WORK PROCEDURE FOR DE WATERING


(Including Cover)

● PROJECT CODE : B50532EA Purpose


● PROJECT NAME : MASINLOC POWER PLANT EXPANSION
□ For Information
PROJECT
□ For Review
● DOCUMENT NO. :
● TITLE : Work Procedure for De watering ■ For Approval
● OWNER : MASINLOC POWER PARTNERS CO.,LTD. □ For Construction

□ As Built

Marie
October G.B Kim M.S Lee J.W Doo J.H.Lee H.S.Woo
A For Approval Bernadas
10,2016

Rev. PREPARED REVIEWED APPROVED CHECKED REVIEWED APPROVED


DESCRIPTION DATE
No. GTC Global Inc. VPCI
Owner

`Contractor
Masinloc Power Plant Expansion Project Doc. No
Work Procedure for De Rev. No. A
Watering Page 2 of 5

TABLE OF CONTENTS

1.0 PURPOSE………………………………………………………………….. 3

2.0 SCOPE……………………………………………………………………… 3

3.0 ROLES AND RESPONSIBILITIES……………………………………… 3

4.0 RESOURCES ……………………………………………………………… 4

5.0 PROCEDURE ……………………………………………………………… 4

6.0 ATTACHMENT………………………………………………………………5
Masinloc Power Plant Expansion Project Doc. No
Work Procedure for De Rev. No. A
Watering Page 3 of 5

1.0 Purpose
The main objective of this procedure is to provide a safe and efficient system in de watering
works.

2.0 Scope
It cover all layout ,marking, levelling for the Masinloc Power Plant Expansion Project.

3.0 Roles and Responsibilities


3.1 VPCI

 VPCI Project Manager shall be the overall responsible for the implementation of this
procedure ensuring that works are completed on schedule and in conformity with
drawings and specifications.

3.2 VPCI

 VPCI Project EHS Manager shall ensure safe implementation of this procedure promoting an
Incident and Injury Free environment.

3.3 VPCI

 VPCI & GTC Global Inc. QA/QC Engineer shall be responsible for the
implementation of construction specification and standards and see to it that this
written method statement of the work shall be carried out.

3.4 GTC

 GTC Global Inc. Construction Manager – shall have the overall responsibility for the
works.

3.5 GTC

 GTC Global Inc. HSE Engineer along with the Safety Officer shall ensure
implementation of all safety procedures, safety measures related to the nature of works
being carried out and in accordance with the HSE Plan..

3.6 GTC

 GTC Global Site Supervisor shall be directly involved in the planning and execution
of the activities. He shall be responsible for the preparation of work plan, safety action
plan and safety.

3.7 GTC
Masinloc Power Plant Expansion Project Doc. No
Work Procedure for De Rev. No. A
Watering Page 4 of 5

 GTC Global First Aider – gives immediate medical attention .

4.0 Resources

4.1 Manpower & Equipment Plan


Manpower’s

Construction Manager 1
Site Engineer 1
Safety Officer 1
Safety Supervisor 1
Leadman 1
Operator 4
mechanic 1
Fire watcher 1

4.2 Equipment’s & Tools

Water pump 4” w/ accessories 2

Water pump 2” w/ accessories 2


Portable light tower 3
Portable generator 1

5.0 Procedure
5.1 Secure all necessary permit for the work to be done in coordination with AES and VPCI.
5.2 Site must be assessed and potential hazard must be determined.
5.3 Conduct a pre job briefing.
5.4 Set boundaries of works, installed hard barricade. Warning signage’s must in place.
5.5 Mechanic should check the unit prior to start the work ( oil, gas, engine).
5.6 Drip tray must be used for spillage.
5.7 Prepare the hose for discharge and intake for the pump.
5.8 Fire watcher must be present at all time when the unit is operational.

B. For Night Work


5.1 Set up the portable light tower, make sure that the drip tray
is available for every portable generator that are going to be used.
5.2 Light tower shall be place in a strategic point for proper illuminating.
5.3 Operator shall check all generator prior to start the work.
5.4 Fire watcher must be present at all time when the unit is operational.
Masinloc Power Plant Expansion Project Doc. No
Work Procedure for De Rev. No. A
Watering Page 5 of 5