Professional Documents
Culture Documents
Wind-Induced Clearances Infringement of Overhead Power Lines
Wind-Induced Clearances Infringement of Overhead Power Lines
4, August 2014
insulator to the bottom of an imaginary ball, fitted into the conventionally at the attachment point to the tower in the
socket of the first insulator. In the case of a composite unit, the direction of the wind, and its intensity is given by:
length is measured from the bottom of the ball to the bottom
of an imaginary ball, fitted into the socket end fitting. Ac ai Gi m2 (2)
TABLE II: OVERHEAD LINE 400 KV INSULATOR STRING [6]
Minimum creepage Insulator string
length(mm) length(mm) ±2%
Tension 9000 4200
Suspension 12500 4100
276
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
swing angle velocity occurring at a specified height above the site ground
level, z, is obtained from the formulae defined in equations 5
Ф
Ф
Ф and 6, for open terrain with few obstacles.
lta
nt
lo
ad
Weight of = Fi =
z he
su conductors
Re & insulators
VZ VT for z 10 he m.s-1 (5)
Wind load of
conductor & Wi
10
insulators
Fc Fc + Fi/2
V z
VZ 1 for z 10 he m.s (6)
-1
Wc Wc + Wi/2 2 10 he
Fig. 4. Determination of swing angle on the basis of relative horizontal (wind)
and vertical (system weight) forces.
Using the value Vz , the dynamic wind pressure, q z , can be
When designing the tower top geometry, the distance calculated as shown in equation 7 below. The air density, ,
between the live conductors and the nearest earthed structure depends on the temperature and the altitude of the line above
should exceed the safety clearance value in still air and light sea level [7], [8]. In general, ρ may be taken as 1.22 kg.m3 ,
wind. In many Europe countries, a swing angle up to 10° based on a temperature measurement of +20 °C and a height
should not lead to any infringement of any stated clearance. In of 0 m above sea level.
very high winds that cause a large swing angle (35°based on
the data in [4]), the infringement will happen, and the
2
clearances will only withstand the power frequency voltage qz Vz (7)
which is required in this case. probability to have lightning 2
and high wind speed at the same time very rare.
The methods for calculating the reposition of conductors
E. Conventional L12 Tower
and insulators towards an overhead line tower due to the wind
speed created by the CIGRE Working Group [4]. Also some The L12 tower is a new model for delivering energy at 400
changes made to adapt the condition of high wind speed. The kV. A twin bundle of 700 mm²AAAC is preferred for use.
swing angle of an overhead line conductor and insulator is The tower is designed to ensure sufficient electrical
determined by the formula given in equation 3. clearances. The ratio of creepage distance to insulator length
used in this case is 3.05 [8]. This ratio is obtained by dividing
the required 12.5 m creepage distance by the insulator length
Ai
qz Ac 2 4.1m, as shown in Fig. 5, which illustrates the main
tan 1 (3) dimensions of a typical L12 tower. The study is based on
W Wi towers carrying twin conductor bundles (separated at 0.5 m by
c
2 horizontal spacers) of AAAC Araucaria conductors, of
0.03726 m diameter and total weight of 18.5 kN, based on
manufacturer’s data of 0.023 kN/m for 400 m span. This span
In equation 3, q z is the dynamic wind pressure, Ac is the
value is for a L12 tower [9], [10] and is the metric equivalent
wind loading area of the conductor, Ai is the wind loading area of 1,312 ft. The insulator is taken to be equipped with fittings
of the insulators, Wc is the total weight of the conductors, and with a total length of 0.5 m, giving a total string length of 4.6
Wi is the total weight of the insulators. The equation m. The insulator used in this case study is taken to have a wind
effectively derives the swing angle on the basis of relative loading area 0.8 m², and a drag factor 0.12, according to the
horizontal (wind) and vertical (system weight) forces. To data in [7], [11]-[13].
determine the dynamic wind pressure, qz, that is used in The L12 tower is a new model for delivering energy at 400
equation 3, it is important to understand the wind speed kV. A twin bundle of 700 mm²AAAC is preferred for use.
distributions used to calculate this value. The tower is designed to ensure sufficient electrical
Reference wind speeds, VR, are presented in standards [6]. clearances. The ratio of creepage distance to insulator length
VR can be used to calculate the maximum average 10-minute used in this case is 3.05 [8]. This ratio is obtained by dividing
wind speed, VT, which will occur in a given return period. For the required 12.5 m creepage distance by the insulator length
a return period that is equal to or greater than two years, the 4.1m, as shown in Fig. 5, which illustrates the main
modified version of Gumbel’s formula [6] can be used. This is dimensions of a typical L12 tower. The study is based on
shown below as equation 4. towers carrying twin conductor bundles (separated at 0.5 m by
horizontal spacers) of AAAC Araucaria conductors, of
0.03726 m diameter and total weight of 18.5 kN, based on
1 6 (4)
VT 2 year VR VR 0.45 ln( ln(1 )) manufacturer’s data of 0.023 kN/m for 400 m span. This span
T value is for a L12 tower [9], [10] and is the metric equivalent
of 1,312 ft. The insulator is taken to be equipped with fittings
Accounting for the roughness of terrain and the height of with a total length of 0.5 m, giving a total string length of 4.6
the considered conductor. Vz , the average value of wind m. The insulator used in this case study is taken to have a wind
277
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
Level 1
loading area 0.8 m², and a drag factor 0.12, according to the
data in [7], [11]-[13].
c
4.1m
5.33m
(ɣ)
4.6m
4.6m
5.16m
9.3m
4.1m
4.3m
m n Angle (α)
m
k
9.67
8.12m
5.16m b
9.3m
L
7.78m 8.7m
4.68
46.5m
h g f
m
y
5.87m
8.81m
1.994m
aa sin( )
Tower details
11.74m
Voltage system 400kV.
2ˣ700 sq.mm AAAC Araucaria
GROUND LEVEL
cos( )
7.060m
On the basis of the insulator and the height of the lower kw2’ presents the vertical distance between the conductor
cross-arm, the 7.6 m minimum clearance to ground [12], [14], and bottom cross-arm based on swing angle and conductor
[15] will be infringed only when the sag exceeds 12 m. This movement.
value of sag is therefore used as reference. The normal sag for
400 m span is 5.4 m. In this case the distance between the kw2 sin( ) 2 ab sin( / 2)
conductor and ground is 14.5 m, which is greater than 7.6m; (10)
the minimum clearance to the ground. (c2 a2 (cc gf ))
ba2
c2 c2
F. Derivation of Equations to Calculate Distance
Infringement (cc gf ) ( cos( ) 2 ab sin( / 2) )
c2 a2
When the insulator moves owing to the wind action, the c2 c2
distance between the conductor and tower body infringes
either to increase or decrease. The distance infringement will As a matter of fact, equations (8) and (9), mentioned above,
vary from one cross-arm to another, depending on the can be used for all top, middle and bottom cross-arms.
cross-arm length and its height from ground level. To Equation 10 can be used for the top and middle cross-arms,
calculate the distance infringement, some analysis should be and it has to be modified for use in the bottom cross-arm,
taken into consideration on the tower, as shown in Fig. 6. because there is no impediment under the bottom cross-arm
Then, some equations have to find the horizontal and vertical and it is subjected directly to the ground.
distances between the conductors and any part of the tower
body. k3 g3 b3 g3 sin( ) 2 a3b3 sin( 2) (11)
It is necessary to name all the tower parts and the possible
positions to drive accurate equations. For example: CC’ is the k3g3 is the vertical distance between the conductor in lower
cross-arm length, AB the insulator length and NK is the cross-arm and the ground level based on swing angle and the
possible distance between the conductor and tower body etc. conductor movement.
Then, the equations can be found based on these tower parts
G. Calculation of Clearances for Fast Front, Slow Front,
(Fig. 6), names as shown in the equations (8 to 10) below.
and PF over Voltages
ab ce sin( ) (2 ab sin( / 2)) In ‘still air’ the clearances have to be wide enough to
kn cc tan( ) ce
(8)
withstand lightning and switching impulses. The lightning
impulse used is that which can propagate beyond a few towers
ca / 2 from the point of the lightning strike. For the purpose of
cos( ) (2 ab sin( / 2)) condbundle / 2 determining clearances this is taken as U50FF, the mean
278
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
lightning impulse voltage which results in 50% flashover and horizontal clearances side (first case), as the infringement of
50% withstands of gap formed between the live parts and the the safety and transient clearances can occur for a 27ºswing
tower. The switching impulse used is the highest that can angle. In contrast, a large swing angle (≥40º) is needed for
occur on the lines called UmaxSF. There are ways of limiting vertical clearance between the conductor and the cross-arm
the switching surges, such as line entry surge arresters or above to infringe these clearances. This value is above the
pre-insertion resistors, in which case the appropriate UmaxSF maximum limit of 35ºdefined in [4], so the chance of the
is the maximum value which can occur on the transmission conductor position infringing the safety clearance is zero. In
lines. The corresponding distance for lightning LFF and LSF, addition, the third case chance of infringing the safety and
are calculated using the formulae below, which are based on electrical clearance is also zero.
IEC60071.
6
LFF
clearance at 27º switching at 33.5º
(12) 5
530 (0.74 0.26 K g ) K A
4
U 50sfo
e
1 3
LSF (13) 2.6m switching distance
LPF (14)
0.55 0
0 5 10 15 20 25 30 35 40
Swing angle (degree)
conductor to tower body ( horizontal) conductor to cross arm above (vertical) conductor to cross arm below (vertical)
3.1m safety distance 2.6m Switching distance 2.51m lightning distance
0.9m TOV distance
III. RESULTS AND ANALYSIS RESULTS Fig. 7. Relationship of the swing angle with the distance from tower to the
Since 1970, 270 kV overhead transmission lines have been top cross-arm conductor for 400kV L12 tower.
used in Libya to supply electricity to Benghazi City (northern
Fig. 8 shows the relation of the swing angle and the distance
part of the country). Nowadays, owing to the increase in
between the top cross-arm conductor and the tower body
population, a 400 kV system will be used instead of 275 kV in
(horizontal), cross- arm above (vertical) and cross-arm below
the near future. In the case of 400 kV, twin bundles of 500
(vertical) for the base design. In the first and second cases, the
mm2 or 700 mm2 AAAC type conductor are preferred, and
swing angle increases as the clearances decreases. In the third
4.6 m insulator length [15]. According to GECOL design
case, the swing angle increases as the clearance increases as
standard, VR = 35 m.s-1 [2].
well.
Apply in equations 1 to 7 to calculate the swing angle at this
amount of wind speed 35 m.s-1and the result as shows in table
9
3.
8
TABLE III: OVERHEAD LINE 400 KV INSULATOR STRING [6] 7 infringe 3.1m safety
max
clearance at 40º
VT VZ qz AC 6
Air gap (m)
5
34.78 38.86 921 11.9 31 4
3.1m safety distance
m.s-1 m.s-1 m2 deg
3 2.6m switching distance
2.51m lightning distance
2
The clearances have to be wide enough to withstand 0.9m TOV
1
lightning and switching impulses. These clearances are
0
calculated according to equations 3.15, 3.16 and 3.17, based
0 5 10 15 20 25 30 35 40
on IEC 60071-1 (1993), and find the conductor distance to Swing angle (degree)
tower body to withstand lightning U50, switching U50 and
TOV. After applying the equations, the clearance is found as
conductor to tower body ( horizontal) conductor to cross arm above (vertical) conductor to cross arm below (vertical)
follows: LFF=2.51 m, LSF = 2.6 m and LPF = 0.9 m. Fig. 8. Relationship of swing angle with the distance from tower to the
Fig. 7 shows the relation of the swing angle and the distance middle cross-arm conductor for 400kV L12 tower.
between the top cross-arm conductor and the tower body
(horizontal), as well as the cross-arm above (vertical) and the The impact is most significant on the vertical clearances
cross-arm below (vertical) for the base design. In the first and side (second case), as the infringement of the safety and
second cases, the swing angle increases as the clearances transient clearances can occur for a 40ºswing angle. In first
decrease. In the third case the swing angle increases as the (horizontal) and third (vertical to lower cross-arm) cases, the
clearance also increases. The impact is most significant on the likelihood of the conductor position infringing the safety and
279
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
electrical clearances is zero, because the middle cross-arm is average wind the conductor height does not change much,
long, as shown in Fig. 5 (middle cross-arm 8.12m length). from VZ = 0 to VZ=20 msˉ¹ The change in conductor height is
Fig. 9 shows the relation of the swing angle and the distance less than 0.07 m, but if the conductor is stroked by high or
between the top cross-arm conductor and the tower body extremely high wind speeds the change in conductor height
(horizontal), and the cross-arm above (vertical) and cross-arm will be remarkable, from VZ = 20 to VZ=45 msˉ¹ the change in
below (vertical) for the base design. In the first and second conductor height exceed to reach 1 m.
cases, the swing angle increases as the clearances decreases.
The third case here is different because there is no cross-arm 20.8
below the Lower cross-arm (as shown in Fig. 3 and 4), and the 20.6
Lower cross-arm is subjected to the ground, and the distance
20.4
to the ground is almost 20m.
20
20
19.8
15 19.6
Air gap (m)
5
Fig. 11. Relationship between the conductor height from the ground and
wind speed of 400kV L12 tower.
2000
tower body. The displacement of live conductors and
1500
insulators towards the tower body will shorten the clearances,
as shown in Fig. 10; the relationship between wind speed and 1000
infringe 1050kV
conductor distance to tower body. switching at 33.5º
500
0
0 5 10 15 20 25 30 35 40
Swing angle (degree)
Fig. 12. Relationship of the swing angle with U50 overvoltage levels of the
base case 400kV L12 tower.
280
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
REFERENCES
[1] IEC, “Insulation coordination part- 4: Computational guide to
TABLE VI: PROBABILITY OF INFRINGEMENT OF VERTICAL CLEARANCES insulation co-ordination and modelling of electrical networks,” 2004.
BETWEEN CONDUCTOR AND CROSS-ARM BELOW OWING TO CONDUCTOR
[2] IEC, “Insulation coordination part -1: Definition, principle and rules,”
SWING FOR BASE CASE TOWER FOR TOP CROSS-ARM 7th edition, 1997.
[3] IEEE Guide for the Application of Insulation Coordination, IEEE
Standard 1213.2, 1999.
[4] CIGRE, “Tower top geometry,” CIGRE Working Group 22.06, June
1995.
[5] BSI, “Overhead electrical lines exceeding AC 45kV - Part 3: Set of
National Normative Aspects,” BS EN 50341-3-2001, October 2001.
[6] BSI, “Loading and strength of overhead transmission lines,” BS EN
7733:1994, April 1994.
[7] BSI, “Conductors for overhead lines - round wire concentric lay
stranded conductors,” BS EN 50182, August 2001.
[8] A. R. Hileman, Insulation Coordination for Power Systems. Boca
Raton, USA: Taylor and Francis Group, LLC, CRC Press, 1999.
[9] P. Nefzger, F. Kiessling, J. F. Nolasco, and U. Kaintzyk, Overhead
Power Lines - Planning, Design, Construction, Germany: Springer,
2003.
[10] BSI, “Live working - minimum approach distances for A.C systems in
the voltage range 72.5kV to 800kV - a method of calculation,” BS EN
61472, 2004.
281
International Journal of Computer and Electrical Engineering, Vol. 6, No. 4, August 2014
[11] CIGRE Working Group, “Guidelines for evaluation of the switching logging engineer from 2006 to 2009. He joined UTHM university as master
impulse strength of external insulation,” CIGRE Technical Brochure student and obtained his M.Sc. degree in electrical engineering in 2011 His
72, 1992. research interests are high voltage, transmission line, power towers, induced
[12] R. S. Guror, E. A. Cherney, and J. T. Burnham, Outdoor Insulator, voltages and lightning.
Phoenix, Arizona USA: Ravi S. Guror Inc., May 1999.
[13] J. S. T. Looms, Insulator for High Voltages: Peter Peregrinus Ltd.
London, United Kingdom, 1988.
[14] Central Electricity Generating Board (CEGB), Overhead Line Zulkurnain Abdul-Malek is an associate professor
Handbook, April 1989. and director at UTM Institute of High Voltage & High
[15] GECOL, Design Standards for Libya, 2003. Current (IVAT) Universiti Teknologi Malaysia
[16] F. Kiessling, P. Nefzger, J. F. Nolasco, and U. Kaintzyk, “Overhead obtained his M.Sc. degree in electrical and
power lines planning, Design, Construction,” Springer. electromagnetic engineering with industrial
[17] Conductor Bundles for Overhead Lines, issue 1, October 2004, applications in University of Wales Cardiff, Unitd
National Grid Transco. Kingdom, 1995. He received his Ph.D. degree in high
[18] S. R. Krishnamurthy and P. Selvan, “Use of AAAC in a distribution voltage engineering from Cardiff University, United
network-a strategy for energy and cost reduction,” 1995. Kingdom, 1999. He is the director in UTM Institute of
[19] S. N. Mohtar, M. N. Jamal, and M. Sulaiman, “Analysis of all High Voltage & High Current (IVAT)/UTM High voltage. He is a member of
aluminum conductor (AAC) and all aluminum alloy conductor Author’sofformal
Institute Electrical and Electronics Engineer (MIEEE) and collective
(AAAC),” in Proc. IEEE Region 10 Conference on TENCON, 2004, member photo
of The International Conference on Large High Voltage Electric
pp. 409-412. Systems (CIGRE). He has been the chairman of Working Group on High
[20] Overhead Line Handbook. Voltage Test Techniques, Malaysia since 2009. He is member in Technical
[21] National Grid, “Internal and contract specific technical specification, Committee on High Voltage Transmission, Malaysia, from 2009 till now, a
insulator sets for overhead lines TS 3.4.17,” issue 2, September 2006. member in Working Group on High Voltage Switchgear, Controlgear and
[22] Insulation Co-ordination. Computational Guide to Insulation Assemblies, Malaysia, form 2002 till now.
Co-ordination and Modelling of Electrical, IEC60071-1, Part 1.
[23] Insulation Co-ordination. Computational Guide to Insulation
Co-ordination and Modelling of Electrical, IEC60071-4, Part 4. Ibtihal Fawzi El-Shami received the BSc. degree in
electrical and electronics engineering from Benghazi
University in 2006 and master degree in electrical
Ali I. El Gayar is a lecturer and the head of Control engineering (EMC) from Universiti Tun Hussein Onn
Department at College of Electrical and Electronics Malaysia (UTHM) in 2011. She is now a PhD student
Technology-Benghazi-Libya. He is a Ph.D. student at at the Faculty of Electrical Engineering, University
UTM University. He obtained his bachelor's degree of Technology Malaysia as doctoral student. She is also a
electrical engineering from Benghazi University at lecturer at College of Electrical and Electronics
Libya in 2005. He had worked as a field engineer at Technology-Benghazi-Libya.
Schlumberger Company from 2005 to 2006, and then
he moved to Halliburton Oil Company to work as Author’s formal
photo
Author’s formal
photo
282