You are on page 1of 1

Client: (PMC): Contractor:

DOCUMENTS SUBMITTAL FORM

Trade : Arch Civil Mech Elect Landscape Others

Submittal type: Project # C15-03

Submittal Ref DWG-5


Rev 0
Shop AS Built Method Time Takeoff Others
Drawing Drawing Statement Schedule Sheets Date 20-06-2015

Response / Action By
Item Document Contract PMC
Document Title Revision
No. Ref Document Ref. Action
Reviewed By
Code
PROPOSED AREA FOR STEEL
1 SD-ST-01 0      
BUILDING YARD
     
     

   
Authorized representative of the
This is to certify that all items submitted herewith have been contractor title and signature :
checked by the contractor are in conformance with the Eng.Khaled El-Hadeedy (P.M)
requirements of the contract documents and are approved by the
contractor for the works, except as noted below:
SAUDI CYPRIAN CONSTRUCTION CO. LTD.

To Contractor Review Comments / or Refer to attached Comments Sheet:

Action Codes Legend : Notes :


1. Approved No Exceptions Taken Installation shall proceed only when action code is 1 / or 2.
2. Approved As Noted (Make Regarding action code 3, resubmitted shall be within the time limit set in the contract.
Corrections Noted) Review does not relieve the contract from his responsibility of compliance with all
3. Revise and Resubmit requirements of contract documents or authorize additional compensation.
4. Rejected - see Comments

Discipline Signature & Date Project Manager


Arch Name
Civil Signature
Mech
Elect Date