Professional Documents
Culture Documents
Guidelines On Wind Power Plants B5 Final 5
Guidelines On Wind Power Plants B5 Final 5
Содржина
1. Вовед................................................................................................................................ 3
2. Преглед на применливите повластени тарифи за ветерни електрани......................... 4
3. Детален дијаграм за постапката и документите за изградба........................................ 5
4. Преглед на чекорите, постапките и документите......................................................... 6
4.1. Основни предуслови: Основање на компанија...................................................... 6
4.2. Мерење на потенцијалот на ветрот........................................................................ 6
4.3. Користење на земјиште...........................................................................................7
4.4. Согласност за приклучок на преносниот или дистрибутивниот систем.............. 8
4.5. Студија за оценка на влијанието врз животната средина..................................... 9
4.6. Овластување за изградба на нови објекти за производство
на електрична енергија (во случај на ветерни електрани
со инсталирана моќност над 10 МW).....................................................................10
4.7. Одобрение за градба.............................................................................................. 11
4.8. Стекнување на привремен статус на повластен производител...........................12
4.9. Проектирање и изведба на приклучокот..............................................................13
4.10. Одобрение за употреба..........................................................................................14
4.11. Лиценца за производство на електрична енергија..............................................14
4.12. Упис на објектот во Регистарот на објекти за производство
на електрична енергија од обновливи извори на енергија.................................. 17
4.13. Доделување на статус на повластен производител.............................................. 17
4.14. Договор за откуп на електрична енергија со оператор
на пазарот на електрична енергија.......................................................................19
5. Обезбедување на гаранции за потекло на електрична енергија
произведена од обновливи извори на енергија........................................................... 20
6. Адреси и податоци за контакт на надлежните институции.........................................21
7. Релевантно законодавство и регулаторни акти........................................................... 22
Оваа публикација е изготвена со помош на Европската Унија. Содржината на оваа публикација е единственa
одговорност на ATC Consultants и нејзините партнери во конзорциумот и на никаков начин не ги рефлектира
гледиштата на Европската Унија.
ВЕТЕРНИ ЕЛЕКТРАНИ 3
1. Вовед
ЕЛЕМ му беше доделена лиценца за изградба на ветерни електрани со вкупна инсталирана моќност
од 50 MW. ЕЛЕМ искористи 36,8 MW од својата лиценца со пуштање во употреба на ветерниците во
Богданци во 2013 год. ЕЛЕМ планира да ги искористи преостанатите 13,2 MW за ветерни електрани во
периодот по 2016 год.
3. Детален дијаграм за постапката и документите за изградба
Времетраење Времетраење
Години Година 1 Година 2 Година 3 Година 4 Година 5
Месеци 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Постапка Надлежен орган
4.1 Основање на компанија 6.1
Мерење на потенцијалот на
4.2 ветрната енергија 6.3 Мерење на потенцијалот на ветерната енергија (најмалку 2 години ) 1
6.1, 6.8, 6.9 или
4.3 Пренамена на земјиштето 2
општината
Согласност за приклучок на
4.4 преносниот или 6.5 или 6.6
дистрибутивната мрежа
Студија за влијанието врз
4.5 6.7 или општината
животната средина
Овластување за изградба на
4.6 6.1 3
(ветерна) електроцентрала
4.7 Одобрение за градба 6.8 или општината 4
ПРОЦЕС НА ГРАДБА
Стекнување на привремен статус
4.8 6.4
на повластен производител
Проектирање и изведба на 6.5, 6.6 или овластена
4.9 приклучокот 5
компанија
Лиценца за производство на
4.12 6.4
електрична енергија
Упис на објектот во Регистарот
ВЕТЕРНИ ЕЛЕКТРАНИ
на објекти за производство на
4.13 6.3
електрична енергија од
обновливи извори
Доделување на статус на
4.14. повластен производител 6.4
Легенда:
:
Ризик 1: Резултатите од мерењето може да не ја поддржат Ризик 4: Неможност да се добие одобрение за градба или
Времетраење на постапката 1 4
изводливоста на проектот за таа локација непредвидено доцнење
Времетраење на мерењето на потенцијалот на ветерот за Ризик 2: Неможност да се добие право на користење на државно Ризик 5: Зголемување на трошоците за приклучок доколку не е
производство на електрична енергија (минимум две години) 2 земјиште, доцнење и несигурност на исходот и трошоците 5 можно да се изврши поврзување на најблискиот приклучок
7. Релевантно законодавство и
подзаконски акти
Закон за енергетика (Службен весник бр. 16/2011, земјиштето во негова непосредна близина
136/2011, 79/2013, 164/2013, 41/2014 и 151/2014) (Службен весник бр. 130/2007 и 156/2012).
Уредба за повластени тарифи за електрична енер- Уредба за начинот и постапката на отуѓување,
гија (Службен весник бр. 56/2013) давање под долготраен закуп и краткотраен
Одлука за вкупната инсталирана моќност на по- закуп, на градежно земјиште сопственост
властените производители на електрична на државата, со јавно наддавање, по пат на
енергија од секој одделен обновлив извор прибирање на понуди и со непосредна спо-
на енергија (Службен весник бр. 56/2013 и годба, висината на трошоците на постапката
10/2014) за отуѓувањето и давањето под закуп, како
Закон за градење (Службен весник бр. 130/2009, и висината на цената на земјиштето и на
124/2010, 18/2011, 36/2011, 54/2011, 13/2012, закупнината (Службен весник бр. 147/2008,
144/2012, 25/2013, 79/2013, 137/2013, 163/2013, 71/2009, 16/2009, 162/2009, 113/2010, 148/2010,
27/2014, 28/2014, 42/2014, 115/2014, 149/2014, 172/2010 и 40/2011)
187/2014 и 44/2015) Закон за сопственост и други стварни пра-
Закон за градежно земјиште (Службен весник бр. ва (Службен весник бр. 18/2001, 92/2008,
82/2008, 143/2008 и 56/2010) 139/2009 и 35/2010)
Закон за земјоделско земјиште (Службен весник бр. Уредба за определување на проектите и за кри-
135/07, 18/11, 148/11, 95/12, 79/13, 87/13, 106/13, териумите врз основа на кои се утврдува
164/13, 39/14, 130/14 и 166/2014) потребата за спроведување на постапка за
Закон за шумите (Службен весник бр. 64/2009, оцена на влијанијата врз животната средина
24/2011, 53/2011, 25/2013, 79/2013, 147/2013, (Службен весник бр. 74/2005)
43/2014, 160/2014, 33/2015 и 44/2015) Правилник за формата и содржината на елаборатот
Закон за животна средина (Службен весник бр. за заштита на животната средина, постапката
53/2005, 81/2005, 24/2007, 159/2008, 83/2009, за нивно одобрување, како и начинот на во-
48/2010, 124/2010, 51/2011, 123/2012, 93/2013, дење на регистарот на одобрени елаборати
187/2013, 42/2014) (Службен весник бр. 50/2009)
Закон за просторно и урбанистичко планирање Правилник за лиценци за вршење на енергетски
(Службен весник бр. 199/2014 и 44/2015) дејности (Службен весник бр. 143/2011, 78/2013
Правилник за формата и содржината на барање- и 33/2015)
то, потребната документација и образецот Правилник за обновливи извори на енергија
на Решението за изведување на градбите (Службен весник бр. 113/2011)
односно поставување на опремата за кои не Правилник за повластени производители на елек-
е потребно одобрение за градење. (Службен трична енергија од обновливи извори на
весник, бр. 147/2009) енергија (Службен весник бр. 18/2012, 97/2012,
Правилник за условите за поставување, градба и 63/2013, 41/2014, 151/2014 и 26/2015)
обележување на објекти, инсталации и уреди Правила за пазар на електрична енергија (Службен
во зоната на аеродромот, објекти и уреди весник бр. 38/2014, 57/2014 и 194/2014)
за контрола на летањето, и објекти надвор Мрежни правила за дистрибуција на електрична
од зоната на аеродромот коишто можат да енергија (Службен весник бр. 87/2012, 30/2014,
влијаат на безбедноста на воздушниот со- 161/2014, 189/2014 и 50/2015)
обраќај и условите и начинот на обработка Мрежни правила за пренос на електрична енергија
на земјиштето во зоната на аеродромот и (2015)
GUIDELINES
On the procedures for the development and
construction of power plants utilising renewable
energy sources
WIND POWER PLANTS
24 WIND POWER PLANTS
Contents
1. Introduction................................................................................................................... 25
2. Review of the applicable feed-in tariffs (FIT) for wind power plants................................ 26
3. Step-by-step diagram of the development procedures and documents................................ 27
4. Review of the steps, procedures and documents............................................................. 28
4.1. Basic prerequisites: Establishing a company........................................................... 28
4.2. Measurement of wind power potential................................................................... 28
4.3. Use of the land........................................................................................................ 29
4.4. Approval for connection to the transmission/distribution system.......................... 29
4.5. Environmental Impact Assessment Study (EIA)........................................................ 31
4.6. Authorisation for construction of new electricty generation facility
(in case of wind power plants with installed capacity greater than 10 MW)............. 31
4.7. Construction permit................................................................................................33
4.8. Award of temporary status of preferential producer...............................................33
4.9. Design and construction of the connection............................................................ 34
4.10. Use permit...............................................................................................................35
4.11. Energy generation license........................................................................................35
4.12. Registration of the facility in the Register of electricity
generation facilities from renewable energy sources...............................................37
4.13. Award of status of preferential producer................................................................ 38
4.14. Power purchase agreement with the electricity market operator.......................... 39
5. Award of guarantees of origin for the electricity generated from
renewable energy sources............................................................................................... 40
6. Addresses and contact details of competent institutions.................................................41
7. Relevant legislative and regulatory acts.......................................................................... 42
This publication has been produced with the assistance of the European Union. The contents of this publication
are the sole responsibility of ATC Consultants and its consortium partners and can in no way be taken to reflect
the views of the European Union.
WIND POWER PLANTS 25
1. INTRODUCTION
This guidelines is envisaged to serve as an information and orientation tool for future investors in
wind power plants. Nevertheless, we recommend the investors to directly contact and consult the
competent authorities before taking any formal activities for the development and construction
of a wind plant and to take account of the most up-to-date legislative and regulatory acts.
26 WIND POWER PLANTS
The preferential tariff for electricity generated and sold by wind power plants (that have qualified
for preferential producers) have been defined by the Ordinance on Preferential Tariffs for Electricity
(Official Gazette No. 56/2013 and 10/2014) and is as follows:
The quota of eligible wind power plants that may use the preferential tariffs has been laid down
by the Decision on the total installed capacity of preferential producers of electricity generated
from each specific renewable source of energy (Official Gazette No. 100/2011) and is as follows:
At the moment of writing this guidelines and until 31 December, 2016, 13,2 MW are still avail-
able for newly developed wind power plants1. The quota shall increase by 35 MW in 2017, and by 50
MW in 2021.
1
Potential investors should note that the State-owned joint stock company ELEM has actually been award-
ed a license for construction of wind power plants with total installed capacity of 50 MW. ELEM used 36,8
MW of its license by commissioning a wind park in Bogdanci in 2013. ELEM envisages to use the remaining
13,2 MW for wind power plants in the period past 2016.
3. Step-by-step diagram of the development procedures and documents
Duration Duration
Years Year 1 Year 2 Year 3 Year 4 Year 5
Months 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Procedure Competent institution
4.1 Establishing a company 6.1
Measurement of the wind power 1
4.2 6.3 Measurement of the wind power potential (minimum 2 years)
potential
6.1, 6.8, 6.9 or
4.3 Use of the land municipality 2
Approval for connection
4.4 to the transmission/distribution 6.5 or 6.6
system
4.5
Environmental Impact 6.7 or municipality
Elaborate Study
4.6 Authorisation of construction of 6.1 3
the wind power plant
4.7 Construction permit 6.8 or municipality 4
CONSTRUCTION PROCESS
4.8
Award of temporary status of 6.4
preferential producer
Design and construction of the 6.5, 6.6 or authorised
4.9 5
connection company
Start of generation
and sale of electricity
Legend:
:
Risk 1: The measurement results may not support Risk 4: Inability to obtain a construction
Duration of the procedure 1 4
the feasibility of the project for that location permit or unforeseeable delay
Duration of the measurement of the wind power potential Risk 2: Inability to obtain right of use of State-owned Risk 5: Escalation of connection costs if the
(minimum of two years) 2 land; delays and uncertainty of outcome and costs 5 nearest connection point is impossible
Only one permit for measuring the wind In case the land parcel(s) where the investor
power potential may be issued for each site. The intends to develop the wind power plant is classified
permit is issued for an area of 0,4 m2 for 1 MW as agricultural land (arable land, forest, pasture
of installed capacity of the future wind power or similar), he/she may request the Ministry of
plant. The shortest distance between two mea- Transport and Communications, or the Municipal-
surement sites may be 2 km. If several inves- ity, as the case might be, to request the Ministry
tors are interested in measuring the wind power of Agriculture, Forestry and Water Economy to
potential on one site, the measurement permit permanently convert the relevant agricultural
shall be issued to the investor that first submit- land into construction land (Law on Agricultural
ted a complete and correct request (“first come, Land, article 49). The duration for this procedure
first served”). depend on the complexity to prepare and review the
The installation of wind power measurement project documentation. The costs for providing the
equipment is not subject to the requirement of a project documentation are borne by the investor.
construction permit. However, an approval from Unless the land parcel(s) where the investor
the Ministry of Transport and Communications intends to install the wind measurement equipment
is needed for install such equipment pursuant to is privately-owned, the investor needs to purchase
the Rulebook on the form and content of the ap- the land, sign a long-term lease contract with the
plication, documentation and form of the approval Government or obtain a concession for the land
for the construction of facilities and installation use (Law on Construction Land, articles 13 – 40).
of equipment for which a construction permit The procedures on the sale, long-term lease and
is not required. In addition, an approval from concession of State-owned construction land are
the Civil Aviation Agency is need to install the based on competitive bidding, which implies a risk
wind power measurement equipment, pursuant of not winning the bid for the specific land parcel.
to the Rulebook on the conditions for the place- If the land parcel is privately-owned, the inves-
ment, construction and designation of facilities, tor and the owner of the land may mutually agree
installations and devices in the zone of an airport, on the sale, long-term lease or use rights of the land.
facilities and flight control devices and facilities
outside the airport zone, that can affect the safety 4.4. Approval for connection
of air traffic and on the conditions and manner of to the transmission/
treatment of the land in the airport zone and the distribution system
land in its immediate proximity (Official Gazette,
No. 130/2007 and 156/2012). Electricity generation facilities with installed ca-
pacity of at least 10 MW are directly connected
4.3. Use of the land to the transmission grid (Electricity Transmission
Grid Code, article 57). Considering that most of the
Most often, the land suitable for construction of wind power plants will be with installed capacity
wind power plants is State-owned agricultural land of above 10 MW, we shall first present the proce-
(pastures, arable land, forests or similar). In such dure for obtaining approval for connection to the
case, the investor should request the initiation of transmission grid.
two procedures: The request for connection, prepared on a
1. Conversion of the agricultural into construc- standard template, and accompanied by a detailed
tion land, and study on the connection to the transmission grid,
2. Buy-out, long-term lease or concession agree- should be submitted to the transmission system
ment for the land use. operator (MEPSO). The study should include:
30 WIND POWER PLANTS
− Technical proposal for the connection, − Annual electricity production plan, per
− Technical characteristics of the equipment month,
for the connection, − Unipolar scheme of the plant,
− Operational requirements for the exploitation − Protection solutions for the aggregates and
and use of the equipment and the generation the corresponding transformers,
facility, − Data for calculating of the short-circuit
− Estimated costs for the connection to the current at the connection point,
transmission grid (Electricity Transmission − Planned duration of the works for connecting
Grid Code, article 68). to the distribution system.
MEPSO approves the technical solutions The award of the Approval for connection to
proposed in the study within 120 days from the the distribution system is subject to signing a Con-
day of receipt of the study, or it may order the tract for connection to the distribution network,
applicant to modify the proposed solutions ac- drafted by EVN Macedonia. EVN is obliged to issue
cording to its recommendations. By approving the Approval for connection to the distribution
the study, MEPSO delivers the approval for the system within 15 days for a standard connection,
connection to the transmission grid and specifies: and 40 days for non-standard connection.
− The technical solution of the connection,
− Technical specifications for the equipment A. Standard connection is a low or medium volt-
and works for the construction of the con- age power connection for facilities located
nection, in area covered by the Detailed Urban Plan
− The conditions for the use of the transmission (DUP), or by an Urban Plan for Village (UPV),
system, or an urban plan for a non-inhabited area and
− The estimated costs for the construction of the maximum approved simultaneous power
the connection (Electricity Transmission Grid of the connection is up to 400kW.
Code, article 70).
Electricity generation facilities with installed B. Non-standard connection is any low or medium
capacity of up to 10 MW may be connected to the voltage connection for facilities located in area
distribution grid. In such case the request for con- covered by the Detailed Urban Plan (DUP),
nection should be submitted to the distribution or by an Urban Plan for Village (UPV), or an
system operator (EVN Macedonia) in the initial urban plan for a non-inhabited area and the
phase of the construction works. The request maximum approved simultaneous power of
should be submitted on the template BSP-2 that the connection is greater than 400kW.
may be found at EVN’s energy users’ centers or may
be downloaded from EVN’s website. The costs for the connection to the transmis-
The following documents should be submitted sion or to the distribution grid, as determined
along with the request: by MEPSO or EVN Macedonia, respectively, are
− Constriction permit borne by the investor. Bearing in mind the usual
− Excerpt from the Trade Register distance to the nearest connection point and the
− Excerpt from the Cadastre designating the complexity of construction of connections for wind
parcel where the facility will be located power plants, we advise the investor to check with
− Proof of ownership of the facility or of the MEPSO and EVN Macedonia what shall be the actual
parcel where the facility shall be constructed connection point and to estimate the costs and
(property or ownership certificate) duration for the construction of the connection.
WIND POWER PLANTS 31
MW are subject to the award of an authorisation The request shall be examined by a nine-
for construction of a new electricity generation member Commission established by the Minister
facility by the Government (Law on Energy, Article of Economy. Should the Commission establishes
49). However, the authorisation for construction that the request is incomplete, it shall invite the
of a new electricity facility shall not be required, applicant to submit a full and correct documenta-
when the development of the wind power plant is tion within 15 days from the date of submission.
subject to the award of a concession for the land If the applicant fails to submit full and correct
use in a competitive procedure. In such cases, the documentation within the deadline, the Commis-
terms and conditions for the construction of the sion shall reject the request.
wind power plant shall be stipulated under the If the request is complete and correct, the
concession agreement. Commission shall propose the Government to
The procedure begins by submitting a re- issue an authorization for the construction of the
quest for the authorisation to the Government. wind power plant within 60 days of the receipt
The request shall be published in the Official of the request. Prior to taking its decision, the
Gazette, and shall be submitted to the Ministry Government shall seek the opinion of the Energy
of Economy. The following documents should be Regulatory Commission.
submitted along with the request (Law on Energy, The authorization shall lay down the follow-
Article 52): ing conditions:
1) Project design and cost-efficiency analysis; 1) The type, characteristics, installed capac-
2) Approval for the connection to the electric- ity and estimated annual generation of
ity transmission or distribution system, electricity;
pursuant to the relevant Grid Code; 2) The location of the plant, in compliance with
3) Decision on the approval of the Environ- the relevant urban planning documents;
mental Impact Assessment Study or of 3) The validity period of the authorisation;
the Environmental Impact Assessment, 4) Conditions for de-commissioning of the
if applicable; wind power plant;
4) Excerpt of the Local Detailed Urban Plan, 5) Conditions for the use of the public infra-
5) Financing plan for the construction of the structure;
wind power plant; 6) Environmental protection requirements;
7) Efficiency requirements concerning the
6) Letter of Intent, issued by a financial in-
operation of the plant; and
stitution or bank, indicating its intention
8) Other terms and conditions related to the
to provide financing to the project,
construction of the plant.
7) Proof of the investor’s equity,
8) Company profile of the investor and its
The authorization for the construction of the
potential partners, and their references
wind power plant shall apply for three years from
related to the implementation of similar
the date of its entry in force. The authorisation
projects;
shall cease to apply if the investor holder failed
9) Investor’s registration documents; to obtain the construction permit for the wind
10) Proof that the applicant is not undergoing power plant in question within three years. The
bankruptcy or liquidation procedure; authorization is transferrable to another entity
11) Proof that the applicant is not subject to subject to an approval by the Government.
misdemeanor or criminal procedure; and The Government may reject the request for
12) Statement of accuracy of the data provided. the authorisation in cases where:
WIND POWER PLANTS 33
1) The Environmental Impact Elaborate Study, been approved by the authorised supervisor, and
or where relevant, the Environmental Im- an use approval has been issued by the Ministry of
pact Assessment, has been rejected; Transport and Communications or the Municipal-
2) The existing urban planning documents ity, as the case may be.
do not provide for the construction of new In case the parcel where the investor intends to
electricity generation facilities; or build is classified as agricultural land (arable land,
3) The applicant fails to demonstrate its abil- forest, pasture or similar), he/she may request the
ity to finance and construction the wind Ministry of Transport and Communications, or
power plant (Law on Energy, articles 54 – 58). the Municipality, as the case might be, to request
the Ministry of Agriculture, Forestry and Water
4.7. Construction permit Economy to permanently convert the relevant
agricultural land into construction land (Law on
A construction permit is required to build a wind Agricultural Land, article 49). The duration for this
power plants. The Municipality on whose territory procedure depend on the complexity to prepare
the wind power plant is envisaged to be located is and review the project documentation. The costs
competent for award of the construction permit for providing the project documentation are borne
regardless of the installed capacity of the future by the investor.
wind power plant (Law on Construction, article 57, 58).
The application for construction permit must 4.8. Award of temporary status
be accompanied by the following documents: of preferential producer
- Excerpt of the Local Detailed Urban Plan,
- Architecture-urban project design (revised The Energy Regulatory Commission has adopted the
and approved), Rulebook on preferential producers of electricity
- Basic project design (revised and approved), from renewable energy sources (Official Gazette No.
- Concept project design, 18/2012, 97/2012, 63/2013 and 25/2015). Pursuant to
- Proof of right to build (ownership, usage the Energy Law and the Rulebook on preferential
right, concession), producers of electricity from renewable energy
- Geodetic survey of the land parcel. sources, the Energy Regulatory Commission shall
issue a decision for the award of a temporary status
The Municipality is obliged to review and of preferential producer, decision for the award of
adopt a decision on awarding the construction status of a preferential producer and a decision for
permit in a period of 15 days after the submitted the use of preferential tariff, and shall publish them
documentation is complete and correct. Prior to on its website, as well as in the Official Gazette. The
receiving the construction permit, the applicant Energy Regulatory Commission shall also publish
must pay a construction fee; the construction on its website the Register of preferential produc-
permit is delivered within five days following the ers, as well as the diagrams of the procedures for
submission of a proof that the construction fee the award of status of preferential producer and
has been paid. the use of the preferential tariff (www.erc.org.mk).
The construction permit may become null and The procedure for the award of the temporary
void if the applicant does not start the construction decision of status of a preferential producer shall
within 2 years, or finish it within six years from commence by the submission of the request to the
the date of issuing the permit (Law on Construc- Energy Regulatory Commission.
tion, article 59 - 68). The wind power plant may be The request shall be submitted to the Energy
put in use only after technical commissioning has Regulatory Commission in written form using the
34 WIND POWER PLANTS
template of the request for the award of a temporary The Energy Regulatory Commission shall hold a
decision for the award of status of a preferential regular session where it shall adopt the temporary
producer, signed and stamped by the applicant decision for the award of status of a preferential
(Template BPRRP). The applicant is obliged to select producer of electricity from renewable energy
and specially mark the confidential documents; sources within 5 (five) days from the date the
in the contrary all documents shall be treated as holding of the preparatory session, at the latest.
non-confidential documents. The temporary decision shall be published in the
The applicant is obliged to submit the following Official Gazette, and shall enter in force on the
information and documents: day of its adoption.
− Request for the award of a temporary decision In the temporary decision the Energy Regu-
for the award of status of a preferential pro- latory Commission shall determine the installed
ducer, signed and stamped by the authorized capacity of the power plant (i.e. of the generation
person; units), as well as the deadline by which the power
− Proof of entry in the Central Registry (original plant must be commissioned. The validity period
document or a notarised copy); of the temporary decision is equal to the dead-
− Proof of compliance with the requirement line for the commissioning of the power plant. In
(valid construction permit or concession this period, the holder of the temporary decision
agreement or public-private partnership is obliged to build the power plant, to obtain a
agreement), original document or a notarised positive technical commissioning report from an
copy; authorized engineer, in accordance with the Law
− Basic project design of the power plant, on Construction and to obtain a license for carrying
prepared by a licensed entity; out of energy activity – generation of electricity.
− Statement of accuracy of the request and the
submitted information and documentation, 4.9. Design and construction
signed by the applicant’s authorized person, of the connection
registered in the Central Registry (template).
Considering that most of the wind power plants
If the Energy Regulatory Commission estab- will be connected to the transmission grid, we
lishes that the request and the documentation shall review the procedure for the design and
are complete, it shall conclude that the request construction of the connection to the transmission
is acceptable and shall continue the procedure in grid. Pursuant to the approval for the connection
accordance with the Rulebook on the licenses for to the transmission grid, the investor and MEPSO
performance of energy activities within 5 (five) days should sign an agreement for connection to the
from the date of receipt of the request. The Energy transmission grid (Electricity Transmission Grid
Regulatory Commission shall submit a copy of the Code, Article 71), which defines:
conclusion to the applicant. − the mutual obligations during the construc-
The Energy Regulatory Commission shall tion of the connection,
schedule a preparatory session that shall take − the acceptance of the project documentation
place within 25 (twenty five) days from the date for the construction of the connection,
of receipt of the request. The Energy Regulatory − the connection-related assets of MEPSO and
Commission shall invite the applicant to attend the investor,
the preparatory session, as well as the authorized − the sharing of costs between MEPSO and the
representatives of interested stakeholders, institu- investor for the construction of the connec-
tions and organizations. tion.
WIND POWER PLANTS 35
electricity from renewable sources from the Energy − Organizational structure of the applicant,
Regulatory Commission, before the receipt of the including information on the number of
technical commissioning report or use permit personnel, and the education and techni-
issued by an authorized supervising engineer in cal qualifications of the personnel that will
cases where: manage the facility and will use the specific
− The investor has been awarded an authoriza- equipment;
tion for the construction of the energy facility − Project design, construction permit, and – if
in question, pursuant to the Energy Law; or the facility has been already built - a technical
− The investor has been awarded a construction commissioning report or use permit, as well
permit for the energy facility if an authori- as an authorization for construction of the
zation for construction of the facility is not electricity generation facility, if relevant;
warranted, or − Statement on the company’s ownership struc-
− The investor has been awarded the right ture, including information and a detailed
to build the energy facility in a competitive description of the applicant’s share in other
procedure for construction of electricity companies, as well as the share of other
generation facilities, or companies in the applicant’s company;
− The investor has obtained a right to build the − Solvency statement for the applicant, issued
facility on the basis of a concession agreement. by a competent body;
− Proof of paid taxes and other fees, issued by
The investor should submit a request for the the Public Revenue Office;
award of license to the Energy Regulatory Commis- − Financial reports prepared in accordance
sion, accompanied by the following information with the applicable regulations for the past
and documents: three years, including an auditor’s report
− General information for the applicant, from an authorized auditor, if the audit is
− Name of the responsible person, warranted by law;
− Type of the energy activity to be carried out, − Proof that the applicant is not subject to
− Brief description of the license claimed, liquidation procedure;
− Statement of accuracy of the information − Statement from the Central Registry that
and the submitted documents, signed by the the applicant is not banned from carrying
authorized person, out professional activities, and that it is not
− Statement on the time period of the request sentenced for criminal deed.
for the award of the license,
− Proof of payment of the fee for the award of In addition to the above-mentioned documents,
the license, the applicant is also obliged to submit additional
− Proof of entry in the Central Registry, documentation on the specific technology for
− Founding act and/or Statute of the company, generation of electricity and the use of natural
− Evidence of the ownership right or of the resources, in accordance with Article 14 of the
land use right and of the basic capital, Rulebook on the licenses for performance of energy
− Concession agreement if the energy activity activities.
is to be carried out on the basis of exploi- The Energy Regulatory Commission shall ex-
tation of natural resources or concession amine the request for award of license and the
agreement for provision of public service, accompanying documentation and shall adopt a
or proof of the right of exploitation of the Conclusion within 8 days. If the documentation for
natural resources; the award of the license is in compliance with the
WIND POWER PLANTS 37
Rulebook on the licenses for performance of energy Following the receipt of the license for genera-
activities, and other relevant laws and regulations, tion of electricity, the investor may, if the technical
the Energy Regulatory Commission shall oblige the conditions so allow, generate and sell electricity
applicant go prepare a notification for the request before the acquisition of the status of preferential
within 3 days and to submit it to the Energy Regu- producer (refer to 4.13) and before signing the
latory Commission for approval. If the submitted power purchase agreement with MEPSO (refer to
documentation has formal and other omissions, 4.14). For this purpose the investor should sign an
then the Energy Regulatory Commission shall oblige agreement with:
the applicant to remove the shortcomings within − the Operator of the electricity transmission
15 days and to submit a complete documentation system (MEPSO),
in accordance with the Rulebook on the licenses − electricity supplier, or
for performance of energy activities. − electricity trader.
The investor is obliged to publish the request
for the award of license for generation of electricity Such agreement may be with definite duration,
from renewable sources on its expense in at least i.e. until the acquisition of the status of preferential
two daily newspapers on both official languages. producer, or alternatively – with indefinite dura-
The announcement serves to notify the award of tion, if the investor fails to obtain the status of
the license and to invite all interested stakeholders preferential producer or chooses to renounce it.
to comment and to present their case.
Following the publication of the request, the 4.12. Registration of the facility
Energy Regulatory Commission shall schedule a in the Register of electricity
preparatory session that shall take place within 50 generation facilities from
days from the date of submission of the request. renewable energy sources
If the Energy Regulatory Commission establishes
at the preparatory session, that the requirements The investor must register its wind power plant
for the award of the license have been fulfilled, it in the Register of electricity generation facilities
shall schedule a regular session within 10 days to from renewable energy sources, maintained by
formally endorse the decision for the award of the Energy Agency. For this purpose, the investor
the license. should submit a request to the Energy Agency for
The Energy Regulatory Commission shall registration in the Register of electricity generation
publish the decision and the license for energy facilities from renewable energy sources, along
activities in the Official Gazette. with the following documents:
If the license has been awarded prior to the 1. Use approval for the energy facility, or
technical commissioning or receipt of the use per- technical commissioning report, in case
mit, whilst the investor has obtained the technical where the use approval is not required, and
commissioning report and the use permit in the Confirmation from the electricity trans-
meanwhile, the investor should submit these ad- mission system operator that the energy
ditional documents in accordance with Article 32 facility is connected on the appropriate
of the Rulebook on the licenses for performance (transmission or distribution) system,
of energy activities. Following the receipt of the 2. Topographic map, on a scale of 1:25.000 show-
additional documentation, the Energy Regulatory ing the location of the wind power plant,
Commission shall issue the decision on the entry 3. Schematic drawings of the wind power plant
in force of the previously awarded license within and the installed equipment, in particular
8 days from the date of submission. the metering equipment, and
38 WIND POWER PLANTS
4. Copy of the license for electricity generation hold a license for carrying out energy activity – gen-
(Rulebook on renewable sources of energy, eration of electricity for the power plant in question.
article 8). The requests shall be submitted to the En-
ergy Regulatory Commission in written form, on
If the Energy Agency establishes that the a template for the request of a decision for the
request is incomplete, it shall notify the appli- award of status of a preferential producer, signed
cant and invite him to complete the necessary and stamped by the applicant (Template BRPP), as
documentation within 30 days from the day of well as a filled-in template for the request for the
the submission of the notification. Should the use of preferential tariff, signed and stamped by
applicant fails to complete the documentation the applicant (Template BKPT).
within the specified deadline, the Energy Agency The applicant is obliged to select and especially
will reject the request, as incomplete. mark the documents with confidential information;
If the Energy Agency establishes the request in the contrary, all submitted documents shall be
and the accompanying documentation is complete treated as non-confidential. The requests for the
and correct, and that all conditions for awarding use of preferential tariff relate to the tariff that
the status of preferential producer are met, it shall applied on the date of adoption of the temporary
adopt a decision for registering the applicant in the decision for the award of status of a preferential
Register of preferential producers of electricity producer of electricity.
within 15 days of the date of submission of the re- The applicant is obliged to accompany the re-
quest. The Energy Agency may decide to perform an quest with the following information and documents:
on-site inspection of the facility prior to the award − Project design of the constructed facility in
of the decision. The Energy Agency shall submit accordance with the Law on Construction, if
the investor the Resolution for registration in the modifications from the basic project design
Register of preferential producers of electricity have been made during the construction;
within three days of the date of adoption of the − Proof of entry in the Register of producers of
decision. The investor shall be registered under a electricity from renewable energy sources, is-
unique registration number, which may not change sued by the Energy Agency, in accordance with
or be transferred (Rulebook on renewable sources of the Rulebook on renewable energy sources;
energy, article 9). − Proof of payment of the fee in accordance
with Article 13-a of the Rulebook on preferen-
4.13. Award of status of tial producers of electricity from renewable
preferential producer energy sources;
− Statement of accuracy of the request and
Following the receipt of the temporary decision the submitted information, signed by an
for the award of status of a preferential producer authorized representative of the applicant,
of electricity from renewable energy sources, the registered at the Central Register.
investor should request the award of status of a
preferential producer of electricity from renewable The submitted documents should be the origi-
energy sources and should simultaneously submit nal document or notarised copy.
a request for the use of preferential tariff for elec- In addition to the requests, the applicant is
tricity obtained from renewable energy sources. obliged to submit a proof that he/she has transferred
As a prerequisite, the power plant should be com- an irrevocable monetary fee to the account of the
missioned within the deadline established in the Energy Regulatory Commission to cover the costs
temporary decision, whereas the applicant should borne during the procedure (the Energy Regulatory
WIND POWER PLANTS 39
Commission should actually transfer this fee to the applicant and to submit it the draft decision for
Energy Agency pursuant to the tariff adopted by the award of status of preferential producer and
the Energy Agency). draft decision for the use of preferential tariff of
The procedure for the award of status of pref- electricity from renewable energy sources not
erential producer and the adoption of the decision later than 7 (seven) days before the holding of the
for the use of the preferential tariff comments on preparatory session. In addition to the applicant,
the date of receipt of the request in the archive of the Energy Regulatory Commission may also invite
the Energy Regulatory Commission. authorized representatives of interested stakehold-
Following the receipt of the requests, the ers, institutions and organizations.
Energy Regulatory Commission shall establish if The Energy Regulatory Commission shall hold
the documentation is complete and if it is submit- a regular session within 5 (five) days from the date
ted in the proper procedure and form. The Energy of holding of the preparatory session to formally
Regulatory Commission shall request a confirma- adopt the Decision for the award of status of a
tion from the Energy Agency within 5 (five) days preferential producer of electricity from renew-
from the date of receipt of the requests, that the able energy sources and the Decision for the use
power plant has been built and that it complies of preferential tariffs for electricity obtained from
with the specific requirements, in particular on renewable energy sources.
the installed capacity, laid down in the Ordinance, The decisions shall be published in the Official
that applied on the date of issuing of the temporary Gazette, as well as on the website of the Energy
decision for the award of status of a preferential Regulatory Commission. On the day of entry on
producer. The Energy Agency is obliged to issue the force of the decision, the Energy Regulatory Com-
confirmation not later than 15 (fifteen) days from mission shall enter the information related to the
the date of receipt of the request by the Energy applicant and the power plant, as well as to the
Regulatory Commission. For the issuing of the applicable preferential tariff in the Register of
confirmation, the Energy Regulatory Commission preferential producers. The Energy Regulatory
pays a fee to the Energy Agency, in accordance with Commission shall submit the decisions to the ap-
the tariffs adopted by the Energy Agency, reflecting plicant, to the Electricity Market Operator and to
the costs of the Energy Agency in the procedure the Energy Agency.
for the issuing of the confirmation.
If the Energy Regulatory Commission estab- 4.14. Power purchase agreement
lishes that the requests and the documentation are with the electricity
complete and do not have any shortcomings, and market operator
if the conformation issued by the Energy Agency
is positive, the Energy Regulatory Commission The electricity market operator (MEPSO) is obliged
conclude within 20 (twenty) days from the date of to purchase the entire electricity generated by the
receipt of the requests that the documentation is preferential electricity producers pursuant to an
complete and that the procedure may continue. agreement, in accordance with the Energy Law,
The Energy Regulatory Commission shall submit the Decision on the application of feed-in tariff
a copy of the conclusions to the applicant. issued by the Energy Regulatory Commission and
The Energy Regulatory Commission shall the Electricity Market Rules. The investor should
schedule a preparatory session to examine the submit a request for signing a power purchase
requests within 35 (thirty five) days from the date agreement to MEPSO.
of receipt of the requests at the latest. The Energy MEPSO is obliged to sign the power purchase
Regulatory Commission is obliged to invite the agreement within 30 days from the date of receipt
40 WIND POWER PLANTS
of the request. The power purchase agreement must This step marks the end of the application
enter in force on the day the Decision on awarding process. After the acquisition of the status of
the status of preferential electricity producer was preferential producer, the investor may apply and
issued by the Energy Regulatory Commission. use the feed-in tariffs laid down in the Ordinance
The investor may decide to terminate the on preferential tariffs for electricity (Article 7).
power purchase agreement, thereby losing the The exact feed-in tariff applicable to the genera-
status of preferential electricity producer and tion facility depends on the monthly amount of
the right to obtain the status again (Energy Law, electricity generated and sold per each block.
Article 153). Depending on the amount of electricity generated
The investor is obliged to sell the entire each month, the actual feed-in tariff applicable
amount of electricity generated to MEPSO, and to the facility may vary. The feed-in tariffs apply
to submit electricity generation plans to MEPSO. for a period of 20 years.
In case where the investor did not succeed in sources of energy. It should be noted that the pref-
acquiring a status of preferential producer of erential tariff is incompatible with the guarantee
electricity and thereby benefit from the prefer- of origin – the investor may either use one or the
ential tariff, or if the investor has voluntarily other. If the investor uses the preferential tariff,
abandoned the power purchase agreement with he/she may not apply for guarantees of origin.
the electricity market operator (see chapter 4.15. Where relevant, the investor should submit
above), the investor may apply for guarantees of a request for the award of guarantees of origin
origin to claim premium price for the electricity for the electricity generated in its wind power
generated in his wind power plant. plant to the Energy Agency. The request should
Guarantees of origin are usually warranted be accompanied by:
by electricity transmission system operators or − A proof of paying the fee for the issuance of
electricity traders that are under obligation to guarantees of origin, and
pay premium prices for electricity generated from − A proof of the electricity transmission or
renewable sources of energy. It should be noted distribution system operator for the quan-
that the preferential tariff is incompatible with the tity of electricity generated and sold by the
guarantee of origin – the investor may either use facility.
one or the other. If the investor uses the preferential
tariff, he/she may not apply for guarantees of origin. If the Energy Agency establishes that all condi-
The manner and procedure for the award of tions for the award of the guarantees of origin for
guarantees of origin is governed by the Rulebook the electricity generated from renewable energy
on renewable sources of energy. Where relevant, sources are fulfilled, it shall award the decision
Guarantees of origin are usually warranted by elec- within 30 days from the date of receipt of the request.
tricity transmission system operators or electricity A guarantee of origin is issued per 1 MW.
traders that are under obligation to pay premium The guarantees of origin are valid for a period
prices for electricity generated from renewable of 12 months.
WIND POWER PLANTS 41
Përmbajtja
1. Hyrja............................................................................................................................... 45
2. Shqyrtimi i tarifave të zbatueshme për hidrocentralet................................................... 46
3. Diagram i hollësishëm për procedurën dhe dokumentet për ndërtim..............................47
4. Shqyrtimi i hapave, procedurave dhe dokumenteve........................................................ 48
4.1. Parakushtet kryesore: Themelimi i kompanisë....................................................... 48
4.2. Koncesion për përdorimin e ujit për prodhimin e energjisë elektrike..................... 48
4.3. Shndërrimi i tokës.................................................................................................. 50
4.4. Studim për vlerësimin e ndikimit mbi mjedisin jetësor............................................ 51
4.5. Miratim për ndërtim................................................................................................52
4.6. Marrja e statusit të përkohshëm të prodhuesit të autorizuar...................................52
4.7. Pëlqim për kyçje në sistemin distribuues................................................................ 54
4.8. Projektimi dhe zbatimi i impiantit...........................................................................55
4.9. Miratim për përdorim..............................................................................................55
4.10. Licencë për prodhimin e energjisë elektrike........................................................... 56
4.11. Regjistrimi i objektit në Regjistrin e objekteve për prodhimin e
energjisë elektrike nga burime të ripërtëritshme të energjisë................................ 58
4.12. Marrja e statusit prodhues i autorizuar.................................................................. 58
4.13. Marrëveshje për blerjen e energjisë elektrike me ndonjë
operator në tregun e energjisë elektrike................................................................. 60
5. Sigurimi i garancive për prejardhjen e energjisë elektrike të
prodhuar nga burimet të ripërtëritshme të energjisë......................................................61
6. Adresa dhe të dhëna kontaktuese të institucioneve kompetente.................................... 62
7. Legjislatura relevante dhe aktet rregullatore................................................................. 63
Ky publikim është përgatitur me ndihmën e Bashkimit Evropian. Përmbajtja e këtij publikimi është përgjegjësi
vetëm e ATC Consultants dhe partnerëve të saj të konsorciumit dhe në asnjë mënyrë nuk pasqyron pikëpamjet e
Bashkimit Evropian.
CENTRALET ME ERË 45
1. Hyrje
Rekomandimi ynë është që investitorët t’i konsultojnë organet kompetente për potencialin dhe
procedurat për ndërtimin e hidrocentralit para fillimit të procedurës si dhe gjatë procedurave
për mbështetje më të drejtpërdrejt në procesin e aplikimit.
46 CENTRALET ME ERË
Tarifat e autorizuara të energjisë elektrike të cilën e prodhojnë dhe shesin centralet me erë (të cilat e
kanë marrë statusin e prodhuesit të autorizuar) janë përcaktuar në Dekretin mbi tarifat e autorizuara
për energji elektrike (Gazeta zyrtare nr. 56/2013) dhe është siç vijon:
Kuota e centraleve me erë të cilat mund të përdorin tarifa të autorizuara është përcaktuar në
Vendimin për fuqinë instaluese të përgjithshme të prodhuesve të autorizuar të energjisë elektrike e
prodhuar nga çdo burim i ripërtëritshëm i energjisë (Gazeta zyrtare nr. 56/2013 dhe 10/2014) siç vijon:
Në momentin e përgatitjes së këtij Manuali e deri më 31 dhjetor 2016, 13,2 MW akoma ishin në
dispozicion për centralet me erë të sapondërtuara1. Kuota do të rritet për 35 MW në vitin 2017, dhe
për 50 MW në vitin 2021.
Investitorët e mundshëm duhet ta dinë se korporatës në pronësi shtetërore ELEM i është dhënë licencë për
1
ndërtimin e centraleve të erës me një kapacitet total të instaluar prej 50 MW. ELEM shfrytëzoi 36,8 MW të
licencës së saj me lëshimin në përdorim të turbinave me erë në Bogdanci në vitin 2013. ELEM është duke
planifikuar që t›i shfrytëzojë 13,2 MW të mbetura për central të erës në periudhën pas vitit 2016.
3. Diagram i hollësishëm për procedurën dhe dokumentet për ndërtim
Kohëzgjatja Kohëzgjatja
Viti Viti 1 Viti 2 Viti 3 Viti 4 Viti 5
Muaj 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Procedura Institucioni kompetent
4.1 Themelimi i kompanisë 6.1
Matja e potencialit të erë për 1
4.2 6.3 Matja e potencialit të erës (minimum 2 vjet)
prodh. e Energjisë elektrike
6.1, 6.8, 6.9 ose
4.3 Përdorimi i tokës komuna 2
Miratim për kyçje në
4.4 Sistemin për përçues apo për 6.5 ose 6.6
distribuim
4.5
Studim për vlerësimin e ndikimit 6.7 ose komuna
mbi mjedisin jetësor
4.6 Autorizim për ndërtimin e 6.1 3
centralet me erë
4.7 Miratim për ndërtim 6.8 ose komuna 4
PROCESI I NDËRTIMIT
4.8
Marrja e statusit të përkohshëm 6.4
të prodhuesit të autorizuar
Projektimi dhe zbatimi i 6.5, 6.6 ose kompani
4.9 5
impiantit e autorizuar
Legjenda:
:
Rreziku 1: Rezultatet e matjes mund të mos e Rrezik 4: Pamundësia për t’u marrë miratim
Kohëzgjatja e procedurës 1 4
mbështesin zbatimin e projektit për këtë lokacion për ndërtim apo vonesë e paparashikuar
Kohëzgjatja e matjes së potencialit të erës për prodhimin e energjisë Rreziku 2: Pamundësia për të fituar të drejtën për shfrytëzimin e tokës Rreziku 5: Rritja e shpenzimeve për kyçje nëse nuk është
elektrike (minimum dy vjet) 2 ndërtimore, vonesë apo pasiguri nga rezultatet dhe shpenzimet 5 e mundur të bëhet lidhshmëria në impiantin më të afërt
janë përzgjedhur, të përgatitura me ligj dhe të kërkojë mendim prej palëve të interesuara në
propozuara prej Qeverisë. afat prej 15 ditëve.
Kur shtruesi do të përzgjidhet si ofrue- Ministria e Mjedisit Jetësor dhe Planifiki-
si më i volitshëm, marrëveshja e koncesionit mit Hapësinor është obligohet t’ia jap lejen për
nënshkruehet vetëm pasi të përmbushen kërkesat shfrytëzimin e ujit shtruesit në afat jo më të gjatë
e nevojshme për marrjen e lejës përkatëse për se tre muaj prej ditës së pranimit të kërkesës dhe
shfrytëzimin e ujit për prodhimin e energjisë pasi që t’i ketë marrë parasysh të gjitha mendimet
elektrike (Ligji për ujërat, neni 23). Këto kërkesa e dhëna prej organeve kompetente dhe palëve të
janë përcaktuar në dokumentacionin e tenderit. interesuara. Leja për shfrytëzimin e ujit hyn në
Kohëzgjatja maksimale e koncesionit për fuqi pas pranimit të raportit pozitiv nga kontrolli
shfrytëzimin e ujit për prodhimin e energjisë i kryer në objekt dhe pajisjet nga ana e Komisionit
energjike është në vijim: prej pesë antarëve i përbërë prej përfaqësuesve
− Për hidrocentralet me fuqi prej 2 deri 10MW të emëruar nga Ministria e Mjedisit Jetësor dhe
– 50 vjet, Planifikimit Hapësinor. Leja për shfrytëzimin e
− Për hidrocentrale me fuqi deri 2 MW – 30 ujit jepet me kohëzgjatje të kufizuar varësisht
vjet. (Ligji për ujërat, neni 57). prej karakteristikave specifike të objektit, por
Gjegjësisht, kohëzgjatja e zakonshme e kon- jo më gjaët se 10 vjet (Ligji për ujërat, neni 28-41).
cesionit për shfrytëzimin e ujit për prodhimin Leja për shfrytëzimin e ujit ndër të tjerash
e energjisë elektrike për hidrocentrale të vogla mund të mos vlejë nëse:
është 23 vjet. − shfrytëzuesi nuk fillon me aktivitetet për
ndërtim në afat prej dy viteve prej ditë së
Kusht për dhënien dhe nënshkrimin e dhënies së lejës,
marrëveshjes së koncesionit për shfrytëzimin − shfrytëzuesi nuk i ka mbaruar aktivitetet
e ujit për prodhimin e energjisë elektrike është për ndërtim në afatin e caktuar me leje,
marrja e lejës për shfrytëzimin e ujit të cilën e − shfrytëzuesi nuk e shfrytëzon ujin pa shkaqe
jep Ministria e Mjedisit Jetësor dhe Planifikimit të arsyeshme në periudhë me të gjatë se dy vjet.
Hapësinor (Ligji për ujërat, neni 56). − leja e dhënë nuk përputhet më me ndryshi-
Shtruesi dorëzon deri te Ministria e Mjedi- met dhe plotësimet e planit(-eve) për me-
sit Jetësor dhe Planifikimit Hapësinor kërkesë naxhimin e pellgjeve lumore, falimentimi i
për marrjen e lejes për shfrytëzimin e ujit, së shfrytëzuesit të ujit (Ligji i ujërave, neni 47).
bashku me kushtet për ekonomizim të ujërave
për projektim dhe kushtet për mbrojte të ekosiste- Leja për shfrytëzimin e ujit merrat përderisa:
meve të cilat varen prej ujit. Ministria e Mjedisit − uji shfrytëzohet në kundërshtim me kushtet
Jetësor dhe Plnaifikimit Hapësinor obligohet e përcaktuara në leje,
të fillojë të veprojë për kërkesën në afat prej 7 − shfrytëzuesi nuk ka paguar kompensim për
ditëve prej datës së pranimit, dhe nëse është e shfrytëzimin e ujit,
nevojshme, t’i rekomandojë shtruesit përsëri − Shfrytëzuesit i është shqiptuar sanksion
të dorëzojë disa dokumente dhe informata të kundërvajtës ndalëse për zbatimin e ve-
cilat kanë munguar ose kanë qenë të gabuara. primtarisë në lidhje me shfrytëzimin e ujit
Ministria e Mjedisit Jetësor dhe Planifikimit (Ligji për ujërat, neni 51).
Hapësinor është obligohet ta publikojë kërkesën
për dhënien e lejës për shfrytëzimin e ujit në Përveç kësaj, në rast të mungesës së ujit të
ueb faqen e saj, si dhe në shtypin ditor dhe të pijshëm, Ministria e Mjedisit Jetësor dhe Planifi-
50 CENTRALET ME ERË
kimit Hapësinor mund të bëjë ndryshim të lejes Afati i dorëzimit të ofertave është se paku
për shfrytëzimin e ujit dhe t’i limitojë sasitë e 30 ditë. Nëse dokumentacioni i tenderit nuk për-
ujit të cilat janë të disponueshme për prodhi- caktohet ndryshe, afati për vlerësimin e ofertave
min e energjisë elektrike. Ngjashëm me këtë, është 30 ditë. Marrëveshja për koncesion mund
Qeveria mund ta marrë lejen për shfrytëzimin të nënshkruhet kur vendimi i ofertës më të mirë
e ujit përshkak të sigurimit të intersit më të bëhet në formë të prerë, përkatësisht kur do të
lartë publik. Në këto raste, shfrytëzuesi mund shtrerohen të gjitha të drejtat për paraqitjen e
të kërkojë kompensim të dëmit në pajtueshmëri ankesës. (Ligji për koncesion dhe partneritet publik
me rregullat e përgjithshme për kompensimin e privat, neni 30, 35, 36).
dëmit (Ligji për ujërat, neni 47 dhe 52). Ta keni parasysh se koncesioni shfuqizohet
Shfrytëzuesit e ujit, duke i përfshirë edhe në rastet kur:
shfrytëzuesit e ujit për prodhimin e energjisë − Leja për shfrytëzimin e ujit është e pezulluar
elektrike, janë të obliguar të paguajnë kompensim apo ka skaduar
për shfrytëzimin e ujit. Obligimi për pagimin e − Koncesioneri nuk ka filluar me kryerjen
kompensimit për shfrytëzimin e ujit fillon prej e veprimtarive për koncesion në afatin e
kur leja fillon të prodhojë veprim ligjor. Shuma e caktuar në marrëveshjen e koncesionit,
kompensimit që paguhet për shfrytëzimin e ujit − Me skadimin e afatit të vlefshmërisë të
për prodhimin e energjisë elektrike është 1% prej paraparë në marrëveshjen e koncesionit,
çmimit prodhues tpër një orë kilovat të pragut − Me blerjen e parakohshme të koncesionit
të hidrocentralit. Prodhuesi i energjisë elektri- për interes publik,
ke është i obliguar ta paguaj kompensimin për − Në rast të prishjes së njëanëshme të
shfrytëzimin e ujit një herë në muaj në llogari të marrëveshjes së koncesionit,
veçantë për pagesë në kornizat e llogarisë trezore − Me falimentimin ose likuidimin e
(Ligji për ujërat, neni 213). koncesionarit,
Në rast të koncesionit për shfrytëzimin e − Raste të tjera të parapara në marrveshen
ujit, koncesioneri është i obliguar të paguaj kom- për koncesion.
pensim për shfrytëzimin e ujit (i definuar në
lejen për shfrytëzimin e ujit) dhe kompensim të 4.3. Shndërrimi i tokës
koncesionit. Kompensimi i koncesionit përbëhet
prej dy pjesëve, duke përfshirë: Zakonisht, toka e cila është përkatëse për ndërti-
− Kompensim i njëhershëm i cili paguhet me min e hidrocentraleve të vogla është tokë bujqëso-
dhënien e koncesiont, dhe re (kullota, tokë e përpunueshme, pyje etj) në
− Kompensim vjetor i cili paguhet për çdo pronë shtetërore. Në këtë rast, investitori duhet
vit gjatë kohëzgjatjes së koncesionit. të kërkojë inicimin e dy procedurave:
1. Shndërrimin e tokës bujqësore në tokë
Zbatuesi është i obliguar ta paguaj kompen- ndërtimore, dhe
simin e koncesionit prej më herët, si kompensim 2. Blerjen, qira afatgjate apo marrëveshje për
fillestar ose me këste. Shuma e kompensimit të koncesion për shfrytëzimin e tokës.
njëfishtë për prodhimin e energjisë elektrike nuk
duhet të jetë më e vogël se shuma e dhjetëfishtë e Nëse parcela(t) e tokës në të cilën investitori
kompensimit vjetor sipas vlerësimit të arritjeve ka për qëllim ta ndërtojë hidrocentralin e vogël
në vitin e parë të shfrytëzimit (Ligji për ujërat, është klasifikuar si tokë bujqësore (tokë e përpu-
neni 58). nueshme, pyje, kullota etj.), investitori mund të
CENTRALET ME ERË 51
shtrojë kërkesë deri te Ministria e Transportit dhe madhësinë e projektit dhe të sipërfaqes
dhe Lidhjeve apo deri te Komuna, varësisht rastit së nevojshme të tokës;
të kërkojë, nga Ministria e Bujqësisë, Pylltarisë − Përshkrim për mjedisin jetësor dhe
dhe Ekonomisë së Ujërave të bëjë shndërrimin lokacionit e tij;
e përhershëm të tokës bujqësore përkatëse në − Përshkrim për trashëgiminë natyrore,
tokë ndërtimore (Ligji për tokë bujqësore, neni kulturore dhe historike dhe përshkrim të
49). Kohëzgjatja e kësaj procedure varet nga peizazhit;
ndërlikueshmëria e përgatitjes dhe shqyrtimit − Përshkrim të llojit dhe sasive të pritura të
të dokumentacionit të projektuar. Shpenzimet emisioneve, veçanërisht të emisioneve të
për sigurimin e dokumentacionit projektues i ajrit, ujrave të zeza, mbeturinave të ngurta
bart investitori. si dhe informacione të tjera të nevojshme
Përveç nëse parcela e tokës në të cilën inve- për vlerësimin e ndikimeve më të mëdha
stitori ka për qëllim ta ndërtojë hidrocentralin të projektit mbi mjedisin jetësor;
nuk është në pronë private, investitori duhet ta − Përshkrimin e masave për parandalimin,
blejë tokën, të nënshkruajë marrëveshje për blerje uljen dhe eliminimin e ndikimit mbi mjedisin
afatgjate me Qeverinë apo të marrë koncesion për jetësor, si dhe të masave për kthimin në
shfrytëzimin e tokës (Ligji për tokë ndërtimore, gjendje të mëparshme;
nenet 13 – 40). Procedurat për tjetërsim, dhënien − Përshkrimin e ndikimeve të projektit mbi
nën qira afatgjate dhe koncesion të tokës ndër- mjedisin jetësor duke e pasur parasysh
timore me pronë shtetërore bëhen me ankand nivelin e zhvillimit të shkencës dhe
publik, që sjell rrezik që të mos fitohet në ankand metodave të pranueshme për vlerësim;
ndonjë parcelë tokësore konkrete. − Përshkrimin e karakteristikave të
Nëse parcela tokësore është në pronë private, teknologjisë e cila përdoret;
investitori dhe pronari i tokës munden së bashku − Përshkrimin e zgjidhjeve alternative për
të dakordohen për tjetërsim, qiramarrje afatgjate realizimin e projektit të cilat i ka pasur
apo për të drejtën e shfrytëzimit të tokës. parasysh investitori dhe shkaqet kryesore
për përzgjedhjen e alternativës së propozuar;
4.4. Studim për vlerësimin e gjithmonë përfshihet edhe alternativi nulta
ndikimit mbi mjedisin jetësor (zero)
− Rezyme për studimin e dorëzuar pa detaje
Ju lutemi që ta keni parasysh se hidrocentralet teknike;
varen nga kërkesat për përgatitjen dhe dorëzi- − Analizë për vështirësitë (mangësitë teknike
min e Studimit për vlerësimin e ndikimit mbi apo mungesën e njohurive) me të cilat
mjedisin jetësor. Që këtu, hidrocentralet nuk investitori apo eksperti janë ballafaquar
mund të ndërtohen apo të fillojnë me punë para gjatë përgatitjes së studimit; dhe
se të merret vendim pozitiv për Studimin për − Propozim për madhësinë dhe karakteristikat
vlerësimin e ndikimit mbi mjedisin jetësor në e ndryshimeve potenciale për të cilat duhet
pajtim me Ligjin për mjedis jetësor. (Ligji për të azhurnohet Studimi për vlerësimin e
ujërat, neni 177). ndikimit mbi mjedisin jetësor.
Studimi për vlerësimin e ndikimit mbi mje-
disin jetësor duhet të përmbajë: Studimi për vlerësimin e ndikimit mbi
− Përshkrim për projektin bashkë me mjedisin jetësor duhet të strukturohet në këtë
informacione për lokacionin, karakterin mënyrë:
52 CENTRALET ME ERË
energjisë (Gazeta zyrtare nr. 18/2012, 97/2012, • Projekti bazë i centralit me erë i punuar
63/2013 dhe 25/2015). Në pajtueshmëri me Ligjin prej personit të licencuar juridik,
për energjetikë dhe Rregulloren për prodhues të • Deklaratë për besueshmërinë e kërkesës
autorizuar të energjisë elektrike prej burimeve të dhe të dhënave dhe dokumenteve të dorëzu-
ripërtërishme të energjisë, Komisioni Rregullator ara, të nënshkruara prej udhëheqësit të
për energjetikë jep vendim për marrjen e statu- autorizuar për përfaqësimin e shtruesit të
sit të përkohshëm të prodhuesit të autorizuar, regjistruar në Regjistrin qendror.
vendim për marrjen e statusit të prodhuesit të
autorizuar dhe vendim për shfrytëzimin e tarifës Nëse Komisioni Rregullator për energjetikë
së autorizuar, të njëjtat i publikon në ueb faqen e përcakton se dokumentacioni është i plotë dhe
tij si dhe në Gazetën Zyrtare. Gjithashtu, në ueb nuk ka mangësi, në afat prej 5 (pesë) ditëve prej
faqen e Komisionit rregullator për energjetikë ditës së marrjes së kërkesës do të sjellë përfundim
publikohet edhe Regjistri i prodhuesve të autori- për rregullshmërinë e kërkesës dhe vazhdimin
zuar, si dhe diagrami i procedurave për marrjen e procedurës në pajtueshmëri me dispozitat e
e statusit prodhues i autorizuar dhe shfrytëzimin Rregullores për licenca për zbatimin e aktivi-
e tarifave të autorizuara: www.erc.org.mk. teteve energjetike. Komisioni rregullator për
Procedura për dhënien e vendimit të për energjetikë dorëzon një ekzemplar të përfundimit
kohshëm për marrjen e statusit të përkohshëm të deri te shtruesi.
prodhuesit të autorizuar fillon me shtrimin e kër- Komisioni Rregullator për energjetikë në
kesës deri te Komisioni rregullator për energjetikë. lidhje me kërkesën e dorëzuar për dhënien e
Kërkesa shtrohet deri te Komisioni rregullator vendimit të përkohshëm për marrjen e statusit
për energjetikë ne formë të shkruar si formular i prodhues i autorizuar do të caktojë seancë për-
plotësuar për kërkesë për dhënien e vendimit të gatitore e cila do të mbahet në afat i cili nuk do
përkohshëm për marrjen e statusit prodhues i au- të mund të jetë më i gjatë se 25 (njëzet e pesë) ditë
torizuar, e nostrifikuar me nënshkrim dhe vulë prej prej ditës së pranimit të kërkesës. Për pjesëmarrje
shtruesit (Formulari KVPPA): Shtruesi është i obli- në seancën përgatitore, komisioni rregullator për
guar t’i ndajë dhe t’i shënojë në mënyrë të veçantë energjetikë e fton shtruesin, si dhe përfaqësuesit
dokumentet të cilat janë me karakter kofidencial. e autorizuar të ndërmarrjeve, institucioneve dhe
Në të kundërtën do të konsiderohet se dokumentet organizatave të interesuara.
e dorëzuara nuk janë me karakter kofidencial. Komisioni Rregullator për energjetikë, së
Shtruesi është i obliguar t’i dorëzojë të dhënat paku në afat prej 5 (pesë) ditëve nga dita e për-
dhe dokumentet në vijim: fundimit të seancës përgatitore, do të mbajë
• Kërkesë për dhënien e vendimit të për seancë të rregullt në të cilën do të sjell vendim të
kohshëm për marrjen e statusit prodhues përkohshëm për marrjen e statusit të prodhuesit
i autorizuar, i nostrifikuar me nënshkrim të autorizuar të energjisë elektrike të prodhuar
dhe vulë prej udhëheqësit; nga burime të ripërtërishme të energjisë. Vendimi
• Vendim për regjistrim në Regjistrin qendror, i përkohshëm do të publikohet në Gazetën Zyrtare,
origjinali ose kopje të nostrifikuar në noter; ndërsa hyn në fuqi prej ditës së sjelljes.
• Dëshmi për plotësimin e kushtit (miratim i Në vendimin e përkohshëm theksohet fuqia
plotfuqishëm për ndërtim ose marrëveshje e elektrocentralit (gjegjësisht të njësive gjene-
për koncesion ose marrëveshje për part- ratore).
neritet publik privat) origjinali ose kopje e Komisioni Rregullator për energjetikë në
notifikuar në noter. vendimin e përkohshëm e përcakton afatin deri
54 CENTRALET ME ERË
për shfrytëzues të izoluar ose nëse planifikohet Kadastrës si dëshmi për të drejtën e pronësisë ose
impianti të shfrytëzohet vetëm për objekt për të drejtave të tjera për përdorimin e objektit (Ligji
prodhimin e energjisë elektrike, investitori mund për ndërtim, neni 87). Në rast se kërkesa e miratimit
të vendos që impianti: për përdorim është e pakompletuar, Ministria
− të projektohet dhe të zbatohet nga EVN e Transportit dhe Lidhjeve do t’i rekomandojë
Maqedoni, ose shtruesit që t’i dorëzojë dokumentet përkatëse
− të projektohet dhe zbatohet prej kompa- dhe të kompletuara në afat prej shtatë ditëve nga
nisë së autorizuar të listës së kompanive pranimi i kërkesës për leje për përdorim.
të përzgjedhura ne tender nga ana e EVN Komisioni i përbërë prej tre inxhinierëve
Maqedoni. të autorizuar për mbikëqyrje të emëruar prej
Ministrisë së Transportit dhe Lidhjeve duhet të
Nëse EVN Maqedoni konstaton se impian- bëjë kontroll teknik të ndërtimit pas pranimit
tin jostandard mund ta përdorin më shumë të kërkesës për miratimin për përdorim në afat
shfrytëzues të ardhshëm, impiantin e projekton prej 15 ditëve prej ditës së pranimit të kërkesës
dhe zbaton EVN. Në këtë rast, investitori paguan së plotë për miratimin për përdorim. Në rast të
shumë e cila është e barabartë me prodhimin prej hidrocentralit me fuqi instaluese deri në 1MW,
vlerës së përgjithshme të impiantit jostandard Komuna e jep miratimin për përdorim në bazë
dhe sasisë midis fuqisë së miratuar maksimale të raportit të kontrollit teknik të inxhinierit
të njëkohshme që i ndahet investitorit dhe vlerën të autorizuar për mbikëqyrje. Komisioni ose
e përgjithshme të fuqisë instaluese aktive të inxhinieri mbikëqyrës, përcakton në mënyrë
impiantit. përkatëse se:
Investitori i mbart shpenzimet e projektimit − objekti është ndërtuar në pajtueshmëri me
dhe/ose zbatimit të impiantit, të llogaritura në projektin themelor ose në rast të ndryshi-
pajtueshmëri me Metodologjinë për konstatimin meve gjatë ndërtimit, projektit në gjendje
e shpenzimeve për kyçje në sistemin distribuues, të zbatueshme dhe miratimit për ndërtim,
i cili është pjesë përbërëse e Rregullave të rrjetit − objekti është i sigurt dhe mund të përdoret.
për distribuim të energjisë elektrike.
Në qoftë se komisioni, ose inxhinieri për
4.9 Miratim për përdorim mbikëqyrje në mënyrë përkatëse, konstatojnë
çfarëdo mangësi të cilat do ta dëmtojnë stabilite-
Për ta lëshuar në përdorim në mënyrë zyrtare tin mekanik dhe rezistencën e objektit, mund të
hidrocentralin duhet miratim për përdorim. kërkojë prej investitorit t’i korrigjojë këto aspekte
Varësisht prej fuqisë instaluese të hidrocentralit, në afat prej 30 ditëve, ose mund të propozojë të
miratimin për përdorim e jep Ministrai e Trans- mos jepet miratimi për ndërtim (Ligji për ndërtim,
portit dhe Lidhjeve (për centrale me fuqi instaluese neni 89-92).
deri në 1 MW ose më shumë) ose Komuna e cila Në rast të raportit pozitiv të komisionit, ose të
e ka dhënë miratimin për ndërtim (për centralet inxhinierit për mbikëqyrje, Ministria e Transportit
me fuqi instaluese deri në 1 MW). dhe Lidhjeve, apo Komuna, në mënyrë përkatëse
Ministria e Transportit dhe Lidhjeve e jep mi- është e obliguar të japë miratim për përdorim në
ratimin për përdorim në bazë të projektit themelor afat prej 15 ditëve prej ditës së kontrollit teknik të
(apo projektit në gjendje të zbatueshme përderisa ndërtesës. Shpenzimet për kryerjen e kontrollit
gjatë realizimit janë bërë ndryshime të mëdha), teknik dhe dhënies së miratimit për përdorim i
raportit të kontrollit teknik dhe certifikatës prej bart investitori.
56 CENTRALET ME ERË
• Vërtetim nga Regjistri qendror se shtru- 50 ditëve prej ditës së fillimit të procedurës. Nëse
esit dhe përfaqësuesit të autorizuar nuk komisioni rregullator për energjetikë konstaton
u është shqiptuar ndalesë për kryerjen e prej seancës përgatitore si dhe prej dokumenta-
profesionit, veprimtarisë dhe obligimeve cionit, se janë plotësuar kushtet për marrjen e
si dhe vërtetim se nuk janë të dënuar për licencës do të caktojë seancë të rregullt në afat
ndonjë vepër penale. prej 10 ditëve që të sjell vendim për dhënien e
licencës.
Përveç dokumenteve të lartpërmendura Komisioni Rregullator për energjetikë e
shtruesi është i obliguar të dorëzojë edhe doku- shpall vendimin dhe licencën për kryerjen e
mentacion shtesë në lidhje me teknologjinë aktiviteteve energjetike në Gazetën Zyrtare.
specifike për prodhimin e energjisë elektrike Përderisa licenca është e dhënë për objekt
në pajtueshmëri me nenin 14 të Rregullores për pa leje për përdorim ose raport për pranim të
licenca për kryerjen e aktiviteteve energjetike. kryer teknik, ndërsa investitori ka siguruar leje
Komisioni rregullator për energjetikë do për përdorim ose raport për pranim të kryer
ta shqyrtojë kërkesën për marrjen e licencës teknik, është e nevojshme investitori të dorëzojë
dhe dokumentacionin e dorëzuar dhe në afat dokumentet në pajtueshmëri me nenin 32 të
prej 8 ditëve do të sjellë Konstatim. Përderisa Rregullores për kryerjen e aktiviteteve energjeti-
dokumentacioni për marrjen e licencës është ke. Pas dokumentacionit të dorëzuar Komisioni
në pajtueshmëri me Rregulloren për licenca për rregullator për energjetikë në afat prej 8 ditëve
kryerjen e aktiviteteve energjetike si dhe ligjet prej dorëzimit do të sjellë vendim për hyrjen në
e tjera, Komision Rregullator për energjetikë fuqi të licencës dhënë paraprakisht.
do ta detyrojë shtruesin të përgatit njoftim për Pas marrjes së licencës për prodhimin e
kërkesën dhe në afat prej 3 ditëve dhe ta dorëzojë energjisë elektrike, investitori ka mundësi, nëse
deri te Komisioni Rregullator për energjetikë për ekzistojnë kushte teknike, të prodhojë dhe të
miratim. Në rast se dokumentacioni i dorëzuar ka shesë energji elektrike para marrjes së statusit
mangësi formale dhe të tjera atëherë Komisioni prodhues i autorizuar i energjisë elektrike (shiko
Rregullator për energjetikë do ta detyrojë shtrue- 4. 12) dhe para nënshkrimit të marrëveshjes për
sin e kërkesës në afat prej 15 ditëve t’i mënjanojë blerjen e energjisë elektrike prodhuese me SH.A
mangësitë dhe ta kompletojë dokumentacionin MEPSO (shiko 4.13). Për këtë qëllim, investitori
në pajtueshmëri me Rregulloren për licenca për duhet të bëjë marrëveshje me:
kryerjen e aktiviteteve energjetike. − operatorin e sistemit distribuues
Investitori është i obliguar ta shpall kërkesën − me ndonjë furnizues të energjisë elektrike,
për dhënien e licencës për prodhimin e energjisë ose
elektrike nga burime të ripërtëritshme me shpen- − tregtar me energji elektrike
zime të veta së paku në dy gazeta të përditshme
në të dy gjuhët zyrtare. Shpallja bëhet me qëllim Marrëveshja e këtillë mund të jetë me
që të publikohet dhënia e licencës dhe të ftohen kohëzgjatje të kufizuar, përkatësisht deri sa
të gjitha palët e interesuara të komentojnë për të merret statusi i prodhuesit të autorizuar të
dhënien e licencës dhe ta prezentojnë rastin e energjisë elektrike, ose me kohëzgjatje të paku-
tyre. fizuar, përderisa investitori nuk arrin të marrë
Pas shpalljes së kërkesës, Komisioni rre- statusin prodhues i autorizuar i energjisë elektrike
gullator për energjetikë do të caktojë seancë ose zgjedh të heqë dorë prej statusit.
përgatitore e cila duhet të mbahet në afat prej
58 CENTRALET ME ERË
4.11. Regjistrimi i objektit në pletuar dhe i saktë dhe se të gjitha kushtet për
Regjistrin e objekteve marrjen e statusit të prodhuesit të autorizuar janë
për prodhimin e energjisë të plotësuara, ai do të sjellë vendim për regjistri-
elektrike nga burime të min e shtruesit në Regjistrin e prodhuesve të auto-
ripërtëritshme të energjisë rizuar të energjisë elektrike në afat prej 15 ditëve
prej datës së dorëzimit të kërkesës. Agjencia për
Investitori duhet ta regjistrojë hirocentralin energjetikë mund të vendos ta shqyrtoj objektin
e tij në Regjistrin e objekteve për prodhimin e para se ta japë vendimin. Agjencia për energjetikë
energjisë elektrike me burime të ripërtëritsh- ia dorëzon investitorit Vendimin për regjistrim
me të energjisë të cilin e drejton Agjencia për në Regjistrin e prodhuesve të autorizuar për
energjetikë. Për këtë qëllim, investitori duhet energji elektrike në afat prej tre ditëve prej datës
të dorëzojë kërkesë deri te Agjencia për energje- së sjelljes së vendimit. Investitori regjistrohet
tikë për regjistrim në Regjistrin e objekteve për me numrin e vetëm të regjistrit i cili nuk mund
prodhimin e energjisë elektrike prej burimeve të ndryshohet apo të transferohet (Rregullorja
të ripërtëritshme të energjisë, bashkë me doku- për burime të ripërtëritshme të energjisë, neni 9).
mentet në vijim:
1. Miratim për përdorimin e objektit energjetik 4.12. Marrja e statusit të
ose raport për kontrollin e kryer teknik, në prodhuesit të autorizuar
rast kur nuk është i nevojshëm miratimi
për përdorim dhe vërtetimi i operatorit të Pas marrjes së vendimit të përkohshëm për marrjen
sistemit përçues për energji elektrike me të e statusit të prodhuesit të autorizuar të energjisë
cilin vërtetohet se objekti i energjisë është elektrike të prodhuar prej burimeve të ripërtërish-
i kyçur në sistemin përkatës (përçues ose me të energjisë, investitori duhet të dorëzojë
distributiv), kërkesë për marrjen e vendimit për marrjen e
2. Hartë topografike me përmasë 1:25.000 ku statusit prodhues i autorizuar i energjisë elektrike
është i shfaqur lokacioni i hidrocentralit, të prodhuar prej burimeve të ripërtërishme të
3. Prezantim skematik të hidrocentralit dhe energjisë dhe njëkohësisht të dorëzojë kërkesë për
i pajisjeve të instaluara, veçanërisht të shfrytëzimin e tarifës së autorizuar të energjisë
pajisjeve për matje, dhe elektrike të prodhuar prej burimeve të ripërtërish-
4. Kopje të licencës për prodhimin e energjisë me të energjisë. Pas kësaj, elektrocentrali duhet
elektrike (Rregullorja për burime të lëshohet në përdorim në afatin e caktuar në vendi-
ripërtëritshme të energjisë, neni 8). min e përkohshëm dhe shtruesi duhet të posedojë
licencë për kryerjen e aktiviteteve energjetike
Nëse Komisioni rregullator për energjetikë – prodhimin e energjisë elektrike për elektro-
konstaton se kërkesa nuk është e plotë, ai do ta centralin për të cilin kërkohet statusi prodhues
njoftojë shtruesin dhe do t’i bëjë thirrje që ta i autorizuar i energjisë elektrike të prodhuar
kompletojë me dokumentacionin e duhur në afat prej burimeve të ripërtërishme të energjisë.
prej 30 ditëve prej ditës së dorëzimit të njoftimit. Kërkesat dorëzohen deri te Komision Rregul-
Nëse shtruesi nuk e kompleton dokumentacionin lator për energjetikë në një ekzemplar në formë të
në afatin e caktuar, Agjencia për energjetikë do shkruar, si formular i plotësuar për kërkesë për
ta refuzojë kërkesën si të pakompletuar. lëshimin e vendimit për marrjen e statusit prodhu-
Nëse Agjencia për energjetikë konstaton se es i autorizuar, i nostrifikuar me nënshkrim dhe
kërkesa dhe dokumentacioni shtesë është i kom- vulë të shtruesit (Formulari KVPA), si dhe formular
CENTRALET ME ERË 59
i plotësuar për kërkesë për shfrytëzimin e tarifës nari, sipas bursës së mesme të Bankës Popullore
së autorizuar, i nostrifikuar me nënshkrim dhe në ditën e shtrimit të kërkesave.
vulë të shtruesit (formulari KSHTA). Procedurat për lëshimin e vendimit për
Shtruesi është i obliguar t’i ndajë dhe t’i marrjen e prodhuesit të autorizuar dhe sjelljen
shënojë në mënyrë të veçantë dokumentet të cilat e vendimit për shfrytëzimin e tarifës së autorizuar
janë me karakter kofidencial. Në të kundërtën do fillojnë në ditën e pranimit të kërkesës në arkivin
të konsiderohet se dokumentet e dorëzuara nuk e Komisionit Rregullator për energjetikë.
janë me karakter kofidencial. Pas marrjes së kërkesave, Komisioni Rre-
Kërkesat dorëzohen për shfrytëzimin e tarifës gullator për energjetikë përcakton nëse është
së autorizuar e cila ka vlejtur në ditën e sjelljes së dorëzuar dokumentacioni i nevojshëm për sjelljen
vendimit të përkohshëm për marrjen e statusit e vendimit dhe sjelljen e vendimit, si dhe nëse
prodhues i autorizuar i energjisë elektrike. dokumentacioni është dorëzuar në formë dhe
Së bashku me kërkesën, shtruesi është i obligu- mënyrë të caktuar. Komisioni rregullator për
ar t’i dorëzojë të dhënat dhe dokumentet në vijim: energjetikë në afat prej 5 (pesë) ditëve nga dita
• Projekt për gjendjen e zbatueshme në pajtim e pranimit të kërkesave, do të kërkojë vërtetim
me Ligjin për ndërtim, nëse janë bërë ndrys- nga Agjencia për Energjetikë se elektrocentrali
hime gjatë ndërtimit; është ndërtuar dhe i plotëson kushtet specifike
• Vendim për regjistrim në Regjistrin e elektro- dhe fuqinë instaluese të përcaktuar me Dekretin
centraleve të cilat shfrytëzojnë burime të të cilat kanë qenë në fuqi në ditën e lëshimin të
ripërtërishme të energjisë për prodhimin vendimit të përkohshëm për marrjen e statusit
e energjisë elektrike, lëshuar nga Agjencia të prodhuesit të autorizuar.
për Energjetikë, në pajtim me Rregulloren Agjencia për Energjetikë obligohet ta lë-
për burime të ripërtërishme të energjisë; shojë vërtetimin në afat jo më të gjatë se 15
• Dëshmi se është paguar kompensimi në (pesëmbëdhjetë) ditë nga dita e shtrimit të kërkesës
pajtim me nenin 13-a të Rregullores për deri te Komisioni Rregullator për energjetikë.
prodhues të autorizuar për energji elektrike Për lëshimin e vërtetimit, Komisioni rre-
të burimeve të ripërtërishme të energjisë; gullator për energjetikë i paguan kompensim
• Deklaratë për besueshmërinë e kërkesës Agjencisë për Energjetikë, sipas tarifores së sjellë
dhe të dhënat detajuese, të nënshkruar nga Agjencia për energjetikë, i përgatitur në bazë
nga personi i autorizuar për përfaqësimin e të shpenzimeve të Agjencisë për Energjetikë në
shtruesit të regjistruar në Regjistrin qendror. procedurën për lëshimin e vërtetimit.
Nëse Komisioni Rregullator për energjetikë
Dokumentet duhet të jenë origjinale ose kopjet përcakton se kërkesat dhe dokumentacioni është
e dokumenteve origjinale të jenë të nostrifikuara i kompletuar dhe se nuk ka mangësi dhe se vërte-
në noter. timi i lëshuar nga Agjencia për Energjetikë është
Me kërkesën, shtruesi në mënyrë të obliguar pozitiv, në afat prej 20 (njëzetë) ditëve nga dita e
duhet të shfaq dëshmi se në llogarinë e Komisionit pranimit të kërkesës do të sjellë konstatime për
rregullator për energjetikë është paguar kompen- rregullshmërinë e kërkesave dhe vazhdimin e
sim i pakthyeshëm në të holla për shpenzimet e procedurave. Nga një ekzemplar, Komisioni rre-
bëra në procedurë (kompensimin të cilin Komisi- gullator për energjetikë e dorëzon deri te shtruesi.
oni Rregullator për energjetikë duhet t’ia paguaj Komisioni rregullator për energjetikë, në
Agjencisë për Energjetikë sipas tarifores së sjellë lidhje me kërkesat e shtruara, do të caktojë seancë
nga Agjencia për Energjetikë ) në kundërvlerë de- përgatitore e cila duhet të mbahet në afat i cili
60 CENTRALET ME ERË
nuk mund të jetë më i gjatë se 35 (tridhjetë e pesë) ke të prodhuar nga prodhuesit e autorizuar të
ditë nga dita e pranimit të kërkesave. Ftesa për energjisë elektrike në pajtueshmëri me kontratën,
pjesëmarrje në seancën përgatitore bashkë me pro- që është në pajtueshmëri me Ligjin për energjetikë,
pozimin e vendimit për fitimin e statusit të prodhu- vendimin për shfrytëzimin e tarifave të autori-
esit të autorizuar dhe propozimit të vendimit për zuara i dhënë prej Komisionit rregullator për
shfrytëzimin e tarifës së autorizuar të energjisë energjetikë dhe Rregullave të tregut të energjisë
elektrike të prodhuar nga burimet të ripërtëritsh- elektrike. Investitori duhet të dorëzojë kërkesë
me të energjisë dorëzohet më së voni 7 (shtatë) ditë për nënshkrimin e marrëveshjes për blerjen e
para mbajtjes së seancës përgatitore. Për prani dhe energjisë elektrike deri te MEPSO.
pjesëmarrje në seancën përgatitore, Komisioni M E P S O obl i g oh e t t a n ë n sh k r u a j ë
rregullator për energjetikë e fton shtruesin, si marrëveshjen për blerjen e energjisë elektrike
dhe përfaqësuesit e autorizuar të ndërmarrjeve, në afat prej 30 (tridhjetë) ditëve prej datës së
institucioneve dhe organizatave të interesuara. pranimit të kërkesës. Marrëveshja për blerjen
Komisioni rregullator për energjetikë më së e energjisë elektrike duhet hyjë në fuqi ditën e
voni në afat prej 5 (pesë) ditëve nga dita e përfun- dhënies së Vendimit për marrjen e statusit të
dimit të seancës përgatitore do të mbajë seancë të prodhuesit të autorizuar të energjisë elektrike prej
rregullt në të cilën do të sjellë vendim për marrjen anës së Komisionit rregullator për energjetikë.
e statusit të prodhuesit të autorizuar të energjisë Investitori mund të vendos ta prish
elektrike të prodhuar nga burimet të ripërtëritsh- marrëveshjen për blerjen e energjisë elektrike
me të energjisë dhe vendim për shfrytëzimin e ta- me çka do ta humbas statusin e prodhuesit të
rifës së autorizuar të energjisë elektrike të prodhu- autorizuar të energjisë elektrike dhe të drejtën që
ar nga burimet e ripërtëritshme të energjisë. përsëri ta marrë këtë status. (Ligji për energjetikë,
Vendimet publikohen në Gazetën Zyrtare neni 153).
dhe në ueb-faqen e Komisionit Rregullator për Investitori është i obliguar ta shesë të gjithë
energjetikë. sasinë prodhuese të energjisë elektrike të MEPSO
Me ditën e hyrjes në fuqi të vendimeve, Komisi- dhe të dorëzojë plane për prodhimin e energjisë
oni Rregullator për energjetikë i shënon të dhënat elektrike deri te MEPSO.
e bartësit të vendimit dhe elektrocentralit si dhe Ky hap e shënon fundin e procesit për aplikim.
të dhënat për tarifën e autorizuar në Regjistrin Pas marrjes së statusit të prodhuesit të autorizuar,
e prodhuesve të autorizuar. investitori mund t’i zbatojë dhe përdorë tarifat
Vendimet e Komisionit Rregullator për e autorizuara të përcaktuara në Dekretin e ta-
energjetikë i dorëzon deri te shtruesi, operatori rifave të autorizuara të energjisë elektrike (Neni
i tregut të energjisë elektrike dhe deri te Agjencia 7). Tarifa e saktë e autorizuar e cila përdoret në
për Energjetikë. objekt për prodhimin e energjisë elektrike varet
prej sasisë mujore të prodhuar dhe të shitur të
4.13. Marrëveshje për blerjen energjisë elektrike në çdo bllok. Varësisht prej
e energjisë elektrike me sasisë të prodhuar të energjisë elektrike për
operatorë e tregut të çdo muaj, tarifa e autorizuar faktike e cila është
energjisë elektrike e zbatueshme për objekt mund të ndryshojë.
Tarifat e autorizuara zbatohen për një periudhë
Operatori i sistemit elektropërçues (MEPSO) prej 20 viteve.
është i obliguar ta blejë të gjithë energjinë elektri-
CENTRALET ME ERË 61
Ligji për energjetikë (Gazeta zyrtare nr. 16/2011, Dekret për përcaktimin e projekteve dhe për kri-
136/2011, 79/2013, 164/2013, 41/2014 dhe teret në bazë të së cilave përcaktohet nevoja
151/2014) për zbatimin e procedurës për vlerësimin e
Ligji për ujërat (Gazeta zyrtare nr. 87/2008, 6/2009, ndikimit mbi mjedisin jetësor (Gazeta zyrtare
161/2009, 83/2010, 51/2011, 44/2012, 23/2013, nr. 74/2005)
163/2013, 180/2014) Rregullore për formën dhe përmbajtjen e elabo-
Ligji për pyjet (Gazeta zyrtare nr. 64/2009, 24/2011, ratit për mbrojtjen e mjedisit jetësor, proce-
53/2011, 25/2013, 79/2013, 147/2013, 43/2014, durën për miratimin e tyre si dhe mënyrën
160/2014, 33/2015 dhe 44/2015) e udhëheqjes së regjistrit të elaborateve të
Ligji për koncesione dhe partneritet privat publik miratuara (Gazeta zyrtare nr. 50/2009)
(Gazeta zyrtare nr. 6/2012, 144/2014) Rregullore për formën dhe përmbajtjen e kërkesës,
Ligji për mjedis jetësor (Gazeta zyrtare nr. 53/2005, dokumentacionit të nevojshëm dhe formu-
81/2005, 24/2007, 159/2008, 83/2009, 48/2010, larin e Vendimit për zbatimin e ndërtimeve
124/2010, 51/2011, 123/2012, 93/2013, 187/2013, përkatësisht vendosjen e paisjeve për të cilat
42/2014) nuk është i nevojshëm miratimi për ndërtim.
Ligji për ndërtim (Gazeta zyrtare nr. 130/2009, (Gazeta zyrtare, nr 147/2009)
124/2010, 18/2011, 36/2011, 54/2011, 13/2012, Rregullore për licenca për kryerjen e veprimtari-
144/2012, 25/2013, 79/2013, 137/2013, 163/2013, ve energjetike (Gazeta zyrtare nr. 143/2011,
27/2014, 28/2014, 42/2014, 115/2014, 149/2014, 78/2013 dhe 33/2015)
187/2014 dhe 44/2015) Dekret për tarifa të autorizuara për energji elektrike
Ligji për tokë bujqësore (Gazeta zyrtare nr. 135/07, (Gazeta zyrtare nr. 56/2013)
18/11, 148/11, 95/12, 79/13, 87/13, 106/13, 164/13, Vendim për fuqinë instaluese të përgjithshme të
39/14, 130/14 dhe 166/2014) prodhuesve të autorizuar të energjisë elektrike
Ligji për planifikim hapësinor dhe urbanistik (Gazeta prej secilit burim ripërtëritës të energjisë
zyrtare nr. 199/2014 dhe 44/2015) (Gazeta zyrtare nr. 56/2013 dhe 10/2014)
Ligji për pronësi dhe të drejta të tjera pronësore Rregullore për burime të ripërtëritshme të energjisë
(Gazeta zyrtare nr. 18/2001, 92/2008, 139/2009 (Gazeta zyrtare nr. 113/2011)
dhe 35/2010) Rregullore për prodhues të autorizuar të energjisë
Dekret për mënyrën dhe procedurën e tjetërsimit, elektrike nga burime të ripërtëritshme të
dhënien me qira afatgjate dhe qira afatshkur- energjisë (Gazeta zyrtare nr. 18/2012, 97/2012
tre, toka në pronësi të shtetit, me ankand dhe 63/2013)
publik, përmes grumbullimit të ofertave dhe Rregulla për tregun e energjisë elektrike (Gazeta
me marrëveshje të drejtpërdrejt, lartësinë zyrtare nr. 38/2014, 57/2014 dhe 194/2014)
e shpenzimeve të procedurës për tjetër- Rregulla të rrjetit për distribuimin e energjisë
sim dhe dhënien me qira si dhe lartësinë e elektrike (Gazeta zyrtare nr. 87/2012, 30/2014,
çmimit të tokës dhe qirasë (Gazeta zyrtare 161/2014, 189/2014 dhe 50/2015)
nr. 147/2008, 71/2009, 16/2009, 162/2009, Rregulla të rrjetit për përçimin energjisë elektrike
113/2010, 148/2010, 172/2010 dhe 40/2011) (2015)