.34 98935.66
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 87722.37 89652.57 92339.95
Cost for 450 cum = a+b+c+d+e 964946.05 986178.26 1015739.40
Rate per cum=(a+b+c+d+e)/450 (with OH.&C.P) 2144.32 2191.51 2257.20
Say 2144.30 2191.50 2257.20
Note:- Quantity provided for aggregate is for estimating purpose.Exact quantity shall be as per mix design.
6.02 602 Cement Concrete Pavement
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Construction of un-reinforced, dowel jointed,
plain cement concrete pavement over a
prepared sub base with approve grade cement
@ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm,
mixed in a batching and mixing plant as per
approved mix design, transported to site, laid
with a fixed form or slip form paver, spread,
compacted and finished in a continuous
operation including provision of contraction,
expansion, construction and longitudinal
joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip,
dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and
grades as per drawing

Unit = cum
Taking output = 900cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00
b) Machinery
Mechanical broom@1250 sqm per hour
hour 0.893 0.893 0.893 642.00 573.31 573.31 573.31
Air compressor 250 cfm hour 0.893 0.893 0.893 416.00 371.49 371.49 371.49
Paver with eiectronic senser
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(i)Paver Finisher Concrete with 300HP hour 4.091
Motor 26752.00 109442.43 0.00 0.00

(ii)Paver Finisher Concrete with 241HP hour 6.000


Motor 17252.00 0.00 103512.00 0.00

(iii)Paver Finisher Concrete with hour 11.250


118HP Motor 4082.00 0.00 0.00 45922.50
Transit truck agitator
For Transportation Transit truck t.km 2070xL1 2070xL1 2070xL1 12.32 25502.40 25502.40 25502.40
agitator 6cum capacity
For unloading time hour 4.091 6.000 11.250 2218.00 9073.84 13308.00 24952.50
Concrete joint cutting machine hour 101.587 101.587 101.587 175.00 17777.73 17777.73 17777.73
Texturing machine
Texturing machine(TCM) up to 18 m hour 4.091 4470.00 18286.77 0.00 0.00
Texturing machine(TCM) up to 18 m hour 6.000 4470.00 0.00 26820.00 0.00
Texturing machine(TCM) up to 9 m hour 11.250 3497.00 0.00 0.00 39341.25
Water tanker (speed @20 km /hr and
return speed@30 km / hr and spreading
speed@3.0 km /hr)
(i)16 KL capacity hour 3.281xL1+15
.75 1426.000 27138.21

(ii) 12 KL capacity hour 4.375xL1+21 1252.000 31769.50


(iii)6 KL capacity hour 8.75xL1+42 907.000 46030.25

c) Material
Concrete from sub analysis of
concrete Rate
(i) Using Batching Plant 240 cum cum 900.000 3110.30 2799270.00 0.00 0.00
Capacity (Rate taken from sub analysis
of concrete 21.19 A)
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii) Using Batching Plant 240 cum cum 900.000 3110.30 0.00 2799270.00 0.00
Capacity(Rate taken from sub analysis
of concrete 21.19 A)
(iii) Using Batching Plant 120 cum cum 900.000 3155.60 0.00 0.00 2840040.00
Capacity (Rate taken from sub analysis
of concrete 21.19 C)
36 mm mild steel dowel bars of grade S tonne 9.170 9.170 9.170 50325.00 461480.25 461480.25 461480.25
240
12 mm deformed steel tie bars of grade tonne 1.051 1.051 1.051 46824.00 49212.02 49212.02 49212.02
S 415
Separation Membrane of imperneable sqm 3150.000 3150.000 3150.000 14.07 44320.50 44320.50 44320.50
plastic sheeting125 micron thick
(including5% overlap)
Joint sealant kg 609.524 609.524 609.524 24.61 15000.39 15000.39 15000.39
Sealent primer kg 100.003 100.003 100.003 24.61 2461.07 2461.07 2461.07
Plastic sheath,1.25 mm thick for dowel
bars sqm 155.735 155.735 155.735 15.02 2339.14 2339.14 2339.14

Curing compound Liter 600.000 600.000 600.000 123.05 73830.00 73830.00 73830.00
Cost of water(Curing) KL 472.500 472.500 472.500 73.60 34776.00 34776.00 34776.00
Add 1 percent of material for cost of 34826.89 34826.89 35234.59
miscellaneous materials like tarpauline,
Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel
bars, work bridges for men to approach
concrete surface without walking over it,
cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide
wires and any other unforeseen items.

Total cost( Without O.H&C.P.) 3729420.83 3740889.09 3762903.79


CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 298353.67 374088.91 451548.45
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 402777.45 411497.80 421445.22
Cost for 900 cum = a+b+c+d+e 4430551.95 4526475.79 4635897.46
Rate per cum=(a+b+c+d+e)/900(with OH.&C.P) 4922.84 5029.42 5151.00
Say 4922.80 5029.40 5151.00
Note The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per mix design.
6.03 Suggestive Transition Section between Rigid and
Flexible Pavement
Due to change in the properties of materials
and type of construction, a gradual
changeover from rigid pavement to flexible
pavement is desirable to avoid any damage at
the butting joint. After provision of an
expansion joint in the cement concrete slab,
the thickness of slab should be tapered to 10
cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness
caused due to tapering of the slab should be
made up by the asphaltic layers.
The quantities of items should be worked out
based on the approved design and drawings
and priced as per rates given under respective
clauses for cement concrete and asphaltic
work.

6.04 sugges Cement-Fly ash Dry Lean Cement


tive Concrete Sub-base
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Construction of dry lean cement
concrete sub-base over a prepared sub-
grade with coarse and fine aggregate
conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the
extent of 20 percent, aggregate cement
ratio not to exceed 15:1,aggregate
gradation after blending to be as per
table 600-1,cement content not to be
less than 129 kg/cum,optimum
moisture content to be determined
during trial length
construction,concrete strength not to be
less than 10 Mpa at 7 days, mixed in a
batching plant, transported to site, laid
with a paver with electronic sensor ,
compacting with 8-10 tonnes vibratory
roller, finishing and curing.

Unit = cum
Taking output= 450 cum
a) Labour
Mate day 0.360 0.360 0.360 310.00 111.60 111.60 111.60
Mazdoor skilled day 2.000 2.000 2.000 370.00 740.00 740.00 740.00
Mazdoor day 7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00
b) Machinery
Paver finisher with electronic sensor

(i) Paver finisher concrete with 300 HP hour 2.045 26752.00 54707.84 0.00 0.00
Motor
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii) Paver Finisher concrete with 241 hour 3.000 17252.00 0.00 51756.00 0.00
HP Motor
(iii) Paver Finisher concrete with 118 HP hour 5.625 4082.00 0.00 0.00 22961.25
Motor
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2338.00 4781.21 7014.00 13151.25
Tipper
For Transportation
(i) 18 cum capacity t.km 990xL1 5.94 5880.60
(ii) 14 cum capacity t.km 990xL1 6.63 6563.70
(iii) 10 cum capacity t.km 990xL1 8.08 7999.20
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2772.00 12598.74 0.00 0.00
(ii) 14 cum capacity hour 5.500 2415.00 0.00 13282.50 0.00
(iii) 10 cum capacity hour 10.625 2121.00 0.00 0.00 22535.63
Water tanker (speed @ 20 km/hr and return
speed @ 30 km/hr and soreading speed @
3.0 km/hr)
(i) 16 KL capacity hour 1.509xL1+7.
245 1426.000 12483.20
(ii) 12 KL capacity hour 2.013xL1+9.6
6 1252.000 14614.60
(iii) 6 KL capacity hour 4.025xL1+19.
32 907.000 21173.92

c) Material
Concrete from sub-analysis of concrete
Rate
(i) Using Batching Plant 240 cum cum 450.000 1457.60
capacity(Rate taken from sub-analysis of 655920.00 0.00 0.00
concrete-21.18 B)
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii) Using Batching Plant 240 cum capacity cum 450.000 1457.60
(Rate taken from sub-analysis of concrete- 0.00 655920.00 0.00
21.18 B)
(iii) Using Batching Plant 120 Cum capacity cum 450.000 1490.60
(Rate taken from sub-analysis of concrete- 0.00 0.00 670770.00
21.18 D)
Cost of water (Curing) KL 217.350 217.350 217.350 73.60 15996.96 15996.96 15996.96
Total cost( Without O.H&C.P.) 765264.15 768043.36 777483.80
d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 61221.13 76804.34 93298.06
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 82648.53 84484.77 87078.19
Cost for 450 cum = a+b+c+d+e 909133.81 929332.46 957860.04
Rate per cum=(a+b+c+d+e)/450(with OH.&C.P) 2020.30 2065.18 2128.58
Say 2020.30 2065.20 2128.60
Note:- Quantity provided for aggregate is for estimating purpose.Exact quantity shall be as per mix design.

6.05 Suggestive Cement - Fly ash concrete pavement.


CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement over
a prepared sub base with approve grade
cement @ 340 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25
mm,replacing cement by fly ash to the extent
of 15 percent and sand by 10 percent,mixed
in a batching and mixing plant as per
approved mix design, transported to site, laid
with a fixed form or slip form paver, spread,
compacted and finished in a continuous
operation including provision of contraction,
expansion, construction and longitudinal
joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip,
dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and
grades as per drawing

Unit = cum
Taking output = 900 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00
b) Machinery
Mechanical broom @ 1250 sqm per hour 0.893 0.893 0.893 642.00 573.31 573.31 573.31
hour
Air compressor 250 cfm hour 0.893 0.893 0.893 416.00 371.49 371.49 371.49
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Paver with electronic sensor
(i) Paver finisher Concrete with 300 HP hour 4.091
Motor 26752.00 109442.43 0.00 0.00

(ii) Paver Finisher Concrete with 241 hour 6.000


HP Motor 17252.00 0.00 103512.00 0.00

(iii) Paver Finisher Concrete with 118 hour 11.250


HP Motor 4082.00 0.00 0.00 45922.50

Transit truck agitator


For Transportation Transit truck t.km 2070xL1 2071xL1 2072xL1 12.32 25502.40 25502.40 25502.40
agitator 6 cum capacity
For Unloading time hour 4.091 6.000 11.250 2218.00 9073.84 13308.00 24952.50
Concrete joint cutting machine hour 101.587 101.587 101.587 175.00 17777.73 17777.73 17777.73
Texturing machine. hour 4.091 6.000 11.250 4470.00 18286.77 26820.00 50287.50
Water tanker (speed @ 20km/hr and
return speed @30 km/hr and spreading
speed@ 3.0 km/hr
(i) 16 KL capacity hour 3.281xL1+15
.75 1426.000 27138.21

(ii) 12 KL capacity hour 4.375xL1+21 1252.000 31769.50


(iii) 6 KL capacity hour 8.75xL1+42 907.000 46030.25
c) Material
Concrete from sub-analysis of
concrete Rate
(i) Using Batching plant 240 Cum cum 900.000 2758.70 2482830.00 0.00 0.00
Capacity (Rate taken from sub-analysis
of concrete- 21.19 B)
(ii) Using Batching Plant 240 cum cum 900.000 2758.70 0.00 2482830.00 0.00
capacity (Rate taken from sub-analysis
of concrete-21.19 B)
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(iii) Using Batching Plant 120 Cum cum 900.000 2749.80 0.00 0.00 2474820.00
Capacity(Rate taken from sub-analysis
of concrete - 21.19 D)
36mm mild steel dowelbars of grade S 240 tonne 9.170 9.170 9.170 50325.00 461480.25 461480.25 461480.25

12 mm deformed steel tie bars of grade S tonne 1.051 1.051 1.051 46824.00 49212.02 49212.02 49212.02
415
Separation Membrance of impermeable sqm 3150.000 3150.000 3150.000 14.07 44320.50 44320.50 44320.50
plastic sheeting 125 micron thick
(including 5% overlap)
Joint Sealant kg 609.524 609.524 609.524 24.61 15000.39 15000.39 15000.39
Sealant primer kg 100.003 100.003 100.003 24.61 2461.07 2461.07 2461.07
Plastic sheath,1.25 mm thick for dowel sqm 155.735 155.735 155.735
bars 15.02 2339.14 2339.14 2339.14

Curing compound Litre 600.000 600.000 600.000 123.05 73830.00 73830.00 73830.00
Cost of water (Curing) KL 472.500 472.500 472.500 73.60 34776.00 34776.00 34776.00
Add 1 percent of material for cost of 31662.49 31662.49 31582.39
miscellaneous materials like tarpaulin,
Hessian cloth, metal cap, cotton/
compressible sponge and cradle for dowel
bars, work bridges for men to approach
concrete surface without walking over it,
cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide
wires and any other unforseen items.

Total cost( Without O.H&C.P.) 3409816.43 3421284.69 3404977.84


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) 272785.31 342128.47 408597.34
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) 368260.17 376341.32 381357.52
Cost for 900 cum = a+b+c+d+e 4050861.92 4139754.47 4194932.69
Rate per cum = (a+b+c+d+e)/900 4500.96 4599.73 4661.04
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Say 4501.00 4599.70 4661.00
Note The quantities for cement, coarse aggregate and fine aggregates are for estimating only. The exact quantities will be as per mix design.

6.06 Sugge Thin White topping


stive
Construction of thin white topping with plain
cement concrete pavement over existing
surface with approve grade cement @ 400 kg
per cum and as per IRC SP-76, coarse and
fine aggregate conforming to IS 383,
maximum size of fine aggregate not
exceeding 25 mm, mixed in a batching and
mixing plant as per approved mix design,
transported to site, laid with a fixed form or
slip form paver, spread, compacted and
finished in a continuous operation including
provision of contraction joint, joint filler,
sealant primer, joint sealant, admixtures as
approved, curing compound, finishing to
lines etc.. and grades as per drawing.

Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00
b) Machinery
Mechanical broom @1250 sqm per hour 0.893 0.893 0.893 642.00
hour 573.31 573.31 573.31
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Air Compresser 250 cfm hour 0.893 0.893 0.893 416.00 371.49 371.49 371.49
Paver with electronic sensor
(i) Paver finisher concrete with 300 hour 2.045
HP Motor 26752.00 54707.84 0.00 0.00
(ii) Paver finisher concrete with 241 hour 3.000
HP Motor 17252.00 0.00 51756.00 0.00
(iii) Paver finisher concrete with 118 hour 5.625
HP Motor 4082.00 0.00 0.00 22961.25

Transit truck agitator


For Transportation Transit truck agitator 6 t.km 2070xL1 2070xL1 2070xL1 12.32 25502.40 25502.40 25502.40
cum capacity
For Unloading time hour 2.045 3.000 5.625 2218.00 4535.81 6654.00 12476.25
Concrete joint cutting machine hour 320.000 320.000 320.000 175.00 56000.00 56000.00 56000.00
Texturing machine
Texturing machine (TCM) upto 18 m hour 2.045 4470.00 9141.15
Texturing machine (TCM) upto 18 m hour 3.000 4470.00 13410.00
Texturing machine (TCM) upto 9 m hour 5.625 3497.00 19670.63
Water tanker (speed @ 20 km/hr and
return speed @ 30 km/hr and spreading
speed @ 3.0 km/hr
(i) 16 KL capacity hour 1.641xL1+7.
875 1426.000 13569.82
(ii) 12 KL capacity hour 2.188xL1+10.
5 1252.000 15885.38

(iii) 6 KL capacity hour 4.375xL1+21 907.000 23015.13


c) Material
Concrete from sub-analysis of
concrete Rate
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(i) Using Batching Plant 240 cum cum 450.000 3110.30
Capacity (Rate taken from sub-analysis 1399635.00 0.00 0.00
of concrete-21.19 A)
(ii) Using Batching Plant 240 Cum cum 450.000 3110.30
capacity (Rate taken from sub-analysis 0.00 1399635.00 0.00
of concrete- 21.19 A)
(iii) Using Batching Plant 120 Cum cum 450.000 3155.60
capacity (Rate taken from sub-analysis 0.00 0.00 1420020.00
of concrete- 21.19 C)
Joint sealant kg 1920.000 1920.000 1920.000 24.61 47251.20 47251.20 47251.20
Sealant primer kg 50.001 50.001 50.001 24.61 1230.52 1230.52 1230.52
Fibre Reinforcement @ 9.25 kg Per tonne 4.163 4.163 4.163 INPUT
Cum #VALUE! #VALUE! #VALUE!
Curing compound Liter 600.000 600.000 600.000 123.05 73830.00 73830.00 73830.00
Cost of water (Curing ) KL 236.250 236.250 236.250 73.60 17388.00 17388.00 17388.00
Add 1 percent of material for cost of #VALUE! #VALUE! #VALUE!
miscellaneous materials like tarpauline,
Hessian cloth, cotton / compressible
sponge and , work bridges for men to
approach concrete surface without
walking over it, cutting blades and
bites, minor equipments like scabbling
machine, threades, ropes, guide wires
and any other unforseen items.

Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for 450 cum = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per cum = (a+b+c+d+e)/450 #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
Note 1.The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per mix design.
6.07 Suggestive Cement- Fly ash Thin White topping
Construction of thin white topping with
plain cement concrete pavement over exiting
surface with approve grade cement @ 340 kg
per cum and Fly ash as per IRC SP-76,
coarse and fine aggregate conforming to IS
383, maximum size of fine aggregate not
exceeding 25mm, mixed in a batching and
mixing plant as per approved mix design,
transported to site, laid with a fixed form or
slip form paver, spread, compacted and
finished in a continuous operation including
provision of contraction joint, joint filler,
sealent primer, joint sealent, admixtures as
approved, curing compound, finishing to
lines etc.. and grades as per drawing.

Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.440 0.440 0.440 310.00 136.40 136.40 136.40
Mazdoor skilled day 5.000 5.000 5.000 370.00 1850.00 1850.00 1850.00
Mazdoor day 6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00
b) Machinery
Mechanical broom @1250 sqm per hour 0.893 0.893 0.893 642.00 573.31 573.31 573.31
hour
Air Compresser 250 cfm hour 0.893 0.893 0.893 416.00 371.49 371.49 371.49
Paver with electronic sensor
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(i) Paver finisher concrete with 300 hour 2.045 26752.00 54707.84 0.00 0.00
HP Motor
(ii) Paver finisher concrete with 241 hour 3.000 17252.00 0.00 51756.00 0.00
HP Motor
(iii) Paver finisher concrete with 118 hour 5.625 4082.00 0.00 0.00 22961.25
HP Motor
Transit truck agitator
For Transportation Transit truck agitator 6 t.km 2070xL1 2070xL1 2070xL1 12.32 25502.40 25502.40 25502.40
cum capacity
For Unloading time hour 2.045 3.000 5.625 2218.00 4535.81 6654.00 12476.25
Concrete joint cutting machine hour 320.000 320.000 320.000 175.00 56000.00 56000.00 56000.00
Texturing machine
Texturing machine (TCM) upto 18 m hour 2.045 4470.00 9141.15
Texturing machine (TCM) upto 18 m hour 3.000 4470.00 13410.00
Texturing machine (TCM) upto 9 m hour 5.625 3497.00 19670.63
Water tanker (speed @ 20 km/hr and
return speed @ 30 km/hr and spreading
speed @ 3.0 km/hr
(i) 16 KL capacity hour 1.641xL1+7.
875 1426.000 13569.82
(ii) 12 KL capacity hour 2.188xL1+10.
5 1252.000 15885.38

(iii) 6 KL capacity hour 4.375xL1+21 907.000 23015.13


c) Material
Concrete from sub-analysis of
concrete Rate
(i) Using Batching Plant 240 cum cum 450.000 2758.70 1241415.00 0.00 0.00
Capacity (Rate taken from sub-analysis
of concrete-21.19 B)
CEMENT CONCRETE PAVEMENTS
Sr. Ref. to Description Unit Quantity as per project category Rate (Rs`) Amount (`Rs)
No. MoRT
H
Spec.
Large Medium Small Large Medium Small
(ii) Using Batching Plant 240 Cum cum 450.000 2758.70 0.00 1241415.00 0.00
capacity (Rate taken from sub-analysis
of concrete- 21.19 B)
(iii) Using Batching Plant 120 Cum cum 450.000 2749.80 0.00 0.00 1237410.00
capacity (Rate taken from sub-analysis
of concrete- 21.19 D)
Joint sealant kg 1920.000 1920.000 1920.000 24.61 47251.20 47251.20 47251.20
Sealant primer kg 50.001 50.001 50.001 24.61 1230.52 1230.52 1230.52
Fibre Reinforcement @ 9.25 kg Per tonne 4.163 4.163 4.163 INPUT
Cum #VALUE! #VALUE! #VALUE!
Curing compound Liter 600.000 600.000 600.000 123.05 73830.00 73830.00 73830.00
Cost of water (Curing ) KL 236.250 236.250 236.250 73.60 17388.00 17388.00 17388.00
Add 1 percent of material for cost of #VALUE! #VALUE! #VALUE!
miscellaneous materials like tarpauline,
Hessian cloth, cotton / compressible
sponge and , work bridges for men to
approach concrete surface without
walking over it, cutting blades and
bites, minor equipments like scabbling
machine, threades, ropes, guide wires
and any other unforseen items.

Total cost( Without O.H&C.P.) #VALUE! #VALUE! #VALUE!


d) Overhead charges on (a+b+c) (@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
Cost for 450 cum = a+b+c+d+e #VALUE! #VALUE! #VALUE!
Rate per cum = (a+b+c+d+e)/450 #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
Note:- 1.The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per mix design.
Remarks/
Input ref.

L-12
L-15
L-13

PM30001
Remarks/
Input ref.

PM30002

PM30003

PM10001

PM72001
PM73001
PM74001

PM6001
PM6002
PM6003

PM11001

PM11002

PM11003

21.18 A
Remarks/
Input ref.

21.18 A

21.18 C

M-191
Remarks/
Input ref.

L-12
L-15
L-13

PM23001
PM15001
Remarks/
Input ref.

PM30001

PM30002

PM30003

PM76001

PM34001
PM61002

PM31001
PM31001
PM31002
L1=1

PM11001

PM11002
PM11003

21.19 A
Remarks/
Input ref.

21.19 A

21.19 C

M-125

M-083

M-165

3185
M-119
M-119

M-137

M-091
M-191
Remarks/
Input ref.
Remarks/
Input ref.

L-12
L-15
L-13

PM30001
Remarks/
Input ref.

PM30002

PM30003

PM10001

L1=1
PM72001
PM73001
PM74001

PM6001
PM6002
PM6003
L1=1

PM11001

PM11002

PM11003

21.18 B
Remarks/
Input ref.

21.18 B

21.18 D=

M-191
Remarks/
Input ref.

L-12
L-15
L-13

PM23001

PM15001
Remarks/
Input ref.

PM30001

PM30002

PM30003

L1=1
PM76001

PM34001
PM61002
PM31001
L1=1

PM11001

PM11002
PM11003

21.19. B

21.19 B
Remarks/
Input ref.

21.19 D

M-125

M-083

M-165

M-119
M-119

M-137

M-091
M-191
Remarks/
Input ref.

L-12
L-15
L-13

PM23001
Remarks/
Input ref.

PM15001

PM30001

PM30002

PM30003

L1=1
PM76001

PM34001
PM61002

PM31001
PM31001
PM31002
L1=1

PM11001

PM11002

PM11003
Remarks/
Input ref.

21.19 A

21.19 A

21.19 C

M-119
M-119

M-091
M-191
Remarks/
Input ref.

L-12
L-15
L-13

PM23001

PM15001
Remarks/
Input ref.

PM30001

PM30002

PM30003

L1=1
PM76001

PM34001
PM61002

PM31001
PM31001
PM31002
L1=1

PM11001

PM11002

PM11003

21.19. B
Remarks/
Input ref.

21.19 B

21.19 D

M-119
M-119

M-091
M-191
CHAPTER - 8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Rate as per peroject category
Item. No. Description Unit
Large Medium Small

Cast-in-Situ Cement Concrete M20 Kerb


(Construction of cement concrete kerb with top and
8.01 bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M-15 grade foundation
150 mm thick, foundation having 50 mm projection
beyond kerb stone, kerb stone laid with kerb laying
machine, foundation concrete laid manually, all
complete as per clause 409)
(i) PCC M15 for Kerb Base RM 117.10 119.20 121.30
(ii) PCC M20 for Kerb cast in situ RM 150.50 153.20 156.00

Cast in Situ Cement Concrete M 20 Kerb with


Channel (Construction of cement concrete kerb with
8.02 channel with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on
M15 grade foundation 150 mm thick, kerb channel
300 mm wide, 50 mm thick in PCCM20 grade,
sloped towards the kerb, kerb stone with channel
laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 409)
(i) PCC M15 for Kerb Base RM 118.60 120.70 122.80
(ii) PCC M20 for Kerb Cast in situ RM 209.00 212.80 216.70

Printing New Letter and Figures of any Shade


8.03 (Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved
colour to give an even shade)
Hindi ( Matras commas and the like not to be
measured and paid for Half letter shall be counted
(i) per cm
as half ) height per
letter 0.90 0.90 0.90

(ii) per cm
English and Roman (Hyphens and the height per
like not to be measured and paid for) letter 0.60 0.60 0.60
8.04 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per
IRC :67 made of class-B Type IV retro reflective
sheeting fixed cover 2 mm thick aluminium sheeting
vide clause 801.3, 3mm/4mm thick aluminium
composite material sheet depending on the size of
the sign fixed over back support frame of min 25 x
25 x 3 mm Angle mounted on a mild steel circular
A pipe 65 NB, 3.2 mm thickness firmly fixed to the
ground by means of properly designed foundation
with M25 grade cement concrete 45 cm x 45 cm x
60 cm, 60 cm below ground level as per approved
drawing. The sign shall be maintained as per
section 12 of IRC 67.

(i) 120 cm equilateral triangle Each 7897.90 8045.20 8194.60


(ii) 90 cm equilateral triangle Each 5327.60 5427.20 5529.00
(iii) 75 cm equilateral triangle Each 4320.10 4401.10 4484.20
(iv) 60 cm equilateral triangle Each 3491.60 3557.20 3625.00
(v) 120 cm circular Each 12671.50 12907.10 13144.90
(vi) 90 cm circular Each 8010.90 8160.20 8311.70
(vii) 75 cm circular Each 6184.30 6299.80 6417.50
(viii) 60 cm circular Each 4687.30 4775.10 4865.00
(ix) 90 cm x 75 cm rectangular Each 8378.10 8534.20 8692.50
(x) 80 cm x 60 cm rectangular Each 6542.10 6664.30 6788.50
(xi) 60 cm x 50 cm rectangular Each 4847.40 4938.10 5031.00
(xii) 60 cm x 45 cm rectangular Each 4564.90 4650.40 4738.10
(xiii) 60 cm x 60 cm square Each 5412.30 5513.50 5616.90
(xiv) 120 cm high octagon Each 13255.20 13501.70 13750.30
(xv) 90 cm high octagon Each 8340.50 8495.90 8653.50
(xvi) 75 cm high octagon Each 6222.00 6338.20 6456.60
Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per
IRC :67 made of class-C Type IX retro reflective
sheeting fixed over 2mm thick aluminium sheeting
vide clause 801.3, 3/4mm thick Aluminium
composite material sheet depending on the size of
the sign fixed over back support frame of min 25 x
25 x 3 mm Angle mounted on a mild steel circular
B pipe 65 NB, 3.2 mm thickness firmly fixed to the
ground by means of properly designed foundation
with M25 grade cement concrete 45 cm x 45 cm x
60 cm, 60 cm below ground level as per approved
drawing. The sign shall be maintained as per
section 12 of IRC 67.

(i) 120 cm equilateral triangle Each 7897.90 8045.20 8194.60


(ii) 90 cm equilateral triangle Each 5327.60 5427.20 5529.00
(iii) 75 cm equilateral triangle Each 4320.10 4401.10 4484.20
(iv) 60 cm equilateral triangle Each 3491.60 3557.20 3625.00
(v) 120 cm circular Each 12671.50 12907.10 13144.90
(vi) 90 cm circular Each 8010.90 8160.20 8311.70
(vii) 75 cm circular Each 6184.30 6299.80 6417.50
(viii) 60 cm circular Each 4687.30 4775.10 4865.00
(ix) 90 cm x 75 cm rectangular Each 8378.10 8534.20 8692.50
(x) 80 cm x 60 cm rectangular Each 6542.10 6664.30 6788.50
(xi) 60 cm x 50 cm rectangular Each 4847.40 4938.10 5031.00
(xii) 60 cm x 45 cm rectangular Each 4564.90 4650.40 4738.10
(xiii) 60 cm x 60 cm square Each 5412.30 5513.50 5616.90
(xiv) 120 cm high octagon Each 13255.20 13501.70 13750.30
(xv) 90 cm high octagon Each 8340.50 8495.90 8653.50
(xvi) 75 cm high octagon Each 6222.00 6338.20 6456.60
Direction and Place Identification Signs upto 0.9
sqm Size Board.(Providing and erecting direction
and place identification retro-reflectorised sign as
per IRC:67 made of high intensity grade sheeting
vide clause 801.3, fixed over aluminium sheeting, 2
mm thick or Aluminium composite material sheet
8.05 with overall thickness of 4 mm with area not Each 12001.80 12225.10 12450.90
exceeding 0.9 sqm fixed over back support frame of
min 35 x 35 x 3 mm Angle mounted on a mild steel
circular pipe 65 NB, firmly fixed to the ground by
means of properly designed foundation with M25
grade cement concrete 45 x 45 x 60 cm, 60 cm
below ground level as per approved drawing)

Direction and Place Identification Signs with size


more than 0.9 sqm size Board.(Providing and
erecting direction and place identification retro-
reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed
8.06 over aluminium sheeting, 2 mm thick or Aluminium Each 12548.00 12781.70 13018.20
composite material sheet with overall thickness of 4
mm with area exceeding 0.9 sqm fixed over back
support frame of min 40 x 40 x 5 mm Angle
mounted on two nos. of mild steel circular pipe 65
NB, 3.2mm thickness and 4.5m meter total height
firmly fixed to the ground by means of properly
designed foundation with M 25 grade cement
concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing)
Overhead Signs (Providing and erecting overhead
signs with a corrosion resistant 2mm thick
aluminium alloy sheet reflectorised with high
intensity retro-reflective sheeting of encapsulated
8.07 lense type with vertical and lateral clearance given
in clause 802.2 and 802.3 and installed as per
clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and
trusses of sections and type as per structural design
requirements and approved plans & as per IRC: 67)

A Truss and Vertical Support tonne 50953.10 51896.70 52840.30


B Aluminium Alloy Plate for Over Head Sign sqm 9578.70 9756.10 9933.40
Painting Two Coats on New Concrete Surfaces
8.08 (Painting two coats after filling the surface with sqm
synthetic enamel paint in all shades on new
plastered concrete surfaces) 75.80 77.20 78.60

Painting on Steel Surfaces (Providing and


8.09 applying two coats of ready mix paint of approved sqm 66.40 67.60 68.80
brand on steel surface after through cleaning of
surface to give an even shade)

Painting on Wood Surfaces (Providing and


8.10 sqm 73.90 75.30 76.70
applying two coats of ready mix paint of approved
brand on wood surface after thorough cleaning of
surface to give an even shade)

Painting Lines, Dashes, Arrows etc on Roads in


Two Coats on New Work (Painting lines, dashes,
8.11 arrows etc on roads in two coats on new work with
ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter,
demarcation at site and traffic control )
(i) Over 10 cm in width sqm 120.60 122.90 125.10
(ii) Up to 10 cm in width sqm 104.20 106.20 108.10
Painting Lines, Dashes, Arrows etc on Roads in
Two Coats on Old Work (Painting lines, dashes,
8.12 arrows etc on roads in two coats on old work with
ready mixed road marking paint conforming to IS:
164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter,
demarcation at site and traffic control )
(i) Over 10 cm in width sqm 82.90 84.40 86.00
(ii) Up to 10 cm in width sqm 88.80 90.40 92.10

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface (Providing and laying of hot
8.13 applied thermoplastic compound 2.5 mm thick sqm 603.50 614.70 625.90
including reflectorising glass beads @ 250 gms per
sqm area, thickness of 2.5 mm is exclusive of
surface applied glass beads as per IRC:35 .The
finished surface to be level, uniform and free from
streaks and holes.)
Kilometre Stone (Reinforced cement concrete
M15grade kilometre stone of standard design as
per IRC:8-1980, fixing in position including painting
8.14 and printing etc)
(i) 5th kilometre stone (precast) Nos 2999.40 3055.10 3117.90
(ii) Ordinary kilometer stone (precast) Nos 1693.10 1725.40 1762.60
(iii) Hectometer stone (precast) Nos 534.90 545.10 556.40

Road Delineators (Supplying and installation


of delineators (Road way indicators, hazard
8.15 markers, object markers), 80-100 cm high above Each 1049.80 1069.20 1088.60
ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm
dia circular reflectorised panels at the top, buried or
pressed into the ground and conforming to IRC-79
and the drawings.)

Boundary pillar (Reinforced cement concrete


8.16 Each 460.20 468.50 477.40
M15 grade boundary pillars of standard design as
per IRC:25, fixed in position including finishing and
lettering but excluding painting)
G.I Barbed Wire Fencing 1.2 Metre High (Providing
and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm
8.17 placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one end post
and corner post shall be strutted on both sides and
end post on one side only and provided with 9
horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles
etc complete as per clause 817 ) RM 259.30 264.20 269.10

G.I Barbed Wire Fencing 1.8 Metre High (Providing


and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm
8.18 placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one end post
and corner post shall be strutted on both sides and
end post on one side only and provided with 12
horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles
etc complete as per clause 808) RM 428.20 436.40 444.50

Fencing With Welded Steel Wire Fabric 75 mm x 50


mm (Providing 1.20 metre high fencing with angle
8.19 iron posts 50 mm x 50 mm x 6 mm at 3 metre center
Suggestive
to center with 0.40 metre embedded in M15 grade
cement concrete, corner, end and every 10th post to
be strutted, provided with welded steel wire fabric of
75 mm x 50 mm mesh or 75 mm x 25 mm mesh and
fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.) Rm 563.70 574.10 584.60
Tubular Steel Railing on Medium Weight Steel
Channel ( ISMC series) 100 mm x 50 mm
8.20 (Providing, fixing and erecting 50 mm dia steel pipe
railing in 3 rows duly painted on medium weight
steel channels (ISMC series) 100 mm x 50 mm, 1.2
metres high above ground, 2 m centre to centre,
complete as per approved drawings) RM 1656.3 1687.5 1719.8

Tubular Steel Railing on Precast RCC Posts, 1.2 m


High Above Ground Level (Providing, fencing and
8.21 erecting 50 mm dia painted steel pipe railing in 3
rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm
dia for pipe, fixed 2 metres centre to, complete as
per approved drawing) RM 2839.20 2896.20 2962.70
8.22 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete


crash barrier at the edges of the road, approaches
A to bridge structures and medians, constructed
with Reinforced Cement Concrete with HYSD
reinforcement conforming to MoRT&H
specification and as per details given IRC-5 (Fig.-5,
b) including dowel bars 25 mm dia, 450 mm long
at expansion joints filled with pre-moulded asphalt
filler board etc., as per approved drawing and at
locations directed by the Engineer, all as specified.
(Area- 0.243 sqm./meter, single face)

(i) M 25 grade concrete Linear


metre 1565.70 1588.30 1615.20
Linear
(ii) M 30 grade concrete metre 1565.70 1588.30 1615.20
Provision of an Reinforced cement concrete New
Jersy crash barrier at the medians constructed with
Reinforced cement concrete with HYSD
reinforcement conforming to MoRT&H specification
and as per details given IRC-119 (Fig.-26) including
dowel bars 25 mm dia, 450 mm long at expansion
B joints filled with pre-moulded asphalt filler board
etc.,as per approved drawing and at locations
directed by the Engineer, all as specified. (Area-
0.261 sqm./meter, Double Face)

(i) M 25 grade concrete Linear


metre 1882.20 1882.80 1883.40
(ii) M 30 grade concrete Linear
metre 1916.60 1917.20 1917.80
8.23 Metal Beam Crash Barrier

Type - A, "W" : Metal Beam Crash Barrier (Providing


and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal
A beam rail, 70 cm above road/ground level, fixed on
ISMC series channel vertical post, 150 x 75 x 5 mm
spaced 2 m centre to centre, 1.8 m high, 1.1 m
below ground/road level, all steel parts and fitments
to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as
per clause 811) RM 2809.50 2861.50 2913.60
Type - B, "THRIE" : Metal Beam Crash Barrier
(Providing and erecting a "Thrie" metal beam crash
barrier comprising of 3 mm thick corrugated sheet
B
metal beam rail, 85 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x 75
x 5 mm spaced 2 m centre to centre, 2 m high with
1.15 m below ground level, all steel parts and
fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal
beam rail to be fixed on the vertical post with a
space of channel section 150 x 75 x 5 mm, 546 mm
long complete as per clause 811) RM 3529.70 3595.10 3660.40

Road Traffic Signals electrically operated


(Since it is a ready made item commercially
8.24
produced and erected by specialised firm in the
electrical and electronic field, rate may be taken
based on market enquiry from firms specialised in
this field and ISI certified for the approved design
and drawing.)

Flexible Crash Barrier, Wire Rope Safety Barrier


(Providing and erecting a wire rope safety barrier
with vertical posts of medium weight RS Joist (ISMB
series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long
0.85 m above ground and 0.65 m below ground
8.25 level, split at the bottom for better grip, embedded in
RM 2039.40 2077.10 2114.90
Suggestive M 15 grade cement concrete 450 x 450 x 450 mm,
1.50 m center to center and with 4 horizontal steel
wire rope 40 mm dia and anchored at terminal posts
15 m apart. Terminal post to be embedded in M 15
grade cement concrete foundation 2400 x 450 x 900
mm (depth), strengthened by a strut of RS joist 100
x 75 mm, 2 m long at 45° inclination and a tie 100 x
8 mm, 1.50 m long at the bottom, all embedded in
foundation concrete as per approved design and
drawing, rate excluding excavation and cement
concrete.)
8.26
Suggestive Anti-Glare Devices in Median
Plantation (Plantation of shrubs and plants of
A
approved species in the median. apart from cutting
off glare from vehicle coming from opposite
direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this
item is available in the chapter 11 on horticulture. )
Anti-glare screen with 25 mm steel pipe framework
fixed with circular and rectangular vans (Providing
and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of
panels of one metre length and 1.75 metre height
fixed with circular vane 250 mm dia at top and
rectangular vane 600 x 300 mm at the middle, made
B out of steel sheet of 3 mm thickness, end vertical RM 3155.70 3214.10 3272.50
pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all
exposed surfaces, all as per approved design and
drawings.)

Anti-glare screen with rectangular vane of MS sheet


(Providing and erecting anti - glare screen with
rectangular vanes of size 750 x 500 mm made from
C MS sheet, 3 mm thick and fixed on MS angle 50 x RM 869.90 886.00 902.10
50 x 6 mm at an angle of 45° to the direction of flow
of traffic, 1.5 m center to center, top edge of the
screen 1.75 m above ground level, vertical post
firmly embedded in M-15 cement concrete
foundation 0.60 m below ground level, applying 2
coats of paint on exposed faces, all complete as per
approved design and drawings)

Street Lighting (Providing and erecting street


light mounted on a steel circular hollow pole of
8.27
Suggestive standard specifications for street lighting, 10 m high
spaced 40 m apart, 1.8 m overhang on both sides if
fixed in the median and on one side if fixed on the
footpath, fitted with sodium vapour lamp and fixed
firmly in concrete foundation.)
(i) For Fixing in Median Each #VALUE! #VALUE! #VALUE!
(ii) For fixing in Footpath Each #VALUE! #VALUE! #VALUE!

Lighting on Bridges (Providing and fixing


8.28 lighting on bridges, mounted on steel hollow
Each #VALUE! #VALUE! #VALUE!
Suggestive circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart
and fitted with sodium vapour lamp)

Cable Duct Across the Road (Providing and


laying of a reinforced cement concrete pipe duct,
300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of
8.29 slope to toe of slope in fills, constructing head walls
Suggestive at both ends, providing a minimum fill of granular
material over top and sides of RCC pipe as per
IRC:98-1997, bedded on a 0.3 m thick layer of
granular material free of rock pieces, outer to outer
distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row
ducts, joints to be made leak proof, invert level of
duct to be above higher than ground level to prevent
entry of water and dirt, all as per IRC: 98 - 1997 and
approved drawings.)
(i) Single row for one utility service RM 1123.20 1137.20 1151.30
(ii) Double row for two utility services RM 2032.60 2060.70 2088.70
(iii) Triple Row for three utility services RM 2959.40 3001.70 3044.00

Highway Patrolling and Traffic Aid Post.


It is proposed to locate one Traffic Aid Post every
8.30
Suggestive
50-60 km of the highway.
The organisation and financial aspect are required
to be finalised in consultation with administrative
and traffic authorities .

Items Related to Underpass/ Subway/ Overhead


8.31 Bridge/ Overhead Foot Bridge (The items involved
Suggestive for underpass/ subway/ overhead bridge/ overhead
foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates
for these items are available in respective chapters
which can be adopted for the quantities derived from
the approved designs and drawings)
Traffic Control System and Communication System
(Providing a traffic control centre and
communication system including telecommunication
facilities and related accessories, CCTV, radar,
vehicle detection camera, central computer system.
8.32 These are specialised item of telecommunication
Suggestive
system and are the commercial products. The
designer is required to contact the manufacturers to
ascertain market prices. In case of civil works
required to be executed for these installations,
pricing may be done as per rates in relevant
chapters for quantities derived as per approved
design and drawing. As regards the locations where
such devices are required to be installed, the traffic
control authority should be consulted to finalise the
location)
8.33 Gantry Mounted Variable Message Sign Board
Suggestive
Providing and erecting gantry mounted variable
message sign board electronically operated capable
of flashing the desired message over a designed
support system of aluminium alloy or galvanised
(i) tonne 48748.30 49651.10 50553.80
steel, erected as per approved design and drawings
and with lateral clearance as per clause 802.3

Message Display (Message display board 6


sqm electronically operated with complete
electronic fitments for flashing the pre-determined
messages.This is a specilised commercial product
(ii)
and the lumpsum rate including erection at site is
required to be as certained from the market and
including in the rate analysis. The size of the board
will vary depending upon specific location.The rate
for the gantry mounted variable sign would be the
addition of cost of gantry support system as per
approved design determined at (i) above and the
cost of message display board as certained from the
market at (ii) above)
8.34
Suggestive Traffic Impact Attenuators at Abutments and Piers
With Scrap Tyres (Provision and installation of
A
traffic attenuators at abutment/pier of flyovers sqm
bridges using scrap tyres of size 100 x 20 retrieved
from trucks laid in 2 rows and 4 tiers, one above the
other and tied with 20 mm wire rope as per
approved design and drawings.) 890.90 907.40 923.90

Using Plastic/Steel Barrel, Filled with Sand


(Provision and installation of traffic impact attenuator
B
at abutment/pier of flyovers bridges using sqm 621.70 633.20 644.70
plastic/steel barrels 0.60 m dia and 1.0 m in height,
filled with sand in three rows and tied with 20 mm
steel wire rope as per approved design and
drawings)
With HI - DRO cell Sandwich (Patented) (In this
patented HI - DRO cell system, water gets
C discharged from plastic tubes on impact over a pre- sqm #VALUE! #VALUE! #VALUE!
determined time, thus absorbing the energy)
Solar Powered Road Marker (Solar Stud) Supplying
of Solar Raised Pavement Markers made of
polycarbonate molded body with circular shape,
solar powered, LED self illumination in active mode,
360 degree illumination and reflective panels with
micro prismatic lens capable of providing total
internal reflection of the light entering the lens face
in passive mode. The marker shall support a load of
20000 kg tested in accordance to ASTM D 4280.
The marker should be resistant to dust and water
ingress according to IP 65 standards and should
8.35 withstand temperatures in the range of 0 C to 70 C.
Nos 228.30 232.60 236.80
Suggestive Color of lighting could be provided in red or yellow
(amber) as per requirement and typical frequency of
blinkikng in 1 Hz. There should be current losses of
less than 20 microamperes at 2.4 V in
sleepcharging mode to enhace the life of the marker
and a full charge should provide for a minimum
autonomy of 50 hours. The height, width and length
of the marker shall not be less than 10mm x 100
mm x 100 mm. Also, the surface diameter of the
marker shall not be less than 100 mm respectively.
The weight of the marker shall not exceed 0.5
Kilograms. Fixing will be by drilling holes on the
road for the shanks to go inside, without nails and
using epoxy resin based adhesive and complete as
directed by the engineer.)

Traffic Cone (Provision of red fluorescent with


white reflective sleeve traffic cone made of low
8.36
Suggestive
density polyethylene (LDPE) material with a
square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all
as per BS 873) Each #VALUE! #VALUE! #VALUE!
8.37
Suggestive Roadside Amenities
Rest areas (Providing plainly furnished
accommodation for rest rooms, dormitories,
restaurants, stalls, shops, petrol pump, telephone
A booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and
sewerage system.
Pricing may be done based on current plinth area
rates approved by PWD/CPWD/MES for a particular
zone. Area is required to be assessed for specific
location as per actual site conditions.)

Parking areas and bus laybyes for trucks, buses and


B
light vehicles (Pricing of parking areas may be done
for the quantities of various items based on the
approved dimensions and pavement design for a
particular terrain and soil. Rates for items may be
from respective chapters.)
Lawn (Providing a lawn planted with grass and
its maintenance .Pricing of lawn may be done as per
C
rates given in the chapter on horticulture for the
quantities as per approved dimensions in the
drawings)

Rumble Strips (Provision of 15 nos rumble


strips covered with premix bituminous carpet, 15-20
8.38 mm high at center, 250 mm wide placed at 1 m
Suggestive sqm
center to center at approved locations to control
speed, marked with white strips of road marking
paint.)

Policeman Umbrella (Provision of a 2 m high


(floor to roof) umbrella for traffic policeman at road
8.39
Suggestive crossings, where necessary, installed on a raised Each #VALUE! #VALUE! #VALUE!
platform, built on a central support of a steel pipe
100 mm dia, roof made of 25 mm dia steel pipe to
provide covered area of 3 sqm, roofed with CGI
sheets, all steel parts to be given 2 coats of paint)
High Mast Pole Lighting at Interchanges and
Flyovers (Providing and erecting a high mast pole
lighting with 30 m high hot dip galvanised mast
designed to withstand forces exerted with wind
speeds of 180 km per hour with 3 seconds gust, as
per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal
lock, lantern carriage, suitable winching
8.40 arrangement for safe working load of 750 kg and
Suggestive high powered electrically driven power tools for
raising and lowering of lantern carriage, flexible 8
core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights
on top of the mast, all complete as per approved
design and drawings.This is a specialised work and
is generally done by firms who specialise in such
jobs. The detailed designs and estimates are
submitted by the firms along with their tender for
checks by the Department. The cost of this work is
required to be worked out based on approved
design, drawings and estimate of the lowest tender.
A separate contract for this work is concluded as the
contractors for road and bridge works generally
donot undertake such jobs.)
Toll Plaza (The construction, operation and
8.41 maintenance of Toll Plaza can be broken into
separate items of work as under based on the
approved design and drawings)
Safety Devices and Signs in Construction Zones
(Provision and fixing of traffic signs for limited period
at suitable locations in construction zone comprising
of warning zone, approach transition zone, working
8.42 zone and terminal transition zone with a minimum
distance of 60 cm from the edge of the kerb in case
of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom
edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6
mm angle iron post, founded and installed as per
approved design and drawings, removed and
disposed of after completion of construction work, all
as per IRC:SP:55) Each

Portable Barricade in Construction Zone (Installation


of a steel portable barricade with horizontal rail 300
8.43 mm wide, 2.5 m in length fitted on a 'A' frame made Each 2834.60 2887.10 2939.60
Suggestive with 45 x 45 x 5 mm angle iron section, 1.5 m in
height, horizontal rail painted (2 coats) with yellow
and white stripes, 150 mm in width at an angle of
45°, 'A' frame painted with 2 coats of yellow paint,
complete as per IRC:SP:55)
8.44
Suggestive Permanent Type Barricade in Construction Zone

With steel components (Construction of a


permanent type barricade made of steel
A components, 1.5 m high from road level, fitted with 3 Each 4433.10 4515.20 4597.30
horizontal rails 200 mm wide and 4 m long on 50 x
50 x 5 mm angle iron vertical support, painted with
yellow and white strips, 150 mm in width at an angle
of 45°, complete as per IRC:SP:55)

With wooden components (Construction of a


permanent type barricade made of wooden
B components, 1.5 m high from road level, fitted with 3 Each 9733.40 9913.70 10093.90
horizontal planks 200 mm wide and 3.66 m long on
100 x 100mm wooden vertical post, painted with
yellow and white strips, 150 mm in width at an angle
of 45°, complete as per IRC:SP:55 )
With bricks (Construction of a permanent type
barricade made with brick work in mud mortar, 1.5
C Each 15875.00 16169.00 16463.00
m high, 4 m long, 600 mm thick, plastered with
cement mortar 1:6, painted with yellow and white
strips)

Drum Delineator in Construction Zone (Provision of


8.45 metal drum/empty bitumen drum delineator, 300 mm Each 484.90 493.90 502.90
Suggestive in diameter, 800 mm high, filled with earth for
stability, painted in circumferential strips of alternate
black and white 100 mm wide fitted with reflectors 3
Nos of 7.5 cm dia, all as per IRC:SP:55)

Water filled barricades work zone sheeting


(Providing water filled barricades made up of LDPE
to segregate the vehicular movement and work zone
8.46 as per IRC SP 55 shall be in Trapezoidal Shape 800
Each #VALUE! #VALUE! #VALUE!
Suggestive mm to 1000 mm in length, 700 mm in height for
Major Roads and expressway and 500 mm tall for
other roads with interlocking arrangements, To be
placed 0.5 m from the edge of the carriageway for
expressway and 0.3 m for other roads. It should
have reboubdable work zone sheeting as per ASTM
D 4956 S2.)

Tubular Marker/ Spring Post 450 mm (Providing


Tubular Marker made up of Polyurethane used to
8.47 divide opposing lanes of road users shall be flexible Each #VALUE! #VALUE! #VALUE!
Suggestive in nature. Tubular marker having height upto 450
mm shall be having 75 mm Reboundable work zone
retroreflective sheeting as per ASTM 4956 S2.
Application of Tubular Marker shall be done as per
IRC SP 55.)

Tubular Marker/ Spring Post 700 mm (Providing


8.48 Tubular Marker made up of Polyurethane used to
Each #VALUE! #VALUE! #VALUE!
Suggestive divide opposing lanes of road users shall be flexible
in nature. Tubular marker having minimum height
700 mm shall be having minimum 75 mm
Reboundable work zone retroreflective sheeting as
per ASTM 4956 S2. Application of Tubular Marker
shall be done as per IRC SP 55.)
Flagman (Positioning of a smart flagman with a
8.49 yellow vest and a yellow cap and a red flag 600 x Each 454.30 462.70 471.10
Suggestive
600 mm securely fastened to a staff 1 m in length
for guiding the traffic)
Advanced Traffic Management System ( ATMS)
work shall cover design, supply, installation,
commissioning and / or operation and maintenance
of Advance Traffic Management Systems (which is
one of the components of intelligent Transport
Systems- ITS). The system would include out-door
equipment including emergency call boxes, variable
message sign systems, meteorological data system,
close circuit TV camera (CCTV) system, traffic
counting and classification system and transmittion
8.50 system. The indoor equipment would comprise a
large display board, central computer (with Network
Management System- NMS), CCTV monitor system,
call centre system or management of emergency
call boxes housed in a control centre with
uninterrupted power supply.

Traffifc Management Commond Centre Equipment


A

B Advanced Traffic Management System ( ATMS)


Software
C PTZ Closed Circuit Television System

D
Video Incident Detection System Equipment (VIDS)
E Automatic Traffic Counters-cum-classifier System
Equipment (ATCC)
F Variable Message Sign Equipment (VMS)
G UPS and Power system
H Meteorological Observation System (MOS)
I Digital Transmission System (DTS)
8.51 Fiber Reinforced Cement Concrete New Jersy
Suggestive Crash Barrier
Provision of an Reinforced cement concrete crash
barrier at th edges of the road, approaches to bridge
structures and medians, constructed with
Reinforced Cement Concrete with fiber steel and as
per details given IRC -5 ( Fig.- 5, b) including dowel
bars 25 mm dia, 450mm long at expansion joints Linear
A filled with pre-moulded asphalt filler board etc., as #VALUE! #VALUE! #VALUE!
metre
per approved drawing and at locations directed by
the engineer, all as specified. (Area- 0.243 Sqm/
Metre, Single Face)

Provision of an Reinforced cement concrete crash


barrier at the edges of the road, approaches to
bridge structures and medians, constructed with
Reinforced Cement Concrete with fiber steel and as
per details given IRC- 119 (Fig. -26) including dowel
bars 25 mm dia, 450 mm long at expansion joints Linear
B filled with pre-moulded asphalt filler board etc., as metre #VALUE! #VALUE! #VALUE!
per approved drawing and at locations directed by
the Engineer ,all as specified. (Area-0.261 Sqm./
meter, Double Face)
CHAPTER - 8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD
Unit
Sr. No. Ref. to M Description
8.01 409 Cast-in-Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M-15 grade foundation 150
mm thick, foundation having 50 mm projection beyond
kerb stone, kerb stone laid with kerb laying machine,
foundation concrete laid manually, all complete as per
clause 409

Unit = Running metre


Taking output = 360 metre
Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb Base
Total Concrete = 11.610 cu.m
a) Labour
Mate day
Mason day
Mazdoor day
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km
For loading and unloading hour
Water tanker (Speed @ 30 km/hr and return speed @
20km/hr and spreading speed @ 3 km/hr

(i) 16 KL Capacity hour

(ii) 12 KL capacity hour

(iii) 6 KL Capacity hour


c) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum
21.20)
Cost of water KL
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost of 360 meter= a+b+c+d+e
Rate per meter= (a+b+c+d+e)/360

(ii) PCC M20 for Kerb cast in situ


Total Concrete = 12.600 cu.m
a) Labour
Mate day
Mason day
Mazdoor day
b) Machinery
Kerb Casting machine @ 120 metres/hour hour
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km
For loading and Unloading time hour
Concrete cutting machine hour
Water tanker (Speed @ 30 km/hr and return speed @
20km/hr and spreading speed @ 3 km/hr

(i) 16 KL Capacity hour

(ii) 12 KL capacity hour

(iii) 6 KL Capacity hour


c) Material
Per Cum Basic Cost (Rate taken from sub-analysis
21.21) cum
Cost of water KL
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost of meter= a+b+c+d+e
Rate per meter= (a+b+c+d+e)/360

8.02 409
Cast in Situ Cement Concrete M 20 Kerb with Channel
Construction of cement concrete kerb with channel with
top and bottom width 115 and 165 mm respectively, 250
mm high in M 20 grade PCC on M15 grade foundation
150 mm thick, kerb channel 300 mm wide, 50 mm thick
in PCCM20 grade, sloped towards the kerb, kerb stone
with channel laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 409

Unit = Running metre


Taking output = 300 metre
Total Concrete = 9.675 cum.
Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb Base
Total Concrete = 9.675 cu.m
a) Labour
Mate day
Mason day
Mazdoor day
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km
For loading and Unloading time hour
Water tanker (Speed @ 30 km/hr and return speed @
20km/hr and spreading speed @ 3 km/hr

(i) 16 KL Capacity hour

(ii) 12 KL capacity hour

(iii) 6 KL Capacity hour


c) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum
21.20)
Cost of water KL
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost of 300 meter= a+b+c+d+e
Rate per meter= (a+b+c+d+e)/300

(ii) PCC M20 for Kerb Cast in situ


Total Concrete = 15.000 cu.m
a) Labour
Mate day
Mason day
Mazdoor day
b) Machinery
Kerb Casting machine @ 90 metres/hour hour
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km
For loading and Unloading time hour
Concrete cutting machine hour

Water tanker (Speed @ 30 km/hr and return speed @


20km/hr and spreading speeding @ 3 km/hr)
(i) 16 KL Capacity hour

(ii) 12 KL capacity hour

(iii) 6 KL Capacity hour


c) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum
21.21)
Cost of water KL
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost of 300meter= a+b+c+d+e
Rate per meter= (a+b+c+d+e)/300

8.03 801 Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved
colour to give an even shade
(i) Hindi ( Matras commas and the like not to be measured
and paid for Half letter shall be counted as half )

Details for 100 letters of 16 cm height i.e. 1600 cm


Unit = per cm height per letter
Taking output= 1600.00 cm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Paint Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter = (a+b+c+ d)/1600

8.03 (ii) English and Roman

Hyphens and the like not to be measured and paid for


Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
Taking output= 1600.00 cm
a) Labour
Mate day
Painter Ist class day
Mazdoor day
b) Material
Paint Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter = (a+b+c +d)/1600

8.04 801 Retro-Reflectorised Traffic Signs


A Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of
class-B Type IV retro reflective sheeting fixed cover 2
mm thick aluminium sheeting vide clause 801.3,
3mm/4mm thick aluminium composite material sheet
depending on the size of the sign fixed over back
support frame of min 25 x 25 x 3 mm Angle mounted on
a mild steel circular pipe 65 NB, 3.2 mm thickness firmly
fixed to the ground by means of properly designed
foundation with M25 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved
drawing. The sign shall be maintained as per section 12
of IRC 67.

Unit = Each
Taking output = one traffic sign

i) Excavation for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

ii) Cement concrete M25 grade sqm

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)

iii) Painting angle iron post two coats sqm

(Rate taken from item No. 8.09 including OH & CP)

a) Labour (For fixing at site)


Mate day
Mazdoor day
b) Material
Mild steel 'L' angle back support frame 25 x 25 x 3 mm kg

Mild steel circular pipe 65 NB, 3.2 mm thickness,3.6


kg
meter height
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs
as applicable
(i) 120 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( ii ) 90 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( iii ) 75 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( iv ) 60 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(v) 120 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(vi) 90 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc. sqm
or
(vii ) 75 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( viii) 60 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(ix) 90 cm x 75 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(x) 80 cm x 60 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xi ) 60 cm x 50 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xii ) 60 cm x 45 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xiii ) 60 cm x 60 cm square sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xiv ) 120 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xv ) 90 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xvi ) 75 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.

c) Machinery
Tractor-trolley hour

(i) 120 cm equilateral triangle


d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( ii ) 90 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( iii ) 75 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)
( iv ) 60 cm equilateral triangle

d) Overhead charges
e) Contractor's profit
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(v ) 120 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(vi) 90 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(vii) 75 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( viii) 60 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(ix) 90 cm x 75 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(x) 80 cm x 60 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xi ) 60 cm x 50 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xii ) 60 cm x 45 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xiii ) 60 cm x 60 cm square

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xiv ) 120 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xv ) 90 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xvi ) 75 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)
8.04 801 B Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of
class-C Type IX retro reflective sheeting fixed over 2mm
thick aluminium sheeting vide clause 801.3, 3/4mm
thick Aluminium composite material sheet depending on
the size of the sign fixed over back support frame of min
25 x 25 x 3 mm Angle mounted on a mild steel circular
pipe 65 NB, 3.2 mm thickness firmly fixed to the ground
by means of properly designed foundation with M25
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing. The sign
shall be maintained as per section 12 of IRC 67.

Unit = Each
Taking output = one traffic sign

i) Excavation for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

ii) Cement concrete M25 grade sqm

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)

iii) Painting angle iron post two coats sqm

(Rate taken from item No. 8.09 including OH & CP)


a) Labour (For fixing at site)
Mate day
Mazdoor day
b) Material
Mild steel 'L' angle back support 25 x 25 x 3 mm kg
Mild steel circulatar pipe 65 NB, 3.2 mm thickness,
kg
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs
as applicable
(i) 120 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( ii ) 90 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( iii ) 75 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( iv ) 60 cm equilateral triangle sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(v) 120 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(vi) 90 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc. sqm
or
(vii ) 75 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( viii) 60 cm circular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(ix) 90 cm x 75 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
(x) 80 cm x 60 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xi ) 60 cm x 50 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xii ) 60 cm x 45 cm rectangular sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xiii ) 60 cm x 60 cm square sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xiv ) 120 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xv ) 90 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.
or
( xvi ) 75 cm high octagon sqm
Add 1 per cent of cost of material (b) towards cost of
drilling holes, nuts, bolts etc.

c) Machinery
Tractor-trolley hour

(i) 120 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( ii ) 90 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( iii ) 75 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( iv ) 60 cm equilateral triangle

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(v ) 120 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)
(vi) 90 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(vii) 75 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( viii) 60 cm circular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(ix) 90 cm x 75 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

(x) 80 cm x 60 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xi ) 60 cm x 50 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xii ) 60 cm x 45 cm rectangular

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xiii ) 60 cm x 60 cm square

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xiv ) 120 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xv ) 90 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

( xvi ) 75 cm high octagon

d) Overhead charges on (a+b+c)


e) Contractor's profit on (a+b+c+d)
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)
Note
1.Any one area of aluminium sheeting given at (i) to (xvi)
may be adopted as per site requirement and in
accordance with IRC : 67
2.Rate for excavation, cement concrete M-25 and
painting may be taken from respective chapters- 08 & 09
respectively.
3. The depth of foundation and quantity of cement
concrete in the foundation are indicative. These may be
increased for areas having higher wind velocities like in
coastal areas. This is applicable to all road signs and
directions boards.

8.05 801 Direction and Place Identification Signs upto 0.9 sqm
Size Board.
Providing and erecting direction and place identification
retro-reflectorised sign as per IRC:67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick or Aluminium composite
material sheet with overall thickness of 4 mm with area
not exceeding 0.9 sqm fixed over back support frame of
min 35 x 35 x 3 mm Angle mounted on a mild steel
circular pipe 65 NB, firmly fixed to the ground by means
of properly designed foundation with M25 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as
per approved drawing
Unit = Each
Taking output = 0.9 sqm

i) Excavation for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

ii) Cement concrete M25 grade sqm

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)

iii) Painting angle iron post two coats sqm

(Rate taken from item No. 8.09 A including OH & CP)


a) Labour (For fixing at site)
Mate day
Mazdoor day
b) Material
Mild steel 'L' angle back support 35 x 35 x 3 mm kg
Mild steel circulatar pipe 65 NB, 3.2 mm thickness, 3.6 kg
meter height
Aluminium sheeting fixed with encapsulated lens type sqm
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes,
nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour
(a+b+c)
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 0.9 sqm= ( i+ii+iii+a+b+c+d+e)
Rate per sqm (for sign having area upto 0.9 sqm)= ( i+ii+iii+a+b+c+d+e)/0.90

I) Lettering and arrow marks on sign board to be


provided separately as per actual requirement. Rates for
Note these items have been analysed separately

ii) Rate for excavation, cement concrete M-25 and


painting may be taken from respective chapters-09 & 08
respectively.

8.06 801 Direction and Place Identification Signs with size more
than 0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick or Aluminium composite
material sheet with overall thickness of 4 mm with area
exceeding 0.9 sqm fixed over back support frame of min
40 x 40 x 5 mm Angle mounted on two nos. of mild steel
circular pipe 65 NB, 3.2mm thickness and 4.5m meter
total height firmly fixed to the ground by means of
properly designed foundation with M 25 grade cement
concrete 45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing

Unit = Each
Taking output = 1.5 sqm

i) Excavation for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

ii) Cement concrete M25 grade sqm

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)

iii) Painting angle iron post two coats sqm

(Rate taken from item No. 8.09 including OH & CP)


(i+ii+iii)
a) Labour (For fixing at site)
Mate day
Mazdoor day
b) Material
Mild steel 'L' angle back support 40 x 40 x 5 mm kg

Mild steel circulatar pipe 65 NB, 3.2 mm thickness, 3.6 kg


meter height
Aluminium sheeting fixed with encapsulated lens type sqm
reflective sheeting
Add 2 per cent of cost of materials for drilling holes,
nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour
(a+b+c)
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 1.5 sqm= ( i+ii+iii+a+b+c+d+e)
Rate per sqm (for sign having area more than 0.9 sqm)= ( i+ii+iii+a+b+c+d+e)/1.50

Note I) Lettering and arrow marks on sign board to be provided separately as per actual requiremen
beenii)analysed separately cement concrete M-25 and painting may be taken from respective
Rate for excavation,

8.07 802 Overhead Signs


Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised
with high intensity retro-reflective sheeting of
encapsulated lense type with vertical and lateral
clearance given in clause 802.2 and 802.3 and installed
as per clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and trusses
of sections and type as per structural design
requirements and approved plans & as per IRC: 67

A Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day
Blacksmith day
Mazdoor including for handling & fixing at site. day
b) Material
Aluminium alloy/galvanised steel including 2 per cent
tonne
wastage
Add 1 per cent on cost of material for nuts, bolts and
drilling and welding consumables
Add 15 per cent on cost of material for fabrication of
trusses as per approved design
c) Machinery
Crane 3 tonne capacity hour
Truck hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Rate per tonne = (a+b+c+d+e)

8.07 B Aluminium Alloy Plate for Over Head Sign


Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day
Blacksmith day
Mazdoor day
b) Material
Aluminium alloy plate,2 mm thick, fixed with high
sqm
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement,
like ladders, pulleys, ropes etc
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per sqm = (a+b+c+d)

Note 1. The cost of excavation and foundation concrete for fixing of vertical support system to be w
2. Letteringas
separately and
perarrow marks ondrawing/design
the approved sign board to beand
provided separately
to be included as per
in the actual requireme
estimate.
items have been included separately in this chapter.

8.08 803 Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Paint conforming to requirement of clause 803.3. Litre
Add for scaffolding @ 1 percent of labour cost where
required
Add @ 5 percent cost of labour and materials to prepare
the surface by filling minutes roughness on the surface
and priming the surface before laying 2 costs of painting.

Total cost without OH & CP


c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 40 sqm = a+b+c+d
Rate per sqm = (a+b+c+d) /40

8.09 803 Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning
of surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Paint ready mixed approved brand. Litre
Add @ 1 per cent on cost of material for scaffolding

Add @ 5 percent cost of labour and materials to prepare


the surface by filling minutes roughness on the surface
and priming the surface before laying 2 costs of painting.

Total cost without OH & CP


c) Overhead charges on (a+b)
d) Contractor's profit (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/10

8.10 803 Painting on Wood Surfaces


Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough
cleaning of surface to give an even shade

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Paint ready mixed of approved brand. Litre
Add @ 1 per cent on cost of material for scaffolding
Add @ 5 percent cost of labour and materials to prepare
the surface by filling minuts roughness on the surface
and priming the surface before laying 2 costs of painting.

Total cost without OH & CP


c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
8.11 803 Painting Lines, Dashes, Arrows etc on Roads in Two
Coats on New Work
Painting lines, dashes, arrows etc on roads in two coats
on new work with ready mixed road marking paint
conforming to IS:164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control

(i) Over 10 cm in width


Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Road marking Paint as per IS :164 Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/10

8.11 (ii) Up to 10 cm in width


Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter day
Mazdoor day
b) Material
Road marking paint Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

8.12 803 Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on Old Work
Painting lines, dashes, arrows etc on roads in two coats
on old work with ready mixed road marking paint
conforming to IS: 164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter Ist class day
Mazdoor day
b) Material
Road marking paint Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

8.12 (ii) Up to 10 cm in width


Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day
Painter Ist class day
Mazdoor day
b) Material
Road marking Paint Litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 10 sqm= a+b+c+d
Rate per sqm = (a+b+c+d)/10

8.13 803 Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface

Providing and laying of hot applied thermoplastic


compound 2.5 mm thick including reflectorising glass
beads @ 250 gms per sqm area, thickness of 2.5 mm is
exclusive of surface applied glass beads as per
IRC:35 .The finished surface to be level, uniform and
free from streaks and holes.
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day
Mazdoor day
b) Machinery
Road marking machine @ 60 sqm per hour hour
Tractor-trolley hour
c) Material
Hot applied thermoplastic compound Litre
Reflectorising glass beads kg
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 600 sqm = a+b+c+d+e
Rate per sqm = a+b+c+d+e)/600
Note 1. A sealing primer may be applied in advance on cement concrete pavement to ensure prope
laitance
2.Cost ofand/or
paintercuring compound
is already to be
included removed
in hire where
charges paintmarking
of road is required to be applied on conc
machine.

8.14 804 Kilometre Stone


Reinforced cement concrete M15grade kilometre stone
of standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.

a) M-15 grade of concrete cum

(Rate taken from item No. 9.06, A, Case-II including OH


& CP)

b) Steel reinforcement @ 5 kg per sqm kg

( Rate taken from items 9.07/1000 including OH & CP)

c) Excavation in soil for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

d) Painting two coats on concrete surface sqm

(Rate taken from item No. 8.08 including OH & CP)

per cm
e) Lettering on km post (average 30 letters of 10 cm per
height each) letter
(Rate taken from item No. 8.03(ii) including OH & CP)

Transportation and fixing


f) Labour
Mate day
Mason day
Mazdoor including loading/unloading day
g) Machinery
Tractor-trolley hour
h) Overhead charges on (f+g)
i) Contractor's profit on (f+g+h)
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i
Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/ 6

8.14 (ii) Ordinary kilometer stone (precast)


Unit = Nos.
Taking output = 14 Nos.

a) M-15 grade of concrete cum

(Rate taken from item No. 9.06, A, Case-II including OH


& CP)

b) Steel reinforcement @ 5 kg per sqm kg

( Rate taken from items 9.07/1000 including OH & CP)

c) Excavation in soil for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

d) Painting two coats on concrete surface sqm

(Rate taken from item No. 8.08 including OH & CP)

per cm
e) Lettering on km post ( average 12 letters of 10 cm
per
height each)
letter

(Rate taken from item No. 8.03 (ii) including OH & CP)
Transportation and fixing
f) Labour
Mate day
Mason day
Mazdoor day
g) Machinery
Tractor-trolley hour
h) Overhead charges on (f+g)
i) Contractor's profit on (f+g+h)
Cost for 14 Nos. ordinary km stone = (a+b+ c+d+e+f+g+h+i)
Rate for each ordinary km stone = (a+b+ c+d+e+f+g+h+j) /14

8.14 (iii) Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.

a) M-15 grade of concrete cum

(Rate taken from item No. 9.06, A, Case-II including OH


& CP)

b) Steel reinforcement @ 5 kg per sqm kg

( Rate taken from items 9.07/1000 including OH & CP)

c) Excavation in soil for foundation cum

(Rate taken from item No. 9.01 A (I) including OH & CP)

d) Painting two coats on concrete surface sqm

(Rate taken from item No. 8.08 including OH & CP)

per cm
e) Lettering on km post ( average 1 letter of 10 cm
per
height each)
letter

(Rate taken from item No. 8.03(ii) including OH & CP)


Transportation and fixing
f) Labour
Mate day
Mason day
Mazdoor day
g) Machinery
Tractor-trolley hour
h) Overhead charges on (f+g)
i) Contractor's profit on (f+g+h)
Cost for 33 Nos. Hectometer stone = (a+b+c+d+e+f+ g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i) / 33
Note The rate for excavation, cement concrete, steel reinforcement, painting and lettering may be t
respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (Road way
indicators, hazard markers, object markers), 80-100 cm
high above ground level, painted black and white in 15
cm wide strips, fitted with 80 x 100 mm rectangular or 75
mm dia circular reflectorised panels at the top, buried or
pressed into the ground and conforming to IRC-79 and
the drawings.

Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day
Mazdoor for fixing day
b) Material

Cost of approved type of delineators from ISI certified each


firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 30 Nos. delineators = (a+b+ c+d)
Rate per delineators = (a+b+c+d) /30
Note In case of soft ground, a proper foundation may be provided as per approved design. In case
required to be provided, the items of excavation and foundation concrete are required to be m
8.16 806 Boundary pillar
Reinforced cement concrete M15 grade boundary pillars
of standard design as per IRC:25, fixed in position
including finishing and lettering but excluding painting

Unit = Each
Taking output = 57 Nos.
a) M-15 grade of the boundary stone

(Rate taken from item No. 9.06, A, Case-II including OH


cum
& CP)

b) Steel reinforcement

( Rate taken from items 9.07/1000 including OH & CP) kg

c) Excavation in soil
(Rate taken from item No. 9.01 A (I) including OH & CP) cum

d) Lettering, each 10 cm high

per
letter
(Rate taken from item No. 8.03(ii) including OH & CP)
per cm
high

Transportation and fixing


e) Labour
Mate day
Mazdoor day
f) Machinery
Tractor-trolley hour
g) Material
Stone spall cum
h) Overhead charges on (e+f+g)
i) Contractor's profit on (e+f+g+h)
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )
Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

Note In case of soft ground, a proper foundation may be provided as per approved design. In case
required to be provided, the items of excavation and foundation concrete are required to be m
8.17 808 G.I Barbed Wire Fencing 1.2 Metre High
Providing and fixing 1.2 metres high GI barbed wire
fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6
mm placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner
post shall be strutted on both sides and end post on one
side only and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc complete as per clause 817

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate day
Blacksmith day
Mazdoor day
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 kg
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in kg
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.08) sqm

Total cost without OH & CP


d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 30 metres fencing = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/30

Note Cost of excavation for foundation and foundation concrete to be added separately in the cost
approved design. The rate for these items may be taken from respective chapters.
8.18 808 G.I Barbed Wire Fencing 1.8 Metre High

Providing and fixing 1.8 metres high GI barbed wire


fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6
mm placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner
post shall be strutted on both sides and end post on one
side only and provided with 12 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc complete as per clause 808
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day
Blacksmith day
Mazdoor day
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 kg
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in kg
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
c) Painting

Applying two coats of painting on exposed surface of


sqm
angle iron posts

Total cost without OH & CP


d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 30 metres fencing = a+b+c+d+e
Rate per metre fencing = (a+b+c +d+e)/30

Note Cost of excavation for foundation and foundation concrete to be added separately in the cost
approved design. The rate for these items may be taken from respective chapters.
8.19 Suggestive
Fencing With Welded Steel Wire Fabric 75 mm x 50 mm
Providing 1.20 metre high fencing with angle iron posts
50 mm x 50 mm x 6 mm at 3 metre center to center with
0.40 metre embedded in M15 grade cement concrete,
corner, end and every 10th post to be strutted, provided
with welded steel wire fabric of 75 mm x 50 mm mesh or
75 mm x 25 mm mesh and fixed to iron posts by flat iron
50 x 5 mm and bolts etc. complete in all respects.

Unit = Running metre


Taking output = 30 m
a) Labour
Mate day
Welder day
Mazdoor day
b) Material

i) Angle iron for posts 50 x 50 x 6 mm kg

ii) Runner flat 50 x 5 mm kg


iii) Welded steel wire fabric 75x50 mm mesh @ 4 kg
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage kg

Add 2.5 per cent of cost of material for drilling holes in


angles, flats, splitting angle at bottom, nuts and bolts
and welded consumables
c) Machinery
Tractor-trolley hour
(a+b+c)
d) Painting

Painting two coats including priming sqm

e) Overhead charges (a+b+c)


f) Contractor's profit (a+b+c+e)
Cost for 30 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/30

Note i) Adopt any one type of welded steel wire fabric 75 x 50 mm or 75 x 25 mm as per app
ii) The item of excavation and cement concrete in foundation shall be measured and pa

8.20 808 Tubular Steel Railing on Medium Weight Steel Channel


( ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe
railing in 3 rows duly painted on medium weight steel
channels (ISMC series) 100 mm x 50 mm, 1.2 metres
high above ground, 2 m centre to centre, complete as
per approved drawings

Unit = Running metre


Taking output = 10metres

i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6

cum
(Rate taken from item No. 9.01 A (I) including OH & CP)
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x
0.3

(Rate taken from item No. 9.06, A, Case-II including OH cum


& CP)
iii) Painting of pipe

(Rate taken from item No. 8.09 including OH & CP) sqm

iv) Painting of channel section 6 nos,1.8 metres each


sqm
0.2x1.8x6=2.16

a) Labour (For fixing at site)


Mate day
Mazdoor day
Plumber day
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre
Medium weight steel channel (ISMC series) 100 mm x
50 mm,10.8 metres length @ 9.2 kg per metre kg

Add for drilling holes @ 2 per cent of cost of channels


c) Machinery
Tractor-trolley hour
(a+b+c)
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

8.21 808 Tubular Steel Railing on Precast RCC Posts, 1.2 m High
Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel
pipe railing in 3 rows on precast M20 grade RCC vertical
posts1.8 metres high (1.2 m above GL) with 3 holes 50
mm dia for pipe, fixed 2 metres centre to, complete as
per approved drawing

Unit = Running metre


Taking output = 10metres

i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6

(Rate taken from item No. 9.01 A (I) including OH & CP) cum

ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 x


0.3

(Rate taken from item No. 9.06, A, Case-II including OH


cum
& CP)

iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres


each

(Rate taken from item No. 9.06, B, Case-II including OH


cum
& CP)

iv) Painting of pipe

(Rate taken from item No. 8.09 including OH & CP) cum

a) Labour
Mate day
Mazdoor day
Plumber day
b) Material
Steel pipe 50 mm dia as per IS:1239 metre
c) Machinery
Tractor-trolley hour
(a+b+c)
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

8.22 811 Reinforced Cement Concrete Crash Barrier


A Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to bridge
structures and medians, constructed with Reinforced
Cement Concrete with HYSD reinforcement conforming
to MoRT&H specification and as per details given IRC-5
(Fig.-5, b) including dowel bars 25 mm dia, 450 mm long
at expansion joints filled with pre-moulded asphalt filler
board etc., as per approved drawing and at locations
directed by the Engineer, all as specified. (Area- 0.243
sqm./meter, single face)

Unit = Linear metre


Taking output = 20 m
A (i) M 25 grade concrete

a) M 25 grade concrete & HYSD steel reinforcement

M 25 grade concrete ( Area-0.243 sqm/meter) cum

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)
HYSD steel reinforcement including dowel bars tonne
b) Labour
Mate day
Mazdoor day
c) Material
Pre-moulded asphalt filler board sqm
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20

8.22 A (ii) M 30 grade concrete


a) M 30 grade concrete & HYSD steel reinforcement

M 30 grade concrete ( Area-0.243 sqm/meter cum

(Rate taken from item No. 9.06, E, Case-II including OH


& CP)
HYSD steel reinforcement including dowel bars tonne
b) Labour
Mate day
Mazdoor day
c) Material
Pre-moulded asphalt filler board sqm
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20

Note i) Excavation and backfilling are incidental to work and not to be measured separately.
ii)If PCC required below crash barrier then it should be measured & Paid separately.
iii) Rate for RCC M 30 may be taken from chapter-12 on foundation.

B Provision of an Reinforced cement concrete New Jersy


crash barrier at the medians constructed with Reinforced
cement concrete with HYSD reinforcement conforming
to MoRT&H specification and as per details given IRC-
119 (Fig.-26) including dowel bars 25 mm dia, 450 mm
long at expansion joints filled with pre-moulded asphalt
filler board etc.,as per approved drawing and at
locations directed by the Engineer, all as specified.
(Area- 0.261 sqm./meter, Double Face)

Unit = Linear metre


Taking output = 20 m
(i) M 25 grade concrete

a) M 25 grade concrete & HYSD steel reinforcement


M 25 grade concrete ( Area-0.261 sqm/meter cum

(Rate taken from item No. 12.11 A (ii), Case-II including


OH & CP)
HYSD steel reinforcement including dowel bars tonne
b) Labour
Mate day
Mazdoor day
c) Material
Pre-moulded asphalt filler board sqm
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20

Note i) Excavation and backfilling are incidental to work and not to be measured separately.
ii)If PCC required below crash barrier then it should be measured & Paid separately.
iii) Rate for RCC M 25 may be taken from chapter-12 on foundation.
8.22 B (ii) M 30 grade concrete

a) M 30 grade concrete & HYSD steel reinforcement


M 30 grade concrete ( Area-0.261 sqm/meter cum

(Rate taken from item No. 12.11 A (iii), Case-II including


OH & CP)
HYSD steel reinforcement including dowel bars tonne
b) Labour
Mate day
Mazdoor day
c) Material
Pre-moulded asphalt filler board sqm
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20

Note i) Excavation and backfilling are incidental to work and not to be measured separately.
ii)If PCC required below crash barrier then it should be measured & Paid separately.
iii) Rate for RCC M 30 may be taken from chapter-12 on foundation.

8.23 811 Metal Beam Crash Barrier


A Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam
rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2
m centre to centre, 1.8 m high, 1.1 m below ground/road
level, all steel parts and fitments to be galvanised by hot
dip process, all fittings to conform to IS:1367 and
IS:1364, metal beam rail to be fixed on the vertical post
with a spacer of channel section 150 x 75 x 5 mm, 330
mm long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day
Blacksmith day
Mazdoor day
b) Machinery
Tractor-trolley hour
c) Material
Corrugated sheet,3 mm thick, "W" beam section
railing,4.5 m in length kg

Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg


kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ kg
16.4 kg per metre
Nuts and bolts kg
Add 25 per cent of the cost of material for fabrication,
nuts, bolts and washers etc.)
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/4.5

8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash
barrier comprising of 3 mm thick corrugated sheet metal
beam rail, 85 cm above road/ground level, fixed on
ISMC series channel vertical post, 150 x 75 x 5 mm
spaced 2 m centre to centre, 2 m high with 1.15 m below
ground level, all steel parts and fitments to be
galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a space of channel section 150 x 75 x
5 mm, 546 mm long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day
Blacksmith day
Mazdoor day
b) Machinery
Tractor-trolley hour
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section kg
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 kg
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg
Nuts and bolts kg
Add 15 per cent of the cost of material for fabrication,
nuts, bolts and washers etc.)
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e
Rate per metre= (a+b+c+d+e)/4.5

Note In the case of median crash barrier, 'W' metal beam or thrie beam section should be provided
the vertical posts fixed in the median. Extra provision for metal beam railing and spacer is req
8.24 811 Road Traffic Signals electrically operated
Since it is a ready made item commercially produced
and erected by specialised firm in the electrical and
electronic field, rate may be taken based on market
Note enquiry from firms specialised in this field and ISI
certified for the approved design and drawing.

8.25 Suggestive Flexible Crash Barrier, Wire Rope Safety Barrier


Providing and erecting a wire rope safety barrier with
vertical posts of medium weight RS Joist (ISMB series)
100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m
above ground and 0.65 m below ground level, split at
the bottom for better grip, embedded in M 15 grade
cement concrete 450 x 450 x 450 mm, 1.50 m center to
center and with 4 horizontal steel wire rope 40 mm dia
and anchored at terminal posts 15 m apart. Terminal
post to be embedded in M 15 grade cement concrete
foundation 2400 x 450 x 900 mm (depth), strengthened
by a strut of RS joist 100 x 75 mm, 2 m long at 45°
inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation
and cement concrete.

Unit = Running metre


Taking output = 15 metre
a) Labour
Mate day
Mazdoor day
Blacksmith day
b) Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 kg


x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
terminal posts @ 62.80 kg/sqm (2 x 1.5) kg
iv) Steel wire rope 40 mm, including 7.50 per cent extra
for fixing at ends 15 x 4 x 1.075 @ 1 kg per m kg

Add 5 per cent of cost of material for drilling, gripping,


fixing, fabrication and welding consumables

(a+b)
c) Painting

Applying 2 coats of painting on exposed surface sqm

(Rate taken from item no. 8.09 including OH & CP)


d) Machinery
Tractor-trolley hour
e) Overhead charges on (a+b+d)
f) Contractor's profit on (a+b+d+e)
Cost for 15 m = a+b+c+d+e+f
Rate per m = (a+b+c+d+e+f)/15

Note The items of excavations and cement concrete works will be measured and included separate
approved designs and drawings.
8.26 Suggestive Anti-Glare Devices in Median
A Plantation
Plantation of shrubs and plants of approved species in
the median. apart from cutting off glare from vehicle
coming from opposite direction, these plants provide a
pleasant envoirenment and are eco-friendly. The rate for
this item is available in the chapter 11 on horticulture.

B Anti-glare screen with 25 mm steel pipe framework fixed


with circular and rectangular vans

Providing and erecting an anti - glare screen with 25 mm


dia vertical pipes fabricated and framed in the form of
panels of one metre length and 1.75 metre height fixed
with circular vane 250 mm dia at top and rectangular
vane 600 x 300 mm at the middle, made out of steel
sheet of 3 mm thickness, end vertical pipes of the panel
made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as
per approved design and drawings.

Unit = Running metre


Taking output = one metre
a) Labour
Mate day
Mazdoor day
b) Material
i) 25 mm steel pipe metre
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one kg
number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 kg
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c) Painting

Applying 2 coats of painting on exposed surface sqm

(Rate taken from item no. 8.09 including OH & CP)


d) Overhead charges on (a+b)
e) Contractor's profit on (a+b+d)
Rate per metre = a+b+c+d+e

Note The items of excavation and cement concrete as per approved design to be measured and pa

8.26 C
Anti-glare screen with rectangular vane of MS sheet
Providing and erecting anti - glare screen with
rectangular vanes of size 750 x 500 mm made from MS
sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6
mm at an angle of 45° to the direction of flow of traffic,
1.5 m center to center, top edge of the screen 1.75 m
above ground level, vertical post firmly embedded in M-
15 cement concrete foundation 0.60 m below ground
level, applying 2 coats of paint on exposed faces, all
complete as per approved design and drawings

Unit = Running metre


Taking output = 1.50 metre
a) Labour
Mate day
Mazdoor day
b) Material
i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg
ii) MS sheet 3 mm thick @ 24 kg/sqm kg
Add 5 percent of cost of material for
fabrication,nuts,bolts etc
c) Machinery
Tractor-trolley hour
d) Painting
Applying 2 coats of painting sqm

(Rate taken from item no. 8.09 including OH & CP)


e) Overhead charges on (a+b+c)
f) Contractor's profit on (a+b+c+e)
Cost for 1.5 m = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/1.50

Note The items of excavation and cement concrete as per approved design to be measured and pa
of painting has been analaysed separately in this chapter.
8.27 Suggestive Street Lighting
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 10 m high spaced 40 m apart, 1.8 m overhang
on both sides if fixed in the median and on one side if
fixed on the footpath, fitted with sodium vapour lamp and
fixed firmly in concrete foundation.

Unit = Each
Taking output = one light
a) Labour
Mate day
Mazdoor day
Electrician day
b) Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 10 m height above road each
level
ii) Sodium vapour lamp each
Add 5 percent of cost of material for holder, electric
cable, insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median

Providing two coats of alluminium paint over steel


sqm
circular hollow pipe with overhang on both sides

For fixing in Footpath

Providing two coats of alluminium paint over steel


sqm
circular hollow pipe with overhang on one side

(i) For Fixing in Median


d) Overhead charges on (a+b)
e) Contractor's profit on (a+b+d)
Rate per light for fixing in Median= a+b+c+d+e
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e

Note The items of excavation and cement concrete foundation will be measured and included sepa
drawing. The rate for painting has been analysed in this chapter.
8.28 Suggestive Lighting on Bridges
Providing and fixing lighting on bridges, mounted on
steel hollow circular poles of standard specifications, 5
m high fixed on parapets with cement concrete, 20 m
apart and fitted with sodium vapour lamp

Unit = Each
Taking output = one light
a) Labour
Mate day
Mazdoor day
Electrician day
b) Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 5 m above deck level each

ii) Sodium vapour lamp 70 watt each


Add 1 per cent of cost of material for holder, electric
cable, insulation, ladder, scaffolding etc
c) Painting

Providing two coats of alluminium paint over steel


sqm
circular hollow pipe

(Rate taken from item no. 8.09 including OH & CP)


d) Overhead charges @ on (a+b)
e) Contractor's profit @ on (a+b+d)
Rate per light = a+b+c+d+e

Note The items of cement concrete to be measured and paid separately as per approved design. T
has already been analysed in this chapter.
8.29 Suggestive Cable Duct Across the Road
Providing and laying of a reinforced cement concrete
pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and
toe of slope to toe of slope in fills, constructing head
walls at both ends, providing a minimum fill of granular
material over top and sides of RCC pipe as per IRC:98-
1997, bedded on a 0.3 m thick layer of granular material
free of rock pieces, outer to outer distance of pipe at
least half dia of pipe subject to minimum 450 mm in
case of double and triple row ducts, joints to be made
leak proof, invert level of duct to be above higher than
ground level to prevent entry of water and dirt, all as per
IRC: 98 - 1997 and approved drawings.

(i) Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in cement
cum
mortar 1:6 for head wall both side

( Rate taken from item no. 12.07(B) including OH & CP)


b) Labour
Mate day
Mazdoor day
Mazdoor skilled day
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre
Granular soil with PI less than 6 for bedding and sides of
pipe (0.6 x 0.6 x 20 m) cum
Collar for joints 300 mm dia each
Cement mortar 1:2 for joints cum
( Rate taken from item no. 15.05 B)
d) Machinery
Tractor-trolley hour
e) Overhead charges on (b+c+d)
f) Contractor's profit on (b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20

8.29 (ii) Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
(Rate taken from item no. 12.07 B) cum
b) Labour
Mate day
Mazdoor day
Mazdoor skilled day
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre
Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each
Cement mortar 1:2 for joints cum
( Rate taken from item no. 15.05 B)
d) Machinery
Tractor-trolley hour
(b+c+d)
e) Overhead charges on (b+c+d)
f) Contractor's profit on (b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20

8.29 (iii) Triple Row for three utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonary/Brick masonry in cement cum
mortar 1:6 for head wall both sides.

(Rate taken from Item No. 12.07 B including OH & CP)


b) Labour
Mate day
Mazdoor day
Mazdoor skilled day
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre
Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each
Cement mortar 1:2 for joints
(Rate taken from sub-analysis 21.01 B) cum
d) Machinery
Tractor-trolley hour
(b+c+d)
e) Overhead charges on (b+c+d)
f) Contractor's profit on (b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
Note 1.Inspection chamber at both ends is the responsibility of the agency who is laying the duct. H
2.The rates for stone masonry / brick masonry and cement mortar to be adopted from res
8.30 Suggestive Highway Patrolling and Traffic Aid Post
It is proposed to locate one Traffic Aid Post every 50-60
km of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .

8.31 Suggestive Items Related to Underpass/ Subway/ Overhead Bridge/


Overhead Foot Bridge

The items involved for underpass/ subway/ overhead


bridge/ overhead foot bridge are earthwork, plain
cement concrete, plastering, painting, information sign
etc. The rates for these items are available in respective
chapters which can be adopted for the quantities derived
from the approved designs and drawings

8.32 Suggestive
Traffic Control System and Communication System
Providing a traffic control centre and communication
system including telecommunication facilities and
related accessories, CCTV, radar, vehicle detection
camera, central computer system

These are specialised item of telecommunication system


and are the commercial products. The designer is
required to contact the manufacturers to ascertain
market prices. In case of civil works required to be
executed for these installations, pricing may be done as
per rates in relevant chapters for quantities derived as
per approved design and drawing.

As regards the locations where such devices are


required to be installed, the traffic control authority
should be consulted to finalise the location

8.33 Suggestive Gantry Mounted Variable Message Sign Board


(i) Providing and erecting gantry mounted variable
message sign board electronically operated capable of
flashing the desired message over a designed support
system of aluminium alloy or galvanised steel, erected
as per approved design and drawings and with lateral
clearance as per clause 802.3
Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day
Mazdoor day
Blacksmith day
b) Material
Alluminium alloy/galvanised steel including 5 per cent tonne
wastage
Add 15 per cent of cost of material for fabrication and
erection.
Add 1 per cent of cost of material for nuts, bolts and
welding
c) Machinery
Truck 10 tonne hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Rate per tonne = a+b+c+d+e
8.33 (ii) Message Display
Message display board 6 sqm electronically operated
with complete electronic fitments for flashing the pre-
determined messages.This is a specilised commercial
product and the lumpsum rate including erection at site
is required to be as certained from the market and
including in the rate analysis. The size of the board will
vary depending upon specific location.The rate for the
gantry mounted variable sign would be the addition of
cost of gantry support system as per approved design
determined at (i) above and the cost of message display
board as certained from the market at (ii) above

8.34 Suggestive
Traffic Impact Attenuators at Abutments and Piers
A With Scrap Tyres
Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of
size 100 x 20 retrieved from trucks laid in 2 rows and 4
tiers, one above the other and tied with 20 mm wire rope
as per approved design and drawings.

Unit = sqm
Taking output = 20sqm
a) Labour
Mate day
Mazdoor day
Blacksmith day
b) Material
Scrap tyres of size 900 x 20 each
20 mm steel wire rope kg
Add 1 per cent of cost of wire rope for clamps etc.
c) Machinery
Tractor-trolley hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20

8.34 B Using Plastic/Steel Barrel, Filled with Sand


Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel
barrels 0.60 m dia and 1.0 m in height, filled with sand in
three rows and tied with 20 mm steel wire rope as per
approved design and drawings

Unit = sqm
Taking output = 20sqm
a) Labour
Mate day
Mazdoor day
Blacksmith day
b) Material
Plastic barrels each
or
Steel barrels each
Sand cum
20 mm steel wire rope kg
Add 1 per cent of cost of wire rope for clamps etc.

c) Machinery
Tractor-trolley hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)

Providing and installing a patentend HI - DRO cell


system as a traffic impact attenuators, using plastic
tubes 50 cm dia, 1.2 m in height, 25 mm opening at the
top, placed in three rows, filled with water and tied with a
20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day
Mazdoor day
b) Material
Plastic tubes 50 cm dia,1.2 m high each
Cost of water KL
20 mm steel wire rope kg

Add 1 per cent of cost of wire rope for clamps etc.


c) Machinery
Tractor-trolley hour
Water tanker6 KL capacity hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10

8.35 Suggestive Solar Powered Road Marker (Solar Stud)


Supplying of Solar Raised Pavement Markers made of
polycarbonate molded body with circular shape, solar
powered, LED self illumination in active mode, 360
degree illumination and reflective panels with micro
prismatic lens capable of providing total internal
reflection of the light entering the lens face in passive
mode. The marker shall support a load of 20000 kg
tested in accordance to ASTM D 4280. The marker
should be resistant to dust and water ingress according
to IP 65 standards and should withstand temperatures in
the range of 0 C to 70 C. Color of lighting could be
provided in red or yellow (amber) as per requirement
and typical frequency of blinkikng in 1 Hz. There should
be current losses of less than 20 microamperes at 2.4 V
in sleepcharging mode to enhace the life of the marker
and a full charge should provide for a minimum
autonomy of 50 hours. The height, width and length of
the marker shall not be less than 10mm x 100 mm x 100
mm. Also, the surface diameter of the marker shall not
be less than 100 mm respectively. The weight of the
marker shall not exceed 0.5 Kilograms. Fixing will be by
drilling holes on the road for the shanks to go inside,
without nails and using epoxy resin based adhesive and
complete as directed by the engineer.

Unit = Nos
Taking output = 50Nos
a) Labour
Mate day
Mazdoor day
b) Material
Poly carbonate or ABS body and shall support a load of
13.635 kg tested in accordance to ASTM D 4280 with
heigth not exceeding 20 mm and width/length not each
exceeding 130mm

Add 10 per cent of cost of material for fixing and


installation
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Cost for 50 studs = a+b+c+d
Rate per studs = (a+b+c+d)/50

8.36 Suggestive Traffic Cone


Provision of red fluorescent with white reflective sleeve
traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m
interval, all as per BS 873

Unit = Each
Taking output = 68 Nos.
a) Labour
Mate day
Mazdoor day
b) Material
Traffic cones with 150 mm reflective sleeve each
c) Machinery
Tractor-trolley hour
Total cost without OH & CP
d) Overhead charges on (a+b+c)
e) Contractor's profit on (a+b+c+d)
Cost for 68 Nos. = a+b+c+d+e
Rate per no = (a+b+c+d+e)/68

8.37 Suggestive Roadside Amenities


A Rest areas
Providing plainly furnished accommodation for rest
rooms, dormitories, restaurants, stalls, shops, petrol
pump, telephone booth, first aid room, traffic aid post,
police assistance booth, including electricity, toilet and
sewerage system.
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone.
Area is required to be assessed for specific location as
per actual site conditions.

B Parking areas and bus laybyes for trucks, buses and


light vehicles

Pricing of parking areas may be done for the quantities


of various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.
C Lawn

Providing a lawn planted with grass and its maintenance


Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per
approved dimensions in the drawings
8.38 Suggestive Rumble Strips

Provision of 15 nos rumble strips covered with premix


bituminous carpet, 15-20 mm high at center, 250 mm
wide placed at 1 m center to center at approved
locations to control speed, marked with white strips of
road marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking
may be adopted from chapter 5 & 8 respectively for the
quantities calculated from approved drawings

8.39 Suggestive Policeman Umbrella


Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed
on a raised platform, built on a central support of a steel
pipe 100 mm dia, roof made of 25 mm dia steel pipe to
provide covered area of 3 sqm, roofed with CGI sheets,
all steel parts to be given 2 coats of paint

Unit = each
Taking output = one number
Earthwork cum
Cement Concrete/ cum
brick masonry or cum
stone masonry cum
Painting

(Rate taken from item no. 8.09 including OH & CP) sqm

a) Labour
Mate day
Mazdoor day
Blacksmith day
Welder day
b) Material
Steel pipe 100 mm dia metre
Steel pipe 25 mm dia metre
CGI sheets kg
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding
consumables, J-hooks, washers etc.
c) Machinery
Tractor-trolley hour
Total cost without OH & CP
d) Overheads charges on (a+b+c)
e) Contractors Profit on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e

8.40 Suggestive
High Mast Pole Lighting at Interchanges and Flyovers
Providing and erecting a high mast pole lighting with 30
m high hot dip galvanised mast designed to withstand
forces exerted with wind speeds of 180 km per hour with
3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with
a base flange, door at the base of mast with heavy duty
internal lock, lantern carriage, suitable winching
arrangement for safe working load of 750 kg and high
powered electrically driven power tools for raising and
lowering of lantern carriage, flexible 8 core electric
cable, lightening conductor, earthing terminal, and fixing
2 nos aviation obstruction lights on top of the mast, all
complete as per approved design and drawings

This is a specialised work and is generally done by firms


who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their
tender for checks by the Department. The cost of this
work is required to be worked out based on approved
design, drawings and estimate of the lowest tender. A
separate contract for this work is concluded as the
contractors for road and bridge works generally donot
undertake such jobs.

8.41 Toll Plaza

The construction, operation and maintenance of Toll


Plaza can be broken into separate items of work as
under based on the approved design and drawings:-
a) Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll
collection. This involves considerable increase in
carriage way width
b) Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g) Water supply, electricity, sanitation, septic-tank
system and drainage
h) Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and
their rates adopted from respective chapters of the
Standard Data Book

8.42 Safety Devices and Signs in Construction Zones


Provision and fixing of traffic signs for limited period at
suitable locations in construction zone comprising of
warning zone, approach transition zone, working zone
and terminal transition zone with a minimum distance of
60 cm from the edge of the kerb in case of kerbed roads
and 2 to 3 m from the edge of the carriageway in case of
un-kerbed roads, the bottom edge of the lowest sign
plate to be not less than 2 m above the road level, fixed
on 60 mm x 60 mm x 6 mm angle iron post, founded and
installed as per approved design and drawings,
removed and disposed of after completion of
construction work, all as per IRC:SP:55

Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as
per site requirement and consistent with IRC:SP:55 and
IRC:67
The rate for traffic signs are already worked out and
given elsewhere in this chapter. The same may be
adopted.

8.43 Suggestive Portable Barricade in Construction Zone


Installation of a steel portable barricade with horizontal
rail 300 mm wide, 2.5 m in length fitted on a 'A' frame
made with 45 x 45 x 5 mm angle iron section, 1.5 m in
height, horizontal rail painted (2 coats) with yellow and
white stripes, 150 mm in width at an angle of 45°, 'A'
frame painted with 2 coats of yellow paint, complete as
per IRC:SP:55

Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day
Mazdoor day
Painter day
Welder day
b) Material
Angle iron 45 x 45 x 5 mm kg
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg
Paint litre
Add 2 per cent of cost of steel for welding
consumables, nuts & bolts and drilling holes
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per barricade = a+b+c+d

8.44 Suggestive Permanent Type Barricade in Construction Zone


A With steel components
Construction of a permanent type barricade made of
steel components, 1.5 m high from road level, fitted with
3 horizontal rails 200 mm wide and 4 m long on 50 x 50
x 5 mm angle iron vertical support, painted with yellow
and white strips, 150 mm in width at an angle of 45°,
complete as per IRC:SP:55

Unit = each
Taking output = one barricade
a) Labour
Mate day
Mazdoor day
Painter day
Welder day
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m kg


length
Paint litre
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per barricade = a+b+c+d

8.44 B With wooden components


Construction of a permanent type barricade made of
wooden components, 1.5 m high from road level, fitted
with 3 horizontal planks 200 mm wide and 3.66 m long
on 100 x 100mm wooden vertical post, painted with
yellow and white strips, 150 mm in width at an angle of
45°, complete as per IRC:SP:55

Unit = each
Taking output = one barricade
a) Labour
Mate day
Mazdoor day
Painter day
Carpenter day
b) Material
Timber cum
Add 1 per cent of cost of timber for nuts & bolts, nails,
etc.
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per barricade = a+b+c+d

8.44 C With bricks


Construction of a permanent type barricade made with
brick work in mud mortar, 1.5 m high, 4 m long, 600 mm
thick, plastered with cement mortar 1:6, painted with
yellow and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day
Mazdoor day
Painter day
Mason day
b) Material
Brick each
Cement kg
Sand cum
Paint litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per barricade = a+b+c+d

8.45 Suggestive Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator,
300 mm in diameter, 800 mm high, filled with earth for
stability, painted in circumferential strips of alternate
black and white 100 mm wide fitted with reflectors 3 Nos
of 7.5 cm dia, all as per IRC:SP:55

Unit = each
Taking output = one drum delineator
a) Labour
Mate day
Mazdoor day
Painter day
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen drum each
Paint litre
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per drum delineator = a+b+c+d

8.46 Suggestive Water filled barricades work zone sheeting


Providing water filled barricades made up of LDPE to
segregate the vehicular movement and work zone as
per IRC SP 55 shall be in Trapezoidal Shape 800 mm to
1000 mm in length, 700 mm in height for Major Roads
and expressway and 500 mm tall for other roads with
interlocking arrangements, To be placed 0.5 m from the
edge of the carriageway for expressway and 0.3 m for
other roads. It should have reboubdable work zone
sheeting as per ASTM D 4956 S2.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day
Mazdoor day
b) Material
Water filled barricades work zone sheeting each
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per drum delineator = a+b+c+d

8.47 suggestive Tubular Marker/ Spring Post 450 mm


Providing Tubular Marker made up of Polyurethane
used to divide opposing lanes of road users shall be
flexible in nature. Tubular marker having height upto
450 mm shall be having 75 mm Reboundable work zone
retroreflective sheeting as per ASTM 4956 S2.
Application of Tubular Marker shall be done as per IRC
SP 55.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day
Mazdoor day
b) Material
Tubular Marker/ Spring Post 450 mm each
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per drum delineator = a+b+c+d

8.48 suggestive Tubular Marker/ Spring Post 700 mm


Providing Tubular Marker made up of Polyurethane
used to divide opposing lanes of road users shall be
flexible in nature. Tubular marker having minimum
height 700 mm shall be having minimum 75 mm
Reboundable work zone retroreflective sheeting as per
ASTM 4956 S2. Application of Tubular Marker shall be
done as per IRC SP 55.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day
Mazdoor day
b) Material
Tubular Marker/ Spring Post 700 mm each
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per drum delineator = a+b+c+d

8.49 Suggestive Flagman


Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely
fastened to a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day
Mazdoor day
b) Material
Flag of red color cloth 600 x 600 mm each
Wooden staff for fastening of flag 25 mm dia, one m
each
long
Total cost without OH & CP
c) Overhead charges on (a+b)
d) Contractor's profit on (a+b+c)
Rate per flagman = a+b+c+d

8.50 816 Advanced Traffic Management System ( ATMS) work


shall cover design, supply, installation, commissioning
and / or operation and maintenance of Advance Traffic
Management Systems (which is one of the components
of intelligent Transport Systems- ITS). The system
would include out-door equipment including emergency
call boxes, variable message sign systems,
meteorological data system, close circuit TV camera
(CCTV) system, traffic counting and classification
system and transmittion system. The indoor equipment
would comprise a large display board, central computer
(with Network Management System- NMS), CCTV
monitor system, call centre system or management of
emergency call boxes housed in a control centre with
uninterrupted power supply.

A Traffifc Management Commond Centre Equipment

Material
A1 Control Centre Server Nos.
A2 Hot Standby Backup Server Nos.
A3 NAS Video Server with storage Minimum 70 TB Nos.
A4 Backup Video (only Incidents) Server Nos.
A5 Graphic Display ( 70" LED DLP in 3x2 Matrix) Set
A6 Graphic Display Controller and software including Video
Switches Set
A7 CCTV Monitoring Workstation Nos.
A8 Emergency Telephone (1033) console Nos.
A9 VIDS- Workstation Nos.
A10 Admintrative Workstation Nos.
A11 ATMS Operator Workstation Nos.
A12 CCTV Joystick Nos.
A13 Operations Laser Printer ( Colour) Nos.
A14 Operations Laser Printer ( Black) Nos.
A15 Rack 19" Nos.

B Advanced Traffic Management System ( ATMS)


Software
B1 ATMS Control Room Software (integreted with VIDS,
ATCC, VMS, MOS) Nos.
B2
Video Management Software with atleast 150 VMS Lic. Nos.
B3 Facility Monitoring System Controller Software Nos.
B4 Server & Database license Nos.
B5 Antivirus license Nos.

C PTZ Closed Circuit Television System


C1 PTZ Camera ( including CCTV Controller) Set
C2
Solar System with UPS, Battery & 12 m Pole & Cabinet Set

D
Video Incident Detection System Equipment (VIDS)
D1 VIDS Camera (including Image Processing unit) Set
D2 Warning Amber Lights with hooters, 72 Hrs solar
backup, 5m poles and foundation Set
D3 Cabinet Nos.
D4
12m Pole ( including manufacturing and galvanizing) Nos.
D5 Solar System with UPS & batteries Set

E Automatic Traffic Counters-cum-classifier System


Equipment (ATCC)
E1 Equipment, Sensor unit, Processing unit, Solar power
supply Set
E2 Solar System with UPS, batteries Set

F Variable Message Sign Equipment (VMS)


F1 VMS (Variable Message Sign- M type) Nos.
F2 Gantry (including manufacturing and galvanizing) Nos.
F3 Solar System with UPS, battery and cabinet for M type
VMS Set

G UPS and Power system


G1 Uninterruptible Power Supply (UPS) For Server Rack
(10 KVA) Set
G2
Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set
G3
Power Distribution Board ( Essential & Critical Supply) Set

H Meteorological Observation System (MOS)


H1
MOS sensor equipment ( including MOS controller) Set
H2 Cabinet Nos.
H3 Pole Nos.
H4 Steel fence for protection Set

I Digital Transmission System (DTS)


I1 24 Core Armored OFC + all accessories km
I2 40mm PLB HDPE duct as per latest TSEC
specifications + all accessories km
I3 Trenching of 1.8 metres, laying & backfilling for PLB
HDPE duct km
Note Overhead and contractor's profit will be added separately on item no. 8.50.
Civil works required to be executed for these installations Drilling may be done as per rates i
for quantiy derived, approved design and drawing.
8.51 Suggestive Fiber Reinforced Cement Concrete New Jersy Crash
Barrier
Unit= Linear metre
Taking Output= 20 m
A Provision of an Reinforced cement concrete crash
barrier at th edges of the road, approaches to bridge
structures and medians, constructed with Reinforced
Cement Concrete with fiber steel and as per details
given IRC -5 ( Fig.- 5, b) including dowel bars 25 mm
dia, 450mm long at expansion joints filled with pre-
moulded asphalt filler board etc., as per approved
drawing and at locations directed by the engineer, all as
specified. (Area- 0.243 Sqm/ Metre, Single Face)

a) M30 Grade concrete

M30 grade concrete (Area- 0.243 Sqm/ Metre) cum


(Rate taken from item No. 12.11 A (iii) Case II including
OH & CP)
b) Labour
Mate day
Mazdoor day
c) Material
Fiber Steel (35 Kg/Cum) tonne
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20
Note i) Excavation and backfilling are incidental to work and not to be measured separetely.
ii) If PCC required below crash barrier then it should be measured & Paid separately.
iii) Rate for RCC M30 may be taken from chapter on 12.

B Provision of an Reinforced cement concrete crash


barrier at the edges of the road, approaches to bridge
structures and medians, constructed with Reinforced
Cement Concrete with fiber steel and as per details
given IRC- 119 (Fig. -26) including dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-
moulded asphalt filler board etc., as per approved
drawing and at locations directed by the Engineer ,all as
specified. (Area-0.261 Sqm./ meter, Double Face)

M30 Grade concrete


M30 grade concrete (Area- 0.261 Sqm/ Metre) cum

(Rate taken from item No. 12.11 A (iii) Case II including


OH & CP)
b) Labour
Mate day
Mazdoor day
c) Material
Fiber Steel (35 Kg/Cum) tonne
d) Overhead charges on (b+c)
e) Contractor's profit on (b+c+d)
Cost for 20 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/20
Note i) Excavation and backfilling are incidental to work and not to be measured separetely.
ii) If PCC required below crash barrier then it should be measured & Paid separately.
iii) Rate for RCC M30 may be taken from chapter on 12.
CHAPTER - 8
SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Quantity as per peroject category Rate (Rs) Amount
Large Medium Small Large Medium Small

ete = 11.610 cu.m

0.240 0.240 0.240 310.00 74.40 74.40 74.40


2.000 2.000 2.000 351.00 702.00 702.00 702.00
4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00

26.703xL1 26.703xL1 26.703xL1 12.32 328.98 328.98 328.98


3.729 3.729 3.729 2218.00 8270.92 8270.92 8270.92

0.011xL1
1426.00 186.81
+0.12
0.015xL1
1252.00 169.02
+0.12
0.03xL1
907.00 136.05
+0.12

11.610 11.610 11.610 2121.80 24634.10 24634.10 24634.10


1.602 1.602 1.602 73.60 117.91 117.91 117.91
35483.11 35465.33 35432.36
(@ 8%) (@ 10%) (@ 12%) 2838.65 3546.53 4251.88
(@ 10%) (@ 10%) (@ 10%) 3832.18 3901.19 3968.42
42153.94 42913.05 43652.67
117.09 119.20 121.26
Say 117.10 119.20 121.30
ete = 12.600 cu.m

0.060 0.060 0.060 310.00 18.60 18.60 18.60


0.500 0.500 0.500 351.00 175.50 175.50 175.50
1.000 1.000 1.000 292.00 292.00 292.00 292.00

3.000 3.000 3.000 1590.00 4770.00 4770.00 4770.00

28.980xL1 28.980xL1 28.980xL1 12.32 357.03 357.03 357.03


3.140 3.140 3.140 2218.00 6964.52 6964.52 6964.52
6.000 6.000 6.000 175.00 1050.00 1050.00 1050.00

0.042xL1
1426.00 231.01
+0.12
0.056xL1
1252.00 220.35
+0.12
0.113xL1
907.00 211.33
+0.12

12.600 12.600 12.600 2483.20 31288.32 31288.32 31288.32


6.086 6.086 6.086 73.60 447.93 447.93 447.93
45594.92 45584.26 45575.23
(@ 8%) (@ 10%) (@ 12%) 3647.59 4558.43 5469.03
(@ 10%) (@ 10%) (@ 10%) 4924.25 5014.27 5104.43
54166.76 55156.95 56148.69
150.46 153.21 155.97
Say 150.50 153.20 156.00

al Concrete = 9.675 cum.


ete = 9.675 cu.m

0.240 0.240 0.240 310.00 74.40 74.40 74.40


2.000 2.000 2.000 351.00 702.00 702.00 702.00
4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00

26.703xL1 26.703xL1 26.703xL1 12.32 328.98 328.98 328.98


3.108 3.108 3.108 2218.00 6893.54 6893.54 6893.54

0.009xL1
1426.00 155.43
+0.1
0.012xL1
1252.00 140.22
+0.1
0.025xL1
907.00 113.38
+0.1

9.675 9.675 9.675 2121.80 20528.42 20528.42 20528.42


1.335 1.335 1.335 73.60 98.26 98.26 98.26
29949.03 29933.82 29906.97
(@ 8%) (@ 10%) (@ 12%) 2395.92 2993.38 3588.84
(@ 10%) (@ 10%) (@ 10%) 3234.50 3292.72 3349.58
35579.45 36219.92 36845.39
118.60 120.73 122.82
Say 118.60 120.70 122.80

ete = 15.000 cu.m

0.060 0.060 0.060 310.00 18.60 18.60 18.60


0.500 0.500 0.500 351.00 175.50 175.50 175.50
1.000 1.000 1.000 292.00 292.00 292.00 292.00

3.333 3.333 3.333 1590.00 5299.47 5299.47 5299.47

28.980xL1 28.980xL1 28.980xL1 12.32 357.03 357.03 357.03


3.500 3.500 3.500 2218.00 7763.00 7763.00 7763.00
5.000 5.000 5.000 175.00 875.00 875.00 875.00
0.05xL1
1426.00 213.90
+0.1
0.067xL1
1252.00 209.08
+0.1
0.134xL1
907.00 212.24
+0.1

15.000 15.000 15.000 2483.20 37248.00 37248.00 37248.00


7.245 7.245 7.245 73.60 533.23 533.23 533.23
52775.74 52770.92 52774.07
(@ 8%) (@ 10%) (@ 12%) 4222.06 5277.09 6332.89
(@ 10%) (@ 10%) (@ 10%) 5699.78 5804.80 5910.70
62697.57 63852.81 65017.66
208.99 212.84 216.73
Say 209.00 212.80 216.70

0.120 0.120 0.120 310.00 37.20 37.20 37.20


2.000 2.000 2.000 373.00 746.00 746.00 746.00
1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.700 0.700 0.700 224.02 156.81 156.81 156.81


1232.01 1232.01 1232.01
(@ 8%) (@ 10%) (@ 12%) 98.56 123.20 147.84
(@ 10%) (@ 10%) (@ 10%) 133.06 135.52 137.99
1463.63 1490.74 1517.84
0.91 0.93 0.95
Say 0.90 0.90 0.90
0.070 0.070 0.070 310.00 21.70 21.70 21.70
1.250 1.250 1.250 373.00 466.25 466.25 466.25
0.500 0.500 0.500 292.00 146.00 146.00 146.00

0.500 0.500 0.500 224.02 112.01 112.01 112.01


745.96 745.96 745.96
(@ 8%) (@ 10%) (@ 12%) 59.68 74.60 89.52
(@ 10%) (@ 10%) (@ 10%) 80.56 82.06 83.55
886.20 902.61 919.02
0.55 0.56 0.57
Say 0.60 0.60 0.60

126.60-L
0.122 0.122 0.122 128.90-M 15.45 15.73 16.02
131.30-S

4441.00-L
0.122 0.122 0.122 4531.60-M 541.80 552.86 566.06
4639.80-S

66.4-L
1.414 1.414 1.414 67.6-M 93.89 95.59 97.28
68.8-S
(i+ii+iii) 651.14 664.17 679.36

0.010 0.010 0.010 310.00 3.10 3.10 3.10


0.250 0.250 0.250 292.00 73.00 73.00 73.00
2.2 2.2 2.2 46.66 102.65 102.65 102.65

20.556 20.556 20.556 46.66 959.10 959.10 959.10

0.624 0.624 0.624 7846.87 4896.45 4896.45 4896.45


59.58 59.58 59.58

0.351 0.351 0.351 7846.87 2754.25 2754.25 2754.25


38.16 38.16 38.16

0.244 0.244 0.244 7846.87 1914.64 1914.64 1914.64


29.76 29.76 29.76

0.156 0.156 0.156 7846.87 1224.11 1224.11 1224.11


22.86 22.86 22.86

1.131 1.131 1.131 7846.87 8874.81 8874.81 8874.81


99.37 99.37 99.37

0.636 0.636 0.636 7846.87 4990.61 4990.61 4990.61


60.52 60.52 60.52

0.442 0.442 0.442 7846.87 3468.32 3468.32 3468.32


45.30 45.30 45.30

0.283 0.283 0.283 7846.87 2220.66 2220.66 2220.66


32.82 32.82 32.82

0.675 0.675 0.675 7846.87 5296.64 5296.64 5296.64


63.58 63.58 63.58

0.480 0.480 0.480 7846.87 3766.50 3766.50 3766.50


48.28 48.28 48.28

0.300 0.300 0.300 7846.87 2354.06 2354.06 2354.06


34.16 34.16 34.16

0.270 0.270 0.270 7846.87 2118.65 2118.65 2118.65


31.80 31.80 31.80

0.360 0.360 0.360 7846.87 2824.87 2824.87 2824.87


38.87 38.87 38.87

1.193 1.193 1.193 7846.87 9361.32 9361.32 9361.32


104.23 104.23 104.23

0.671 0.671 0.671 7846.87 5265.25 5265.25 5265.25


63.27 63.27 63.27

0.446 0.446 0.446 7846.87 3499.70 3499.70 3499.70


45.61 45.61 45.61

0.010 0.010 0.010 612.00 6.12 6.12 6.12

(a+b+c) 6100.00 6100.00 6100.00


(@ 8%) (@ 10%) (@ 12%) 488.00 610.00 732.00
(@ 10%) (@ 10%) (@ 10%) 658.80 671.00 683.20
7897.93 8045.17 8194.56
say 7897.90 8045.20 8194.60

(a+b+c) 3936.38 3936.38 3936.38


(@ 8%) (@ 10%) (@ 12%) 314.91 393.64 472.37
(@ 10%) (@ 10%) (@ 10%) 425.13 433.00 440.87
5327.56 5427.19 5528.98
say 5327.60 5427.20 5529.00

(a+b+c) 3088.37 3088.37 3088.37


(@ 8%) (@ 10%) (@ 12%) 247.07 308.84 370.60
(@ 10%) (@ 10%) (@ 10%) 333.54 339.72 345.90
4320.12 4401.09 4484.23
say 4320.10 4401.10 4484.20

(a+b+c) 2390.94 2390.94 2390.94


(@ 8%) (@ 10%) (@ 12%) 191.28 239.09 286.91
(@ 10%) (@ 10%) (@ 10%) 258.22 263.00 267.79
3491.57 3557.20 3625.00
say 3491.60 3557.20 3625.00

(a+b+c) 10118.15 10118.15 10118.15


(@ 8%) (@ 10%) (@ 12%) 809.45 1011.81 1214.18
(@ 10%) (@ 10%) (@ 10%) 1092.76 1113.00 1133.23
12671.49 12907.12 13144.91
say 12671.50 12907.10 13144.90

(a+b+c) 6195.10 6195.10 6195.10


(@ 8%) (@ 10%) (@ 12%) 495.61 619.51 743.41
(@ 10%) (@ 10%) (@ 10%) 669.07 681.46 693.85
8010.92 8160.24 8311.72
say 8010.90 8160.20 8311.70

(a+b+c) 4657.59 4657.59 4657.59


(@ 8%) (@ 10%) (@ 12%) 372.61 465.76 558.91
(@ 10%) (@ 10%) (@ 10%) 503.02 512.33 521.65
6184.35 6299.85 6417.50
say 6184.30 6299.80 6417.50

(a+b+c) 3397.46 3397.46 3397.46


(@ 8%) (@ 10%) (@ 12%) 271.80 339.75 407.69
(@ 10%) (@ 10%) (@ 10%) 366.93 373.72 380.52
4687.32 4775.09 4865.03
say 4687.30 4775.10 4865.00

(a+b+c) 6504.19 6504.19 6504.19


(@ 8%) (@ 10%) (@ 12%) 520.34 650.42 780.50
(@ 10%) (@ 10%) (@ 10%) 702.45 715.46 728.47
8378.12 8534.24 8692.52
say 8378.10 8534.20 8692.50

(a+b+c) 4958.75 4958.75 4958.75


(@ 8%) (@ 10%) (@ 12%) 396.70 495.87 595.05
(@ 10%) (@ 10%) (@ 10%) 535.54 545.46 555.38
6542.13 6664.25 6788.54
say 6542.10 6664.30 6788.50

(a+b+c) 3532.19 3532.19 3532.19


(@ 8%) (@ 10%) (@ 12%) 282.58 353.22 423.86
(@ 10%) (@ 10%) (@ 10%) 381.48 388.54 395.61
4847.38 4938.12 5031.01
say 4847.40 4938.10 5031.00

(a+b+c) 3294.43 3294.43 3294.43


(@ 8%) (@ 10%) (@ 12%) 263.55 329.44 395.33
(@ 10%) (@ 10%) (@ 10%) 355.80 362.39 368.98
4564.92 4650.43 4738.09
say 4564.90 4650.40 4738.10

(a+b+c) 4007.71 4007.71 4007.71


(@ 8%) (@ 10%) (@ 12%) 320.62 400.77 480.93
(@ 10%) (@ 10%) (@ 10%) 432.83 440.85 448.86
5412.29 5513.50 5616.85
say 5412.30 5513.50 5616.90

(a+b+c) 10609.52 10609.52 10609.52


(@ 8%) (@ 10%) (@ 12%) 848.76 1060.95 1273.14
(@ 10%) (@ 10%) (@ 10%) 1145.83 1167.05 1188.27
13255.24 13501.68 13750.28
say 13255.20 13501.70 13750.30

(a+b+c) 6472.49 6472.49 6472.49


(@ 8%) (@ 10%) (@ 12%) 517.80 647.25 776.70
(@ 10%) (@ 10%) (@ 10%) 699.03 711.97 724.92
8340.45 8495.88 8653.46
say 8340.50 8495.90 8653.50

(a+b+c) 4689.29 4689.29 4689.29


(@ 8%) (@ 10%) (@ 12%) 375.14 468.93 562.71
(@ 10%) (@ 10%) (@ 10%) 506.44 515.82 525.20
6222.01 6338.21 6456.56
say 6222.00 6338.20 6456.60
126.60-L
0.122 0.122 0.122 128.90-M 15.45 15.73 16.02
131.30-S

4441.00-L
0.122 0.122 0.122 4531.60-M 541.80 552.86 566.06
4639.80-S

66.40-L
1.414 1.414 1.414 67.60-M 93.89 95.59 97.28
68.80-S
651.14 664.17 679.36

0.01 0.01 0.01 310.00 3.10 3.10 3.10


0.25 0.25 0.25 292.00 73.00 73.00 73.00

2.200 2.200 2.200 46.66 102.65 102.65 102.65


959.10 959.10 959.10
20.556 20.556 20.556 46.66

0.624 0.624 0.624 7846.87 4896.45 4896.45 4896.45


59.58 59.58 59.58

0.351 0.351 0.351 7846.87 2754.25 2754.25 2754.25


38.16 38.16 38.16

0.244 0.244 0.244 7846.87 1914.64 1914.64 1914.64


29.76 29.76 29.76

0.156 0.156 0.156 7846.87 1224.11 1224.11 1224.11


22.86 22.86 22.86

1.131 1.131 1.131 7846.87 8874.81 8874.81 8874.81


99.37 99.37 99.37

0.636 0.636 0.636 7846.87 4990.61 4990.61 4990.61


60.52 60.52 60.52

0.442 0.442 0.442 7846.87 3468.32 3468.32 3468.32


45.30 45.30 45.30

0.283 0.283 0.283 7846.87 2220.66 2220.66 2220.66


32.82 32.82 32.82

0.675 0.675 0.675 7846.87 5296.64 5296.64 5296.64


63.58 63.58 63.58
.
0.480 0.480 0.480 7846.87 3766.50 3766.50 3766.50
48.28 48.28 48.28

0.300 0.300 0.300 7846.87 2354.06 2354.06 2354.06


34.16 34.16 34.16

0.270 0.270 0.270 7846.87 2118.65 2118.65 2118.65


31.80 31.80 31.80

0.360 0.360 0.360 7846.87 2824.87 2824.87 2824.87


38.87 38.87 38.87
1.193 1.193 1.193 7846.87 9361.32 9361.32 9361.32
104.23 104.23 104.23

0.671 0.671 0.671 7846.87 5265.25 5265.25 5265.25


63.27 63.27 63.27

0.446 0.446 0.446 7846.87 3499.70 3499.70 3499.70


45.61 45.61 45.61

0.010 0.010 0.010 612.00 6.12 6.12 6.12

(a+b+c) 6100.00 6100.00 6100.00


(@ 8%) (@ 10%) (@ 12%) 488.00 610.00 732.00
(@ 10%) (@ 10%) (@ 10%) 658.80 671.00 683.20
7897.93 8045.17 8194.56
say 7897.90 8045.20 8194.60

(a+b+c) 3936.38 3936.38 3936.38


(@ 8%) (@ 10%) (@ 12%) 314.91 393.64 472.37
(@ 10%) (@ 10%) (@ 10%) 425.13 433.00 440.87
5327.56 5427.19 5528.98
say 5327.60 5427.20 5529.00

(a+b+c) 3088.37 3088.37 3088.37


(@ 8%) (@ 10%) (@ 12%) 247.07 308.84 370.60
(@ 10%) (@ 10%) (@ 10%) 333.54 339.72 345.90
4320.12 4401.09 4484.23
say 4320.10 4401.10 4484.20

(a+b+c) 2390.94 2390.94 2390.94


(@ 8%) (@ 10%) (@ 12%) 191.28 239.09 286.91
(@ 10%) (@ 10%) (@ 10%) 258.22 263.00 267.79
3491.57 3557.20 3625.00
say 3491.60 3557.20 3625.00

(a+b+c) 10118.15 10118.15 10118.15


(@ 8%) (@ 10%) (@ 12%) 809.45 1011.81 1214.18
(@ 10%) (@ 10%) (@ 10%) 1092.76 1113.00 1133.23
12671.49 12907.12 13144.91
say 12671.50 12907.10 13144.90
(a+b+c) 6195.10 6195.10 6195.10
(@ 8%) (@ 10%) (@ 12%) 495.61 619.51 743.41
(@ 10%) (@ 10%) (@ 10%) 669.07 681.46 693.85
8010.92 8160.24 8311.72
say 8010.90 8160.20 8311.70

(a+b+c) 4657.59 4657.59 4657.59


(@ 8%) (@ 10%) (@ 12%) 372.61 465.76 558.91
(@ 10%) (@ 10%) (@ 10%) 503.02 512.33 521.65
6184.35 6299.85 6417.50
say 6184.30 6299.80 6417.50

(a+b+c) 3397.46 3397.46 3397.46


(@ 8%) (@ 10%) (@ 12%) 271.80 339.75 407.69
(@ 10%) (@ 10%) (@ 10%) 366.93 373.72 380.52
4687.32 4775.09 4865.03
say 4687.30 4775.10 4865.00

(a+b+c) 6504.19 6504.19 6504.19


(@ 8%) (@ 10%) (@ 12%) 520.34 650.42 780.50
(@ 10%) (@ 10%) (@ 10%) 702.45 715.46 728.47
8378.12 8534.24 8692.52
say 8378.10 8534.20 8692.50

(a+b+c) 4958.75 4958.75 4958.75


(@ 8%) (@ 10%) (@ 12%) 396.70 495.87 595.05
(@ 10%) (@ 10%) (@ 10%) 535.54 545.46 555.38
6542.13 6664.25 6788.54
say 6542.10 6664.30 6788.50

(a+b+c) 3532.19 3532.19 3532.19


(@ 8%) (@ 10%) (@ 12%) 282.58 353.22 423.86
(@ 10%) (@ 10%) (@ 10%) 381.48 388.54 395.61
4847.38 4938.12 5031.01
say 4847.40 4938.10 5031.00

(a+b+c) 3294.43 3294.43 3294.43


(@ 8%) (@ 10%) (@ 12%) 263.55 329.44 395.33
(@ 10%) (@ 10%) (@ 10%) 355.80 362.39 368.98
4564.92 4650.43 4738.09
say 4564.90 4650.40 4738.10

(a+b+c) 4007.71 4007.71 4007.71


(@ 8%) (@ 10%) (@ 12%) 320.62 400.77 480.93
(@ 10%) (@ 10%) (@ 10%) 432.83 440.85 448.86
5412.29 5513.50 5616.85
say 5412.30 5513.50 5616.90

(a+b+c) 10609.52 10609.52 10609.52


(@ 8%) (@ 10%) (@ 12%) 848.76 1060.95 1273.14
(@ 10%) (@ 10%) (@ 10%) 1145.83 1167.05 1188.27
13255.24 13501.68 13750.28
say 13255.20 13501.70 13750.30

(a+b+c) 6472.49 6472.49 6472.49


(@ 8%) (@ 10%) (@ 12%) 517.80 647.25 776.70
(@ 10%) (@ 10%) (@ 10%) 699.03 711.97 724.92
8340.45 8495.88 8653.46
say 8340.50 8495.90 8653.50

(a+b+c) 4689.29 4689.29 4689.29


(@ 8%) (@ 10%) (@ 12%) 375.14 468.93 562.71
(@ 10%) (@ 10%) (@ 10%) 506.44 515.82 525.20
6222.01 6338.21 6456.56
say 6222.00 6338.20 6456.60
126.60-L
0.122 0.122 0.122 128.90-M 15.45 15.73 16.02
131.30-S

4441.00-L
0.122 0.122 0.122 4531.60-M 541.80 552.86 566.06
4639.80-S

66.40-L
1.414 1.414 1.414 67.60-M 93.89 95.59 97.28
68.80-S
651.14 664.17 679.36

0.008 0.008 0.008 310.00 2.48 2.48 2.48


0.200 0.200 0.200 292.00 58.40 58.40 58.40

6.080 6.080 6.080 46.66 283.68 283.68 283.68


20.556 20.556 20.556 46.66 959.10 959.10 959.10

0.900 0.900 0.900 7846.87 7062.18 7062.18 7062.18

166.10 166.10 166.10

0.020 0.020 0.020 612.000 12.24 12.24 12.24


8544.18 8544.18 8544.18
(@ 8%) (@ 10%) (@ 12%) 683.53 854.42 1025.30
(@ 10%) (@ 10%) (@ 10%) 922.77 939.86 956.95
10801.63 11002.63 11205.79
+ii+iii+a+b+c+d+e)/0.90 12001.81 12225.15 12450.88
say 12001.80 12225.10 12450.90
126.60-L
0.243 0.243 0.243 128.90-M 30.76 31.32 31.91
131.30-S

4441.00-L
0.243 0.243 0.243 4531.60-M 1079.16 1101.18 1127.47
4639.80-S

66.40-L
2.827 2.827 2.827 67.60-M 187.71 191.11 194.50
68.80-S

1297.64 1323.61 1353.87

0.012 0.012 0.012 310.00 3.72 3.72 3.72


0.300 0.300 0.300 292.00 87.60 87.60 87.60

14.400 14.400 14.400 46.66 671.88 671.88 671.88

41.112 41.112 41.112 46.66 1918.20 1918.20 1918.20

1.500 1.500 1.500 7846.87 11770.31 11770.31 11770.31

287.21 287.21 287.21

0.020 0.020 0.020 612.00 12.24 12.24 12.24


14751.15 14751.15 14751.15
(@ 8%) (@ 10%) (@ 12%) 1180.09 1475.12 1770.14
(@ 10%) (@ 10%) (@ 10%) 1593.12 1622.63 1652.13
18822.01 19172.50 19527.29
)= ( i+ii+iii+a+b+c+d+e)/1.50 12548.01 12781.67 13018.20
say 12548.00 12781.70 13018.20
ded separately as per actual requirement. Rates for these items have
painting may be taken from respective chapters-09 & 08 respectively.

0.240 0.240 0.240 310.00 74.40 74.40 74.40


2.000 2.000 2.000 351.00 702.00 702.00 702.00
4.000 4.000 4.000 292.00 1168.00 1168.00 1168.00

1.020 1.020 1.020 31920.15 32558.55 32558.55 32558.55

325.59 325.59 325.59

4883.78 4883.78 4883.78

3.000 3.000 3.000 862.00 2586.00 2586.00 2586.00


0.500 0.500 0.500 1183.00 591.50 591.50 591.50
42889.82 42889.82 42889.82
(@ 8%) (@ 10%) (@ 12%) 3431.19 4288.98 5146.78
(@ 10%) (@ 10%) (@ 10%) 4632.10 4717.88 4803.66
50953.11 51896.68 52840.26
Say 50953.10 51896.70 52840.30
0.010 0.010 0.010 310.00 3.10 3.10 3.10
0.100 0.100 0.100 351.00 35.10 35.10 35.10
0.150 0.150 0.150 292.00 43.80 43.80 43.80

1.000 1.000 1.000 7980.04 7980.04 7980.04 7980.04

0.82 0.82 0.82


8062.86 8062.86 8062.86
(@ 8%) (@ 10%) (@ 12%) 645.03 806.29 967.54
(@ 10%) (@ 10%) (@ 10%) 870.79 886.91 903.04
9578.68 9756.06 9933.44
say 9578.70 9756.10 9933.40
fixing of vertical support system to be worked out
ded separately
be included as per
in the actual requirement. Rates for these
estimate.

0.120 0.120 0.120 310.00 37.20 37.20 37.20


2.000 2.000 2.000 373.00 746.00 746.00 746.00
1.000 1.000 1.000 292.00 292.00 292.00 292.00

6.000 6.000 6.000 224.02 1344.12 1344.12 1344.12


10.75 10.75 10.75

120.97 120.97 120.97

2551.04 2551.04 2551.04


(@ 8%) (@ 10%) (@ 12%) 204.08 255.10 306.12
(@ 10%) (@ 10%) (@ 10%) 275.51 280.61 285.72
3030.63 3086.76 3142.88
75.77 77.17 78.57
Say 75.80 77.20 78.60
0.028 0.028 0.028 310.00 8.68 8.68 8.68
0.450 0.450 0.450 373.00 167.85 167.85 167.85
0.250 0.250 0.250 292.00 73.00 73.00 73.00

1.250 1.250 1.250 224.02 280.03 280.03 280.03


2.80 2.80 2.80

26.48 26.48 26.48

558.83 558.83 558.83


(@ 8%) (@ 10%) (@ 12%) 44.71 55.88 67.06
(@ 10%) (@ 10%) (@ 10%) 60.35 61.47 62.59
663.89 676.19 688.48
66.39 67.62 68.85
Say 66.40 67.60 68.80

0.028 0.028 0.028 310.00 8.68 8.68 8.68


0.500 0.500 0.500 373.00 186.50 186.50 186.50
0.200 0.200 0.200 292.00 58.40 58.40 58.40

1.500 1.500 1.500 224.02 336.03 336.03 336.03


3.36 3.36 3.36

29.48 29.48 29.48


622.45 622.45 622.45
(@ 8%) (@ 10%) (@ 12%) 49.80 62.25 74.69
(@ 10%) (@ 10%) (@ 10%) 67.22 68.47 69.71
739.47 753.17 766.86
73.95 75.32 76.69
Say 73.90 75.30 76.70
0.084 0.084 0.084 310.00 26.04 26.04 26.04
0.550 0.550 0.550 373.00 205.15 205.15 205.15
1.550 1.550 1.550 292.00 452.60 452.60 452.60

1.480 1.480 1.480 224.02 331.55 331.55 331.55


1015.34 1015.34 1015.34
(@ 8%) (@ 10%) (@ 12%) 81.23 101.53 121.84
(@ 10%) (@ 10%) (@ 10%) 109.66 111.69 113.72
1206.22 1228.56 1250.90
120.62 122.86 125.09
Say 120.60 122.90 125.10

0.068 0.068 0.068 310.00 21.08 21.08 21.08


0.350 0.350 0.350 373.00 130.55 130.55 130.55
1.350 1.350 1.350 292.00 394.20 394.20 394.20

1.480 1.480 1.480 224.02 331.55 331.55 331.55


877.38 877.38 877.38
(@ 8%) (@ 10%) (@ 12%) 70.19 87.74 105.29
(@ 10%) (@ 10%) (@ 10%) 94.76 96.51 98.27
1042.33 1061.63 1080.93
104.23 106.16 108.09
Say 104.20 106.20 108.10
0.062 0.062 0.062 310.00 19.22 19.22 19.22
0.300 0.300 0.300 373.00 111.90 111.90 111.90
1.250 1.250 1.250 292.00 365.00 365.00 365.00

0.900 0.900 0.900 224.02 201.62 201.62 201.62


697.74 697.74 697.74
(@ 8%) (@ 10%) (@ 12%) 55.82 69.77 83.73
(@ 10%) (@ 10%) (@ 10%) 75.36 76.75 78.15
828.91 844.26 859.61
82.89 84.43 85.96
Say 82.90 84.40 86.00

0.068 0.068 0.068 310.00 21.08 21.08 21.08


0.350 0.350 0.350 373.00 130.55 130.55 130.55
1.350 1.350 1.350 292.00 394.20 394.20 394.20

0.900 0.900 0.900 224.02 201.62 201.62 201.62


747.45 747.45 747.45
(@ 8%) (@ 10%) (@ 12%) 59.80 74.74 89.69
(@ 10%) (@ 10%) (@ 10%) 80.72 82.22 83.71
887.97 904.41 920.86
88.80 90.44 92.09
Say 88.80 90.40 92.10

0.030 0.030 0.030 310.00 9.30 9.30 9.30


0.750 0.750 0.750 292.00 219.00 219.00 219.00

10.000 10.000 10.000 1965.00 19650.00 19650.00 19650.00


0.500 0.500 0.500 612.00 306.00 306.00 306.00

1500.000 1500.000 1500.000 183.25 274875.00 274875.00 274875.00


150.000 150.000 150.000 65.04 9756.00 9756.00 9756.00
304815.30 304815.30 304815.30
(@ 8%) (@ 10%) (@ 12%) 24385.22 30481.53 36577.84
(@ 10%) (@ 10%) (@ 10%) 32920.05 33529.68 34139.31
362120.58 368826.51 375532.45
603.53 614.71 625.89
ment concrete pavement to ensure proper bonding. Any Say 603.50 614.70 625.90
eroad
paintmarking
is required to be applied on concrete surface.
machine.

3331.70-L
2.350 2.350 2.350 3401.70-M 7829.50 7994.00 8200.09
3489.40-S

60.538-L
22.080 22.080 22.080 61.708-M 1336.68 1362.51 1389.63
62.936-S

126.60-L
1.680 1.680 1.680 128.90-M 212.69 216.55 220.58
131.30-S

75.80-L
9.850 9.850 9.850 77.20-M 746.63 760.42 774.21
78.60-S

1800.000 1800.000 1800.000 0.60 1080.00 1080.00 1080.00


0.264 0.264 0.264 310.00 81.84 81.84 81.84
0.600 0.600 0.600 351.00 210.60 210.60 210.60
6.000 6.000 6.000 292.00 1752.00 1752.00 1752.00

6.000 6.000 6.000 612.00 3672.00 3672.00 3672.00


(@ 8%) (@ 10%) (@ 12%) 457.32 571.64 685.97
(@ 10%) (@ 10%) (@ 10%) 617.38 628.81 640.24
17996.62 18330.37 18707.16
2999.44 3055.06 3117.86
say 2999.40 3055.10 3117.90

3331.70-L
3.770 3.770 3.770 3401.70-M 12560.51 12824.41 13155.04
3489.40-S

60.538-L
26.320 26.320 26.320 61.708-M 1593.36 1624.15 1656.48
62.936-S

126.60-L
2.770 2.770 2.770 128.90-M 350.68 357.05 363.70
131.30-S

75.80-L
11.410 11.410 11.410 77.20-M 864.88 880.85 896.83
78.60-S

1680.000 1680.000 1680.000 0.600 1008.00 1008.00 1008.00

0.320 0.320 0.320 310.00 99.20 99.20 99.20


1.000 1.000 1.000 351.00 351.00 351.00 351.00
7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00
6.000 6.000 6.000 612.00 3672.00 3672.00 3672.00
(@ 8%) (@ 10%) (@ 12%) 493.30 616.62 739.94
(@ 10%) (@ 10%) (@ 10%) 665.95 678.28 690.61
23702.87 24155.57 24676.80
1693.06 1725.40 1762.63
say 1693.10 1725.40 1762.60

3331.70-L
1.580 1.580 1.580 3401.70-M 5264.09 5374.69 5513.25
3489.40-S

60.538-L
66.000 66.000 66.000 61.708-M 3995.51 4072.73 4153.78
62.936-S

126.60-L
1.390 1.390 1.390 128.90-M 175.97 179.17 182.51
131.30-S

75.80-L
6.270 6.270 6.270 77.20-M 475.27 484.04 492.82
78.60-S

330.000 330.000 330.000 0.60 198.00 198.00 198.00

0.340 0.340 0.340 310.00 105.40 105.40 105.40


1.500 1.500 1.500 351.00 526.50 526.50 526.50
7.000 7.000 7.000 292.00 2044.00 2044.00 2044.00

6.000 6.000 6.000 612.00 3672.00 3672.00 3672.00


(@ 8%) (@ 10%) (@ 12%) 507.83 634.79 761.75
(@ 10%) (@ 10%) (@ 10%) 685.57 698.27 710.96
17650.14 17989.59 18360.97
534.85 545.14 556.39
say 534.90 545.10 556.40
cement, painting and lettering may be taken from

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

30.000 30.000 30.000 794.08 23822.40 23822.40 23822.40

2382.24 2382.24 2382.24


26509.04 26509.04 26509.04
(@ 8%) (@ 10%) (@ 12%) 2120.72 2650.90 3181.08
(@ 10%) (@ 10%) (@ 10%) 2862.98 2915.99 2969.01
31492.74 32075.94 32659.14
1049.76 1069.20 1088.64
ovided as per approved design. In case foundation is say 1049.80 1069.20 1088.60
oundation concrete are required to be measured and paid

3331.70-L
1.250 1.250 1.250 3401.70-M 4164.63 4252.13 4361.75
3489.40-S

60.538-L
79.800 79.800 79.800 61.708-M 4830.93 4924.30 5022.29
62.936-S
126.60-L
10.720 10.720 10.720 128.90-M 1357.15 1381.81 1407.54
131.30-S

2280.000 2280.000 2280.000 0.60 1368.00 1368.00 1368.00

0.570 0.570 0.570 310.000 176.70 176.70 176.70


14.250 14.250 14.250 292.000 4161.00 4161.00 4161.00

6.000 6.000 6.000 612.000 3672.00 3672.00 3672.00

11.970 11.970 11.970 351.360 4205.78 4205.78 4205.78


(@ 8%) (@ 10%) (@ 12%) 977.24 1221.55 1465.86
(@ 10%) (@ 10%) (@ 10%) 1319.27 1343.70 1368.13
26232.70 26706.96 27209.05
460.22 468.54 477.35
say 460.20 468.50 477.40
ovided as per approved design. In case foundation is
oundation concrete are required to be measured and paid

0.090 0.090 0.090 310.00 27.90 27.90 27.90


0.250 0.250 0.250 351.00 87.75 87.75 87.75
2.000 2.000 2.000 292.00 584.00 584.00 584.00

31.420 31.420 31.420 57.950 1820.79 1820.79 1820.79


80.500 80.500 80.500 46.658 3755.97 3755.97 3755.97

111.54 111.54 111.54

75.80-L
2.110 2.110 2.110 77.20-M 159.94 162.89 165.85
78.60-S
6547.88 6550.84 6553.79
(@ 8%) (@ 10%) (@ 12%) 523.83 655.08 786.45
(@ 10%) (@ 10%) (@ 10%) 707.17 720.59 734.02
7778.88 7926.51 8074.27
259.30 264.22 269.14
say 259.30 264.20 269.10
rete to be added separately in the cost estimate as per
en from respective chapters.

0.116 0.116 0.116 310.00 35.96 35.96 35.96


0.400 0.400 0.400 351.00 140.40 140.40 140.40
2.500 2.500 2.500 292.00 730.00 730.00 730.00

40.150 40.150 40.150 57.95 2326.69 2326.69 2326.69

152.000 152.000 152.000 46.66 7092.02 7092.02 7092.02

188.37 188.37 188.37

75.80-L
3.960 3.960 3.960 77.20-M 300.17 305.71 311.26
78.60-S
10813.61 10819.15 10824.70
(@ 8%) (@ 10%) (@ 12%) 865.09 1081.92 1298.96
(@ 10%) (@ 10%) (@ 10%) 1167.87 1190.11 1212.37
12846.57 13091.18 13336.03
428.22 436.37 444.53
say 428.20 436.40 444.50
rete to be added separately in the cost estimate as per
en from respective chapters.

0.120 0.120 0.120 310.00 37.20 37.20 37.20


1.000 1.000 1.000 394.00 394.00 394.00 394.00
2.000 2.000 2.000 292.00 584.00 584.00 584.00

106.000 106.000 106.000 46.66 4945.75 4945.75 4945.75

26.000 26.000 26.000 46.66 1213.11 1213.11 1213.11


151.000 151.000 151.000 41.34 6242.34 6242.34 6242.34

293.000 293.000 293.000

310.03 310.03 310.03

0.100 0.100 0.100 612.00 61.20 61.20 61.20


13787.63 13787.63 13787.63

66.40-L
8.000 8.000 8.000 67.60-M 531.20 540.80 550.40
68.80-S
(@ 8%) (@ 10%) (@ 12%) 1103.01 1378.76 1654.52
(@ 10%) (@ 10%) (@ 10%) 1489.06 1516.64 1544.21
16910.90 17223.83 17536.76
563.70 574.13 584.56
say 563.70 574.10 584.60
c 75 x 50 mm or 75 x 25 mm as per approved design.
in foundation shall be measured and paid separately

126.60-L
1.296 1.296 1.296 128.90-M 164.07 167.05 170.16
131.30-S

3331.70-L
0.648 0.648 0.648 3401.70-M 2158.94 2204.30 2261.13
3489.40-S

66.40-L
4.710 4.710 4.710 67.60-M 312.74 318.40 324.05
68.80-S
66.40-L
2.160 2.160 2.160 67.60-M 143.42 146.02 148.61
68.80-S

0.010 0.010 0.010 310.000 3.100 3.100 3.100


0.250 0.250 0.250 292.000 73.000 73.000 73.000
0.010 0.010 0.010 394.000 3.940 3.940 3.940

30.000 30.000 30.000 221.220 6636.600 6636.600 6636.600

99.360 99.360 99.360 46.658 4635.939 4635.939 4635.939

225.451 225.451 225.451

0.040 0.040 0.040 612.000 24.480 24.480 24.480


11602.510 11602.510 11602.510
(@ 8%) (@ 10%) (@ 12%) 928.201 1160.251 1392.301
(@ 10%) (@ 10%) (@ 10%) 1253.071 1276.276 1299.481
16562.965 16874.805 17198.244
1656.296 1687.480 1719.824
say 1656.300 1687.500 1719.800

126.60-L
1.296 1.296 1.296 128.90-M 164.07 167.05 170.16
131.30-S

3331.70-L
0.648 0.648 0.648 3401.70-M 2158.94 2204.30 2261.13
3489.40-S

3804.00-L
4.710 4.710 4.710 3882.70-M 17916.84 18287.52 18742.03
3979.20-S

66.40-L
2.160 2.160 2.160 67.60-M 143.42 146.02 148.61
68.80-S

0.010 0.010 0.010 310.000 3.10 3.10 3.10


0.250 0.250 0.250 292.000 73.00 73.00 73.00
0.010 0.010 0.010 394.000 3.94 3.94 3.94
0.00 0.00 0.00
30.000 30.000 30.000 221.220 6636.60 6636.60 6636.60

0.040 0.040 0.040 612.000 24.48 24.48 24.48


6741.12 6741.12 6741.12
(@ 8%) (@ 10%) (@ 12%) 539.29 674.11 808.93
(@ 10%) (@ 10%) (@ 10%) 728.04 741.52 755.01
28391.73 28961.64 29627.00
2839.17 2896.16 2962.70
2839.20 2896.20 2962.70

4441.00-L
4.860 4.860 4.860 4531.60-M 21583.26 22023.58 22549.43
4639.80-S

0.194 0.194 0.194 46824.00 9083.86 9083.86 9083.86

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.250 0.250 0.250 961.32 240.33 240.33 240.33


(@ 8%) (@ 10%) (@ 12%) 43.58 54.47 65.37
(@ 10%) (@ 10%) (@ 10%) 58.83 59.92 61.01
31314.26 31766.56 32304.39
1565.71 1588.33 1615.22
say 1565.70 1588.30 1615.20

4441.00-L
4.860 4.860 4.860 4531.60-M 21583.26 22023.58 22549.43
4639.80-S

0.194 0.194 0.194 46824.000 9083.86 9083.86 9083.86


0.040 0.040 0.040 310.000 12.40 12.40 12.40
1.000 1.000 1.000 292.000 292.00 292.00 292.00

0.250 0.250 0.250 961.320 240.33 240.33 240.33


(@ 8%) (@ 10%) (@ 12%) 43.58 54.47 65.37
(@ 10%) (@ 10%) (@ 10%) 58.83 59.92 61.01
31314.26 31766.56 32304.39
1565.71 1588.33 1615.22
say 1565.70 1588.30 1615.20
not to be measured separately.
e measured & Paid separately.
on foundation.

5.220 5.220 5.220 5212.90 27211.34 27211.34 27211.34

0.209 0.209 0.209 46824.00 9786.22 9786.22 9786.22

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.250 0.250 0.250 961.32 240.33 240.33 240.33


(@ 8%) (@ 10%) (@ 12%) 43.58 54.47 65.37
(@ 10%) (@ 10%) (@ 10%) 58.83 59.92 61.01
37644.69 37656.68 37668.66
1882.23 1882.83 1883.43
say 1882.20 1882.80 1883.40
not to be measured separately.
e measured & Paid separately.
on foundation.
5.220 5.220 5.220 5344.50 27898.29 27898.29 27898.29

0.209 0.209 0.209 46824.00 9786.22 9786.22 9786.22

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.250 0.250 0.250 961.32 240.33 240.33 240.33


(@ 8%) (@ 10%) (@ 12%) 43.58 54.47 65.37
(@ 10%) (@ 10%) (@ 10%) 58.83 59.92 61.01
38331.65 38343.63 38355.61
1916.58 1917.18 1917.78
say 1916.60 1917.20 1917.80
not to be measured separately.
e measured & Paid separately.
on foundation.

0.060 0.060 0.060 310.00 18.60 18.60 18.60


0.500 0.500 0.500 351.00 175.50 175.50 175.50
1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.100 0.100 0.100 612.00 61.20 61.20 61.20


41.210 41.210 41.210 47.35 1951.29 1951.29 1951.29

88.560 88.560 88.560 46.66 4132.03 4132.03 4132.03

16.240 16.240 16.240 46.66 757.73 757.73 757.73


20.000 20.000 20.000 61.74 1234.80 1234.80 1234.80

2018.96 2018.96 2018.96


10642.11 10642.11 10642.11
(@ 8%) (@ 10%) (@ 12%) 851.37 1064.21 1277.05
(@ 10%) (@ 10%) (@ 10%) 1149.35 1170.63 1191.92
12642.83 12876.96 13111.09
2809.52 2861.55 2913.57
say 2809.50 2861.50 2913.60

0.060 0.060 0.060 310.00 18.60 18.60 18.60


0.500 0.500 0.500 351.00 175.50 175.50 175.50
1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.100 0.100 0.100 612.00 61.20 61.20 61.20

72.940 72.940 72.940 47.35 3453.71 3453.71 3453.71

98.400 98.400 98.400 46.66 4591.15 4591.15 4591.15

26.860 26.860 26.860 46.66 1253.23 1253.23 1253.23


30.000 30.000 30.000 61.74 1852.20 1852.20 1852.20
1672.54 1672.54 1672.54
13370.13 13370.13 13370.13
(@ 8%) (@ 10%) (@ 12%) 1069.61 1337.01 1604.42
(@ 10%) (@ 10%) (@ 10%) 1443.97 1470.71 1497.45
15883.72 16177.86 16472.00
3529.72 3595.08 3660.45
say 3529.70 3595.10 3660.40
thrie beam section should be provided on both sides of
or metal beam railing and spacer is required to be made

0.120 0.120 0.120 310.00 37.20 37.20 37.20


2.000 2.000 2.000 292.00 584.00 584.00 584.00
1.000 1.000 1.000 351.00 351.00 351.00 351.00

190.000 190.000 190.000 46.66 8865.02 8865.02 8865.02

46.000 46.000 46.000 46.66 2146.27 2146.27 2146.27

188.400 188.400 188.400 46.66 8790.37 8790.37 8790.37


65.000 65.000 65.000 42.65 2772.25 2772.25 2772.25

1128.70 1128.70 1128.70

24674.80 24674.80 24674.80

66.40-L
16.500 16.500 16.500 67.60-M 1095.60 1115.40 1135.20
68.80-S

0.250 0.250 0.250 612.00 153.00 153.00 153.00


(@ 8%) (@ 10%) (@ 12%) 1986.22 2482.78 2979.34
(@ 10%) (@ 10%) (@ 10%) 2681.40 2731.06 2780.71
30591.03 31157.04 31723.05
2039.40 2077.14 2114.87
say 2039.40 2077.10 2114.90
will be measured and included separately as per the

0.004 0.004 0.004 310.00 1.24 1.24 1.24


0.100 0.100 0.100 292.00 29.20 29.20 29.20

16.000 16.000 16.000 123.62 1977.92 1977.92 1977.92


4.320 4.320 4.320 46.66 201.56 201.56 201.56

4.800 4.800 4.800 46.66 223.96 223.96 223.96

120.17 120.17 120.17

66.40-L
1.830 1.830 1.830 67.60-M 121.51 123.71 125.90
68.80-S

(@ 8%) (@ 10%) (@ 12%) 204.32 255.41 306.49


(@ 10%) (@ 10%) (@ 10%) 275.84 280.95 286.05
3155.73 3214.11 3272.50
say 3155.70 3214.10 3272.50
approved design to be measured and paid separately

0.004 0.004 0.004 310.00 1.24 1.24 1.24


0.100 0.100 0.100 292.00 29.20 29.20 29.20

10.580 10.580 10.580 46.66 493.64 493.64 493.64


9.000 9.000 9.000 46.66 419.92 419.92 419.92
45.68 45.68 45.68

0.100 0.100 0.100 612.00 61.20 61.20 61.20


66.40-L
0.850 0.850 0.850 67.60-M 56.43 57.48 58.52
68.80-S

(@ 8%) (@ 10%) (@ 12%) 84.07 105.09 126.11


(@ 10%) (@ 10%) (@ 10%) 113.50 115.60 117.70
1304.88 1329.04 1353.21
869.92 886.03 902.14
say 869.90 886.00 902.10
approved design to be measured and paid separately. Rate
pter.

0.030 0.030 0.030 310.00 9.30 9.30 9.30


0.500 0.500 0.500 292.00 146.00 146.00 146.00
0.250 0.250 0.250 394.00 98.50 98.50 98.50

1.000 1.000 1.000 INPUT #VALUE! #VALUE! #VALUE!

1.000 1.000 1.000 170.68 170.68 170.68 170.68


#VALUE! #VALUE! #VALUE!

66.40-L
5.750 5.750 5.750 67.60-M 381.80 388.70 395.60
68.80-S

66.40-L
4.630 4.630 4.630 67.60-M 307.43 312.99 318.54
68.80-S

(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!


(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
on will be measured and included separately in the estimate as per approved design and
is chapter.

0.024 0.024 0.024 310.00 7.44 7.44 7.44


0.400 0.400 0.400 292.00 116.80 116.80 116.80
0.200 0.200 0.200 394.00 78.80 78.80 78.80

1.000 1.000 1.000 INPUT #VALUE! #VALUE! #VALUE!

1.000 1.000 1.000 170.68 170.68 170.68 170.68

#VALUE! #VALUE! #VALUE!

66.40-L
2.760 2.760 2.760 67.60-M 183.26 186.58 189.89
68.80-S

(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!


(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

d separately as per approved design. The rate for painting


2.360 2.360 2.360 3081.40 7272.10 7272.10 7272.10

0.050 0.050 0.050 310.00 15.50 15.50 15.50


1.000 1.000 1.000 292.00 292.00 292.00 292.00
0.250 0.250 0.250 370.00 92.50 92.50 92.50

20.000 20.000 20.000 516.74 10334.80 10334.80 10334.80

7.200 7.200 7.200 163.53 1177.42 1177.42 1177.42


9.000 9.000 9.000 55.00 495.00 495.00 495.00
0.020 0.020 0.020 3692.60 73.85 73.85 73.85

0.500 0.500 0.500 612.00 306.00 306.00 306.00


(@ 8%) (@ 10%) (@ 12%) 1022.97 1278.71 1534.45
(@ 10%) (@ 10%) (@ 10%) 1381.00 1406.58 1432.15
22463.14 22744.46 23025.77
1123.16 1137.22 1151.29
say 1123.20 1137.20 1151.30

3.370 3.370 3.370 3081.40 10384.32 10384.32 10384.32


0.090 0.090 0.090 310.00 27.90 27.90 27.90
2.000 2.000 2.000 292.00 584.00 584.00 584.00
0.250 0.250 0.250 370.00 92.50 92.50 92.50

40.000 40.000 40.000 516.74 20669.60 20669.60 20669.60


14.400 14.400 14.400 163.53 2354.83 2354.83 2354.83
18.000 18.000 18.000 55.00 990.00 990.00 990.00
0.040 0.040 0.040 3692.60 147.70 147.70 147.70

1.000 1.000 1.000 612.00 612.00 612.00 612.00


25478.54 25478.54 25478.54
(@ 8%) (@ 10%) (@ 12%) 2038.28 2547.85 3057.42
(@ 10%) (@ 10%) (@ 10%) 2751.68 2802.64 2853.60
40652.82 41213.35 41773.87
2032.64 2060.67 2088.69
say 2032.60 2060.70 2088.70

4.380 4.380 4.380 3081.40 13496.53 13496.53 13496.53

0.160 0.160 0.160 310.00 49.60 49.60 49.60


3.000 3.000 3.000 292.00 876.00 876.00 876.00
1.000 1.000 1.000 370.00 370.00 370.00 370.00

60.000 60.000 60.000 516.74 31004.40 31004.40 31004.40


21.600 21.600 21.600 163.53 3532.25 3532.25 3532.25
27.000 27.000 27.000 55.00 1485.00 1485.00 1485.00

0.060 0.060 0.060 3748.70 224.92 224.92 224.92

1.500 1.500 1.500 612.00 918.00 918.00 918.00


38460.17 38460.17 38460.17
(@ 8%) (@ 10%) (@ 12%) 3076.81 3846.02 4615.22
(@ 10%) (@ 10%) (@ 10%) 4153.70 4230.62 4307.54
59187.21 60033.34 60879.46
2959.36 3001.67 3043.97
y of the agency who is laying the duct. Hence not included. say 2959.40 3001.70 3044.00
d cement mortar to be adopted from respective clauses.
0.120 0.120 0.120 310.00 37.20 37.20 37.20
2.000 2.000 2.000 292.00 584.00 584.00 584.00
1.000 1.000 1.000 351.00 351.00 351.00 351.00

1.050 1.050 1.050 31920.15 33516.16 33516.16 33516.16

5027.42 5027.42 5027.42

335.16 335.16 335.16

1.000 1.000 1.000 1183.00 1183.00 1183.00 1183.00


41033.94 41033.94 41033.94
(@ 8%) (@ 10%) (@ 12%) 3282.72 4103.39 4924.07
(@ 10%) (@ 10%) (@ 10%) 4431.67 4513.73 4595.80
48748.32 49651.07 50553.82
say 48748.30 49651.10 50553.80
0.070 0.070 0.070 310.00 21.70 21.70 21.70
1.500 1.500 1.500 292.00 438.00 438.00 438.00
0.250 0.250 0.250 351.00 87.75 87.75 87.75

80.000 80.000 80.000 76.91 6152.80 6152.80 6152.80


150.000 150.000 150.000 42.65 6397.50 6397.50 6397.50

63.98 63.98 63.98

3.000 3.000 3.000 612.00 1836.00 1836.00 1836.00


14997.73 14997.73 14997.73
(@ 8%) (@ 10%) (@ 12%) 1199.82 1499.77 1799.73
(@ 10%) (@ 10%) (@ 10%) 1619.75 1649.75 1679.75
17817.30 18147.25 18477.20
890.86 907.36 923.86
say 890.90 907.40 923.90

0.130 0.130 0.130 310.00 40.30 40.30 40.30


3.000 3.000 3.000 292.00 876.00 876.00 876.00
0.250 0.250 0.250 351.00 87.75 87.75 87.75

50.000 50.000 50.000

50.000 50.000 50.000 123.71 6185.50 6185.50 6185.50


8.000 8.000 8.000 175.80 1406.40 1406.40 1406.40
15.000 15.000 15.000 42.65 639.75 639.75 639.75
6.40 6.40 6.40

2.000 2.000 2.000 612.00 1224.00 1224.00 1224.00


10466.10 10466.10 10466.10
(@ 8%) (@ 10%) (@ 12%) 837.29 1046.61 1255.93
(@ 10%) (@ 10%) (@ 10%) 1130.34 1151.27 1172.20
12433.72 12663.98 12894.23
621.69 633.20 644.71
say 621.70 633.20 644.70
0.100 0.100 0.100 310.00 31.00 31.00 31.00
2.500 2.500 2.500 292.00 730.00 730.00 730.00

40.000 40.000 40.000 INPUT #VALUE! #VALUE! #VALUE!


12.000 12.000 12.000 73.60 883.20 883.20 883.20
100.000 100.000 100.000 42.65 4265.00 4265.00 4265.00

42.65 42.65 42.65

2.000 2.000 2.000 612.00 1224.00 1224.00 1224.00


2.000 2.000 2.000 907.00 1814.00 1814.00 1814.00
#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
0.040 0.040 0.040 310.00 12.40 12.40 12.40
1.000 1.000 1.000 292.00 292.00 292.00 292.00

50.000 50.000 50.000 169.19 8459.50 8459.50 8459.50

845.95 845.95 845.95


9609.85 9609.85 9609.85
(@ 8%) (@ 10%) (@ 12%) 768.79 960.99 1153.18
(@ 10%) (@ 10%) (@ 10%) 1037.86 1057.08 1076.30
11416.50 11627.92 11839.34
228.33 232.56 236.79
say 228.30 232.60 236.80
0.020 0.020 0.020 310.00 6.20 6.20 6.20
0.500 0.500 0.500 292.00 146.00 146.00 146.00

68.000 68.000 68.000 INPUT #VALUE! #VALUE! #VALUE!

0.100 0.100 0.100 612.00 61.20 61.20 61.20


#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
66.40-L
2.500 2.500 2.500 67.60-M 166.00 169.00 172.00
68.80-S

0.090 0.090 0.090 310.00 27.90 27.90 27.90


1.000 1.000 1.000 292.00 292.00 292.00 292.00
1.000 1.000 1.000 351.00 351.00 351.00 351.00
0.250 0.250 0.250 394.00 98.50 98.50 98.50

3.500 3.500 3.500 INPUT #VALUE! #VALUE! #VALUE!


10.000 10.000 10.000 123.62 1236.20 1236.20 1236.20
8.000 8.000 8.000 73.84 590.72 590.72 590.72
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

0.500 0.500 0.500 612.00 306.00 306.00 306.00


#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
0.040 0.040 0.040 310.00 12.40 12.40 12.40
0.250 0.250 0.250 292.00 73.00 73.00 73.00
0.500 0.500 0.500 373.00 186.50 186.50 186.50
0.250 0.250 0.250 394.00 98.50 98.50 98.50

25.000 25.000 25.000 46.66 1166.45 1166.45 1166.45


15.000 15.000 15.000 46.66 699.87 699.87 699.87
0.500 0.500 0.500 224.02 112.01 112.01 112.01

37.33 37.33 37.33


2386.06 2386.06 2386.06
(@ 8%) (@ 10%) (@ 12%) 190.88 238.61 286.33
(@ 10%) (@ 10%) (@ 10%) 257.69 262.47 267.24
2834.64 2887.13 2939.62
say 2834.60 2887.10 2939.60

0.048 0.048 0.048 310.00 14.88 14.88 14.88


0.300 0.300 0.300 292.00 87.60 87.60 87.60
0.600 0.600 0.600 373.00 223.80 223.80 223.80
0.300 0.300 0.300 394.00 118.20 118.20 118.20

15.000 15.000 15.000 46.66 699.87 699.87 699.87

50.000 50.000 50.000 46.66 2332.90 2332.90 2332.90


1.000 1.000 1.000 224.02 224.02 224.02 224.02

30.33 30.33 30.33


3731.60 3731.60 3731.60
(@ 8%) (@ 10%) (@ 12%) 298.53 373.16 447.79
(@ 10%) (@ 10%) (@ 10%) 403.01 410.48 417.94
4433.14 4515.23 4597.33
say 4433.10 4515.20 4597.30
0.060 0.060 0.060 310.00 18.60 18.60 18.60
0.300 0.300 0.300 292.00 87.60 87.60 87.60
0.600 0.600 0.600 373.00 223.80 223.80 223.80
0.600 0.600 0.600 394.00 236.40 236.40 236.40

0.180 0.180 0.180 41951.09 7551.20 7551.20 7551.20

75.51 75.51 75.51


8193.11 8193.11 8193.11
(@ 8%) (@ 10%) (@ 12%) 655.45 819.31 983.17
(@ 10%) (@ 10%) (@ 10%) 884.86 901.24 917.63
9733.41 9913.66 10093.91
say 9733.40 9913.70 10093.90

0.240 0.240 0.240 310.00 74.40 74.40 74.40


3.000 3.000 3.000 292.00 876.00 876.00 876.00
1.000 1.000 1.000 373.00 373.00 373.00 373.00
2.000 2.000 2.000 351.00 702.00 702.00 702.00

1800.000 1800.000 1800.000 6.075 10935.00 10935.00 10935.00


22.000 22.000 22.000 4.84 106.57 106.57 106.57
0.090 0.090 0.090 175.80 15.82 15.82 15.82
1.250 1.250 1.250 224.02 280.03 280.03 280.03
13362.82 13362.82 13362.82
(@ 8%) (@ 10%) (@ 12%) 1069.03 1336.28 1603.54
(@ 10%) (@ 10%) (@ 10%) 1443.18 1469.91 1496.64
15875.02 16169.01 16462.99
say 15875.00 16169.00 16463.00
0.020 0.020 0.020 310.00 6.20 6.20 6.20
0.250 0.250 0.250 292.00 73.00 73.00 73.00
0.250 0.250 0.250 373.00 93.25 93.25 93.25

1.000 1.000 1.000 123.71 123.71 123.71 123.71


0.500 0.500 0.500 224.02 112.01 112.01 112.01
408.17 408.17 408.17
(@ 8%) (@ 10%) (@ 12%) 32.65 40.82 48.98
(@ 10%) (@ 10%) (@ 10%) 44.08 44.90 45.72
484.91 493.89 502.87
say 484.90 493.90 502.90

0.010 0.010 0.010 310.00 3.10 3.10 3.10


0.250 0.250 0.250 292.00 73.00 73.00 73.00

1.000 1.000 1.000 INPUT #VALUE! #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
0.010 0.010 0.010 310.00 3.10 3.10 3.10
0.250 0.250 0.250 292.00 73.00 73.00 73.00

1.000 1.000 1.000 INPUT #VALUE! #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

0.010 0.010 0.010 310.00 3.10 3.10 3.10


0.250 0.250 0.250 292.00 73.00 73.00 73.00

1.000 1.000 1.000 INPUT #VALUE! #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
0.040 0.040 0.040 310.00 12.40 12.40 12.40
1.000 1.000 1.000 292.00 292.00 292.00 292.00

1.000 1.000 1.000 51.91 51.91 51.91 51.91


1.000 1.000 1.000 26.06 26.06 26.06 26.06
382.37 382.37 382.37
(@ 8%) (@ 10%) (@ 12%) 30.59 38.24 45.88
(@ 10%) (@ 10%) (@ 10%) 41.30 42.06 42.83
454.26 462.67 471.08
say 454.30 462.70 471.10

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!
1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!

1 1 1 INPUT #VALUE! #VALUE! #VALUE!


tely on item no. 8.50.
ons Drilling may be done as per rates in relevant chapters

4.860 4.860 4.860 5344.50 25974.27 25974.27 25974.27

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.170 0.170 0.170 INPUT #VALUE! #VALUE! #VALUE!


(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
not to be measured separetely.
e measured & Paid separately.
2.

5.220 5.220 5.220 5344.50 27898.29 27898.29 27898.29

0.040 0.040 0.040 310.00 12.40 12.40 12.40


1.000 1.000 1.000 292.00 292.00 292.00 292.00

0.183 0.183 0.183 INPUT #VALUE! #VALUE! #VALUE!


(@ 8%) (@ 10%) (@ 12%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
not to be measured separetely.
e measured & Paid separately.
2.
Input_Ref

L-12
L-10
L-13

PM76001
PM34001

PM11001

PM11002

PM11003

21.20
M-191
L-12
L-10
L-13

PM37001

PM76001
PM34001
PM61002

PM11001

PM11002

PM11003

21.20
M-191
L-12
L-10
L-13

PM76001
PM34001

PM11001

PM11002

PM11003

21.20
M-191

L-12
L-10
L-13

PM37001

PM76001
PM34001
PM61002
PM11001

PM11002

PM11003

21.21
M-191

L-12
L-18
L-13

M130
L-12
L-18
L-13

M130

9.01 A (i)

9.06 E
Case-II

8.09

L-12
L-13
M181/1000

M181/1000

M061

M061

M061

M061

M061

M061

M061

M061

M061

M061
M061

M061

M061

M061

M061

M061

PM12001
9.01 A (I)

9.06 E
Case-II

8.09

L-12
L-13

M181/1000

M181/1000

M061

M061
M061

M061

M061

M061

M061

M061

M061

M061

M061

M061

M061
M061

M061

M061

PM12001
9.01 A (I)

9.06 E
Case-II

8.09 A

L-12
L-13

M181/1000
M181/1000

M061

PM12001
9.01 A (I)

9.06 E
Case-II

8.09

L-12
L-13

M181/
1000
M181/
1000

M061

PM12001
L-12
L-25
L-13

M060

PM63001
PM6004
L-12
L-25
L-13

M059

L-12
L-18
L-13

M130
L-12
L-18
L-13

M130

L-12
L-18
L-13

M130
L-12
L-18
L-13

M131

L-12
L-18
L-13

M131
L-12
L-18
L-13

M131

L-12
L-18
L-13

M131

L-12
L-13

PM40001
PM12001

M117
M153

9.06 A
Case-II

9.07/
1000

9.01 A (I)

8.08

8.03(ii)
L-12
L-10
L-13

PM12001

9.06 A
Case-II

9.07/
1000

9.01 A (I)

8.08

8.03(ii)

L-12
L-10
L-13
PM12001

9.06 A
Case-II

9.07/1000

9.01 A (I)

8.08

8.03 (ii)

L-12
L-10
L-13

PM12001
L-12
L-13

M092

9.06 A
Case-II

9.07/1000
9.01 A (I)

8.03 (ii)

L-12
L-13

PM12001

M-008

L-12
L-25
L-13

M063
M181
/1000

8.08

L-12
L-25
L-13

M063

M181/
1000

8.08
L-12
L-02
L-13

M181/
1000
M181/
1000
M193

M193

PM12001

item 8.9
9.01 A (I)

9.06 Case-II

8.09

item 8.9

L-12
L-13
L-02

M176

M181/
1000

PM12001
9.01 A (I)

9.06 A
Case-II

9.06 B
Case-II

8.09

L-12
L-13
L-02

M176

PM12001
9.06 E
Case-II

M083

L-12
L-13

M143

9.06 E
Case-II

M083
L-12
L-13

M143

12.11 A (ii)
Case-II

M083

L-12
L-13

M143
12.11 A(iii)
Case-II

M083

L-12
L-13

M143

L-12
L-25
L-13

PM12001
M089

M181/
1000
M181/
1000
M129

L-12
L-25
L-13

PM12001

M089

M181/
1000
M181/
1000
M129
L-12
L-13
L-25

M181/
1000
M181/
1000
M181/
1000
M179

8.09

PM12001

L-12
L-13

M175
M181/
1000
M181/
1000

8.09

L-12
L-13

M181/1000
M181/1000

PM12001
8.09

L-12
L-13
L-02

M172

M169

item 8.9

item 8.9
L-12
L-13
L-02

M171

M169

8.09
12.07 (B)

L-12
L-13
L-15

M152

M-009
M084
15.05 (B)

PM12001

12.07 B
L-12
L-13
L-15

M152
M-009
M084
15.05 B

PM12001

12.07 B

L-12
L-13
L-15

M152
M-009
M084

21.01 B

PM12001
L-12
L-13
L-25

M060

PM6004
L-12
L-13
L-25

M162
M178

PM12001

L-12
L-13
L-25

M173
M-004
M178

PM12001
L-12
L-13

M138
M191
M178

PM12001
PM11003
L-12
L-13

M062
L-12
L-13

M188

PM12001
8.09

L-12
L-13
L-25
L-02

M177
M175
M082

PM12001
L-12
L-13
L-18
L-02

M181/
1000
M181/
1000
M130

L-12
L-13
L-18
L-02

M181/
1000
M181/
1000
M130
L-12
L-13
L-18
L-04

M187

L-12
L-13
L-18
L-10

M079
M081/1000
M-004
M130
L-12
L-13
L-18

M173
M130

L-12
L-13

M238
L-12
L-13

M237

L-12
L-13

M236
L-12
L-13

M099
M198

M244
M245
M246
M247
M248

M249
M250
M251
M252
M253
M254
M255
M256
M257
M258

M259

M260
M261
M262
M263

M264

M265

M266

M267
M268

M269
M270

M271
M272

M273
M274

M275

M276
M277

M278

M279
M280
M281
M282

M283

M284

M285

12.11 A
(iii) Case II

L-12
L-13

M225
12.11 A (iii)
Case II

L-12
L-13

M225
CHAPTER - 9
PIPE CULVERTS
Ref. to
Sr. No. MoRTH Description Unit Quantity as per project category
Spec.
9.01 304 Excavation for structures Large Medium

Earth work in excavation of foundation of structures as per


drawing and technical specification , including setting out ,
construction of shoring and bracing , removal of stumps and
other deleterious matter , dressing of sides and bottom and
backfilling with approved material.

I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140
Mazdoor day 3.500 3.500
b) Overhead charges
c) Contractor's profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

1. Cost of dewatering may be added where required , upto ,


Note 10 percent of labour cost Assessment for dewatering shall be
made as per site conditions.

2. The excavated earth can be used partially for backfilling of


foundation pit and partly for road work except for marshy soil
.Hence cost of disposal has not been added except for
marshy soil .This remark is common to all cases of item 9.01
excluding marshy soil .

3 . The cost of shoring and shuttering , where needed , may


be added @ 1 percent on cost of excavation for open
foundation .

9.01 A (ii) Depth 3 m to 6 m


a) Labour
Mate / Supervisor day 0.180 0.180
Mazdoor day 4.500 4.500
b) Overhead charges
c) Contractor's profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
1. Cost of dewatering may be added where required upto
Note 15 percent of labour cost. Assessment for dewatering shall
be done as per actual ground conditions.

9.01 A (iiI) Depth above 6 m


a) Labour
Mate / Supervisor day 0.240 0.240
Mazdoor day 6.000 6.000
b) Overhead charges
c) Contractor's profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

1. Cost of dewatering may be added where required upto


Note
20 percent of labour cost.
2 .. Assessment for dewatering shall be made as per site
conditions.

9.01 B (i) Mechanical Means( Depth upto 3 m )


Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day .8.000 .8.000
b) Machinery Hydraulic Excavator
For excavation
(i) 1.2 cum bucket .4.627
hour
capacity
(ii) 1.1 cum bucket 5.329
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For backfilling ( considering 60 % of the excavated material )
(i) 1.2 cum bucket 2.776
hour
capacity
(ii) 1.1 cum bucket 3.197
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Tipper for transportation of excess material to dumping yard
considering lead @ 1 km
(i) 18 cum capacity t-km 198.000
(ii) 14 cum capacity t-km 198.000
(iiI) 10 cum capacity
t-km

c) Overhead charges
d) Contractor's profit
Cost for 330 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 330

9.01 B (iI) Mechanical Means( Depth 3 m to 6 m)


Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day .8.000 .8.000
b) Machinery Hydraulic Excavator
For excavation
(i) 1.2 cum bucket .4.674
hour
capacity
(ii) 1.1 cum bucket 5.383
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For backfilling ( considering 60 % of the excavated material )
(i) 1.2 cum bucket 2.804
hour
capacity
(ii) 1.1 cum bucket 3.230
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Tipper for transportation of excess material to dumping yard
considering lead @ 1 km
(i) 18 cum capacity t-km 180.000
(ii) 14 cum capacity t-km 180.000
(iiI) 10 cum capacity
t-km

c) Overhead charges
d) Contractor's profit
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 300

9.01 B (iII) Mechanical Means( Depth above 6 m)


Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day .8.000 .8.000
b) Machinery Hydraulic Excavator
For excavation
(i) 1.2 cum bucket .4.732
hour
capacity
(ii) 1.1 cum bucket 5.450
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For backfilling ( considering 60 % of the excavated material )
(i) 1.2 cum bucket 2.839
hour
capacity
(ii) 1.1 cum bucket 3.270
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Tipper for transportation of excess material to dumping yard
considering lead @ 1 km
(i) 18 cum capacity t-km 162.000
(ii) 14 cum capacity t-km 162.000
(iiI) 10 cum capacity
t-km

c) Overhead charges
d) Contractor's profit
Cost for 270 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 270

9.01 II Ordinary Rock ( not requiring blasting)


A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 0.200
Mazdoor day 5.000 5.000
b) Overhead charges @ on (a)
c) Contractor's profit @ on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

Cost of dewatering upto 10 percent of labour cost may be


Note added , where required. Assessment for dewatering shall be
made as per site conditions.

9.01 B Mechanical Means


Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.120 0.120
Mazdoor day 3.000 3.000
b) Machinery Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket 5.818
hour
capacity
(ii) 1.1 cum bucket 6.845
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For loading
(i) 1.2 cum bucket 0.872
hour
capacity
(ii) 1.1 cum bucket 1.005
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Jack Hammer hour 5.818 6.845
Tipper for transportation considering lead @ 1 km
(i) 18 cum capacity t-km 75.000
(ii) 14 cum capacity t-km 75.000
(iiI) 10 cum capacity
t-km

For loading & unloading time


(i) 18 cum capacity hour 0.872
(ii) 14 cum capacity hour 1.005
(iiI) 10 cum capacity
hour

c) Overhead charges
d) Contractor's profit
Cost for 50 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 50

301&
9.01 III Hard Rock ( requiring blasting)
302
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.350 0.350
Driller day 0.500 0.500
Blaster day 0.250 0.250
Mazdoor day 8.000 8.000
b) Machinery
Air Compressor 250 cfm 1.000 1.000
hour
with 2 jack hammer for drilling
c) Material
Explosives (Blasting Material) 3.500 3.500
kg
Detonator electric each 14.000 14.000
d) Overhead charges
e) Contractor's profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 10

Cost of dewatering @ 10 percent of (a+b) may be added ,


Note where required . Assessment for dewatering shall be made
as per site conditions.

301,
9.01 III Hard Rock ( requiring blasting)
302

Carrying out excavation in hard rock to achieve a specified


slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes , collection of the excavated rock by a dozer , loading
in tipper by a front end loader and disposing of the material
with all lifts and lead upto 1000 m, all as specified in clause
No . 303

B Mechanical Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210
Mazdoor day 3.000 3.000
Driller day 2.000 2.000
Blaster day 0.250 0.250
b) Machinery
Air Compressor hour 6.000 6.000
Jack Hammer for drilling holes (@4.5 m per hour ) hour 24.000 24.000
1.024 1.024
Jack Hammer (consider 5% of the volume for dressing ) hour

Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket 1.024
hour
capacity
(ii) 1.1 cum bucket 1.024
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For loading
(i) 1.2 cum bucket 2.094
hour
capacity
(ii) 1.1 cum bucket 2.411
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000
(ii) 14 cum capacity t-km 180.000
(iiI) 10 cum capacity
t-km

For loading & unloading time


(i) 18 cum capacity hour 2.094
(ii) 14 cum capacity hour 2.411
(iiI) 10 cum capacity
hour

c) Materials
Small dia Explosive at 0.40 kg / cum for 120 cum (120x0.40) 48.000 48.000
Explosive at 0.20 kg / cum for secondary blast @ 5 % of the kg
total volume (120x0.2x5%)
Electric detonators at 1 per hole for main blast holes 69.000 69.000
no
(21x3+20*2)= 103 nos
Ordinary detonators @ 1 per hole for 10 secondary holes 7.000 7.000
( required for 5 % of the total quantity @ 0.6 m per hole for 1 no
cum )
Detonating fuse coil m 213.000 213.000
d) Overhead charges
e) Contractor's profit
Cost for 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 120

9.01 IV Hard Rock ( blasting prohibited))


Unit = cum
Taking output = 35 cum
A Mechanical Means
a) Labour
Mate day 0.080 0.080
Mazdoor day 2.000 2.000
b) Machinery
Jack Hammer hour 5.973 7.467
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket 5.973
hour
capacity
(ii) 1.1 cum bucket 7.467
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
For loading
(i) 1.2 cum bucket 0.611
hour
capacity
(ii) 1.1 cum bucket 0.703
hour
capacity
(iiI) 0.9 cum bucket
hour
capacity
Tipper

For transportation to dumping yard considering lead @ 1 km

(i) 18 cum capacity t-km 52.500


(ii) 14 cum capacity t-km 52.500
(iiI) 10 cum capacity
t-km

For loading & unloading time


(i) 18 cum capacity hour 0.611
(ii) 14 cum capacity hour 0.703
(iiI) 10 cum capacity
hour

c) Overhead charges
d) Contractor's profit
Cost for 35 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 35

9.01 V Marshy Soil


Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual Means
a) Labour
Mate / Supervisor day 0.400 0.400
Mazdoor day 10.000 10.000
b) Machinery
Tractor -trolley for removal hour 2.670 2.670
c) Overhead charges
d) Contractor's profit
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 10

1. Cost of dewatering @ 30 percent of (a), may be


Note added , where required . Assessment for dewatering shall be
made as per site conditions.
2. Shoring & strutting 15 percent of (a) , where required may
be added

3. It is assumed that Marshy Soil will be available upto 3 m


depth only .For deeper excavation below 3 m depth , refer
analysis in item 12.01 (i) to (iv) for ordinary soil

9.01 B Mechanical Means


Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.400 0.400
Mazdoor day 1.000 1.000
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket hour 8.506
capacity
(ii) 1.1 cum bucket hour 9.796
capacity
(iiI) 0.9 cum bucket hour
capacity
Tipper
For transportation to dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 390.000
(ii) 14 cum capacity t-km 390.000
(iiI) 10 cum capacity t-km
For loading & unloading time
(i) 18 cum capacity hour 8.506
(ii) 14 cum capacity hour 9.796
(iiI) 10 cum capacity hour
c) Material
Selected earth for refilling cum 156.000 156.000
d) Overhead charges
e) Contractor's profit
Cost for 260 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 260

9.02 304 Sand Filling in Foundation Trenches as per Drawing & Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040
Mazdoor day 1.000 1.000
b) Machinery
Water tanker ( speed @ Water tanker speed km / hr and return speed @ 20 km / hr and spreading speed @ 2.5 Km / hr .)
(i) 16 KL capacity 0.125xL1+
hour
0.16
(ii) 12 KL capacity 0.167xL1+
hour
0.213
(iii) 6 KL capacity
hour
c) Material
Sand ( assuming 20 percent voids) at site Water cum 120.000 120.000
Water KL 18.000 18.000
d) Overhead charges
e) Contractor's profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 100
9.01 PCC 1:3:6 in Foundation Large Medium
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.320 0.320
Mason day 1.000 1.000
Mazdoor day 7.000 7.000
b) Material
Plain cement concrete 1:3:6 nominal mix using batching cum 15.000 15.000
plant ( Rate taken from sub-analysis 21.02)
water KL 3.240 3.240
c) Machinery
Plate Compactor Water tanker ( speed @ km /hr and return hour 1.000 1.000
speed @ km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.023xL1+
hour
0.135
(ii) 12 KL capacity 0.03xL1+
hour
0.18
(iii) 6 KL capacity
hour
d) Overhead charges
e) Contractor's profit
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 15

Note Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
9.04 2900 Laying Reinforced Cement Concrete Pipe NP4 / Prestressed
Concrete Pipe on First Class Bedding in Single Row .

Laying Reinforced cement concrete pipe NP4 / prestressed


concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length each )
A 1000 mm dia
a) Labour
Mate day 0.100 0.100
Mason day 0.500 0.500
Mazdoor day 2.000 2.000
b) Material
Sand at site cum 0.070 0.070
Cement at site tonne 0.050 0.050
RCC pipe NP-4 /prestressed concrete pipe including collar at metre 12.500 12.500
site
Granular material passing 5.6 mm sieve for bedding cum 4.500 4.500
c) Machinery
Light Crane 3 tonnes capacity for placing of Hume pipe hour 2.083 2.083
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5

Note 1. In case of cement craddle bedding, quantity of PCC M15 is


to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.04 B 1200 mm dia
a) Labour
Mate day 0.160 0.160
Mason day 1.000 1.000
Mazdoor day 3.000 3.000
b) Material
Sand at site cum 0.090 0.090
Cement at site tonne 0.070 0.070
RCC pipe NP-4/prestressed concrete pipe including collar at metre 12.500 12.500
site
Granular material passing 5-6 mm sieve for class bedding cum 5.000 5.000
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe hour 2.083 2.083
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5

Note 1. In case of cement craddle bedding, quantity of PCC M15 is


to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.04 C 1500 mm dia


a) Labour
Mate day 0.160 0.160
Mason day 1.000 1.000
Mazdoor day 3.000 3.000
b) Material
Sand at site cum 0.090 0.090
Cement at site tonne 0.070 0.070
RCC pipe NP-4/prestressed concrete pipe including collar at metre 12.500 12.500
site
Granular material passing 5-6 mm sieve for class bedding cum 5.750 5.750
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe hour 2.500 2.500
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5
Note 1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and adde
2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and pa
9.05 2900 to be
Laying Reinforced calculated
Cement as perPipe
Concrete approved design and drawings and priced separately on rates available under respect
NP4 / Prestressed
Concrete Pipe on First Class Bedding in Double Row .

Laying Reinforced cement concrete pipe NP4 / prestressed


concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.200 0.200
Mason day 1.000 1.000
Mazdoor day 4.000 4.000
b) Material
Sand at site cum 0.140 0.140
Cement at site tonne 0.100 0.100
RCC pipe NP-4/prestressed concrete pipe including collar at metre 25.000 25.000
site
Granular material passing 5.6 mm sieve for bedding cum 12.500 12.500
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe hour 4.167 4.167
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5
Note 1. In case of cement craddle bedding, quantity of PCC M15 is
to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.05 B 1200 mm dia
a) Labour
Mate day 0.320 0.320
Mason day 2.000 2.000
Mazdoor day 6.000 6.000
b) Material
Sand at site cum 0.180 0.180
Cement at site tonne 0.140 0.140
RCC pipe NP-4 /prestressed concrete pipe including collar at metre 25.000 25.000
site
Granular material passing 5-6 mm sieve for class bedding cum 13.750 13.750
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe hour 4.167 4.167
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5
Note 1. In case of cement craddle bedding, quantity of PCC M15 is
to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.05 C 1500 mm dia


a) Labour
Mate day 0.320 0.320
Mason day 2.000 2.000
Mazdoor day 6.000 6.000
b) Material
Sand at site cum 0.180 0.180
Cement at site tonne 0.140 0.140
RCC pipe NP-4 /prestressed concrete pipe including collar at metre 25.000 25.000
site
Granular material passing 5-6 mm sieve for class bedding cum 15.625 15.625
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe hour 5.000 5.000
d) Overhead charges
e) Contractor's profit
Cost for 12.5 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/ 12.5
Note 1. In case of cement craddle bedding, quantity of PCC M15 is
to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.06 1500 , Plain/ Reinforced Cement Concrete in Open


1700& Foundation complete as per Drawing and
2100 Technical Specifications .
9.06 A PCC Grade M15
Case I PCC Grade M15 using batching plant , transit mixer & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis 21.03 ) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) Labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation tonne- 75xL1 75xL1
(6 cum Capacity) km
For unloading hour 0.650 0.650
Hydraulic Boom placer hour 0.650 0.650
pump
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.109xL1+
hour
0.656
(ii) 12 KL capacity 0.146xL1+
hour
0.875
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 30 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 30

Case II PCC Grade M15 using batching plant , transit mixer & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis 21.03 ) cum 15.000 15.000

Water for curing KL 7.875 7.875


b) Labour
For pouring and placing
Mate day 0.380 0.380
Mason day 1.500 1.500
Mazdoor day 8.000 8.000
c) Machinery
Transit truck agitator
For transportation tonne- 37.5xL1 37.5xL1
(6 cum Capacity) km
For unloading hour 0.833 0.833
Water tanker ( speed @ km / hr and return speed @ km / hr and 30 mins for unloading)
(i) 16 KL capacity 0.055xL1+
hour
0.328
(ii) 12 KL capacity 0.073xL1+
hour
0.438
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
onOverhead
e) cost of concrete
charges i.e. cost of material , labour and machinery
f) Contractor's profit
Cost for 15 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 15

9.06 B PCC Grade M20


Case I PCC Grade M20 using batching plant , transit mixer & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis 21.04 ) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) Labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation tonne- 75xL1 75xL1
(6 cum Capacity) km
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @ km / hr and return speed @ km / hr and 30 mins for unloading)
(i) 16 KL capacity 0.109xL1+
hour
0.656
(ii) 12 KL capacity 0.146xL1+
hour
0.875
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 30 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 30

Case II PCC Grade M20 using batching plant , transit


mixer & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis 21.04 ) cum 15.000 15.000
Water for curing KL 7.875 7.875
b) Labour
For pouring and placing
Mate day 0.380 0.380
Mason day 1.500 1.500
Mazdoor day 8.000 8.000
c) Machinery
Transit truck agitator
For transportation tonne- 37.5xL1 37.5xL1
(6 cum Capacity) km
For unloading hour 0.833 0.833
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.055xL1+
hour
0.328
(ii) 12 KL capacity 0.073xL1+
hour
0.438
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 15 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 15

9.06 C RCC Grade M20


Case I RCC Grade M20 using batching plant , transit
mixer & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis 21.05 ) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) Labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation tonne- 75xL1 75xL1
(6 cum Capacity) km
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.109xL1+
hour
0.656
(ii) 12 KL capacity 0.146xL1+
hour
0.875
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 30 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 30

Case II RCC Grade M20 using batching plant , transit


mixer & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum 15.000 15.000
21.05 )
Water for curing KL 7.875 7.875
b) Labour
For pouring and placing
Mate day 0.420 0.420
Mason day 1.500 1.500
Mazdoor day 9.000 9.000
c) Machinery
Transit truck agitator
For transportation tonne- 37.5xL1 37.5xL1
(6 cum Capacity) km
For unloading hour 0.833 0.833
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.055xL1+
hour
0.328
(ii) 12 KL capacity 0.073xL1+
hour
0.438
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 15 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 15

9.06 D PCC Grade M25


Case I PCC Grade M25 using batching plant , transit
mixer & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum 30.000 30.000
21.06 )
Water for curing KL 15.750 15.750
b) Labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation tonne- 75xL1 75xL1
(6 cum Capacity) km
For unloading hour 0.650 0.650
Hydraulic Boom placer hour 0.650 0.650
pump
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.109xL1+
hour
0.656
(ii) 12 KL capacity 0.146xL1+
hour
0.875
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 30 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 30

Case II PCC Grade M25 using batching plant , transit


mixer & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum 15.000 15.000
21.06 )
Water for curing KL 7.875 7.875
b) Labour
For pouring and placing
Mate day 0.380 0.380
Mason day 1.500 1.500
Mazdoor day 8.000 8.000
c) Machinery
Transit truck agitator
For transportation tonne- 37.5xL1 37.5xL1
(6 cum Capacity) km
For unloading hour 0.833 0.833
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.055xL1+
hour
0.328
(ii) 12 KL capacity 0.073xL1+
hour
0.438
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 15 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 15

9.06 E RCC Grade M25


Case I RCC Grade M25 using batching plant , transit
mixer & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum 30.000 30.000
21.07 )
Water for curing KL 15.750 15.750
b) Labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation t-km 75xL1 75xL1
(6 cum Capacity)
For unloading hour 0.650 0.650
Hydraulic Boom placer hour 0.650 0.650
pump
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
0.109xL1+
(i) 16 KL capacity hour
0.656
0.146xL1+
(ii) 12 KL capacity hour
0.875
(iii) 6 KL capacity hour
d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 30 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 30

Case II RCC Grade M25 using batching plant , transit


mixer & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate taken from sub-analysis cum 15.000 15.000
21.07 )
Water for curing KL 7.875 7.875
b) Labour
For pouring and placing
Mate day 0.420 0.420
Mason day 1.500 1.500

Mazdoor day 9.000 9.000


c) Machinery
Transit truck agitator
For transportation t-km 37.5xL1 37.5xL1
(6 cum Capacity)
For unloading hour 0.833 0.833
Water tanker ( speed @ km / hr and return speed @ km / hr
and 30 mins for unloading)
(i) 16 KL capacity 0.055xL1+
hour
0.328
(ii) 12 KL capacity 0.073xL1+
hour
0.438
(iii) 6 KL capacity
hour

d) Formwork @ 10 percent
on cost of concrete i.e. cost of material , labour and
machinery
e) Overhead charges
f) Contractor's profit
Cost for 15 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/ 15
9.07 1600 Supplying ,Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per
Drawing and Technical Specifications .

Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 tonne 8.400 8.400
percent overlaps and
wastage
Binding wire Kg 48.000 48.000
b) Labour for
straightening , cutting ,
bending , shifting to site ,
tying and placing in
position
Mate day 0.160 0.160
Blacksmith day 1.000 1.000
Mazdoor day 3.000 3.000
c) Machinery
Cutting Machine & hour 5.333 5.333
Bending Machine
Electric generator 15 hour 5.333 5.333
KVA
Tipper
Tipper for
transportation
(i) 18 cum capacity t-km 8xL1
(ii) 14 cum capacity t-km 8xL1
(iiI) 10 cum capacity
t-km

loading & unloading time


(i) 18 cum capacity hour 1.000
(ii) 14 cum capacity hour 1.280
(iiI) 10 cum capacity
hour

Light weight Crane


At cutting bending yard hour 2.000 2.000
At site hour 2.000 2.000
d) Overhead charges
e) Contractor's profit
Cost for 8 MT ( a+b+c+d+e)
Rate for per MT (a+b+c+d+e)/ 8
R-9
ERTS
Rate
y as per project category Amount Input ref.
(Rs.)

Small Large Medium Small

0.140
3.500

0.180
4.500
0.240
6.000

0.320
.8.000

7.450

4.470

198.000
0.320
.8.000

7.525

4.515

180.000

0.320
.8.000
7.619

4.571

162.000

0.200
5.000

0.120
3.000
7.273

1.405

7.273

75.000

1.405

0.350
0.500
0.250
8.000

1.000

3.500
14.000

0.210
3.000
2.000
0.250

6.000
24.000
1.024

1.024

3.371
180.000

3.371

48.000

69.000

7.000

213.000

0.080
2.000

9.190

9.190
0.983

52.500

0.983

0.400
10.000

2.670
0.400
1.000

13.695

390.000

13.695

156.000

0.040
1.000

spreading speed @ 2.5 Km / hr .)

0.333XL1+
0.427

120.000
18.000
small Large Medium small

0.320
1.000
7.000

15.000

3.240

1.000

0.06XL1+
0.36

0.100
0.500
2.000
0.070
0.050
12.500

4.500

2.083

0.160
1.000
3.000

0.090
0.070
12.500

5.000

2.083
0.160
1.000
3.000

0.090
0.070
12.500

5.750

2.500

esign and priced separately and added .


s, backfilling, protection works and parapet walls. The same are
ately on rates available under respective sections

0.200
1.000
4.000

0.140
0.100
25.000

12.500

4.167
0.320
2.000
6.000

0.180
0.140
25.000

13.750

4.167

0.320
2.000
6.000

0.180
0.140
25.000

15.625

5.000
30.000
15.750

0.113
1.500
1.325

75xL1

0.650
0.650

0.292XL1+
1.75
15.000

7.875

0.380
1.500
8.000

37.5xL1

0.833

0.146XL1+
0.875

30.000
15.750

0.113
1.500
1.325

75xL1

0.650
0.650

0.292XL1+
1.75

15.000
7.875

0.380
1.500
8.000

37.5xL1

0.833
0.146XL1+
0.875

30.000
15.750

0.153
1.500
2.325

75xL1

0.650
0.650

0.292XL1+
1.75
15.000

7.875

0.420
1.500
9.000

37.5xL1

0.833

0.146XL1+
0.875

30.000

15.750
0.113
1.500
1.325

75xL1

0.650
0.650

0.292XL1+
1.75

15.000

7.875

0.380
1.500
8.000

37.5xL1
0.833

0.146XL1+
0.875

30.000

15.750

0.153
1.500
2.325

75xL1

0.650
0.650

0.292XL1+
1.75
15.000

7.875

0.420
1.500 CHAPTER
-9

9.000

37.5xL1

0.833

0.146XL1+
0.875
8.400

48.000

0.160
1.000
3.000

5.333

5.333

8xL1

1.778

2.000
2.000
CHAPTER - 10
MAINTENANCE OF ROADS
Ref. to
Sr. No. Description Unit Quantity as per project category
MoRTH
10.01 3002 Restoration of Rain Cuts Lagre Medium
Restoration of rain cuts with soil, moorum, gravel or a mixture
of these, clearing the loose soil, benching for 300 mm width,
laying fresh material in layers not exceeding 250 mm and
compacting with plate compactor or power rammers to
restore the original alignment, levels and slopes

Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 0.080
Mazdoor day 2.000 2.000
b) Machinery Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.007
(ii) 1.1 cum bucket capacity hour 0.008
(iii) 0.9 cum bucket capacity hour
Tipper for transportation to dumping yard considering lead @
1 km
(i) 18 cum capacity t-km 12×L2

(ii) 14 cum capacity t-km 12×L2

(iii) 10 cum capacity t-km

For loading & unloading


(i) 18 cum capacity hour 0.007

(ii) 14 cum capacity hour 0.008

(iii) 10 cum capacity hour

Plate compactor hour 0.500 0.500

c) Overhead charges
d) Contractor's profit
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Note Only 75 percent of fresh material has been provided as 25
per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of there in cuts
10.02 3003 Maintenance of Earthen Shoulder (filling with fresh soil)

Making up loss of material/ irregularities on shoulder to the


design level by adding fresh approved soil and compacting it
with appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate day 0.180 0.180
Mazdoor day 4.500 4.500
b) Machinery Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.011
(ii) 1.1 cum bucket capacity hour 0.012
(iii) 0.9 cum bucket capacity hour
Tipper For transportation to dumping yard considering lead
@ 1 km
(i) 18 cum capacity t-km 24×L2

(ii) 14 cum capacity t-km 24×L2

(iii) 10 cum capacity t-km

For loading & unloading


(i) 18 cum capacity hour 0.011

(ii) 14 cum capacity hour 0.012

(iii) 10 cum capacity hour

Plate compactor @ 25 sqm per hour hour 12.000 12.000

c) Overhead charges
d) Contractor's profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100

10.3 3003 Maintenance of Earth Shoulder (stripping excess soil)

Stripping excess soil from the shoulder surface to achieve


the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.100 0.100

Mazdoor day 2.500 2.500

b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 4.000

c) Overhead charges
d) Contractor's profit
Cost for 100 sqm = a+b+c+d
Rate per sqm on= (a+b+c+d)100

Note The earth stripped from earthen shoulders to be dumped on


the side slopes locally for disposal.
10.4 3004.2 Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 510, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2

Unit = Sqm
Taking out put = 10250 sqm
a) Labour
Mate Day 3.760 3.760
Mazdoor Day 90.000 90.000
Mazdoor skilled Day 4.000 4.000
b) Machinery Hot mix Plant
(i) HMP 200 TPH hour 2.700
(i) HMP 160 TPH hour 3.375
(i) HMP 120 TPH hour
Mechanical broom (2.1m sweeping width) hour 3.051 3.051
Air compressor 250 cfm hour 3.051 3.051
Electric generator
(i) 500 KVA hour 2.700
(ii) 400 KVA hour 3.375
(iii) 250 KVA hour
Front end loader for feeding the plant tonne
(i) 3.1 Cum Capacity hour 2.700
(ii) 2.1 Cum Capacity hour 3.375
(iii) 1 Cum Capacity hour
Tipper
For transportation
(i) 18 cum capacity t-km 405×L

(ii) 14 cum capacity t-km 405×L

(iii) 10 cum capacity t-km

For loading & unloading time


(i) 18 cum capacity hour 2.700

(ii) 14 cum capacity hour 3.375

(iii) 10 cum capacity hour

smooth steel wheeled tandem roller for static and vibratory hour 14.512 14.512
passages
c) Material
Crushed stone aggregates nominal size 13.2 mm cum 184.500 184.500

Crushed stone aggregates nominal size 11.2 mm cum 92.250 92.250

Bitumen 80/100 tonne 14.970 14.970

Bitumen emulsion for tack coat including vertical sides tonne 2.460 2.460
of pot hole.
d) Overhead charges
e) Contractor's profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250

10.05 3004.2 Filling Pot-holes and Patch Repairs with Bituminous


concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2

Unit = Sqm
Taking out put = 4900 sqm
a) Labour
Mate Day 2.920 2.920

Mazdoor Day 70.000 70.000

Mazdoor skilled Day 3.000 3.000

b) Machinery Hot Mix Plant


(i) HMP 200 TPH hour 3.000

(ii) HMP 160 TPH hour 3.750

(iii) HMP 120 TPH hour


Mechanical broom (2.1m sweeping width) hour 1.458 1.458

Air compressor 250 cfm hour 1.458 1.458

Electric generator
(i) 500 KVA hour 3.000

(ii) 400 KVA hour 3.750

(iii) 250 KVA hour


Front end loader for feeding the plant
(i) 3.1 cum capacity hour 3.000

(ii) 2.1 cum capacity hour 3.750

(iii) 1 cum capacity hour


Tipper
For Transportation
(i) 18 cum capacity t.km 450x L

(ii) 14 cum capacity t.km 450x L

(iii) 10 cum capacity t.km


For loading & unloading time
(i) 18 cum capacity hour 3.000

(ii) 14 cum capacity hour 3.750

(iii) 10 cum capacity hour


Smooth steel wheeled tandem roller for static and vibratory hour 13.875 13.875
passages
c) Material
I) Bitumen tonne 23.890 23.890

ii) Bitumen emulsion for tack coat . tonne 1.180 1.180

iii) Aggregates
Grading I - 19mm (Nominal size)
20-10mm 38 percent cum 108.255 108.255

10-5 mm 17 percent cum 48.430 48.430

5mm and below 43 per cent cum 122.499 122.499

Filler @ 2 percent of weight of aggregates tonne 8.546 8.546

Add 5 per cent for wastage


or
Grading-II 13mm (Nominal size)
13.2-10 mm 21 percent cum 59.825 85.500

10-5 mm 17 percent cum 48.430 71.250

5 mm and Below 60 percent cum 170.928 122.550

Filler 2 percent tonne 8.546 8.546

Add 5 per cent for wastage


Any one of the above alternatives of aggregate i.e. 19mm or
13mm nominal size may be adopted as per approved design.

10.5 (i) for grading I Material


d)Overhead charges
e)Contractor's profit
Cost for 4900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4900

10.5 (ii) for grading II Material


d)Overhead charges
e)Contractor's profit
Cost for 4900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4900

Note For detailed working of quantities of aggregates,& bitumen


refer item 5.05 of chapter 5.
10.6 3004.3.3 Crack Filling

Filling of crack using slow - curing bitumen emulsion and


applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 0.040

Mazdoor day 1.000 1.000

b) Material
Slow-curing bitumen emulsion Kg 33.000 33.000

Stone crusher dust cum 0.020 0.020

c)Overhead charges
d)Contractor's profit
Cost for 500sqm = a+b+c+d
Rate per meter = (a+b+c+d+e)/500
10.7 3004.4 Dusting
Applying crusher dust to areas of road where bleeding of
excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 0.080

Mazdoor day 2.000 2.000

b) Material
Stone crusher dust finer than 3mm with not more than cum 6.250 6.250
10 percent passing 0.075 sieve.
c)Overhead charges
d)Contractor's profit
Cost for 3500sqm = a+b+c+d
Rate per meter = (a+b+c+d)/3500

10.08 (A) Fog Seal sqm


3004.3.2

(B) Crack Prevention courses.


3004.3.4

(i) Stress Absorbing Membrane (SAM) crack width less than 6 sqm
mm
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to sqm
9 mm
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm sqm
and cracked area above 50 percent
(iv) Bitumen Impregnated Geotextile sqm
10.08 (C) Slurry Seal
3004.5
(i) 5 mm thickness sqm
(ii) 3 mm thickness sqm
(iii) 1.5 mm thickness sqm
10.08 (D) Surface Dressing for maintenance works.
3004.6
(i) 19 mm nominal chipping size sqm
(ii) 13 mm nominal size chipping sqm
The above mentioned items have already been included in
chapter 5.
10.09 3005.1 Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 0.040

Mazdoor day 0.500 0.500


Chiseller day 0.500 0.500

b) Material
Epoxy primer kg 2.500 2.500

Epoxy compound with accessories for preparing kg 10.000 10.000


epoxy mortar
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 0.050

d)Overhead charges
e)Contractor's profit
Cost for 10 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10

10.10 3005.2 Repair of old Joints Sealant


Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.020 0.020

Mazdoor day 0.500 0.500

b) Material
Primer kg 0.250 0.250

Sealant kg 1.000 1.000

c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 0.050

d)Overhead charges
e)Contractor's profit
Cost for 10 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10

10.11 Hill Side Drain Clearance


Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2 cum

a) Labour
Mate day 0.040 0.040

Mazdoor day 1.000 1.000

b)Overhead charges
c)Contractor's profit
Cost for 10 metres = a+b+c
Rate per metre = (a+b+c)/10
10.12 3000 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock by a bull-
dozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040

Mazdoor day 1.000 1.000

b) Machinery
Dozer 175 HP hour 1.670 1.670

b)Overhead charges
c)Contractor's profit
Cost for 100 cum = a+b+c+d
Rate per cum = (a+b+c+d)/100

Note Land Slide clearance involves pushing of loose earth slided


on the road surface from hill face on the valley side. Since no
cutting of original ground is involved, the output of dozer has
been taken as 60 cum per hour for soil, ordinary rock and
blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.

10.13 3000 Landslide Clearance in Hard Rock Requiring Blasting

Clearing of land slide in hard rock requiring blasting for 50


per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.093 0.093

Mazdoor day 1.500 1.500

Driller day 0.750 0.750

Blaster day 0.070 0.070

b) Machinery
Dozer 175 HP hour 1.670 1.670

Air compressor 250 cfm with two jack hammer hour 2.500 2.500

c) Materials
Explosives kg 17.500 17.500

Electric Detonators @ 1 Detonator for 2 Gelatin sticks each 70.000 70.000


of 125 gms each
d)Overhead charges
e)Contractor's profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Note Credit for the rock if found acceptable as construction
material shall be afforded
10.14 3000 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 0.080

Mazdoor day 2.000 2.000

b) Machinery
Dozer 175 HP hour 5.880 5.880

c)Overhead charges
d)Contractor's profit
Cost for 5000 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5000

Note i) Labour provided will not be cutting the snow. They will be
guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc
10.15 3000 Snow Clearance on Roads with Snow Blowers
Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum
Taking output = 3600 cum
a) Labour
Mate day 0.080 0.080

Mazdoor day 2.000 2.000

b) Machinery
Snow blower equipment 175 HP @ 600 cum per hour hour 6.000 6.000

c)Overhead charges
d)Contractor's profit
Cost for 3600 cum (a+b+c+d)
Rate per cum = (a+b+c+d)/3600

10.16 811 Replacement of Metal Beam


Crash Barrier
A Type - A , " W" : Metal Beam
Crash Barrier
Replacement of "W" metal
beam crash barrier comprising
of 3 mm thick corrugated
sheet metal beam rail , 70 cm
above road / ground level , fixed
on ISMC series channel
vertical post , 150x75x5 mm
spaced 2 m centre to centre,
1.8 m high , 1.1 m below
ground /road level, all steel
parts and fitments to be
galvanised by hot dip process ,
all fittings to conform to
IS: 1367 and IS :1364 , metal
beam rail to be fixed on the
vertical post with a spacer of
channel section 150x75x5
mm ,330 mm long complete
as per clause 811

Unit = Running metre


Taking output = 4.5 metre
length
a) Labour
Mate day 0.080 0.060

Blacksmith day 0.500 0.500

Mazdoor day 1.500 1.000

b) Machinery
Tractor-trolley hour 0.100 0.100

c) Material
Corrugated sheet , 3 mm kg 41.210 41.210
thick ,:"W:" beam section
railing , 4.5 m in length
Channel post 150x75x kg 88.560 88.560
5 mm , 1.8 m long , 3 Nos
@ 16.4 kg per metre
Spacer 150x75x5 mm kg 16.240 16.240
channel 0.33 m long , 3
Nos @ 16.4 kg per metre

Nuts and bolts kg 20.000 20.000


Add 25 percent of the cost of material for fabrication ,
nuts , bolts and washers etc ..}
Credit for salvage value kg 166.010 166.010
of dismantled material
d)Overhead charges
e)Contractor profit
Cost for 4.5 metre = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/4.5
10.16 B Type - B , " THRIE" : Metal
Beam Crash Barier

Replacement of "Thrie" metal beam crash barrier


comprising of 3 mm thick corrugated
sheet metal beam rail , 85 cm above road / ground
level , fixed on ISMC series channel verrtical post ,
150 x 75 x 5 mm spaced 2 m centre to centre,2 m
high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip
process ,all fittings to conform to IS: 1367 and IS :
1364 , metal beam rail to be fixed on the vertical
post with a space of channel section 150x75x5
mm, 546 mm long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.080 0.080

Blacksmith day 0.500 0.500

Mazdoor day 1.500 1.500

b) Machinery
Tractor-trolley hour 0.100 0.100

c) Material
Corrugated sheet , 3 mm kg 72.940 72.940
thick , "Thrie" beam section
railing , 4.5 m in length
Channel post 150x75x kg 98.400 98.400
5 mm , 2 m long , 3 Nos
@ 16.4 kg per metre
Spacer 150x75x5 mm kg 26.860 26.860
channel 0.546 m long , 3
Nos
Nuts and bolts
kg 30.000 30.000
Add 15 percent of the cost of material for fabrication ,
nuts , bolts and washers etc ..}
Credit for salvage value kg 228.200 228.200
of dismantled material
d)Overhead charges
e)Contractor's profit
Cost for 4.5 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/4.5
10.17 Network Survey Vehicle (NSV) attached with SUV

Data collection of longitudinal profiling


( International Roughness Index),Transverse
profiling (Rut Depth) , Pavement Texture in terms
of Mean Profile Depth , Road Geometry Data
(cross slope , gradient , curvature ), GPS
coordinates ( X , Y , Z ) viz. longitude , latitude &
altitude , video imaging for Roadside furniture/
Road Assets and Video imaging for Pavement
Surface Distresses and reports.

Unit = Lane Kilometer


Taking output = 200 Lane Km.
a) Labour
Mate day 0.360 0.360

Mazdoor (skilled) day 9.000 9.000

b) Machinery
Network Survey Vehicle (NSV) hour 8.000 8.000

Network Survey Vehicle (NSV) Mobilization & hour 15.000 15.000

demobilization

Add 1 percent of cost of a+b for Miscellaneous


work
c)Overhead charges
d)Contractor's profit
Cost for 200 Km. = a+b+c+d
Rate per Km. = (a+b+c+d)/200

Note : (I) Average Distance has been considered 300 km


for mobilization at working site and same for
demobilization
(ii) Speed of vehicle 40 km / hr. has been
considered .
(iii) The survey speed shall be within 30 to 80 kmph
.
10.18 Falling weight deflectometer (FWD)
Unit = Lane Kilometer
Taking output = 120 Lane Km.
a) Labour
Mate day 0.120 0.120

Mazdoor (skilled) day 1.000 1.000

Mazdoor day 2.000 2.000

b) Machinery
Falling weight deflectometer (FWD) hour 8.000 8.000

Equipment hour 15.000 15.000

Falling weight deflectometer (FWD)


Equipment Mobilization & demobilization

Add 1 percent of cost of a+b for Miscellaneous


work
c)Overhead charges
d)Contractor's profit
Cost for 120 Km. = a+b+c+d
Rate per Km. = (a+b+c+d)120
Note : (I) Average Distance has been considered 300 km
for mobilization at working site and same for
demobilization
(ii) Speed of vehicle 40 km / hr. has been consider.

10.19 Road Retro reflectometer attached with SUV


Unit = Km.
Taking output = 50 Km.
a) Labour
Mate day 1.200 1.200

Mazdoor (skilled) day 20.000 20.000

Mazdoor day 10.000 10.000

b) Machinery
Road Retro reflectometer attached with SUV hour 80.000 80.000

Road Retro reflectometer attached with SUV hour 15.000 15.000

Mobilization & demobilization

Add 1 percent of cost of a+b as Miscellaneous


work
c)Overhead charges
d)Contractor's profit
Cost for 50 Km. = a+b+c+d
Rate per Km. = (a+b+c+d)/50
Note : (I) Average Distance has been considered 300 km
for mobilization at working site and same for
demobilization
(ii) Speed of vehicle 40 km / hr. has been
considered .
(iii) The km is only for one side if road is more than
2 lane
10.20 Automatic Vehicle Counter Classifier (ATCC)
Unit = Per Location
Taking output = 1 Location
a) Labour
Mate day 1.696 1.696

Mazdoor (skilled) day 0.400 0.400

Mazdoor day 42.000 42.000

b) Machinery
Automatic Vehicle Counter Classifier (ATCC) hour 168.000 168.000

Equipment etc..
Sport utility vehicle (SUV) including hour 72.000 72.000

Mobilization& demobilization
Data processing and Report charges Lumpsum 1.000 1.000

Add 1 percent of cost of a+b as Miscellaneous


work
c)Overhead charges
d)Contractor's profit
Cost for 1 location . = a+b+c+d
Rate per Location = (a+b+c+d)/1
Note : (I) Average interval of location has been
considered 50 km.
(ii) The duration of traffic counting 24 hours for 7
days has been considered for one location
R - 10
OF ROADS
y as per project category Rate (`) Amount Input ref.
Small Large Medium Small

0.080
2.000

0.012

12×L2

0.012
0.500
0.180
4.500

0.017

24×L2

0.017
12.000

0.100
2.500

4.000
3.760
90.000
4.000

4.500
3.051
3.051

4.500

4.500

405×L

4.500
14.512

184.500
92.250
14.970
2.460
2.920
70.000
3.000

5.000
1.458
1.458

5.000

5.000

450x L

5.000
13.875

23.890
1.180
108.255
48.430
122.499
8.546

85.500
71.250
122.550
8.546

0.040
1.000

33.000
0.020
0.080
2.000

6.250

0.040
0.500
0.500

2.500
10.000

0.050

0.020
0.500

0.250
1.000

0.050

0.040
1.000
0.040
1.000

1.670

0.093
1.500
0.750
0.070

1.670
2.500

17.500
70.000
0.080
2.000

5.880

0.080
2.000

6.000
0.060
0.500
1.000

0.100

41.210

88.560

16.240

20.000
166.010

0.080
0.500
1.500

0.100

72.940

98.400

26.860
30.000

228.200

0.360
9.000

8.000
15.000
0.120
1.000
2.000

8.000
15.000

1.200
20.000
10.000

80.000
15.000
1.696
0.400
42.000

168.000

72.000

1.000
CHAPTER - 11
HORTICULTURE
Ref. to
Sr. No. MoRTH Description Unit Quantity as per project category
Spec.
11.01 307 Spreading of Sludge Farm Yard Manure or/and good Earth Large Medium

Spreading of sludge farm yard manure or/and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 0.040
Mazdoor day 1.000 1.000
b) Overhead charges
c) Contractor's profit
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15

11.02 307 Grassing with ' Doobs' Grass


Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.070 0.070
Mazdoor for grassing day 0.750 0.750
Mazdoor for maintenance for 30 days day 1.000 1.000
b) Machinery
Water tanker 6 KL capacity hour 0.500 0.500
c) Material
Doob grass kg 100.000 100.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100

11.02 (ii) In rows 7.5 cm apart in either direction


a) Labour
Mate day 0.090 0.090
Mazdoor for grassing. day 1.250 1.250
for maintenance for 30 days day 1.000 1.000
b) Machinery
Water tanker 6 KL capacity hour 0.750 0.750
c) Material
Doob grass kg 200.000 200.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.03 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.060 0.060
Mazdoor for preparation of ground day 0.500 0.500
Mali for fetching doobs grass roots and grassing at 15 day 1.000 1.000
cm apart
b) Machinery
Water tanker 6 KL capacity hour 0.500 0.500
Tractor with tipper hour 0.010 0.010
c) Material
Supply of farm yard manure at site of work cum 0.180 0.180
Fine grass kg 100.000 100.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

11.04 307 Maintenance of Lawns or Turfing of Slopes


Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400
Mali day 10.000 10.000
b) Machinery
Water tanker 6 KL capacity hour 15.000 15.000
c) Material
Cost of water KL 90.000 90.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

11.05 307 Turfing Lawns with Fine Grassing including Ploughing,


Dressing
Turfing lawns with fine grassing including ploughing, dressing
including breaking of clods, removal of rubbish, dressing and
supplying doobs grass roots at 10 cm apart, including
supplying and spreading of farm yard manure at rate of 0.6
cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.100 0.100
Mazdoor for preparation of ground day 1.000 1.000
Mali for fetching doobs grass roots and grassing at day 1.500 1.500
15 cm apart
b) Machinery
Water tanker 6 KL capacity hour 0.500 0.500
Tractor with tiller hour 0.010 0.010
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 0.600
per 100 sqm
Fine grass kg 100.000 100.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

11.06 307 Maintenance of Lawns with Fine Grassing for the First Year

Maintenance of lawns with fine grassing for the first year


including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400
Mali day 10.000 10.000
b) Machinery
Water tanker 6 KL capacity hour 20.000 20.000
c) Material
Cost of water KL 60.000 60.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

11.07 307 Planting and Maintaining of Permanent Hedges


(a) Planting permanent hedges including digging of trenches

Planting permanent hedges including digging of trenches, 60


cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100 metre
a) Labour
Mate day 0.560 0.560
Mazdoor for digging of trench 60 cm wide and 45 cm day 10.000 10.000
deep
Mazdoor for refilling the excavated earth mixed with day 4.000 4.000
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position
b) Machinery
Water tanker 6 KL capacity hour 0.500 0.500
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 2x340
Supply of farm yard manure at site of work cum 4.670 4.670
Pesticide kg 0.250 0.250
Cost of water KL 3.000 3.000
d) Overhead charges
e) Contractor's profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100

(b) Maintenance of hedge for one year


Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 1.200 1.200
Mazdoor day 30.000 30.000
b) Machinery
Water tanker 6 KL capacity hour 5.000 5.000
c) Material
Manure sludge/Farm yard manure cum 2.000 2.000
Pesticide kg 0.500 0.500
Cost of water KL 30.000 30.000
Cost of hedge plants @ 10 percent casualty each 68.000 68.000
d) Overhead charges
e) Contractor's profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100

11.08 307 Planting and Maintaining of Flowering Plants and Shrubs

(a) Planting flowering plants and shrubs in central verge

200 plants and 800 shrubs in two rows in one km length of


road where width of verge is 3m and above.

Unit = Running metre


Taking output = 1000 metres
a) Labour
Mate day 0.480 0.480
Mazdoor day 12.000 12.000
b) Machinery
Water tanker 6 KL capacity hour 6.000 6.000
c) Material
Plants each 200.000 200.000
Shrubs each 800.000 800.000
Manure sludge/Farm yard manure cum 63.640 63.640
Pesticide kg 0.500 0.500
Cost of water KL 36.000 36.000
d) Overhead charges
e) Contractor's profit
Rate per Km = (a+b+c+d+e)

11.08 (b) Maintenance of flowering plants and shrubs in central verge


for one year
Unit = km
Taking output = one km
a) Labour
Mate day 14.600 14.600
Mazdoor day 365.000 365.000
b) Machinery
Water tanker 6 KL capacity hour 90.000 90.000
c) Material
Manure Sludge / farm yard manure at site cum 10.000 10.000
Cost of water KL 180.000 180.000
Replacement of casualties @ 10 percent
Plants each 20.000 20.000
Shrubs each 80.000 80.000
Pesticides kg 1.500 1.500
d) Overhead charges
e) Contractor's profit
Rate per Km for one year = (a+b+c+d+e)

11.09 307 Planting of Trees and their Maintenance for one Year

Planting of trees by the road side (Avenue trees) in 0.60 m


dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 0.680 0.680
Mazdoor for planting day 2.000 2.000
Mazdoor for maintenance for one year day 15.000 15.000
b) Machinery
Water tanker 6 KL capacity hour 2.000 2.000
c) Material
Sapling 2 m high 25 mm dia each 10.000 10.000
Farm yard manure cum 0.940 0.940
Pesticide kg 0.500 0.500
Cost of water KL 12.000 12.000
d) Overhead charges
e) Contractor's profit
Cost for 10 trees = a+b+c+d+e
Rate per trees = (a+b+c+d+e)/10

11.10 308 Renovation Lawns including, Weeding, Forking the Ground,


Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground, top
dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120
Mazdoor day 3.000 3.000
b) Machinery
Water tanker 6 KL capacity hour 0.500 0.500
c) Material
Cost of water KL 3.000 3.000
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e) / 100

11.11 308.2 Supply at Site Well Decayed Farm Yard Manure


Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 1.000
screened, loading, carriage, unloading and stacking at
site
b) Overhead charges
c) Contractor's profit
Rate per cum = (a+b+c)

11.12 308.2 Supply at Site of Work/ Store-Deoiled Neem Cake


Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000 1.000
store/site
b) Overhead charges
c) Contractor's profit
Rate per quintal = a+b+c
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading, unloading cum 1.000 1.000
and stacking at site
b) Overhead charges
c) Contractor's profit
Rate per cum = a+b+c
11.14 308 Half Brick Circular Tree Guard, in 2nd Class Brick, internal
&1300 diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020
Mason day 0.250 0.250
Mazdoor day 0.250 0.250
b) Material
Brick 2nd class including carriage each 230.000 230.000
Cement mortar 1:6 (Rate taken from sub- analysis cum 0.025 0.025
21.01 D )
b) Overhead charges
c) Contractor's profit
Rate per tree Guard = a+b+c+d

11.15 308 Edging with 2nd Class Bricks, Laid Dry Lengthwise
&1300
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.004 0.004
Mason day 0.050 0.050
Mazdoor day 0.050 0.050
b) Material
Brick 2nd class including carriage each 50.000 50.000
c) Overhead charges
d) Contractor's profit
Cost for 10 metre = a+b+c+d
Rate per metre = (a+b+c+d)/10

11.16 Sugges Making Tree Guard 53 cm dia and 1.3 m High as per Design
tive from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.009 0.009
Blacksmith day 0.150 0.150
Mazdoor day 0.070 0.070
b) Material
Empty bitumen drum each 1.000 1.000
MS sheet 50 x 0.5 mm kg 0.650 0.650
Rivets 6 mm dia and 10 mm in length each 22.000 22.000
c) Overhead charges
d) Contractor's profit
Rate for each tree guard = a+b+c+d

11.17 Suggestive Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects

Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.016 0.016
Blacksmith day 0.200 0.200
Mazdoor 0.200 0.200
b) Material
Empty bitumen drum each 1.500 1.500
MS sheet50 x 0.5 mm kg 0.650 0.650
Rivets 6 mm dia and 10 mm in length each 50.000 50.000
MSplate30 x 3 mm kg 1.300 1.300
c) Overhead charges
d) Contractor's profit
Rate for each tree guard = a+b+c+d

11.18 Suggestive Wrought Iron and Mild Steel Welded Work

Wrought iron and mild steel welded work (using angles,


square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.180 0.180
Blacksmith/ welder for cutting to design and shape day 2.000 2.000
and jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 2.500
b) Material
Angle, tees, channels etc quintal 1.050 1.050
Deduct the cost of scrap quintal 0.050 0.050
Add 5 per cent of cost of material for welding rods and other
welding accessories
c) Overhead charges
d) Contractor's profit
Rate per quintal = a+b+c+d

11.19 Suggestive Tree Guard with MS Iron

Providing and fixing MS iron tree guard 60 cm dia and 2


metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020
Blacksmith day 0.250 0.250
Mazdoor day 0.250 0.250
b) Material
MS iron 25 x 6 mm kg 19.200 19.200
MS iron 25 x 3 mm kg 9.600 9.600
Add 5 percent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 0.040
d) Painting
Painting two coats including priming Rate for sqm 1.770 1.770
concrete may be adopted vide item no. 8.09
e) Overhead charges
f) Contractor's profit
Rate per tree guard =a+b+c+d+e+f

1 The items of excavation and concreting to be measured


and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 Suggestive Tree Guard with MS Angle Iron and Steel Wire

Providing and fixing tree guard 0.60 metre square, 2.00


metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS
iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.030 0.030
Blacksmith day 0.250 0.250
Welder day 0.250 0.250
Mazdoor day 0.250 0.250
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 13.500
MS iron 25 x 3 mm kg 18.000 18.000
Steel wire 3 mm dia kg 6.000 6.000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 0.040
d) Painting
Painting two coats including priming Rate for sqm 1.500 1.500
concrete may be adopted vide item no. 8.09
e) Overhead charges
f) Contractor's profit
Rate per tree guard = a+b+c+d+e+f

11.21 Compensatory Afforestation


Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 1.000 1.000
Mazdoor day 25.000 25.000
ii) For Maintenance for one year
Mate day 5.000 5.000
Mazdoor day 50.000 50.000
b) Machinery
Dozer 90 HP @ 1000 sqm/hour hour 10.000 10.000
Water tanker 6 KL capacity (for planting) hour 3.000 3.000
Water tanker 6 KL capacity (for maintenance) hour 25.000 25.000
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 290.000
Add 10 per cent of sapling each 29.000 29.000
Decayed farm yard/sludge manure (planting) cum 60.900 60.900
Decayed farm yard/sludge manure (maintenance) cum 4.000 4.000
Pesticides for planting kg 0.500 0.500
Pesticides for maintenance kg 1.500 1.500
Cost of water KL 18.000 18.000
d) Overhead charges
e) Contractor's profit
Rate per hectare = a+b+c+d+e
Note- Cost of fencing to be Provided as per size of plot and
approved design, measured and paid separately

11.22 Rain Water Harvesting Constructing rain water harvesting


recharge trench cum recharge shaft/well including grating
passage joining storm water drain and trench having brick
walls, RCC cover slab and filled with layers of filter media
(size 75 mm to 100 mm), grating having brick walls and CC
1:2:4 base and PVC pipe shaft packed with gravel, provided
with wire screen and bottom plug complete as per Drawing,
direction of the Engineer and MORT&H Specifications
sections 300, 1000, 1300, 1500, 1600 & 1700. (Dimension of
rain water harvesting pit 6.5 m depth, 2.10 meter inner dia,
wall width 375 mm and top slab thickness 150 mm)

Unit=Number
Taking output=10 Number
a) Material
Excavation 12.01 (Rate taken from item NO.-12.01 (I) B (iii)) Cum 230.213 230.213

Brick Wall (2.5 meter) (Rate taken from Item No.-12.05) cum 61.819 61.819
Brick wall (without Mortar-4 meter) (Rate taken from Item cum 98.910 98.910
NO.-12.05×83%)
RCC M20 for slab (Rate taken from Item No.-12.08 C, Case- cum 5.193 5.193
II)
Reinforcement (Rate taken from Item No.-12.42) MT 0.415 0.415
b) Filter Material (Size from 75-100 mm) cum 225.020 225.020
c) Add 1 percent of the cost of (a+b) for other miscellenus
(i.e. Pipe etc) activities required to complete the item in all
respect.
d) Overhead charges
e) Contractor's profit
Cost for 10 Nos.=a+b+c+d+e
Rate per No.=(a+b+c+d+e)/10
R - 11
ULTURE
y as per project category Rate (`) Amount Input ref.

Small Large Medium Small

0.040
1.000

0.070
0.750
1.000

0.500

100.000

0.090
1.250
1.000
0.750

200.000

0.060
0.500
1.000

0.500
0.010

0.180
100.000

0.400
10.000

15.000
90.000

0.100
1.000
1.500

0.500
0.010

0.600

100.000

0.400
10.000

20.000

60.000
0.560
10.000

4.000

0.500

2x340
4.670
0.250
3.000

1.200
30.000

5.000

2.000
0.500
30.000
68.000
0.480
12.000

6.000

200.000
800.000
63.640
0.500
36.000

14.600
365.000

90.000

10.000
180.000

20.000
80.000
1.500
0.680
2.000
15.000

2.000

10.000
0.940
0.500
12.000

0.120
3.000

0.500

3.000
1.000

1.000

1.000
0.020
0.250
0.250

230.000
0.025

0.004
0.050
0.050

50.000

0.009
0.150
0.070

1.000
0.650
22.000

0.016
0.200
0.200

1.500
0.650
50.000
1.300

0.180
2.000

2.500

1.050
0.050
0.020
0.250
0.250

19.200
9.600

0.040

1.770

0.030
0.250
0.250
0.250

13.500
18.000
6.000

0.040

1.500

1.000
25.000

5.000
50.000

10.000
3.000
25.000

290.000
29.000
60.900
4.000
0.500
1.500
18.000
230.213

61.819
98.910

5.193

0.415
225.020
CHAPTER-12
FOUNDATION
Item No. Unit Rate as per project category
Description
Large Medium Small
12.01 Excavation for strucutres

Earth work in excavation of foundation of structures as


per drawing and technical specification, including
setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.
I Ordinary soil
A Manual Means
(i) Depth upto 3 m cum 140.60 140.60 140.60
(ii) Depth 3 m to 6 m cum 180.80 180.80 180.80
(iii) Depth above 6 m cum 241.10 241.10 241.10
B Mechanical Means
(i) Depth upto 3 m cum 114.80 118.00 145.00
(ii) Depth 3 m to 6 m cum 126.90 130.50 160.30
(iii) Depth above 6 m cum 142.00 145.90 179.30
II Ordinary Rock ( not requiring blasting)
A Manual Means
(i) Depth upto 3m cum 200.90 200.90 200.90
B Mechanical Means cum 729.70 764.60 777.40
III Hard Rock (requiring blasting)

Carrying out excavation in hard rock to achieve a specified


slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a dozer, loading in
tipper by a front end loader and disposing of the material with
all lifts and lead upto 1000m, all as specified in clause No.
303
A Manual means cum #VALUE! #VALUE! #VALUE!
IV Hard Rock ( blasting prohibited )
A Mechanical Means cum 986.30 1006.30 1036.70
V Marshy Soil
A Manual means cum 617.50 617.50 617.50
B Mechanical Means cum 306.90 312.60 380.50
VI Back Filling in Marshy Foundation Pits cum 470.20 470.20 470.20
12.02 Filling Annular Space around footing in rock cum 2960.40 2963.80 2974.10
Sand Filling in foundation trenches as per drawing & cum
12.03 technical specification 316.40 319.30 327.90
12.04 PCC 1:3:6 in Foundation

Plain cement concrete 1:3:6 nominal mix in foundation with


cum
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days. 2960.40 2963.80 2974.10

Brick Masonry Work in Cement Mortar 1:3 in Foundation cum


complete excluding Pointing and Plastering, as per Drawing
12.05 and Technical Specifications. 6068.90 6076.00 6099.40
12.06 (A) Cement Mortar 1:3 (1 cement : 3 sand) cum 2971.50 2971.50 2971.50
(B) Cement Mortar1:2 (1cement :2 sand) cum 3748.70 3748.70 3748.70
(C ) Cement Mortar1:4 (1cement :4 sand) cum 2456.60 2456.60 2456.60
(D) Cement Mortar1:6 (1cement :6 sand) cum 1928.45 1928.45 1928.45

Stone masonry work in cement mortar 1:3 in foundation


12.07 complete as per drawing and technical specifications.

cum
(A) Square Rubble Coursed Rubble masonry (first sort) 3225.30 3225.30 3225.30
(B) Random Rubble masonry (coursed/uncoursed) cum 3120.60 3120.60 3120.60

Plain/Reinfoced Cement concrete in open foundation


12.08 complete as per drwaing and technical specifications.
A PCC Grade M15

Case I PCC Grade M15 using batching plant & Concrete pump cum 3287.90 3296.50 3322.80

Case II PCC Grade M15 using batching plant & manual placing cum 3500.00 3508.50 3534.70
B PCC Grade M20
PCC Grade M20 using batching plant, transit mixture &
Case I Concrete pump cum 3784.00 3792.60 3818.90
PCC Grade M20 using batching plant, transit mixer & manual
Case II placing cum 3996.10 4004.60 4030.80
C RCC Grade M20
RCC Grade M20 using batching plant, transit mixture &
Case I Concrete pump cum 4169.90 4178.50 4204.70
RCC Grade M20 using batching plant, transit mixer & manual
Case II placing cum 4395.80 4404.40 4430.60
D PCC Grade M25
PCC Grade M25 using batching plant, transit mixture &
Case I Concrete pump cum 4156.00 4164.50 4190.80
PCC Grade M25 using batching plant, transit mixer & manual
Case II placing cum 4368.00 4376.60 4402.80
E RCC Grade M25
RCC Grade M25 using batching plant,transit mixer &
Case I Concrete pump cum 4439.40 4448.00 4474.20
RCC Grade M25 using batching plant, transit mixer & manual
Case II placing cum 4665.30 4673.90 4700.10
F PCC Grade M30
PCC Grade M30 using batching plant,transit mixer &
Case I Concrete pump cum 4192.20 4200.80 4227.00
PCC Grade M30 using batching plant, transit mixer & manual
Case II placing cum 4404.20 4412.80 4439.00
G RCC Grade M30
RCC Grade M30 using batching plant,transit mixer &
Case I Concrete pump cum 4553.50 4562.00 4588.30
RCC Grade M30 using batching plant, transit mixer & manual
Case II placing cum 4779.40 4788.00 4814.20
H RCC Grade M35
RCC Grade M35 using batching plant,transit mixer &
Case I Concrete pump cum 4758.60 4767.10 4793.40
RCC Grade M35 using batching plant, transit mixer & manual
Case II placing cum 4984.50 4993.10 5019.30
I RCC Grade M40
RCC Grade M40 using batching plant,transit mixer &
Case I Concrete pump cum 5195.70 5204.20 5230.50
RCC Grade M40 using batching plant, transit mixer & manual
Case II placing cum 5421.60 5430.20 5456.40
J RCC Grade M45
RCC Grade M45 using batching plant,transit mixer &
Case I Concrete pump cum 5384.00 5392.60 5418.80
RCC Grade M45 using batching plant, transit mixer & manual
Case II placing cum 5610.00 5618.50 5644.70
12.09 WELL FOUNDATION

Providing and constructing temporary island 24m diameter


for construction of Well foundation for 8m dia. Well.

Assuming depth of water 1.0 m and height of island to be


1.25m including Royalty for earth @ ₹ 18661.1 for each
A island. no. 83179.40 83179.40 83179.40

Assuming depth of water 4.0 m and height of island to be


4.5m including Royalty for earth @ ₹ 44748.0 for each
B island no. 447608.00 447608.00 447608.00

Providing and constructiing one span service road to reach


C island location from one pter location to another pier loaction

Assuming span length 30m, width of service road 10m and


depth of water 1m including Royalty for earth @ ₹495.00
per m length of span metre 4232.90 4232.90 4232.90

Providing and Laying Cutting Edge of Mild Steel weighing 40


kg permetre for Well Foundation complete as per Drawing
12.10 and Technical Specification. MT 95852.20 95853.20 95855.20

Plain/Reinforced Cement Concrete, in Well Foundation


12.11 complete as per Drawing and Technical Specification.
A Well curb
(i) RCC M20 Grade

Case I RCC Grade M20 using batching plant &concrete pump cum 4683.00 4683.00 4683.00

Case II RCC Grade M20 using batching plant & manual placing cum 4901.90 4901.90 4901.90
(ii) RCC M25 Grade

Case I RCC Grade M25 using batching plant &concrete pump cum 4994.00 4994.00 4994.00

Case II RCC Grade M25 using batching plant & manual placing cum 5212.90 5212.90 5212.90
(iii) RCC M30 Grade

Case I RCC Grade M30 using batching plant &concrete pump cum 5125.60 5125.60 5125.60

Case II RCC Grade M30 using batching plant & manual placing cum 5344.50 5344.50 5344.50
(iv) RCC M35 Grade
Case I RCC Grade M35 using batching plant &concrete pump cum 5362.20 5362.20 5362.20

Case II RCC Grade M35 using batching plant & manual placing cum 5581.10 5581.10 5581.10
(v) RCC M40 Grade

Case I RCC Grade M40 using batching plant &concrete pump cum 5866.60 5866.60 5866.60

Case II RCC Grade M40 using batching plant & manual placing cum 6085.50 6085.50 6085.50
B Well steining
(i) PCC M15Grade

Case I PCC Grade M15 using batching plant & Concrete pump cum 3359.90 3359.90 3359.90

Case II PCC Grade M15 using batching plant & manual placing cum 3575.30 3575.30 3575.30
(ii) PCC M20 Grade

Case I PCC Grade M20 using batching plant & Concrete pump cum 3884.70 3884.70 3884.70

Case II PCC Grade M20 using batching plant & manual placing cum 4100.00 4100.00 4100.00
(iii) RCC M20 Grade

Case I RCC Grade M20 using batching plant &concrete pump cum 4292.80 4292.80 4292.80

Case II RCC Grade M20 using batching plant & manual placing cum 4493.40 4493.40 4493.40
(iV) PCC M25 Grade

Case I PCC Grade M25 using batching plant & Concrete pump cum 4278.00 4278.00 4278.00

Case II PCC Grade M25 using batching plant & manual placing cum 4493.40 4493.40 4493.40
(V) RCC M25 Grade

Case I RCC Grade M25 using batching plant &concrete pump cum 4577.80 4577.80 4577.80

Case II RCC Grade M25 using batching plant & manual placing cum 4778.50 4778.50 4778.50
(vi) PCC M30 Grade

Case I PCC Grade M30 using batching plant & Concrete pump cum 4316.40 4316.40 4316.40

Case II PCC Grade M30 using batching plant & manual placing cum 4531.80 4531.80 4531.80
(vii) RCC M30 Grade

Case I RCC Grade M30 using batching plant &concrete pump cum 4698.50 4698.50 4698.50

Case II RCC Grade M30 using batching plant & manual placing cum 4899.10 4899.10 4899.10
(viii) RCC M35 Grade

Case I RCC Grade M35 using batching plant &concrete pump cum 4915.40 4915.40 4915.40

Case II RCC Grade M35 using batching plant & manual placing cum 5116.00 5116.00 5116.00
(ix) RCC M40 Grade
Case I RCC Grade M40 using batching plant &concrete pump cum 5377.70 5377.70 5377.70

Case II RCC Grade M40 using batching plant & manual placing cum 5578.40 5578.40 5578.40
C Bottom Plug
(i) PCC Grade M20

Case I PCC Grade M20 using batching plant & concrete pump cum 3721.70 3721.70 3721.70

Case II PCC Grade M20 using batching plant & manual placing cum 3966.70 3966.70 3966.70
(II) PCC Grade M25

Case I PCC Grade M25 using batching plant & concrete pump cum 4097.20 4097.20 4097.20

Case II PCC Grade M25 using batching plant & manual placing cum 4342.20 4342.20 4342.20
(iII) PCC Grade M30

Case I PCC Grade M30 using batching plant & concrete pump cum 4133.80 4133.80 4133.80

Case II PCC Grade M30 using batching plant & manual placing cum 4378.80 4378.80 4378.80
(iV) PCC Grade M35

Case I PCC Grade M35 using batching plant & concrete pump cum 4576.00 4576.00 4576.00

Case II PCC Grade M35 using batching plant & manual placing cum 4820.90 4820.90 4820.90
D Intermediate plug
(i) Grade M20 PCC

Case I PCC Grade M20 using batching plant & Concrete pump cum 3556.20 3556.20 3556.20

Case II PCC Grade M20 using batching plant & Manual placing cum 3790.50 3790.50 3790.50
(ii) Grade M25 PCC

Case I PCC Grade M25 using batching plant & Concrete pump cum 3913.80 3913.80 3913.80

Case II PCC Grade M25 using batching plant & Manual placing cum 4148.10 4148.10 4148.10
(iii) Grade M30 PCC

Case I PCC Grade M30 using batching plant & Concrete pump cum 3948.60 3948.60 3948.60

Case II PCC Grade M30 using batching plant & Manual placing cum 4183.00 4183.00 4183.00
E Top Plug
(i) Grade M15 PCC

Case I PCC Grade M15 using batching plant & concrete pump cum 3161.50 3169.70 3195.00

Case II PCC Grade M15 using batching plant & manual placing cum 3365.40 3373.60 3398.80
(ii) Grade M20 PCC

Case I PCC Grade M20 using batching plant & concrete pump cum 3638.50 3646.80 3672.00

Case II PCC Grade M20 using batching plant & manual placing cum 3842.40 3850.60 3875.80
(iii) Grade M25 PCC

Case I PCC Grade M25 using batching plant & concrete pump cum 3996.10 4004.40 4029.60

Case II PCC Grade M25 using batching plant & manual placing cum 4200.00 4208.20 4233.40
(iv) Grade M30 PCC

Case I PCC Grade M30 using batching plant & concrete pump cum 4031.00 4039.20 4064.50

Case II PCC Grade M30 using batching plant & manual placing cum 4234.80 4243.10 4268.30
F Well Cap
(i) RCC Grade M20
RCC Grade M20 using batching plant, transit mixer &
Case I concrete pump cum 4169.90 4178.50 4204.70
RCC Grade M20 using batching plant, transit mixer & manual
Case II placing cum 4368.00 4376.60 4402.80
(ii) RCC Grade M25
RCC Grade M25 using batching plant, transit mixer &
Case I concrete pump cum 4439.40 4448.00 4474.20
RCC Grade M25 using batching plant, transit mixer & manual
Case II placing cum 4637.50 4646.00 4672.20
(iii) RCC Grade M30
RCC Grade M30 using batching plant, transit mixer &
Case I concrete pump cum 4553.50 4562.00 4588.30
RCC Grade M30 using batching plant, transit mixer & manual
Case II placing cum 4751.50 4760.10 4786.30
(iv) RCC Grade M35
RCC Grade M35 using batching plant, transit mixer &
Case I concrete pump cum 4758.60 4767.10 4793.40
RCC Grade M35 using batching plant, transit mixer & manual
Case II placing cum 4956.60 4965.20 4991.40
(v) RCC Grade M40
RCC Grade M40 using batching plant, transit mixer &
Case I concrete pump cum 5195.70 5204.20 5230.50
RCC Grade M40 using batching plant, transit mixer & manual
Case II placing cum 5393.70 5402.30 5428.50
(vi) RCC Grade M45
RCC Grade M45 using batching plant, transit mixer &
Case I concrete pump cum 5384.00 5392.60 5418.84
RCC Grade M45 using batching plant, transit mixer & manual
Case II placing cum 5582.10 5590.70 5616.90

Sinking of 6 m external diameter well (other than pneumatic


method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
12.12 of sinking is reckoned from bed level.
(A) Sandy Soil
(i) Depth below bed level upto 3.0m metre 3869.40 3869.40 3869.40
(iI) Beyond 3m upto 10m depth metre 5469.20 5469.20 5469.20
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey soil (6m dia. Well)
(i) Depth below bed level upto 3.0 M metre 5490.90 5490.90 5490.90
(ii) Beyond 3m upto 10m depth metre 12189.90 12189.90 12189.90
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.12 (A) or (B) irrespective of depth for
C sinking in soft Rock (6m dia well) metre 46532.10 46532.10 46532.10
Extra over item no. 12.12 (A) or (B) irrespective of depth for
sinking in Hard Rock (6m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.12 (A) or (B) irrespective of depth for
sinking in Rock bouldery strata (6m dia well)

E metre 70330.30 70330.30 70330.30

Sinking of 7 m external diameter well (other than pneumatic


method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
12.13 of sinking is reckoned from bed level.
A Sandy Soil
(i) Depth below bed level upto 3.0m metre 5785.30 5785.30 5785.30
(ii) Beyond 3m upto 10m depth metre 7701.20 7701.20 7701.20
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (7 m dia. Well)
(I) Depth below bed level upto 3.0 M metre 7701.20 7701.20 7701.20
(ii) Beyond 3m upto 10m depth metre 12231.40 12231.40 12231.40
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.13 (A) or (B) irrespective of depth for
sinking in soft Rock (7m dia well)
C metre 60847.80 60847.80 60847.80
Extra over item no. 12.13 (A) or (B) irrespective of depth for
sinking in Hard Rock (7m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.13 (A) or (B) irrespective of depth for
sinking in Rock bouldery strata (7m dia well)

E metre 93573.20 93573.20 93573.20


Sinking of 8 m external diameter well (other than pneumatic
method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

12.14
A Sandy Soil
(i) Depth below bed level upto 3.0 M metre 7068.90 7068.90 7068.90
(ii) Beyond 3m upto 10m depth metre 8668.60 8668.60 8668.60
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (8 m dia. Well)
(i) Depth from bed level upto 3.0 M metre 9427.10 9427.10 9427.10
(ii) Beyond 3m upto 10m depth metre 12843.60 12843.60 12843.60
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.14 (A) or (B) irrespective of depth for
sinking in soft Rock (8m dia well)
C metre 77222.70 77222.70 77222.70
Extra over item no. 12.14 (A) or (B) irrespective of depth for
sinking in Hard Rock (8m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.14 (A) & (B) irrespective of depth for
sinking in Rock bouldery strata (8m dia well)

E metre 120249.60 120249.60 120249.60


Sinking of 9 m external diameter well (other than pneumatic
method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

12.15
A Sandy Soil
(i) Depth below bed level upto 3.0 M metre 7173.30 7173.30 7173.30
(ii) Beyond 3m upto 10m depth metre 9509.70 9509.70 9509.70
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (9 m dia. Well)
(i) Depth from bed level upto 3.0 M metre 9973.90 9973.90 9973.90
(ii) Beyond 3m upto 10m depth metre 13835.80 13835.80 13835.80
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.15 A) or (B) irrespective of depth for
sinking in soft Rock (9m dia well)
C metre 95658.70 95658.70 95658.70
Extra over item no. 12.15 (A) or (B) irrespective of depth for
sinking in Hard Rock (9m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.15 (A) & (B) irrespective of depth for
sinking in Rock bouldery strata (9m dia well)

E metre 150359.80 150359.80 150359.80

Sinking of 10 m external diameter well (other than pneumatic


method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
12.16 of sinking is reckoned from bed level.
A Sandy Soil
(i) Depth below bed level upto 3.0m metre 8542.40 8542.40 8542.40
(ii) Beyond 3m upto 10m depth metre 10056.50 10056.50 10056.50
(iii) Beyond 10m upto 20m
Rate may be taken from analysis
(iv) Beyond 20m upto 30m
Rate may be taken from analysis
(v) Beyond 30m upto 40m
Rate may be taken from analysis
B Clayey Soil (10 m dia. Well)
(I) Depth below bed level upto 3.0 M metre 11147.10 11147.10 11147.10
(ii) Beyond 3m upto 10m depth metre 13815.60 13815.60 13815.60
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.16 (A) or (B) irrespective of depth for
sinking in soft Rock (10m dia well)
C metre 116154.80 116154.80 116154.80
Extra over item no. 12.16 (A) or (B) irrespective of depth for
sinking in Hard Rock (10m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.16 (A) or (B) irrespective of depth for
sinking in Rock bouldery strata (10m dia well)

E metre 183903.20 183903.20 183903.20


Sinking of 11 m external diameter well (other than pneumatic
method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

12.17
A Sandy Soil
(i) Depth from bed level upto 3.0 M metre 19447.10 19447.10 19447.10
(ii) Beyond 3m upto 10m depth metre 15895.40 15895.40 15895.40
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (11 m dia. Well)
(i) Depth from bed level upto 3.0 M metre 18511.90 18511.90 18511.90
(ii) Beyond 3m upto 10m depth metre 28646.90 28646.90 28646.90
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.17 (A) or (B) irrespective of depth for
sinking in soft Rock 11m dia well)
C metre 138710.40 138710.40 138710.40
Extra over item no. 12.17 (A) or (B) irrespective of depth for
sinking in Hard Rock (11m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.17 (A) & (B) irrespective of depth for
sinking in Rock bouldery strata (11m dia well)

E metre 220880.60 220880.60 220880.60


Sinking of 12m external diameter well (other than pneumatic
method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

12.18
A Sandy Soil
(i) Depth below bed level upto 3.0 M metre 40568.40 40568.40 40568.40
(ii) Beyond 3m upto 10m depth metre 45865.00 45865.00 45865.00
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (12 m dia. Well)
(i) Depth from bed level upto 3.0 M metre 45192.20 45192.20 45192.20
(ii) Beyond 3m upto 10m depth metre 70607.20 70607.20 70607.20
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.18 ( A) or (B) irrespective of depth for
sinking in soft Rock (12m dia well)
C metre 163326.80 163326.80 163326.80
Extra over item no. 12.18 (A) or (B) irrespective of depth for
sinking in Hard Rock (12m dia well)
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.18 (A) & (B) irrespective of depth for
sinking in Rock bouldery strata (12m dia well)

E metre 261291.70 261291.70 261291.70


Sinking of Twin D Type well (other than pneumatic method of
sinking) through all types of strata namely sandy soil, clayey
soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is
reckoned from bed level.

12.19
A Sandy Soil
(i) Depth from bed level upto 3.0 M metre 9152.90 9152.90 9152.90
(ii) Beyond 3m upto 10m depth metre 9864.10 9864.10 9864.10
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
B Clayey Soil (Twin D Type Well)
(i) Depth below bed level upto 3.0 M metre 10836.80 10836.80 10836.80
(ii) Beyond 3m upto 10m depth metre 15300.00 15300.00 15300.00
(iii) Beyond 10m upto 20m metre
Rate may be taken from analysis
(iv) Beyond 20m upto 30m metre
Rate may be taken from analysis
(v) Beyond 30m upto 40m metre
Rate may be taken from analysis
Extra over item no. 12.19 (A) or (B) irrespective of depth for
sinking in soft Rock
C metre 96520.40 96520.40 96520.40
Extra over item no. 12.19 (A) or (B) irrespective of depth for
sinking in Hard Rock
D metre #VALUE! #VALUE! #VALUE!
Extra over item no. 12.19 (A) & (B) irrespective of depth for
sinking in Rock bouldery strata
E metre 151795.90 151795.90 151795.90

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by competent and
trained personnel and comprising of compression and
decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of
fresh air to working chambers, check valves, exhaust valves,
shafts made from steel plates of riveted construction not less
than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing, arrangement for
compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations
and compliance with safety precautions as per IS:4138, all as
12.20 per clause1208.8 of MoRTH Specifications. cum 53223.20 53237.00 53279.00
Sand Filling in Wells complete as per Drawing and Technical
12.21 Specifications. cum 399.00 399.00 399.00
Providing Steel Liner 10 mm thick for Curbs and 6 mm thick
for Steining of Wells including Fabricating and Setting out as
12.22 per Detailed Drawing. MT 87859.80 87859.80 87859.80

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
12.23 and lead upto 1000 m. metre 15155.00 15165.80 15254.90

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
12.24 and lead upto 1000 m. metre 17138.50 17157.80 17316.00
Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.

12.25
Pile diameter-1200 mm metre 21206.40 21234.40 21462.20
12.26 Pile diameter-1500 mm metre 26952.70 26996.20 27352.30
Driven cast-in-place vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.27
Pile diameter-750mm metre 6385.30 6389.10 6400.70
Driven cast-in-place vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.28
Pile diameter-1000mm metre 9480.40 9487.10 9507.70
Driven cast-in-place vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.29
Pile diameter-1200mm metre 13977.00 13986.70 14016.40
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.30
Pile diameter-500mm metre 3943.30 3945.00 3950.30
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.31
Pile diameter-750mm metre 5763.80 5767.60 5779.30
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.32
Pile diameter-1000mm metre 8347.90 8354.70 8375.50
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.33
Size of pile-300mm×300mm metre 3372.70 3373.50 3375.90
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.34
Size of pile-500mm×500mm metre 4692.90 4695.00 4701.70
Driven precast vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification
12.35
Size of pile-750mm×750mm metre 7072.70 7077.50 7092.50
Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
12.36
Section of the pile-H Section steel columm 400×250 mm
(ISHB Series)
metre 7577.70 7577.70 7577.70
Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
12.37
Section of the pile-H Section steel columm 450×250 mm
(ISHB Series)
metre 8627.40 8627.40 8627.40
Pile Load Test on single Vertical Pile in accordance with MT
IS:2911 (Part-IV)
12.38 #VALUE! #VALUE! #VALUE!
Dismantling of Reinforced Concrete Pile head complete as
per Drqwing and Technical Specification

12.39 cum 1504.10 1534.20 1553.50


Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

12.40
RCC Grade M20
A

RCC Grade M20 using batching plant & Concrete pump

Case I cum 4036.40 4036.40 4036.40


RCC Grade M20 using batching plant & manual placing
Case II cum 4056.30 4056.30 4056.30
RCC Grade M25
B

RCC Grade M25 using batching plant & Concrete pump

Case I cum 4305.90 4305.90 4305.90


RCC Grade M25 using batching plant & manual placing
Case II cum 4325.80 4325.80 4325.80
RCC Grade M30
C

RCC Grade M30 using batching plant & Concrete pump

Case I cum 4419.90 4419.90 4419.90


RCC Grade M30 using batching plant & manual placing
Case II cum 4439.80 4439.80 4439.80
RCC Grade M35
D

RCC Grade M35 using batching plant & Concrete pump

Case I cum 4625.00 4625.00 4625.00


RCC Grade M35 using batching plant & manual placing
Case II cum 4644.90 4644.90 4644.90
RCC Grade M40
E
RCC Grade M40 using batching plant & Concrete pump

Case I cum 5062.10 5062.10 5062.10


RCC Grade M40 using batching plant & manual placing
Case II cum 5082.00 5082.00 5082.00
RCC Grade M45
F

RCC Grade M45 using batching plant & Concrete pump

Case I cum 5250.50 5250.50 5250.50


RCC Grade M45 using batching plant & manual placing
Case II cum 5270.40 5270.40 5270.40
12.41 Levelling Course for Pile cap
Providing and laying of PCC M15 levelling course 100 mm
thick below the pile cap.
PCC Grade M15 using batching plant & Concrete pump
Case I cum 3161.50 3169.70 3195.00
PCC Grade M15 using batching plant & manual placing
Case II cum 3365.40 3373.60 3398.80
Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing and
Technical Specifications.
12.42 MT 67558.30 67611.90 67726.00
Supplying, Fitting and Placing un-coated Mild steel
Reinforcement in Foundation complete as per Drawing and
Technical Specifications.
12.43 MT 72410.70 72464.30 72578.40
CHAPTER- 13
SUB-STRUCTURE
Item No. Unit Rate as per project category
Description
Large Medium Small

Brick masonry work in 1:3 in substructure complete excluding


13.01 pointing and plastering, as per drawing and Technical
Specifications cum 6031.40 6039.40 6063.60

13.02 Pointing with cement mortar (1:3) on brick work in


substrucutre as per technical specifications sqm 558.40 558.40 558.40

13.03 Plastering with cement mortar (1:3) on brick work in


substructure as per technical specifications sqm 103.20 103.40 104.10

13.04 Stone masonry work in cement mortar 1:3 for substructure


complete as per drawing and technical specifications
A Random Rubble Masonry (Coursed/uncoursed) cum 3244.20 3259.80 3305.40
B Coursed rubble masonry (first sort) cum 3447.00 3462.70 3508.20
C Ashlar masonry (first sort) cum 4501.00 4516.70 4562.20

13.05 Plain/Reinforced cement concrete in sub-strucutre complete


as per drawing and Technical specifications
A PCC Grade M15
(p) Height upto 5m

PCC Grade M15 using batching plant & concrete pump cum 3477.60 3486.70 3514.50
B PCC Grade M20
(p) Height upto 5m
PCC Grade M20 using batching plant, transit mixer &
concrete pump cum 4002.40 4011.40 4039.20

C PCC Grade M25 using batching plant, transit mixer &


concrete pump cum 4395.70 4404.80 4432.60
(q) Height 5m to 10m
PCC Grade M25 using batching plant, transit mixer &
concrete pump cum 4555.60 4565.00 4593.80
( r) Height above 10m
PCC Grade M25 using batching plant, transit mixer &
concrete pump cum 4755.40 4765.20 4795.20
D PCC Grade M30
(p) Height upto 5 m
PCC Grade M30 using batching plant, transit mixer &
concrete pump cum 4434.10 4443.10 4470.90
(q) Height 5m to 10m
PCC Grade M30 using batching plant, transit mixer &
concrete pump cum 4595.31 4604.70 4633.50
( r) Height above 10m
PCC Grade M30 using batching plant, transit mixer &
concrete pump cum 4796.90 4806.70 4836.70
E RCC Grade M20
(p) Height upto 5m
RCC Grade M20 using batching plant, transit mixer &
concrete pump cum 4112.50 4121.60 4149.40
(q) Height 5m to 10m
RCC Grade M20 using batching plant, transit mixer &
concrete pump cum 4262.10 4271.50 4300.20
( r) Height above 10m
RCC Grade M20 using batching plant, transit mixer &
concrete pump cum 4449.00 4458.80 4488.90
F RCC Grade M25
(p) Height upto 5m
RCC Grade M25 using batching plant, transit mixer &
concrete pump cum 4695.50 4704.60 4732.30
(q) Height 5 to 10m
RCC Grade M25 using batching plant, transit mixer &
concrete pump cum 4849.20 4858.50 4887.20
( r) Height above 10m
RCC Grade M25 using batching plant, transit mixer &
concrete pump cum 5079.70 5089.50 5119.50
G RCC Grade M30
(p) Height upto 5m
RCC Grade M30 using batching plant, transit mixer &
concrete pump cum 4816.20 4825.20 4853.00
(q) Height 5m to 10m
RCC Grade M30 using batching plant, transit mixer &
concrete pump cum 4951.90 4961.20 4989.80
( r) Height above 10m
RCC Grade M30 using batching plant, transit mixer &
concrete pump cum 5144.50 5154.20 5183.90
H RCC Grade M35
(p) Height upto 5 m
RCC Grade M35 using batching plant, transit mixer &
concrete pump cum 5033.10 5042.20 5069.90
(q) Height 5m to 10m
RCC Grade M35 using batching plant, transit mixer &
concrete pump cum 5142.90 5152.20 5180.50
( r) Height above 10m
RCC Grade M35 using batching plant, transit mixer &
concrete pump cum 5307.60 5317.20 5346.50
I RCC Grade M40
(p) Height upto 5m
RCC Grade M40 using batching plant, transit mixer &
concrete pump cum 5495.40 5504.50 5532.20
(q) Height 5m to 10m
RCC Grade M40 using batching plant, transit mixer &
concrete pump cum 5615.30 5624.60 5653.00
( r) Height above 10m
RCC Grade M40 using batching plant, transit mixer &
concrete pump cum 5795.20 5804.70 5834.00
J RCC Grade M 45
(p) Height upto 5m
RCC Grade M45 using batching plant, transit mixer &
concrete pump cum 5694.60 5703.70 5731.50
(q) Height 5m to 10m
RCC Grade M45 using batching plant, transit mixer &
concrete pump cum 5818.90 5828.10 5856.50
( r) Height above 10m
RCC Grade M45 using batching plant, transit mixer &
concrete pump cum 6005.20 6014.80 6044.10
K RCC Grade M50
(p) Height upto 5m
RCC Grade M50 using batching plant, transit mixer &
concrete pump cum 6671.50 6680.80 6709.30
(q) Height 5m to 10m
RCC Grade M50 using batching plant, transit mixer &
concrete pump cum 6636.10 6645.30 6673.70
(r ) Height above 10m
RCC Grade M50 using batching plant, transit mixer &
concrete pump cum 6848.60 6858.20 6887.50

Supplying, fitting and placing HYSD bar reinforcement in sub


13.06 structure complete as per drawing and technical
specifications MT 67795.60 67849.20 67963.30

Supplying, fitting and placing Mild steel reinforcement


13.07 complete in sub structure as per drawing and technical
specifications MT 72648.00 72701.60 72815.70

Providing weep holes in Brick masonry/ Plain/Reinforced


concrete abutment , wing wall/ returen wall with 100 mm dia
13.08 AC pipe, extending through the full width of the structure with
slope of 1V:20 H towards drawing face. Complete as per
drawing and technical specifications.
Nos. 123.70 123.70 123.70

Back filling behind abutment, wing wall, return wall complete


13.09
as per drawing and technical specifications

A Granular Material cum 662.40 662.40 662.40


B Sandy material cum 683.10 683.10 683.10
Providing and laying of filter media with granular
materials/stones crushed aggregates satisfying the
13.10 requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall
and provided over the entire surface behind abutment , wing
wall and return wall to the full height compacted to a firm
condition complete as per drwaing and technical
specification. cum 1138.00 1138.00 1138.00

Supplying and laying of drainage composite for use behind


walls , between two different fills, alongside drains of road,
below concrete lining of canals etc.. Geo composite for
planar drainage, realised by thermos bonding a draining core
13.11
in extruded monofilaments with two filtering nonwoven
geotextiles that may also be working as seperation or
protecting layers. The draining three dimensional core will
have a "W" configuration as longitudinal parallel channels.

sqm 675.60 675.60 675.60

Supplying and laying of drainage composite for use behind


walls between two different fills, along side drains of road,
below concrete lining of canals etc having thermos bonding
draining core- HDPE geonet comprises of two sets of parallel
overlaid ribs integrally connected to have a rhomboidal shape
with a polyehtylene film and a nonwoven geotextile having
mass per unit area 130g/m2 and tensile strength of 8KN/m
13.12
that will be working as separation or protecting layer,
geocomposite having in plane flow capacity of 0.7 l/(m.s) at
hydraulic gradient of 1.0 and 20 kpa pressure and tensile
strength of 13.5 KN/m, with mass per unit area of 830 gsm,
at easily accesible location including top and bottom, with all
leads and lifts, manpower and machinery, materials, labour
etc complete and as directed by Engineer in charge

sqm 802.80 802.80 802.80

Supplying fitting and fixing in positon true to line and level


13.13 cast steel rocker bearing conforming to IRC: 83 (pt.-1)
Section IX and clause 2003 of MoRT&H specifications
complete including all accessories as per drawing and
technical specification tonne 437.70 437.70 437.70
Supplying fitting and fixing in positon true to line and level
13.14 forged steel roller bearing conforming to IRC: 83 (pt.-1)
Section IX and clause 2003 of Mort&h specifications
complete including all accessories as per drawing and
technical specification tonne 245.10 245.10 245.10
Supplying fitting and fixing in positon true to line and level
sliding plate bearing with PTFE surface sliding of stainless
steel complete including all accessories as per drawing and
technical specification and BS:5400, section 9.1 & 9.2 (for
13.15 PTFE) and clause 2004 of Mort&H specifications

tonne 209.90 209.90 209.90

13.16 Supplying , fitting and fixing in position true to line and level
elastomeric bearing conforming to IRC:83 (Part-II) section IX
and clause 2005 of Mort&H specification complete including
all accessories as per drwaing and technical specifications cubic cm 0.82 0.82 0.82

13.17 Supplying fitting and fixing in position true to line and level
sliding plate bearing with stainless steel plate sliding on
stainless steel plate with mild steel matrix complete including
all accessories as per drawing and technical specifications. tonne 188.20 188.20 188.20

Supplying, fitting and fixing in position true to line and level


13.18 POT-PTFE bearing consisting of a metal piston saupported
by a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel /fabricated structural steel, metal and
elastomer elements to be as per IRC:83 Part I & ii
respectively and other parts conforming to BS:5400 section
9.1 & 9.2 and clause 2006 of Mort&h specification complete
as per dwrawing and approved technical specificatons tonne 185.60 185.60 185.60

13.19
Protection to sub strucutre by using coal tar epoxy sqm #VALUE! #VALUE! #VALUE!

13.20 Providing strucutral steel for sub-structure complete as per


drwaing and technical specifications MT 106277.40 106277.40 106277.40
CHAPTER-13
BRIDGE SUBSTRUCUTRE
Quantity as per peroject category
Sr No Ref. to M. Description Unit
Large Medium

1300 &
13.01 Brick masonry work in 1:3 in substructure
2200
complete excluding pointing and plastering, as
per drawing and Technical Specifications
Unit=cum
Taking output=1cum
a) Material
Brick Ist class each 500.000 500.000
Cement mortar 1:3 (Rate taken from subanalysis
21.01 A) cum 0.240 0.240
Water for curing KL 0.483 0.483
b) Labour
Mate day 0.064 0.064
Mason day 0.800 0.800
Mazdoor day 0.800 0.800
Add for scaffolding @5 percent of cost of material
and labour
c) Machinery

Water tanker (speed @ km/hr and return speed


@km/hr and spreading @30 mins per trip)
0.003 X L1
(i) 16 KL capacity hour +0.02
0.004 X L1 +
(ii) 12 KL capacity hour 0.027

(iii) 6 KL capacity hour


d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Rate per cum (a+b+c+d+e)

1300 &
13.02 Pointing with cement mortar (1:3) on brick work in
2200
substrucutre as per technical specifications
Unit=sqm
Taking output =10 sqm
a) Material
Cement mortar 1:3 ( Rate taken from sub-analysis
21.01 A) cum 0.030 0.030
b) Labour
Mate day 0.040 0.040
Mason day 0.500 0.500
Mazdoor day 0.500 0.500
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d)Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Rate for 10 sqm (a+b+c+d)

Note
Scaffolding is already included in item 13.01

1300 &
13.03 Plastering with cement mortar (1:3) on brick work
2200
in substructure as per technical specifications
Unit= 10sqm
Taking output=10sqm
a) Material
Cement mortar 1:3 ( Rate taken from sub-analysis
21.01 A) cum 0.144 0.144
Water for curing KL 0.139 0.139
b) Labour
Mate day 0.040 0.040
Mason day 0.500 0.500
Mazdoor day 0.500 0.500
c) Machinery

Water tanker (speed @km/hr and return speed @


km/hr and spreading @30 mins per trip)
0.001 X L1 +
(i) 16 KL capacity hour 0.006
0.001 X L1 + .
(ii) 12 KL capacity hour 008

(iii) 6 KL capacity hour


d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Cost for 10 sqm= (a+b+c+d+e)
Rate per sqm=(a+b+c+d+e)/10
Note 1. Scaffolding is already included in item no.
13.01

2. The number of mason and mazdoors already


catered in the cement mortar have been taken
into acount while providing these categories in
brick masonry, pointing and plastering

1400 Stone masonry work in cement mortar 1:3 for


13.04 substructure complete as per drawing and
2200
technical specifications

A
Random Rubble Masonry (Coursed/uncoursed)
unit=cum
Taking output=1cum
a) Material
Stone cum 1.000 1.000
Through and bond stone (7no. X 0.24m X 0.24m
X 0.39m=0.16cum) No. 7.000 7.000
Cement mortar 1:3 (Rate taken from sub analysis
21.01 A) cum 0.330 0.330
Water for curing KL 0.966 0.966
b) Labour
Mate day 0.096 0.096
Mason day 1.200 1.200
Mazdoor day 1.200 1.200
Add for scaffolding @5 percent of cost of a)
Material and b) Labour)
c) Machinery

Water tanker (speed @ km/hr and return speed


@km/hr and spreading @ 30mins per trip)
0.007 X L1 +
(i) 16 KL capacity hour 0.04
0.009 X L1 +
(ii) 12 KL capacity hour 0.054

(iii) 6 KL capacity hour


d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Rate per cum (a+b+c+d+e)
13.04 B Coursed rubble masonry (first sort)
unit=cum
Taking output=1cum
a) Material
Stone cum 1.100 1.100
Through and bond stone (7no. X 0.24m X 0.24m
X 0.39m=0.16cum) No. 7.000 7.000
Cement mortar 1:3 (Rate taken from sub analysis
21.01 A) cum 0.300 0.300
Water for curing KL 0.966 0.966
b) Labour
Mate day 0.120 0.120
Mason day 1.500 1.500
Mazdoor day 1.500 1.500
Add for scaffolding @5 percent of cost of a)
Material and b) Labour)
c) Machinery

Water tanker (speed @ km/hr and return speed


@km/hr and spreading @ 30mins per trip)
0.007 X L1 +
(i) 16 KL capacity hour 0.04
0.009 X L1 +
(ii) 12 KL capacity hour 0.054

(iii) 6 KL capacity hour


d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Rate per cum (a+b+c+d+e)

13.04 C Ashlar masonry (first sort)


Plain ashlar
Unit=cum
Taking output=1cum
a) Material
Stone cum 1.110 1.110
Through and bond stone (7no. X 0.24m X 0.24m
X 0.39m=0.16cum) No. 7.000 7.000
Cement mortar 1:3 (Rate taken from sub analysis
21.01 A) cum 0.330 0.330
Water for curing KL 0.966 0.966
b) Labour for masonry work
Mate day 0.200 0.200
Mason day 2.500 2.500
Mazdoor day 2.500 2.500
Add for scaffolding @5 percent of cost of a)
Material and b) Labour)
c) Machinery

Water tanker (speed @ km/hr and return speed


@km/hr and spreading @ 30mins per trip)
0.007 X L1 +
(i) 16 KL capacity hour 0.04
0.009 X L1 +
(ii) 12 KL capacity hour 0.054

(iii) 6 KL capacity hour


d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Rate per cum (a+b+c+d+e)

The labour already considered in the cement


Note mortar have been taken into account while
providing these categories in the stone masonry
works.

1500,170 Plain/Reinforced cement concrete in sub-


13.05 strucutre complete as per drawing and Technical
0 & 2200
speciofications
A PCC Grade M15
(p) Height upto 5m
PCC Grade M15 using batching plant & concrete
pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.03) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @10 percent on cost of concrete i.e.


cost of material , labour and machinery
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Rate per cum (a+b+c+d+e+f)/30

13.05 B PCC Grade M20


(p) Height upto 5m
PCC Grade M20 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.04) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @10 percent on cost of concrete i.e.


cost of maerial , labour and machinery
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 C PCC Grade M25 using batching plant, transit


mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.06) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @10 percent on cost of concrete i.e.


cost of maerial , labour and machinery
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum=a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 C (q) Height 5m to 10m


PCC Grade M25 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.06) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( spread @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork @12 percent on cost of concrete i.e.
cost of maerial , labour and machinery

Add 2 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum=a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 C (r) Height above 10m


PCC Grade M25 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.06) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @15 percent on cost of concrete i.e.


cost of maerial , labour and machinery
Add 4 percent of cost of material, labour and
machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum=a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 D PCC Grade M30


(p) Height upto 5 m
PCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.08) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @10 percent on cost of concrete i.e.


cost of maerial , labour and machinery
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum=a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 D (q) Height 5m to 10m


PCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.08) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @12 percent on cost of concrete i.e.


cost of maerial , labour and machinery

Add 2 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum=a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30
13.05 D (r) Height above 10m
PCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.08) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.113 0.113
Mason day 1.500 1.500
Mazdoor day 1.325 1.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 min for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @15 percent on cost of concrete i.e.


cost of maerial , labour and machinery

Add 4 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 E RCC Grade M20


(p) Height upto 5m
RCC Grade M20 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.05) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @10 percent on cost of concrete i.e.


cost of maerial , labour and machinery
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 E (q) Height 5m to 10m


RCC Grade M20 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.05) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @12 percent on cost of concrete i.e.


cost of maerial , labour and machinery

Add 2 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 E (r) Height above 10m


RCC Grade M20 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.05) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour

d) Formwork @15 percent on cost of concrete i.e.


cost of maerial , labour and machinery

Add 4 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 F RCC Grade M25


(p) Height upto 5m
RCC Grade M25 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.07) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @ 10 percent on cost of concrete i.e cost of


material , labour and machinery (a+b+c) for
formwork
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 F (q) Height 5 to 10m


RCC Grade M25 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.07) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @11.8 percent on cost of concrete i.e. cost


of maerial , labour and machinery (a+b+c) for
formwork

Add 1.8 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 F (r) Height above 10m


RCC Grade M25 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.07) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @15 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 4 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 G RCC Grade M30


(p) Height upto 5m
RCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.09) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @10 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 G (q) Height 5m to 10m


RCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.09) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @11.5 percent on cost of concrete i.e. cost


of maerial , labour and machinery (a+b+c) for
formwork

Add 1.6 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 G (r) Height above 10m


RCC Grade M30 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.09) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875
(iii) 6 KL capacity hour
d) Formwork

Add @14 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 3.5percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 H RCC Grade M35


(p) Height upto 5 m
RCC Grade M35 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.11) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875
(iii) 6 KL capacity hour
d) Formwork

Add @10 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 H (q) Height 5m to 10m


RCC Grade M35 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.11) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork
Add @11 percent on cost of concrete i.e. cost of
maerial , labour and machinery (a+b+c) for
formwork

Add 1.4percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

The basic components of this analysis are the


Note same as those of items 13.08 (A to H). The only
changes are as under

(a) Ramps/Stairs: Extra expenditure on structures


which are more than 5m high @ 2 percent of cost
for height upto 10m and 4 percent for heights
above 10m will be involved for approaching the
work spot by providing higher ramp/stairs case for
use by the working parties.

(b) The above mentioned percentages have been


suitably modified for different categories as cost
for various categories varies whereas effort for
access for same height will be similar. As the cost
of richer concrete is comparitively more , the
percentage to be added has been reduced to
maintaine the same cost for extra efforts.

13.05 H (r) Height above 10m


RCC Grade M35 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.11) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @13 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 3 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 I RCC Grade M40


(p) Height upto 5m
RCC Grade M40 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.12) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @10 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 I (q) Height 5m to 10m


RCC Grade M40 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.12) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @11 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 1.4 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 I (r) Height above 10m


RCC Grade M40 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.12) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @13 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 3 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 J RCC Grade M 45


(p) Height upto 5m
RCC Grade M45 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.13) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @10 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 J (q) Height 5m to 10m


RCC Grade M45 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.13) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @11 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 1.4 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 J (r) Height above 10m


RCC Grade M45 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.13) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875
(iii) 6 KL capacity hour
d) Formwork

Add @13 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 3 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 K RCC Grade M50


(p) Height upto 5m
RCC Grade M50 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.14) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875
(iii) 6 KL capacity hour
d) Formwork

Add @10 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 3 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 K (q) Height 5m to 10m


RCC Grade M50 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.14) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)
0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork

Add @11 percent on cost of concrete i.e. cost of


maerial , labour and machinery (a+b+c) for
formwork

Add 1.4percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

13.05 K (r) Height above 10m


RCC Grade M50 using batching plant, transit
mixer & concrete pump
Unit=cum
Taking output=30cum
a) Material
Per cum Basic cost (Rate taken from sub-
analysis-21.14) cum 30.000 30.000
Water for curing KL 15.750 15.750
b) labour
For pouring and placing
Mate day 0.153 0.153
Mason day 1.500 1.500
Mazdoor day 2.325 2.325
c) Machinery
Transit truck agitator
For transportation (6cum capacity) tonne-km 75 X L1 75 X L1
For unloading hour 0.650 0.650
Hydraulic Boom placer pump hour 0.650 0.650
Water tanker ( speed @km/hr and return speed
@ km/hr and 30 mins for unloading)

0.109 X L1 +
(i) 16 KL capacity hour 0.656
0.146 X L1 +
(ii) 12 KL capacity hour 0.875

(iii) 6 KL capacity hour


d) Formwork
Add @13 percent on cost of concrete i.e. cost of
maerial , labour and machinery (a+b+c) for
formwork

Add 3 percent of cost of material, labour and


machinery excluding formwork to cater for extra
lift
e) Overhead charges @ on (a+b+c+d) (@ 20%) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%) (@ 10%)
Cost for 30 cum= a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/30

The basic components of this analysis are the


Note same as those of items 13.08 (A to K). The only
changes are as under

(a) Ramps/Stairs: Extra expenditure on structures


which are more than 5m high @ 2 percent of cost
for height upto 10m and 4 percent for heights
above 10m will be involved for approaching the
work spot by providing higher ramp/stairs case for
use by the working parties.

(b) The above mentioned percentage have been


suitably modified for different categories as cost
for various categories varies whereas effort for
access for same height will be similar. As the cost
of richer concrete is comparitively more , the
percentage to be added has been reduced to
maintain the same cost for extra efforts.

Section
13.06 1600 & Supplying, fitting and placing HYSD bar
2200 reinforcement in sub structure complete as per
drawing and technical specifications
Unit=MT
Taking output=8MT
a) Material

HYSD bars including 5% overlaps and wastage tonne 8.400 8.400


Binding Wire kg 48.000 48.000
b) Labour for straightening, cutting, bending ,
shifting to site tying and placing in position.
Mate day 0.160 0.160
Blacksmith day 1.000 1.000
Mazdoor day 3.000 3.000
c) Machinery
Cutting Machine hour 6.667 6.667
Bending machine hour 6.667 6.667
Electric generator 15 KVA hour 6.667 6.667
Tipper
Tipper for transportation
(i) 18 cum capacity t.km 8 X L1
(ii) 14 cum capacity t.km 8 X L1
(iii) 10 cum capacity t.km
Loading & unloading time
(i) 18 cum capacity hour 1.000
(ii) 14 cum capacity hour 1.280
(iii) 10 cum capacity hour
Light weight crane
At cutting bending yard hour 2.000 2.000
At site hour 2.000 2.000
d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Cost for 8MT (a+b+c+d+e)
Rate per MT= (a+b+c+d+e)/8

Section
13.07 1600 & Supplying, fitting and placing Mild steel
2200 reinforcement complete in sub structure as per
drawing and technical specifications
Unit=MT
Taking output=8MT
a) Material

MS bars including 5% overlaps and wastage tonne 8.400 8.400


Binding Wire kg 48.000 48.000

b) Labour for straightening, cutting, bending ,


shifting to site tying and placing in position.
Mate day 0.160 0.160
Blacksmith day 1.000 1.000
Mazdoor day 3.000 3.000
c) Machinery
Cutting Machine hour 6.667 6.667
Bending machine hour 6.667 6.667
Electric generator 15 KVA hour 6.667 6.667
Tipper
Tipper for transportation
(i) 18 cum capacity t.km 8 X L1
(ii) 14 cum capacity t.km 8 X L1
(iii) 10 cum capacity t.km
Loading & unloading time
(i) 18 cum capacity hour 1.000
(ii) 14 cum capacity hour 1.280
(iii) 10 cum capacity hour
Light weight crane
At cutting bending yard hour 2.000 2.000
At site hour 2.000 2.000
d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Cost for 8MT (a+b+c+d+e)
Rate per MT= (a+b+c+d+e)/8

Providing weep holes in Brick masonry/


Plain/Reinforced concrete abutment , wing wall/
2706 & returen wall with 100 mm dia AC pipe, extending
13.08
2200 through the full width of the structure with slope of
1V:20 H towards drawing face. Complete as per
drawing and technical specifications.

Unit=Nos.
Taking output=30 nos.
a) Material

AC pipe 100 mm dia (including wastage @ 5% ) metre 31.500 31.500


Average length of weep hole is taken as 1m for
the purpose of estimating
MS Clamp each 30.000 30.000
Collar for AC pipe ( average ) each 10.000 10.000
taking 10 % of above pipe rate
Per cum basic cost (rate taken from sub analysis-
21.01 A) cum 0.050 0.050
b) Labour
Mate day 0.030 0.030
Mason day 0.500 0.500
Mazdoor day 0.250 0.250
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractors profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 30 Nos.= (a+b+c+d)
Rate per No.=(a+b+c+d)/30

1. In case of stone masonry, the size of the weep


holes shall be 150mm X 80 mm or circular with
150mm diameter.

2. For strucutre in stone masonry, the weep holes


shall be deemed to be included in the item of
stone masonry work and shall not be paid
separately

710.1.4.
Back filling behind abutment, wing wall, return
of
13.09 wall complete as per drawing and technical
IRC:78 &
specifications
2200

Unit=cum
Taking output=10 cum
A Granular Material
a) Labour
Mate day 0.280 0.280
Mazdoor day 7.000 7.000
b) Material
Granular material cum 12.000 12.000
c) Machinery
Plate compactor/power rammer hour 2.500 2.500
Water tanker 6KL capacity hour 0.050 0.050
d) Overhead charges @ on ( a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)

Cost for 10 cum of granular backfill=a+b+c+d+e


Rate per cum= (a+b+c+d+e)/10

13.09 B Sandy material


a) Labour
Mate day 0.280 0.280
Mazdoor for filling, watering,ramming, etc day 7.000 7.000
b) Material
Sand cum 12.000 12.000
c) Machinery
Plate compactor/ power rammer hour 2.500 2.500
Water tanker 6KL capacity hour 0.060 0.060
d) Overhead charges @ on ( a+b+c) (@ 20%) (@ 20%)
e)Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)

Cost for 10 cum of sandy backfill= a+b+c+d+e


Rate per cum= (a+b+c+d+e)/10

710.1.4 Providing and laying of filter media with granular


of IRC : materials/stones crushed aggregates satisfying
13.10 the requirements laid down in clause 2504.2.2 of
78 &
2504.2 MoRT&H specifications to a thickness of not less
than 600 mm with smaller size towards the soil
and bigger size towards the wall and provided
over the entire surface behind abutment , wing
wall and return wall to the full height compacted
to a firm condition complete as per drwaing and
technical specification.
Unit=cum
Taking output=10 cum
a) Labour
Mate day 0.320 0.320
Mazdoor for filling, watering , ramming, etc day 7.000 7.000
Mazdoor (skilled) day 1.000 1.000
b) Material

Filter media of stone aggregate conforming ito


clause 2504.2.2 of MoRT&H specification cum 12.000 12.000
c)Machinery
Water tanker of 6KL capacity hour 0.060 0.060
d) Overhead charges @ on ( a+b+c) (@ 20%) (@ 20%)
e)Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Cost for 10 cum of filter media = a+b+c+d+e
Rate per cum= (a+b+c+d+e)/10

Supplying and laying of drainage composite for


use behind walls , between two different fills,
alongside drains of road, below concrete lining of
canals etc.. Geo composite for planar drainage,
realised by thermos bonding a draining core in
13.11 704
extruded monofilaments with two filtering
nonwoven geotextiles that may also be working
as seperation or protecting layers. The draining
three dimensional core will have a "W"
configuration as longitudinal parallel channels.

Minimum thickness to be 7.2 mm with two filtering


UV stabilised polypropylene nonwoven geotextile
of minimum thickness of 0.75mm having pores of
150 micron and tensile strength of 8KN/m that will
be working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1
L /(m.s ) at hydraulic gradient of 1.0 and 20 kpa
pressure and tensile strength of 18KN/m, with
mass per unit area of 740 gsm , supplied in the
form of roll for easy transportation to site of work
as per detailed specification all complete as per
direction of Engineer in charge.
Unit=sqm
Taking output=300 sqm
a) Labour
Mate day 0.200 0.200
Mazdoor day 3.000 3.000
Mazdoor (skilled) day 2.000 2.000
b) Material
Geosynthetic drainge composite sqm 300.000 300.000
Add 10 percent of the cost of synthetic
composites for wastage and accessories for
joining sheets with the fascia panels, overlap,
other protective elements for synthetic
composites and other miscellaneous activities
required to complete the item in all respect
including transportation and takes.
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 300 sqm = a+b+c+d
Rate per sqm=(a+b+c+d)/300

Supplying and laying of drainage composite for


use behind walls between two different fills, along
side drains of road, below concrete lining of
canals etc having thermos bonding draining core-
HDPE geonet comprises of two sets of parallel
overlaid ribs integrally connected to have a
rhomboidal shape with a polyehtylene film and a
nonwoven geotextile having mass per unit area
130g/m2 and tensile strength of 8KN/m that will
13.12 704
be working as separation or protecting layer,
geocomposite having in plane flow capacity of
0.7 l/(m.s) at hydraulic gradient of 1.0 and 20 kpa
pressure and tensile strength of 13.5 KN/m, with
mass per unit area of 830 gsm, at easily accesible
location including top and bottom, with all leads
and lifts, manpower and machinery, materials,
labour etc complete and as directed by Engineer
in charge

Unit= sqm
Taking output= 300sqm
a) Labour
Mate day 0.200 0.200
Mazdoor day 3.000 3.000
Mazdoor (skilled) day 2.000 2.000
b) Material
Geosynthetic drainage composite sqm 300.000 300.000

Add 10 percent of the cost of synthetic


composites for wastage and accessories for
joining sheets with the fascia panels, overlaps,
other protective elements for synthetic
composites and other miscellaneous activities
required to complete the item in all respect
including transportation and takes.
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 300 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/300

Supplying fitting and fixing in positon true to line


2000,100
13.13 and level cast steel rocker bearing conforming to
0 &2200
IRC: 83 (pt.-1) Section IX and clause 2003 of
MoRT&H specifications complete including all
accessories as per drawing and technical
specification
Unit=one Tonne capacity
Considering a 250 tonne capacity bearing for the
analysis
a) Labour
Mate day 0.060 0.060
Mazdoor( skilled) day 0.500 0.500
Mazdoor day 1.000 1.000
b) Material

Cast steel rocker bearing assembly of 250 tonne


design load capacity duly painted complete with
all its components as per drawing and
specification each 1.000 1.000

Add 1 percent of cost of bearing assembly for


foundation anchorage bolts, lifting arrangements,
grease and other consumables
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 250 tonnes capacity bearing =a+b+c+d
Rate per tonne capacity = (a+b+c+d) /250

Supplying fitting and fixing in positon true to line


2000,100
13.14 and level forged steel roller bearing conforming
0 & 2200
to IRC: 83 (pt.-1) Section IX and clause 2003 of
Mort&h specifications complete including all
accessories as per drawing and technical
specification
Unit= one tonne capacity
Considering a 250 tonne capacity bearing for the
analysis
a) Labour
Mate day 0.060 0.060
Mazdoor day 1.000 1.000
Mazdoor (skilled) day 0.500 0.500
b) Material

forged steel roller bearing of 250 tonne design


load capacity duly painted complete with all its
component as per drawing and specification each 1.000 1.000

Add 1 percent of cost of bearing assembly for


foundation anchorage bolts, lifting arrangements,
grease and other consumables
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)

Cost for 250 tonnes capacity bearing =a+b+c+d


Rate per tonne capacity =(a+b+c+d)/ 250

Supplying fitting and fixing in positon true to line


and level sliding plate bearing with PTFE surface
sliding of stainless steel complete including all
accessories as per drawing and technical
2000 & specification and BS:5400, section 9.1 & 9.2 (for
13.15 PTFE) and clause 2004 of Mort&H specifications
2200
Unit= one tonne capacity
Considering a 80 tonne capacity bearing for the
analysis
a) Labour
Mate day 0.060 0.060
Mazdoor day 1.000 1.000
Mazdoor (skilled) day 0.500 0.500
b) Material

PTFE sliding plate bearing assembly of 80 tonnes


design load capacity duly painted complete with
all its component as per drawing and specification each 1.000 1.000
Add 1 percent for foundation anchorage bolts,
and consumables
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)

Cost for 80 tonnes capacity bearing =a+b+c+d


Rate per tonne capacity =(a+b+c+d)/ 80

Supplying , fitting and fixing in position true to line


2000 &
13.16 and level elastomeric bearing conforming to
2200
IRC:83 (Part-II) section IX and clause 2005 of
Mort&H specification complete including all
accessories as per drwaing and technical
specifications
Unit= one cubic centimetre
Considering an elastomeric bearing of size 500 X
400 X 96 mm for this analysis.
Overall volume 19200 cu.cm
Volume of 6 nos.488 X 388 X4 mm size
reinforcing steel plates= 4545 cu.cm

Hence volume of elastomneric = 14655 cu.cm


a) Labour
Mate day 0.060 0.060
Mazdoor day 1.000 1.000
Mazdoor (skilled) day 0.500 0.500
b) Material
Elastomeric bearing assembly consisting of 7
layers of elastomer bonded to 6 nos. internal
reinforcing steel laminates by the process of
vulcanisation, complete with all component as per
drawing and technical specifications each 1.000 1.000

Add 1 percent of cost of bearing assembly for


foundation anchorage bolts and consumables.
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 19200 cc of elastomeric bearing
=a+b+c+d
Rate per cc of elastomeric bearing =
(a+b+c+d)/19200

2000 &
13.17 Supplying fitting and fixing in position true to line
2200
and level sliding plate bearing with stainless steel
plate sliding on stainless steel plate with mild
steel matrix complete including all accessories as
per drawing and technical specifications.
Unit= one tonne capacity
Considering the sliding bearing of 80 tonnes
design capacity for this analysis
a) Labour
Mate day 0.044 0.044
Mazdoor day 0.750 0.750
Mazdoor (skilled) day 0.350 0.350
b) Material

Supplying of sliding plate bearing of 80 tonnes


design capacity complete as per drawing and
specification each 1.000 1.000

Add 1 percent of cost of bearing assembly for


foundation anchorage bolts, and consumables
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)

Cost for 80 tonnes of capacity bearing =a+b+c+d


Rate per tonne capacity =(a+b+c+d)/80

Supplying, fitting and fixing in position true to line


and level POT-PTFE bearing consisting of a
2000 & metal piston saupported by a disc or unreinforced
13.18
2200 elastomer confined within a metal cylinder,
sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete
assembly to be of cast steel /fabricated structural
steel, metal and elastomer elements to be as per
IRC:83 Part I & ii respectively and other parts
conforming to BS:5400 section 9.1 & 9.2 and
clause 2006 of Mort&h specification complete as
per dwrawing and approved technical
specificatons
Unit=one tonne capacity
Considering a pot bearing assembly of 250
tonnes capacity for this analysis
a) Labour
Mate day 0.080 0.080
Mazdoor day 1.500 1.500
Mazdoor (skilled) day 0.500 0.500
b) Material

Pot type bearing assembly consoisting of a metal


piston supported by a disc, PTFE pads providing
sliding surfaces against stainless steel mating
together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all
components as per clause 2006 and complete as
per drwaings and technical specifications each 1.000 1.000

Add 1 percent of cost of bearing assembly for


foundation anchorage bolts and consumables
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 250 tonnes capacity bearing =a+b+c+d
Rate per tonne capacity =(a+b+c+d)/ 250

suggesti
13.19
ve Protection to sub strucutre by using coal tar epoxy

Providing and applying two coats of two


components, high build, 100% solid content, low
VOC, polycyclin aromatic hydrocarbon based, Pot
life= 2hrs @ 72 deg. F, Tack free- 4-6 hrs, DFT
per coat 80-120 microns (dry) coal tar epoxy
coating with coal tar
Unit=sqm
Taking output=100sqm
a) Labour
Mate day 0.360 0.360
Painter day 6.000 6.000
Mazdoor day 3.000 3.000
b) Material
Coal tar epoxy coating @ 0.5kg/sqm coverage
including 5% wastage kg 52.500 52.500
Add 1 percent of cost of abs towards
miscellaneous (water, painting brush, etc)
c) Overhead charges @ on (a+b) (@ 20%) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%) (@ 10%)
Cost for 100 sqm=a+b+c+d
Rate per sqm=(a+b+c+d)/100

Providing strucutral steel for sub-structure


13.20 complete as per drwaing and technical
specifications
Unit=MT
Taking output=10MT
a) Material
Structural steel in plates, angles etc including 5 %
wastage tonne 10.500 10.500
Nuts and bolts kg 105.00 105.00
b) Labour
(for cutting, bending, making holes,joining welding
and erecting in position)
Mate day 12.312 12.312
Fitter day 45.000 45.000
Blacksmith day 45.000 45.000
Welder day 45.000 45.000
Painter I class day 18.900 18.900
Mazdoor day 153.900 153.900

Electodes, cutting gas and other consumables @


10 percent of cost of (a) above
c) Machinery
Mobile hydraulic crane 10 tonne capacity ( for
fabrication) hrs 40.000 40.000
Crane 35 tonne capacity ( for loading &
unloading@ 1 hr for each operation) hrs 2.000 2.000
Crane 35 tonne capacity ( for lifting and placing in
position @ 2 hr) hrs 2.000 2.000

Trailer 30 tonne capacity for transporting to site hrs 2+ L/15 2+ L/15


Applying two coats primer before painting of truss
and girder ( 42 sqm/tonne) lits 525.000 525.000
Painting of Truss and girder lits 525.000 525.000
Sundries @ 3% of the above
d) Overhead charges @ on (a+b+c) (@ 20%) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%) (@ 10%)
Cost for 10 MT=a+b+c+d+e
Rate per MT=(a+b+c+d+e)/10
R-13
RUCUTRE
per peroject category Rate (Rs) Amount Input_Ref
Small Large Medium Small

500.000 6.08 3037.50 3037.50 3037.50 M079

0.240 2971.50 713.16 713.16 713.16 21.01 A


0.483 73.60 35.55 35.55 35.55 M191

0.064 310.00 19.84 19.84 19.84 L-12


0.800 351.00 280.80 280.80 280.80 L-10
0.800 292.00 233.60 233.60 233.60 L-13

216.02 216.02 216.02

1426.00 32.80 PM11001

1252.00 38.81 PM11002


0.009 X L1 +
0.054 907.00 57.14 PM11003
(@ 20%) 913.85 915.06 918.72
(@ 10%) 548.31 549.03 551.23
6031.44 6039.37 6063.57
Say 6031.40 6039.40 6063.60
0.030 2971.50 89.15 89.15 89.15 21.01 A

0.040 310.00 12.40 12.40 12.40 L-12


0.500 351.00 175.50 175.50 175.50 L-10
0.500 292.00 146.00 146.00 146.00 L-13
(@ 20%) 84.61 84.61 84.61
(@ 10%) 50.77 50.77 50.77
558.42 558.42 558.42
Say 558.40 558.40 558.40

0.144 2971.50 427.90 427.90 427.90 21.01 A


0.139 73.60 10.23 10.23 10.23 M191

0.040 310.00 12.40 12.40 12.40 L-12


0.500 351.00 175.50 175.50 175.50 L-10
0.500 292.00 146.00 146.00 146.00 L-13

1426.00 9.98 PM11001

1252.00 11.27 PM11002


0.003 X L1 +
0.015 907.00 16.33 PM11003
(@ 20%) 156.40 156.66 157.67
(@ 10%) 93.84 94.00 94.60
1032.25 1033.95 1040.63
103.23 103.39 104.06
Say 103.20 103.40 104.10

1.000 351.36 351.36 351.36 351.36 M001

7.000 10.35 72.45 72.45 72.45 M184

0.330 2971.50 980.60 980.60 980.60 21.01 A


0.966 73.60 71.10 71.10 71.10 M191

0.096 310.00 29.76 29.76 29.76 L-12


1.200 351.00 421.20 421.20 421.20 L-10
1.200 292.00 350.40 350.40 350.40 L-13

113.84 113.84 113.84

1426.00 67.02 PM11001

1252.00 78.88 PM11002


0.018 X L1 +
0.107 907.00 113.38 PM11003
(@ 20%) 491.55 493.92 500.82
(@ 10%) 294.93 296.35 300.49
3244.20 3259.85 3305.39
Say 3244.20 3259.80 3305.40

1.100 351.36 386.50 386.50 386.50 M001

7.000 10.35 72.45 72.45 72.45 M184

0.300 2971.50 891.45 891.45 891.45 21.01 A


0.966 73.60 71.10 71.10 71.10 M191

0.120 310.00 37.20 37.20 37.20 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.500 292.00 438.00 438.00 438.00 L-13

121.16 121.16 121.16

1426.00 67.02 PM11001

1252.00 78.88 PM11002


0.018 X L1 +
0.107 907.00 113.38 PM11003
(@ 20%) 522.28 524.65 531.55
(@ 10%) 313.37 314.79 318.93
3447.02 3462.66 3508.20
Say 3447.00 3462.70 3508.20

1.110 351.36 390.01 390.01 390.01 M001

7.000 10.35 72.45 72.45 72.45 M184

0.330 2971.50 980.60 980.60 980.60 21.01 A


0.966 73.60 71.10 71.10 71.10 M191

0.200 310.00 62.00 62.00 62.00 L-12


2.500 351.00 877.50 877.50 877.50 L-10
2.500 292.00 730.00 730.00 730.00 L-13

159.18 159.18 159.18

1426.00 67.02 PM11001

1252.00 78.88 PM11002


0.018 X L1 +
0.107 907.00 113.38 PM11003
(@ 20%) 681.97 684.34 691.24
(@ 10%) 409.18 410.61 414.75
4501.01 4516.66 4562.20
Say 4501.00 4516.70 4562.20

30.000 2121.80 63654.00 63654.00 63654.00 21.03


15.750 73.60 1159.20 1159.20 1159.20 M191
0.113 310.00 35.03 35.03 35.03 L-12
1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

7185.20 7203.94 7261.32


(@ 20%) 15807.44 15848.67 15974.91
(@ 10%) 9484.47 9509.20 9584.95
3477.64 3486.71 3514.48
Say 3477.60 3486.70 3514.50

30.000 2483.18 74495.40 74495.40 74495.40 21.04


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM 11001

1252.00 1278.29 PM 11002


0.292 X L1
+1.75 907.00 1852.09 PM 11003

8269.34 8288.08 8345.46


(@ 20%) 18192.55 18233.78 18360.02
(@ 10%) 10915.53 10940.27 11016.01
120070.85 120342.95 121176.11
4002.36 4011.43 4039.20
Say 4002.40 4011.40 4039.20

30.000 2754.10 82623.00 82623.00 82623.00 21.06


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001


1252.00 1278.29 PM11002
0.292 X L1
+1.75 907.00 1852.09 PM11003

9082.10 9100.84 9158.22


(@ 20%) 19980.62 20021.85 20148.09
(@ 10%) 11988.37 12013.11 12088.85
131872.12 132144.23 132977.39
4395.74 4404.81 4432.58
Say 4395.70 4404.80 4432.60

30.000 2754.10 82623.00 82623.00 82623.00 21.06


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003
10898.52 10921.01 10989.87

1816.42 1820.17 1831.64


(@ 20%) 20707.19 20749.92 20880.75
(@ 10%) 12424.32 12449.95 12528.45
136667.47 136949.47 137812.93
4555.58 4564.98 4593.76
Say 4555.60 4565.00 4593.80

30.000 2754.10 82623.00 82623.00 82623.00 21.06


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

13623.15 13651.26 13737.33


3632.84 3640.34 3663.29
(@ 20%) 21615.40 21660.00 21796.57
(@ 10%) 12969.24 12996.00 13077.94
142661.66 142956.03 143857.36
4755.39 4765.20 4795.25
Say 4755.40 4765.20 4795.20

30.000 2780.50 83415.00 83415.00 83415.00 21.08


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

9161.30 9180.04 9237.42


(@ 20%) 20154.86 20196.09 20322.33
(@ 10%) 12092.92 12117.66 12193.40
133022.11 133294.21 134127.37
4434.07 4443.14 4470.91
Say 4434.10 4443.10 4470.90

30.000 2780.50 83415.00 83415.00 83415.00 21.08


15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

10993.56 11016.05 11084.91

1832.26 1836.01 1847.48


(@ 20%) 20887.77 20930.50 21061.32
(@ 10%) 12532.66 12558.30 12636.79
137859.27 138141.28 139004.73
4595.31 4604.71 4633.49
Say 4595.31 4604.70 4633.50
30.000 2780.50 83415.00 83415.00 83415.00 21.08
15.750 73.60 1159.20 1159.20 1159.20 M191

0.113 310.00 35.03 35.03 35.03 L-12


1.500 351.00 526.50 526.50 526.50 L-10
1.325 292.00 386.90 386.90 386.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

13741.95 13770.06 13856.13

3664.52 3672.02 3694.97


(@ 20%) 21803.90 21848.50 21985.07
(@ 10%) 13082.34 13109.10 13191.04
143905.73 144200.10 145101.43
4796.86 4806.67 4836.71
Say 4796.90 4806.70 4836.70
30.000 2548.90 76467.00 76467.00 76467.00 21.05
15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

8496.94 8515.68 8573.06


(@ 20%) 18693.27 18734.50 18860.74
(@ 10%) 11215.96 11240.70 11316.44
123375.60 123647.71 124480.87
4112.52 4121.59 4149.36
Say 4112.50 4121.60 4149.40
30.000 2548.90 76467.00 76467.00 76467.00 21.05
15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

10196.33 10218.82 10287.67

1699.39 1703.14 1714.61


(@ 20%) 19373.03 19415.76 19546.58
(@ 10%) 11623.82 11649.45 11727.95
127861.98 128143.99 129007.44
4262.07 4271.47 4300.25
Say 4262.10 4271.50 4300.20

30.000 2548.90 76467.00 76467.00 76467.00 21.05


15.750 73.60 1159.20 1159.20 1159.20 M191
0.153 310.00 47.43 47.43 47.43 L-12
1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

12745.41 12773.52 12859.59

3398.78 3406.27 3429.22


(@ 20%) 20222.72 20267.32 20403.89
(@ 10%) 12133.63 12160.39 12242.33
133469.96 133764.34 134665.66
4449.00 4458.81 4488.86
Say 4449.00 4458.80 4488.90

30.000 2950.40 88512.00 88512.00 88512.00 21.07


15.750 73.60 1159.20 1159.20 1159.20 M191
0.153 310.00 47.43 47.43 47.43 L-12
1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

9701.44 9720.18 9777.56


(@ 20%) 21343.17 21384.40 21510.64
(@ 10%) 12805.90 12830.64 12906.38
140864.94 141137.05 141970.21
4695.50 4704.57 4732.34
Say 4695.50 4704.60 4732.30

30.000 2950.40 88512.00 88512.00 88512.00 21.07


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13
75 X L1 12.32 924.00 924.00 924.00 PM76001
0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

11447.70 11469.81 11537.52

1746.26 1749.63 1759.96


(@ 20%) 22041.68 22084.25 22214.62
(@ 10%) 13225.01 13250.55 13328.77
145475.06 145756.08 146616.50
4849.17 4858.54 4887.22
Say 4849.20 4858.50 4887.20

30.000 2950.40 88512.00 88512.00 88512.00 21.07


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

14552.16 14580.27 14666.34

3880.58 3888.07 3911.02


(@ 20%) 23089.43 23134.03 23270.60
(@ 10%) 13853.66 13880.42 13962.36
152390.25 152684.62 153585.95
5079.68 5089.49 5119.53
Say 5079.70 5089.50 5119.50

30.000 3033.50 91005.00 91005.00 91005.00 21.09


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001
1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

9950.74 9969.48 10026.86


(@ 20%) 21891.63 21932.86 22059.10
(@ 10%) 13134.98 13159.72 13235.46
144484.77 144756.88 145590.04
4816.16 4825.23 4853.00
Say 4816.20 4825.20 4853.00

30.000 3033.50 91005.00 91005.00 91005.00 21.09


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001


1252.00 1278.29 PM11002
0.292 X L1
+1.75 907.00 1852.09 PM11003

11443.35 11464.90 11530.89

1592.12 1595.12 1604.30


(@ 20%) 22508.58 22550.97 22680.76
(@ 10%) 13505.15 13530.58 13608.46
148556.62 148836.39 149693.03
4951.89 4961.21 4989.77
Say 4951.90 4961.20 4989.80

30.000 3033.50 91005.00 91005.00 91005.00 21.09


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

13931.04 13957.28 14037.61

3482.76 3489.32 3509.40


(@ 20%) 23384.24 23428.28 23563.13
(@ 10%) 14030.55 14056.97 14137.88
154336.01 154626.67 155516.64
5144.53 5154.22 5183.89
Say 5144.50 5154.20 5183.90

30.000 3182.90 95487.00 95487.00 95487.00 21.11


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

10398.94 10417.68 10475.06


(@ 20%) 22877.67 22918.90 23045.14
(@ 10%) 13726.60 13751.34 13827.08
150992.64 151264.75 152097.91
5033.09 5042.16 5069.93
Say 5033.10 5042.20 5069.90

30.000 3182.90 95487.00 95487.00 95487.00 21.11


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003
11438.84 11459.45 11522.57

1455.85 1458.48 1466.51


(@ 20%) 23376.82 23418.95 23547.94
(@ 10%) 14026.09 14051.37 14128.76
154287.02 154565.07 155416.41
5142.90 5152.17 5180.55
Say 5142.90 5152.20 5180.50

30.000 3182.90 95487.00 95487.00 95487.00 21.11


15.750 73.60 1159.20 1159.20 1159.20 M191
0.153 310.00 47.43 47.43 47.43 L-12
1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

13518.62 13542.99 13617.58

3119.68 3125.30 3142.52


(@ 20%) 24125.55 24169.02 24302.14
(@ 10%) 14475.33 14501.41 14581.29
159228.60 159515.55 160394.16
5307.62 5317.18 5346.47
Say 5307.60 5317.20 5346.50

30.000 3501.30 105039.00 105039.00 105039.00 21.12


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

11354.14 11372.88 11430.26


(@ 20%) 24979.11 25020.34 25146.58
(@ 10%) 14987.47 15012.20 15087.95
164862.14 165134.25 165967.41
5495.40 5504.47 5532.25
Say 5495.40 5504.50 5532.20

30.000 3501.30 105039.00 105039.00 105039.00 21.12


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

12489.56 12510.17 12573.29

1589.58 1592.20 1600.24


(@ 20%) 25524.11 25566.24 25695.23
(@ 10%) 15314.47 15339.74 15417.14
168459.13 168737.18 169588.52
5615.30 5624.57 5652.95
Say 5615.30 5624.60 5653.00

30.000 3501.30 105039.00 105039.00 105039.00 21.12


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001
1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

14760.38 14784.75 14859.34

3406.24 3411.86 3429.08


(@ 20%) 26341.61 26385.09 26518.21
(@ 10%) 15804.97 15831.05 15910.93
173854.62 174141.57 175020.18
5795.15 5804.72 5834.01
Say 5795.20 5804.70 5834.00

30.000 3638.50 109155.00 109155.00 109155.00 21.13


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001
1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

11765.74 11784.48 11841.86


(@ 20%) 25884.63 25925.86 26052.10
(@ 10%) 15530.78 15555.52 15631.26
170838.57 171110.68 171943.84
5694.62 5703.69 5731.46
Say 5694.60 5703.70 5731.50

30.000 3638.50 109155.00 109155.00 109155.00 21.13


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001


1252.00 1278.29 PM11002
0.292 X L1
+1.75 907.00 1852.09 PM11003

12942.32 12962.93 13026.05

1647.20 1649.83 1657.86


(@ 20%) 26449.39 26491.52 26620.51
(@ 10%) 15869.63 15894.91 15972.30
174565.96 174844.01 175695.34
5818.87 5828.13 5856.51
Say 5818.90 5828.10 5856.50

30.000 3638.50 109155.00 109155.00 109155.00 21.13


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

15295.46 15319.83 15394.42

3529.72 3535.34 3552.56


(@ 20%) 27296.52 27340.00 27473.12
(@ 10%) 16377.91 16404.00 16483.87
180157.04 180443.99 181322.60
6005.23 6014.80 6044.09
Say 6005.20 6014.80 6044.10

30.000 4189.30 125679.00 125679.00 125679.00 21.14


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003

13418.14 13436.88 13494.26

4025.44 4031.06 4048.28


(@ 20%) 30325.00 30367.35 30497.03
(@ 10%) 18195.00 18220.41 18298.22
200145.01 200424.53 201280.42
6671.50 6680.82 6709.35
Say 6671.50 6680.80 6709.30

30.000 4189.30 125679.00 125679.00 125679.00 21.14


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003
14759.96 14780.57 14843.69

1878.54 1881.16 1889.20


(@ 20%) 30163.98 30206.11 30335.10
(@ 10%) 18098.39 18123.67 18201.06
199082.29 199360.33 200211.67
6636.08 6645.34 6673.72
Say 6636.10 6645.30 6673.70

30.000 4189.30 125679.00 125679.00 125679.00 21.14


15.750 73.60 1159.20 1159.20 1159.20 M191

0.153 310.00 47.43 47.43 47.43 L-12


1.500 351.00 526.50 526.50 526.50 L-10
2.325 292.00 678.90 678.90 678.90 L-13

75 X L1 12.32 924.00 924.00 924.00 PM76001


0.650 2218.00 1441.70 1441.70 1441.70 PM34001
0.650 4052.00 2633.80 2633.80 2633.80 PM36001

1426.00 1090.89 PM11001

1252.00 1278.29 PM11002


0.292 X L1
+1.75 907.00 1852.09 PM11003
17443.58 17467.95 17542.54

4025.44 4031.06 4048.28


(@ 20%) 31130.09 31173.57 31306.69
(@ 10%) 18678.05 18704.14 18784.01
205458.59 205745.54 206624.15
6848.62 6858.18 6887.47
Say 6848.60 6858.20 6887.50

8.400 46824.00 393321.60 393321.60 393321.60 M083


48.000 58.95 2829.60 2829.60 2829.60 M072
0.160 310.00 49.60 49.60 49.60 L-12
1.000 351.00 351.00 351.00 351.00 L-25
3.000 292.00 876.00 876.00 876.00 L-13

6.667 334.00 2226.78 2226.78 2226.78 PM43001


6.667 334.00 2226.78 2226.78 2226.78 PM43001
6.667 410.00 2733.47 2733.47 2733.47 PM22009

5.94 47.54 PM72001


6.63 53.04 PM73001
8 X L1 8.08 64.64 PM74001

2772.00 2772.00 PM6001


2415.00 3091.20 PM6002
1.778 2121.00 3771.14 PM6003

2.000 862.00 1724.00 1724.00 1724.00 PM63001


2.000 862.00 1724.00 1724.00 1724.00 PM63001
(@ 20%) 82176.47 82241.41 82379.72
(@ 10%) 49305.88 49344.85 49427.83
542364.72 542793.33 543706.16
67795.59 67849.17 67963.27
Say 67795.60 67849.20 67963.30

8.400 50325.00 422730.00 422730.00 422730.00 M125


48.000 58.95 2829.60 2829.60 2829.60 M072

0.160 310.00 49.60 49.60 49.60 L-12


1.000 351.00 351.00 351.00 351.00 L-25
3.000 292.00 876.00 876.00 876.00 L-13

6.667 334.00 2226.78 2226.78 2226.78 PM43001


6.667 334.00 2226.78 2226.78 2226.78 PM43001
6.667 410.00 2733.47 2733.47 2733.47 PM22009

5.94 47.54 PM72001


6.63 53.04 PM73001
8 X L1 8.08 64.64 PM74001

2772.00 2772.00 PM6001


2415.00 3091.20 PM6002
1.778 2121.00 3771.14 PM6003

2.000 862.00 1724.00 1724.00 1724.00 PM63001


2.000 862.00 1724.00 1724.00 1724.00 PM63001
(@ 20%) 88058.15 88123.09 88261.40
(@ 10%) 52834.89 52873.86 52956.84
581183.81 581612.42 582525.25
72647.98 72701.55 72815.66
Say 72648.00 72701.60 72815.70

31.500 42.54 1340.01 1340.01 1340.01 M056

30.000 34.06 1021.80 1021.80 1021.80 M122


10.000 4.25 42.54 42.54 42.54 M056 X 0.1
0.050 2971.50 148.58 148.58 148.58 21.01 A

0.030 310.00 9.30 9.30 9.30 L-12


0.500 351.00 175.50 175.50 175.50 L-10
0.250 292.00 73.00 73.00 73.00 L-13
(@ 20%) 562.15 562.15 562.15
(@ 10%) 337.29 337.29 337.29
3710.16 3710.16 3710.16
123.67 123.67 123.67
Say 123.70 123.70 123.70

0.280 310.00 86.80 86.80 86.80 L-12


7.000 292.00 2044.00 2044.00 2044.00 L-13

12.000 163.53 1962.36 1962.36 1962.36 M009

2.500 352.00 880.00 880.00 880.00 PM46001


0.050 907.00 45.35 45.35 45.35 PM11003
(@ 20%) 1003.70 1003.70 1003.70
(@ 10%) 602.22 602.22 602.22

6624.43 6624.43 6624.43


662.44 662.44 662.44
Say 662.40 662.40 662.40
0.280 310.00 86.80 86.80 86.80 L-12
7.000 292.00 2044.00 2044.00 2044.00 L-13

12.000 175.80 2109.60 2109.60 2109.60 M005

2.500 352.00 880.00 880.00 880.00 PM46001


0.060 907.00 54.42 54.42 54.42 PM11003
(@ 20%) 1034.96 1034.96 1034.96
(@ 10%) 620.98 620.98 620.98

6830.76 6830.76 6830.76


683.08 683.08 683.08
Say 683.10 683.10 683.10

0.320 310.00 99.20 99.20 99.20 L-12


7.000 292.00 2044.00 2044.00 2044.00 L-13
1.000 370.00 370.00 370.00 370.00 L-15

12.000 504.46 6053.52 6053.52 6053.52 M011

0.060 907.00 54.42 54.42 54.42 PM11003


(@ 20%) 1724.23 1724.23 1724.23
(@ 10%) 1034.54 1034.54 1034.54
11379.90 11379.90 11379.90
1137.99 1137.99 1137.99
Say 1138.00 1138.00 1138.00

0.200 310.00 62.00 62.00 62.00 L-12


3.000 292.00 876.00 876.00 876.00 L-13
2.000 370.00 740.00 740.00 740.00 L-15

300.000 460.17 138051.00 138051.00 138051.00 M290


13805.10 13805.10 13805.10
(@ 20%) 30706.82 30706.82 30706.82
(@ 10%) 18424.09 18424.09 18424.09
202665.01 202665.01 202665.01
675.55 675.55 675.55
Say 675.60 675.60 675.60

0.200 310.00 62.00 62.00 62.00 L-12


3.000 292.00 876.00 876.00 876.00 L-13
2.000 370.00 740.00 740.00 740.00 L-15

300.000 547.82 164346.00 164346.00 164346.00 M291

16434.60 16434.60 16434.60


(@ 20%) 36491.72 36491.72 36491.72
(@ 10%) 21895.03 21895.03 21895.03
240845.35 240845.35 240845.35
802.82 802.82 802.82
Say 802.80 802.80 802.80

0.060 310.00 18.60 18.60 18.60 L-12


0.500 370.00 185.00 185.00 185.00 L-15
1.000 292.00 292.00 292.00 292.00 L-13

1.000 81589.38 81589.38 81589.38 81589.38 M065

815.89 815.89 815.89


(@ 20%) 16580.17 16580.17 16580.17
(@ 10%) 9948.10 9948.10 9948.10
109429.15 109429.15 109429.15
437.72 437.72 437.72
Say 437.70 437.70 437.70

0.060 310.00 18.60 18.60 18.60 L-12


1.000 292.00 292.00 292.00 292.00 L-13
0.500 370.00 185.00 185.00 185.00 L-15

1.000 45479.26 45479.26 45479.26 45479.26 M067

454.79 454.79 454.79


(@ 20%) 9285.93 9285.93 9285.93
(@ 10%) 5571.56 5571.56 5571.56

61287.14 61287.14 61287.14


245.15 245.15 245.15
Say 245.10 245.10 245.10
0.060 310.00 18.60 18.60 18.60 L-12
1.000 292.00 292.00 292.00 292.00 L-13
0.500 370.00 185.00 185.00 185.00 L-15

1.000 12104.94 12104.94 12104.94 12104.94 M069

121.05 121.05 121.05


(@ 20%) 2544.32 2544.32 2544.32
(@ 10%) 1526.59 1526.59 1526.59

16792.50 16792.50 16792.50


209.91 209.91 209.91
Say 209.90 209.90 209.90

0.060 310.00 18.60 18.60 18.60 L-12


1.000 292.00 292.00 292.00 292.00 L-13
0.500 370.00 185.00 185.00 185.00 L-15
1.000 11328.00 11328.00 11328.00 11328.00 M066

113.28 113.28 113.28


(@ 20%) 2387.38 2387.38 2387.38
(@ 10%) 1432.43 1432.43 1432.43

15756.68 15756.68 15756.68

Say 0.82 0.82 0.82

0.044 310.00 13.64 13.64 13.64 L-12


0.750 292.00 219.00 219.00 219.00 L-13
0.350 370.00 129.50 129.50 129.50 L-15

1.000 10933.11 10933.11 10933.11 10933.11 M070

109.33 109.33 109.33


(@ 20%) 2280.92 2280.92 2280.92
(@ 10%) 1368.55 1368.55 1368.55

15054.05 15054.05 15054.05


188.18 188.18 188.18
Say 188.20 188.20 188.20

0.080 310.00 24.80 24.80 24.80 L-12


1.500 292.00 438.00 438.00 438.00 L-13
0.500 370.00 185.00 185.00 185.00 L-15

1.000 34165.00 34165.00 34165.00 34165.00 M068

341.65 341.65 341.65


(@ 20%) 7030.89 7030.89 7030.89
(@ 10%) 4218.53 4218.53 4218.53
46403.87 46403.87 46403.87
185.62 185.62 185.62
Say 185.60 185.60 185.60

0.360 310.00 111.60 111.60 111.60 L-12


6.000 373.00 2238.00 2238.00 2238.00 L-18
3.000 292.00 876.00 876.00 876.00 L-13

52.500 input #VALUE! #VALUE! #VALUE! M234

#VALUE! #VALUE! #VALUE!


(@ 20%) #VALUE! #VALUE! #VALUE!
(@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!

10.500 46658.00 489909.00 489909.00 489909.00 M181


105.00 61.74 6482.70 6482.70 6482.70 M129
12.312 310.00 3816.72 3816.72 3816.72 L-12
45.000 351.00 15795.00 15795.00 15795.00 L-08
45.000 351.00 15795.00 15795.00 15795.00 L-25
45.000 394.00 17730.00 17730.00 17730.00 L-02
18.900 373.00 7049.70 7049.70 7049.70 L-18
153.900 292.00 44938.80 44938.80 44938.80 L-13

49639.17 49639.17 49639.17

40.000 1019.00 40760.00 40760.00 40760.00 PM63003

2.000 2337.00 4674.00 4674.00 4674.00 PM63006

2.000 2337.00 4674.00 4674.00 4674.00 PM63006

2+ L/15 2772.00 5728.80 5728.80 5728.80 PM6001

525.000 70.48 37002.00 37002.00 37002.00 M145


525.000 113.26 59461.50 59461.50 59461.50 M058
1675.10 1675.10 1675.10
(@ 20%) 161026.30 161026.30 161026.30
(@ 10%) 96615.78 96615.78 96615.78
1062773.57 1062773.57 1062773.57
106277.36 106277.36 106277.36
Say 106277.40 106277.40 106277.40
CHAPTER- 14
SUPERSTRUCTURE
Item No. Unit Rate as per project category
Description
Large Medium Small

Furnishing and Placing Reinforced/ Prestressed cement


14.01 concrete in super-structure as per drawing and Technical
Specification
A RCC Grade M20
Using Batching Plant ,Transit Mixer and Concrete Pump

For solid slab super-structure, 20-30 per cent of (a+b+c)


(i)

(p) Height upto 5m cum 4440.70 4450.60 4480.90


(q) Height 5m to 10m cum 4625.80 4636.00 4667.60
(r) Height above 10m cum 4810.80 4821.50 4854.30
(ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m cum 4625.80 4636.00 4667.60
(q) Height 5m to 10m cum 4810.80 4821.50 4854.30
(r) Height above 10m cum 4995.80 5006.90 5041.00
RCC Grade M25 Using Batching Plant, Transit Mixer and
B Concrete Pump
For solid slab super-structure, 20-30 per cent of (a+b+c)
(i)

(p) Height upto 5m cum 5076.70 5086.50 5116.80


(q) Height 5m to 10m cum 5288.30 5298.50 5330.00
(r) Height above 10m cum 5499.80 5510.40 5543.30
(ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m cum 5288.30 5298.50 5330.00
(q) Height 5m to 10m cum 5499.80 5510.40 5543.30
(r) Height above 10m cum 5711.30 5722.40 5756.50
RCC Grade M30 Using Batching Plant,Transite Mixer and
C Concrete Pump.
For solid slab super-structure, 20-30 per cent of (a+b+c)
(i)

(p) Height upto 5m cum 5208.40 5218.20 5248.50


(q) Height 5m to 10m cum 5425.40 5435.60 5467.20
(r) Height above 10m cum 5642.40 5653.00 5685.90
(ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m cum 5425.40 5435.60 5467.20
(q) Height 5m to 10m cum 5642.40 5653.00 5685.90
(r) Height above 10m cum 5859.40 5870.40 5904.50
D RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump

For solid slab super-structure, 18-28 per cent of (a+b+c)


(i)
(p) Height upto 5m cum 5354.30 5363.90 5393.70
(q) Height 5m to 10m cum 5581.10 5591.20 5622.30
(r) Height above 10m cum 5808.00 5818.50 5850.80
(ii) For T-beam & slab, 23-33 per cent of (a+b+c)
(p) Height upto 5m cum 5581.10 5591.20 5622.30
(q) Height 5m to 10m cum 5808.00 5818.50 5850.80
(r ) Height above 10m cum 6034.90 6045.80 6079.30
For box girder and balanced cantilever ,38-58 percent of cost
(iii) concrete.
(p) Height upto 5m cum 6261.80 6273.00 6307.90
(q) Height 5m to 10m cum 6715.50 6727.60 6765.00
(r) Height above 10m cum 7169.30 7182.20 7222.10
E RCC/PSC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump

For solid slab/voided slab super-structure, 18-28 per cent of


(i) (a+b+c)
(p) Height upto 5m cum 5850.20 5859.90 5889.60
(q) Height 5m to 10m cum 6098.10 6108.20 6139.20
(r) Height above 10m cum 6346.00 6356.40 6388.80
(ii) For T-beam & slab, 23-33 per cent of (a+b+c)
(p) Height upto 5m cum 6098.10 6108.20 6139.20
(q) Height 5m to 10m cum 6346.00 6356.40 6388.80
(r) Height above 10m cum 6593.90 6604.70 6638.30
For cast-in situ box girder,segmental construction and
(iii) balanced cantilever ,38-58 percent of cost of concrete.

(p) Height upto 5m cum 6841.80 6853.00 6887.90


(q) Height 5m to 10m cum 7337.50 7349.60 7387.00
(r) Height above 10m cum 7833.30 7846.20 7886.10
F RCC/PSC Grade M-45
For solid slab / voided slab super-structure, 16-26 per cent
(i) of cost of concrete (a+b+c)
(p) Height upto 5m cum 5961.10 5970.60 5999.90
(q) Height 5m to 10m cum 6218.10 6228.00 6258.50
(r) Height above 10m cum 6475.00 6485.30 6517.10
For T-beam & slab including launching of precast girders by
(ii) launching truss up to 40 m span, 21-31 per cent cost of
concrete .

(p) Height upto 5m cum 6218.10 6228.00 6258.50


(q) Height 5m to 10m cum 6475.00 6485.30 6517.10
(r) Height above 10m cum 6732.00 6742.70 6775.80
For cast-in situ box girder,segmental construction and
(iii) balanced cantilever ,36-56 percent of cost of concrete.

(p) Height upto 5m cum 6988.90 7000.00 7034.40


(q) Height 5m to 10m cum 7502.80 7514.70 7551.60
(r) Height above 10m cum 8016.70 8029.40 8068.80
G PSC Grade M-50
For cast-in-situ box girder, segmental construction and
(i) balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m cum 7919.00 7930.10 7964.20


(q) Height 5m to 10m cum 8505.60 8517.50 8554.10
(r) Height above 10m cum 9092.20 9104.90 9144.00
H PSC Grade M- 55
For cast-in-situ box girder, segmental construction and
(i) balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m cum 8057.10 8068.20 8102.30


(q) Height 5m to 10m cum 8654.00 8665.80 8702.40
(r) Height above 10m cum 9250.80 9263.50 9302.60
I PSC Grade M- 60
For cast-in-situ box girder, segmental construction and
(i) balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m cum 8379.90 8390.90 8425.00


(q) Height 5m to 10m cum 9000.60 9012.50 9049.10
(r) Height above 10m cum 9621.30 9634.00 9673.10
J PSC Grade M- 65
For cast-in-situ box girder, segmental construction and
(i) balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m cum 8451.90 8462.90 8497.00


(q) Height 5m to 10m cum 9077.90 9089.80 9126.40
(r) Height above 10m cum 9704.00 9716.70 9755.80
Supplying, fitting and placing HYSD bar reinforcement in
14.02 super-structure complete as per drawing and technical
specifications
MT 68032.70 68086.30 68200.40
High tensile steel wires/strands including all accessories for
stressing, stressing operations and grouting complete as per
14.03 drawing and Technical Specifications

MT 129849.80 129849.80 129849.80


Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing and
14.04 Technical Specifications

cum 9500.60 9512.80 9546.60


14.05 Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in Table 500-
39, prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine grained hard
stone chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of 10
cm center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg. C,
protruding 1 mm to 4 mm over mastic surface, all complete
as per clause 516.

sqm 1247.50 1247.50 1247.50


Construction of precast RCC railing of M30 Grade, aggregate
size not exceeding 12 mm, true to line and grade, tolerance
of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
14.06 complete as per approved drawings and technical
specifications.

metre 1695.20 1697.00 1701.60


Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
14.07 complete as per approved drawings and technical
specifications.

metre 1640.40 1642.20 1646.60


Providing, fitting and fixing mild steel railing complete as per
14.08 drawing and Technical Specification

metre 3048.50 3048.50 3048.50


Drainage Spouts complete as per drawing and Technical
14.09 specification
no. 4869.60 4869.60 4869.60
PCC M15 Grade leveling course below approach slab
14.10 complete as per drawing and Technical specification

PCC Grade M15 using batching plant & Concrete


Case I pump
cum 3161.49 3169.73 3194.98
PCC Grade M15 using batching plant & manual
Case II placing
cum 3365.35 3373.59 3398.78
Reinforced cement concrete approach slab including
14.11 reinforcement and formwork complete as per drawing and
Technical specification
cum 7867.50 7878.60 7910.10
Providing anti-corrosive treatment to HYSD reinforcement
14.12 with Fusion Bonded Epoxy Coating (FBEC)

To be taken as per the prevailing market rates. MT


14.13 Precast - pretensioned Girders
Providing, precasting, transportation and placing in position
precast pretensioned concrete girders as per drawing and
technical specifications

cum #VALUE! #VALUE! #VALUE!


Providing and fixing Helical pipes in voided concrete slabs
14.14
m #VALUE! #VALUE! #VALUE!
14.15 Crash Barriers for Bridge
Provision of an Reinforced cement concrete crash barrier at
the bridge decks& approaches to bridge structures
constructed with Rein forced Cement Concrete With HYSD
reinforcement confirming MoRT&H Specification and as per
details given IRC-5 including dowel bars ,expansion joints
filled with pre-moulded asphalt filler board etc.. and
approved drawing and at locations directed by the
Engineer ,all as specified .

Crash Barriers for Bridge (Height 950 mm) as per detais


A given IRC-5 (fig.-1) (Area -0.254 sqm. For 1 meter length )

metre 3117.70 3121.40 3131.60


Crash Barriers for Bridge (Height 1100 mm) as per detais
B given IRC-5 (fig.-2 ) (Area -0.298 sqm. For 1 meter length )

metre 3646.20 3650.50 3662.40


Crash Barriers for Bridge (Height 1550 mm) as per detais
C given IRC-5 (fig.-3 ) (Sueface Area 0.514 sqm. For 1 meter
length )
metre 6285.70 6293.20 6313.70
14.16 Painting on concrete surface
Providing and applying 2 coats of water based cement paint
to unplastered concrete surface after cleaning the surface of
dirt, dust, oil, grease, efflorescence and applying paint @ of 1
litre for 2 sqm.
sqm 100.60 100.60 100.60
14.17 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in
(i) expansion joint complete as per drawing & Technical
Specification.
metre 4570.50 4570.50 4570.50
Providing & fixing 20 mm thick compressible fibre board in
(ii) expansion joint complete as per drawing & Technical
Specification.
metre 314.80 314.80 314.80
Providing and fixing in position 20 mm thick premoulded joint
filler in expansion joint for fixed ends of simply supported
spans not exceeding 10 m to cater for a horizontal movement
upto 20 mm, covered with sealant complete as per drawing
(iii) and technical specifications.

metre 391.60 391.60 391.60


Providing and filling joint sealing compound as per drawings
(iv) and technical specifications with coarse sand and 6 per cent
bitumen by weight
metre 26.00 26.00 26.00
14.18 Asphaltic Plug joint
Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in traffic direction), covered
with a closure plate of 200mm x 6mm of weldable structural
steel conforming to IS: 2062, asphaltic plug to consist of
polymer modified bitumen binder, carefully selected single
size aggregate of 12.5 mm nominal size and a heat resistant
foam caulking/backer rod, all as per approved drawings and
specifications.

metre 381226.80 381226.80 381226.80


14.19 Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab steel expansion
joint, catering to right or skew (less than 20 deg., moderately
curved with maximum horizontal movement upto 50 mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the
manufacturer's instructions for installation and clause 2605 of
MoRT&H specifications for road & bridge works.

metre 37757.50 37757.50 37757.50


14.20 Compression Seal Joint
Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
fixed into the joint gap with special adhesive binder to cater
for a horizontal movement upto 40 mm and vertical
movement of 3 mm.

metre #VALUE! #VALUE! #VALUE!


14.21 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.

metre 11741.00 11741.00 11741.00


14.22 Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal expansion
joint including anchorage catering to a horizontal movement
beyond 70 mm and upto 140mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

metre 39621.90 39621.90 39621.90


14.23 Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal expansion
joint catering to a horizontal movement beyond 140mm and
upto 210mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

metre 39634.50 39634.50 39634.50


Painting with synthetic enamel paint bridge No. and span
14.24 arrangements
Painting two coat after filling the surface with synthetic
enamel paint bridge No. and span arrangements as per
direction by Enginner .
no. 168.40 168.40 168.40
Bipolar corrosion inhibiting admixture in concrete for
14.25 protection of reinforced steel from corrosion

Admix polydentate ,bipolar ,migratory, intergal non nitrate


base concrete penetrating corrosion inhibiting admixture at
dosage of 3Kg per cu.m. of concrete as per manufactures
specification. Inhibitor should conforms to following-

cum 631.70 631.70 631.70


Providing structural steel for super- structure complete as
14.26 per drawing and technical specifications

MT 111695.20 111695.20 111695.20


CHAPTER-14
BRIDGE SUPERSTRUCUTRE
Quantity as per peroject catego
Sr No Ref. to M. Description Unit
Large
14.01 1500 &1600
1700
Furnishing and Placing Reinforced/ Prestressed
cement concrete in super-structure as per
drawing and Technical Specification
14.01A A RCC Grade M20
Using Batching Plant ,Transit Mixer and Concrete
Pump
Case I
Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.05 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1-lead in tonne-km 300xL1
kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour

For formwork and staging add the following

14.01A (i) For solid slab super-structure, 20-30 per cent of


(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 20 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01A (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01A (r) Height above 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 30 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01A (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 30 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01A (ii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 35 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 B Case II RCC Grade M25 Using Batching Plant, Transit


Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.07 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1-lead in tonne-km 300xL1
kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour
(iii)6 KL capacity hour
For formwork and staging add the following

14.01B (i) For solid slab super-structure, 20-30 per cent of


(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 20 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01B(i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01B (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 30 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)
e) Overheadcharges @ on (a+b+c+d) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01B(ii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 30 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01B (ii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 35 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 C RCC Grade M30 Using Batching Plant,Transite


14.01C Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.09 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1-lead in tonne-km 300xL1
kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following

14.01C (i) For solid slab super-structure, 20-30 per cent of


(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 20 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01C(i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01C(i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 30 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 25 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01C(ii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 30 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01C(ii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 35 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D RCC/PSC Grade M35


caseII Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.11 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following

14.01 D (i) For solid slab super-structure, 18-28 per cent of


(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 18 percent of (a+b+c)

e) Overheadcharges @ on( a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 23 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 28 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 23 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(ii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 28 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(ii) (r ) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 33 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D (iii) For box girder and balanced cantilever ,38-58


percent of cost concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d)Formwork and staging 38 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(iii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 48 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 D(iii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 58 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 E RCC/PSC Grade M-40


14.01E Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.12 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truck and agitator
For transportation ( 6 cum Capacity ),L1-lead in tonne-km 300xL1
kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following

14.01E (i) For solid slab/voided slab super-structure, 18-28


per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d)Formwork and staging 18 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(i) (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 23 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(i) (r) Height above 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 28 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d)Formwork and staging 23 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(ii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 28 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(ii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 33 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E (iii) For cast-in situ box girder,segmental construction


and balanced cantilever ,38-58 percent of cost of
concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 38 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(iii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 48 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01E(iii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 58 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 F RCC/PSC Grade M-45


Unit = 1cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.13 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truck and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following

14.01F (i) For solid slab / voided slab super-structure, 16-26


per cent of cost of concrete (a+b+c)

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 16 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F(i) (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d)Formwork and staging 21 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
14.01F(i) (r) Height above 10m
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 26 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F (ii) For T-beam & slab including launching of precast


girders by launching truss up to 40 m span, 21-31
per cent cost of concrete .

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 21 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F(ii) (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 26 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F(ii) (r) Height above 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 31 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
14.01F (iii) For cast-in situ box girder,segmental construction
and balanced cantilever ,36-56 percent of cost of
concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d)Formwork and staging 36 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F(iii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d)Formwork and staging 46 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01F(iii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 56 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 G PSC Grade M-50


Unit = cum
Taking output = 120 cum
a) Material
Per cum Basic cost (Rate taken from sub cum 120.000
-analysis -21.14 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truck and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following:

14.01G (i) For cast-in-situ box girder, segmental construction


and balanced cantilever, 35-55 per cent of cost of
concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 35 per cent of
(a+b+c)
e) Overheadcharges @ on (a+b+c+d) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01G (q) Height 5m to 10m


(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 45 per cent of
(a+b+c)
e) Overhead charges @ on (a+b+c+d) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
14.01G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 55 per cent of
(a+b+c)
e) Overhead charges @ on (a+b+c+d) (@ 20%)
f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 H PSC Grade M- 55


Unit = 1 cum
Taking output = 120 cum
a) Material
Per cum Basic Cost (Rate taken from sub cum 120.000
-analysis -21.15 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following:

14.01H (i) For cast-in-situ box girder, segmental construction


and balanced cantilever, 35-55 per cent of cost of
concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 35 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (q) Height 5m to 10m


(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 45 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (r) Height above 10m


(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 55 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

Note 1. Cement provided for various components of the


super structure is for estimating purpose .

2. Actual quantity of cement will be as per


approved mix design. Similarly, the provision for
coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the
mix design.

3. The items like needle and surface vibrators are


part of minor T & P which is already covered
under the overhead charges. As such these items
have not been added separately in the rate
analysis.
14.01 I PSC Grade M- 60
Unit = 1 cum
Taking output = 120 cum
a) Material
Per cum Basic Cost (Rate taken from sub cum 120.000
-analysis -21.16 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truk and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following:

14.01H (i) For cast-in-situ box girder, segmental construction


and balanced cantilever, 35-55 per cent of cost of
concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 35 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (i) (q) Height 5m to 10m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 45 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@20%)


f) Contractor's profit @ on (a+b+c+d+e) (@10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery


(a+b+c) for 120 cum
d) Formwork and staging 55 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01 J PSC Grade M- 65


Unit = 1 cum
Taking output = 120 cum
a) Material
Per cum Basic Cost (Rate taken from sub cum 120.000
-analysis -21.17 )
Water for curing kl 63.000
b) Labour
For pouring and placing
Mate day 0.192
Mason day 1.500
Mazdoor day 3.300
c) Machinery
Transit truck and agitator
For transportation ( 6 cum Capacity ),L1- tonne-km 300xL1
lead in kilometer
For unloading hour 2.600
Hydraulic Boom placer pump hour 2.600
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.438xL1+2.6


25
(ii)12 KL capacity hour

(iii)6 KL capacity hour


For formwork and staging add the following:

14.01 (i) For cast-in-situ box girder, segmental construction


and balanced cantilever, 35-55 per cent of cost of
concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 35 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (q) Height 5m to 10m


(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 45 percent of (a+b+c)

e) Overheadcharges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120

14.01H (r) Height above 10m


(i)
Basic Cost of Labour, Material & Machinery
(a+b+c) for 120 cum
d) Formwork and staging 55 percent of (a+b+c)

e) Overhead charges @ on (a+b+c+d) (@ 20%)


f) Contractor's profit @ on (a+b+c+d+e) (@ 10%)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
Note 1. Cement provided for various components of the
super structure is for estimating purpose only.
Actual quantity of cement will be as per approved
mix design. Similarly, the provision for coarse and
fine aggregates is for estimating purpose and the
exact quantity shall be as per the mix design.

2. The items like needle and surface vibrators are


part of minor T & P which is already covered
under the overhead charges. As such these items
have not been added separately in the rate
analysis.

14.02 1600 Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as per
drawing and technical specifications

Unit = MT
Taking output = 8 MT
a) Material
HYSD bars including 5 per cent overlaps tonne 8.400
and wastage
Binding wire Kg 48.000
b) Labour for straightening, cutting, bending,
shifting to site , tying and placing in position

Mate day 0.160


Blacksmith day 1.000
Mazdoor day 3.000
C) Machinery
Cutting Machine hour 8.000
Bending Machine hour 8.000
Electric generator 15 KVA hour 8.000
Tipper
Tipper for Transportation
(i) 18 cum capacity t-km 8xL1
(ii) 14 cum capacity t-km
(iii) 10 cum capacity t-km
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000
(ii) 14 cum capacity hour
(iii) 10 cum capacity hour
Light weight Crane
At cutting bending yard hour 2.000
At site hour 2.000
d) Overhead charges @ on (a+b+c) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%)
Cost for 8 MT (a+b+c+d+e)
Rate for per MT(a+b+c+d+e) /8

14.03 1800 High tensile steel wires/strands including all


accessories for stressing, stressing operations
and grouting complete as per drawing and
Technical Specifications

Unit = MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable
(weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per tonne 0.385
cent for wastage and extra length for
jacking

Sheathing duct ID 66 mm along with 5 per metre 42.000


cent extra length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing each 2.000
plate, permanent wedges etc
Cement for grouting including 3 per cent tonne 0.125
wastage @ 3.00 kg/m = 3 x 1.03 x 40 =
123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for


Spacers, Insulation tape and
miscellaneous items

b) Labour
i) For making and fixing cables, anchorages

Mate day 0.160


Blacksmith day 1.000
Mazdoor day 3.000
ii) For prestressing
Mate/Supervisor day 0.050
Prestressing operator / Fitter day 0.250
Mazdoor day 1.000
iii) For grouting
Mate/Supervisor day 0.050
Mason day 0.250
Mazdoor day 1.000
c) Machinery
Stressing jack with pump hour 2.500
Grouting pump with agitator hour 1.000
Generator 33 KVA. hour 3.500
d) Overhead charges @ on (a+b+c) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%)
Cost for 0.377 MT (a+b+c+d +e)
Rate per MT = (a+b+c+d+e)/0.377

14.04 2702 Providing and laying Cement concrete wearing


coat M-30 grade including reinforcement
complete as per drawing and Technical
Specifications

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer cum 1.000
relevant item of concrete in Item 14.01
excluding formwork

HYSD bar reinforcement Rate as per item tonne 0.075


No 14.02(Excluding OH & CP)

b) Labour
Mazdoor for cleaning deck slab concrete day 0.150
surface.
c) Overheadcharges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Rate per cum (a+b+c+d)

14.05 516 & 2702 Mastic Asphalt


Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding
prime coat with paving grade bitumen meeting the
requirements given in Table 500-39, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including
providing antiskid surface with bitumen precoated
fine grained hard stone chipping of 9.5 mm
nominal size at the rate of 0.005cum per 10 sqm
and at an approximate spacing of 10 cm center to
center in both directions, pressed into surface
when the temperature of surfaces not less than
100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 516.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.

a) Labour
Mate day 0.490
Mazdoor day 11.000
Mazdoor (Skilled) day 1.250
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060

Air compressor 250 cfm hour 0.060


Mastic cooker 1 tonne capacity hour 6.000
Bitumen boiler 1500 litres capacity hour 6.000
Tractor for towing and positioning of mastic hour 1.000
cooker and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40
per cent .
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design
done by CRRI for a specific case)
i) Bitumen 80/100 or60 /70 or 30/40 @ tonne 0.204
10.2 per cent by weight of mix. 2 x
10.2/100 = 0.204

ii) Crusher stone dust @ 31.9 per cent by cum 0.390


weight of mix = 2 x 31.9/100 = 0.638
tonnes = 0.638/1.625 = 0.39

iii) Lime stone dust filler with calcium tonne 0.360


carbonate content not less than 80 per cent
by weight @ 17.92 per cent by weight of
mix = 2 x 17.92/100 = 0.36

iv) Coarse aggregates 9.5 mm to 3.35 mm cum 0.550


size @ 40 per cent by weight of mix = 2 x
40/100 = 0.8 MT = 0.8/1.456 = 0.55

v) Pre-coated stone chips of 9.5 mm cum 0.036


nominal size for skid resistance =
72.46x0.005/10 = 0.036

vi) Bitumen for coating of chips @ 2 per kg 1.050


cent by weight = 0.036 x 1.456 x 2/100 =
0.001048MT = 1.05kg

d) Overhead charges @ on (a+b+c) (@ 20%)


e) Contractor's profit @ on ( a+b+c+d) (@ 10%)
Cost for 72.46 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/72.46

Note 1.The rates for 6 mm or any other thickness may


be worked out on pro-data basis.
2. Where tack coat is required to be provided
before laying mastic asphalt, the same is required
to be measured and paid separately.

3.The quantities of binder, filler and aggregates


are for estimating purpose. Exact quantities shall
be as per mix design.

4.This rate analysis is based on design made by


CRRI for a specific case and is meant for
estimating purposes only. Actual design is
required to be done for each case.

5.The quantity of bitumen works out 17 per cent


of the mastic asphalt blocks without aggregates
and falls within the standards laid down by
MoRT&H Specifications.
14.06 2703, 1500, Construction of precast RCC railing of M30
1600 & 1700 Grade, aggregate size not exceeding 12 mm, true
to line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for
expansion, complete as per approved drawings
and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m
span= 48 m.
a) Material
Cement concrete M30 Grade refer cum 4.092
relevent item of concrete in Item 14.01 (C)
by using batching plant, excluding form
work i.e. per cum basic cost (a+b+c)
No. of vertical posts =(12+2)2=28 Nos.,
External area of vertical posts=0.25x0.275
=0.069sqm, Concrete in Vertical posts
=0.069x28 =1.932 cum, Hand rail in 3 tiers
=3x24= 72 m, External area =0.170x0.175
=0.03 sqm, Concrete in hand rails = 0.03 x
72 = 2.16 cum, Total Concrete = 1.932 +
2.16 = 4.092 cum.

Add 5 percent of above cost for form work


for casting in casting yard
HYSD bar tonne 0.865
reinforcement Rate as per item No 14.02

Add 5 per cent of (a) for handling and fixing


of precast panels in position
b) Overhead charges @ on (a) (@ 20%)
c) Contractor's profit @ on ( a+b) (@ 10%)
Rate for 48 m (a+b+c)
Rate per metre (a+b+c) / 48

Note 1. Quantities of material have been adopted from


standard plans of MoRTH vide drawing no.
SD/202.

2. 48 m length is the total linear length adding


both sides of 24 m span.
14.07 2703, 1500, Construction of RCC railing of M30 Grade in-situ
1600 & 1700 with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical RCC post not to
exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for
expansion, complete as per approved drawings
and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m
span= 48 m.
a) Material
Cement concrete M30 Grade refer cum 4.092
relevent item of concrete in Item 14.01 (C)
by using batching plant, excluding form
work i.e. per cum basic cost (a+b+c) No. of
vertical posts = (12 + 2)2 = 28 Nos.,
External area of vertical post 0.25x0.275 =
0.069sqm, Concrete in verticle posts =
0.069 x 28 = 1.932 cum, Hand rail in 3 tiers
= 3 x 24 = 72 m, External area = 0.170 x
0.175 = 0.03 sqm, Concrete in hand rails =
0.03 x 72 = 2.16 cum, Total Concrete =
1.932 + 2.16 = 4.092 cum.

Add 12 per cent of above cost for form


work.
HYSD bar reinforcement Rate as per item tonne 0.865
No 14.02 (Excluding OH & CP)

b) Overhead charges @ on (a) (@ 20%)


c) Contractor's profit @ on (a+b) (@ 10%)
Rate for 48 m (a+b+c)
Rate per metre (a+b+c) / 48

Note 1. Quantities of material have been calculated as


per above assumption .
2. 48 m length is the total linear length adding
both sides of 24 m span.
14.08 2703.2 & Providing, fitting and fixing mild steel railing
1900 complete as per drawing and Technical
Specification

Unit = RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.946
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.012
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.180
4) MS bolts, nuts and washers tonne 0.150
Add @ 5 per cent of cost of material for
painting one shop coat with red oxide
primer and three coats of synthetic enamel
paint and consumables to safeguard
against weathering and corrosion.

Add for cost of concrete for fixing vertical


posts in the performed recess @ 1 per cent
of cost of material.

Add for electricity charges, welding and


drilling equipment, electrodes and other
consumables @ 1 per cent of cost of
material.

b) Labour
Mate day 2.800
Mazdoor (Skilled) day 30.000
Mazdoor day 40.000
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on(a+b+c) (@ 10%)
Cost for 100 m steel railing = (a+b+c+d)
Rate per metre (a+b+c+d) /100

14.09 2705 Drainage Spouts complete as per drawing and


Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per Kg 4.000
cent wastage
GI pipe 100mm dia metre 6.000
GI bolt 10 mm Dia each 6.000
Galvanised MS flat clamp each 2.000
b) Labour
For fabrication
Mate day 0.002
Skilled (Blacksmith, welder etc.) day 0.020
Mazdoor day 0.020
For fixing in position
Mate day 0.008
Mason day 0.010
Mazdoor day 0.200
Add @ 5 per cent of cost of material and
labour for electrodes, cutting gas, sealant,
anti-corrosive bituminous paint, mild steel
grating etc.

c) Overhead charges @ on (a+b) (@ 20%)


d) Contractor's profit @ on(a+b+c) (@ 10%)
Rate per No. = (a+b+c+d)

Note 1. In case of viaducts in urban areas, the drainage


spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains
provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe


shall be provided to ensure that there is no
splashing of water from the drainage spout on the
structure.

14.10 2700 PCC M15 Grade leveling course below approach


slab complete as per drawing and Technical
specification

Unit = 1 cum
Taking output = 1 cum
Material
Case I PCC Grade M15 using batching plant &
Concrete pump
a) Concrete, Rate as per item No. 12.08 cum 1.000
(A) excluding formworks

Concrete, Rate as per item No. 12.08 (A) cum


excluding formworks

Concrete, Rate as per item No. 12.08 (A) cum


excluding formworks

b) Overhead charges @ on (a) (@ 20%)


c) Contractor profit @ on (a+b) (@ 10%)
Rate per cum= (a+b+c)
Case II PCC Grade M15 using batching plant &
manual placing
a) Concrete, Rate as per item No. 12.08 cum 1.000
(A) excluding formworks

Concrete, Rate as per item No. 12.08 (A) cum


excluding formworks

Concrete, Rate as per item No. 12.08 (A) cum


excluding formworks

b) Overhead charges @ on (a) (@ 20%)


c) Contractor profit @ on (a+b) (@ 10%)
Rate per cum= (a+b+c)

14.11 1500,1600,1 Reinforced cement concrete approach slab


700 & 2704 including reinforcement and formwork complete
as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer cum 1.000
relevant item of concrete in item
12.08(G)by using batching plant, excluding
formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)

( Refer relevant item of concrete in item


No. 12.8 (G) except that form work may be
added at the rate of 2 per cent of cost
against 3.5 per cent provided in the
foundation concrete.

HYSD bar tonne 0.050


reinforcement Rate as per item No
14.02(Excluding OH & CP)

b) Overhead charges @ on (a) (@ 20%)


c) Contractor's profit @ on (a+b) (@ 10%)
Rate per cum (a+b+c)

Note The grade of reinforced cement concrete may be


adopted as M30 for severe conditions and M25
for moderate conditions.
14.12 1600 Providing anti-corrosive treatment to HYSD
reinforcement with Fusion Bonded Epoxy Coating
(FBEC)

Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.

Note Contractors generally do not have expertise for


this item . The job is therefore, got done from
specialised firms who have the expertise in the
field of construction chemicals. The prevailing rate
in the market is required to be ascertained from
the market and added in the cost estimate. HYSD
reinforcement with Fusion Bonded Epoxy
Coating(FBEC) as per MoRT&H circular /
specification.

14.13 1800 & 2300 Precast - pretensioned Girders

Providing, precasting, transportation and placing


in position precast pretensioned concrete girders
as per drawing and technical specifications

Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Per Cum Basic Cost (Rate as in sub cum 1.000
-analysis )
Water for curing KL 0.525
HYSD steel . tonne 0.100
HT strand with 5 per cent as wastage and tonne 0.060
extra length for anchoring
LDO for steam curing Litre 37.000
Add consumables such as binding wire,
foam, packing tape, shuttering oil, HDPE
pipe for unbonding of strand, bolt & nuts
etc @ 1 per cent of material cost

b) Labour
(i) Cutting, bending, making reinforcement cage,
placing in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate day 0.070
Mazdoor (Skilled) day 0.350
Mazdoor day 1.400
(ii) Cable cutting and threading in position
including binding by insulation tape with HDPE
pipes etc., prestessing and cutting of extra length
of HT strand after de-stressing.

Taking quantity of HT strand 60 Kg/cum


Mate day 0.026
Mazdoor (Skilled) day 0.140
Mazdoor day 0.500
(iii) Erection and dismantling of shuttering

Taking shuttering area 10 sqm/cum of concrete

Mate day 0.120


Mazdoor (Skilled) day 1.000
Mazdoor day 2.000
(iv) Concreting by Batching plant and stationary
concrete pump
Mate day 0.026
Mazdoor (Skilled) day 0.050
Mazdoor day 0.600
(v) Steam curing and manual curing
Mate day 0.014
Mazdoor day 0.350
(vi) Handling of precast girder, stacking in
stockyard and again loading in trailor

Mate day 0.010


Mazdoor day 0.250
(vii) Placement of girders in position over pier
caps including placement of sand jacks, channel,
levelling etc.

Mate day 0.012


Mazdoor (Skilled) day 0.060
Mazdoor day 0.240
c) Machinery
i) At casting yard Transit truck agitator
For transportation (6 cum capacity) ,L1 -lead in tonne-km 2.5xL
Kilometer
For unloading hour 0.022
Hydraulic Boom placer pump hour 0.022
Water tanker (speed @ 20km /hr and return
speed @ 30 km /hr and 30 mins for uploading )

(i)16 KL capacity hour 0.004XL1+0.


022
(ii)12 KL capacity hour

(iii)6 KL capacity hour

Crane 35 tonne capacity hour 0.100


Trailer 30 tonne capacity hour 0.100
ii) For transportation and placement at site

Crane 35 tonne capacity hour 0.150


Trailer 30 tonne capacity for transporting to tonne.km 2.5xL
site.
(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.150

Cost of formwork, steam curing


arrangement, pretensioning arrangement
etc @ 5 per cent of cost material, labour
and machinery

d) Overhead charges @ on (a+b+c)


e) Contractor's profit @ on (a+b+c+d)
Rate per cum = (a+b+c+d+e)

14.14 1700 & 1800 Providing and fixing Helical pipes in voided
concrete slabs
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.000
Tie rods 20mm diameter each 1.000
Consumables for sealing joints etc.@ 5 per cent
of cost of material
b) Labour
Mate day 0.010
Fitter day 0.050
Mazdoor day 0.200
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Rate per m = (a+b+c+d)

14.15 800 Crash Barriers for Bridge


Provision of an Reinforced cement concrete crash
barrier at the bridge decks& approaches to bridge
structures constructed with Rein forced Cement
Concrete With HYSD reinforcement confirming
MoRT&H Specification and as per details given
IRC-5 including dowel bars ,expansion joints filled
with pre-moulded asphalt filler board etc.. and
approved drawing and at locations directed by
the Engineer ,all as specified .

Unit = Linear meter


Taking output 10 m
A Crash Barriers for Bridge (Height 950 mm) as per
detais given IRC-5 (fig.-1) (Area -0.254 sqm. For
1 meter length )

a) M 40 grade concrete &HYSD steel


reinforcment
M 40 grade concrete cum 2.540
(Area -0.254 Sqm. /Meter ) (Rate taken
from item No. 14.01 E (p) including OH&CP)

HYSD steel reinforcement including dowel bars tonne 0.229


(Rate taken from item No. 14.02 including OH &
CP)

b) Labour
Mate day 0.040
Mazdoor day 1.000
c) Material
Pre-moulded ashphalt filler board sqm 0.265
d) Overhead charges @ on (b+c) (@ 20%)
e) Contractor's profit @ on (b+c+d) (@ 10%)
Cost for 10 metre =a+b+c+d+e
Rate per metre =(a+b+c+d+e ) /10

14.15 B Crash Barriers for Bridge (Height 1100 mm) as


per detais given IRC-5 (fig.-2 ) (Area -0.298 sqm.
For 1 meter length )

a) M 40 grade concrete &HYSD steel


reinforcment
M 40 grade concrete cum 2.980
(Area 0.298 Sqm. /Meter ) (Rate taken
from item No. 14.01 E (p) including OH&CP)

HYSD steel reinforcement including dowel bars tonne 0.268


(Rate taken from item No. 14.02 including OH &
CP)

b) Labour
Mate day 0.040
Mazdoor day 1.000
c) Material
Pre-moulded ashphalt filler board sqm 0.310
d) Overhead charges @ on (b+c) (@ 20%)
e) Contractor's profit @ on (b+c+d) (@ 10%)
Cost for 10 metre =a+b+c+d+e
Rate per metre =(a+b+c+d+e ) /10

14.5 c Crash Barriers for Bridge (Height 1550 mm) as


per detais given IRC-5 (fig.-3 ) (Sueface Area
0.514 sqm. For 1 meter length )

a) M 40 grade concrete &HYSD steel


reinforcment
M 40 grade concrete cum 5.140
(Area 0.514 Sqm. /Meter ) (Rate taken
from item No. 14.01 E (p) including OH&CP)

HYSD steel reinforcement including dowel bars tonne 0.463


(Rate taken from item No. 14.02 including OH &
CP)

b) Labour
Mate day 0.060
Mazdoor day 1.500
c) Material
Premoulded ashphalt filler board sqm 0.540
d) Overhead charges @ on (b+c) (@ 20%)
e) Contractor's profit @ (b+c+d) (@ 10%)
Cost for 10 metre =a+b+c+d+e
Rate per metre =(a+b+c+d+e ) /10

The rate analysis for semi - rigid crash barrier


with metal beam and flexible crash barrier with
wire ropes have been made and included in
Note chapter-8 on Traffic and Transportation.
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
after cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2
sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.020
Painter day 0.250
Mazdoor (Skilled) day 0.250
b) Material
Water based paint of approved quality for Litres 5.000
cement concrete surface
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 10 sqm =a+b+c+d
Rate per sqm =(a+b+c+d) /10

14.17 2604 Filler joint


(i) Providing & fixing 2 mm thick corrugated copper
plate in expansion joint complete as per drawing
& Technical Specification.

Unit = Running meter


Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.040
Mazdoor day 0.500
Mazdoor (Skilled) day 0.500
b) Material
Copper plate - 12m long x 250 mm wide kg 55.000
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say =
55 kg.
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d ) /12
14.17 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing
& Technical Specification.

Unit = Running meter


Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008
Mazdoor day 0.100
Mazdoor (Skilled) day 0.100
b) Material
20 mm thick compressible fibre board 12 m sqm 3.000
long x 25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d) /12

14.17 (iii) Providing and fixing in position 20 mm thick


premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10
m to cater for a horizontal movement upto 20 mm,
covered with sealant complete as per drawing
and technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.012
Mazdoor day 0.200
Mazdoor (Skilled) day 0.100
b) Material
Pre-moulded joint filler 12 m long,20 mm sqm 3.600
thick and 300 mm deep.
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d ) /12
14.17 (iv) Providing and filling joint sealing compound as
per drawings and technical specifications with
coarse sand and 6 per cent bitumen by weight

Unit = Running meter


Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess

a) Labour
Mate day 0.024
Mazdoor day 0.500
Mazdoor (Skilled) day 0.100
b) Material
Sand cum 0.012
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen tonne 0.001
16.8 x 0.06 = 1 kg
c) Overhead charges @ on (a+b) (@ 20%)
d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d) /12

Note For arriving at the final rate of filler joints per m

length and per cm depth of joint filling compound,

the rates at Sl. No. i), ii), iii) & iv) shall be added

14.18 2608 Asphaltic Plug joint


Providing and laying of asphaltic plug joint to
provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint varying
from 75 mm to 100 mm, width varying from 500
mm to 750 mm (in traffic direction), covered with a
closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic
plug to consist of polymer modified bitumen
binder, carefully selected single size aggregate of
12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings
and specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.052
Mazdoor day 1.000
Mazdoor (Skilled) day 0.300
b) Material
Crushed stone aggregate 12.5 mm nominal cum 0.750
size
Polymer modified bitumen kg 77.500
Galvanised structural steel plate 200 mm kg 113.000
wide,6 mm thick, 12 m long (2.4 sqm) @
47.10 kg/sqm including 5 per cent wastage

Add 1 per cent for welding and foam


caulking/backer rod and other incidentals.

c) Machinery
Mastic cooker 1 tonne capacity hour 1.000
Smooth 3-wheeled steel roller 8-10 hour 0.500
capacity
d) Overhead charges @ on (a+b+c) (@ 20%)
e) Contractor's profit @ on (a+b+c+d) (@ 10%)
Cost for 12 m asphalt plug joint =a+b+c+d +e

Rate per m =(a+b+c+d+e) /12


Note The nominal size of aggregates shall be 12.5 mm
for depth of joint upto 75 mm and 20 mm for joints
of depth more than 75 mm.

14.19 2605 Elastomeric Slab Steel Expansion Joint


Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less
than 20 deg., moderately curved with maximum
horizontal movement upto 50 mm, complete as
per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and
clause 2605 of MoRT&H specifications for road &
bridge works.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.060
Mazdoor day 1.000
Mazdoor (Skilled) day 0.500
b) Material
Supply of elastomeric slab seal expansion joint metre 12.000
assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II), complete as per
approved drawings and standard specification
conforming to clause 2605 of MoRT&H
Specification

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.

c) Overhead charges @ on (a+b) (@ 20%)


d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d ) /12

14.20 2600 Compression Seal Joint


Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges
of the joint gap suitably anchored to the deck
concrete and a preformed chloroprene elastomer
or closed cell foam joint sealer compressed and
fixed into the joint gap with special adhesive
binder to cater for a horizontal movement upto 40
mm and vertical movement of 3 mm.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.036
Mazdoor day 0.600
Mazdoor (Skilled) day 0.300
b) Material
1. Galvanised angle sections 100mm x kg 446.000
100mm of 12mm thickness weldable
structural steel as per IS: 2062, 2 nos. of
12 m length each @ 17.7 kg/m and 5 per
cent wastage.

Add 5 per cent of cost of above for


structural steel for anchorage, welding and
other incidentals.

Preformed continuous chloroprene metre 12.000


elastomer or closed cell foam sealing
element with high tear strength, vulcanised
in a single operation for the full length of a
joint to ensure water tightness.

Add 1 per cent of cost of sealing element


for lubricant-cum-adhesive and other
consumables.

c) Overhead charges @ on on (a+b) (@ 20%)


d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d ) /12

Note 1. The installation shall be done by the


manufacturer or his authorised representative to
the satisfaction of the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in
this analysis as the same is catered in the
quantities of RCC deck.

3. The anchoring bars of the expansion joint


assembly shall be welded to the main
reinforcement of the deck.

14.21 2607 Strip Seal Expansion Joint


Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto
70 mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.050
Mazdoor day 1.000
Mazdoor (Skilled) day 0.250
b) Material
Supply of complete assembly of strip seal metre 12.000
expansion joint comprising of edge beams,
anchorage, strip seal element and complete
accessories as per approved specifications and
drawings.

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals

c) Overhead charges @ on (a+b) (@ 20%)


d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c+d
Rate per m =(a+b+c+d ) /12

Note 1. The installation shall be done by the


manufacturer or his authorised representative to
the satisfaction of the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in
this analysis as the same is catered in the
quantities of RCC deck.

14.22 2600 Modular Strip / Box Seal Joint


Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto
140mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.056
Mazdoor day 1.000
Mazdoor (Skilled) day 0.400
b) Material
Supply of a modular strip/box seal joint assembly metre 12.000
comprising of edge beams, central beam,2
modules chloroprene seal, anchorage elements,
support and control system, all steel sections
protected against corrosion and installed by the
manufacturer or his authorised representative.

c) Overhead charges @ on (a+b) (@ 20%)


d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 12 m Modular strip/ box seal joint
=a+b+c+d
Rate per m =(a+b+c+d ) /12

Note 1. The installation shall be done by the


manufacturer or his authorised representative to
the satisfaction of the Engineer.

2. The concreting for joining the expansion joint


assembly with the deck has not been included in
this analysis as the same is catered in the
quantities of RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main
reinforcement of the deck.

14.23 2600 Modular Strip / Box Seal Joint


Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as
per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.070
Mazdoor day 1.250
Mazdoor (Skilled) day 0.500
b) Material
Supply of a modular box/box seal joint assembly metre 12.000
containing 3 modules/cells and comprising of
edge beams, two central beams, chloroprene
seal, anchorage elements, support and control
system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.

c) Overhead charges @on(a+b) (@ 20%)


d) Contractor's profit @on (a+b+c) (@ 10%)
Cost for 12 m =a+b+c +d
Rate per m =(a+b+c +d ) /12

Note 1. The installation shall be done by the


manufacturer or his authorised representative to
the satisfaction of the Engineer.

2. The concreting for joining the expansion joint


assembly with the deck has not been included in
this analysis as the same is catered in the
quantities of RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main
reinforcement of the deck.

14.24 Painting with synthetic enamel paint bridge No.


and span arrangements
Painting two coat after filling the surface with
synthetic enamel paint bridge No. and span
arrangements as per direction by Enginner .

Unit = Nos.
Taking output = 1 Nos
a) Labour
Mate day 0.006
Painter day 0.100
Mazdoor day 0.05
b) Material
Paint confirming to requirement of clause 803.3 Litre 0.300

Add for scaffolding @ 1 percent of labour cost


where required
Add @ 5 percent cost of labour and materials to
prepare the surface by filling minutes roughness
on the surface and priming the surface before
laying 2 coats of painting.

c) Overhead charges @ on (a+b) (@ 20%)


d) Contractor's profit @ on (a+b+c) (@ 10%)
Cost for 1 No. =a+b+c+d
Rate per Nos.=(a+b+c+d )

14.25 Suggestive Bipolar corrosion inhibiting admixture in concrete


for protection of reinforced steel from corrosion

Admix polydentate ,bipolar ,migratory, intergal


non nitrate base concrete penetrating corrosion
inhibiting admixture at dosage of 3Kg per cu.m. of
concrete as per manufactures specification.
Inhibitor should conforms to following-

i. ASTM G-109-2005-Long term corrosion test


resulting in a corrosion rate of zero coulombs.
ii JIS Z1535- Accelerated corrosion test showing
significant reduction in corrosion using the
admixture.

iii ASTM G1-Immersion test for 720 hrs


indicating rebar weight loss less than 5 mpy.

iv ASTM G3-Polarization test by Tafel test


indicating Rebar weight loss less than 5 mpy.

Unit =Cum
Taking output =100.000 cum
a) Material
Corrosion inhibiting Admixture @3 kg per cubic kg. 300.000
meter
b) Overhead charges @ on (a) (@ 20%)
c) Contractor's profit @ (a+b) (@ 10%)
Cost for 100 cum. =a+b+c
Rate per cum.=(a+b+c )/100

14.26 1700 Providing structural steel for super- structure


complete as per drawing and technical
specifications

Unit = MT
Taking output =17.135 MT
a) Material
Structural steel in plates ,angles, etc. including 5 Tonne 17.992
percent wastage
Nuts & bolts kg. 180.000
b) Labour
( for cutting, bending , marking holes ,joining,
welding, and erecting im position)
mate day 21.097
Filter day 77.108
Blacksmith day 77.108
Welder day 77.108
Painter Iclass day 32.385
Mazdoor day 263.708
Electrode, cutting gas and other consummables
@10 percent of cost of (a) above

c) Machinery
Mobile Hydraulic Crane 10 tonne capacity (for Hrs 68.540
fabrication)
Crane 35 tonne capacity (for Loading &Unloading Hrs 4.000
@1 hr for each operation )
Crane 35 tonne capacity (for Lifting and placing Hrs 4.000
in position @2 hr )
Trailer30 tonne capacity for transporting to site Hrs 4+L /15

Applying 2 coats primer before painting of Truss Lit 899.598


and Girder (42 sqm /tonne)
Painting of Truss and Girder Lit 899.598
Sundries @5% of the above (a,b,&c )
d) Overhead charges on (a+b+c) (@ 20%)
e) Contractor's profit on (a+b+c+d) (@ 10%)
Cost for 17.135MT =a+b+c+d+e
Rate for per MT.=(a+b+c +d+e) /17.135
CHAPTER-14
IDGE SUPERSTRUCUTRE
Quantity as per peroject category Rate (Rs) Amount Input_Ref
Medium Small Large Medium Small

120.000 120.000 2548.90 305868.00 305868.00 305868.00 21.05

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001

0.583xL1+3.50 1252.00 5111.92 PM11002


0
1.167xL1+7.0 907.00 7407.47 PM11003
00

336420.26 337164.34 339459.89


67284.05 67432.87 67891.98
(@ 20%) (@ 20%) 80740.86 80919.44 81470.37
(@ 10%) (@ 10%) 48444.52 48551.66 48882.22
532889.69 534068.31 537704.46
4440.75 4450.57 4480.87
Say 4440.70 4450.60 4480.90

336420.26 337164.34 339459.89

84105.06 84291.08 84864.97


(@ 20%) (@ 20%) 84105.06 84291.08 84864.97
(@ 10%) (@ 10%) 50463.04 50574.65 50918.98
555093.43 556321.15 560108.82
4625.78 4636.01 4667.57
Say 4625.80 4636.00 4667.60

336420.26 337164.34 339459.89

100926.08 101149.30 101837.97


(@ 20%) (@ 20%) 87469.27 87662.73 88259.57
(@ 10%) (@ 10%) 52481.56 52597.64 52955.74
577297.16 578574.00 582513.17
4810.81 4821.45 4854.28
Say 4810.80 4821.50 4854.30

336420.26 337164.34 339459.89

84105.06 84291.08 84864.97


(@ 20%) (@ 20%) 84105.06 84291.08 84864.97
(@ 10%) (@ 10%) 50463.04 50574.65 50918.98
555093.43 556321.15 560108.82
4625.78 4636.01 4667.57
Say 4625.80 4636.00 4667.60

336420.26 337164.34 339459.89


100926.08 101149.30 101837.97
(@ 20%) (@ 20%) 87469.27 87662.73 88259.57
(@ 10%) (@ 10%) 52481.56 52597.64 52955.74
577297.16 578574.00 582513.17
4810.81 4821.45 4854.28
Say 4810.80 4821.50 4854.30

336420.26 337164.34 339459.89

117747.09 118007.52 118810.96


(@ 20%) (@ 20%) 90833.47 91034.37 91654.17
(@ 10%) (@ 10%) 54500.08 54620.62 54992.50
599500.90 600826.85 604917.52
4995.84 5006.89 5040.98
Say 4995.80 5006.90 5041.00

120.000 120.000 2950.40 354048.00 354048.00 354048.00 21.07

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001

0.583xL1+3.5 1252.00 5111.92 PM11002


1.167xL1+7 907.00 7407.47 PM11003

384600.26 385344.34 387639.89

76920.05 77068.87 77527.98

(@ 20%) (@ 20%) 92304.06 92482.64 93033.57


(@ 10%) (@ 10%) 55382.44 55489.58 55820.14
609206.81 610385.43 614021.58
5076.72 5086.55 5116.85
Say 5076.70 5086.50 5116.80

384600.26 385344.34 387639.89

96150.06 96336.08 96909.97


(@ 20%) (@ 20%) 96150.06 96336.08 96909.97
(@ 10%) (@ 10%) 57690.04 57801.65 58145.98
634590.43 635818.15 639605.82
5288.25 5298.48 5330.05
Say 5288.30 5298.50 5330.00

384600.26 385344.34 387639.89

115380.08 115603.30 116291.97


(@ 20%) (@ 20%) 99996.07 100189.53 100786.37
(@ 10%) (@ 10%) 59997.64 60113.72 60471.82
659974.04 661250.88 665190.05
5499.78 5510.42 5543.25
Say 5499.80 5510.40 5543.30

384600.26 385344.34 387639.89

96150.06 96336.08 96909.97


(@ 20%) (@ 20%) 96150.06 96336.08 96909.97
(@ 10%) (@ 10%) 57690.04 57801.65 58145.98
634590.43 635818.15 639605.82
5288.25 5298.48 5330.05
Say 5288.30 5298.50 5330.00

384600.26 385344.34 387639.89

115380.08 115603.30 116291.97


(@ 20%) (@ 20%) 99996.07 100189.53 100786.37
(@ 10%) (@ 10%) 59997.64 60113.72 60471.82
659974.04 661250.88 665190.05
5499.78 5510.42 5543.25
Say 5499.80 5510.40 5543.30

384600.26 385344.34 387639.89

134610.09 134870.52 135673.96


(@ 20%) (@ 20%) 103842.07 104042.97 104662.77
(@ 10%) (@ 10%) 62305.24 62425.78 62797.66
685357.66 686683.61 690774.28
5711.31 5722.36 5756.45
Say 5711.30 5722.40 5756.50

120.000 120.000 3033.50 364020.00 364020.00 364020.00 21.09

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13
300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001

0.583xL1+3.5 1252.00 5111.92 PM11002

1.167xL1+7 907.00 7407.47 PM11003

394572.26 395316.34 397611.89

78914.45 79063.27 79522.38


(@ 20%) (@ 20%) 94697.34 94875.92 95426.85
(@ 10%) (@ 10%) 56818.41 56925.55 57256.11
625002.46 626181.08 629817.23
5208.35 5218.18 5248.48
Say 5208.40 5218.20 5248.50

394572.26 395316.34 397611.89

98643.06 98829.08 99402.97


(@ 20%) (@ 20%) 98643.06 98829.08 99402.97
(@ 10%) (@ 10%) 59185.84 59297.45 59641.78
651044.23 652271.95 656059.62
5425.37 5435.60 5467.16
Say 5425.40 5435.60 5467.20

394572.26 395316.34 397611.89

118371.68 118594.90 119283.57


(@ 20%) (@ 20%) 102588.79 102782.25 103379.09
(@ 10%) (@ 10%) 61553.27 61669.35 62027.45
677085.99 678362.83 682302.00
5642.38 5653.02 5685.85
Say 5642.40 5653.00 5685.90

394572.26 395316.34 397611.89

98643.06 98829.08 99402.97


(@ 20%) (@ 20%) 98643.06 98829.08 99402.97
(@ 10%) (@ 10%) 59185.84 59297.45 59641.78
651044.23 652271.95 656059.62
5425.37 5435.60 5467.16
Say 5425.40 5435.60 5467.20

394572.26 395316.34 397611.89

118371.68 118594.90 119283.57


(@ 20%) (@ 20%) 102588.79 102782.25 103379.09
(@ 10%) (@ 10%) 61553.27 61669.35 62027.45
677085.99 678362.83 682302.00
5642.38 5653.02 5685.85
Say 5642.40 5653.00 5685.90

394572.26 395316.34 397611.89

138100.29 138360.72 139164.16


(@ 20%) (@ 20%) 106534.51 106735.41 107355.21
(@ 10%) (@ 10%) 63920.71 64041.25 64413.13
703127.76 704453.71 708544.39
5859.40 5870.45 5904.54
Say 5859.40 5870.40 5904.50
120.000 120.000 3182.90 381948.00 381948.00 381948.00 21.11

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001

0.583xL1+3.5 1252.00 5111.92 PM11002

1.167xL1+7 907.00 7407.47 PM11003

412500.26 413244.34 415539.89

74250.05 74383.98 74797.18


(@ 20%) (@ 20%) 97350.06 97525.66 98067.41
(@ 10%) (@ 10%) 58410.04 58515.40 58840.45
642510.40 643669.38 647244.93
5354.25 5363.91 5393.71
Say 5354.30 5363.90 5393.70

412500.26 413244.34 415539.89

94875.06 95046.20 95574.17


(@ 20%) (@ 20%) 101475.06 101658.11 102222.81
(@ 10%) (@ 10%) 60885.04 60994.86 61333.69
669735.42 670943.50 674670.56
5581.13 5591.20 5622.25
Say 5581.10 5591.20 5622.30

412500.26 413244.34 415539.89

115500.07 115708.41 116351.17


(@ 20%) (@ 20%) 105600.07 105790.55 106378.21
(@ 10%) (@ 10%) 63360.04 63474.33 63826.93
696960.44 698217.63 702096.20
5808.00 5818.48 5850.80
Say 5808.00 5818.50 5850.80

412500.26 413244.34 415539.89

94875.06 95046.20 95574.17


(@ 20%) (@ 20%) 101475.06 101658.11 102222.81
(@ 10%) (@ 10%) 60885.04 60994.86 61333.69
669735.42 670943.50 674670.56
5581.13 5591.20 5622.25
Say 5581.10 5591.20 5622.30

412500.26 413244.34 415539.89

115500.07 115708.41 116351.17


(@ 20%) (@ 20%) 105600.07 105790.55 106378.21
(@ 10%) (@ 10%) 63360.04 63474.33 63826.93
696960.44 698217.63 702096.20
5808.00 5818.48 5850.80
Say 5808.00 5818.50 5850.80

412500.26 413244.34 415539.89

136125.09 136370.63 137128.16


(@ 20%) (@ 20%) 109725.07 109922.99 110533.61
(@ 10%) (@ 10%) 65835.04 65953.80 66320.17
724185.45 725491.76 729521.83
6034.88 6045.76 6079.35
Say 6034.90 6045.80 6079.30

412500.26 413244.34 415539.89

156750.10 157032.85 157905.16

(@ 20%) (@ 20%) 113850.07 114055.44 114689.01


(@ 10%) (@ 10%) 68310.04 68433.26 68813.41
751410.47 752765.88 756947.46
6261.75 6273.05 6307.90
Say 6261.80 6273.00 6307.90

412500.26 413244.34 415539.89

198000.12 198357.28 199459.15

(@ 20%) (@ 20%) 122100.08 122320.32 122999.81


(@ 10%) (@ 10%) 73260.05 73392.19 73799.88
805860.50 807314.13 811798.73
6715.50 6727.62 6764.99
Say 6715.50 6727.60 6765.00

412500.26 413244.34 415539.89

239250.15 239681.71 241013.14


(@ 20%) (@ 20%) 130350.08 130585.21 131310.60
(@ 10%) (@ 10%) 78210.05 78351.13 78786.36
860310.54 861862.39 866649.99
7169.25 7182.19 7222.08
Say 7169.30 7182.20 7222.10
120.000 120.000
3501.30 420156.00 420156.00 420156.00 21.12
63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1
12.32 3696.00 3696.00 3696.00 PM76001
2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001
2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001


0.583xL1+3.5
1252.00 5111.92 PM11002
1.167xL1+7 907.00 7407.47 PM11003

450708.26 451452.34 453747.89

81127.49 81261.42 81674.62


(@ 20%) (@ 20%) 106367.15 106542.75 107084.50
(@ 10%) (@ 10%) 63820.29 63925.65 64250.70
702023.18 703182.16 706757.71
5850.19 5859.85 5889.65
Say 5850.20 5859.90 5889.60

450708.26 451452.34 453747.89

103662.90 103834.04 104362.01


(@ 20%) (@ 20%) 110874.23 111057.27 111621.98
(@ 10%) (@ 10%) 66524.54 66634.36 66973.19
731769.93 732978.01 736705.07
6098.08 6108.15 6139.21
Say 6098.10 6108.20 6139.20

450708.26 451452.34 453747.89

126198.31 126406.65 127049.41


(@ 20%) (@ 20%) 115381.31 115571.80 116159.46
(@ 10%) (@ 10%) 69228.79 69343.08 69695.68
761516.67 762773.87 766652.43
6345.97 6356.45 6388.77
Say 6346.00 6356.40 6388.80

450708.26 451452.34 453747.89

103662.90 103834.04 104362.01


(@ 20%) (@ 20%) 110874.23 111057.27 111621.98
(@ 10%) (@ 10%) 66524.54 66634.36 66973.19
731769.93 732978.01 736705.07
6098.08 6108.15 6139.21
Say 6098.10 6108.20 6139.20

450708.26 451452.34 453747.89

126198.31 126406.65 127049.41


(@ 20%) (@ 20%) 115381.31 115571.80 116159.46
(@ 10%) (@ 10%) 69228.79 69343.08 69695.68
761516.67 762773.87 766652.43
6345.97 6356.45 6388.77
Say 6346.00 6356.40 6388.80

450708.26 451452.34 453747.89

148733.73 148979.27 149736.80


(@ 20%) (@ 20%) 119888.40 120086.32 120696.94
(@ 10%) (@ 10%) 71933.04 72051.79 72418.16
791263.42 792569.72 796599.79
6593.86 6604.75 6638.33
Say 6593.90 6604.70 6638.30

450708.26 451452.34 453747.89

171269.14 171551.89 172424.20


(@ 20%) (@ 20%) 124395.48 124600.84 125234.42
(@ 10%) (@ 10%) 74637.29 74760.51 75140.65
821010.16 822365.58 826547.15
6841.75 6853.05 6887.89
Say 6841.80 6853.00 6887.90

450708.26 451452.34 453747.89

216339.96 216697.12 217798.99


(@ 20%) (@ 20%) 133409.64 133629.89 134309.38
(@ 10%) (@ 10%) 80045.79 80177.93 80585.63
880503.65 881957.28 886441.88
7337.53 7349.64 7387.02
Say 7337.50 7349.60 7387.00

450708.26 451452.34 453747.89

261410.79 261842.35 263173.78


(@ 20%) (@ 20%) 142423.81 142658.94 143384.33
(@ 10%) (@ 10%) 85454.29 85595.36 86030.60
939997.14 941548.99 946336.60
7833.31 7846.24 7886.14
Say 7833.30 7846.20 7886.10

120.000 120.000
3638.50 436620.00 436620.00 436620.00 21.13
63.000 63.000 73.60 4636.80 4636.80 4636.80 M191
0.192 0.192 310.00 59.52 59.52 59.52 L-12
1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1
12.32 3696.00 3696.00 3696.00 PM76001
2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001
2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001


0.583xL1+3.5
1252.00 5111.92 PM11002
1.167xL1+7 907.00 7407.47 PM11003

467172.26 467916.34 470211.89

74747.56 74866.61 75233.90


(@ 20%) (@ 20%) 108383.96 108556.59 109089.16
(@ 10%) (@ 10%) 65030.38 65133.95 65453.49
715334.16 716473.49 719988.44
5961.12 5970.61 5999.90
Say 5961.10 5970.60 5999.90

467172.26 467916.34 470211.89

98106.17 98262.43 98744.50


(@ 20%) (@ 20%) 113055.69 113235.75 113791.28
(@ 10%) (@ 10%) 67833.41 67941.45 68274.77
746167.53 747355.97 751022.43
6218.06 6227.97 6258.52
Say 6218.10 6228.00 6258.50
467172.26 467916.34 470211.89

121464.79 121658.25 122255.09


(@ 20%) (@ 20%) 117727.41 117914.92 118493.40
(@ 10%) (@ 10%) 70636.45 70748.95 71096.04
777000.90 778238.45 782056.41
6475.01 6485.32 6517.14
Say 6475.00 6485.30 6517.10

467172.26 467916.34 470211.89

98106.17 98262.43 98744.50


(@ 20%) (@ 20%) 113055.69 113235.75 113791.28
(@ 10%) (@ 10%) 67833.41 67941.45 68274.77
746167.53 747355.97 751022.43
6218.06 6227.97 6258.52
Say 6218.10 6228.00 6258.50

467172.26 467916.34 470211.89

121464.79 121658.25 122255.09


(@ 20%) (@ 20%) 117727.41 117914.92 118493.40
(@ 10%) (@ 10%) 70636.45 70748.95 71096.04
777000.90 778238.45 782056.41
6475.01 6485.32 6517.14
Say 6475.00 6485.30 6517.10

467172.26 467916.34 470211.89

144823.40 145054.06 145765.69


(@ 20%) (@ 20%) 122399.13 122594.08 123195.51
(@ 10%) (@ 10%) 73439.48 73556.45 73917.31
807834.27 809120.93 813090.40
6731.95 6742.67 6775.75
Say 6732.00 6742.70 6775.80
467172.26 467916.34 470211.89

168182.01 168449.88 169276.28


(@ 20%) (@ 20%) 127070.85 127273.24 127897.63
(@ 10%) (@ 10%) 76242.51 76363.95 76738.58
838667.64 840003.41 844124.38
6988.90 7000.03 7034.37
Say 6988.90 7000.00 7034.40

467172.26 467916.34 470211.89

214899.24 215241.51 216297.47


(@ 20%) (@ 20%) 136414.30 136631.57 137301.87
(@ 10%) (@ 10%) 81848.58 81978.94 82381.12
900334.38 901768.36 906192.35
7502.79 7514.74 7551.60
Say 7502.80 7514.70 7551.60

467172.26 467916.34 470211.89

261616.46 262033.15 263318.66


(@ 20%) (@ 20%) 145757.74 145989.90 146706.11
(@ 10%) (@ 10%) 87454.65 87593.94 88023.67
962001.11 963533.32 968260.32
8016.68 8029.44 8068.84
Say 8016.70 8029.40 8068.80

120.000 120.000
4189.30 502716.00 502716.00 502716.00 21.14
63.000 63.000 73.60 4636.80 4636.80 4636.80 M191
0.192 0.192 310.00 59.52 59.52 59.52 L-12
1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1
12.32 3696.00 3696.00 3696.00 PM76001
2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001
2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001


0.583xL1+3.5
1252.00 5111.92 PM11002
1.167xL1+7 907.00 7407.47 PM11003

533268.26 534012.34 536307.89

186643.89 186904.32 187707.76


(@ 20%) (@ 20%) 143982.43 144183.33 144803.13
(@ 10%) (@ 10%) 86389.46 86510.00 86881.88
950284.04 951609.98 955700.66
7919.03 7930.08 7964.17
Say 7919.00 7930.10 7964.20

533268.26 534012.34 536307.89

239970.72 240305.55 241338.55

(@ 20%) (@ 20%) 154647.79 154863.58 155529.29


(@ 10%) (@ 10%) 92788.68 92918.15 93317.57
1020675.45 1022099.61 1026493.30
8505.63 8517.50 8554.11
Say 8505.60 8517.50 8554.10
533268.26 534012.34 536307.89

293297.54 293706.78 294969.34

(@ 20%) (@ 20%) 165313.16 165543.82 166255.45


(@ 10%) (@ 10%) 99187.90 99326.29 99753.27
1091066.86 1092589.24 1097285.94
9092.22 9104.91 9144.05
Say 9092.20 9104.90 9144.00

120.000 120.000 4266.80 512016.00 512016.00 512016.00 21.15

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001

0.583xL1+3.5 1252.00 5111.92 PM11002

1.167xL1+7 907.00 7407.47 PM11003


542568.26 543312.34 545607.89

189898.89 190159.32 190962.76


(@ 20%) (@ 20%) 146493.43 146694.33 147314.13
(@ 10%) (@ 10%) 87896.06 88016.60 88388.48
966856.64 968182.58 972273.26
8057.14 8068.19 8102.28
Say 8057.10 8068.20 8102.30

542568.26 543312.34 545607.89

244155.72 244490.55 245523.55


(@ 20%) (@ 20%) 157344.79 157560.58 158226.29
(@ 10%) (@ 10%) 94406.88 94536.35 94935.77
1038475.65 1039899.81 1044293.50
8653.96 8665.83 8702.45
Say 8654.00 8665.80 8702.40

542568.26 543312.34 545607.89

298412.54 298821.78 300084.34


(@ 20%) (@ 20%) 168196.16 168426.82 169138.45
(@ 10%) (@ 10%) 100917.70 101056.09 101483.07
1110094.66 1111617.04 1116313.74
9250.79 9263.48 9302.61
Say 9250.80 9263.50 9302.60
120.000 120.000
4447.90 533748.00 533748.00 533748.00 21.16
63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1
12.32 3696.00 3696.00 3696.00 PM76001
2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001
2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001


0.583xL1+3.5
1252.00 5111.92 PM11002
1.167xL1+7 907.00 7407.47 PM11003

564300.26 565044.34 567339.89

197505.09 197765.52 198568.96


(@ 20%) (@ 20%) 152361.07 152561.97 153181.77
(@ 10%) (@ 10%) 91416.64 91537.18 91909.06
1005583.06 1006909.01 1010999.68
8379.86 8390.91 8425.00
Say 8379.90 8390.90 8425.00
564300.26 565044.34 567339.89

253935.12 254269.95 255302.95

(@20%) (@20%) 163647.07 163862.86 164528.57


(@10%) (@10%) 98188.24 98317.71 98717.14
1080070.69 1081494.86 1085888.55
9000.59 9012.46 9049.07
Say 9000.60 9012.50 9049.10

564300.26 565044.34 567339.89

310365.14 310774.38 312036.94

(@ 20%) (@ 20%) 174933.08 175163.74 175875.37


(@ 10%) (@ 10%) 104959.85 105098.25 105525.22
1154558.33 1156080.71 1160777.41
9621.32 9634.01 9673.15
Say 9621.30 9634.00 9673.10

120.000 120.000 4488.30 538596.00 538596.00 538596.00 21.17

63.000 63.000 73.60 4636.80 4636.80 4636.80 M191

0.192 0.192 310.00 59.52 59.52 59.52 L-12


1.500 1.500 351.00 526.50 526.50 526.50 L-10
3.300 3.300 292.00 963.60 963.60 963.60 L-13

300xL1 300xL1 12.32 3696.00 3696.00 3696.00 PM76001

2.600 2.600 2218.00 5766.80 5766.80 5766.80 PM34001


2.600 2.600 4052.00 10535.20 10535.20 10535.20 PM36001

1426.00 4367.84 PM11001


0.583xL1+3.5 1252.00 5111.92 PM11002

1.167xL1+7 907.00 7407.47 PM11003

569148.26 569892.34 572187.89

199201.89 199462.32 200265.76

(@ 20%) (@ 20%) 153670.03 153870.93 154490.73


(@ 10%) (@ 10%) 92202.02 92322.56 92694.44
1014222.20 1015548.14 1019638.82
8451.85 8462.90 8496.99
Say 8451.90 8462.90 8497.00

569148.26 569892.34 572187.89

256116.72 256451.55 257484.55

(@ 20%) (@ 20%) 165052.99 165268.78 165934.49


(@ 10%) (@ 10%) 99031.80 99161.27 99560.69
1089349.77 1090773.93 1095167.62
9077.91 9089.78 9126.40
Say 9077.90 9089.80 9126.40

569148.26 569892.34 572187.89

313031.54 313440.78 314703.34

(@ 20%) (@ 20%) 176435.96 176666.62 177378.25


(@ 10%) (@ 10%) 105861.58 105999.97 106426.95
1164477.34 1165999.72 1170696.42
9703.98 9716.66 9755.80
Say 9704.00 9716.70 9755.80
8.400 8.400 46824.00 393321.60 393321.60 393321.60 M083

48.000 48.000 58.95 2829.60 2829.60 2829.60 M072

0.160 0.160 310.00 49.60 49.60 49.60 L-12


1.000 1.000 351.00 351.00 351.00 351.00 L-01
3.000 3.000 292.00 876.00 876.00 876.00 L-13

8.000 8.000 334.00 2672.00 2672.00 2672.00 PM43001


8.000 8.000 334.00 2672.00 2672.00 2672.00 PM43001
8.000 8.000 410.00 3280.00 3280.00 3280.00 PM22009

5.94 47.54 PM72001


8xL1 6.63 53.04 PM73001
8xL1 8.08 64.64 PM74001

2772.00 2772.00 PM6001


1.280 2415.00 3091.20 PM6002
1.778 2121.00 3771.14 PM6003

2.000 2.000 862.00 1724.00 1724.00 1724.00 PM63001


2.000 2.000 862.00 1724.00 1724.00 1724.00 PM62001
(@ 20%) (@ 20%) 82463.87 82528.81 82667.12
(@ 10%) (@ 10%) 49478.32 49517.28 49600.27
544261.52 544690.13 545602.96
68032.69 68086.27 68200.37
Say 68032.70 68086.30 68200.40

0.385 0.385 68410.22 26337.93 26337.93 26337.93 M118

42.000 42.000 84.61 3553.62 3553.62 3553.62 M166

2.000 2.000 46.14 92.28 92.28 92.28 M189

0.125 0.125 4844.00 605.50 605.50 605.50 M081

152.95 152.95 152.95

0.160 0.160 310.00 49.60 49.60 49.60 L-12


1.000 1.000 351.00 351.00 351.00 351.00 L-01
3.000 3.000 292.00 876.00 876.00 876.00 L-13

0.050 0.050 310.00 15.50 15.50 15.50 L-12


0.250 0.250 351.00 87.75 87.75 87.75 L-08
1.000 1.000 292.00 292.00 292.00 292.00 L-13

0.050 0.050 310.00 15.50 15.50 15.50 L-12


0.250 0.250 351.00 87.75 87.75 87.75 L-10
1.000 1.000 292.00 292.00 292.00 292.00 L-13
2.500 2.500 406.00 1015.00 1015.00 1015.00 PM65001
1.000 1.000 521.00 521.00 521.00 521.00 PM60001
3.500 3.500 783.00 2740.50 2740.50 2740.50 PM22008
(@ 20%) (@ 20%) 7417.18 7417.18 7417.18
(@ 10%) (@ 10%) 4450.31 4450.31 4450.31
48953.36 48953.36 48953.36
129849.77 129849.77 129849.77
Say 129849.80 129849.80 129849.80

1.000 1.000 3288.10 L 3288.10 3294.30 3313.43 14.01 C


3294.30 M
3313.43 S

0.075 0.075 51539.92 L 3865.49 3868.54 3875.02 14.02


51580.51M excluding OH
51666.95 S & CP

0.150 0.150 292.00 43.80 43.80 43.80 L-13

(@ 20%) (@ 20%) 1439.48 1441.33 1446.45


(@ 10%) (@ 10%) 863.69 864.80 867.87
9500.56 9512.77 9546.57
Say 9500.60 9512.80 9546.60
0.490 0.490 310.00 151.90 151.90 151.90 L-12
11.000 11.000 292.00 3212.00 3212.00 3212.00 L-13
1.250 1.250 370.00 462.50 462.50 462.50 L-15

0.060 0.060 642.00 38.52 38.52 38.52 PM23001

0.060 0.060 416.00 24.96 24.96 24.96 PM15001


6.000 6.000 461.00 2766.00 2766.00 2766.00 PM27001
6.000 6.000 606.00 3636.00 3636.00 3636.00 PM26001
1.000 1.000 612.00 612.00 612.00 612.00 PM12001
0.204 0.204 44525.00 9083.10 9083.10 9083.10 M327

0.390 0.390 117.23 45.72 45.72 45.72 M020

0.360 0.360 3637.51 1309.50 1309.50 1309.50 M190

0.550 0.550 657.91 361.85 361.85 361.85 M050

0.036 0.036 634.05 22.83 22.83 22.83 M141

1.050 1.050 44525.00 46751.25 46751.25 46751.25 M327

(@ 20%) (@ 20%) 13695.63 13695.63 13695.63


(@ 10%) (@ 10%) 8217.38 8217.38 8217.38
90391.13 90391.13 90391.13
1247.46 1247.46 1247.46
Say 1247.50 1247.50 1247.50
4.092 4.092 3288.10L 13454.91 13480.29 13558.57 14.01 C
3294.30 M excluding
3313.43 S formwork

672.75 674.01 677.93

0.865 0.865 51539.92 L 44582.03 44617.14 44691.91 14.02


51580.51 M (excluding OH
51666.95 S & CP)

2935.48 2938.57 2946.42

(@ 20%) (@ 20%) 12329.03 12342.00 12374.96


(@ 10%) (@ 10%) 7397.42 7405.20 7424.98
81371.63 81457.21 81674.77
1695.24 1697.03 1701.56
Say 1695.20 1697.00 1701.60
4.092 4.092 3288.10 L 13454.91 13480.29 13558.57 Same as 14.01
3294.30 M ( C) excluding
3313.43 S formwork

1614.59 1617.63 1627.03

0.865 0.865 51539.92 L 44582.03 44617.14 44691.91 Same as 14.02


51580.51 M excluding OH
51666.95 S & CP

(@ 20%) (@ 20%) 11930.31 11943.01 11975.50


(@ 10%) (@ 10%) 7158.18 7165.81 7185.30
78740.02 78823.88 79038.30
1640.42 1642.16 1646.63
Say 1640.40 1642.20 1646.60
2.946 2.946 46658.00 137454.47 137454.47 137454.47 M181
1.012 1.012 46658.00 47217.90 47217.90 47217.90 M181
0.180 0.180 50325.00 9058.50 9058.50 9058.50 M125
0.150 0.150 61.74 9.26 9.26 9.26 M129
9687.01 9687.01 9687.01

1937.40 1937.40 1937.40

1937.40 1937.40 1937.40

2.800 2.800 310.00 868.00 868.00 868.00 L-12


30.000 30.000 370.00 11100.00 11100.00 11100.00 L-15
40.000 40.000 292.00 11680.00 11680.00 11680.00 L-13
(@ 20%) (@ 20%) 46189.99 46189.99 46189.99
(@ 10%) (@ 10%) 27713.99 27713.99 27713.99
304853.91 304853.91 304853.91
3048.54 3048.54 3048.54
Say 3048.50 3048.50 3048.50

4.000 4.000 43.85 175.38 175.38 175.38 M088

6.000 6.000 522.42 3134.52 3134.52 3134.52 M239


6.000 6.000 15.96 95.76 95.76 95.76 M109
2.000 2.000 14.53 29.06 29.06 29.06 M101
0.002 0.002 310.00 0.62 0.62 0.62 L-12
0.020 0.020 394.00 7.88 7.88 7.88 L-02
0.020 0.020 292.00 5.84 5.84 5.84 L-13

0.008 0.008 310.00 2.48 2.48 2.48 L-12


0.010 0.010 351.00 3.51 3.51 3.51 L-10
0.200 0.200 292.00 58.40 58.40 58.40 L-13
175.67 175.67 175.67

(@ 20%) (@ 20%) 737.82 737.82 737.82


(@ 10%) (@ 10%) 442.69 442.69 442.69
4869.64 4869.64 4869.64
Say 4869.60 4869.60 4869.60

2395.07 2395.07 12.08 (A) Case


I (Large)

1.000 2401.31 2401.31 12.08 (A) Case


I (Medium)

1.000 2420.44 2420.44 12.08 (A) Case


I (small)

(@ 20%) (@ 20%) 479.01 480.26 484.09


(@ 10%) (@ 10%) 287.41 288.16 290.45
3161.49 3169.73 3194.98
2549.51 2549.51 12.08 (A) Case
II (large)

1.000 2555.75 2555.75 12.08 (A) Case


II (Medium)

1.000 2574.84 2574.84 12.08 (A) Case


II (small)

(@ 20%) (@ 20%) 509.90 511.15 514.97


(@ 10%) (@ 10%) 305.94 306.69 308.98
3365.35 3373.59 3398.78

1.000 1.000 3316.91 L 3316.91 3323.16 3342.29 12.08 G Case I


3323.16 M
3342.29 S

66.34 66.46 66.85

0.050 0.050 51539.92 L 2577.00 2579.03 2583.35 14.02


51580.51 M excluding OH
51666.5 S &CP

(@ 20%) (@ 20%) 1192.05 1193.73 1198.50


(@ 10%) (@ 10%) 715.23 716.24 719.10
7867.53 7878.62 7910.07
Say 7867.50 7878.60 7910.10
1.000 1.000 3501.30 3501.30 3501.30 3501.30 21.12

0.525 0.525 73.60 38.64 38.64 38.64 M191


0.100 0.100 46824.00 4682.40 4682.40 4682.40 M083
0.060 0.060 68410.22 4104.61 4104.61 4104.61 M118

37.000 37.000 input #VALUE! #VALUE! #VALUE! M121


#VALUE! #VALUE! #VALUE!
0.070 0.070 310.00 21.70 21.70 21.70 L-12
0.350 0.350 370.00 129.50 129.50 129.50 L-15
1.400 1.400 292.00 408.80 408.80 408.80 L-13

0.026 0.026 310.00 8.06 8.06 8.06 L-12


0.140 0.140 370.00 51.80 51.80 51.80 L-15
0.500 0.500 292.00 146.00 146.00 146.00 L-13

0.120 0.120 310.00 37.20 37.20 37.20 L-12


1.000 1.000 370.00 370.00 370.00 370.00 L-15
2.000 2.000 292.00 584.00 584.00 584.00 L-13

0.026 0.026 310.00 8.06 8.06 8.06 L-12


0.050 0.050 370.00 18.50 18.50 18.50 L-15
0.600 0.600 292.00 175.20 175.20 175.20 L-13

0.014 0.014 310.00 4.34 4.34 4.34 L-12


0.350 0.350 292.00 102.20 102.20 102.20 L-13

0.010 0.010 310.00 3.10 3.10 3.10 L-12


0.250 0.250 292.00 73.00 73.00 73.00 L-13

0.012 0.012 310.00 3.72 3.72 3.72 L-12


0.060 0.060 370.00 22.20 22.20 22.20 L-15
0.240 0.240 292.00 70.08 70.08 70.08 L-13

2.5xL 2.5xL 12.32 30.80 30.80 30.80 PM76001


0.022 0.022 2218.00 48.80 48.80 48.80 PM34001
0.022 0.022 4052.00 89.14 89.14 89.14 PM36001

1426.00 37.08 PM11001

0.005xL1+0.02 1252.00 42.57 PM11002


9
0.01xL1+0.05 907.00 61.68 PM11003
8
0.100 0.100 6082.00 608.20 608.20 608.20 PM62001
0.100 0.100 2772.00 277.20 277.20 277.20 PM6001
0.00 0.00

1.150 2.15 6082.00 912.30 6994.30 13076.30 PM62001


2.5xL 2.5xL 5.94 14.86 14.86 14.86 PM72001

1.15 2.150 2772.00 415.80 3187.80 5959.80 PM6001

#VALUE! #VALUE! #VALUE!

#VALUE! #VALUE! #VALUE!


#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!

1.000 1.000 input #VALUE! #VALUE! #VALUE! M116


1.000 1.000 57.80 57.80 57.80 57.80 M185
#VALUE! #VALUE! #VALUE!

0.010 0.010 310.00 3.10 3.10 3.10 L-12


0.050 0.050 351.00 17.55 17.55 17.55 L-08
0.200 0.200 292.00 58.40 58.40 58.40 L-13
(@ 20%) (@ 20%) #VALUE! #VALUE! #VALUE!
(@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!

2.540 2.540 5850.20 L 14859.51 14884.15 14959.58 14.01 E (i) (p)


5859.90 M
5889.60 S

0.229 0.229 68032.70 L 15579.49 15591.76 15617.89 14.02 including


68086.30M OH & CP
68200.40 S

0.040 0.040 310.00 12.40 12.40 12.40 L-12


1.000 1.000 292.00 292.00 292.00 292.00 L-13

0.265 0.265 961.32 254.75 254.75 254.75 M143


(@ 20%) (@ 20%) 111.83 111.83 111.83
(@ 10%) (@ 10%) 67.10 67.10 67.10
31177.07 31213.99 31315.55
3117.71 3121.40 3131.56
Say 3117.70 3121.40 3131.60
2.980 2.980 5850.20 L 14.01 E (i) (p)
5859.90 M
5889.60 S
17433.60 17462.50 17551.01
0.268 0.268 68032.70 L 14.02 including
68086.30M OH & CP
68200.40 S
18232.76 18247.13 18277.71

0.040 0.040 310.00 12.40 12.40 12.40 L-12


1.000 1.000 292.00 292.00 292.00 292.00 L-13

0.310 0.310 961.32 298.01 298.01 298.01 M143


(@ 20%) (@ 20%) 120.48 120.48 120.48
(@ 10%) (@ 10%) 72.29 72.29 72.29
36461.54 36504.81 36623.90
3646.15 3650.48 3662.39
Say 3646.20 3650.50 3662.40

5.140 5.140 5850.20 L 14.01 E (i) (p)


5859.90 M
5889.60 S
30070.03 30119.89 30272.54
0.463 0.463 68032.70 L 14.02 including
68086.30M OH & CP
68200.40 S
31499.14 31523.96 31576.79

0.060 0.060 310.00 18.60 18.60 18.60 L-12


1.500 1.500 292.00 438.00 438.00 438.00 L-13

0.540 0.540 961.32 519.11 519.11 519.11 M143


(@ 20%) (@ 20%) 195.14 195.14 195.14
(@ 10%) (@ 10%) 117.09 117.09 117.09
62857.11 62931.78 63137.27
6285.71 6293.18 6313.73
Say 6285.70 6293.20 6313.70
0.020 0.020 310.00 6.20 6.20 6.20 L-12
0.250 0.250 373.00 93.25 93.25 93.25 L-18
0.250 0.250 370.00 92.50 92.50 92.50 L-15

5.000 5.000
114.01 570.05 570.05 570.05 M192
(@ 20%) (@ 20%) 152.40 152.40 152.40
(@ 10%) (@ 10%) 91.44 91.44 91.44
1005.84 1005.84 1005.84
100.58 100.58 100.58
Say 100.60 100.60 100.60

0.040 0.040 310.00 12.40 12.40 12.40 L-12


0.500 0.500 292.00 146.00 146.00 146.00 L-13
0.500 0.500 370.00 185.00 185.00 185.00 L-15

55.000 55.000 749.21 41206.55 41206.55 41206.55 M087

(@ 20%) (@ 20%) 8309.99 8309.99 8309.99


(@ 10%) (@ 10%) 4985.99 4985.99 4985.99
54845.93 54845.93 54845.93
4570.49 4570.49 4570.49
Say 4570.50 4570.50 4570.50
0.008 0.008 310.00 2.48 2.48 2.48 L-12
0.100 0.100 292.00 29.20 29.20 29.20 L-13
0.100 0.100 370.00 37.00 37.00 37.00 L-15

3.000 3.000
930.96 2792.88 2792.88 2792.88 M085

(@ 20%) (@ 20%) 572.31 572.31 572.31


(@ 10%) (@ 10%) 343.39 343.39 343.39
3777.26 3777.26 3777.26
314.77 314.77 314.77
Say 314.80 314.80 314.80

0.012 0.012 310.00 3.72 3.72 3.72 L-12


0.200 0.200 292.00 58.40 58.40 58.40 L-13
0.100 0.100 370.00 37.00 37.00 37.00 L-15

3.600 3.600
961.32 3460.75 3460.75 3460.75 M140
(@ 20%) (@ 20%) 711.97 711.97 711.97
(@ 10%) (@ 10%) 427.18 427.18 427.18
4699.03 4699.03 4699.03
391.59 391.59 391.59
Say 391.60 391.60 391.60
0.024 0.024 310.00 7.44 7.44 7.44 L-12
0.500 0.500 292.00 146.00 146.00 146.00 L-13
0.100 0.100 370.00 37.00 37.00 37.00 L-15

0.012 0.012 175.80 2.11 2.11 2.11 M005

0.001 0.001 43502.00 43.50 43.50 43.50 M074

(@ 20%) (@ 20%) 47.21 47.21 47.21


(@ 10%) (@ 10%) 28.33 28.33 28.33
311.59 311.59 311.59
25.97 25.97 25.97
Say 26.00 26.00 26.00
0.052 0.052 310.00 16.12 16.12 16.12 L-12
1.000 1.000 292.00 292.00 292.00 292.00 L-13
0.300 0.300 370.00 111.00 111.00 111.00 L-15

0.750 0.750
686.05 514.54 514.54 514.54 M051
77.500 77.500 44632.00 3458980.00 3458980.00 3458980.00 M078
113.000 113.000 42.70 4825.10 4825.10 4825.10 M103

48.25 48.25 48.25

1.000 1.000 461.00 461.00 461.00 461.00 PM27001


0.500 0.500 901.00 450.50 450.50 450.50 PM8001

(@ 20%) (@ 20%) 693139.70 693139.70 693139.70


(@ 10%) (@ 10%) 415883.82 415883.82 415883.82

4574722.03 4574722.03 4574722.03


381226.84 381226.84 381226.84
Say 381226.80 381226.80 381226.80
0.060 0.060 310.00 18.60 18.60 18.60 L-12
1.000 1.000 292.00 292.00 292.00 292.00 L-13
0.500 0.500 370.00 185.00 185.00 185.00 L-15

12.000 12.000 27202.73 326432.76 326432.76 326432.76 M094

16321.64 16321.64 16321.64


(@ 20%) (@ 20%) 68650.00 68650.00 68650.00
(@ 10%) (@ 10%) 41190.00 41190.00 41190.00
453090.00 453090.00 453090.00
37757.50 37757.50 37757.50
Say 37757.50 37757.50 37757.50
0.036 0.036 310.00 11.16 11.16 11.16 L-12
0.600 0.600 292.00 175.20 175.20 175.20 L-13
0.300 0.300 370.00 111.00 111.00 111.00 L-15

446.000 446.000 42.70 19044.20 19044.20 19044.20 M103

952.21 952.21 952.21

12.000 12.000 input #VALUE! #VALUE! #VALUE! M142

#VALUE! #VALUE! #VALUE!

(@ 20%) (@ 20%) #VALUE! #VALUE! #VALUE!


(@ 10%) (@ 10%) #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
Say #VALUE! #VALUE! #VALUE!
0.050 0.050 310.00 15.50 15.50 15.50 L-12
1.000 1.000 292.00 292.00 292.00 292.00 L-13
0.250 0.250 370.00 92.50 92.50 92.50 L-15

12.000 12.000 8439.38 101272.56 101272.56 101272.56 M180

5063.63 5063.63 5063.63

(@ 20%) (@ 20%) 21347.24 21347.24 21347.24


(@ 10%) (@ 10%) 12808.34 12808.34 12808.34
140891.77 140891.77 140891.77
11740.98 11740.98 11740.98
Say 11741.00 11741.00 11741.00
0.056 0.056 310.00 17.36 17.36 17.36 L-12
1.000 1.000 292.00 292.00 292.00 292.00 L-13
0.400 0.400 370.00 148.00 148.00 148.00 L-15

12.000 12.000 29978.49 359741.88 359741.88 359741.88 M126

(@ 20%) (@ 20%) 72039.85 72039.85 72039.85


(@ 10%) (@ 10%) 43223.91 43223.91 43223.91

475463.00 475463.00 475463.00


39621.92 39621.92 39621.92
Say 39621.90 39621.90 39621.90
0.070 0.070 310.00 21.70 21.70 21.70 L-12
1.250 1.250 292.00 365.00 365.00 365.00 L-13
0.500 0.500 370.00 185.00 185.00 185.00 L-15

12.000 12.000 29978.49 359741.88 359741.88 359741.88

M127
(@ 20%) (@ 20%) 72062.72 72062.72 72062.72
(@ 10%) (@ 10%) 43237.63 43237.63 43237.63
475613.93 475613.93 475613.93
39634.49 39634.49 39634.49
Say 39634.50 39634.50 39634.50
0.006 0.006 310.00 1.86 1.86 1.86 L-12
0.100 0.100 373.00 37.30 37.30 37.30 L-18
0.05 0.05 292.00 14.60 14.60 14.60 L-13

0.300 0.300
224.02 67.21 67.21 67.21 M130

0.54 0.54 0.54

6.05 6.05 6.05


(@ 20%) (@ 20%) 25.51 25.51 25.51
(@ 10%) (@ 10%) 15.31 15.31 15.31
168.37 168.37 168.37
168.37 168.37 168.37
Say 168.40 168.40 168.40
300.000 300.000
159.51 47853.00 47853.00 47853.00 M182
(@ 20%) (@ 20%) 9570.60 9570.60 9570.60
(@ 10%) (@ 10%) 5742.36 5742.36 5742.36
63165.96 63165.96 63165.96
631.66 631.66 631.66
Say 631.70 631.70 631.70

17.992 17.992
46658.00 839470.74 839470.74 839470.74 M181
180.000 180.000 61.74 11113.20 11113.20 11113.20 M129

21.097 21.097 310.00 6540.07 6540.07 6540.07 L-12


77.108 77.108 351.00 27064.91 27064.91 27064.91 L-08
77.108 77.108 351.00 27064.91 27064.91 27064.91 L-25
77.108 77.108 394.00 30380.55 30380.55 30380.55 L-02
32.385 32.385 373.00 12079.61 12079.61 12079.61 L-18
263.708 263.708 292.00 77002.74 77002.74 77002.74 L-13

85058.39 85058.39 85058.39

68.540 68.540
1019.00 69842.26 69842.26 69842.26 PM63003
4.000 4.000
2337.00 9348.00 9348.00 9348.00 PM63006
4.000 4.000
2337.00 9348.00 9348.00 9348.00 PM63006
4+L /15 4+L /15
2772.00 11272.80 11272.80 11272.80 PM6001
899.598 899.598
70.48 63403.67 63403.67 63403.67 M145
899.598 899.598 113.26 101888.47 101888.47 101888.47 M058
69043.92 69043.92 69043.92
(@ 20%) (@ 20%) 289984.44 289984.44 289984.44
(@ 10%) (@ 10%) 173990.67 173990.67 173990.67
1913897.33 1913897.33 1913897.33
111695.20 111695.20 111695.20
Say 111695.20 111695.20 111695.20
Quantity as per peroject category
Sr No Ref. to M. Description Unit
Large Medium Small
16.01 2503 Proving and laying boulders apron on
river bed for protection against scour
with stone boulders weighing not less
than 40 kg each complete as per drawing
and Technical specification.
A Boulder Laid Dry without wire crates
Unit = cum
Taking output= 1 cum
a) Material
Stone cum 1 1 1
Stone Spalls cum 0.2 0.2 0.2
b) Labour
Mate day 0.044 0.044 0.044
Mason day 0.35 0.35 0.35
Mazdoor* day 0.75 0.75 0.75
c) Overhead charges
d) Contractor's profit
Rate per cum= (a+b+c+d)
* Including excavation for trimming for preparation of bed.
Nominal excavation required for
preparation of bed has been taken into
Note account while making provision for
labour.

16.02 2503 Boulder Apron Laid in Wire Crates

Providing and laying of boulder apron


laid in wire crates made with 4mm dia
GI wire conforming to IS: 280 &
IS:4826 in 100mm x 100mm mesh
(weaved diagonally) including 10 per
cent extra for laps and joints laid with
stone boulders weighing not less than 40
kg each.

Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size
of 100 mm x 100 mm. sqm 22 22 22
Stone cum 5.63 5.63 5.63
Stone Spalls cum 1.13 1.13 1.13
b) Labour
Mate day 0.18 0.18 0.18
Mazdoor (Skilled) day 1.5 1.5 1.5
Mazdoor* day 3 3 3
c) Overhead charges
d) Contractor's profit
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63
* Including excavation for trimming for preparation of bed.

Readymade woven wire crate rolls have


been considered in the rate analysis. In
case readymade rolls are not available,
Note GI wire 4mm dia. @ 32 kg per 10 sqm
may be provided. In that case 2 per cent
of the cost of GI wire may be added for
weaving the wire crates.

16.03 2503 Cement Concrete Blocks (size 0.5 x


0.5 x 0.5 m)

Providing and laying of apron with


cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made
with nominal mix of M-15 grade cement
concrete with a minimum cement
content of 250 kg/cum as per IRC: 21-
2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 (Rate taken from
items 12.8 A, Case II) including OH &
CP cum 1 1 1

Add 2 per cent of cost to account for


excavation for preparation of bed,
nominal surface reinforcement and
filling of granular material in recesses
between blocks.
Rate per cum

16.04 2504
Providing and laying Pitching on slopes
laid over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications

A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum
Stone spalls of minimum 25 mm size cum
b) Labour
Mate day
Mason day
Mazdoor day
c) Overhead charges
d) Contractor's profit
Rate per cum = (a+b+c+d)

16.04 B
Cement Concrete Blocks of size
0.3x0.3 x0.3 m cast in cement concrete
of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 (Rate taken from
items 12.8 A, Case II) including OH &
CP cum 1 1 1

Add 2 per cent of cost to account for


nominal surface reinforcement and
filling of granular material in recesses
between blocks.
Rate per cum

16.05 2504
Providing and laying Filter material
underneath pitching in slopes complete
as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material

Graded stone aggregate of required size cum 1.2 1.2 1.2


b) Labour
Mate day 0.05 0.05 0.05
Mazdoor (Skilled) day 0.25 0.25 0.25
Mazdoor * day 1 1 1
c) Overhead charges
d) Contractor's profit
Rate per cum = (a+b+c+d)
* Includes Mazdoor required for trimming of slope to proper profile and preparation of bed.

16.06 700 & Geotextile Filter


2504
Laying of a geotextile filter between
pitching and embankment slopes on
which pitching is laid to prevent escape
of the embankment material through the
voids of the stone pitching/cement
concrete blocks as well as to allow free
movement of water without creating any
uplift head on the pitching.
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.016 0.016 0.016
Mazdoor day 0.3 0.3 0.3
Mazdoor (Skilled) day 0.1 0.1 0.1
b) Material

Permeable synthetic geotextile including


5 per cent for overlap and wastage sqm 11 11 11
c) Overhead charges
d) Contractor's profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

16.07 2504.4 Toe protection

A toe wall for toe protection can either


be in dry rubble masonry in case of dry
rubble pitching or pitching with stones
in wire crates or it can be in PCC M15
nominal mix if cement concert block
have been used for pitching . Rates for
toe wall can be adopted from respective
clauses depending upon approved
design. The rate for excavation for
foundation, dry rubble masonry and
PCC M15 have been analysed and given
in respective chapters.

16.08 2505
Providing and laying Flooring complete
as per drawing and Technical
specifications laid over cement concert
bedding.
A
Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Ratetaken
from Items 21.01 A) cum 0.133 0.133 0.133

b) Add for cement concrete bedding


(M15 Nominal mix) vide Item 12.8 (A)
including OH & CP . Quantity shall be
adopted as per design ( Assume Rubble
stone Flooring thickness 300 mm and
cement concrete bedding thickness 100
mm) cum 0.333 0.333 0.333
Add 1 per cent of cost to account for
excavation for preparation of bed.
c) Material
Stone cum 1 1 1
Stone Spalls cum 0.2 0.2 0.2
d) Labour
Mate day 0.08 0.08 0.08
Mason day 0.5 0.5 0.5
Mazdoor (for laying stones, filling of
quarry spalls) day 1.5 1.5 1.5
e) Overhead charges
f) Contractor's profit
Rate per cum = (a+b+c+d+e+f)
* Includes cement mortar for laying and filling of joints.

16.08 B
Cement Concrete blocks Grade M15

Concrete Grade M15 block. (Rate taken


from items 12.8 A) including OH & CP. cum 1 1 1

Add for cement concrete bedding (M15


Nominal mix) vide Item 12.8 (A)
including OH & CP. Quantity shall be
adopted as per design ( Assume Cement
Concrete blocks thickness 300mm and
cement concrete bedding thickness
100mm) cum 0.33 0.33 0.33
Add 1 per cent of cost to account for
excavation for preparation of bed.
Rate per cum

16.09 2506 Dry Rubble Flooring


Construction of dry rubble flooring at
cross drainage works for relatively less
important works.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1 1 1
Stone Spalls cum 0.2 0.2 0.2
b) Labour
Mate day 0.08 0.08 0.08
Mason day 0.5 0.5 0.5
mazdoor day 1.5 1.5 1.5
Add 1 per cent of (b) for trimming and
preparation of base.
c) Overhead charges )
d) Contractor's profit
Rate per cum = (a+b+c+d)

16.10 2507.2

Curtain wall complete as per drawing


and Technical specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1 1 1
Rate same as per item No. 12.7 (A)
including OH & CP
Rate per cum
or
16.10 B Cement concrete Grade M15

Concrete Grade M15 (Rate taken from


items 12.8 A) including OH & CP cum 1 1 1
Rate per cum

Other items like excavation for


Note foundation, filling behind wall, filter
media, weep holes etc. shall be added
separately as per approved design.

16.11 2507.2
Flexible Apron :Construction of flexible
apron 1 m thick comprising of loose
stone boulders weighing not less than 40
kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1 1 1
Stone Spalls cum 0.2 0.2 0.2
b) Labour
Mate day 0.05 0.05 0.05
Mason day 0.25 0.25 0.25
Mazdoor day 1 1 1

Add 1 per cent of cost of (a+b) for


trimming and preparation of bed.
c) Overhead charges
d) Contractor's profit
Rate per cum = (a+b+c+d)

16.12 2503.3 Gabian Structure for Retaining Earth

Providing and construction of a gabian


structure for retaining earth with
segments of wire crates of size 7 m x 3
m x 0.6 m each divided into 1.5 m
compartments by cross netting, made
from 4 mm galvanised steel wire @ 32
kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to
IS:280 and galvanizing coating
conforming to IS:4826, woven into
mesh with double twist, mesh size not
exceeding 100 x 100 mm, filled with
boulders with least dimension of 200
mm, all loose ends to be tied with 4 mm
galvanised steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 0.28 0.28
Mazdoor day 5 5 5
Mazdoor (Skilled) day 2 2 2
b) Material
Galvanised steel wire crates of mesh
size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size. sqm 61 61 61
Stone boulders with least dimension of
200 mm cum 12.6 12.6 12.6

Stone spalls of minimum size 25 mm cum 2.52 2.52 2.52


c) Overhead charges
d) Contractor's profit
Cost for 12.60 cum (a+b+c+d)
Rate per cum (a+b+c+d)/12.60

Readymade woven wire crate rolls have


been considered in the rate analysis. In
Note case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm
may be provided. In that case 2 per cent
of the cost of GI wire may be added for
weaving the wire crates.

16.13 2503.3
Gabian Structure for Erosion Control,
River Training Works and Protection
works

Providing and constructing gabian


structures for erosion control, river
training works and protection works
with wire crates of size 2 m x 1 m x 0.3
m each divided into 1m compartments
by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of
300 Mpa conforming to IS:280 and
galvanizing coating conforming to
IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm
x 100 mm, filled with boulders with
least dimension of 200 mm, all loose
ends to be securely tied with 4 mm
galvanised steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 0.14 0.14
Mazdoor day 2.5 2.5 2.5
Mazdoor (Skilled) day 1 1 1
b) Material

Galvanised steel wire crates of mesh


size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size to cover 6.00 cum. sqm 65 65 65
Stone boulders with least dimension of
200 mm cum 6 6 6

Stone spalls of minimum size 25 mm cum 1.2 1.2 1.2


c) Overhead charges
d) Contractor's profit
Cost for 6.00 cum (a+b+c+d)
Rate per cum (a+b+c+d)/6.00

Readymade woven wire crate rolls have


been considered in the rate analysis. In
Note case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm
may be provided. In that case 2 per cent
of the cost of GI wire may be added for
weaving the wire crates.

16.14 2503

Providing & making Gabion structure


with Mechanically Woven Double
Twisted Hexagonal Shaped Wire mesh
Gabion Boxes as per IS 16014;201,
MORT&H Clause 2500, of reuired size,
Mesh Type 10x12 (D=100 mm with
Tolerance of+/- 2%) Zinc Coated Mesh
Wire diameter 3.0 mm, mechanically
edged/ selvedge with partitions at every
1m interval and shall have minimum 10
number of openings per meter of mesh
perpendicular to twisst , trying with
lacing wire of diameter 2.2 mm,
supplied @ 3% by weight of Gabion
boxes, filled with boulders with least
dimension of 200 mm, as per drawing,
all complete as per direction of
Engineer-in-charge.
Unit = cum
Taking output = 2 x 1 x1 m = 2 cum
a) Material

Crates made of Mesh Type 10 x12 (D=


100mm) Zn coated. (Mesh wire
diameter 3.00 mm). Surface Area
reuired= 11.00 sqm. sqm 11 11 11
Stone boulder with least dimension
200mm cum 2 2 2
b) Labour
Mate day 0.08 0.08 0.08

Mason (for plain stone work) 2nd class day 0.5 0.5 0.5
Mazdoor* day 1.5 1.5 1.5
c) Overhead charges )
d) Contractor's profit
Cost for 2 cum= (a+b+c+d)
Rate per cum = (a+b+c+d)/2

16.15
Embankment Erosion Protection
using Fine Aggregate concrete filled
fabric form mattress system
Laying of a fine aggregate concrete
grade M30 filled fabric form for erosion
protection of embankments
Unit= Sqm
Taking output=60 sqm
a) Labour
Mate day 0.096 0.096 0.096
Mazdoor day 1.8 1.8 1.8
Mazdoor (skilled) day 0.6 0.6 0.6
b) Machinery
Transit Truck agitator
For Transportation Transit truck agitator
6 cum capacity t.km
Unloading time hour 0.13 0.13 0.13
Concrete Pump hour 0.13 0.13 0.13
c) Materials

PCC M30 Grade Refer relevent item of


concrete in item 12.08 (F) Case I by
using batching plant, excluding
formwork i.e. per cum basic cost
(a+b+c) cum 6 6 6
Fabric Form Mattress with 30%
Shrinkage sqm 78 78 78

Non-woven Geotextile to be placed


under concrete filled fabric form
including 15 percent for overlap and
shrinkage sqm 9 9 9
c) Overhead charges )
d) Contractor's profit
Cost for 60 sqm= (a+b+c+d)
Rate per sqm = (a+b+c+d)/60
Amount
Input_Ref
Large Medium Small
ration of bed.
Quantity as per projec
Sr No. Ref. to M Description Unit
Large
17.01 2811 Removal of existing cement concrete wearing coat
including its disposal complete as per technical
specification without causing ang detrimental effect
to any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000
m

Unit = Sqm (Thickness 75 mm)


Taking output = 10 sqm
a) Labour
Mate day 0.040
Mazdoor day 1.000
b) Machinery
Air Copressor 250 cfm with pneumatic breaker/jack hour
hammer along with accessories. 1.000
Tractor-trolley hour 0.500
c) Overhead charges
d) Contractor's profit
cost for 10sqm=(a +b+c+d)
Rate per sqm=(a+b+c+d)/10

17.02 2811
Removal of existing asphaltic wearing coat
comparising of 50 mm thick asphaltic concrete laid
over 12 mm thick mastic asphalt including disposal
with all lifts and lead upto 1000 m
Unit=Sqm
Tacking output=10 Sqm
a) Labour
Mate day 0.030
Masdoor day 0.750
b) Machinery
Air Copressor 250 cfm with pneumatic breaker/jack
hammer along with accessories. hour 0.750
Tractor-trolley hour 0.400
c) Overhead charges
d) Contractor's profit
Cost for 10 sqm=(a+b+c+d)
Rate per sqm=(a+b+c+d)/10

17.03 2807
Guniting concrete surface with cement morter
applied with compressor after cleaning surface and
spraying with epoxy complete as per Technical
Specification.
Unit=Sqm
Taking output= 1 sqm
Assuming thickness 25mm
a) Material
Cement kg 16.000
Graded sand cum 0.040
Wire mesh 50mm x 50mm size of 3mm wire kg 2.000
Epoxy kg 0.670
Accelerator compound for guniting @ 4 percent of
weight of cement kg 0.640

Add 2 percent of cost of material for miscelleneous


consumables like nozzles,wire brush,cotton waste etc.
b) Labour
Mate day 0.007
Mason day 0.040
Mazdoor day 0.140
c) Machinery
Compressor with guniting equipment along with
accessories
d) Overhead charges
e) Contractor's profit
Rate per sqm=(a+b+c+d+e)

17.04 2800
Providing and inserting nipple with approved fixing
compound after drilling holes for grouting as per
technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary
of nipples after completion of grouting with
Cement/Epoxy
Unit=Number
Taking output=1 No
a)Material
Nipples each 1.000
Cement,fixing compound and consumables@15 percent
of cost of nipple
b) Labour
Mate day 0.006
Mazdoor(Skilled) labour for drilling day 0.080
Mazdoor (skilled) labour for fixing nipple and sealing
inlets day 0.080
Mazdoor for cutting and removing of nipples day 0.040
Add 10 percent of labour cost for drilling holes etc
c) Overhead charges
d) Contractor's profit
Rate per no=(a+b+c+d)
17.05 2806 Sealing of cracks/porous concrete by injection
process through nipplles/Grouting complete as per
Technical Specification.
A Cement Grout
Unit= kg
Taking output= 1kg
a) Material
Cement including 10 percent wastage kg 1.1
Admixture (anti shrinkage compound) @ 20 percent
of cost of cement
b) Labour
Mate day 0.08
Mazdoor(Skilled) day 0.1
Mazdoor day 0.1
c) Machinery
Grout pump with agitator and accessories hour 0.1
d) overhead Charges
e) Contractor's profit
Rate per kg =(a+b+c+d+e)

B Cement Mortar (1:1) grouting


Unit=kg
Taking output=1kg
a) Material
Cement including 10 percent wastage kg 0.55
Sand including 10 percent wastage kg 0.55
Admixture (anti shrinkage compound) @ 20 percent of
cost of cement
b) Labour
Mate day 0.08
Mazdoor(skilled) day 0.1
Mazdoor day 0.1
c) Machinery
Grout pump with agitator and accessories
d) overhead Charges
e) Contractor's profit
Rate per kg =(a+b+c+d+e)

17.06 2800
Patching of damaged concrete surface with polymer
concrete and curing compounds,initiator and
promoter,available in present formulations, to be
applied as per instructions of manufacturer and as
approved by the Engineer.
Unit =sqm
Taking output=10sqm for an average thickness of
25mm
a) Labour
Mate day 0.060
Mazdoor(skilled) day 0.750
Mazdoor day 0.750
b) Material
Pre-packed polymer concrete based on epoxy system
complete with curing compound, initiator and promotor
including 5 percentage wastage. kg 315.000
c) Machinery
Grout pump with agitator and accessories hour 2.000
d) Overhead Charges
e) Contractor's profit
Cost for 10 sqm=a+b+c+d+e
Rate per sqm=(a+b+c+d+e)/10
This item is a proprietary item available in market as
Note pre-packed polymer concrete and is required to be
applied as per instructions of the manufacturer

17.07 2801 Sealing of cracks/porous concrete with Epoxy Grout


by injection through nipples complete as per clause
2803.1
Unit=kg
Taking output=1kg
a) Material
Epoxy including 10 percent wastage kg 1.100
b) Labour
Mate day 0.008
Masdoor(skilled) day 0.100
Masdoor day 0.100
c) Machinery
Epoxy injection gun hour 0.100
d) Overhead charges
e) Contractor's profit
Rate per kg= (a+b+c+d+e)

17.08 2804
Applying epoxy mortar over leached, honey combed
and spalled concrete surface and exposed steel
reinforcement complete as per Technical
Specification.
unit=sqm
Taking output=10sqm
Assuming average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.500
Epoxy mortar kg 2.200
Epoxy resin-hardener mix for seal coat. kg 2.000
Add 3 percent cost of material for other consumables
like acetone etc and to cover wastage.
b) Labour
Mate day 0.040
Masdoor(skilled) day 0.500
Masdoor day 0.500
c) Overhead charge
d) Contractor's profit
Cost for 10 sqm=a+b+c+d
Rate per sqm=(a+b+c+d)/10

17.09 2807

Removal of defective concrete, cleaning the surface


thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates,
water and quick setting compound in the proportion
as per clause 2807.1 sand and coarse aggregates
conforming to IS:383 and table 1 of IS: 9012
respectively, water cement ratio ranging from 0.35
to 0.50 density of gunite not less than 2000 kg/cum
,stength not less than25 Mpa and workmanship
conforming to clause 2807.6.
Unit=sqm
Taking output=10sqm,
40mm average thickness
a) Labour
Mate day 0.040
Mazdoor day 0.500
Mazdoor(skilled) day 0.500
b) Machinery
Air compressor 250 cfm hour 1.000
shotcreting equipment hour 1.000
water tanker 6KL capacity hour 0.020
c) Material
Cement kg 120.000
Sand cum 0.150
Coarse aggregate of size 4.75mm cum 0.150
Quick setting compound kg 2.500
Water KL 0.100
d) Overhead charges
e) Contractor's profit
Cost for 10 sqm=a+b+c+d+e
Rate per sqm=(a+b+c+d+e)/10
17.10 2800 Appling pre-packed cement based polymer mortar
of strength 45 Mpa at 28 days for replacement of
spalled concrete
Unit=sqm
Taking output=10sqm
assumed thickness-10mm
a) Material
Acrylic polymer bonding coat Litre 1.400
Pre-packed cement based polymer mortar of strength 45
Mpa at 28 days Kg 12.000
Add 3 percent of (a) above for wastage
b) Labour
Mate day 0.040
Mazdoor (skilled) day 0.500
Mazdoor day 0.500
c) Overhead charges
d) Contractor's profit
Cost for 10 sqm=a+b+c+d
Rate per sqm=(a+b+c+d)/10

17.11 2805 Epoxy bonding of new concrete to old concrete


Unit= sqm
Taking output=10sqm
a) Material
Epoxy resing with pot life not leess than 60-90 minutes
and satisfying testing as per clause 2803.9 Add 3
percent of (a) above for wastage kg 8.000
b) Labour
Mate day 0.040
Mazdoor (skilled) day 0.500
Mazdoor day 0.500
c) Overhead charges
d) Contractor's profit
Cost for 10sqm=a+b+c+d
Rate per sqm=(a+b+c+d)/10

17.12 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestressing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification.
Span assumed: 25m
No. of cables:4
No. of anchorage:8
Unit=MT
Taking output = 1MT
Assume 12.7mm dia.Strand in 12T13 system Weight-
9.42 kg/m of cable.
a) Material
HTS strand including 5 percent wastage and extra
length of jacking tonne 1.050
HDPE pipes 75mm dia including 5 percent wastage meter 112.000
cement for grouting kg 400.000
Tube anchorage set complete with bearing
plate,permanent wedges etc. each 8.000
Epoxy kg 6.000
MS plates for deviator(where deviator blocks are not
provided) tonne 2.100
Add 20 percent cost of material for other materials like
lead sheet,sleeves,deviator fixture etc.
b) Labour
i) For making holes in the structure
Mate day 0.240
Mazdoor(Semi-skilled) day 3.000
Mazdoor day 3.000
ii) For making and fixing anchorages for cables and
placement of cables.
Mate day 0.440
Blacksmith day 3.000
Mzdoor day 8.000
iii) For prestressing
Mate/Supervisor day 0.134
Fitter day 0.700
Mazdoor day 2.650
iv) For grouting
Mate/Supervisor day 0.134
Mason day 0.700
Mazdoor day 2.650
c) Machinery
stressing jack with pump hour 4.000
Grouting pump with agitator hour 1.350
d) Overhead charge
e) Contractor's profit
Rate per MT=(a+b+c+d+e)

17.13 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestressing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification.
Span assumed: 50m
No.of cables:4no
No.of anchorages:8no.
Unit=MT
Taking output = 3.10MT
Assume 12.7mm dia.Strand in 19T13 system Weight-
14.73 kg/m of cable.
a)Material
HTS strand including 5 percent wastage and extra
length for jacking tonne 3.100

HDPE pipes 90mm dia including 5 percent wastage meter 224.000


Cement for grouting tonne 1.010
Tube anchorage set complete with bearing plate,
permanent wedges etc each 8.000
Epoxy kg 10.000
MS plates for deviator(where deviator blocks are not
provided) tonne 7.000
Add 20 percent cost of material for other materials like
lead sheet,sleeves,deviator fixture etc.
b)Labour
i)For making holes in the structure
Mate day 0.080
Mazdoor(Semi-skilled) day 8.000
Mazdoor day 8.000
ii)For making and fixing anchorages for cables and
placement of cables.
Mate day 1.280
Blacksmith day 7.000
Mazdoor day 25.000
iii) For prestressing
Mate/Supervisor day 0.200
Fitter day 1.000
Mazdoor day 4.000
iv) For grouting
Mate/Superviser day 0.260
Mason day 1.500
Mazdoor day 5.000
c) Machinery
stressing jack with pump hour 7.000
Grouting pump with agitator hour 3.000
d) Overhead charges
e)Contractor's profit
Cost for 3.10 MT=a+b+c+d+e
Rate per MT=(a+b+c+d+e)/3.10
17.14 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestressing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification.
Span assumed:100
No. of cables:6 No.
No. of anchorages:12 no.
Unit=MT
Taking output = 9.28MT
Assuming 12.7mm dia Strand in 19T13 system.Weight
14.73kg/m of cable
a) Material
HTS strand including 5 percent wastage and extra
length for jacking tonne 9.280
HDPE pipes 90 mm dia including 5 percent wastage meter 672.000
Cement for grouting tonne 3.040
Tube anchorage set complete with bearing
plate,permanent wedges etc. each 12.000
Epoxy kg 14.000
MS plates for deviator(where deviator blocks are not
provided) tonne 20.000
Add 20 percent cost of material for other materials like
lead sheet,sleeves,deviator fixture etc.
b)Labour
i) For making holes in the structure
Mate day 1.720
Mazdoor(Semi-skilled) day 18.000
Mazdoor day 25.000
ii) For making and fixing anchorages for cables and
placement of cables.
Mate day 4.000
Blacksmith day 20.000
Mazdoor day 80.000
iii) For prestressing
Mate/Supervisor day 0.300
Fitter day 1.500
Mazdoor day 6.000
iv) For grouting
Mate/Supervisor day 1.000
Mason day 5.000
Mazdoor day 20.000
c) Machinery
stressing jack with pump hour 10.000
Grouting pump with agitator hour 10.000
d) Overhead charges
e)Contractor's profit
Cost for 9.28MT=a+b+c+d+e
Rate per MT=(a+b+c+d+e)/9.28

17.15 2810 Replacement of Bearings complete as per Technical


Specification
Unit=No
Taking output=3No.
Lifting of superstructure span by jacking up from
beloww i.e by placing the jacks on pier/abutment caps
for span length of 30m
a)Labour
Mate day 0.640
Mazdoor(skilled) day 4.000
Mazdoor day 12.000
b)Machinery
i)Hire charge for jack of 40tonne lifting
capacity(Lifting of span) day 3.000
Material
Wooden packing cum 0.150
Cost of bearing (Replacement of bearing) each 3.000
d)Overhead charges
e)Contractor's profit
Cost of repair per 3 bearings =a+b+c+d+e
Rate of repair per bearing=(a+b+c+d+e)/3

Note The work entails replacement of all the bearings on one


side of the span

17.16 2811 Rectification of Bearings as per Technical


Specifications
Unit=1 No
Taking output=3 No.
Lifting of superstructure span byjacking up from
below i.e by placing the jacks on pier/abutment caps
for span length of 30m
a)Labour
Mate day 0.640
Mazdoor(skilled) day 4.000
Mazdoor day 12.000
b)Machinery
i)Hire charge for jack of 40 tonne lifting capacity each 3.000
c)Material
Cost of parts to be replaced for 3 bearings each 3.000
Wooden packing cum 0.150
d)Overhead charges
e)Contractor's profit
Cost of repair of 3 bearinsg=a+b+c+d+e
Rate of repair per bearing = ((a+b+c+d+e)/3

Note The rectification of 3 bearings included in this analysis


are on the same side of the span

17.17 Replacement of expansion joints complete as per


drawings
Unit=1RM
Taking output=12RM
a)Material
Epoxy for bonding new concrete to old concrete @ 0.8
kg/sqm kg 9.600
M-30 grade cement concrete excluding OH&CP (Rate
taken from item 14.01c (i) (p) cum 3.600
b)Labour
Removal of old expansion joint including breaking of
concrete, cutting of lugs and shifting of broken material
etc.
Mate day 0.260
Mazdoor day 6.000
Mazdoor (skilled) day 0.500
c)Overhead charges
d)Contractor's profit
Cost of replacement of12 RM=a+b+c+d
Rate per RM=(a+b+c+d)/12

The rate for the installation of new expansion joints


Note may be taken from the chapter on superstructure.
Broken concrete will have to be replaced which has
been included in this analysis.

17.18 Replacement of Damaged Concrete Railing.


Unit =RM
Taking output = 10 RM
a)Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.200
Mazdoor day 5.000
b)Machinery
Tractor-trolly for disposal of dismantled material hour 1.000
c)Overhead charge
d)Contractor's profit
Cost for 10 M =a+b+c+d
Rate per meter = (a+b+c+d)/10

Note The rate for the provision ofnew railing may be


adopted from the chapter on superstructure

17.19 Replacement of Crash barrier.


Unit =RM
Taking output = 10M
a) Labour
Labour for dismantaling old railing and disposal of
dismantled material.
Mate day 0.400
Mazdoor day 10.000
b) Machinery
Tractor-trolley for disposal of dismantled material. hour 1.000
c) Overhead charged
d) Contractor's profit
Cost for 10m = a+b+c+d
Rate per meter = (a+b+c+d)/10
The rate for the construction of new crash barrier may
Note be adopted from chapter 8 0n Traffic and
Transportation.

17.20 Replacement of Damaged mild Steel Railing


Unit = RM
Taking output = 10M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.160
Mazdoor day 4.000
b) Machinery
Tractor-troiiey for disposal of dismantled material hour 1.0
c)Overhead charges
d)Contractor's profit
Cost for 10 m=a+b+c+d
Rate per mrter = (a+b+c+d)/10

17.21 Repair of Crash Barrier

Repair of conrete crash barrier with cement concrete of


M-30 grade by cutting and trimming the damaged
portion to a regular shape,cleaning the area to be
repaired thoroughly applying cement concrete after
erection of proper form work.
Unit = Running meter
Taking output = 10m
it is assumed that damage is to the extent of 10 percent
of the volume of concrete. This will require 0.30 cum
of concrete
a) Manpower*
Mate day 0.04
Mazdoor day 1
*For dismantling and trimming the surface to a regular
shape and removal of damaged material.
b)Material
M-30 grade cement concrete excluding OH &CP (Rate
taken from item 14.01c(i)(p) cum 0.3
This may be priced based on the rate given the chapter
of superstructure
c)Overhead
d)Contractor's profit
Cost for 10m = a+b+c+d
Rate per meter = (a+b+c+d)/10

17.22 Repair of RCC Railing


Carrying out repair of RCC M-30 railing to bring it to
the original shape
Unit = Running meter
Taking output = 10M

It is assumed that damage is to the extent of 10 percent.


a)Material
M - 30 grade cement concrete excluding OH & CP
(Rate taken from items 14.01 C (i)(p) cum 0.100
HYSD bar reinforcement Rate as per item No
14.02(Excluding OH & CP)A tonne 0.013
b)Labour*
Mate day 0.008
Mazdoor day 0.200
*For dismantaling and trimming the surface to a regular
shape and removal of damaged material.
c) Overhead
d)Contractor's profit
Cost of 10m = a+b+c+d
Rate per meter = (a+b+c+d)/10

17.23 Repair of Steel Railing

Repair of Steel Railing to bring it to the original shape


It is assumed that the damaged to the steel railing is to
the extent of 10 percent.
Unit = Running meter
Taking output = 10 M
Material
Mild steelISMC series kg 29.000
Flat iron kg 10.000
MS bolt and nuts kg 1.000
Add 5 percent of cost of material for painting
b)Labour
Mate day 0.016
Mazdoor(Skilled) day 0.200
Mazdoor day 0.200
c)Overhead charge
d)Contractor's profit
Cost of repair for 10m =a+b+c+d
Cost per meter = (a+b+c+d)/10

17.24 Mobile Bridge Inspection Unit (MBIU)


Inspection of bridge by using of Mobile Bridge
Inspection Unit(MBIU)
Unit = Km
Taking Output = 50km
a) Labour
Mate day 1.360
Mazdoor(skilled) day 34.000
Mazdoor day 34.000
b)Machinery
Mobile Bridge Inspection Unit (MBIU) hour 266.667
Mobile Bridge Inspection Unit (MBIU) Mobilization &
demobilization hour 15.000
Add 1 percent of cost of a+b for Miscellaneous
c) Overhead charge
d)Contractor's profit
Cost for 50km = a+b+c+d
Rate per km = (a+b+c+d)/50
(i)Average Distance has been considered 300 km for
Note mobilization at working site and same for
demobilization.
(ii) Speed of vehicle 40km/ hour has been considered.
Quantity as per project category Rate Amount
Remarks
Medium Small (Rs.) Large Medium Small

0.040 0.040
1.000 1.000

1.000 1.000
0.500 0.500

0.030 0.030
0.750 0.750

0.750 0.750
0.400 0.400
16.000 16.000
0.040 0.040
2.000 2.000
0.670 0.670

0.640 0.640

0.007 0.007
0.040 0.040
0.140 0.140

1.000 1.000

0.006 0.006
0.080 0.080

0.080 0.080
0.040 0.040
1.1 1.1

0.08 0.08
0.1 0.1
0.1 0.1

0.1 0.1

0.55 0.55
0.55 0.55

0.08 0.08
0.1 0.1
0.1 0.1
0.060 0.060
0.750 0.750
0.750 0.750

315.000 315.000

2.000 2.000

1.100 1.100

0.008 0.008
0.100 0.100
0.100 0.100

0.100 0.100

2.500 2.500
2.200 2.200
2.000 2.000

0.040 0.040
0.500 0.500
0.500 0.500

0.040 0.040
0.500 0.500
0.500 0.500

1.000 1.000
1.000 1.000
0.020 0.020

120.000 120.000
0.150 0.150
0.150 0.150
2.500 2.500
0.100 0.100
1.400 1.400

12.000 12.000

0.040 0.040
0.500 0.500
0.500 0.500

8.000 8.000

0.040 0.040
0.500 0.500
0.500 0.500
1.050 1.050
112.000 112.000
400.000 400.000

8.000 8.000
6.000 6.000

2.100 2.100

0.240 0.240
3.000 3.000
3.000 3.000

0.440 0.440
3.000 3.000
8.000 8.000

0.134 0.134
0.700 0.700
2.650 2.650

0.134 0.134
0.700 0.700
2.650 2.650

4.000 4.000
1.350 1.350
3.100 3.100

224.000 224.000
1.010 1.010

8.000 8.000
10.000 10.000

7.000 7.000

0.080 0.080
8.000 8.000
8.000 8.000

1.280 1.280
7.000 7.000
25.000 25.000

0.200 0.200
1.000 1.000
4.000 4.000

0.260 0.260
1.500 1.500
5.000 5.000

7.000 7.000
3.000 3.000
9.280 9.280
672.000 672.000
3.040 3.040

12.000 12.000
14.000 14.000

20.000 20.000

1.720 1.720
18.000 18.000
25.000 25.000

4.000 4.000
20.000 20.000
80.000 80.000

0.300 0.300
1.500 1.500
6.000 6.000

1.000 1.000
5.000 5.000
20.000 20.000

10.000 10.000
10.000 10.000

0.640 0.640
4.000 4.000
12.000 12.000

3.000 3.000

0.150 0.150
3.000 3.000

0.640 0.640
4.000 4.000
12.000 12.000

3.000 3.000

3.000 3.000
0.150 0.150

9.600 9.600

3.600 3.600

0.260 0.260
6.000 6.000
0.500 0.500

0.200 0.200
5.000 5.000

1.000 1.000
0.400 0.400
10.000 10.000

1.000 1.000

0.160 0.160
4.000 4.000

1.0 1.0
0.04 0.04
1 1

0.3 0.3

0.100 0.100

0.013 0.013

0.008 0.008
0.200 0.200
29.000 29.000
10.000 10.000
1.000 1.000

0.016 0.016
0.200 0.200
0.200 0.200

1.360 1.360
34.000 34.000
34.000 34.000

266.667 266.667

15.000 15.000
CHAPTER 18
TUNNEL WORK
Sr. No Ref.to Description Unit Quantity as per Project Category
M
Large Medium
18.01 304 Excavation in Ordinary Rock using Hydraulic
Excavator and Tippers with Disposal upto
1000 metres.
Excavation for Portal in Ordinary Rock with
hydraulic excavator including cutting and
loading in tippers, trimming bottom and side
slopes, in accordance with requirements of
lines, grades and cross sections, and disposal
of excavated materials including all lifts and
lead upto 1000m

Unit = cum
Taking Output = 60.00 cum
a) Labour
a) Labour day 0.040 0.040
Mazdoor day 1.000 1.000
b) Machinery
Excavator 1.1 cum bucket capacity hour 8.214 8.214
Jack hammer hour 8.214 8.214
Loading & unloading charges for disposed cum 72 72
of grabbed material (using by10 cum
capacity Tipper &1 Cum capacity Loader)

Tipper 10 cum capacity for t.km 120 120


transportation to dumping yard
considering lead @ 1 km
Total cost Without O.H.&C.P.
C) Over head charge on (a+b) (@25%) (@25%)
d) Contractor's profit on (a+b+c) (@10%) (@10%)
Cost for 60 cum = (a+b+c+d)
Rate per cum= (a+b+c+d) / 60
18.02 303&3 Excavation in Hard Rock (blasting prohibited)
04
Excavation for Portal in Hard Rock (blasting
prohibited) with hydraulic excavator including
cutting and loading in tippers, trimming
bottom and side slopes, in accordance with
requirements of lines, grades and cross
sections, and and disposal of excavated
materials including all lifts and lead upto
1000m

Unit = cum
Taking Output = 50.00 cum
Labour
Mate day 0.040
Mazdoor day 1.000
b) Machinery
Excavator 1.1 cum bucket capacity hour 10.039 10.039
Jack hammer hour 10.039 10.039
Loading & unloading charges for disposal cum 60.000 60.000
of grabbed material (using by10 cum
capacity Tipper &1 Cum capacity Loader)

Tipper 10 cum capacity for transportation t.km 100.000 100.000


to dumping yard considering lead @ 1 km
Credit for excavated rock found suitable cum 30.000 30.000
for use @ 50 percent of excavated
quantity.
Total cost Without O.H.&C.P.
C) Over head charge on (a+b) (@25%) (@25%)
d) Contractor's profit on (a+b+c) (@10%) (@10%)
Cost for 50 cum = (a+b+c+d)
Rate per cum= (a+b+c+d) / 50

18.03 304 Excavation in Soil using Hydraulic Excavator


and Tippers with Disposal upto 1000 metres.

Excavation for portal in soil with hydraulic


excavator including cutting and loading in
tippers, trimming bottom and side slopes, in
accordance with requirements of lines,
grades and cross sections, and and disposal of
excavated materials including all lifts and lead
upto 1000m

Unit = cum
Taking Output = 350.00 cum
a) Labour
a) Labour day 0.040 0.040
Mazdoor day 1.000 1.000
b) Machinery
Excavator 1.1 cum bucket capacity hour 5.024 5.024
Loading & unloading charges for hour 5.024 5.024
disposal of grabbed material
(using by10 cum capacity Tipper &1 Cum
capacityLoader)

Tipper 10 cum capacity for t.km 525.000 525.000


transportation to dumping yard
considering lead @ 1 km
Total cost Without O.H.&C.P.
C) Over head charge on (a+b) (@25%) (@25%)
d) Contractor's profit on (a+b+c) (@10%) (@10%)
Cost for 350 cum = (a+b+c+d)
Rate per cum= (a+b+c+d) / 350

18.04 Drill steel with Drill jumboo


Excavation for tunnel by using drilling &
blasting methods in all types of rock including
cost of all materials,machinery, labour,
scaling excavated surface, marking,
ventilation, lighting, drainage, removing and
hauling the excavated muck outside tunnel
upto specified dump area and all other
ancillary operations etc.

Unit = cum
Taking Output = 480.00 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day 6.000 6.000
Majdoor (Skilled) day 2.000 2.000
b) Machinery
Three boom hydraulic Drill jumbo hour 25.067 25.067
Excavator for Scaling hour 2.000 2.000
Tipper 10 cum capacity for transportatio t.km 480x2L 480x2L
Loading & unloading charges (Using by cum 576.000 576.000
10 cum capacity tipper & 1 cum capacity
Loader)
Dozer(175HP) hour 9.600 9.600
C) Materials
Expolsives kg 576.000 576.000
Delay Detonators Nos 228.000 228.000
Electric Detonators Nos 35.000 35.000
Detonation fuse coil Meter 50.000 50.000
3.7 meter long extension rod Nos 1.043 1.043
Drifter rod Nos 0.505 0.505
R 32 shank adapter Nos 1.043 1.043
45 mm Buttom Bit Nos 3.692 3.692
Add 10 percent of cost of a+b+c towasds
Other consumable petty stores such as
blasting batteries,galvanometers and
sharpening charges of bit etc…

Total cost Without O.H.&C.P.


d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 480 cum=(a+b+c+d+e)
Rate per cum=(a+b+c+d+e)/480

18.05 304 Dewatering tunnel by pumping out water


collected by natural drainage inside tunnel
including
Dewatering in tunnel by pumping out water
collected by natural drainage inside tunnel
including providing sump wherever
necessary, cost of all materials, machinery,
labour, drainage and all other ancillary
operations etc., complete.

Unit=Hour
Taking output=20000 Hour
a) Labour
Mate day 100.00
Mazdoor day 2500.00
b) Machinery
Water Pump 10 HP hour 20000.00
C) Materials
GI Pipe 100mm Dia Meter 500.00
Flange Kg 41.67
Nut&Bolt Kg 133.33
Bracket Kg 1125.00
Credit for salvage value of GI Pipe @ 30 Meter 150.00
percent
Total cost Without O.H.&C.P.
d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 20000hour =(a+b+c+d+e)
Rate per hour = (a+b+c+d+e) / 20000

18.06 304 Providing , Fitting and Placing of Ribs


Providing , Fitting and Placing of Ribs
including Fabrication, Erection,Temporary
fixture, Handling of material inside fabrication
workshop, final matching, field welding and
complete as per Drawing and Technical
Specifications.

Unit=Tonne
Taking output=26Tonne
a) Labour
Mate day 0.800
Mazdoor day 10.000
Mazdoor(Semi-Skilled) day 5.000
Welder day 5.000
b) Machinery
Rotating Telehandlers hour 37.180
C) Materials
ISMB 350 (Including 0.25% Wastage) Tonne 20.732
MS Channel ISMC 75 (Including 0. 25% Tonne 3.830
Wastage)
MS Plate 200x200x12mm (Including Tonne 1.504
0.25% Wastage)
Nuts & Bolts (M 16x40) Kg 151.200
Add 40 per cent of cost of a+b+c
towards of Fabrication,
Erection,Temporary fixture, Handling of
material, final matching and field
welding etc.

Total cost Without O.H.&C.P.


d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 26 Tonne =(a+b+c+d+e)
Rate perTonne = (a+b+c+d+e) / 26

18.07 2807 Shotcreting with Steel fibre reinforced micro


silica shotcrete (SFRS)
Shotcreting to upper bench / lower bench
with steel fiber reinforced shotcrete (SFRS) ,
shotcrete compressive strength shall be 25
N/mm2 and complete as per Drawing and
Technical Specifications.

Unit=cum
Taking output=120 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day 8.000 8.000
b) Machinery
Batching Plant of capacity 120 cum / hou hour 1.333 1.333
Generator 250 KVA hour 1.333 1.333
Loader 3.1 cum capacity hour 1.333 1.333
Transit Truck agitator
For transportation (6 cum capacity) t.km. 300xL 300xL
For Loading & unloading hour 11.333 11.333
Shotcrete Machine @ 12 cum /hour hour 10.000 10.000
Compressor 500 cfm hour 10.000 10.000
c) Materials
Cement Tonne 49.440 49.440
Sand Cum 86.850 86.850
10mm to 4.76 mm Aggregate Cum 52.080 52.080
Steel Fiber Tonne 6.120 6.120
Admixture @ 4 % of Cement Kg 197.760 197.760
Micro Silca @ 6 % of Cement Kg 2966.400 2966.400
Accelerator @ 4.5 % of Cement Kg 2224.800 2224.800
Add 20 Percent of cost of a+b+c for
Wastage due to rebound.
Total cost Without O.H.&C.P.
d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 120 Cum =(a+b+c+d+e)
Rate per Cum = (a+b+c+d+e) / 120

18.08 2807 Shotcreting with welded wire mesh.


Shotcreting to upper bench / lower bench
with welded wire mesh, shotcrete
compressive strength shall be 25 N/mm2 and
complete as per Drawing and Technical
Specifications.

Unit=cum
Taking output=120 cum
a) Labour
Mate day 0.320 0.320
Mazdoor day 8.000 8.000
b) Machinery
Batching Plant of capacity 120 cum / hou hour 1.333 1.333
Generator 250 KVA hour 1.333 1.333
Loader 3.1 cum capacity hour 1.333 1.333
Transit Truck agitator
For transportation (6 cum capacity) t.km. 300xL 300xL
For Loading & unloading hour 11.333 11.333
Shotcrete Machine @ 12 cum /hour hour 10.000 10.000
Compressor 500 cfm hour 10.000 10.000
c) Materials
Cement Tonne 49.440 49.440
Sand Cum 86.850 86.850
10mm to 4.76 mm Aggregate Cum 52.080 52.080
Wire mesh (Including 10 % for lapping.) Sqm 1320.000 1320.000
Admixture @ 4 % of Cement Kg 197.760 197.760
Micro Silca @ 6 % of Cement Kg 2966.400 2966.400
Accelerator @ 4.5 % of Cement Kg 2224.800 2224.800
Add 20 Percent of cost of a+b+c for
Wastage due to rebound.
Total cost Without O.H.&C.P.
d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 120 Cumr =(a+b+c+d+e)
Rate perTonne = (a+b+c+d+e) / 120

18.09 2806& Providing and fixing 25 mm diameter 3 meter


3200 long steel rock bolts including drilling 45 mm
dia holes, plate, nuts, cement grout, cost of
all materials, machinery, labour, ventilation,
lighting, drainage and all other ancillary
operations etc. complete as per Drawing and
Technical Specifications.

Unit=Number
Taking output=155 Nos
a) Labour
Mate day 0.480 0.480
Mazdoor day 8.000 8.000
Mason (Iind class) day 4.000 4.000
b) Machinery
Single boom Hydraulic Drill Jumbo. hour 25.833 25.833
c) Materials
3.7 m .long extension rod. Nos 1.011 1.011
R32 shank adapter. Nos 1.011 1.011
45mm Dia cross bit. Nos 3.577 3.577
25mm tor Steel ( Including 25% Tonne 1.927 1.927
Wastage)
Add 15 % of cost of a+b+c towards
cutting,making tip,
Threading,nut,plate,grouting and bit
sharpening etc..

Total cost Without O.H.&C.P.


d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 155 Nos =(a+b+c+d+e)
Rate perNumber = (a+b+c+d+e) /155

18.10 2806& Providing and fixing 32 mm diameter 7 meter


3200 long steel rock bolts including drilling 51 mm
dia holes, plate, nuts, cement grout, cost of
all materials, machinery, labour, ventilation,
lighting, drainage and all other ancillary
operations etc. complete as per Drawing and
Technical Specifications.

Unit=Number
Taking output=70 Nos
a) Labour
Mate day 0.600 0.600
Mazdoor day 10.000 10.000
Mason (Iind class) day 5.000 5.000
b) Machinery
Single boom Hydraulic Drill Jumbo. hour 17.500 17.500
c) Materials
3.7 m .long extension rod. Nos 1.065 1.065
R32 shank adapter. Nos 1.065 1.065
32mm coupling sleeve Nos 1.065 1.065
51mm Dia button bit Nos 3.769 3.769
32mm tor Steel (Including 2.5% Wastage) Tonne 3.237 3.237
Add 15 % of cost of a+b+c towards
cutting,making tip,
Threading,nut,plate,grouting and bit
sharpening etc..
Total cost Without O.H.&C.P.
d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 70 Nos =(a+b+c+d+e)
Rate perNumber = (a+b+c+d+e) / 70

18.11 2806 Grouting with Cement


Grouting cement slurry in grout holes under
specified pressure for consolidation / contact
grouting including cost of all materials,
machinery, labour, predrilling wherever
necessary, ventilation,lighting, drainage and
other ancillary operations etc. complete as
per Drawing and Technical Specifications.

Unit=Tonne
Taking output=1.5 Tonne
a) Labour
Mate day 0.080 0.080
Mazdoor day 2.000 2.000
b) Machinery
Grouting Machine @ 25 Bags Per Hours hour 1.200 1.200
Pump 10 HP. hour 1.200 1.200
Single boom Hydraulic . hour 1.250 1.250
c) Materials
Cement (Including 1% Wastage) Tonne 1.515 1.515
Cost of Water (Water /Cement Ratio- KL 0.606 0.606
0.4)
3.7 m .long extension rod. Nos 0.076 0.076
R32 shank adapter. Nos 0.076 0.076
32mm coupling sleeve Nos 0.076 0.076
51mm Dia cross bit Nos 0.269 0.269
Add 5 % of cost of a+b+c towards
cutting,making tip,
Threading,nut,plate,grouting and bit
sharpening etc..

Total cost Without O.H.&C.P.


d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 1.5Tonne =(a+b+c+d+e)
Rate perTonne = (a+b+c+d+e) /1.5
18.12 1700 Furnishing and Placing Reinforced cement
concrete in Tunnel Work as per drawing and
Technical Specification
A RCC Grade M 20
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a)Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.05 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
B RCC Concrete M 25
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a)Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.07 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
C RCC Concrete M 30
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.09 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
D RCC Concrete M 35
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.11 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
E RCC Concrete M 40
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.12 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
F RCC Concrete M 45
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.13 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
G RCC Concrete M 50
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.14 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
H RCC Concrete M 55
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.15 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
I RCC Concrete M 60
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.16 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.12 1700 Furnishing and Placing Reinforced cement


concrete in Tunnel Work as per drawing and
Technical Specification
J RCC Concrete M 65
Using Batching Plant ,Transit Mixer and
Concrete Pump.
Unit=Cum
Taking output=120Cum
a) Material
Per Cum Basic Cost
(Rate taken from sub analysis -21.17 cum 120.000 120.000
Water for curing KL 63.000 63.000
b) Labour
For pouring and placing
Mate day 0.232 0.232
Mason day 1.500 1.500
Mazdoor day 4.300 4.300
c) Machinery
Transit Truck agitator
For Transportation (6cum Capacity),L1- t.km 300xL1 300xL2
Lead in Kilometer.
For unloading hour 2.600 2.600
Hydroulic boom placer pump hour 2.600 2.600
Water tanker (Speed @ 20km /hour and
return speed @ 30 km /hr.and 30 mins
for unloading)
(i)12KL capacity. hour 0.583xL1+ 0.583xL1+
3.5 3.5
d) Formwork and staging 40 percent of (a+b+c)
Total cost Without O.H.&C.P.
e) Overhead charge on (a+b+c+d) (@25%) (@25%)
f) Contractor's profit on (a+b+c+d+e) (@10%) (@10%)
Cost for 120 cum =(a+b+c+d+e+f)
Rate per cum = (a+b+c+d+e+f) /120

18.13 1600 Supply, Fitting and placing HYSD bar


reinforcement in Tunnel Work complete as
per drawing and technical specifications.

Unit-MT
Taking out put =8 MT
a) Material
MS bars including 5 % overlaps and Tonne 8.400 8.400
Wastage
Binding wire Kg 48.000 48.000
b) Labour for straightening,cutting,bending,
shifting to site ,tying and placing in position

Mate day 0.160 0.160


Blacksmith day 1.000 1.000
Mazdoor day 3.000 3.000
c) Machinery
Cutting Machine hour 8.000 8.000
Bending Machine hour 8.000 8.000
Electric Generator 15 KVA hour 8.000 8.000
Tipper
Tipper forTtransportation
(i) 14 cum capacity t.km 8xL 8xL
Loading and Unloading Time
(i) 14 cum capacity hour 2.000 2.000
Light weight Crane
At cutting bending yard hour 2.000 2.000
At site hour 2.000 2.000
Total cost Without O.H.&C.P.
d) Overhead charge on (a+b+c) (@25%) (@25%)
e) Contractor's profit on (a+b+c+d) (@10%) (@10%)
Cost for 8MT =(a+b+c+d+e)
Rate per MT = (a+b+c+d+e) / 8
K
s per Project Category Rate Amount Remarks

Small Large Medium Small

0.040
1.000

8.214
8.214
72

120

(@25%)
(@10%)
10.039
10.039
60.000

100.000

30.000

(@25%)
(@10%)
0.040
1.000

5.024
5.024

525.000

(@25%)
(@10%)

0.320
6.000
2.000

25.067
2.000
480x2L
576.000

9.600

576.000
228.000
35.000
50.000
1.043
0.505
1.043
3.692

(@25%)
(@10%)

(@25%)
(@10%)

(@25%)
(@10%)
0.320
8.000

1.333
1.333
1.333

300xL
11.333
10.000
10.000

49.440
86.850
52.080
6.120
197.760
2966.400
2224.800

(@25%)
(@10%)
0.320
8.000

1.333
1.333
1.333

300xL
11.333
10.000
10.000

49.440
86.850
52.080
1320.000
197.760
2966.400
2224.800

(@25%)
(@10%)

0.480
8.000
4.000
25.833

1.011
1.011
3.577
1.927

(@25%)
(@10%)

0.600
10.000
5.000

17.500

1.065
1.065
1.065
3.769
3.237
(@25%)
(@10%)

0.080
2.000

1.200
1.200
1.250

1.515
0.606

0.076
0.076
0.076
0.269

(@25%)
(@10%)
120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)
120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600
0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)
120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000
0.232
1.500
4.300

300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300
300xL3

2.600
2.600

0.583xL1+3
.5

(@25%)
(@10%)

120.000
63.000

0.232
1.500
4.300

300xL3

2.600
2.600
0.583xL1+3
.5

(@25%)
(@10%)

8.400

48.000

0.160
1.000
3.000

8.000
8.000
8.000

8xL

2.000

2.000
2.000

(@25%)
(@10%)
Quantity as per peroject category
Sr No Ref. to M. Description Unit
Large Medium
19.01 Suggestive Noise Barriers
(i) Masonry wall
Unit = cum
Taking output= 5 cum
a) Material
Brick 1st class each 2500 2500
Cement mortar 1:3 (Rate as sub
analysis) cum 1.2 1.2
water for curing KL 2.415 2.415
b) Labour
Mate day 0.48 0.48
Mason day 4 4
Mazdoor day 8 8
c) Machinery
Water tanker ( speed @ 20km/hr and
return speed @ 30km/hr and 30 mins
for unloading)
(i) 16KL
(II) 12 KL
(III) 6 KL
d) Overhead charges
e) Contractor's profit
Cost for 5 Cum=a+b+c+d+e
Rate per Cum= (a+b+c+d+e)/5
(ii) Galvanized steel plain sheet
Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.06 0.06
Blacksmith day 0.5 0.5
Mazdoor day 1 1
b) Material
Galvanized steel plain sheet (5 mm)
including 5% wastage kg 3.15 3.15
MS Angle kg 154.5 154.5
Add 10 percent of cost of (a+b) towards
of drilling, nut & bolt etc.
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm=a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
Rate for excavation, cement concrete
Note:
M-25 and painting may be taken from
respective chapters.
(iii) Acylic noise barrier sheet
Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.06 0.06
Blacksmith day 0.5 0.5
Mazdoor day 1 1
b) Material
Acylic noise barrier sheet (3 mm)
including 5% wastage sqm 105 105
MS Angle kg 154.5 154.5
Add 10 percent of cost of (a+b) towards
of drilling, nut & bolt etc.
c) Overhead charges
d) Contractor's profit
Cost for 100 sqm=a+b+c+d
Rate per sqm= (a+b+c+d)/100
Rate for excavation, cement concrete
Note: M-25 and painting may be taken from
respective chapters.

19.02 Suggestive
Construction of bamboo crib wall
complete as per drawing and
additional Technical specification.
Unit= Rm
Taking output= 1 Rm
a) Labour
Mate day 0.016 0.016
Mazdoor skilled day 0.1 0.1
Mazdoor day 0.3 0.3
b) Machinery
Water tanker 6 KL capacity hour 0.008 0.008
c) Materials
Bamboos ( For Horizontal Beam) Rm 4 4
Live stake stump/ Bamboos (vertical) Rm 1.5 1.5
Live Stake Stump/ Bamboos
(Horizontal) Rm 1 1
Binding Material Rm 2 2
Cost of water KL 0.05 0.05
Grass Kg 1.5 1.5
d) Overhead charges
e) Contractor's profit
Cost for 1 Rm=a+b+c+d+e
Rate per Rm= (a+b+c+d+e)

19.03 Suggestive
Construction of Fascines with a
bundle of sticks complete as per
drawing and additional Technical
specification.
Unit= Rm
Taking output= 10 Rm
a) Labour
Mate day 0.1 0.1
Mazdoor skilled day 0.5 0.5
Mazdoor day 2 2
b) Machinery
Tractor-trolley hour 1 1
c) Materials
Hard wood sticks Nos 8 8
Binding Material Rm 5 5
d) Overhead charges
e) Contractor's profit
Cost for 10 Rm=a+b+c+d+e
Rate per Rm= (a+b+c+d+e)/10

19.04 Suggestive
Construction and laying of brush
layers across the slope complete as
per drawing and additional Technical
specification.
Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.12 0.12
Mazdoor for preparation of ground day 3 3
b) Machinery
Water tanker 6KL capacity including
watering for 3 months hour 2 2
Tractor-trolley hour 0.5 0.5
c) Material
Live Sods (0.6m length) Nos. 1000 1000
Farm yard manure @ 0.18 cum per 100
sqm at site of work cum 0.18 0.18
Cost of water KL 12 12
Grass kg 100 100
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm=a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

19.05 Suggestive
Construction of vegetative Palisades
in Rills using hard wood cutting
complete as per drawing and
additional Technical specification
Unit= Rm
Taking output= 2 Rm
a) Labour
Mate day 0.012 0.012
Mazdoor skilled day 0.1 0.1
Mazdoor day 0.2 0.2
b) Machinery
Tractor-trolley hour 0.25 0.25
c) Materials
Horizontal Live Sods (2M Length) Nos. 2 2
Vertical Live Sods (2M Length) Nos. 40 40
Cost of water KL 0.1 0.1
Binding Material Rm 5 5
d) Overhead charges
e) Contractor's profit
Cost for 2 Rm=a+b+c+d+e
Rate per Rm= (a+b+c+d+e)/2

19.06 Suggestive
Laying of Palisabes in Slopes
complete as per drawing and
aditional Technical specification.
Unit= sqm
Taking output= 100 sqm
a) Labour
Mate day 0.12 0.12
Mazdoor for preparation of ground day 3 3
b) Machinery
Water tanker 6KL capacity including
watering for 3 months hour 2 2
Tractor-trolley hour 0.5 0.5
c) Material
Live Sods (0.6m length) Nos. 1000 1000
Farm yard manure @ 0.18 cum per 100
sqm at site of work cum 0.18 0.18
Cost of water KL 12 12
Grass kg 100 100
d) Overhead charges
e) Contractor's profit
Cost for 100 sqm=a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

19.07 Suggestive Dust suppression


Sprinkling of water in the settlement
area as per instruction of Engineer.
Unit= 6 KL
Taking output= 6 KL
a) Labour
Mate day 0.008 0.008
Mazdoor day 0.2 0.2
b) Machinery
Water tanker 6 KL capacity hour 0.75 0.75
c) Materials
Cost of Water KL 6 6
d) Overhead charges
e) Contractor's profit
Cost for 6 KL =a+b+c+d+e

19.08 Suggestive Water Quality Monitoring


(Grab Sample as per the monitoring
locations mention in the EIA/EMP
report or one sample/ 10km length
Unit=Number
Taking output= One Number
a) Cost of Water Quality monitoring Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.09 Suggestive
Soil Quantity Monitoring (Grab
Sample as per the monitoring
locations mention in the EIA/EMP
report or one sample/10 km length
Unit=Number
Taking output= One Number
a) Cost of Soil Quality monitoring Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c
19.10 Suggestive
Ambient Air Quality Monitoring 24
hrs continuous for location as
mention in the EIA/EMP report or
one monitoring location within 10km
radius
Unit=Number
Taking output= One Number
a) Cost of Ambient Air Quality Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.11 Suggestive
Ambient Noise Monitoring 24 hour
continuous (To be carried out as per
the location as mention in the
EIA/EMP report
Unit=Number
Taking output= One Number
a) Cost of Ambient Noise Monitoring 24
hour continuous Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.12 Suggestive Consent Approvals (Once)


Unit=Number
Taking output= One Number
(i) a) Consent to Establish (CTE) Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.12 (ii) a) Consent to Operate (CTO) Nos. 1 1


b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.13 Suggestive Compliance submission for Consent


Approvals (Half Yearly)
Unit=Number
Taking output= One Number
19.13 (i) a) compliance submission for Consent
to Establish (CTE) Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.13 (ii) a) compliance submission for Consent


to Operate (CTO) Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.14 Suggestive Environmental Clearance


Compliance (Half Yearly)
Unit=Number
Taking output= One Number
a) Cost of Workshop Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.15 Suggestive Environmental Workshops (Half


Yearly)
Unit=Number
Taking output= One Number
a) Cost of Workshop Nos. 1 1
b) Overhead charges
c) Contractor's profit
Rate per number = a+b+c

19.16 Suggestive Pollution prevention

Silt fencing on either side of the streams


and rivers including erection and
maintenance for entire construction
phase
Unit= Rm
Taking output= 100 Rm
a) Labour
Mate day 0.08 0.08
Mazdoor day 2 2
b) Machinery
Tractor-trolley hour 2 2
c) Materials
Silt Fence Sheet Sqm 100 100
Hard wood sticks Nos 34 34
d) Overhead charges
e) Contractor's profit
Cost for 100 Rm=a+b+c+d+e
Rate per Rm= (a+b+c+d+e)/100
19.17 IRC-SP-88 Road Safety Audit during
Construction Period & Maintainance
Period

Road Safety Audit during Construction


Period & Maintainance Period including
collection of Road accident data and
analysis of fatal and grievously injured
accdent with black spot identification
report, submission of GAP report, Road
Safety Audit Reports on all activities
which were planned, actually executed
and planned for the next quarter report,
Submission of audit report of work zone
safety, workshop report and Final Safety
report complete as per IRC-SP-88 and
directed by engineer
Unit= Kilometer
19.17 A Upto 50.00 Kilometer
a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 4 4


Traffic Planner Month 6 6
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 90 90
No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 90 90

c) Reports and Documents Cost

Collection of Road accident data and


analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit reportof work zone No. of
safely Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for upto 50.00 kilometer = (a+b+c+d+e)

19.17 B Between 50.00 Km. to 100 Km.


a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 6 6


Traffic Planner Month 8 8
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 126 126
No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 126 126
c) Reports and Documents Cost
Collection of Road accident data and
analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit reportof work zone No. of
safely Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for 50.00 to 100.00 kilometer = (a+b+c+d+e)

19.17 C More than 100 Km.


a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 8 8


Traffic Planner Month 10 10
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 162 162

No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 162 162
c) Reports and Documents Cost

Collection of Road accident data and


analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit reportof work zone No. of
safely Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for more than 100.00 kilometer = (a+b+c+d+e)

19.18 IRC-SP-88 Road Safety Audit during Maintenance Period


Road Safety Audit during Maintenance
Period including collection of Road
accident data and analysis of fatal and
grievously injured accdent with black
spot identification report, submission of
GAP report, Road Safety Audit Reports
on all activities which were planned,
actually executed and planned for the
next quarter report, Submission of audit
report of work zone safety (Maintenance
work), workshop report and Final Safety
report complete as per IRC-SP-88 and
directed by engineer
Unit= Kilometer
A Upto 50.00 Kilometer
a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 2 2


Traffic Planner Month 3 3
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 45 45
No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 45 45

c) Reports and Documents Cost


Collection of Road accident data and
analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit reportof work zone No. of
safely Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for upto 50.00 kilometer = (a+b+c+d+e)

B Between 50.00 Km. to 100 Km.


a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 3 3


Traffic Planner Month 4 4
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 45 45

No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 45 45

c) Reports and Documents Cost


Collection of Road accident data and
analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit report of work zone No. of
safely Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for 50.00 to 100.00 kilometer = (a+b+c+d+e)

C More than 100 Km.


a) Experts/ key Personnel

Sr. Road Safety/ Auditor / Team Leader Month 4 4


Traffic Planner Month 5 5
b) Boarding & Loading
Boarding & Loading and Per Diem for
Site Visits Days 45 45
No. of
Transportation at site and Head Office Trips 20 20
Duty travel to Site Days 45 45
c) Reports and Documents Cost
Collection of Road accident data and
analysis of fatal and grievously injured No. of
accident with black spot identification Copies 5 5
No. of
Submission of GAP report Copies 5 5

Road Safety Audit Reports on all


activities which were planned, actually
excuted and planned for the next No. of
quarter. Copies 5 5
Submission of audit reportof work zone No. of
safely (Maintenance Work) Copies 5 5
No. of
workshop report Copies 5 5
No. of
Final safety report Copies 5 5
Add 10 percent of cost of a+b+c as
Miscellaneous work
d) Overhead charges
e) Contractor's profit
Rate for more than 100.00 kilometer = (a+b+c+d+e)
s per peroject category Amount Input_Ref
Small Large Medium Small

2500

1.2
2.415

0.48
4
8

0.06
0.5
1

3.15
154.5
0.06
0.5
1

105
154.5

0.016
0.1
0.3

0.008

4
1.5

1
2
0.05
1.5
0.1
0.5
2

8
5

0.12
3

2
0.5

1000

0.18
12
100
0.012
0.1
0.2

0.25

2
40
0.1
5

0.12
3

2
0.5

1000

0.18
12
100
0.008
0.2

0.75

1
1

1
1

0.08
2

100
34
4
6

90

20
90

5
5

6
8

126

20
126

8
10

162

20
162

5
2
3

45

20
45

5
3
4

45

20
45

4
5

45

20
45

5
Summary of Sub- Analysis
CHAPTER-21
SUB-ANALYSIS OF CONCRTE/MORTAR RATE(Excluding O.H&C.P)
Ref.to
Sl No. Description Unit Rate as per Projet Category
M.
Large Medium Small
21.01 (A) Cement Mortar 1:3 (1 cement: 3 sand) cum 2971.50 2971.50 2971.50
21.01 (B) Cement Mortar 1:2 (1 cement: 2 sand) cum 3748.70 3748.70 3748.70
21.01 (C) Cement Mortar 1:4 (1 cement: 4 sand) cum 2456.60 2419.60 2395.60
21.01 (D) Cement Mortar 1:6 (1 cement: 6 sand) cum 1928.45 1928.45 1928.45
21.02 PCC 1:3:6 using batching plant
Plain Cement concrete 1:3:6 nominal mix with
crushedstone aggregate 40 mm nominal size cum 2022.10 2022.10 2022.10
mechanically mixed
21.03 Plain/Reinforced cement concrete complete as per
Drawingand Technical specefication.
PCC Grade M15 Using Batching Plant cum 2121.80 2121.80 2121.80
21.04 PCC Grade M20 Using Batching Plant cum 2483.18 2483.18 2483.18
21.05 RCC Grade M20 Using Batching Plant cum 2548.90 2548.90 2548.90
21.06 PCC Grade M25 Using Batching Plant cum 2754.10 2754.10 2754.10
21.07 RCC Grade M25 Using Batching Plant cum 2950.40 2950.40 2950.40
21.08 PCC Grade M30 Using Batching Plant cum 2780.50 2780.50 2780.50
21.09 RCC Grade M30 Using Batching Plant cum 3033.50 3033.50 3033.50
21.10 PCC Grade M35 Using Batching Plant cum 3099.50 3099.50 3099.50
21.11 RCC GradeM35 Using Batching plant cum 3182.90 3182.90 3182.90
21.12 RCC Grade M40 Using Batching Plant cum 3501.30 3501.30 3501.30
21.13 RCC Grade M45 Using Batching Plant cum 3638.50 3638.50 3638.50
21.14 RCC Grade M50 Using Batching Plant cum 4189.30 4189.30 4189.30
21.15 RCC Grade M55 Using Batching Plant cum 4266.80 4266.80 4266.80
21.16 RCC Grade M60 Using Batching Plant cum 4447.90 4447.90 4447.90
21.17 RCC Grade M65 Using Batching Plant cum 4488.30 4488.30 4488.30
21.18 601
A DLC Using Batching Plant -240 cum capacity cum 1562.00 1562.00 1562.00
Plant
B Dry Lean Concrete Sub -base Fly ash
21.18 601 ( Using Batching Plant) -240 cum capacity Plant cum 1457.60 1457.60 1457.60

21.18 601 C DLC Using Batching Plant -120 cum capacity cum 1595.00 1595.00 1595.00
Plant

21.18 601 D Dry Lean Concrete Sub -base Fly ash ( Using cum 1490.60 1490.60 1490.60
Batching Plant) -120 cum capacity Plant

21.19 602 A PQC M 35 grade Using Batching Plant-240 cum cum 3110.30 3110.30 3110.30
capacity plant
B PQC M 35 grade Using Batching Plant-240 cum
21.19 602 cum 2758.70 2758.70 2758.70
capacity(Cement-Fly ash)

21.19 602 C PQC M 35 grade Using Batching Plant-120 cum cum 3155.60 3155.60 3155.60
capacity

21.19 602 D PQC M 35 grade Using Batching Plant-120 cum cum 2749.80 2749.80 2749.80
capacity(Cement-Fly ash)
21.20 409 PCC Grade M15 grade Using Batching Plant for cum 2121.80 2121.80 2121.80
Kerb
21.21 409 PCC Grade M20 grade Using Batching Plant for cum 2483.20 2483.20 2483.20
Kerb
21.22 Cost of water KL 73.60 73.60 73.60
SUB-ANALYSIS OF CONCERTE /MORTAR RATE

Sr. No Quantity as per project category


Ref.
Description Unit
to M.

Large Medium Small


21.01 (A) Cement Mortar 1:3 (1 cement: 3 sand)
Unit =cum
Taking output =1 cum
a) Materials
Cement tonne 0.510 0.510 0.510
coarse sand cum 1.050 1.050 1.050
Cost of water KL 0.255 0.255 0.255
b) Labour
Mate
day 0.036 0.036 0.036
Mazdoor day 0.900 0.900 0.900
c)Machinery
Water tanker 12 KL capacity (speed @20 km /hr and
return speed @ 30 km / hr and 30 mins for unloading)

hour 0.019 0.019 0.019


Rate per cum= (a+b+c)

21.01 (B) Cement Mortar 1:2 (1 cement: 2 sand)


Unit =cum
Taking output =1 cum

a) Materials
Cement tonne 0.672 0.672 0.672
coarse sand cum 0.930 0.930 0.930
Cost of water KL 0.336 0.336 0.336
b) Labour
Mate day 0.036 0.036 0.036
Mazdoor day 0.900 0.900 0.900
c) Machinery
Water tanker 12 KL capacity (speed @20 km / hr and hour
return speed @ 30 km / hr and 30 mins for unloading) 0.025 0.025 0.025

Rate per cum= (a+b+c)

21.01 (C) Cement Mortar 1:4 (1 cement: 4 sand)


Unit =cum
Taking output =1 cum
a) Materials
Cement tonne 0.403 0.403 0.403
coarse sand cum 1.120 1.120 1.120
Cost of water KL 0.202 0.202 0.202
b) Labour
Mate day 0.036 0.036 0.036
Mazdoor day 0.900 0.900 0.900
c)Machinery
Water tanker 12 KL capacity (speed @20 km / hr and hour
return speed @ 30 km /hr and 30 mins for unloading) 0.015 0.015 0.015

Rate per cum= (a+b+c)

21.01 (D) Cement Mortar 1:6 (1 cement: 6 sand)


Unit =cum
Taking output =1 cum
a) Materials
Cement tonne 0.288 0.288 0.288
coarse sand cum 1.337 1.337 1.337
Cost of water KL 0.144 0.144 0.144
b) Labour
Mate day 0.036 0.036 0.036
Mazdoor day 0.900 0.900 0.900
c)Machinery
Water tanker 12 KL capacity (speed @20 km / hr and
return speed @ 30 km /hr and 30 mins for unloading) hour
0.011 0.011 0.011
Rate per cum= (a+b+c)

21.02 PCC 1:3:6 using batching plant


Plain Cement concrete 1:3:6 nominal mix with
crushedstone aggregate 40 mm nominal size
mechanically mixed
Unit =cum
Taking output =15 cum
a) Labour
Mate day 0.320 0.320 0.320
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 7.000 7.000 7.000
b) Materials
40 mm Aggregate cum 13.500 13.500 13.500
coarse sand cum 6.750 6.750 6.750
Cement tonne 3.450 3.450 3.450
Cost of water KL 1.380 1.380 1.380
c) Machinery
Batching plant of capacity 120 cum /hour hour 0.167 0.167 0.167
Generator 250 KVA hour 0.167 0.167 0.167
Loader 3.1cum capacity hour 0.362 0.362 0.362
Transit truck agitator
For loading & unloading time hour 0.167 0.167 0.167

Rate per cum= (a+b+c) /15


Vibrator is part ofminorT& P which is already
Note included in overhead charges of the contractor.
Plain/Reinforced cement concrete complete as per
21.03 Drawingand Technical specefication.
PCC Grade M15Using Batching Plant
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 99.000 99.000 99.000
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 194.400 194.400 194.400
20 mm Aggregate cum 97.200 97.200 97.200
10 mm Aggregate cum 32.400 32.400 32.400
Cost of water ( Water /cement Ratio-0.4) KL 39.600 39.600 39.600
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000

Per cum Basic cost of Labour, Material &


Machinery (a+b+c)/360
21.04 PCC Grade M20 Using Batching Plant
Unit = cum
Taking output = 360 cum
a) Materials
Cement tonne 123.840 123.840 123.840
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 129.600 129.600 129.600
20 mm Aggregate cum 129.600 129.600 129.600
10 mm Aggregate cum 64.800 64.800 64.800
Cost of water ( Water /cement Ratio-0.4) KL 49.536 49.536 49.536
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of Labour, Material &
Machinery (a+b+c)/360
21.05 RCC Grade M20 Using Batching Plant
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 124.980 124.980 124.980
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Cost of water KL 49.952 49.952 49.952
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.06 PCC Grade M25 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 143.850 143.850 143.850
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 129.600 129.600 129.600
20 mm Aggregate cum 129.600 129.600 129.600
10 mm Aggregate cum 64.800 64.800 64.800
Cost of water KL 57.540 57.540 57.540
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.07 RCC Grade M25 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 145.140 145.140 145.140
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.2% of cement kg 290.280 290.280 290.280
Cost of water KL 58.056 58.056 58.056
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For
Per loading & unloading
cum Basic cost of time hour 4.000 4.000 4.000
Labour,Material&Machinery(a+b+c)/360

21.08 PCC Grade M30 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 145.800 145.800 145.800
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 129.600 129.600 129.600
20 mm Aggregate cum 129.600 129.600 129.600
10 mm Aggregate cum 64.800 64.800 64.800
Cost of water KL 58.320 58.320 58.320
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.09 RCC Grade M30 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 146.400 146.400 146.400
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.3% of cement kg 439.200 439.200 439.200
Cost of water KL 58.560 58.560 58.560
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor
day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000

Per cum Basic cost of


Labour,Material&Machinery(a+b+c)/360

21.10 PCC Grade M35 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 150.840 150.840 150.840
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.3% of cement kg 452.520 452.520 452.520
Cost of water KL 60.336 60.336 60.336
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000

Per cum Basic cost of


Labour,Material&Machinery(a+b+c)/360
21.11 RCC GradeM35 Using Batching plant
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 151.920 151.920 151.920
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.4% of cement kg 607.680 607.680 607.680
Cost of water KL 60.768 60.768 60.768
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.12 RCC Grade M40 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 154.800 154.800 154.800
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.8% of cement kg 1238.400 1238.400 1238.400
Cost of water KL 61.920 61.920 61.920
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /cum hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.13 RCC Grade M45 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 154.800 154.800 154.800
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 1 % of cement kg 1548.000 1548.000 1548.000
Cost of water KL 61.920 61.920 61.920
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.14 RCC Grade M50 Using Batching Plant


Unit= cum

a) Materials
Cement tonne 154.800 154.800 154.800
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 0.8 % of cement kg 1238.400 1238.400 1238.400
Silica Fume @ 5% of cement kg 7740.000 7740.000 7740.000
Cost of water KL 61.920 61.920 61.920
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.15 RCC Grade M55 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 158.400 158.400 158.400
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 1 % of cement kg 1267.200 1267.200 1267.200
Silica Fume @ 5% of cement kg 7920.000 7920.000 7920.000
Cost of water KL 63.360 63.360 63.360
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360
21.16 RCC Grade M60 Using Batching Plant
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 160.200 160.200 160.200
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 1 % of cement kg 1281.600 1281.600 1281.600
Silica Fume @ 5% of cement kg 9612.000 9612.000 9612.000
Cost of water KL 64.080 64.080 64.080
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360

21.17 RCC Grade M65 Using Batching Plant


Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 162.000 162.000 162.000
coarse sand cum 162.000 162.000 162.000
20 mm Aggregate cum 194.400 194.400 194.400
10 mm Aggregate cum 129.600 129.600 129.600
Admixture @ 1 % of cement kg 1296.000 1296.000 1296.000
Silica Fume @ 5% of cement kg 9720.000 9720.000 9720.000
Cost of water KL 64.800 64.800 64.800
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360
A DLC Using Batching Plant -240 cum capacity
21.18 601 Plant
Unit= cum
Taking output= 450 cum
a) Materials
Cement @150 kg /cum of concrete tonne 67.500 67.500 67.500
coarse sand
nominal asgraded
sizes per IS: as
383
per@0.45 cum /cum of concrete
table600-1@0.90cum/cum cum 202.500 202.500 202.500
of concrete confirming to clause602.2.6 cum 405.000 405.000 405.000
Cost of water(Water /cement Ratio -0.4) KL 27.000 27.000 27.000
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 240 cum /hour hour 2.500 2.500 2.500
Generator 250 KVA hour 2.500 2.500 2.500
Loader 3.1cum capacity hour 10.848 10.848 10.848
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/450

B Dry Lean Concrete Sub -base Fly ash ( Using


21.18 601 Batching Plant) -240 cum capacity Plant
Unit= cum
Taking output= 450 cum
a) Materials
Cement @129 kg /cum of concrete tonne 57.860 57.860 57.860
coarse
nominalsand asgraded
sizes per IS: as
383
per@0.45 cum /cum of concrete
table600-1@0.90cum/cum cum 202.500 202.500 202.500
of concrete confirming to clause602.2.6 cum 405.000 405.000 405.000
Fly ash conforming to IS:3812-1966 (Part -I) cum 9.640 9.640 9.640
Cost of water(Water /cement Ratio -0.4) KL 23.144 23.144 23.144
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 240 cum /hour hour 2.500 2.500 2.500
Generator 250 KVA hour 2.500 2.500 2.500
Loader 3.1cum capacity hour 10.848 10.848 10.848
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/450
Quantity provided for aggregate is for estimating
Note purpose. Exact quantity shall be as per mix design.
*Calculation of cement and fly ash
Cement
20 @ of
percent 150 /kg cum=
cement to be450x150
replaced=67.500 tonnes
by fly ash =13.50
tonnes
Balance
Quantitycement =54.0
of fly ash tonnesspecific gravity of fly
=13.50x
ash /specific gravity of cement =13.50x 2.25/3.15 =9.64
tonnes
C DLC Using Batching Plant -120 cum capacity
21.18 601 Plant
Unit= cum
Taking output= 450 cum
a) Materials
Cement @150 kg /cum of concrete tonne 67.500 67.500 67.500
coarse
nominalsand asgraded
sizes per IS: as
383
per@0.45 cum /cum ofcum/cum
table600-1@0.90 concrete cum 202.500 202.500 202.500
of concrete confirming to clause602.2.6 cum 405.000 405.000 405.000
Cost of water(Water /cement Ratio -0.4) KL 27.000 27.000 27.000
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 5.000 5.000 5.000
Generator 250 KVA hour 5.000 5.000 5.000
Loader 3.1cum capacity hour 10.848 10.848 10.848

Per cum Basic cost of


Labour,Material&Machinery(a+b+c)/450

D Dry Lean Concrete Sub -base Fly ash ( Using


21.18 601 Batching Plant) -120 cum capacity Plant
Unit= cum
Taking output= 450 cum
a) Materials
Cement @150 kg /cum of concrete tonne 57.860 57.860 57.860
coarse sand as per IS: 383 @0.45 cum /cum of concrete cum 202.500 202.500 202.500
Crushed stone coarse aggregate of 25 mm and 12.5 mm cum 405.000 405.000 405.000
nominal sizes graded as per table600-1@0.90 cum/cum
of concrete confirming to clause602.2.6
Fly ash conforming to IS:3812-1966 (Part -I) cum 9.640 9.640 9.640
Cost of water(Water /cement Ratio -0.4) KL 23.144 23.144 23.144
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 5.000 5.000 5.000
Generator 250 KVA hour 5.000 5.000 5.000
Loader 3.1cum capacity hour 10.848 10.848 10.848
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/450
Quantity provided for aggregate is for estimating
Note purpose. Exact quantity shall be as per mix design.
*Calculation of cement and fly ash
Cement
20 @ of
percent 150 /kg cum
cement 450x150
to be =67.500
replaced tonnes
by fly ash =13.50
tonnes
Balance cement =54.0 tonnes
Quantity of fly ash =13.50x specific gravity of fly
ash /specific of cement =13.50x 2.25/3.15 =9.64 tonnes
A PQC M 35 grade Using Batching Plant-240 cum
21.19 602 capacity plant
Unit= cum
Taking output= 900 cum
a) Materials
Cement @4000 kg /cum of concrete tonne 360.000 360.000 360.000
coarse sand as per IS: 383 and confirming to clause
nominal size @0.90 cum/cum of concrete confirming to cum 405.000 405.000 405.000
602.2.4 @0.45 cum /cum of concrete
clause602.2.6 cum 810.000 810.000 810.000
Admixture @ 0.5% of cement kg 1800.000 1800.000 1800.000
Cost of water KL 144.000 144.000 144.000
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 240 cum /hour hour 5.000 5.000 5.000
Generator 250 KVA hour 5.000 5.000 5.000
Loader 3.1cum capacity hour 21.696 21.696 21.696
Transit truck agitator
For loading & unloading time hour 5.000 5.000 5.000

Per cum Basic cost of


Labour,Material&Machinery(a+b+c)/900

B PQC M 35 grade Using Batching Plant-240 cum


21.19 602 capacity(Cement-Fly ash)
Unit= cum
Taking output= 900 cum
a) Material
Cement tonne 306.000 306.000 306.000
Fly ash confirming to IS 3812(Part-I) tonne 93.000 93.000 93.000
coarse sand
nominal size @0.90 cum/cum of concrete confirming to cum 364.500 364.500 364.500
clause 602.2.4 cum 810.000 810.000 810.000
Admixture @ 0.5% of cement kg 1530.000 1530.000 1530.000
Cost of water KL 122.400 122.400 122.400
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 240 cum /hour hour 5.000 5.000 5.000
Generator 250 KVA hour 5.000 5.000 5.000
Loader 3.1cum capacity hour 20.973 20.973 20.973
Transit truck agitator
For loading & unloading time hour 5.000 5.000 5.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/900
aggregates are for estimating only. The exact
Note quantities
2.IRC: 68 will
may be
be as per mixfor
refferred design.
guidelines on the design
of cement-fly ash concrete rigid pavement construction.
*Calculation of cement and fly ash
Cement @ of
15 percent 400 kg /cum=
cement to be900x 450 =360
replaced by flytonnes.
ash 54.0
tonnes
Balance cement =306.00 tonnes.
Quantity of fly ash =54.000x specific gravity of fly
ash /specificgravity of cement =54.00x 2.25/3.15
=38.571
Sand @0.45tonnes.
cum /of concrete =900x0.45 =405x1.6
=648
Balanced sand =percent
tonnes.10 to be replaced by Fly ash
648x0.9=583.2
tonnes=583.2/1.6=364.5cum
fly ash /specificgravity of sand=64.8 x 2.687 =54.26
tonnes.
Fly ashTotal fly ash=38.571+54.26=92.831 tonnes.(Say
93 toones)
C PQC M 35 grade Using Batching Plant-120 cum
21.19 602 capacity
Unit= cum
Taking output= 900 cum
a) Materials
Cement @4000 kg /cum of concrete tonne 360.000 360.000 360.000
coarse sand
nominal sizeas@0.90
per IS:cum/cum
383 and of
confirming to
concrete confirming to cum 405.000 405.000 405.000
clause602.2.4
clause 602.2.4@0.45 cum /cum of concrete cum 810.000 810.000 810.000
Admixture @ 0.5% of cement kg 1800.000 1800.000 1800.000
Cost of water KL 144.000 144.000 144.000
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 10.000 10.000 10.000
Generator 250 KVA hour 10.000 10.000 10.000
Loader 3.1cum capacity hour 21.696 21.696 21.696
Transit truck agitator
For loading & unloading time hour 10.000 10.000 10.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/900

D PQC M 35 grade Using Batching Plant-120 cum


21.19 602 capacity(Cement-Fly ash)
Unit= cum
Taking output= 900 cum
a) Materials
Cement tonne 306.000 306.000 306.000
Fly ash confirming to IS :3812(Part-I) tonne 93.000 93.000 93.000
coarse sand
nominal size @0.90 cum/cum of concrete confirming to cum 364.500 364.500 364.500
clause 602.2.4 cum 810.000 810.000 810.000
Admixture @ 0.4% of cement kg 1224.000 1224.000 1224.000
Cost of water KL 122.400 122.400 122.400
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 10.000 10.000 10.000
Generator 250 KVA hour 10.000 10.000 10.000
Loader 3.1cum capacity hour 20.973 20.973 20.973
Transit truck agitator
For loading & unloading time hour 10.000 10.000 10.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/900
aggregate are for estimating only. The exact quantities
Note will be as per
of cement -flymix
ash design.
concrete for rigid pavement
construction.
*Calculation of cement and fly ash
Cement @ of
15 percent 400 kg /cum=
cement to be900x 400 =360
replaced by flytonnes.
ash =54.0
tonnes
Balance
Quantitycement =306.00
of fly ash tonnes.
=54.000x specific gravity of fly
ash /specific of cement =54.000x 2.25/3.15 =38.571
tonnes.
Sand @0.45 cum /cum of concrete =900x0.45
=405x1.6 =648 tonnes.
10 percent
Balance to =be648x0.9=583.2.
sand replaced by Flytonnes
ash. =583.2/1.6
=364.5 cum.
fly ash /specfic gravity of sand
=64.8x2.25/2.687=54.26 tonnes
FlyashTotal fly ash =38.571+54.26= 92.831 tonnes.
(Say93tonnes)
PCC Grade M15 grade Using Batching Plant for
21.20 409 Kerb
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 99.000 99.000 99.000
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 194.400 194.400 194.400
20 mm Aggregate cum 97.200 97.200 97.200
10 mm Aggregate cum 32.400 32.400 32.400
Cost of water ( Water /cement Ratio-0.4) KL 39.600 39.600 39.600
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /hour hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000
Per cum Basic cost of
Labour,Material&Machinery(a+b+c)/360
PCC Grade M20 grade Using Batching Plant for
21.21 409 Kerb
Unit= cum
Taking output= 360 cum
a) Materials
Cement tonne 123.840 123.840 123.840
coarse sand cum 162.000 162.000 162.000
40 mm Aggregate cum 129.600 129.600 129.600
20 mm Aggregate cum 129.600 129.600 129.600
10 mm Aggregate cum 64.800 64.800 64.800
Cost of water ( Water /cement Ratio-0.4) KL 49.536 49.536 49.536
b) Labour
Mate day 0.160 0.160 0.160
Skilled Mazdoor day 1.000 1.000 1.000
Mazdoor day 3.000 3.000 3.000
c) Machinery
Batching plant of capacity 120 cum /cum hour 4.000 4.000 4.000
Generator 250 KVA hour 4.000 4.000 4.000
Loader 3.1cum capacity hour 8.679 8.679 8.679
Transit truck agitator
For loading & unloading time hour 4.000 4.000 4.000

Per cum Basic cost of


Labour,Material&Machinery(a+b+c)/360

21.22 Cost of water


Unit =KL
Taking output= 12 KL
a) Labour
Mate day 0.005 0.005 0.005
Mazdoor day 0.133 0.133 0.133
b) Machinery
Centrifugal water pump (600LMP) hour 0.533 0.533 0.533
Water tanker 12 KL hour 0.533 0.533 0.533
Cost for 12 KL =a+b
Rate per KL= (a+b) /12
ORTAR RATE

Rate(Rs.) Amount

Large

4844.00 2470.44
175.80 184.59
73.60 18.77

310.00 11.16
292.00 262.8

1252.00 23.79
2971.55
2971.50

4844.00 3255.168
175.80 163.494
73.60 24.73

310.00 11.16
292.00 262.80

1252.00 31.30

3748.65
say 3748.70

4844.00 1952.132
175.80 196.896
73.60 14.87

310.00 11.16
292.00 262.8
1252.00 18.78

2456.64
say 2456.60

4844.00 1395.072
175.80 235.0446
73.60 10.60
0.00
310.00 11.16
292.00 262.80

1252.00 13.77
1928.45

310.00 99.20
370.00 370.00
292.00 2044.00

486.92 6573.42
175.80 1186.65
4844.00 16711.8
73.60 101.57

3627.00 605.71
4359.00 727.95
4255.00 1540.31

2218.00 370.41
30331.02
2022.07
say 2022.10
4844.00 479556
175.80 28479.6
486.92 94657.248
595.36 57868.992
657.91 21316.284
73.60 2914.56

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
763833.429
2121.76
say 2121.80

4844.00 599880.96
175.80 28479.6
486.92 63104.832
595.36 77158.656
657.91 42632.568
73.60 3645.8496

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
893943.211
2483.18

4844.00 605403.12
175.80 28479.6
595.36 115737.984
657.91 85265.136
73.60 3676.4672

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.0 36929.15

2218.00 8872.00
917603.05
2548.90
say 2548.90

4844.00 696809.4
175.80 28479.6
486.92 63104.832
595.36 77158.656
657.91 42632.568
73.60 4234.944

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
991460.745
2754.06
say 2754.10

4844.00 703058.16
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 46302.5628
73.60 4272.9216

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1062157.11
2950.44
say 2950.40

4844.00 706255.2
175.80 28479.6
486.92 63104.832
595.36 77158.656
657.91 42632.568
73.60 4292.352

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1000963.95
2780.46
say 2780.50

4844.00 709161.6
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 70056.792
73.60 4310.016

310.00 49.60
370.00 370.00

292.00 876.00
3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1092051.87
3033.48

say 3033.50

4844.00 730668.96
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 72181.4652
73.60 4440.7296

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1115814.62
3099.49
say 3099.50

4844.00 735900.48
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 96931.0368
73.60 4472.5248

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15
2218.00 8872.00
1145827.51
3182.85
say 3182.90

4844.00 749851.2
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 197537.184
73.60 4557.312

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1260469.16
3501.30
say 3501.30

4844.00 749851.2
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 246921.48
73.60 4557.312

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1309853.46
3638.48
say 3638.50

4844.00 749851.2
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 197537.184
32.00 247680
73.60 4557.312

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1508149.16
4189.30
say 4189.30

4844.00 767289.6
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 202131.072
32.00 253440
73.60 4663.296

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1536047.43
4266.80
say 4266.80
4844.00 776008.8
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 204428.016
32.00 307584
73.60 4716.288

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1601260.57
4447.95
say 4447.90

4844.00 784728
175.80 28479.6
595.36 115737.984
657.91 85265.136
159.51 206724.96
32.00 311040
73.60 4769.28

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
1615785.71
4488.29
say 4488.30
4844.00 326970
175.80 35599.5
656.34 265817.7
73.60 1987.2

310.00 49.60
370.00 370.00
292.00 876.00

5670.00 14175.00
4359.00 10897.50
4255.00 46158.24
702900.74
1562.00
say 1562.00

4844.00 280273.84
175.80 35599.5
656.34 265817.7
0.00 0
73.60 1703.3984

310.00 49.60
370.00 370.00
292.00 876.00

5670.00 14175.00
4359.00 10897.50
4255.00 46158.24
655920.778
1457.60
say 1457.60
4844.00 326970
175.80 35599.5
656.34 265817.7
73.60 1987.2

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 18135.00
4359.00 21795.00
4255.00 46158.24
717758.24
1595.02
say 1595.00

4844.00 280273.84
175.80 35599.5
656.34 265817.7

0.00 0
73.60 1703.40

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 18135.00
4359.00 21795.00
4255.00 46158.24
670778.278
1490.62
say 1490.60
4844.00 1743840
175.80 71199
656.34 531635.4
159.51 287118
73.60 10598.4

310.00 49.60
370.00 370.00
292.00 876.00

5670.00 28350.00
4359.00 21795.00
4255.00 92316.48

2218.00 11090.00
2799237.88
3110.26
say 3110.30

4844.00 1482264
0.00 0
175.80 64079.1
656.34 531635.4
159.51 244050.3
73.60 9008.64

310.00 49.60
370.00 370.00
292.00 876.00

5670.00 28350.00
4359.00 21795.00
4255.00 89240.12

2218.00 11090.00
2482808.16
2758.68
say 2758.70
4844.00 1743840
175.80 71199
656.34 531635.4
159.51 287118
73.60 10598.4

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 36270.00
4359.00 43590.00
4255.00 92316.48

2218.00 22180.00
2840042.88
3155.60
say 3155.60

4844.00 1482264
0.00 0
175.80 64079.1
656.34 531635.4
159.51 195240.24
73.60 9008.64

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 36270.00
4359.00 43590.00
4255.00 89240.12

2218.00 22180.00
2474803.10
2749.78
say 2749.80

4844.00 479556
175.80 28479.6
486.92 94657.248
595.36 57868.992
657.91 21316.284
73.60 2914.56

310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
763833.43
2121.76
say 2121.80

4844.00 599880.96
175.80 28479.6
486.92 63104.832
595.36 77158.656
657.91 42632.568
73.60 3645.8496
310.00 49.60
370.00 370.00
292.00 876.00

3627.00 14508.00
4359.00 17436.00
4255.00 36929.15

2218.00 8872.00
893943.21
2483.18
say 2483.20

310.00 1.55
292.00 38.84

329.00 175.36
1252.00 667.32
883.06
73.59
say 73.60
CHAPTER -1
CARRIAGE OF MATERIALS
Sl.No Ref.to Description Unit Quantity as per Project Category Rate Amount
M.
Large Medium Small Large Medium Small
Loading and unloading of stone boulder / stone
1.01 A aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
A.Taking output = 5.5 Cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket capacity Min 6.630 6.630 6.630
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.630 13.630 13.630
a) Machinery
Backhoe-loader 1 cum bucket capacity Hour 0.227 0.227 0.227 #REF! #REF! #REF! #REF!
Tipper-5.5 Cum Hour 0.227 0.227 0.227 #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@8 %) (@10 %) (@12 %)
c) Contractor's profit on (a+b) (@10 %) (@10 %) (@10 %)

Total Cost for 5.5 cum = (a+b+c) Including OH & CP

Unit Cost= (a+b+c)/5.5 Including OH & CP


Note : Unloading will be by tipping. Say
1.01 B Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking Output = 10.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket capacity Min 12.060 12.060 12.060

iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 19.060 19.060 19.060
a) Machinery
Backhoe-loader 1 cum bucket capacity Hour 0.318 0.318 0.318 1,657.00 526.38 526.38 526.38
Tipper-10 Cum Hour 0.318 0.318 0.318 2,106.00 669.02 669.02 669.02
Total Cost Excluding OH & CP 1,195.40 1,195.40 1,195.40
b) Overheads on (a) (@12 %) (@10 %) (@8 %) 143.45 119.54 95.63
c) Contractor's profit on (a+b) (@10 %) (@10 %) (@10 %) 133.88 131.49 129.1
Total Cost for 10 cum = (a+b+c) Including OH & CP 1,472.73 1,446.43 1,420.13
Unit Cost= (a+b+c)/10 Including OH & CP 147.27 144.64 142.01
Note : Unloading will be by tipping. Say
Loading and unloading of stone boulder / stone
1.01 C. aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking Output = 14.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.010 1.020
ii) Loading by front end loader 2.1 cum bucket capacity Min 8.030 8.040 8.050
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.010 2.020
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.010 4.020
Total Min 15.030 15.040 15.050
a) Machinery
Front End loader 2.1 cum bucket capacity Hour 0.250 0.250 0.250 2417.000 605.410 605.410 605.410
Tipper-14 Cum Hour 0.250 0.250 0.250 2361.000 591.380 591.380 591.380
Total Cost Excluding OH & CP 1,196.780 1,196.780 1,196.780
b) Overheads on (a) (@12 %) (@10 %) (@8 %) 143.610 119.680 95.740
c) Contractor's profit on (a+b) (@10 %) (@10 %) (@10 %) 134.040 131.650 129.250
Total Cost for 14 cum = (a+b+c) Including OH & CP 1,474.440 1,448.110 1,421.780
Unit Cost= (a+b+c)/14 Including OH & CP 105.320 103.440 101.560
Note : Unloading will be by tipping.
Loading and unloading of stone boulder / stone
1.01 D aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking Output = 18.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.010 1.020
ii) Loading by front end loader 3.1 cum bucket capacity Min 7.000 7.010 7.020
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.010 2.020
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.010 4.020
Total Min 14.000 14.010 14.020
a) Machinery
Front End loader 3.1 cum bucket capacity Hour 0.233 0.233 0.233 3,932.00 917.2 917.2 917.2
Tipper-18 Cum Hour 0.233 0.233 0.233 2,651.00 618.39 618.39 618.39
Total Cost Excluding OH & CP 1,535.590 1,535.590 1,535.590
b) Overheads on (a) (@12 %) (@10 %) (@8 %) 184.270 153.560 122.850
c) Contractor's profit on (a+b) (@10 %) (@10 %) (@10 %) 171.990 168.910 165.840
Total Cost for 18 cum = (a+b+c) Including OH & CP 1,891.850 1,858.060 1,824.280
Unit Cost= (a+b+c)/18 Including OH & CP 105.100 103.230 101.350
Note : Unloading will be by tipping.
1.02 Ref.to Loading and Unloading of Boulders by Manual Means
M. Unit = cum
Taking output = 10 Cum
a) Labour
Mate / Supervisor day 0.055 0.055 0.055 569 31.04 31.04 31.04
Mazdoor day 1.364 1.364 1.364 503 685.91 685.91 685.91
b) Machinery
Tipper-10 Cum Hour 1.364 1.364 1.364 2,106.00 2,871.82 2,871.82 2,871.82
Total Cost Excluding OH & CP 3,588.76 3,588.76 3,588.76
c) Overheads on (a+b) (@12 %) (@10 %) (@8 %) 430.65 358.88 287.1
d) Contractor's profit on (a+b+c) (@10 %) (@10 %) (@10 %) 401.94 394.76 387.59
Total Cost for 10 cum=(a+b+c+d) Including OH & CP 4,421.36 4,342.40 4,263.45
Unit Cost=(a+b+c+d)/10 Including OH & CP 442.14 434.24 426.34
Note : Unloading will be by tipping. Say
1.03 Ref.to Loading and Unloading of Cement or Steel by Manual
M. Means and Stacking.
Unit = tonne
Taking Output = 18.00 tonnes
a) Labour
Mate / Supervisor day 0.144 0.144 0.144 569 81.94 81.94 81.94
Mazdoor day 3.6 3.6 3.6 503 1,810.80 1,810.80 1,810.80
b) Machinery
Truck-18 tonne capacity. Hour 3.6 3.6 3.6 2,106.00 7,581.60 7,581.60 7,581.60
Total Cost Excluding OH & CP 9,474.34 9,474.34 9,474.34
c) Overheads on (a+b) (@12 %) (@10 %) (@8 %) 1,136.92 947.43 757.95
d) Contractor's profit on (a+b+c) (@10 %) (@10 %) (@10 %) 1,061.13 1,042.18 1,023.23
Total Cost for 18 tonnes=(a+b+c+d) Including OH & 11,672.38 11,463.95 11,255.51
CP
Unit Cost=(a+b+c+d)/18 Including OH & CP 648.47 636.89 625.31
Say
1.04 (i) A Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
i) A.Case-I : Surfaced Road (Taking output 10 tonnes
load
Unit and lead 10 km)
= t.km
Taking Output 10 tonnes load and lead 10 km=100.00
t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
Time taken for empty return trip. Hour 0.286 0.286 0.286
1,619.00 462.570 462.570 462.570
Time taken for onward haulage with load Hour 0.400 0.400 0.400
1,619.00 647.600 647.600 647.600
Total Cost Excluding OH & CP 1110.170 1110.170 1110.170
Overheads (@12 %) (@10 %) (@8 %) 133.220 111.020 88.810
Contractors profit (@10 %) (@10 %) (@10 %) 124.340 122.120 119.900
Total Cost Including OH & CP 1367.730 1343.310 1318.880
Unit Cost Including OH & CP 13.680 13.430 13.190
Say
Cost of Haulage Excluding Loading and Unloading
i) B.Case-I : Surfaced Road (Taking output 18
tonnes load and lead 10 km)
Unit = t.km
Taking Output = 180.00 t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
Machinery
Time taken for empty return trip. Hour 0.286 0.286 0.286 2106.000 601.710 601.710 601.710
Time taken for onward haulage with load Hour 0.400 0.400 0.400 2106.000 842.400 842.400 842.400
Total Cost Excluding OH & CP ### ### 1,444.110
Total Cost Including OH & CP ### ### 1,715.610
Unit Cost Including OH & CP 9.880 9.710 9.530
Say
Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
i) C.Case-I : Surfaced Road (Taking output 25
tonnes load and lead 10 km)
Unit = t.km
Taking Output = 250.00 t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
Machinery
Time taken for empty return trip. Hour 0.286 0.286 0.2862361.000 674.570 674.570 674.570
Time taken for onward haulage with load Hour 0.400 0.400 0.4002361.000 944.400 944.400 944.400
Total Cost Excluding OH & CP 1618.970 1618.970 1618.970
Overheads (@12 %) (@10 %) (@8 %) 194.280 161.900 129.520
Contractors profit (@10 %) (@10 %) (@10 %) 181.320 178.090 174.850
Total Cost Including OH & CP 1994.570 1958.950 1923.340
Unit Cost Including OH & CP 7.980 7.840 7.690

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
i) D.Case-I : Surfaced Road (Taking output 32
tonnes load and lead 10 km)
Unit = t.km
Taking Output = 320.00 t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
Machinery
Time taken for empty return trip. Hour 0.286 0.286 0.2862,651.00 757.43 757.43 757.43
Time taken for onward haulage with load Hour 0.400 0.400 0.4002,651.00 1,060.40 1,060.40 1,060.40
Total Cost Excluding OH & CP ### ### 1,817.830
Unit Cost Excluding OH & CP 5.680 5.680 5.680
Overheads (@12 %) (@10 %) (@8 %) 218.140 181.780 145.430
Contractors profit (@10 %) (@10 %) (@10 %) 203.600 199.960 196.330
Total Cost Including OH & CP ### ### 2,159.580
Unit Cost Including OH & CP 7.000 6.870 6.750

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
ii) A.Case-II : Unsurfaced Gravelled Road (Taking
output 10 tonnes load and lead 10 km)
Unit = t.km
Taking Output = 100.00 t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
Machinery
Time taken for empty return trip. Hour 0.333 0.333 0.3331619.000 539.670 539.670 539.670
Time taken for onward haulage with load Hour 0.500 0.500 0.5001619.000 809.500 809.500 809.500
Total Cost Excluding OH & CP ### ### 1,349.170
Overheads (@12 %) (@10 %) (@8 %) 161.900 134.920 107.930
Contractors profit (@10 %) (@10 %) (@10 %) 151.110 148.410 145.710
Total Cost Including OH & CP ### ### 1,602.810
Unit Cost Including OH & CP 16.620 16.320 16.030
Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
ii) B.Case-II : Unsurfaced Gravelled Road (Taking
output 10 tonnes load and lead 18 km)
Unit = t.km
Taking Output = 180.00 t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
Machinery
Time taken for empty return trip. Hour 0.333 0.333 0.3332,106.00 702 702 702
Time taken for onward haulage with load Hour 0.500 0.500 0.5002,106.00 1,053.00 1,053.00 1,053.00
Total Cost Excluding OH & CP ### ### 1,755.000
Overheads (@12 %) (@10 %) (@8 %) 210.600 175.500 140.400
Contractors profit (@10 %) (@10 %) (@10 %) 196.560 193.050 189.540
Total Cost Including OH & CP ### ### 2,084.940
Unit Cost Including OH & CP 12.010 11.800 11.580

Cost of Haulage Excluding Loading and Unloading


ii) C.Case-II : Unsurfaced Gravelled Road (Taking
output 10 tonnes load and lead 25 km)

Unit = t.km
Taking Output = 250.00 t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
Machinery
Time taken for empty return trip. Hour 0.333 0.333 0.3332,361.00 787 787 787
Time taken for onward haulage with load Hour 0.500 0.500 0.5002,361.00 1,180.50 1,180.50 1,180.50
Total Cost Excluding OH & CP 1,967.50 1,967.50 1,967.50
Overheads (@12 %) (@10 %) (@8 %) 236.1 196.75 157.4
Contractors profit (@10 %) (@10 %) (@10 %) 220.36 216.42 212.49
Total Cost Including OH & CP 2,423.96 2,380.67 2,337.39
Unit Cost Including OH & CP 9.7 9.52 9.35

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
ii) D.Case-II : Unsurfaced Gravelled Road (Taking
output 10 tonnes load and lead 32 km)
Unit = t.km
Taking Output = 320.00 t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
Machinery
Time taken for empty return trip. Hour 0.333 0.333 0.3332,651.00 883.67 883.67 883.67
Time taken for onward haulage with load Hour 0.500 0.500 0.5002,651.00 1,325.50 1,325.50 1,325.50
Total Cost Excluding OH & CP ### ### 2,209.170
Overheads (@12 %) (@10 %) (@8 %) 265.100 220.920 176.730
Contractors profit (@10 %) (@10 %) (@10 %) 247.430 243.010 238.590
Total Cost Including OH & CP ### ### 2,624.490
Unit Cost Including OH & CP 8.510 8.350 8.200

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
iii) A.Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed. (Taking output 10 tonnes
load
Unit =and lead 10 km)
t.km
Taking Output = 100.00 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
Machinery
Time taken for empty return trip Hour 0.667 0.667 0.6671,619.00 1,079.33 1,079.33 1,079.33
Time taken for onward haulage Hour 1 1 1 1,619.00 1,619.00 1,619.00 1,619.00
Total Cost Excluding OH & CP 2,698.33 2,698.33 2,698.33
Overheads (@12 %) (@10 %) (@8 %) 323.8 269.83 215.87
Contractors profit (@10 %) (@10 %) (@10 %) 302.21 296.82 291.42
Total Cost Including OH & CP 3,324.35 3,264.98 3,205.62
Unit Cost Including OH & CP 33.24 32.65 32.06

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
iii) B.Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed. (Taking output 18 tonnes
Unit = t.km
load
Taking and lead 18
Output km) t.km
= 180.00
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
Machinery
Time taken for empty return trip Hour 0.667 0.667 0.6672106.000 1404.000 1404.000 1404.000
Time taken for onward haulage Hour 1.000 1.000 1.0002106.000 2106.000 2106.000 2106.000
Total Cost Excluding OH & CP ### ### 3,510.000
Overheads (@12 %) (@10 %) (@8 %) 421.200 351.000 280.800
Contractors profit (@10 %) (@10 %) (@10 %) 393.120 386.100 379.080
Total Cost Including OH & CP ### ### 4,169.880
Unit Cost Including OH & CP 24.020 23.600 23.170

Cost of Haulage Excluding Loading and Unloading

Haulage of materials by tipper excluding cost of


loading, unloading and stacking.
iii) C.Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed. (Taking output 25 tonnes
load and lead 10 km)
Unit = t.km
Taking Output = 250.00 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
Machinery
Time taken for empty return trip Hour 0.667 0.667 0.667 2,361.00 1,574.00 1,574.00 1,574.00
Time taken for onward haulage Hour 1 1 1 2,361.00 2,361.00 2,361.00 2,361.00
Total Cost Excluding OH & CP 3,935.00 3,935.00 3,935.00
Overheads (@12 %) (@10 %) (@8 %) 472.2 393.5 314.8
Contractors profit (@10 %) (@10 %) (@10 %) 440.72 432.85 424.98
Total Cost Including OH & CP 4,847.92 4,761.35 4,674.78
Unit Cost Including OH & CP 19.39 19.05 18.7

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
iii) D.Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed. (Taking output 32 tonnes
load
Unit =and lead 10 km)
t.km
Taking Output = 320.00 t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
Machinery
Time taken for empty return trip Hour 0.667 0.667 0.667
2651.000 1,767.33 1,767.33 1,767.33
Time taken for onward haulage Hour 1.000 1.000 1.000
2651.000 2,651.00 2,651.00 2,651.00
Total Cost Excluding OH & CP 4,418.33 4,418.33 4,418.33
Overheads (@12 %) (@10 %) (@8 %) 530.2 441.83 353.47

Contractors profit (@10 %) (@10 %) (@10 %) 494.85 486.02 477.18


Total Cost Including OH & CP 5,443.39 5,346.18 5,248.98
Unit Cost Including OH & CP 17.01 16.71 16.4
Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
iv) .Case-IV : Katcha Track in hilly area. (Taking
output 10 tonnes load and lead 10 km)
Unit = t.km
Taking Output = 100.00 t.km
Speed with load: 5 km / hour
Speed while returning empty: 7 km / hour
Machinery
Time taken for empty return trip Hour 1.429 1.429 1.4291,619.00 2,312.86 2,312.86 2,312.86
Time taken for onward haulage Hour 2 2 2 1,619.00 3,238.00 3,238.00 3,238.00
Total Cost Excluding OH & CP 5,550.86 5,550.86 5,550.86
Overheads (@12 %) (@10 %) (@8 %) 666.1 555.09 444.07
Contractors profit (@10 %) (@10 %) (@10 %) 621.7 610.59 599.49
Total Cost Including OH & CP 6,838.66 6,716.54 6,594.42
Unit Cost Including OH & CP 68.39 67.17 65.94
Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
v) .Case-V : Transit Mixture (Taking output 15
tonnes load and lead 10 km)
Unit = t.km
Taking Output = 150.00 t.km
Speed with load : 20 km / hour
Speed while returning empty: 30 km / hour
Machinery
Time taken for empty return trip Hour 0.333 0.333 0.333 2,235.00 745 745 745
Time taken for onward hanlage with load Hour 0.500 0.500 0.500 2,235.00 1,117.50 1,117.50 1,117.50
Total Cost Excluding OH & CP 1,862.50 1,862.50 1,862.50
Overheads (@12 %) (@10 %) (@8 %) 223.5 186.25 149
Contractors profit (@10 %) (@10 %) (@10 %) 208.6 204.87 201.15
Total Cost Including OH & CP 2,294.60 2,253.62 2,212.65
Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as directed
1.Taking output = 10 Cum
Unit = cum
Taking Output = 1.00 cum
Labour
Mate / Supervisor day 0.0600 0.0600 0.0600 569.0000 34.140 34.140 34.140
Material
Supply of quarried stone 150 - 200 mm size cum 1.1000 1.1000 1.1000 454.1800 499.600 499.600 499.600
Total Cost Excluding OH & CP 1288.240 1288.240 1288.240

Overheads (@12 %) (@10 %) (@8 %) 154.590 128.820 103.060


Contractors profit (@10 %) (@10 %) (@10 %) 144.280 141.710 139.130
Total Cost Including OH & CP 1587.110 1558.770 1530.430
Unit Cost Including OH & CP 1587.110 1558.770 1530.430

Crushing of stone aggregates (Nominal size)


Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.
0.Taking output = 1125 Tonne (750 Cum)
Unit = cum
Taking Output = 1125.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Machinery
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,684.98
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.92
Integrated stone crusher of 250 TPH including belt Hour 6 6 6 ### ### ### 88,470.00
conveyor and vibrating screens
Generator 725 KVA Hour 6 6 6 ### ### ### 60,636.00
Material
Stone Boulder of size 150 mm and below at Cruser cum 750 750 750 350 ### ### ###
Plant
Total Cost Excluding OH & CP ### ### ###
Overheads (@12 %) (@10 %) (@8 %) 49.83 41.53 33.22
Contractors profit (@10 %) (@10 %) (@10 %) 46.51 45.68 44.85
Total Cost Including OH & CP 511.61 502.47 493.34
Unit Cost Including OH & CP 511.61 502.47 493.34

Crushing of stone aggregates (Nominal size)

Crushing of stone boulders of 150 mm size in an


integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.
1.Crushing Pattern 40 mm (tonne)- Cost Distribution
28.98
Unit = %
cum
Taking Output = 1125.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Machinery
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,684.98
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.92
Integrated stone crusher of 250 TPH including belt Hour 6 6 6 ### ### ### 88,470.00
conveyor and vibrating screens
Generator 725 KVA Hour 6 6 6 ### ### ### 60,636.00
Material
Stone Boulder of size 150 mm and below at Cruser cum 750 750 750 350 ### ### ###
Plant
Total Cost Excluding OH & CP ### ### ###
Overheads (@12 %) (@10 %) (@8 %) 95.38 79.49 63.59
Contractors profit (@10 %) (@10 %) (@10 %) 89.03 87.44 85.85
Total Cost Including OH & CP 979.29 961.8 944.31
Unit Cost Including OH & CP 979.29 961.8 944.31

Crushing of stone aggregates (Nominal size)


Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.
2.Crushing Pattern 20 mm (tonne)- Cost Distribution
31.95
Unit = %
cum
Taking Output = 1125.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Machinery
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,684.98
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.92
Integrated stone crusher of 250 TPH including belt Hour 6 6 6 ### ### ### 88,470.00
conveyor and vibrating screens
Generator 725 KVA Hour 6 6 6 ### ### ### 60,636.00
Material
Stone Boulder of size 150 mm and below at Cruser cum 750 750 750 350 ### ### ###
Plant
Total Cost Excluding OH & CP ### ### ###
Overheads (@12 %) (@10 %) (@8 %) 103.83 86.53 69.22
Contractors profit (@10 %) (@10 %) (@10 %) 96.91 95.18 93.45
Total Cost Including OH & CP 1,066.03 1,047.00 1,027.96
Unit Cost Including OH & CP 1,066.03 1,047.00 1,027.96
Crushing of stone aggregates (Nominal size)

Crushing of stone boulders of 150 mm size in an


integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.
3.Crushing Pattern10 mm (tonne)- Cost Distribution
30.75
Unit = %
cum
Taking Output = 1125.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Machinery
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,684.98
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.92
Integrated stone crusher of 250 TPH including belt Hour 6 6 6 ### ### ### 88,470.00
conveyor and vibrating screens
Generator 725 KVA Hour 6 6 6 ### ### ### 60,636.00
Material
Stone Boulder of size 150 mm and below at Cruser cum 750 750 750 350 ### ### ###
Plant
Total Cost Excluding OH & CP ### ### ###
Overheads (@12 %) (@10 %) (@8 %) 88.88 74.07 59.25
Contractors profit (@10 %) (@10 %) (@10 %) 82.96 81.48 79.99
Total Cost Including OH & CP 912.52 896.23 879.93
Unit Cost Including OH & CP 912.52 896.23 879.93

Crushing of stone aggregates (Nominal size)


Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.
4.Crushing Pattern Dust (tonne)- Cost Distribution
08.32%
Unit = cum
Taking Output = 1125.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,684.98
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.92
Integrated stone crusher of 250 TPH including belt Hour 6 6 6 ### ### ### 88,470.00
conveyor and vibrating screens
Generator 725 KVA Hour 6 6 6 ### ### ### 60,636.00
Material
Stone Boulder of size 150 mm and below at Cruser cum 750 750 750 350 ### ### ###
Plant
Total Cost Excluding OH & CP ### ### ###
Overheads (@12 %) (@10 %) (@8 %) 21.87 18.23 14.58
Contractors profit (@10 %) (@10 %) (@10 %) 20.42 20.05 19.69
Total Cost Including OH & CP 224.58 220.57 216.56
Unit Cost Including OH & CP 224.58 220.57 216.56
Crushing of stone aggregates (GSB Crusher Run)

Crushing of stone boulders of 150 mm size in an


integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain crusher run (all in aggregate) for GSB.
1.Taking output = 1125 Tonne (750 Cum) (Note:
Considering Crushed volume will be 1.2 times the
volume of boulder)
Unit = cum
Taking Output = 900.00 cum
Labour
Mate / Supervisor day 0.24 0.24 0.24 569 136.56 136.56 136.56
Mazdoor day 6 6 6 503 3,018.00 3,018.00 3,018.00
Machinery
Tipper 14 cum capacity for transportation within 1 1,125.00 1,125.00 1,125.00 15.74 ### ### 17,707.50
km
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 3,932.00 ### ### 21,683.82
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 2,361.00 ### ### 13,020.22
Integrated stone crusher of 250 TPH including belt Hour 4.615 4.615 4.615 ### ### ### 68,048.18
conveyor and vibrating screens (for producing
crusher run production capacity will increas by 30%)
Generator 725 KVA Hour 4.615 4.615 4.615 ### ### ### 46,639.19
Material
Stone Boulder of size 150 mm and below cum 750 750 750 350 ### ### ###
Total Cost Excluding OH & CP ### ### ###

Overheads (@12 %) (@10 %) (@8 %) ### ### 34,620.28


Contractors profit (@10 %) (@10 %) (@10 %) ### ### 46,737.37
Unit Cost Including OH & CP 592.39 581.81 571.23
Rep
ort
gene
rated
by :
Input_Re
f

#REF!
PM6004
PM5003
PM6003
PM5002
PM6002

PM5001
PM6001

L12
L13
PM6003

L12
L13

PM6003

PM6004
PM6004
PM6003
PM6003

PM6002
PM6002
PM6001
PM6001

PM6004
PM6004
PM6003
PM6003

PM6002
PM6002
PM6001
PM6001

PM6004
PM6004
PM6003
PM6003

PM6002
PM6002
PM6001
PM6001

PM6004
PM6004
PM3400
1
PM3400
1

L12

M002
L12
L13

PM7300
3
PM5001
PM6002
PM1600
1
PM2200
1
M001

L12
L13

PM7300
3
PM5001
PM6002
PM1600
1
PM2200
1
M001

L12
L13

PM7300
3
PM5001
PM6002
PM1600
1
PM2200
1
M001
L12
L13

PM7300
3
PM5001
PM6002
PM1600
1
PM2200
1
M001
L12
L13
PM7300
3
PM5001

PM6002
PM1600
1
PM2200
1
M001

L12
L13

PM7300
3
PM5001
PM6002
PM1600
1

PM2200
1
M001
CHAPTER - 15
BOX CELL STRUCTURES
Ref. to
Sr. No. MoRTH Description Unit Quantity as per project category Rate (`) Cost (`)
Spec.
Large Medium Small LAmt
15.01 304 Excavation for structures
Earth work in excavation of foundation of structures as
per drawing and technical specifications, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.

I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140
Mazdoor day 3.500 3.500 3.500
Total cost without OH & CP
b) Overhead charges on (a) @ @ @
c) Contractor's profit on (a + b) @ @ @
Rate per cum = a+b+c/10

Note 1. Cost of dewatering may be added where required


upto 10 percent of labour cost. Assessment for
dewatering shall be made as per site conditions.

2. The excavated earth can be partially used for


backfilling of foundation pit and partly for road work
except for marshy soil. Hence cost of disposal has not
been added except for marshy soil. This remark is
common to all cases of item 15.01 excluding marshy
soil.
3. The cost of shoring and shuttering, where needed,
may be added @ 1 percent on cost of excavation for
15.01 A (ii) Depth 3 m to 6 m
open foundation.
a) Labour
Mate/Supervisor day 0.180 0.180 0.180
Mazdoor day 4.500 4.500 4.500
Total cost without OH & CP

b) Overhead charges on (a) @ @ @


c) Contractor's profit on (a + b) @ @ @

Cost for 10 cum = a+b+c


Rate per cum = (a+b+c)/10
Note Cost of dewatering may be added where required upto
15 percent of labour cost.Assessment for dewatering
shall be done as per actual ground conditions.

15.01 A (iii) Depth above 6 m

a) Labour
Mate/Supervisor day 0.240 0.240 0.240

Mazdoor day 6.000 6.000 6.000


Total cost without OH & CP
b) Overhead charges on (a) @ @ @
c) Contractor's profit on (a + b) @ @ @
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note 1. Cost of dewatering may be added where required
upto 20 percent of labour cost. Assessment for
dewatering shall be made as per site conditions.

15.01 B (i) Mechanical Means (Depth upto 3 m)


Unit = cum
Taking Output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320
Mazdoor day 8.000 8.000 8.000
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.627

(ii) 1.1 cum bucket capacity hour 5.329

(iii) 0.9 cum bucket capacity hour 7.450

For backfilling (considering 60% of the


excavated material
(i) 1.2 cum bucket capacity hour 2.776
(ii) 1.1 cum bucket capacity hour 3.197
(iii) 0.9 cum bucket capacity hour 4.470
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 198.000
(ii) 14 cum capacity t-km 198.000
(iii)10 cum capacity t-km 198.00
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 330 cum = a+b+c+d
Rate per cum =(a+b+c+d)/330
15.01 B (ii) Mechanical Means (Depth 3 m to 6 m)
Unit = cum
Taking Output = 300 cum
a) Labour
Mate day 0.320 0.320 0.320
Mazdoor day 8.000 8.000 8.000
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.674
(ii) 1.1 cum bucket capacity hour 5.383
(iii) 0.9 cum bucket capacity hour 7.525
For backfilling (considering 60% of the
excavated material
(i) 1.2 cum bucket capacity hour 2.804
(ii) 1.1 cum bucket capacity hour 3.230
(iii) 0.9 cum bucket capacity hour 4.515
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 180.000
(ii) 14 cum capacity t-km 180.000
(iii)10 cum capacity t-km 180.00
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 300 cum = a+b+c+d
Rate per cum =(a+b+c+d)/300

15.01 B (iii) Mechanical Means (Depth above 6 m)


Unit = cum
Taking Output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320
Mazdoor day 8.000 8.000 8.000
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732
(ii) 1.1 cum bucket capacity hour 5.450
(iii) 0.9 cum bucket capacity hour 7.619
For backfilling (considering 60% of the
excavated material
(i) 1.2 cum bucket capacity hour 2.839
(ii) 1.1 cum bucket capacity hour 3.270
(iii) 0.9 cum bucket capacity hour 4.571
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000
(ii) 14 cum capacity t-km 162.000
(iii)10 cum capacity t-km 162.00
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 270 cum = a+b+c+d
Rate per cum =(a+b+c+d)/270
15.01 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 0.200 0.200
Mazdoor day 5.000 5.000 5.000
Total cost without OH & CP
c) Overhead charges on (a) @ @ @
d) Contractor's profit on (a+b) @ @ @
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note Cost of dewatering may be added where required upto
10 percent of labour cost may be added, where
required. Assessment for dewatering shall be made as
per site conditions.
15.01 B Mechanical Means
Unit = cum
Taking Output = 50 cum
a) Labour
Mate day 0.120 0.120 0.120
Mazdoor day 3.000 3.000 3.000
b) Machinery
Hydraulic Excavator
Excavator For excavation
(i) 1.2 cum bucket capacity hour 5.818
(ii) 1.1 cum bucket capacity hour 6.845
(iii) 0.9 cum bucket capacity hour 7.273
For loading
(i) 1.2 cum bucket capacity hour 0.872
(ii) 1.1 cum bucket capacity hour 1.005
(iii) 0.9 cum bucket capacity hour 1.405
Jack Hammer hour 5.818 6.845 7.273
Tipper for transportation considering lead @ 1
km
(i) 18 cum capacity t-km 75.000
(ii) 14 cum capacity t-km 75.000
(iii)10 cum capacity t-km 75.000
For loading & unloading time
(i) 18 cum capacity hour 0.872
(ii) 14 cum capacity hour 1.005
(iii)10 cum capacity hour 1.405
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 50 cum= a+b+c+d
Rate per cum =(a+b+c+d)/50
15.01 302 & 303 lll Hard Rock ( requiring blasting)

A Manual Means
Unit = cum
Taking Output = 10 cum
a) Labour
Mate day 0.350 0.350 0.350
Driller day 0.500 0.500 0.500
Blaster day 0.250 0.250 0.250
Mazdoor day 8.000 8.000 8.000
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.000 1.000 1.000
drilling
c) Material
Explosives (Blasting Material) kg 3.500 3.500 3.500\
Detonator electric each 14.000 14.000 14.000
Total cost without OH & CP
d) Overhead charges on (a+b+c) @ @ @
e) Contractor's profit on (a+b+c+d) @ @ @
Cost for 10 cum = a+b+c+d+e
Rate per cum =(a+b+c+d+e)/10
Note Cost of dewatering @ 10 percent of (a+b) may be
added, where required. Assessment for dewatering
shall be made as per site conditions.
15.01 302 & lll Hard Rock ( requiring blasting)
303
Carrying out excavation hard rock to achieve a
specified slope of the rock face by controlied use of
explosives and blasting accessories in properly aligned
and spaced drill holes, collection of the excavated rock
by a dozer, loading in tipper by a front end loader and
disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303

B Mechanical Means
Unit = cum
Taking Output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210
Mazdoor day 3.000 3.000 3.000
Driller day 2.000 2.000 2.000
Blaster day 0.250 0.250 0.250
b) Machinery
Air compressor hour 6.000 6.000 6.000
Jack Hammer for drilling holes (@ 4.5 m per hour 24.000 24.000 24.000
hour)
Jack hammer ( consider 5% of the volume for hour 1.024 1.024 1.024
dressing)
Hydraulic Excavator
Excavator For excavation
(i) 1.2 cum bucket capacity hour 1.024
(ii) 1.1 cum bucket capacity hour 1.024
(iii) 0.9 cum bucket capacity hour 1.024
For loading
(i) 1.2 cum bucket capacity hour 2.094
(ii) 1.1 cum bucket capacity hour 2.411
(iii) 0.9 cum bucket capacity hour 3.371
Tipper for transportation considering lead @ 1
km
(i) 18 cum capacity t-km 180.000
(ii) 14 cum capacity t-km 180.000
(iii)10 cum capacity t-km 180.000
For loading & unloading time
(i) 18 cum capacity hour 2.094
(ii) 14 cum capacity hour 2.411
(iii)10 cum capacity hour 3.371
c) Materials
Small dia Explosive at 0.40 kg/cum for 120 cum ( 120 kg 48.000 48.00 48.000
x0.40) Explosive at 0.20 kg/cum for secondary
blast @ 5% of the total volume (120x0.2x5%)

Electric detonators at 1 per hole for main blast holes no 69.000 69.00 69.000
(21x3+20*2)= 103 nos.
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000
holes (required for 5% of the total quantity @ 0.6 m per
hole for 1 cum)
Detonating fuse coil m 213.000 213.000 213.000
Total cost without OH & CP
d) Overhead charges on (a+b+c) @ @ @
e) Contractor's profit @ @ @
Cost for 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

15.01 lV Hard Rock ( blasting prohibited)


Unit = cum
Taking Output = 35 cum
A Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080
Mazdoor day 2.000 2.000 2.000
b) Machinery
Jack Hammer hour 5.973 7.467 9.190
Hydraulic Excavator
Excavator For excavation
(i) 1.2 cum bucket capacity hour 5.973
(ii) 1.1 cum bucket capacity hour 7.467
(iii) 0.9 cum bucket capacity hour 9.190
For loading
(i) 1.2 cum bucket capacity hour 0.611
(ii) 1.1 cum bucket capacity hour 0.703
(iii) 0.9 cum bucket capacity hour 0.983
Tipper
For transportation to dumping yard considering
lead @ 1 km
(i) 18 cum capacity t-km 52.500
(ii) 14 cum capacity t-km 52.500
(iii)10 cum capacity t-km 52.500
For loading & unloading time
(i) 18 cum capacity hour 0.611
(ii) 14 cum capacity hour 0.703
(iii)10 cum capacity hour 0.983
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 35 cum= a+b+c+d
Rate per cum = (a+b+c+d)/35

15.01 V Marshy soil


Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual Means
a) Labour
Mate/ Supervisor day 0.400 0.400 0.400
Mazdoor day 10.000 10.000 10.000
b) Machinery
Tractor-trolley for removal hour 2.670 2.670 2.670
Total cost without OH & CP
c) Overhead charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10

Note 1. Cost of dewatering @ 30 percent of (a), may be


added where required. Assessment for dewatering shall
be made as per site conditions.
2. Shoring and strutting 15 percent of (a), where
required may be added.
3. It is assumed that Marshy soil will be available upto
3 m depth only. For deeper excavation below 3 m
depth, refer analysis in item 15.01 (i) to (iv) for
ordinary soil.

15.01 B Mechanical Means


Unit = cum
Taking Output = 260 cum
a) Labour
Mate day 0.040 0.040 0.040
Mazdoor day 1.000 1.000 1.000
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506
(ii) 1.1 cum bucket capacity hour 9.796
(iii) 0.9 cum bucket capacity hour 13.695
Tipper
For transportation to dumping yard considering
lead @ 1 km
(i) 18 cum capacity t-km 390.000
(ii) 14 cum capacity t-km 390.000
(iii)10 cum capacity t-km 390.000
For loading & unloading time
(i) 18 cum capacity hour 8.506
(ii) 14 cum capacity hour 9.796
(iii)10 cum capacity hour 13.695
c) Material
Selected earth for refilling cum 156.000 156.00 156.000
Total cost without OH & CP
d) Overhead charges on (a+b+c) @ @ @
e) Contractor's profit on (a+b+c+d) @ @ @
Cost for 260 cum= a+b+c+d
Rate per cum = (a+b+c+d)/260

15.01 Vl Back filling in Marshy foundation pits


Unit=cum
Taking output = 6 cum
a) Labour
Mate day 0.120 0.120 0.120
Mazdoor for dressing sides, bottom and backfilling day 3.000 3.000 3.000
b) Machinery
Tractor-trolley for transportation hour 2.000 2.000 2.000
Total cost without OH & CP
c) Overhead Charges on (a+b) @ @ @
d) Contractor's profit on (a+b+c) @ @ @
Cost for 6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/6

15.02 304 Filling Annular space Around Footing in Rock


Unit= cum
Taking output = 1 cum
PCC-15 nominal mix. Rate may be taken as per item
15.11

15.03 304 Sand Filling in Foundation Trenches as per


Drawing and Technical Specification
Unit= cum
Taking output= 100 cum
a) Labour
Mate day 0.040 0.040 0.040
Mazdoor day 1.000 1.000 1.000
b) Machinery
Water tanker ( speed @ 20 km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip)

(i) 16 KL capacity hour 0.125xL1+0.750


(i) 12 KL capacity hour 0.167xL1+1.000
(i) 6 KL capacity hour 0.333xL1+2.000
c) Material
Sand (assuming 20 percent voids) at site cum 120.000 120.000 120.000
Water KL 18.000 18.000 18.000
Total cost without OH & CP
d) Overhead Charges on (a+b+c) @ @ @
e) Contractor's profit on (a+b+c+d) @ @ @
Rate per 100 cum= a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
15.04 1300 Brick Masonary Work in Cement Mortar 1:3 in
Foundation complete excluding pointing and
plastering, as per Drawing and Technical
specifications.
Unit = cum
Taking output =5 cum
a) Material
Brick 1st class each 2500.000 2500.000 2500.000
Cement mortar 1:3 (Rate taken from sub-analysis cum 1.200 1.200 1.200
items 21.01A)
Remarks/
Cost (`)
Input ref.

MAmt Samt
Comparative Statement of usages rate of Plants & Machinery for preparation of Schedule of rate 2021-22 including all
charges ,cost of repair,maintaintance,tyre- replacement,running and operating charges such as fuel lubricant,labour etc
but excluding GST,Overhead and Contractor's profit.

Sl.No Code Description Unit Uses rates as Uses rates as Lowest Proposed Rate Remarks
per per NH Rate
downloaded Mechanical
from Deptt,RCD
uptodated Bihar.
MORT&H on
line SOR
software
( based upon
new MORT&H
Data Book
2019)

1 PM1001 Dozer - 240 HP Hour 6,461.00 - - 6,461.00


2 PM1002 Dozer - 175 HP Hour 4,930.00 - - 4,930.00
3 PM1003 Dozer - 90 HP Hour 3,274.00 - - 3,274.00
4 PM2001 Motor Grader 4.3 metre blade Hour 5,900.00 - - 5,900.00
5 PM2002 Motor Grader 3.7 metre blade Hour 5,398.00 - - 5,398.00
6 PM2003 Motor Grader 3.35 metre blade Hour 4,665.00 2982 2982 2982
7 PM3003 Hydraulic Excavator of 1.2 cum bucket Hour 3,388.00 - - 3,388.00
8 PM3004 Hydraulic Excavator of 1.1 cum bucket Hour 3,021.00 - - 3,021.00
9 PM3005 Hydraulic Excavator of 0.9 cum bucket Hour 2,702.00 - - 2,702.00
10 PM4001 Jack Hammer (attachment of Hydraulic Excavator) Hour 206.00 - - 206.00
11 PM5001 Front End loader 3.1 cum bucket capacity Hour 4,255.00 - - 4,255.00
12 PM5002 Front End loader 2.1 cum bucket capacity Hour 2,588.00 - - 2,588.00
13 PM5003 Backhoe-loader 1 cum bucket capacity Hour 1,703.00 1594 1594 1594
14 PM6001 Tipper-18 Cum Hour 2,772.00 - - 2772
15 PM6002 Tipper-14 Cum Hour 2,415.00 2725 2415 2415
16 PM6003 Tipper-10 Cum Hour 2,121.00 - - 2121
17 PM6004 Tipper-5.5 Cum Hour 1,536.00 1183 1183 1183
18 PM7001 Vibratory Soil Compactor (10 tonne) Hour 2,367.00 2156 2156 2156
19 PM8001 Smooth Wheeled Roller 8 tonne Hour 1,893.00 901 901 901
20 PM9001 Tandem Roller Hour 2,357.00 - - 2,357.00
21 PM9002 Mini Tandem Roller hour 1,210.00 - - 1,210.00
PM10001 Pneumatic Road Roller Hour 2,437.00 2338 2338 2338 Vibratory road
Roller
22
23 PM11001 Water Tanker (16 KL) Hour 1,426.00 - - 1,426.00
24 PM11002 Water Tanker (12 KL) Hour 1,252.00 - - 1,252.00
25 PM11003 Water Tanker (6 KL) Hour 907.00 - - 907.00
26 PM12001 Tractor-Trolly Hour 787.00 612.00 612.00 612.00
(25 HP )
27 PM13001 Rotavator Hour 17.00 - - 17.00
28 PM14001 Ripper Hour 21.00 - - 21.00
29 PM15001 Air Compressor -250 cfm Hour 416.00 - - 416.00
30 PM15002 Air Compressor -500 cfm Hour 2,848.00 - - 2,848.00
31 PM16001 Integrated Stone Crusher Stone (3 Stage) 250 TPH Hour 13,431.00 - - 13,431.00
32 PM17001 Wet Mix Plant - 250 TPH Capacity Hour 642.00 642.00 No Capacity
33 PM17002 Wet Mix Plant - 200 TPH Capacity Hour 348.00 - - 348.00
34 PM17003 Wet Mix Plant - 100 TPH Capacity Hour 322.00 322.00
3171.00
(75 TPH) -
35 PM18001 Hotmix Plant - 200 TPH Capacity Hour 14,810.00 - - 14,810.00
36 PM18002 Hotmix Plant - 160 TPH Capacity Hour 10,450.00 - - 10,450.00
37 PM18003 Hotmix Plant - 120 TPH capacity Hour 8,309.00 61700.00 8309.00 8309.00
38 PM19001 Batching and Mixing Plant - 240 cum Capacity Hour 5,670.00 - - 5670.00
39 PM19002 Batching and Mixing Plant - 120 cum Capacity Hour 3,627.00 3627.00
40 PM20001 Mobile Concrete Batching / Mixing Plant Hour 735.00 - - 735.00
41 PM21001 Concrete Mixer - 0.4/0.28 cum Hour 300.00 286.00 286.00 286.00
42 PM21002 Concrete Mixer - 1 cum Hour 344.00 - - 344.00
43 PM22001 Generator 725 KVA Hour 13,148.00 - - 13,148.00
44 PM22002 Generator 500 KVA Hour 9,075.00 - - 9,075.00
45 PM22003 Generator 400 KVA Hour 7,303.00 - - 7,303.00
46 PM22004 Generator 250 KVA Hour 5,133.00 4359.00 4359.00 4359.00
47 PM22005 Generator 125 KVA Hour 2,653.00 3131.00 2653.00 2653.00
48 PM22006 Generator 100 KVA Hour 2,251.00 2277.00 2251.00 2251.00
49 PM22007 Generator 62.5 KVA Hour 1,421.00 - - 1,421.00
50 PM22008 Generator 33 KVA Hour 783.00 - - 783.00
51 PM22009 Generator 15 KVA Hour 410.00 - - 410.00
52 PM23001 Mechanical Broom Hydraulic Hour 936.00 642.00 642.00 642.00
53 PM24001 Bitumen Pressure Distributor Hour 1,645.00 - - 1,645.00
54 PM25001 Emulsion Pressure Distributor Hour 1,645.00 - - 1,645.00
55 PM26001 Bitumen Boiler Oil Fired Hour 606.00 - - 606.00
56 PM27001 Mastic Cooker Hour 461.00 - - 461.00
57 PM28001 Paver Finisher Mechanical Hour 2,409.00 1583.00 1583.00 1583.00
(75 /100TPH)
58 PM29001 Paver Finisher Hydrostatic with sensor control -240 HP Hour 8,710.00 - - 8710.00
59 PM29002 Paver Finisher Hydrostatic with sensor control -170 HP Hour 6,808.00 6808.00
60 PM30001 Paver Finisher Concrete with 300 HP Motor Hour 26,752.00 - - 26752.00
61 PM30002 Paver Finisher Concrete with 241 HP Motor Hour 17,252.00 - - 17252.00
62 PM30003 Paver Finisher Concrete with 118 HP Motor Hour 4,082.00 - - 4,082.00
63 PM31001 Texture Curing Machine (TCM) - upto 18 m Hour 4,470.00 - - 4,470.00
64 PM31002 Texture Curing Machine (TCM) - upto 9 m Hour 3,497.00 - - 3,497.00
65 PM32001 Hydraulic Chip Spreader Hour 2,146.00 - - 2,146.00
66 PM33001 Pot-Hole Repair Machine Hour 1,718.00 - - 1,718.00
67 PM34001 Transit Mixer - 6 Cum Hour 2,218.00 - - 2,218.00
68 PM35001 Concrete Pump Hour 1,050.00 - - 1,050.00
69 PM36001 Boom Placer Hour 4,052.00 - - 4,052.00
70 PM37001 Kerb Casting Machine Hour 1,590.00 - - 1,590.00
71 PM38001 Piling Rig with Bentonite Pump Hour 19,622.00 - - 19,622.00
72 PM39001 Pneumatic Sinking Plant Hour 7,055.00 - - 7,055.00
73 PM40001 Road marking machine Hour 1,965.00 - - 1,965.00
74 PM41001 Mobile Slurry Seal Equipment Hour 3,619.00 - - 3,619.00
75 PM42001 Joint Cutting Machine Hour 317.00 - - 317.00
76 PM43001 Bar Bending & Cutting Machine Hour 334.00 - - 334.00
77 PM44001 Needle Vibrator Hour 347.00 - - 347.00
78 PM45001 Jack Hammer for air compressor Hour 11.00 - - 11.00
79 PM46001 Plate Compactor Hour 352.00 - - 352.00
80 PM47001 Milling Machine with 1 meter Drum Width Hour 4,448.00 - - 4,448.00
81 PM47002 Milling Machine with 1.2 meter Drum Width Hour 5,276.00 - - 5,276.00
82 PM47003 Milling Machine With 1.3 meter Drum Width Hour 7,711.00 - - 7,711.00
83 PM47004 Milling Machine With 2 meter Drum Width Hour 11,192.00 - - 11,192.00
84 PM48001 Cold in Situ recycling of bitumen's pavement with foam Hour 28,850.00 28,850.00
bitumen technology
- -
85 PM49001 In situ stabilisation of WMM/GSB/Sub grade Hour 25,715.00 - - 25,715.00
86 PM50001 Cement spreader Hour 7,872.00 - - 7,872.00
87 PM51001 Mobile cold recycling mixing plant Hour 21,242.00 - - 21,242.00
88 PM52001 Hot in place recycling Hour 103,416.00 - - 103,416.00
89 PM53001 Pre heater unit for hot in place recycling Hour 902.00 - - 902.00
90 PM54001 Single boom Hydraulic Drill Jumbo Hour 4,513.00 - - 4,513.00
91 PM55001 Two boom Hydraulic Drill Jumbo Hour 6,857.00 - - 6,857.00
92 PM56001 Three boom Hydraulic Drill Jumbo Hour 10,022.00 - - 10,022.00
93 PM57001 Hydraulic Rock bolt drill Hour 6,711.00 - - 6,711.00
94 PM58001 Rotating Telehandlers Hour 1,075.00 - - 1,075.00
95 PM59001 Shotcrete Machine Hour 1,433.00 - - 1,433.00
96 PM60001 Grouting machine Hour 521.00 - - 521.00
97 PM61001 Dewatering Pump 10 HP Hour 260.00 - - 260.00
98 PM61002 Concrete cutting machine Hour 175.00 - - 175.00
99 PM62001 Crawler mounted Crane 35 tonne capacity Hour 6,082.00 - - 6,082.00
100 PM62002 Crawler mounted Crane 80 tonne capacity Hour 6,403.00 - - 6,403.00
101 PM62003 Crawler mounted Crane 100 tonne capacity Hour 9,736.00 - - 9,736.00
102 PM63001 Mobile Hydraulic Crane 3 tonne capacity Hour 862.00 - - 862.00
103 PM63002 Mobile Hydraulic Crane 5 tonne capacity Hour 909.00 - - 909.00
104 PM63003 Mobile Hydraulic Crane 10 tonne capacity Hour 1,019.00 - - 1,019.00
105 PM63004 Mobile Hydraulic Crane 15 tonne capacity Hour 1,057.00 - - 1,057.00
106 PM63005 Mobile Hydraulic Crane 20 tonne capacity Hour 1,466.00 - - 1,466.00
107 PM63006 Mobile Hydraulic Crane 35 toone capacity Hour 2,337.00 - - 2,337.00
108 PM64001 Concrete Bucket Hour 83.00 - - 83.00
109 PM65001 Prestressing Jack with Pump & Access Hour 406.00 - - 406.00
110 PM66001 Boat to carry atleast 20 persons hour 773.00 - - 773.00
111 PM67001 Crane with grab 0.75 cum capacity hour 871.00 - - 871.00
112 PM68001 Epoxy Injection gun hour 241.00 - - 241.00
113 PM6900 Induction, deinduction and erection of plant and hour 9,688.00 9,688.00
1 equipment including all components and accessories for
pneumatic method of well sinking.
- -
114 PM7000 Jack for Lifting 40 tonne lifting capacity. hour 232.00 - - 232.00
115 1
PM7100 Vibrating Pile driving hammer complete with power unit hour 18,501.00 18,501.00
1 and accessories.
- -
116 PM7200 Tipper 18 Cum ( Surface Road) Per As per Carriage
1 Tonn Rate
e
Km. - -
117 PM7200 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding t.km Do
2 OH & CP
- -
118 PM7200 Tipper-18 Cum (Katcha Track) excluding OH & CP t.km - - Do
3
PM7300 Tipper -14 Cum (Surface Road) excluding OH & CP t.km Do
119 - -
120 1
PM7300 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding t.km Do
2 OH & CP
- -
121 PM7300 Tipper -14 Cum (Katcha Track) excluding OH & CP t.km - - Do
3
PM7400 Tipper -10 Cum (Surface Road) excluding OH & CP t.km Do
122 - -
123 1
PM7400 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding t.km Do
2 OH & CP
- -
124 PM7400 Tipper -10 Cum (Katcha Track) excluding OH & CP t.km - - Do
125 3
PM7500 Tipper- 5.5 Cum (Surface Road) excluding OH & CP t.km Do
- -
126 1
PM7500 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding t.km Do
2 OH & CP
- -
127 PM7500 Tipper- 5.5 Cum (Katcha Track) excluding OH & CP t.km - - Do
3
PM76001 Transit Mixer - 6 Cum excluding OH & CP t.km Do
128 - -
129 PM77001 Loading and unloading of stone boulder / stone aggregates / cum - - Do
sand / kanker / moorum (Using by 18 cum capacity Tipper
& 3.1 Cum capacity Loader) excluding OH & CP

130 PM77002 Loading and unloading of stone boulder / stone aggregates / cum - - Do
sand / kanker / moorum (Using by 14 cum capacity Tipper
& 2.1 Cum capacity Loader) excluding OH & CP

131 PM77003 Loading and unloading of stone boulder / stone aggregates / cum - - Do
sand / kanker / moorum (Using by 10 cum capacity Tipper
& 1.0 Cum capacity Loader) excluding OH & CP

132 PM77004 Loading and unloading of stone boulder / stone aggregates / cum - - Do
sand / kanker / moorum (Using by 5 cum capacity Tipper &
1.0 Cum capacity Loader) excluding OH & CP

133 PM77005 Loading and Unloading of Cement or Steel by Manual tonne Do


Means and Stacking
134 PM78001 Centrifugal water pump Hour 329.00 - - 329.00
135 PM79001 Shredding Machine Hour 416.00 - - 416.00
136 PM80001 Mobile Bridge Inspection Unit (MBIU) hour 6,887.00 - - 6,887.00
137 PM81001 Network Survey Vehicle (NSV) With SUV hour 6,287.00 - - 6,287.00
PM82001 Falling weight deflectometer (FWD) Equipment With SUV hour 3,128.00 3,128.00
138 - -
PM83001 Retroreflectometer testing equipment with Vehicle With hour 1,709.00 1,709.00
SUV
139 - -
140 PM84001 Sport utility vehicle (SUV) hour 1,221.00 - - 1,221.00
141 PM85001 Automatic Vehicle Counter Classifier (ATCC) System hour 74.00 - - 74.00
142 PM90001 WMM Paver finisher hour 1810.00 - 1810.00
143 PM90002 6.5 KVA Generator set hour 304.00 - 304.00
144 PM90003 Sensor Paver Finisher(158 BHP) hour 3958.00 3958.00
145 PM90004 Mini Hot Mix Plant(06-10 TPH) hour 4278.00 For
consideration of
committee
-
146 PM90005 Batching &Mixing Plant 30cum Capacity hour 3249.00 - Do
147 PM90006 40-60 TPH Hot Mix Plant hour 27543.00 - Do
148 PM90007 60-90 TPH Hot Mix Plant hour 39453.00 - Do
149 PM90008 100 TPH Hot Mix Plant hour 46860.00 - Do

mDr of.kZr enksa dks jkT; Lrjh; vuqlwfpr nj fu/kkZj.k lfefr dh cSBd esa fopkj&foe'kZ gsrq miLFkkfir fd;k tkrk
gSA

lgk;d vfHk;ark dk;Zikyd vfHk;ark v/kh{k.k vfHk;ark


PROPOSED CARRIAGE RATE OF MATERIALS (By TIPPER) Meeting Date…..
Sl.No Ref.t Description Unit Quantity as per Project Category Rate Amount Input_Re
o M. f

Large Medium Small Large Medium Small


Loading and unloading of stone boulder / stone
1.01 A aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front
end loader, dumping, turning for return trip,
excluding time for haulage and return trip
Unit = cum
A.Taking output = 5.5 Cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 6.633 6.633 6.633
capacity
iii) Maneuvering, reversing, dumping and turning Min 2.000 2.000 2.000
for return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.633 13.633 13.633
a) Machinery
Tipper-5.5 Cum capacity Hour 0.227 0.227 0.227 1,183.00 268.541 268.541 268.541 #REF!
Front end -loader 1 cum bucket capacity Hour 0.227 0.227 0.227 1,594.00 361.838 361.838 361.838 #REF!
Total Cost Excluding OH & CP 630.379 630.379 630.379
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 50.430 63.038 75.645
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 68.081 69.342 70.602

Total Cost for 5.5 cum = (a+b+c) Including OH & 748.890 762.759 776.627
CP
Unit Cost= (a+b+c)/5.5 Including OH & CP 136.162 138.683 141.205

Note :Unloading will be by tipping. Say 136.200 138.700 141.200


1.01 B Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front
end loader, dumping, turning for return trip,
excluding time for haulage and return trip
Unit = cum
Taking Output = 10.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 12.060 12.060 12.060
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 19.060 19.060 19.060
a) Machinery
Tipper-10 Cum capacity Hour 0.318 0.318 0.318 #REF! #REF! #REF! #REF! #REF!
Front end-loder 1 cum bucket capacity Hour 0.318 0.318 0.318 1,594.00 506.892 506.892 506.892 #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for 10 cum = (a+b+c)Including OH & CP #REF! #REF! #REF!

Unit Cost= (a+b+c)/10 Including OH & CP #REF! #REF! #REF!


Note :Unloading will be by tipping. Say #REF! #REF! #REF!
1.01 C. Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front
end loader, dumping, turning for return trip,
excluding time for haulage and return trip
Unit = cum
Taking Output = 14.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 2.1 cum bucket capaci Min 8.029 8.029 8.029
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 15.029 15.029 15.029
a) Machinery
Tipper-14 Cum capacity Hour 0.250 0.250 0.250 #REF! #REF! #REF! #REF! #REF!
Front End loader 2.1 cum bucket capacity Hour 0.250 0.250 0.250 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for 14 cum = (a+b+c)Including OH & CP #REF! #REF! #REF!

Unit Cost= (a+b+c)/14 Including OH & CP #REF! #REF! #REF!


Note :Unloading will be by tipping. Say #REF! #REF! #REF!
1.01 D Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front
end loader, dumping, turning for return trip,
excluding time for haulage and return trip
Unit = cum
Taking Output = 18.00 cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 3.1 cum bucket Min 6.996 6.996 6.996
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.996 13.996 13.996
a) Machinery
Tipper-18 Cum capacity. Hour 0.233 0.233 0.233 #REF! #REF! #REF! #REF! #REF!
Front End loader 3.1 cum bucket capacity Hour 0.233 0.233 0.233 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
Total Cost for 18 cum = (a+b+c)Including OH & CP #REF! #REF! #REF!

Unit Cost= (a+b+c)/18 Including OH & CP #REF! #REF! #REF!


Note :Unloading will be by tipping. Say #REF! #REF! #REF!
1.02 Ref.t Loading and Unloading of Boulders by Manual
o M. Means
Unit = cum
Taking output = 10 Cum
a) Labour
Mate day 0.055 0.055 0.055 310.000 17.050 17.050 17.050 L-12
Mazdoor day 1.364 1.364 1.364 292.000 398.288 398.288 398.288 L-13
b) Machinery
Tipper-10 Cum capacity Hour 1.364 1.364 1.364 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for10 cum=(a+b+c+d)Including OH & #REF! #REF! #REF!


CP
Unit Cost=(a+b+c+d)/10 Including OH & CP #REF! #REF! #REF!

Note :Unloading will be by tipping. Say #REF! #REF! #REF!


1.03 Ref.t Loading and Unloading of Cement or Steel by
o M. Manual Means and Stacking.

Unit = tonne
Taking Output = 18.00 tonne
a) Labour
Mate day 0.144 0.144 0.144 310.000 44.640 44.640 44.640 L-12
Mazdoor day 3.600 3.600 3.600 292.000 1051.200 1051.200 1051.200 L-13
b) Machinery
Truck-18 tonne capacity. Hour 3.600 3.600 3.600 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
Total Cost for 18 tonnes=(a+b+c+d)Including OH & #REF! #REF! #REF!
CP
Unit Cost=(a+b+c+d)/18 Including OH & CP #REF! #REF! #REF!
Say #REF! #REF! #REF!
Cost of Haulage Excluding Loading and
1.04 (i) A Unloading
i) A.Case-I : Surfaced Road.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load and lead 10 km=100.
t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 1,183.00 473.200 473.200 473.200 #REF!
Time taken for empty return trip. Hour 0.286 0.286 0.286 1,183.00 338.338 338.338 338.338 #REF!
Total Cost Excluding OH & CP 811.538 811.538 811.538
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 64.923 81.154 97.385
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 87.646 89.269 90.892

Total Cost for100 t.km = (a+b+c)Including OH & 964.107 981.961 999.815


CP
Rate per t.km= (a+b+c)/100 Including OH & CP 9.641 9.820 9.998

Say 9.600 9.800 10.000


Cost of Haulage Excluding Loading and
Unloading

B i) Case-I : Surfaced Road .


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output =18tonnes load and lead10 km=180.
t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 18 tonne capacity.
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.286 0.286 0.286 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
Total Cost for180 t.km = (a+b+c)Including OH & #REF! #REF! #REF!
CP
Rate per t.km= (a+b+c)/180 Including OH & CP
#REF! #REF! #REF!
Say #REF! #REF! #REF!
C Case-I : Surfaced Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output = 25 tonne load and lead
10km=250.t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 25 tonnes capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.286 0.286 0.286 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for250 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/250 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


D Case-I : Surfaced Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output =32tonnes load and lead10km= 320.
t.km
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery
i) Tipper 32 tonne capacity
Time taken for onward haulage with load. Hour 0.400 0.400 0.400 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.286 0.286 0.286 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for320 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/320 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (ii) A .Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10 km= 100
t.km
Speed with load: 20 km/hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 1183.000 591.500 591.500 591.500 #REF!
Time taken for empty return trip. Hour 0.333 0.333 0.333 1183.000 393.939 393.939 393.939 #REF!
Total Cost Excluding OH & CP 985.439 985.439 985.439
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 78.835 98.544 118.253
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 106.427 108.398 110.369
Total Cost for100 t.km = (a+b+c)Including OH & 1,170.702 1,192.381 1,214.061
CP
Rate per t.km= (a+b+c)/100 Including OH & CP 11.707 11.924 12.141

Say 11.700 11.900 12.100


1.04 (ii) B Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 18 tonnes load & lead10
km=180.t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage with load. Hour 0.500 0.500 0.500 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.333 0.333 0.333 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for180 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/180 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (ii) C Case-II : Unsurfaced Gravelled Road .
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 25 tonnes load & lead10 km =250.
t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
Tipper 25 tonnes capacity.
Time taken for onward haulage with load Hour 0.500 0.500 0.500 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.333 0.333 0.333 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for250 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/250 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (ii) D Case-II : Unsurfaced Gravelled Road.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 32tonnes load & lead 10 km= 320.
t.km
Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage with load Hour 0.500 0.500 0.500 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.333 0.333 0.333 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for320 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/320 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (iii) ACase-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10km= 100
t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 1.000 1.000 1.000 1,183.00 1183.000 1183.000 1183.000 #REF!
Time taken for empty return trip. Hour 0.667 0.667 0.667 1,183.00 789.061 789.061 789.061 #REF!
Total Cost Excluding OH & CP 1,972.061 1,972.061 1,972.061
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 157.765 197.206 236.647
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 212.983 216.927 220.871

Total Cost for100 t.km = (a+b+c)Including OH & 2,342.808 2,386.194 2,429.579


CP
Rate per t.km= (a+b+c)/100 Including OH & CP 23.428 23.862 24.296

Say 23.400 23.900 24.300


1.04 (iii) Biii) B.Case-III : Katcha Track and Track in river
bed / nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output18 tonnes load &lead10km=180.00
t.km
Speed with load: 10 km / hour
Speed while returning empty: 15 km / hour
a) Machinery
Tipper 18 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.667 0.667 0.667 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
Total Cost for180 t.km = (a+b+c)Including OH & #REF! #REF! #REF!
CP
Rate per t.km= (a+b+c)/180 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (iii) CCase-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output25Tonnes load &lead10 km=250.t.km

Speed with load: 10 km / hour


Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 25 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.667 0.667 0.667 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for250 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/250 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (iii) DCase-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output32 tonnes load &lead 1 km= 320. t.km

Speed with load: 10 km / hour


Speed while returning empty: 15 km / hour
a) Machinery
i) Tipper 32 tonnes capacity
Time taken for onward haulage Hour 1.000 1.000 1.000 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip Hour 0.667 0.667 0.667 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for320 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/320 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.04 (iv) Case-IV : Katcha Track in hilly area.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking Output 10 tonnes load & lead 10km= 100.
t.km
Speed with load: 5 km / hour
Speed while returning empty: 7 km / hour
a) Machinery
i) Tipper 10 tonnes capacity.
Time taken for onward haulage Hour 2.000 2.000 2.000 1,183.00 2366.000 2366.000 2366.000 #REF!
Time taken for empty return trip. Hour 1.429 1.429 1.429 1,183.00 1690.507 1690.507 1690.507 #REF!
Total Cost Excluding OH & CP 4,056.507 4,056.507 4,056.507
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 324.52056 405.6507 486.78084
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 438.102756 446.21577 454.328784

Total Cost for100 t.km = (a+b+c)Including OH & 4,819.130 4,908.373 4,997.617


CP
Rate per t.km= (a+b+c)/100 Including OH & CP 48.191 49.084 49.976

Say 48.200 49.100 50.000


1.04 (v) Case-V : Transit Mixture
Haulage of Concrete by transit mixture excluding
cost of loading, unloading and stacking.

Unit = t.km
Taking Output 15Tonnes load & lead 10km= 150
t.km
Speed with load : 20 km / hour
Speed while returning empty: 30 km / hour
a) Machinery
i) Transit Mixture 6 cum capacity.
Time taken for onward hanlage with load Hour 0.500 0.500 0.500 #REF! #REF! #REF! #REF! #REF!
Time taken for empty return trip. Hour 0.333 0.333 0.333 #REF! #REF! #REF! #REF! #REF!
Total Cost Excluding OH & CP #REF! #REF! #REF!
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

Total Cost for150 t.km = (a+b+c)Including OH & #REF! #REF! #REF!


CP
Rate per t.km= (a+b+c)/150 Including OH & CP #REF! #REF! #REF!

Say #REF! #REF! #REF!


1.05 Hand Broken Stone Aggregates 63 mm nominal
size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as directed

Unit = cum
Taking Output = 1.00 cum
a) Labour
Mate day 0.0600 0.0600 0.0600 310.000 18.600 18.600 18.600 L-12
Mazdoor day 1.500 1.500 1.500 292.000 438.000 438.000 438.000 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.1000 1.1000 1.1000 351.360 386.496 386.496 386.496 M-001
Total Cost Excluding OH & CP 843.096 843.096 843.096
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 67.448 84.310 101.172
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 91.054 92.741 94.427

Total Cost for1cum = (a+b+c+d)Including OH & CP 1,001.598 1,020.146 1,038.694

Rate per cum= (a+b+c+d) Including OH & CP Say 1,001.600 1,020.100 1,038.700

Crushing of stone aggregates (Nominal size)


1.06
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per hour
capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.

(i) 1.Crushing Pattern 40 mm (tonne)- Cost


Distribution 28.98 %
Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.000 99.200 99.200 99.200 L-12
Mazdoor(Skilled) day 2.000 2.000 2.000 370.000 740.000 740.000 740.000 L-15
Mazdoor day 6.000 6.000 6.000 292.000 1752.000 1752.000 1752.000 L-13
b) Material
Stone Boulder of size 150 mm and below at Cruser cum 750.000 750.000 750.000 4.00 3000.000 3000.000 3000.000 1.00
Plant
c) Machinery
Integrated stone crusher of 250 TPH including belt Hour 6.000 6.000 6.000 #REF! #REF! #REF! #REF! #REF!
conveyor and vibrating screens
Generator 725 KVA Hour 6.000 6.000 6.000 #REF! #REF! #REF! #REF! #REF!
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 #REF! #REF! #REF! #REF! #REF!
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 #REF! #REF! #REF! #REF! #REF!
Tipper 14 cum capacity for transportation within 1 t.km 1,125.000 1,125.000 1,125.000 #REF! #REF! #REF! #REF! #REF!
km
d) Total Cost for 750 cum(Excluding OH & CP) #REF! #REF! #REF!

e) Crushing pattern 40mm(tonne) tonne 22.71% 22.71% 22.71% 255.488


f) % Cost distribution={(d)x(f)/e)x1.5} cum 28.98% 28.98% 28.98% 0.2898 #REF! #REF! #REF!
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

i) Total Cost for1cum = (f+g+h) Including OH & CP #REF! #REF! #REF!

Rate per cum= (f+g+h) Including OH & CP Say #REF! #REF! #REF!

(ii) Crushing of stone aggregates (Nominal size)

2.Crushing Pattern 20 mm (tonne)- Cost


Distribution 31.95 %
d) Total Cost for 750 cum(Excluding OH & CP) #REF! #REF! #REF!

e) Crushing pattern 20mm(tonne) tonne 23.00% 258.75


f) % Cost distribution={(d)x(f)/e)x1.5} cum 31.95% 0.3195 #REF! #REF! #REF!
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

i)Total Cost for1cum =(f+g+h)Including OH& CP #REF! #REF! #REF!


Rate per cum= (f+g+h) Including OH & CP Say #REF! #REF! #REF!
Crushing of stone aggregates (Nominal size)
(iii)
3.Crushing Pattern 10 mm (tonne)- Cost
Distribution 30.75 %
d) Total Cost for 750 cum(Excluding OH & CP) #REF! #REF! #REF!

e) Crushing pattern 20mm(tonne) tonne 25.86% 290.925


f) % Cost distribution={(d)x(f)/e)x1.5} cum 30.75% 0.3075 #REF! #REF! #REF!
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
i) Total Cost for1cum = (f+g+h)Including OH & CP #REF! #REF! #REF!

Rate per cum= (f+g+h) Including OH & CP #REF! #REF! #REF!


Crushing of stone aggregates (Nominal size)
(iv)
4 Crushing Pattern dust (tonne)- Cost
Distribution 08.32 %
d) Total Cost for 750 cum(Excluding OH & CP) #REF! #REF! #REF!

e) Crushing pattern dust (tonne) tonne 28.43% 319.838


f) % Cost distribution={(d)x(f)/e)x1.5} cum 8.32% 0.0832 #REF! #REF! #REF!
g) Overheads on (f) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
h) Contractor's profit on (f+g) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!

i) Total Cost for1cum = (f+g+h)Including OH & CP #REF! #REF! #REF!

Rate per cum= (f+g+h) Including OH & CP #REF! #REF! #REF!


Note: The average density of 1.5 tonne/cum is only a reference density in this Data Book.
1.07 Crushing of stone aggregates (GSB Crusher Run)

Crushing of stone boulders of 150 mm size in an


integrated stone crushing unit of 250 tonnes per hour
capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain crusher run (all in aggregate) for GSB.

Unit = cum
Taking Output = 750.00 cum
a) Labour
Mate day 0.320 0.320 0.320 310.000 99.200 99.200 99.200 L-12
Mazdoor (Skilled) day 2.000 2.000 2.000 370.000 740.000 740.000 740.000 L-15
Mazdoor day 6.000 6.000 6.000 292.000 1752.000 1752.000 1752.000 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750 750 750 4.00 3000.000 3000.000 3000.000 1.00
c) Machinery
Integrated stone crusher of 250 TPH including belt Hour 4.615 4.615 4.615 #REF! #REF! #REF! #REF! #REF!
conveyor and vibrating screens (for producing
crusher run production capacity will increas by 30%)

Generator 725 KVA Hour 4.615 4.615 4.615 #REF! #REF! #REF! #REF! #REF!
Front end loader 3.1 cum bucket capacity at quarry Hour 5.515 5.515 5.515 #REF! #REF! #REF! #REF! #REF!
and crusher
Tipper 14 cum capacity for loading at quarry site Hour 5.515 5.515 5.515 #REF! #REF! #REF! #REF! #REF!
Tipper 14 cum capacity for transportation within 1 t.km 1,125.00 1,125.00 1,125.00 #REF! #REF! #REF! #REF! #REF!
km
Total Cost Excluding OH & CP #REF! #REF! #REF!
d) Overheadson (a+b+c) (@ 8%) (@ 10%) (@ 12%) #REF! #REF! #REF!
e) Contractor's profit on (a+b+c+d) (@ 10%) (@ 10%) (@ 10%) #REF! #REF! #REF!
Cost for 900 cum =(a+b+c+d+e) #REF! #REF! #REF!
Rate per cum =(a+b+c+d+e)/900( Including OH Say #REF! #REF! #REF!
& CP)
Note: Considering Crushed volume will be 1.2 times the volume of boulder.
Note:-1. For local transportation , carriage rate will be given as per provision of different Capacity of vehicle in Large/Medium/Small Projects in rate
analysis of particular item of any Chapter.
Note:-2.
Except Note 1, transportation of Stone Aggregate/Stone Boulder/Moorum/Bitumen/Steel/Cement and Other Construction Materials,Loading-
Unloading charges&Haulage charges will be allowed by 18 Cum Capacity tipper(18 tonne Capacity Truck in case of loading-unloading of
Cement /Steel Bitumen by manual means) and32 tonne Capacity tipper respectively only for all types of Projects(Large/Medium/Small) except in
cases / circumstances where any limitation/restriction regarding capacity of Vehicle has been imposed by competent
Authority(Local/District/State). Incase of restriction, rate of restricted capacity of vehicle will be allowed.
Note:-3. In case of Loading &Unloading of Boulders by Manual means, loading-unloading charges will be allowed by 10Cum Capacity tipper.

The above proposed details&Calculations may be placed before State Level SOR Committee for discussion.

A.E. E.E. S.E.


CARRIAGE OF MATERIAL (By TRACTOR) Date 25.02.2021

Sr.
No. Ref.
to
MoR Rate Amount Remarks/
Description Unit Quantity as per Project Category
TH (Rs`) (Rs) Input ref.
Spec
.

1.1 Loading and Unloading of Stone Boulder/ Stone cum


aggregates/Sand /Kanker/Moorum Large Medium Small Large Medium Small
Placing Tractor at loading point, loading with front
end loader, dumping, turning for return trip,
excluding time for haulage and return trip
Unit = cum
Taking output = 2.25 cum
Time required for
i) Positioning of Tractor at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 5 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and 0 Min
turning for return
iv) Waiting time, unforeseen contingencies etc 0 Min

Total 6 Min
a) Labour
Mate day 0.050 0.050 0.050 310.00 15.500 15.500 15.500 L-12
Mazdoor for loading and unloading day 0.310 0.310 0.310 292.00 90.520 90.520 90.520 L-13
b) Machinery
Tractor 3.60 tonnes capacity hour 0.100 0.100 0.100 612.00 61.200 61.200 61.200 #REF!
Front end-loader 1 cum bucket capacity hour 0.083 0.083 0.083 1594.00 132.302 132.302 132.302 #REF!
Total Cost Excluding OH & CP 299.52 299.52 299.52
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 23.962 29.952 35.943
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 32.348 32.947 33.546

Total Cost for2.25 cum = (a+b+c+d)Including OH & 355.832 362.422 369.011


CP
Rate per cum= (a+b+c+d)/2.25 Including OH & 158.148 161.076 164.005
CP
Note Unloading will be done manually. say 158.100 161.100 164.000

1.2 Loading and Unloading of Boulders by Manual


Means
Unit = cum
Taking output = 2.25 cum
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.300 9.300 9.300 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.240 210.240 210.240 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.310 0.310 0.310 612.00 189.720 189.720 189.720 #REF!
Total Cost Excluding OH & CP 409.260 409.260 409.260 #REF!
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 32.741 40.926 49.111
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 44.200 45.019 45.837

Total Cost for2.25 cum = (a+b+c+d)Including OH & 486.201 495.205 504.208


CP
Rate per cum= (a+b+c+d)/2.25 Including OH & 216.089 220.091 224.093
CP
Say 216.100 220.100 224.100
Note Unloading will be done manually.

1.3 Loading and Unloading of Cement or Steel by


Manual Means and Stacking.
Unit = tonne
Taking output = 3.60 tonnes
a) Labour
Mate day 0.030 0.030 0.030 310.00 9.300 9.300 9.300 L-12
Mazdoor for loading and unloading day 0.720 0.720 0.720 292.00 210.240 210.240 210.240 L-13
b) Machinery
Tractor 3.60 tonne capacity hour 0.720 0.720 0.720 612.00 440.640 440.640 440.640 #REF!
Total Cost Excluding OH & CP 660.180 660.180 660.180
c) Overheads on (a+b) (@ 8%) (@ 10%) (@ 12%) 52.814 66.018 79.222
d) Contractor's profit on (a+b+c) (@ 10%) (@ 10%) (@ 10%) 71.299 72.620 73.940

Total Cost for3.6 tonnes= (a+b+c+d)Including OH & 784.294 798.818 813.342


CP
Rate per tonne= (a+b+c+d)/3.6 Including OH & 217.859 221.894 225.928
CP
say 217.900 221.900 225.900
1.4 (i) Cost of Haulage Excluding Loading and
Unloading
Haulage of materials by Tractor excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking output 3.60 tonnes load and lead 10 km =
36.0 t.km
Surfaced Road
Speed with load : 15 km / hour.
Speed while Returning empty :25 km / hour.
a) Machinery.
Tractor 3.6 tonne capacity
Time taken for onward haulage with load hour 0.667 0.667 0.667 612.00 408.204 408.204 408.204 #REF!
Time taken for empty return trip. hour 0.400 0.400 0.400 612.00 244.800 244.800 244.800 #REF!
Total Cost Excluding OH & CP 653.004 653.004 653.004
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 52.240 65.300 78.360
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 70.524 71.830 73.136

Total Cost for36 t.km = (a+b+c)Including OH & CP 775.769 790.135 804.501

Rate per t.km= (a+b+c)/36 Including OH & CP 21.549 21.948 22.347

say 21.500 21.900 22.300


(ii) Unsurfaced Graveled Road
Speed with load: 12 km / hour
Speed for empty return trip :20 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage with load hour 0.833 0.833 0.833 612.00 509.796 509.796 509.796 #REF!
Time taken for empty return trip hour 0.500 0.500 0.500 612.00 306.000 306.000 306.000 #REF!
Total Cost Excluding OH & CP 815.80 815.80 815.80
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 65.264 81.580 97.896
c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 88.106 89.738 91.369

Total Cost for36 t.km = (a+b+c)Including OH & CP 969.166 987.113 1,005.061

Rate per t.km= (a+b+c)/36 Including OH & CP 26.921 27.420 27.918

26.90 27.40 27.90


1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed
and Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tractor 3.6 tonnes capacity
Time taken for onward haulage hour 1.000 1.000 1.000 612.00 612.000 612.000 612.000 #REF!
Time taken for empty return trip hour 0.667 0.667 0.667 612.00 408.204 408.204 408.204 #REF!
Total Cost Excluding OH & CP 1020.20 1020.20 1020.20
b) Overheads on (a) (@ 8%) (@ 10%) (@ 12%) 81.616 102.020 122.424

c) Contractor's profit on (a+b) (@ 10%) (@ 10%) (@ 10%) 110.182 112.222 114.263

Total Cost for36 t.km = (a+b+c)Including OH & CP 1,212.002 1,234.447 1,256.891

Rate per t.km= (a+b+c)/36 Including OH & CP 33.667 34.290 34.914

say 33.700 34.300 34.900


oSls LFky tgk¡ ij Truck ,oa Tipper ds }kjk <qykbZ fd;k tkuk laHko ugha gS rFkk Tractor ls <qykbZ economical gks dsoy oSls gh LFkyksa ds fy,
Note:- Tractor ls <qykbZ dk izko/kku fd;k tk;A
lgk;d vfHk;ark dk;Zikyd vfHk;ark v/kh{k.k vfHk;ark

You might also like