ПРИРАЧНИК

за постапките за развој и изградба на електрани


за производство на електрична енергија
од обновливи извори на енергија
ВЕТЕРНИ ЕЛЕКТРАНИ
2 ВЕТЕРНИ ЕЛЕКТРАНИ

Содржина

1. Вовед................................................................................................................................ 3
2. Преглед на применливите повластени тарифи за ветерни електрани......................... 4
3. Детален дијаграм за постапката и документите за изградба........................................ 5
4. Преглед на чекорите, постапките и документите......................................................... 6
4.1. Основни предуслови: Основање на компанија...................................................... 6
4.2. Мерење на потенцијалот на ветрот........................................................................ 6
4.3. Користење на земјиште...........................................................................................7
4.4. Согласност за приклучок на преносниот или дистрибутивниот систем.............. 8
4.5. Студија за оценка на влијанието врз животната средина..................................... 9
4.6. Овластување за изградба на нови објекти за производство
на електрична енергија (во случај на ветерни електрани
со инсталирана моќност над 10 МW).....................................................................10
4.7. Одобрение за градба.............................................................................................. 11
4.8. Стекнување на привремен статус на повластен производител...........................12
4.9. Проектирање и изведба на приклучокот..............................................................13
4.10. Одобрение за употреба..........................................................................................14
4.11. Лиценца за производство на електрична енергија..............................................14
4.12. Упис на објектот во Регистарот на објекти за производство
на електрична енергија од обновливи извори на енергија.................................. 17
4.13. Доделување на статус на повластен производител.............................................. 17
4.14. Договор за откуп на електрична енергија со оператор
на пазарот на електрична енергија.......................................................................19
5. Обезбедување на гаранции за потекло на електрична енергија
произведена од обновливи извори на енергија........................................................... 20
6. Адреси и податоци за контакт на надлежните институции.........................................21
7. Релевантно законодавство и регулаторни акти........................................................... 22

Оваа публикација е изготвена со помош на Европската Унија. Содржината на оваа публикација е единственa
одговорност на ATC Consultants и нејзините партнери во конзорциумот и на никаков начин не ги рефлектира
гледиштата на Европската Унија.
ВЕТЕРНИ ЕЛЕКТРАНИ 3

1. Вовед

Овој Прирачник има за цел да обезбеди детални НАПОМЕНА:


насоки за инвеститорите во процесот на развој
и спроведување на проекти за обновливи извори Овој Прирачник не се осврнува на прашања
на енергија, поконкретно ветерни електрани. поврзани со:
Прирачникот не претставува исцрпен, детален и − основање на компанија или основање на
длабински преглед. За подетални информации странски подружници земјата корисник
осврнете се на релевантното законодавство на проектот и нивното работење;
и регулаторните акти коишто се наведени на − добивање на одобрение за градење,
крајот на овој Прирачник. − добивање на лиценци за стручен кадар и
Прирачникот е структуриран во три дела. други работни и социјални дозволи,
Во првиот дел е даден преглед на примен- − сопственост на земјиште, експропријација
ливите повластени тарифи за сите проекти за и други имотни права,
обновливи извори на енергија, вклучувајќи ги и − оданочување,
повластените тарифи за ветерните електрани. − Правилник за државна помош, и сл.
Во вториот дел е даден детален дијаграм
на постапките за изградба и потребната доку- Сепак, имајте предвид дека ова се важни
ментација. прашања кои секој инвеститор треба внима-
Во третиот дел е даден детален преглед на телно да ги анализира кога подготвува проект
релевантните процедури и барања за изградба, за ветерна електрана.
пуштање во употреба и функционирање на
ветерните електрани. Читателот го упатуваме
постојано да го консултира овој дел и деталниот
дијаграм, којшто е даден во вториот дел.
На крајот од брошурата е даден список
на надлежните органи со нивните адреси и
податоци за контакт, како и список на сите
релевантни закони и други регулаторни акти.

Овој Прирачник е наменет да служи како алатка за информирање и ориентација на идните


инвеститори во ветерни електрани. Сепак, наша препорака е инвеститорите директно
да контактираат и да ги консултираат надлежните органи пред да преземат какви било
официјални активности за развој и изградба на ветерни електрани и да ги имаат предвид
применливите законодавни и регулаторни акти.
4 ВЕТЕРНИ ЕЛЕКТРАНИ

2. Преглед на применливите повластени


тарифи за хидроелектрани

Повластената тарифа за електрична енергија која ја произведуваат и продаваат ветерните


електрани (кои се стекнале со статус на повластен производител) се утврдени во Уредбата за
повластени тарифи за електрична енергија (Службен весник бр. 56/2013) и е како што следува:
Квотата на ветерни електрани кои можат да користат повластени тарифи е утврдена во

Инсталирана моќност на ветерната електрана 0 – 50 MW

Повластена тарифа(€¢/kWh) 8.9

Времетраење повластената тарифа 20 години

Одлуката за вкупната инсталирана моќност на повластените производители на електрична


енергија произведена од секој одделен обновлив извор на енергија (Службен весник бр. 56/2013
и 10/2014) како што следува:
Во моментот на подготовка на овој Прирачник па до 31 декември 2016 година, 13,2 MW беа

до 31 декември до 31 декември до 31 декември


Период
2016 година 2020 година 2025 година
Квота (инсталирана моќност
65 MW 100 MW 150 MW
на ветерните електрани)

се уште на располагање за ново изградените ветерни електрани1. Квотата ќе се зголеми за 35


MW во 2017 година, и за 50 MW во 2021 година.

Потенцијалните инвеститори треба да знаат дека на акционерското друштво во државна сопственост


1

ЕЛЕМ му беше доделена лиценца за изградба на ветерни електрани со вкупна инсталирана моќност
од 50 MW. ЕЛЕМ искористи 36,8 MW од својата лиценца со пуштање во употреба на ветерниците во
Богданци во 2013 год. ЕЛЕМ планира да ги искористи преостанатите 13,2 MW за ветерни електрани во
периодот по 2016 год.
3. Детален дијаграм за постапката и документите за изградба
Времетраење Времетраење
Години Година 1 Година 2 Година 3 Година 4 Година 5
Месеци 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Постапка Надлежен орган
4.1 Основање на компанија 6.1
Мерење на потенцијалот на
4.2 ветрната енергија 6.3 Мерење на потенцијалот на ветерната енергија (најмалку 2 години ) 1
6.1, 6.8, 6.9 или
4.3 Пренамена на земјиштето 2
општината
Согласност за приклучок на
4.4 преносниот или 6.5 или 6.6
дистрибутивната мрежа
Студија за влијанието врз
4.5 6.7 или општината
животната средина
Овластување за изградба на
4.6 6.1 3
(ветерна) електроцентрала
4.7 Одобрение за градба 6.8 или општината 4
ПРОЦЕС НА ГРАДБА
Стекнување на привремен статус
4.8 6.4
на повластен производител
Проектирање и изведба на 6.5, 6.6 или овластена
4.9 приклучокот 5
компанија

4.10 Употребна дозвола 6.8 или општината

Лиценца за производство на
4.12 6.4
електрична енергија
Упис на објектот во Регистарот
ВЕТЕРНИ ЕЛЕКТРАНИ

на објекти за производство на
4.13 6.3
електрична енергија од
обновливи извори
Доделување на статус на
4.14. повластен производител 6.4

Договор за откуп на електрична


4.15 енергија со оператор на 6.5
пазарот на електрична енергија
Почеток на производство и
продажба на електрична
енергија

Легенда:

:
Ризик 1: Резултатите од мерењето може да не ја поддржат Ризик 4: Неможност да се добие одобрение за градба или
Времетраење на постапката 1 4
изводливоста на проектот за таа локација непредвидено доцнење

Времетраење на мерењето на потенцијалот на ветерот за Ризик 2: Неможност да се добие право на користење на државно Ризик 5: Зголемување на трошоците за приклучок доколку не е
производство на електрична енергија (минимум две години) 2 земјиште, доцнење и несигурност на исходот и трошоците 5 можно да се изврши поврзување на најблискиот приклучок

Ризик 3: Неможност да се исполнат барањата за доделување


Градежни работи 3 Почеток на производство и продажба на електрична енергија
овластување за изградба на нова ветерна електрана
5
6 ВЕТЕРНИ ЕЛЕКТРАНИ

4. Преглед на чекорите, постапките


и документите
4.1. Основни предуслови: 4.2. Мерење на потенцијалот
Основање на компанија на ветрот

Производство на електрична енергија можат Документиран и соодветен потенцијал на ветрот


да вршат домашни и странски лица врз основа е потребен за изградба и одржливо функциони-
на лиценца издадена од страна на Регулатор- рање на ветерната електрана. Инвеститорите
ната комисија за енергетика. За да се стекнат треба да спроведат сопствено мерење на кон-
со лиценца за производство на електрична кретните локации.
енергија, странските лица треба да основаат За мерење на потенцијалот на ветрот е по-
подружница регистрирана во трговскиот реги- требно одобрение од Агенцијата за енергетика.
стар што го води Централниот регистар (Закон Кон барањето за издавање одобрение за мерење
за енергетика, член 5). Ова барање се проверува на потенцијалот на ветрот инвеститорот треба
со увид во изводот од Централниот регистар. да ја приложи следната документација:
Производството на електрична енергија – биланс на состојба/тековна состојба од
не може да започне пред добивањето на со- Централниот регистар не постара од шест
одветната лиценца. Лиценцата за енергетски месеци;
дејности се издава за период од три до 35 – прелиминарна физибилити студија во
години во зависност од видот на енергетска- која е дадена анализа на техничкото и
та дејност, видот и обемот на обврската за финансиското работење на ветерната
обезбедување на јавна услуга во вршењето електрана и којашто се базира на претход-
на енергетската дејност, обемот на средства- ните мерења на потенцијалот на ветрот;
та потребни за извршување на енергетската – геодетски елаборат (со размер 1:25.000)
дејност, времетраењето на правото за корис- за земјишната парцела на која ќе биде
тење/концесијата на соодветниот енергетски поставена опремата за мерење на ветрот
ресурс, како и конкретни барања на вршителот (за секоја локација за мерење е потребен
на енергетската дејност. Вообичаеното вре- посебен геодетски елаборат),
метраење на лиценцата за производството – топографска мапа (со размер 1:25.000) за
на електрична енергија изнесува 35 години. земјишната парцела каде што ќе се врши
На исто лице може да му се издадат повеќе мерењето.
лиценци за вршење на енергетски дејности
(Закон за енергетика, член 37). Доколку Агенцијата за енергетика утврди
Ветерна електрана со вкупна инсталира- дека барањето не е целосно, ќе го задолжи под-
на моќност за производство на електрична носителот да достави комплетна и коригирана
енергија помала или еднаква на 10 МW може документација во рок од 15 дена од денот на
да се изгради без „овластување за изградба на известувањето. Агенцијата за енергетика ќе го
нови објекти за производство на електрична отфрли барањето доколку подносителот не ги
енергија“ кое го издава Владата на предлог исполни барањата од известувањето. Доколку
на Министерството за економија. (Закон за Агенцијата за енергетика утврди дека барањето
енергетика, член 49) е комплетно и точно ќе му издаде одобрение за
ВЕТЕРНИ ЕЛЕКТРАНИ 7

мерење на потенцијалот на ветрот на подноси- тето во зоната на аеродромот и земјиштето во


телот во рок од 30 дена од денот на доставување негова непосредна близина (Службен весник
на барањето и ќе го објави на својата веб страна. бр. 130/2007 и 156/2012).
Одобрението се издава со важност од една
година, но може да се продолжи за уште три 4.3. Користење на земјиште
години. Доколку биде потребно продолжување
на одобрението, инвеститорот треба да доста- Најчесто, земјиштето коешто е соодветно за
ви барање за продолжување до Агенцијата за изградба на ветерни електрани е земјоделско
енергетика кон кое ќе приложи образложение земјиште (пасишта, обработливо земјиште,
за потребата за продолжување на мерењето и шуми или слично) во државна сопственост.
доказ дека опремата за мерење на потенцијалот Во тој случај, инвеститорот треба да побара
на ветрот е поставена и работи. иницирање на две постапки:
За една локација може да се издаде само 1. Пренамена на земјоделско во градежно
едно одобрение за мерење на потенцијалот на земјиште, и
ветрот. Одобрението се издава за површина од 2. Откуп, долгорочен закуп или договор за
0,4 м2 за 1 MW инсталирана моќност на идната концесија за користење на земјиштето.
ветерна електрана. Најмалото растојание помеѓу
две мерни локации може да биде 2 км. Доколку Доколку земјишната парцела(-и) на која
повеќе инвеститори се заинтересирани за ме- инвеститорот има намера да гради ветерна
рење на потенцијалот на ветрот на една лока- електрана е класифицирана како земјодел-
ција, одобрение за мерење му се издава на инвес- ско земјиште (обработливо земјиште, шуми,
титорот кој прв поднел барање со комплетна и пасишта или слично), инвеститорот може да
точна документација („прв дојден, прв услужен“). достави барање до Министерството за транс-
За поставувањето на опрема за мерење на порт и врски или до Општината, во зависност
потенцијалот на ветрот не е потребно одобрение од случајот, да побара од Министерството за
за градење. Сепак, за поставувањето на таква земјоделство, шумарство и водостопанство да
опрема потребно е решение од Министерството изврши трајна пренамена на соодветното земјо-
за транспорт и врски во согласност со Правил- делско земјиште во градежно земјиште (Закон за
никот за формата и содржината на барањето, земјоделско земјиште, член 49). Времетраењето
потребната документација и образецот на Ре- на оваа постапка зависи од сложеноста на
шението за изведување на градбите односно подготовката и разгледувањето на проектната
поставување на опремата за кои не е потребно документација. Трошоците за обезбедување на
одобрение за градење. Исто така, за поставу- проектна документација ги сноси инвеститорот.
вањето на опрема за мерење на потенцијалот Освен ако земјишната парцела(-и) на која
на ветрот потребна е согласност од Агенцијата инвеститорот има намера да постави опрема
за цивилна воздушна пловидба во согласност за мерење на потенцијалот на ветрот не е во
со Правилникот за условите за поставување, приватна сопственост, инвеститорот треба
градба и обележување на објекти, инсталации и да го купи земјиштето, да потпише договор
уреди во зоната на аеродромот, објекти и уреди за долготраен закуп со Владата или да добие
за контрола на летањето, и објекти надвор од концесија за користење на земјиште (Закон за
зоната на аеродромот коишто можат да влијаат градежно земјиште, членови 13 – 40). Постапките
на безбедноста на воздушниот сообраќај и за отуѓување, давање под долготраен закуп и
условите и начинот на обработка на земјиш- концесија на градежно земјиште во државна
8 ВЕТЕРНИ ЕЛЕКТРАНИ

сопственост се врши со јавно наддавање, што МЕПСО издава согласност за приклучување на


носи ризик да не се победи на наддавањето за преносната мрежа во коешто е утврдено:
конкретната земјишна парцела. − Техничкото решение за приклучок,
Доколку земјишната парцела е во приватна − Технички спецификации за опремата и
сопственост, инвеститорот и сопственикот на работите за изградба на приклучокот,
земјиштето можат заедно да се договорат за − Услови за користење на преносниот сис-
отуѓувањето, долготрајниот закуп или правото тем,
на користење на земјиштето. − Проценети трошоци за изградба на при-
клучокот (Мрежни правила за пренос на
4.4. Согласност за приклучок електрична енергија, член 70).
на преносниот или Објектите за производство на енергија
дистрибутивниот систем со инсталирана моќност до 10 MW можат се
приклучат на преносната мрежа. Во тој слу-
Објектите за производство на енергија со инста- чај барањето за приклучок се поднесува до
лирана моќност од најмалку 10 MW директно операторот на дистрибутивниот систем, (ЕВН
се поврзуваат на преносната мрежа (Мрежни Македонија) во почетната фаза на градежните
правила за пренос на електрична енергија, работи. Барањето треба да се достави на обра-
член 57). Со оглед дека повеќето ветерни елек- зецот БСП-2, којшто можете да го најдете во
трани ќе бидат со инсталирана моќност од над корисничките енергетски центри на ЕВН или
10 MW, прво ќе ја презентираме постапката да го преземете од веб страната на ЕВН.
за добивање согласност за приклучување на Во прилог на барањето треба да ги доста-
преносната мрежа. вите следните документи:
Барањето за приклучок се подготвува на − Одобрение за градба
стандарден образец кон кој се приложува де- − Извод од Трговскиот регистар
тална студија за приклучувањето на пренос- − Извод од катастарскиот план со вцртана
ната мрежа и се поднесува до операторот на парцела на која ќе се наоѓа објектот
преносната мрежа (МЕПСО). Студијата треба − доказ за сопственост на објектот или
да вклучува: парцелата каде што објектот треба да биде
− Техничко решение за приклучок, изграден (имотен или поседовен лист)
− Технички карактеристики на опремата − План за годишно производство по месеци
на приклучокот, − еднополна шема на електраната,
− Оперативни барања за експлоатација и − Решенија за заштита на агрегатите и при-
управување на опремата и производната падните трансформатори,
единица, − Податоци за пресметка на струите на куси
− Проценети трошоци за приклучување врски на местото на приклучок
на преносна мрежа (Мрежни правила за − Предвидено времетраење на работите за
пренос на електрична енергија, член 68). приклучување на дистрибутивниот систем.
МЕПСО ги одобрува техничките решенија
коишто се предложени во студијата во рок од Издавањето на Согласност за приклучу-
120 дена од денот на приемот на студијата, вање на дистрибутивниот систем подлежи на
или може да му наложи на подносителот да ги потпишување на Договор за приклучување на
измени предложените решенија според него- дистрибутивна мрежа подготвен од страна
вите препораки. Со одобрувањето на студијата, на ЕВН Македонија. ЕВН е должно да издаде
ВЕТЕРНИ ЕЛЕКТРАНИ 9

Согласност за приклучување на дистрибутив- решение за Студијата за оценка на влијанието


ниот систем во рок од 15 дена за стандарден врз животната средина во согласност со Законот
приклучок и 40 дена за нестандарден приклучок. за животна средина.
А. Стандарден приклучок е нисконапонски или Студијата за оценка на влијанието врз жи-
среднонапонски приклучок за објекти кои вотната средина треба да содржи:
се наоѓаат на подрачје коешто е опфатено − Опис на проектот заедно со информации
со детален урбанистички план (ДУП), или за локацијата, карактерот и големината
урбанистички план за село (УПС), или урба- на проектот и на потребната земјишна
нистички план вон населено место (УПВНМ) површина;
и одобрената максимална едновремена моќ- − Опис на животната средина и нејзината
ност на приклучокот е помала или еднаква локација;
на 400kW. − Опис на природното, културното и исто-
Б. Нестандарден приклучок е нисконапонски риското наследство и опис на пределот;
или среднонапонски приклучок за објекти − Опис на видот и количините очекувани
кои се наоѓаат на подрачје коешто е опфатено емисии, особено на емисиите во воздухот,
со детален урбанистички план (ДУП), или цврстиот отпад, како и други информации
урбанистички план за село (УПС), или урба- потребни за евалуација на поголемите
нистички план вон населено место (УПВНМ) влијанија на проектот врз животната сре-
и одобрената максимална едновремена моќ- дина;
ност на приклучокот е поголема од 400kW. − Опис на мерките за спречување, намалу-
вање и елиминирање на влијанието врз
Трошоците за приклучување на преносната животната средина, како и на мерките
или на дистрибутивната мрежа, како што се за враќање во поранешната состојба;
утврдени од страна на МЕПСО или ЕВН Ма- − Опис на влијанијата на проектот врз жи-
кедонија, соодветно, ги сноси инвеститорот. вотната средина имајќи го предвид ни-
Имајќи ја предвид вообичаената одалеченост вото на развој на науката и прифатените
на најблискиот приклучок и сложеноста на методи за евалуација;
изградбата на приклучоците за ветерни елек- − Опис на карактеристиките на техноло-
трани, им советуваме на инвеститорите да гијата која се користи;
проверат во МЕПСО и во ЕВН Македонија каде − Опис на алтернативните решенија за ре-
ќе биде нивниот фактички приклучок за да ализација на проектот што инвеститорот
можат да направат проценка на трошоците и ги имал предвид и главните причини за
времетрањето на изведбата на приклучокот. избирање на предложената алтернатива;
секогаш се вклучува и нултата алтерна-
4.5. Студија за оценка на влијанието тива;
врз животната средина − Резиме на доставената студија без техни-
чки детали;
Ве молиме да имате предвид дека ветерните − Анализа на потешкотиите (технички не-
електрани подлежат на барањата за подго- достатоци или недостиг на знаења) со кои
товка и поднесување на Студија за оценка на инвеститорот или експертот биле соочени
влијанието врз животната средина. Оттука, за време на подготовката на студијата; и
ветерни електрани не може да се градат или да − Предлог за големината и карактеристи-
почнат со работа пред да се добие позитивно ките на потенцијалните промени поради
10 ВЕТЕРНИ ЕЛЕКТРАНИ

кои е потребно да се ажурира Студијата 4.6. Овластување за изградба на


за оценката на влијанието врз животната нови објекти за производство
средина. на електрична енергија
(Во случај на ветерни електрани со
Студијата за оценката на влијанието врз инсталирана моќност над 10 МW)
животната средина треба да се структурира
на следниот начин: Развојот и изградбата на ветерни електрани
1) Општи податоци; со инсталирана моќност поголема од 10 MW
2) Вид на елаборат; подлежат на доделување на овластување за
3) Орган надлежен за одобрување на ела- изградба на нови објекти за производство на
боратот; електрична енергија од страна на Владата (Закон
за енергетика, член 49). Сепак, овластување
4) Опис на проектот во кој се врши деј-
за изградба на нов енергетски објект нема
носта или активноста;
да биде потребно кога изградбата на ветерна
5) Опис на животната средина околу
електрана подлежи на доделување на конце-
локацијата на проектот;
сија за користење на земјиште во постапка
6) Влијание на проектот врз животната
со наддавање. Во такви случаи, условите за
средина;
изградба на ветерни електрани се утврдуваат
7) Програма за заштита на животната во договорот за концесија.
средина; Постапката започнува со доставување на
8) Заклучок; барање за овластување до Владата. Барањето се
9) Список на прилози; објавува во Службениот весник и се поднесува
10) Изјава. до Министерството за економија. Во прилог
на барањето треба да ги доставите следните
Инвеститорот треба да добие одобрение за документи (Закон за енергетика, член 52):
Студијата за оценката на влијанието врз живот- 1) проект и економска анализа,
ната средина. Орган надлежен за разгледување 2) согласност за приклучување на пре-
и одобрување на Студијата (во случај на ветерни носниот или дистрибутивен систем за
електрани над 1 MW) е Управата за животна електрична енергија во согласност со
средина, орган во состав на Министерството соодветните мрежни правила;
за животна средина и просторно планирање. 3) решение со кое се одобрува Студијата
Градоначалникот на општината е надлежен за за оценка на влијанието врз животна-
разгледување и одобрување на Студијата (во та средина или елаборатот за животна
случај на ветерни електрани до 1 MW). средина, доколку е применливо;
Ве молиме да имате предвид дека ќе биде 4) извод од локалниот детален урбанис-
потребно да се направи Студија за оценката тички план;
на влијанието врз животната средина доколку 5) финансиски план за изградба на ветерна
за ветерната електрана биде потребно да се електрана;
изгради напонска мрежа од 110 kV со должина 6) Писмо за намера издадено од финан-
од најмалку 15 км. Тоа може да доведе до зголе- сиска институција или банка за нејзи-
мување на трошоците за подготовка на проектот ната намера да обезбеди финансиски
и од го одложи неговото финализирање. средства за проектот;
ВЕТЕРНИ ЕЛЕКТРАНИ 11

7) доказ за финансиската способност на 6) условите кои треба да се исполнат за


инвеститорот; заштитата на животната средина;
8) Профил на компанијата на инвеститорот 7) условите во врска со ефикасноста на
и потенцијалните партнери и нивните работењето на објектот; и
референци поврзани со реализацијата 8) други услови во врска со изградбата на
на проекти од овој вид; објектот.
9) документи од регистрацијата на инвес-
титорот; Овластувањето за изградба на ветерна елек-
10) доказ дека подносителот не е во постапка трана важи три години од денот на неговото
за стечај или ликвидација; влегување во сила. Овластувањето престанува да
11) доказ дека против подносителот не се води важи доколку инвеститорот што е носител на ов-
кривична или прекршочна постапка, и ластувањето не обезбеди одобрение за градење
12) изјава за веродостојноста на податоците. на ветерната електрана во рок од три години.
Овластувањето може да се пренесе на друго лице
Барањето го разгледува деветчлена Комиси- по претходно добиена согласност од Владата.
ја формирана од страна на министерот за еконо- Владата може да го одбие барањето за
мија. Доколку Комисијата утврди дека барањето овластување во случај кога:
е нецелосно, ќе му наложи на подносителот 1) Студијата за оценка на влијанието врз
да достави комплетна и точна документација животната средина или онаму кадешто
во рок од 15 дена од денот на поднесувањето. е релевантно, елаборатот за животна
Доколку подносителот не достави комплетна средина, е одбиено;
и точна документација во наведениот рок, 2) во постојната планска документација не
Комисијата ќе го отфрли барањето. е предвидена изградба на нови објекти
Доколку барањето е комплетно и точно, за производство на електрична енергија;
Комисијата ќе и предложи на Владата да издаде или
овластување за изградба на ветерна електрана 3) подносителот не докаже дека може да
во рок од 60 дена од приемот на барањето. Вла- го обезбеди финансирањето на изград-
дата пред донесување на одлуката ќе побара ми- бата на ветерната електрана (Закон за
слење од Регулаторната комисија за енергетика. енергетика, член 54 – 58).
Во овластувањето се утврдуваат следниве
услови: 4.7. Одобрение за градба
1) видот, карактеристиките, инсталира-
ната моќност и очекуваното годишно За изградба на ветерна електрана е потребно
производство на електрична енергија; одобрение за градба. Општината на чијашто
2) локацијата на објектот во согласност територија е предвидено да биде изградена
со соодветната урбанистичко-планска ветерната електрана е надлежна за издавање
документација; на одобрение за градба без оглед на капаци-
3) рокот на важност на овластувањето; тетот на идната ветерна електрана (Закон за
4) услови за постапување со ветерните градење, член 57).
електрани по престанување на нивната Кон барањето за одобрение за градба треба
работа; да ги доставите следните документи:
5) услови за користење на јавната инфра- – извод од локалниот детален урбанистички
структура; план;
12 ВЕТЕРНИ ЕЛЕКТРАНИ

– архитектонско-урбанистички проект (ре- обезбедување на проектна документација ги


видиран и одобрен), сноси инвеститорот.
– основен проект (ревидиран и одобрен),
– Идеен проект, 4.8. Стекнување на привремен
– доказ за право на градење (сопственост, статус на повластен
право на користење, концесија), производител
– геодетски елаборат за земјишната парцела.
Регулаторната комисија за енергетика донесе
Општината е должна да ја разгледа и да Правилник за повластени производители на
донесе решение за доделување на одобрение електрична енергија од обновливи извори на
за градење во рок од 15 дена од денот на дос- енергија (Службен весник бр. 18/2012, 97/2012,
тавување на комплетна и точна документација. 63/2013 и 25/2015). Согласно Законот за енерге-
Пред да го добие одобрението за градење, под- тиката и Правилникот за повластени произво-
носителот треба да го плати надоместокот за дители на електрична енергија од обновливи
уредување на градежно земјиште; одобрението извори на енергија, Регулаторната комисија за
за градење се издава во рок од пет работни дена енергетика издава решение за стекнување на
од доставување на доказ за платен надоместок привремен статус на повластен прозводител,
за уредување на градежно земјиште. решение за стекнување на статус на повлас-
Одобрението за градење престанува да важи тен производител и одлука за користење на
доколку подносителот не почне со изградба повластена тарифа, и истите ги објавува на
во рок од 2 (две) години, или не го заврши во својата веб страна и во Службен весник. Исто
рок од 6 (шест) години од денот на издавање така, на веб страната на Регулаторната комисија
на одобрението за градење (Закон за градење, за енергетика се објавува и Регистарот на пов-
член 59 - 68). Ветерната електрана може да биде ластени прозводители, како и дијаграмите за
пуштена во употреба само по одобрување на постапките за стекнување на статус на повластен
техничкиот преглед од страна на овластениот производител и користењето на повластената
супервизор, а Министерството за транспорт и тарифа: www.erc.org.mk.
врски или Општината, во зависност од случајот, Постапката за издавање на привремено
ќе издадат одобрение за употреба на градба. решение за стекнување на статус на повластен
Доколку парцелата на која инвеститорот производител отпочнува со поднесување на ба-
има намера да гради е класифицирана како рање до Регулаторната комисија за енергетика.
земјоделско земјиште (обработливо земјиште, Барањето се поднесува до Регулаторната
шуми, пасишта или слично), инвеститорот може комисија за енергетика во писмена форма како
да достави барање до Министерството за транс- пополнет образец за барање за издавање на
порт и врски или до Општината, во зависност привремено решение за стекнување на статус
од случајот, да побара од Министерството за на повластен производител, заверен со потпис и
земјоделство, шумарство и водостопанство печат на барателот (Образец БПРПП): Барателот
да изврши трајна пренамена на соодветното е должен да ги определи и посебно да ги означи
земјоделско земјиште во градежно земјиште документите кои што се од доверлив карактер.
(Закон за земјоделско земјиште, член 49). Вре- Во спротивно ќе се смета дека доставените
метраењето на оваа постапка зависи од сло- документи не се од доверлив карактер.
женоста на подготовката и разгледувањето Барателот е должен да ги достави следните
на проектната документација. Трошоците за податоци и документи:
ВЕТЕРНИ ЕЛЕКТРАНИ 13

− Барање за издавање на привремено реше- завршувањето на подготвителната седница,


ние за стекнување на статус на повластен ќе одржи редовна седница на која ќе донесе
производител, заверено со потпис и печат привремено решение за стекнување на статус
од управителот; на повластен производител на електрична
− Решение за упис од Централниот Регистер, енергија произведена од обновливи извори на
оригинал или копија заврена на нотар; енергија. Привременото решение се објавува
− Доказ за исполнување на условот (право- во Службен весник, а влегува во сила со денот
силно одобрение за градење или договор на донесувањето.
за концесија или договор за јавно приватно Во привременото решение се наведува
партнерство), оригинал или копија заве- моќноста на електроцентралата (односно на
рена на нотар; генераторските единици).
− Основен проект за електроцентралата Регулаторната комисија за енергетика во
изработен од лиценцирано правно лице, привременото решение го утврдува рокот до
− Изјава за веродостојност на барањето кој електроцентралата треба да биде пуштена
и поднесените податоци и документа- во употреба. Рокот на важење на привременото
ција, потпишана од управител овластен решение е еднаков на рокот до кој електроцен-
за застапување на барателот запишан во тралата треба да биде пуштена во употреба. Во
Централниот регистар. овој рок, носителот на привременото решение
е должен да ја изгради електроцентралата,
Доколку Регулаторната комисија за енерге- да обезбеди документи издаден од надлежен
тика утврди дека барањето и документацијата орган за употреба на електроцентралата или
се комплетни и нема недостатоци, во рок од извештај за извршен технички преглед) согласно
5 (пет) дена од денот на приемот на барањето Законот за градење и да поседува лиценца за
ќе донесе заклучок за уредност на барањето вршење на енергетска дејност – производство
и продолжување на постапката во согласност на електрична енергија.
со одредбите на Правилникот за лиценци за
вршење на енергетски дејности. Регулаторната 4.9. Проектирање и изведба
комисија за енергетика доставува еден приме- на приклучокот
рок од заклучокот до барателот.
Регулаторната комисија за енергетика во Со оглед дека повеќето ветерни електрани ќе
врска со поднесеното барање за издавање на бидат приклучени на преносната мрежа, ќе
привремено решение за стекнување на статус ја разгледаме постапката за проектирање и
на повластен производител ќе закаже подгот- изведба на приклучокот на преносната мрежа.
вителна седница која треба да се одржи во Во согласност со решението за согласност за
рок кој не може да биде подолг од 25 (дваесет приклучување на преносната мрежа, инвес-
и пет) дена од денот на приемот на барањето. титорот и МЕПСО треба да потпишат договор
За присуство и учество на подготвителната за приклучување на преносна мрежа (Мрежни
седница, Регулаторната комисија за енерге- правила за пренос на електрична енергија, член
тика го поканува барателот, како и овластени 71) во кој се утврдени:
претставници на заинтересирани претпријатија, − меѓусебните обврски во текот на изведбата
институции и организации. на приклучокот,
Регулаторната комисија за енергетика − одобрението на проектната документација
најдоцна во рок од 5 (пет) дена од денот на за изведба на приклучокот,
14 ВЕТЕРНИ ЕЛЕКТРАНИ

− средствата поврзани со приклучокот на 4.10. Одобрение за употреба


МЕПСО и на инвеститорот,
− поделбата на трошоци помеѓу МЕПСО и За официјално пуштање во употреба на ветерна-
инвеститорот за изведба на приклучокот. та електрана е потребно одобрение за употреба.
Одобрението за употреба на ветерна електрана,
МЕПСО е должен да го подготви и да дос- како и на секоја друга електрана со инсталирана
тави договор за приклучување на преносната моќност над 1 MW, го издава Министерството
мрежа до инвеститорот во рок од 30 дена од за транспорт и врски врз основа на основниот
издавањето на решение за согласност за при- проект (или проектот на изведена состојба до-
клучување на преносната мрежа. колку во текот на изведбата настанале поголеми
Доколку МЕПСО и инвеститорот се догово- промени), извештај од техничкиот преглед и
рат дека инвеститорот треба да ја организира извод од Катастарот како доказ за право на
и да управува со изведбата на приклучокот на сопственост или други права на користење на
преносната мрежа, интвеститорот треба да ги објектот (Закон за градење, член 87). Во случај на
достави до МЕПСО за одобрување техничките некомплетно барање за одобрение за употреба,
спецификации за приклучокот и целокупната Министерството за транспорт и врски ќе му на-
документација којашто е потребна за добивање ложи на поднесителот да достави комплетна и
на одобрение за градба. Со оглед на потребата соодветна документација во рок од седум дена од
за координирање на многу сложена техничка приемот на барањето за одобрение за употреба.
документација и потребата за информирање и Комисија составена од тројца овластени
барање на одобрение од МЕПСО во постапката надзорни инженери именувани од страна на
за добивање на одобрение за градење за прик- Министерството за транспорт и врски треба
лучување на преносната мрежа, наша препорака да изврши техничкиот преглед на градбата по
е инвеститорот да му ја довери изведбата на приемот на барањето за одобрение за употреба
приклучокот на МЕПСО. во рок од 15 дена од денот на приемот на ком-
МЕПСО ги пресметува трошоците за прик- плетно и соодветно барање за одобрение за
лучување на преносната мрежа во согласност употреба. Комисијата утврдува дека:
со Метологијата за пресметка на надоместокот − градбата е изградена согласно основниот
за приклучување, којшто е составен дела на проект или во случај на измени во текот на
Мрежните правила за пренос на електрична градбата, проектот на изведена состојба
енергија (Прилог 7). и одобрението за градење,
Трошоците за приклучување на преносната − објектот е безбеден и може да се користи.
мрежа се состојат од: Доколку комисијата утврди какви било
− трошоци за градба на нов приклучок или недостатоци кои ја нарушуваат механичката
надградба на постоен приклучок, и стабилност и отпорност на објектот, може да
− трошоци за создавање на технички ус- побара од инвеститорот да ги коригира овие
лови за зголемување на капацитетот на аспекти во рок од 30 дена, или може да пред-
преносниот систем и приклучување на ложи да не се издаде одобрение за употреба
нови корисници. (Закон за градење, член 89-92).
Во случај на позитивен извештај на коми-
Трошоците за приклучување на нова вет- сијата, Министерството за транспорт и врски е
ерна електрана на преносниот систем ги сноси должно да издаде одобрение во рок од 15 дена
инвеститорот. од датумот на техничкиот преглед на градбата.
ВЕТЕРНИ ЕЛЕКТРАНИ 15

Трошоците за извршување на техничкиот пре- − Краток опис на бараната лиценца,


глед и издавање на одобрение за употреба ги − Изјава за веродостојност на податоците и
сноси инвеститорот. приложената документација потпишана
од овластеното лице,
4.11. Лиценца за производство − Изјава за временскиот период за барање
на електрична енергија за издавање на лиценцата,
− Платен надоместок за издавање на ли-
Условите зa издавање нa лиценца зa произ- ценца,
водство нa електрична енергија од обновливи − Решение за упис во Централен Регистар,
извори ce yтвpдeни во Правилникот зa лиценци − Акт за основање и/или Статут на компа-
зa вршење нa енергетски дејности (Службен нијата,
весник 6p. 141/2011, 78/2013 и 33/2015). Инвести- − Доказ за правото на сопственост или
торот мoжe да пo6apa да мy ce издаде лиценца правото на користење на земјиштето и
зa производство нa електрична енергија oд основните средства,
обновливи извори од Регулаторната комисија − Договор за концесија ако дејноста се врши
за енергетика и пред добивање на извештај зa со користење на природно богатство или
извршен технички прием или употребна дозвола договор за концесија за јавна услуга, од-
од надзорен орган во следниве случаи: носно доказ за право на користење на при-
− Aкo инвеститорот зa енергетскиот објект родното богатство во согласност со закон;
има обезбедено овластување за изградба − Организациска структура на подносите-
согласно Законот за енергетика; или лот, вклучувајќи и информации за бројот
− Aкo инвеститорот зa енергетскиот објект на вработени, образованието и стручната
имa обезбедено одобрение за градење оспособеност на лицата коишто ќе ра-
на објектот во случај кога за изградба на ководат со објектот и на кадарот кој ќе
објектот не е потребно овластување за ракодови со опремата;
изградба на објектот, или − Проект, одобрение за градба, а доклку
− Ако инвеститорот на енергетскиот објект објектот е изграден и извештај за извр-
се стекнал со право на градење на објект шен технички преглед или одобрение
врз основа на постапка спроведена по пат за ставање на објектот во употреба, како
на јавен повик за изградба на објекти за и овластување за изградба на објект за
производство на електрична енергија, или производство на електрична енергија,
− Ако инвеститорот се стекнал со право на во случај ако изградбата на објектот е
градење на објектот врз основа на потпи- предмет на такво барање;
шан концесиски договор. − Изјава за сопственичката структура на
компанијата, вклучувајќи и информации
Инвеститорот треба да достави барање за и детален опис на учеството на подно-
издавање на лиценца до Регулаторната комисија сителот во други компании и учество
за енергетика заедно со следниве информации на други компании во компанијата на
и документи: подносителот;
− Општи информации за подносителот, − Потврда за бонитет на подносителот из-
− Име на одговорното лице, дадена од надлежен орган;
− Вид на енергетската дејност што трба да − Уверение за платени даноци и други јавни
се врши, давачки од Управата за јавни приходи;
16 ВЕТЕРНИ ЕЛЕКТРАНИ

− Финансиски извештаи подготвени во цел да се објави издавањето на лиценцата и


согласност со важечките регулативи за да се повикаат сите заинтересирани страни
последните три години, вклучувајќи и да коментираат за издавањето на лиценцата
ревизорски извештаи од овластен ревизор, и да го презентираат својот случај.
доколку ревизијата е утврдена со закон; По објавувањето на барањето, Регулатор-
− Потврда дека подносителот не е предмет ната комисија за енергетика ќе закаже под-
на постапка за стечај или ликвидација; готвителна седница која треба да се одржи во
− Потврда од Централен Регистар дека на рок од 50 дена од денот на отпочнувањето на
подносителот и овластениот застапник постапката. Доколку Регулаторната комисија за
не им е изречена забрана за вршење на енергетика утврди од подготвителната седница,
професија, дејност и должност и потврда како и од документацијата, дека се исполнети
дека не се осудени за сторено кривично условите за издавање на лиценцата, ќе закаже
дело. редовна седница во рок од 10 дена за да донесе
одлука за издавање на лиценца.
Покрај горенаведените документи бара- Регулаторната комисија за енергетика ја
телот е должен да достави и дополнителна објавува одлуката и лиценцата за вршење на
документција во врска со специфицната техно- енергетски дејности во Службен весник.
логија за производство на електрична енергија Доколку лиценцата е издадена за објект без
согласно член 14 од Правилникот за лиценци употребна дозвола или извештај за извршен те-
за вршење на енергетски дејности. хнички прием, а инвеститорот има обезбедено
Регулаторната комисија за енергетика ќе употребна дозвола или извештај за извршен
го разгледа барањето за издавање на лиценца и технички прием, потребно е инвеститорот да
приложената документација и во рок од 8 дена достави документација во согласност со член
ќе донесе Заколучок. Доколку документацијата 32 од Правилникот за лиценци за вршење на
за издавање на лиценцата е во согласност енергетски дејности. По доставената докумен-
со Правилникот за лиценци за вршење на тација Регулаторната комисија за енергетика
енергетски дејности како и другите закони, во рок од 8 дена од доставувањето ќе издаде
Регулаторната комисија за енергетика ќе го одлука за влегување во сила на претходно
задолжи барателот да подготви известување издадената лиценца.
за барањето во рок од 3 дена и да го достави По добивањето на лиценцата за производ-
до Регулаторната комисија за енергетика на ство на електрична енергија, инвеститорот
одобрување. Во случај да приложената доку- има можност, доколку има технички услови,
ментација има формални и други недостатоци да произведува и продава електрична енергија
тогаш Регулаторната комисија за енергетика пред добивањето на статус на повластен про-
ќе го задолжи барателот во рок од 15 дена да изводител на електрична енергија (види 4.13)
ги отстрани недостатоците и да ја комплетира и пред потпишувањето на договорот за откуп
документацијата во согласност со Правилникот на произведената електрична енергија со АД
за лиценци за вршење на енергетски дејности. МЕПСО (види 4.14). За оваа цел, инвеститорот
Инвеститорот е должен да го објави ба- треба да склучи договор со:
рањето за издавање на лиценца за производство − операторот на електро-преносниот систем
на електрична енергија од обновливи извори (АД МЕПСО),
на свој трошок во најмалку два дневни весници − снабдувач со електрична енергија, или
на македонски и албански јазик. Огласот е со − трговец со електрична енергија.
ВЕТЕРНИ ЕЛЕКТРАНИ 17

Таквиот договор може да биде со ограни- ќе го извести подносителот и ќе го повика да


чено времетраење, односно до добивањето на ја комплетира неопходната документација во
статус на повластен производител на електрич- рок од 30 дена од денот на доставување на
на енергија, или со неограничено времетраење, известувањето. Доколку подносителот не ја
доколку инвеститорот не успее да добие статус комплетира документацијата во утврдениот
на повластен производител на електрична рок, Агенцијата за енергетика ќе го отфрли
енергија или избере да се откаже од истиот. барањето како нецелосно.
Доколку Агенцијата за енергетика утврди
4.12. Упис на објектот во Регистарот дека барањето и придружната документација
на објекти за производство се целосни и точни и дека условите за доделу-
на електрична енергија од вање на статус на повластен производител се
обновливи извори на енергија исполнети, таа ќе донесе решение за упис на
подносителот во Регистарот на повластени
Инвеститорот мора да ја регистрира својата производители на електрична енергија во рок од
ветерна електрана во Регистарот на објекти за 15 дена од датумот на доставување на барањето.
производство на електрична енергија од обнов- Агенцијата за енергетика може да одлучи да
ливи извори на енергија кој го води Агенцијата изврши увид на лице место на објектот пред
за енергетика. За таа цел, инвеститорот треба да издавањето на решението. Агенцијата за енерге-
достави барање до Агенцијата за енергетика за тика доставува до инвеститорот Одлука за упис
упис во Регистарот на објекти за производство во Регистарот на повластени производители на
на електрична енергија од обновливи извори електрична енергија во рок од три дена од дату-
на енергија, заедно со следниве документи: мот на донесување на решението. Инвеститорот
се упишува под единствен регистарски број кој
1. Одобрение за употреба на енергетскиот не може да се промени или да се пренесе (Пра-
објект или извештај за извршен технички вилник за обновливи извори на енергија, член 9).
преглед, во случај кога не е потребно
одобрение за употреба, и потврда од 4.13. Доделување на статус на
операторот на преносниот систем со која повластен производител
се потврдува дека енергетскиот објект
е приклучен на соодветниот (преносен По добивањето на привременото решение за
или дистрибутивен) систем, стекнување на статус на повластен произво-
2. Топографска карта со размер 1:25.000 дител на електрична енергија произведена од
на која е прикажана локацијата на вет- обновливи извори на енергија, инвеститорот
ерната електрана, треба да достави барање за издавање на решение
3. Шематски приказ на ветерната електрана за стекнување на статус на повластен произво-
и на поставената опрема, особено на дител на електрична енергија произведена од
опремата за мерење, и обновливи извори на енергија и истовремено
4. Копија од лиценцата за производство да достави барање за користење на повластена
на електрична енергија (Правилник за тарифа на електрична енергија произведена
обновливи извори на енергија, член 8). од обновливи извори на енергија. При тоа,
електроцентралата треба да биде пуштена во
Доколку Регулаторната комисија за енер- употреба во рокот утврден во привременото
гетика утврди дека барањето е нецелосно, таа решение и барателот да поседува лиценца за
18 ВЕТЕРНИ ЕЛЕКТРАНИ

вршење на енергетска дејност – производство Приложените документи треба да бидат


на електрична енергија за електроцентралата оригинал или фотокопија на оригиналот за-
за која се бара статус на повластен произво- врена од нотар.
дител на електрична енергија произведена од Кон барањата, барателот задолжител-
обновливи извори на енергија. но треба да приложи доказ дека на сметка
Барањета се поднесуваат до Регулаторната на Регулаторната комисија за енергетика е
комисија за енергетика во еден примерок во пис- уплатен неповратен паричен надоместок за
мена форма, како пополнет образец за барање трошоците направени во постапката (надо-
за издавање на решение за стекнување на статус местокот кој Регулаторната комисија за енер-
на повластен производител, заврен со потпис гетика треба да го плати на Агенцијата за
и печат на барателот (Образец БРПП), како и енергетика според тарифникот донесен од
пополнет образец за барање за користење на Агенцијата за енергетика) во денарска про-
повластена тарифа, заверен со потпис и печат тиввредност, по средниот курс на Народната
на барателот (Образец БКПТ). банка на денот на поднесувањето на барањата.
Барателот е должен да ги определи и по- Постапките за издавање на решение за стек-
себно да ги означи документите кои што се од нување на повластен производител и донесување
доверлив карактер, во спротивно ќе се смета на одлука закористење на повластена тарифа от-
дека доставените документи не се од доверлив почнуваат со денот на приемот на барањата во ар-
карактер. хивата на Регулаторната комисија за енергетика.
Барањата се поднесуваат за користење на По добивањето на барањата, Регулаторната
повластена тарифа која што важела на денот комисија за енергетика утврдува дали е доста-
на донесување на приврементото решение за вена потребната документација за донесување
стекнување на статус на повластен повластен на решението и донесувањето на одлуката, како
производител на електрична енергија. и тоа дали документацијата е доставена на про-
Кон барањата, барателот е должан да ги пишан начин и форма. Регулаторната комисија
достави следните податоци и документи: за енергетика во рок од 5 (пет) дена од денот
− Проект за изведена состојба согласно на приемот на барањата, ќе побара потврда од
Законот за градење, доколку се извршени Агенцијата за енергетика дека електроцентра-
измени во текот на изградбата; лата е изградена и ги исполнува специфичните
− Решение за упис во Регистарот на електро- услови и инсталираната моќност утврдени со
централи што користат обновливи извори Уредбата, што биле во сила на денот на изда-
на енергија за производство на електрич- вање на привременото решение за стекнување
на енергија, издадено од Агенцијата за на статус на повластен производител.
енергетика, согласно Правилникот за Агенцијата за енергетика е должна да ја из-
обновливи извори на енергија; даде потврдата во рок не подолг од 15 (петнаесет)
− Доказ дека е платен надоместок во со- дена од денот на поднесување на барањето на
гласност со член 13-а од Правилникот за Регулаторната комисија за енергетика.
повластени производители на електрична За издавање на потврдата, Регулаторната
енергија од обновливи извори на енергија; комисија за енергетика плаќа надоместок на
− Изјава за веродостојност на барањето и Агенцијата за енергетика, според тарифникот
дадените податоци, потпишана од лицето донесен од Агенцијата за енергетика, изготвен
овластено за застапување на барателот врз основа на трошоците на Агенцијата за енер-
запишано во Централниот регистар. гетика во постапката за издавање на потврдата.
ВЕТЕРНИ ЕЛЕКТРАНИ 19

Доколку Регулаторната комисија за енерге- за повластената тарифа во Регистарот на пов-


тика утврди дека барањата и документацијата ластени производители.
се комплетни и немаат недостатоци, и изда- Решението и одлуката на Регулаторната
дената потврда од Агенцијата за енергетика е комисија за енергетика ги доставува до бара-
позитивна, во рок од 20 (дваесет) дена од денот телот, операторот на пазарот на електрична
на приемот на барањата ќе донесе заклучоци енергија и до Агенцијата за енергетика.
за уредност на барањата и продолжување на
постапките. По еден примерок од заклучоците, 4.14. Договор за откуп на
Регулаторната комисија за енергетика доставува електрична енергија со
до барателот. оператор на пазарот на
Регулаторната комисија за енергетика, во електрична енергија
врска со поднесените барања, ќе закаже подгот-
вителна седница која треба да се одржи во рок Македонскиот електропреносен систем опера-
кој не може да биде подолг од 35 (триесет и пет) тор (МЕПСО) е должен да ја откупи целокупната
дена од денот на приемот на барањата. Поканата електрична енергија произведена од повласте-
за учество на подготвителната седница заедно ните производители на електрична енергија во
со предлогот на решението за стекнување на согласност со договорот, согласно со Законот за
статус на повластен производител и предло- енергетика, Решение за користење на повласте-
гот на одлуката за користење на повластена ни тарифи издадена од страна на Регулаторната
тарифа на електрична енергија произведена комисија за енергетика и Правилата за пазарот
од обновливи извори на енергија се доставува на електрична енергија. Инвеститорот треба да
најдоцна 7 (седум) дена пред одржувањето на достави барање за потпишување на договор за
подготвителната седница. За присуство и учест- откуп на електрична енергија до МЕПСО.
во на подготвителната седница, Регулаторната МЕПСО е должен да го потпише договорот
комисија за енергетика го поканува барателот, за откуп на електрична енергија во рок од 30
како и овластени претставници на заинтереси- дена од датумот на приемот на барањето. До-
рани претпријатија, институции и организации. говорот за откуп на електрична енергија мора
Регулаторната комисија за енергетика нај- да влезе во сила на денот на издавањето на
доцна во рок од 5 (ден) дена од денот на завршу- Решението за стекнување на статус на повластен
вањето на подготвителната седница ќе одржи производител на електрична енергија од страна
редовна седница на која ќе донесе решение за на Регулаторната комисија за енергетика.
стекнување на статус на повластен производител Инвеститорот може да одлучи да го раскине
на електрична енергија произведена од обнов- договорот за откуп на електрична енергија со
ливи извори на енергија и одлука за користење што ќе го изгуби статусот на повластен про-
на повластена тарифа на електрична енергија изводител на електрична енергија и правото
произведена од обновливи извори на енергија. повторно да се стекне со тој статус (Закон за
Решението и одлуката се објауваат во енергетика, член 153).
Службен весник и на веб-страната на Регула- Инвеститорот е должен да ја продаде цело-
торната комисија за енергетика. купната произведена количина на електрична
Со денот на влегување во сила на решението енергија на МЕПСО и да достави планови за про-
и одлуката, Регулаторната комисија за енерге- изводство на електрична енергија до МЕПСО.
тика ги впишува податоците за носителот на Овој чекор го означува крајот на процесот
решението и електроцентралата и податоците на аплицирање. По стекнувањето на статус на
20 ВЕТЕРНИ ЕЛЕКТРАНИ

повластен производител, инвеститорот може енергија произведена и продадена по секој


да ги применува и да ги користи повластените блок. Во зависност од количината на електрична
тарифи утврдени во Уредбата за повластени енергија произведена секој месец, фактичката
тарифи за електрична енергија (Член 7). Точ- повластена тарифа која е применлива за објек-
ната повластена тарифа која се применува на тот може да варира. Повластените тарифи се
објект за производство на електрична енергија применуваат за период од 20 години.
зависи од месечната количина на електрична

5. Обезбедување на гаранции за потекло


на електрична енергија произведена
од обновливи извори на енергија
Во случај кога инвеститорот не успеал да добие на повластени цени за електрична енергија
статус на повластен производител на електрич- произведена од обновливи извори на енер-
на енергија со што би можел да има корист од гија. Треба да се напомене дека повластената
преференцијалните тарифи, или ако инвести- тарифа е некомпатибилна со гаранцијата за
торот доброволно се откажал од договорот за потекло - инвеститорот може да го користи
откуп на електрична енергија со операторот или едното или другото. Ако инвеститорот ја
на пазарот на електрична енергија (види точка користи повластената тарифа, тој/таа не може
4.15. погоре), инвеститорот може да се пријави да се пријави за гаранции за потекло.
за гаранции за потеклото врз основа на што би Онаму каде што е релевантно, инвестито-
побарал повластена цена за електричната енер- рот треба да поднесе барање за доделување на
гија произведена во неговата ветерна електрана. гаранции за потекло на електричната енергија
Гаранции за потекло обично им се даваат произведена во неговата ветерна електрана до
на операторите на електропреносни системи Агенцијата за енергетика. Кон барањето треба
или трговци со електрична енергија коишто да се приложи следново:
имаат обврска за плаќање на повластени цени − Доказ за плаќањето на надоместокот за
за електрична енергија произведена од обнов- издавање на гаранции за потекло, и
ливи извори на енергија. Треба да се напомене − Доказ за операторот на системот за пренос
дека повластената тарифа е некомпатибилна со или дистрибуција на електрична енергија за
гаранцијата за потекло - инвеститорот може да количината на електрична енергија произ-
го користи или едното или другото. Ако инвес- ведена и продадена од страна на објектот.
титорот ја користи повластената тарифа, тој/таа
не може да се пријави за гаранции за потекло. Ако Агенцијата за енергетика утврди дека
Начинот и постапката за доделување на се исполнети сите услови за доделување на
гаранции за потекло се уредени со Правилникот гаранции за потекло на електрична енергија
за обновливи извори на енергија. Онаму каде произведена од обновливи извори на енергија,
што е релевантно, гаранции за потекло обично Агенцијата издава решение во рок од 30 дена
им се даваат на операторите на електропре- од денот на приемот на барањето.
носни системи или трговци со електрична Гаранцијата за потекло се издава по 1 MW.
енергија коишто имаат обврска за плаќање Гаранциите за потекло важат 12 месеци.
ВЕТЕРНИ ЕЛЕКТРАНИ 21

6. Адреси и податоци за контакт на


надлежните институции
6.1. Влада на РМ 6.6. Оператор на систем за дистрибуција/
Адреса: Бул. Илинден бр. 2 снабдување со електрична
1000 Скопје енергија (ЕВН Македонија)
Телефон: + 389 02 31 18 022 Адреса: 11 Октомври бр. 9
Веб страница: www.vlada.mk 1000 Скопје
Телефон: + 389 2 3205 000,
6.2. Министерство за економија, + 389 89 089 089
Сектор за енергетика Е-mail: info@evn.mk
Адреса: Јуриј Гагарин бр. 15 (1-ви кат) Веб страница: www.evn.mk
1000 Скопје
Телефон: + 389 2 30 93 485, 6.7. Министерство за животна средина
+ 389 2 30 93 485 и просторно планирање
Е-mail: info@economy.gov.mk Адреса: Гоце Делчев бр. 18
Веб страница: www.economy.gov.mk 1000 Скопје
Телефон: + 389 2 32 51 403,
6.3. Агенција за енергетика + 389 2 32 51 503,
Адреса: Орце Николов бр. 68 + 389 2 32 51 460
1000 Скопје Веб страница: www.moepp.gov.mk
Телефон: + 389 2 32 30 300
Е-mail: ea@ea.gov.mk 6.8. Министерство за транспорт и врски
Веб страница: www.ea@ea.gov.mk Адреса: Даме Груев бр. 6
1000 Скопје
6.4. Регулаторна комисија за енергетика Телефон: + 389 2 31 45 497
Адреса: Димитрие Чуповски бр 2, 4-ти кат + 389 2 31 23 292
1000 Скопје Веб страница: www.mtc.gov.mk
Телефон: + 389 2 32 33 580,
+ 389 2 32 54 010 6.9. Министерство за земјоделство,
Е-mail: erc@erc.org.mk шумарство и водостопанство
Веб страница: www.erc.org.mk Адреса: Аминта Трети бр. 2
1000 Скопје
6.5. Оператор за пазарот на Телефон: + 389 2 31 34 477
електрична енергија/ Е-mail: info@mzsv.gov.mk
Македонски електропреносен Веб страница: www.mzsv.gov.mk
систем оператор (МЕПСО)
Адреса: Максим Горки бр. 4 6.10. Централен Регистар
1000 Скопје Адреса: Кузман Јосифовски Питу бр. 1
Телефон: + 389 2 31 49 811 1000 Скопје
Е-mail: info@mepso.com.mk Телефон: + 389 2 32 88 100
Веб страница: www.mepso.com.mk Веб страница: www.crm.com.mk
22 ВЕТЕРНИ ЕЛЕКТРАНИ

7. Релевантно законодавство и
подзаконски акти

Закон за енергетика (Службен весник бр. 16/2011, земјиштето во негова непосредна близина
136/2011, 79/2013, 164/2013, 41/2014 и 151/2014) (Службен весник бр. 130/2007 и 156/2012).
Уредба за повластени тарифи за електрична енер- Уредба за начинот и постапката на отуѓување,
гија (Службен весник бр. 56/2013) давање под долготраен закуп и краткотраен
Одлука за вкупната инсталирана моќност на по- закуп, на градежно земјиште сопственост
властените производители на електрична на државата, со јавно наддавање, по пат на
енергија од секој одделен обновлив извор прибирање на понуди и со непосредна спо-
на енергија (Службен весник бр. 56/2013 и годба, висината на трошоците на постапката
10/2014) за отуѓувањето и давањето под закуп, како
Закон за градење (Службен весник бр. 130/2009, и висината на цената на земјиштето и на
124/2010, 18/2011, 36/2011, 54/2011, 13/2012, закупнината (Службен весник бр. 147/2008,
144/2012, 25/2013, 79/2013, 137/2013, 163/2013, 71/2009, 16/2009, 162/2009, 113/2010, 148/2010,
27/2014, 28/2014, 42/2014, 115/2014, 149/2014, 172/2010 и 40/2011)
187/2014 и 44/2015) Закон за сопственост и други стварни пра-
Закон за градежно земјиште (Службен весник бр. ва (Службен весник бр. 18/2001, 92/2008,
82/2008, 143/2008 и 56/2010) 139/2009 и 35/2010)
Закон за земјоделско земјиште (Службен весник бр. Уредба за определување на проектите и за кри-
135/07, 18/11, 148/11, 95/12, 79/13, 87/13, 106/13, териумите врз основа на кои се утврдува
164/13, 39/14, 130/14 и 166/2014) потребата за спроведување на постапка за
Закон за шумите (Службен весник бр. 64/2009, оцена на влијанијата врз животната средина
24/2011, 53/2011, 25/2013, 79/2013, 147/2013, (Службен весник бр. 74/2005)
43/2014, 160/2014, 33/2015 и 44/2015) Правилник за формата и содржината на елаборатот
Закон за животна средина (Службен весник бр. за заштита на животната средина, постапката
53/2005, 81/2005, 24/2007, 159/2008, 83/2009, за нивно одобрување, како и начинот на во-
48/2010, 124/2010, 51/2011, 123/2012, 93/2013, дење на регистарот на одобрени елаборати
187/2013, 42/2014) (Службен весник бр. 50/2009)
Закон за просторно и урбанистичко планирање Правилник за лиценци за вршење на енергетски
(Службен весник бр. 199/2014 и 44/2015) дејности (Службен весник бр. 143/2011, 78/2013
Правилник за формата и содржината на барање- и 33/2015)
то, потребната документација и образецот Правилник за обновливи извори на енергија
на Решението за изведување на градбите (Службен весник бр. 113/2011)
односно поставување на опремата за кои не Правилник за повластени производители на елек-
е потребно одобрение за градење. (Службен трична енергија од обновливи извори на
весник, бр. 147/2009) енергија (Службен весник бр. 18/2012, 97/2012,
Правилник за условите за поставување, градба и 63/2013, 41/2014, 151/2014 и 26/2015)
обележување на објекти, инсталации и уреди Правила за пазар на електрична енергија (Службен
во зоната на аеродромот, објекти и уреди весник бр. 38/2014, 57/2014 и 194/2014)
за контрола на летањето, и објекти надвор Мрежни правила за дистрибуција на електрична
од зоната на аеродромот коишто можат да енергија (Службен весник бр. 87/2012, 30/2014,
влијаат на безбедноста на воздушниот со- 161/2014, 189/2014 и 50/2015)
обраќај и условите и начинот на обработка Мрежни правила за пренос на електрична енергија
на земјиштето во зоната на аеродромот и (2015)
GUIDELINES
On the procedures for the development and
construction of power plants utilising renewable
energy sources
WIND POWER PLANTS
24 WIND POWER PLANTS

Contents

1. Introduction................................................................................................................... 25
2. Review of the applicable feed-in tariffs (FIT) for wind power plants................................ 26
3. Step-by-step diagram of the development procedures and documents................................ 27
4. Review of the steps, procedures and documents............................................................. 28
4.1. Basic prerequisites: Establishing a company........................................................... 28
4.2. Measurement of wind power potential................................................................... 28
4.3. Use of the land........................................................................................................ 29
4.4. Approval for connection to the transmission/distribution system.......................... 29
4.5. Environmental Impact Assessment Study (EIA)........................................................ 31
4.6. Authorisation for construction of new electricty generation facility
(in case of wind power plants with installed capacity greater than 10 MW)............. 31
4.7. Construction permit................................................................................................33
4.8. Award of temporary status of preferential producer...............................................33
4.9. Design and construction of the connection............................................................ 34
4.10. Use permit...............................................................................................................35
4.11. Energy generation license........................................................................................35
4.12. Registration of the facility in the Register of electricity
generation facilities from renewable energy sources...............................................37
4.13. Award of status of preferential producer................................................................ 38
4.14. Power purchase agreement with the electricity market operator.......................... 39
5. Award of guarantees of origin for the electricity generated from
renewable energy sources............................................................................................... 40
6. Addresses and contact details of competent institutions.................................................41
7. Relevant legislative and regulatory acts.......................................................................... 42

This publication has been produced with the assistance of the European Union. The contents of this publication
are the sole responsibility of ATC Consultants and its consortium partners and can in no way be taken to reflect
the views of the European Union.
WIND POWER PLANTS 25

1. INTRODUCTION

This guidelines is aimed at providing step-by- DISCLAIMER


step guidelines to investors in the process of
developing and implementing renewable energy This guidelines shall not elaborate on issues
projects, namely wind power plants. This is not such as the:
an exhaustive, detailed and in-depth review. For − Creation of a company or establishing a
full reading refer to the relevant legislative and foreign subsidiary in the beneficiary country
regulatory acts that are listed at the end of this and the work thereof,
guidelines. − Acquisition of a construction permit,
− Acquisition of professional staff licenses
This guidelines is structured in three parts. and other working and social permits,
In the first part we shall provide a review of − Land ownership, expropriation and other
the applicable feed-in tariffs (FIT) for all renew- ownership rights,
able energy projects, including the FIT for wind − Taxation,
power plants. − Rules on State aid etc.
In the second part we shall provide a step-
by-step diagram of the development procedures However, please bear in mind that these
and documents necessary. are important issues that any investor should
In the third part we shall provide a detailed carefully analyze when developing a wind power
review of the relevant procedures and require- plant project.
ments for the development, commissioning and
functioning of wind power plants. The reader
is invited to refer interchangeably to this part
and the step-by-step diagram, provided in the
second part.
At the end of the brochure we provide a list
of the competent authorities with their addresses
and contact details and a list of all relevant laws
and other regulatory acts.

This guidelines is envisaged to serve as an information and orientation tool for future investors in
wind power plants. Nevertheless, we recommend the investors to directly contact and consult the
competent authorities before taking any formal activities for the development and construction
of a wind plant and to take account of the most up-to-date legislative and regulatory acts.
26 WIND POWER PLANTS

2. Review of the applicable feed-in tariffs


(FIT) for wind power plants

The preferential tariff for electricity generated and sold by wind power plants (that have qualified
for preferential producers) have been defined by the Ordinance on Preferential Tariffs for Electricity
(Official Gazette No. 56/2013 and 10/2014) and is as follows:

Installed capacity of the wind power plant 0 – 50 MW

Preferential tariff (€cents/KWh) 8.9

Duration of the preferential tariff 20 years

The quota of eligible wind power plants that may use the preferential tariffs has been laid down
by the Decision on the total installed capacity of preferential producers of electricity generated
from each specific renewable source of energy (Official Gazette No. 100/2011) and is as follows:

Until December 31, Until December 31, Until December 31,


Period
2016 2020 2025
Quota (total installed capacity
65 MW 100 MW 150 MW
of wind power plants)

At the moment of writing this guidelines and until 31 December, 2016, 13,2 MW are still avail-
able for newly developed wind power plants1. The quota shall increase by 35 MW in 2017, and by 50
MW in 2021.

1
Potential investors should note that the State-owned joint stock company ELEM has actually been award-
ed a license for construction of wind power plants with total installed capacity of 50 MW. ELEM used 36,8
MW of its license by commissioning a wind park in Bogdanci in 2013. ELEM envisages to use the remaining
13,2 MW for wind power plants in the period past 2016.
3.  Step-by-step diagram of the development procedures and documents
Duration Duration
Years Year 1 Year 2 Year 3 Year 4 Year 5
Months 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Procedure Competent institution
4.1 Establishing a company 6.1
Measurement of the wind power 1
4.2 6.3 Measurement of the wind power potential (minimum 2 years)
potential
6.1, 6.8, 6.9 or
4.3 Use of the land municipality 2
Approval for connection
4.4 to the transmission/distribution 6.5 or 6.6
system

4.5
Environmental Impact 6.7 or municipality
Elaborate Study
4.6 Authorisation of construction of 6.1 3
the wind power plant
4.7 Construction permit 6.8 or municipality 4
CONSTRUCTION PROCESS

4.8
Award of temporary status of 6.4
preferential producer
Design and construction of the 6.5, 6.6 or authorised
4.9 5
connection company

4.10 Use permit 6.8 or municipality

4.12 Energy generation license 6.4

Registration of the facility in the


WIND POWER PLANTS

Register of electricity generation 6.3


4.13
facilities from renewable energy
sources
Award of status of preferential
4.14. 6.4
producer
Power purchase agreement
4.15 with the electricity market 6.5
operator

Start of generation
and sale of electricity

Legend:

:
Risk 1: The measurement results may not support Risk 4: Inability to obtain a construction
Duration of the procedure 1 4
the feasibility of the project for that location permit or unforeseeable delay

Duration of the measurement of the wind power potential Risk 2: Inability to obtain right of use of State-owned Risk 5: Escalation of connection costs if the
(minimum of two years) 2 land; delays and uncertainty of outcome and costs 5 nearest connection point is impossible

Risk 3: Inability to meet the requirements for the award of


Construction works 3 Start of generation and sale of electricity`
authorization for the construction of a new wind power plant
27
28 WIND POWER PLANTS

4. Review of the steps, procedures


and documents
4.1. Basic prerequisites: A permit by the Energy Agency is required for
Establishing a company measuring the wind power potential. The inves-
tor should submit the following documentation
Electricity generation may be performed by domes- along with the request for awarding the permit
tic and foreign companies on the basis of a license for measuring the wind power potential:
issued by the Energy Regulatory Commission. In – Balance sheet issued by the Central Register
order to apply for electricity generation license, (may not be older than six months),
foreign companies must at least establish a sub- – Preliminary feasibility study, analyzing the
sidiary registered at the Trade Register maintained technical and financial operation of the
by the Central Register (Energy Law, article 5). This wind power plant and based on previous
requirement is verified by reviewing the excerpt measurements of the wind power potential,
from the Central Register. – Geodetic report (in a scale of 1:25,000) for the
Electricity generation may not commence prior land parcel the wind measurement equip-
to the obtaining of the relevant license. A license ment shall be located (a separate geodetic
for the energy-related activity may be issued for report is required for each measurement
a period of three to 35 years depending on the site),
type of energy, type and scope of the provision – Geodetic map (in a scale of 1:25,000) for the
of public service obligation, the capital necessary land parcel and are where the measurement
for the carrying out of the energy-related activ- shall be carried out.
ity, duration of the right/concession to use the
specific energy resource, as well as on the specific Should the Energy Agency establishes that the
requirements of the operator. The typical duration request is incomplete, it shall notify the applicant
of the license for electricity generation is 35 years. and shall invite the applicant to submit a com-
A single legal entity may acquire several licenses plete and correct documentation within 15 days
for energy-related activities (Energy Law, article 37). from the date of notification. The Energy Agency
A wind power plant with a total electricity shall reject the request if the application fails to
generation capacity up to 10 MW may be devel- comply with the notification. Should the Energy
oped without the “authorisation for construc- Agency establishes that the request is complete
tion of new energy generation facilities” that is and correct, it shall award the applicant a permit
granted by the Government, on the proposal of for measuring the wind power potential within 30
the Ministry of Economy. (Energy Law, article 49). days from the date of submission of the request
and shall publish the permit on its website.
4.2. Measurement of wind The permit is issued for a period of one year,
power potential but it may be extended for thee additional years.
In case an extension of the permit is needed, the
A documented and adequate wind power potential investor should submit a request for this aim to
is necessary for the development and sustainable the Energy Agency, accompanied by a rationale
functioning of a wind power plant. The investors for the need of the extended measurement and
should carry out their own measurement on the an evidence that the wind potential measurement
specific locations. equipment has been installed and operational.
WIND POWER PLANTS 29

Only one permit for measuring the wind In case the land parcel(s) where the investor
power potential may be issued for each site. The intends to develop the wind power plant is classified
permit is issued for an area of 0,4 m2 for 1 MW as agricultural land (arable land, forest, pasture
of installed capacity of the future wind power or similar), he/she may request the Ministry of
plant. The shortest distance between two mea- Transport and Communications, or the Municipal-
surement sites may be 2 km. If several inves- ity, as the case might be, to request the Ministry
tors are interested in measuring the wind power of Agriculture, Forestry and Water Economy to
potential on one site, the measurement permit permanently convert the relevant agricultural
shall be issued to the investor that first submit- land into construction land (Law on Agricultural
ted a complete and correct request (“first come, Land, article 49). The duration for this procedure
first served”). depend on the complexity to prepare and review the
The installation of wind power measurement project documentation. The costs for providing the
equipment is not subject to the requirement of a project documentation are borne by the investor.
construction permit. However, an approval from Unless the land parcel(s) where the investor
the Ministry of Transport and Communications intends to install the wind measurement equipment
is needed for install such equipment pursuant to is privately-owned, the investor needs to purchase
the Rulebook on the form and content of the ap- the land, sign a long-term lease contract with the
plication, documentation and form of the approval Government or obtain a concession for the land
for the construction of facilities and installation use (Law on Construction Land, articles 13 – 40).
of equipment for which a construction permit The procedures on the sale, long-term lease and
is not required. In addition, an approval from concession of State-owned construction land are
the Civil Aviation Agency is need to install the based on competitive bidding, which implies a risk
wind power measurement equipment, pursuant of not winning the bid for the specific land parcel.
to the Rulebook on the conditions for the place- If the land parcel is privately-owned, the inves-
ment, construction and designation of facilities, tor and the owner of the land may mutually agree
installations and devices in the zone of an airport, on the sale, long-term lease or use rights of the land.
facilities and flight control devices and facilities
outside the airport zone, that can affect the safety 4.4. Approval for connection
of air traffic and on the conditions and manner of to the transmission/
treatment of the land in the airport zone and the distribution system
land in its immediate proximity (Official Gazette,
No. 130/2007 and 156/2012). Electricity generation facilities with installed ca-
pacity of at least 10 MW are directly connected
4.3. Use of the land to the transmission grid (Electricity Transmission
Grid Code, article 57). Considering that most of the
Most often, the land suitable for construction of wind power plants will be with installed capacity
wind power plants is State-owned agricultural land of above 10 MW, we shall first present the proce-
(pastures, arable land, forests or similar). In such dure for obtaining approval for connection to the
case, the investor should request the initiation of transmission grid.
two procedures: The request for connection, prepared on a
1. Conversion of the agricultural into construc- standard template, and accompanied by a detailed
tion land, and study on the connection to the transmission grid,
2. Buy-out, long-term lease or concession agree- should be submitted to the transmission system
ment for the land use. operator (MEPSO). The study should include:
30 WIND POWER PLANTS

− Technical proposal for the connection, − Annual electricity production plan, per
− Technical characteristics of the equipment month,
for the connection, − Unipolar scheme of the plant,
− Operational requirements for the exploitation − Protection solutions for the aggregates and
and use of the equipment and the generation the corresponding transformers,
facility, − Data for calculating of the short-circuit
− Estimated costs for the connection to the current at the connection point,
transmission grid (Electricity Transmission − Planned duration of the works for connecting
Grid Code, article 68). to the distribution system.

MEPSO approves the technical solutions The award of the Approval for connection to
proposed in the study within 120 days from the the distribution system is subject to signing a Con-
day of receipt of the study, or it may order the tract for connection to the distribution network,
applicant to modify the proposed solutions ac- drafted by EVN Macedonia. EVN is obliged to issue
cording to its recommendations. By approving the Approval for connection to the distribution
the study, MEPSO delivers the approval for the system within 15 days for a standard connection,
connection to the transmission grid and specifies: and 40 days for non-standard connection.
− The technical solution of the connection,
− Technical specifications for the equipment A.  Standard connection is a low or medium volt-
and works for the construction of the con- age power connection for facilities located
nection, in area covered by the Detailed Urban Plan
− The conditions for the use of the transmission (DUP), or by an Urban Plan for Village (UPV),
system, or an urban plan for a non-inhabited area and
− The estimated costs for the construction of the maximum approved simultaneous power
the connection (Electricity Transmission Grid of the connection is up to 400kW.
Code, article 70).
Electricity generation facilities with installed B.  Non-standard connection is any low or medium
capacity of up to 10 MW may be connected to the voltage connection for facilities located in area
distribution grid. In such case the request for con- covered by the Detailed Urban Plan (DUP),
nection should be submitted to the distribution or by an Urban Plan for Village (UPV), or an
system operator (EVN Macedonia) in the initial urban plan for a non-inhabited area and the
phase of the construction works. The request maximum approved simultaneous power of
should be submitted on the template BSP-2 that the connection is greater than 400kW.
may be found at EVN’s energy users’ centers or may
be downloaded from EVN’s website. The costs for the connection to the transmis-
The following documents should be submitted sion or to the distribution grid, as determined
along with the request: by MEPSO or EVN Macedonia, respectively, are
− Constriction permit borne by the investor. Bearing in mind the usual
− Excerpt from the Trade Register distance to the nearest connection point and the
− Excerpt from the Cadastre designating the complexity of construction of connections for wind
parcel where the facility will be located power plants, we advise the investor to check with
− Proof of ownership of the facility or of the MEPSO and EVN Macedonia what shall be the actual
parcel where the facility shall be constructed connection point and to estimate the costs and
(property or ownership certificate) duration for the construction of the connection.
WIND POWER PLANTS 31

4.5. Environmental Impact − Proposal about the scope and characteristics of


Assessment Study (EIA) potential changes that would require an update
of the Environment Impact Elaborate Study.
Please bear in mind that wind power plants are
subject to the requirement of preparing and sub- The Environmental Impact Assessment Study
mitting an Environmental Impact Elaborate Study. should be structured as follows:
Therefore they may not be constructed or start 1) General data;
their operation before a positive decision on the 2) Type of the Elaborate Study;
Environmental Impact Assessment Study is ob- 3) Authority responsible for approving the
tained in accordance with the Law on environment. Elaborate Study;
The Environmental Protection Assessment 4) Description of the project in which the
Study should contain: activity will be done;
− Description of the project, along with infor- 5) Description of the environment around the
mation on the location, the nature and the project location;
size of the project and the required land area; 6) Impact of the project on the environment;
− Description of the environment and its location; 7) Program for environmental protection;
− Description of the natural, cultural and his- 8) Conclusion;
torical heritage and a description of the area; 9) List of annexes;
− Description of the types and quantities of 10) Statement
the expected emissions, especially of the
air emissions, solid waste, as well as other The Investor should obtain an approval of
information necessary for evaluation of the the Environmental Impact Assessment Study.
project’s broader environmental impact; The Environment Directorate, body under the
− Description of the measures for prevention, competence of the Ministry of Environment and
reduction and elimination of the environ- Physical planning is responsible for reviewing and
mental impact, as well as of the measures approving the Study (in case of wind power plants
of restoring into previous condition; of above 1 MW). The Mayor of the municipality is
− Description of the environmental impacts of responsible for reviewing and approving the Study
the project, taking into account the scientific (in case of wind power plants of up to 1 MW).
development and the accepted methods for Please bear in mind, that the conduct of an En-
evaluation; vironmental Impact Assessment shall be necessary
− Description of the characteristics of the if the wind power plant requires the construction
technology used; of at least 110 kV voltage grid and for at least 15
− Description of the alternative solutions for km. This may increase the project’s development
the realization of the project that the investor costs and delay its finalization.
has to take into consideration and the main
reasons for selecting the proposed alterna- 4.6. Authorisation for construction
tive; the zero alternative is always included of new electricty generation
− Summary of the submitted study, without facility (in case of wind
technical details; power plants with installed
− Analysis of the difficulties (technical deficien- capacity greater than 10 MW)
cies or lack of knowledge) with which the
investor or the expert were faced during the The development and construction of wind power
preparation of the study; and plants with installed capacity greater than 10
32 WIND POWER PLANTS

MW are subject to the award of an authorisation The request shall be examined by a nine-
for construction of a new electricity generation member Commission established by the Minister
facility by the Government (Law on Energy, Article of Economy. Should the Commission establishes
49). However, the authorisation for construction that the request is incomplete, it shall invite the
of a new electricity facility shall not be required, applicant to submit a full and correct documenta-
when the development of the wind power plant is tion within 15 days from the date of submission.
subject to the award of a concession for the land If the applicant fails to submit full and correct
use in a competitive procedure. In such cases, the documentation within the deadline, the Commis-
terms and conditions for the construction of the sion shall reject the request.
wind power plant shall be stipulated under the If the request is complete and correct, the
concession agreement. Commission shall propose the Government to
The procedure begins by submitting a re- issue an authorization for the construction of the
quest for the authorisation to the Government. wind power plant within 60 days of the receipt
The request shall be published in the Official of the request. Prior to taking its decision, the
Gazette, and shall be submitted to the Ministry Government shall seek the opinion of the Energy
of Economy. The following documents should be Regulatory Commission.
submitted along with the request (Law on Energy, The authorization shall lay down the follow-
Article 52): ing conditions:
1) Project design and cost-efficiency analysis; 1) The type, characteristics, installed capac-
2) Approval for the connection to the electric- ity and estimated annual generation of
ity transmission or distribution system, electricity;
pursuant to the relevant Grid Code; 2) The location of the plant, in compliance with
3) Decision on the approval of the Environ- the relevant urban planning documents;
mental Impact Assessment Study or of 3) The validity period of the authorisation;
the Environmental Impact Assessment, 4) Conditions for de-commissioning of the
if applicable; wind power plant;
4) Excerpt of the Local Detailed Urban Plan, 5) Conditions for the use of the public infra-
5) Financing plan for the construction of the structure;
wind power plant; 6) Environmental protection requirements;
7) Efficiency requirements concerning the
6) Letter of Intent, issued by a financial in-
operation of the plant; and
stitution or bank, indicating its intention
8) Other terms and conditions related to the
to provide financing to the project,
construction of the plant.
7) Proof of the investor’s equity,
8) Company profile of the investor and its
The authorization for the construction of the
potential partners, and their references
wind power plant shall apply for three years from
related to the implementation of similar
the date of its entry in force. The authorisation
projects;
shall cease to apply if the investor holder failed
9) Investor’s registration documents; to obtain the construction permit for the wind
10) Proof that the applicant is not undergoing power plant in question within three years. The
bankruptcy or liquidation procedure; authorization is transferrable to another entity
11) Proof that the applicant is not subject to subject to an approval by the Government.
misdemeanor or criminal procedure; and The Government may reject the request for
12) Statement of accuracy of the data provided. the authorisation in cases where:
WIND POWER PLANTS 33

1) The Environmental Impact Elaborate Study, been approved by the authorised supervisor, and
or where relevant, the Environmental Im- an use approval has been issued by the Ministry of
pact Assessment, has been rejected; Transport and Communications or the Municipal-
2) The existing urban planning documents ity, as the case may be.
do not provide for the construction of new In case the parcel where the investor intends to
electricity generation facilities; or build is classified as agricultural land (arable land,
3) The applicant fails to demonstrate its abil- forest, pasture or similar), he/she may request the
ity to finance and construction the wind Ministry of Transport and Communications, or
power plant (Law on Energy, articles 54 – 58). the Municipality, as the case might be, to request
the Ministry of Agriculture, Forestry and Water
4.7. Construction permit Economy to permanently convert the relevant
agricultural land into construction land (Law on
A construction permit is required to build a wind Agricultural Land, article 49). The duration for this
power plants. The Municipality on whose territory procedure depend on the complexity to prepare
the wind power plant is envisaged to be located is and review the project documentation. The costs
competent for award of the construction permit for providing the project documentation are borne
regardless of the installed capacity of the future by the investor.
wind power plant (Law on Construction, article 57, 58).
The application for construction permit must 4.8. Award of temporary status
be accompanied by the following documents: of preferential producer
- Excerpt of the Local Detailed Urban Plan,
- Architecture-urban project design (revised The Energy Regulatory Commission has adopted the
and approved), Rulebook on preferential producers of electricity
- Basic project design (revised and approved), from renewable energy sources (Official Gazette No.
- Concept project design, 18/2012, 97/2012, 63/2013 and 25/2015). Pursuant to
- Proof of right to build (ownership, usage the Energy Law and the Rulebook on preferential
right, concession), producers of electricity from renewable energy
- Geodetic survey of the land parcel. sources, the Energy Regulatory Commission shall
issue a decision for the award of a temporary status
The Municipality is obliged to review and of preferential producer, decision for the award of
adopt a decision on awarding the construction status of a preferential producer and a decision for
permit in a period of 15 days after the submitted the use of preferential tariff, and shall publish them
documentation is complete and correct. Prior to on its website, as well as in the Official Gazette. The
receiving the construction permit, the applicant Energy Regulatory Commission shall also publish
must pay a construction fee; the construction on its website the Register of preferential produc-
permit is delivered within five days following the ers, as well as the diagrams of the procedures for
submission of a proof that the construction fee the award of status of preferential producer and
has been paid. the use of the preferential tariff (www.erc.org.mk).
The construction permit may become null and The procedure for the award of the temporary
void if the applicant does not start the construction decision of status of a preferential producer shall
within 2 years, or finish it within six years from commence by the submission of the request to the
the date of issuing the permit (Law on Construc- Energy Regulatory Commission.
tion, article 59 - 68). The wind power plant may be The request shall be submitted to the Energy
put in use only after technical commissioning has Regulatory Commission in written form using the
34 WIND POWER PLANTS

template of the request for the award of a temporary The Energy Regulatory Commission shall hold a
decision for the award of status of a preferential regular session where it shall adopt the temporary
producer, signed and stamped by the applicant decision for the award of status of a preferential
(Template BPRRP). The applicant is obliged to select producer of electricity from renewable energy
and specially mark the confidential documents; sources within 5 (five) days from the date the
in the contrary all documents shall be treated as holding of the preparatory session, at the latest.
non-confidential documents. The temporary decision shall be published in the
The applicant is obliged to submit the following Official Gazette, and shall enter in force on the
information and documents: day of its adoption.
− Request for the award of a temporary decision In the temporary decision the Energy Regu-
for the award of status of a preferential pro- latory Commission shall determine the installed
ducer, signed and stamped by the authorized capacity of the power plant (i.e. of the generation
person; units), as well as the deadline by which the power
− Proof of entry in the Central Registry (original plant must be commissioned. The validity period
document or a notarised copy); of the temporary decision is equal to the dead-
− Proof of compliance with the requirement line for the commissioning of the power plant. In
(valid construction permit or concession this period, the holder of the temporary decision
agreement or public-private partnership is obliged to build the power plant, to obtain a
agreement), original document or a notarised positive technical commissioning report from an
copy; authorized engineer, in accordance with the Law
− Basic project design of the power plant, on Construction and to obtain a license for carrying
prepared by a licensed entity; out of energy activity – generation of electricity.
− Statement of accuracy of the request and the
submitted information and documentation, 4.9. Design and construction
signed by the applicant’s authorized person, of the connection
registered in the Central Registry (template).
Considering that most of the wind power plants
If the Energy Regulatory Commission estab- will be connected to the transmission grid, we
lishes that the request and the documentation shall review the procedure for the design and
are complete, it shall conclude that the request construction of the connection to the transmission
is acceptable and shall continue the procedure in grid. Pursuant to the approval for the connection
accordance with the Rulebook on the licenses for to the transmission grid, the investor and MEPSO
performance of energy activities within 5 (five) days should sign an agreement for connection to the
from the date of receipt of the request. The Energy transmission grid (Electricity Transmission Grid
Regulatory Commission shall submit a copy of the Code, Article 71), which defines:
conclusion to the applicant. − the mutual obligations during the construc-
The Energy Regulatory Commission shall tion of the connection,
schedule a preparatory session that shall take − the acceptance of the project documentation
place within 25 (twenty five) days from the date for the construction of the connection,
of receipt of the request. The Energy Regulatory − the connection-related assets of MEPSO and
Commission shall invite the applicant to attend the investor,
the preparatory session, as well as the authorized − the sharing of costs between MEPSO and the
representatives of interested stakeholders, institu- investor for the construction of the connec-
tions and organizations. tion.
WIND POWER PLANTS 35

occurred during the construction), technical com-


MEPSO is obliged to draft and submit the missioning report and an excerpt of the Cadastre
agreement for connection to the transmission grid proving the ownership or other use rights of the
to the investor within 30 days from the award of ap- facility (Law on Construction, Article 87). In case of
proval for the connection to the transmission grid. incomplete request for use permit, the Ministry
If MEPSO and the investor agree that the inves- of Transport and Communications shall order the
tor should organize and manage the construction applicant to submit full and proper documentation
of the connection to the transmission grid, the within seven days from the receipt of the request
investor must submit to MEPSO the technical for use permit.
specifications of the connection and the entire A three-member commission composed of
documentation necessary for obtaining the con- licensed supervising engineers, appointed by the
struction permit for approval. Considering the Minister of Transport and Communications has
need for coordination of many complex technical to carry out a site inspection upon the receipt of
documents and the need to inform and seek ap- the request for use permit within 15 days from
proval from MEPSO in the procedure for obtaining the receipt of the full and proper request for use
the construction permit for the connection to the permit. The commission verifies that:
transmission grid, we recommend the investors to − the facility has been built in accordance
confer the construction to MEPSO. with the basic project design or, in case of
MEPSO calculates the costs for the connection modifications during the construction, with
to the transmission grid pursuant to the Method- the project design of the finished facility, and
ology for calculating the connection fee, which is in accordance with the construction permit,
an integral part of the Electricity Transmission − the facility is safe and may be used.
Grid Code (Annex 7). The costs for the connection
to the transmission grid are in turn composed of: If the commission established any shortcom-
− The costs for construction of the new con- ings that affect the mechanical stability and re-
nection or upgrade of an existing connection, sistance of the facility, it may request the investor
and to remedy those aspects within 30 days, or it may
− The costs for the creation of technical condi- propose to refuse the issuance of the use permit
tions for increasing the capacity of the trans- (Law on Construction, Article 89-92).
mission system and connection of new users. In case of positive report of the commission,
the Ministry of Transport and Communications
The costs for the connection of the new wind is obliged to issue the use permit within 15 days
power plant to the transmission system are borne from the date of the site inspection. The costs for
by the investor. the site inspection and issuance of the use permit
are borne by the investor.
4.10. Use permit
4.11. Energy generation license
A use permit is required for the official commis-
sioning of the wind power plant. The use permit The requirements for the award of a license for
for wind power plant, as any other power plant electricity generation from renewable sources
with installed capacity greater than 1 MW, is issued are laid down in the Rulebook on the licenses for
by the Ministry of Transport and Communications performance of energy activities (Official Gazette
on the basis of the basic project design (or project No. 141/2011, 78/2013 and 33/2015). The investor
design of the finished facility if major changes may request the award of license for generation of
36 WIND POWER PLANTS

electricity from renewable sources from the Energy − Organizational structure of the applicant,
Regulatory Commission, before the receipt of the including information on the number of
technical commissioning report or use permit personnel, and the education and techni-
issued by an authorized supervising engineer in cal qualifications of the personnel that will
cases where: manage the facility and will use the specific
− The investor has been awarded an authoriza- equipment;
tion for the construction of the energy facility − Project design, construction permit, and – if
in question, pursuant to the Energy Law; or the facility has been already built - a technical
− The investor has been awarded a construction commissioning report or use permit, as well
permit for the energy facility if an authori- as an authorization for construction of the
zation for construction of the facility is not electricity generation facility, if relevant;
warranted, or − Statement on the company’s ownership struc-
− The investor has been awarded the right ture, including information and a detailed
to build the energy facility in a competitive description of the applicant’s share in other
procedure for construction of electricity companies, as well as the share of other
generation facilities, or companies in the applicant’s company;
− The investor has obtained a right to build the − Solvency statement for the applicant, issued
facility on the basis of a concession agreement. by a competent body;
− Proof of paid taxes and other fees, issued by
The investor should submit a request for the the Public Revenue Office;
award of license to the Energy Regulatory Commis- − Financial reports prepared in accordance
sion, accompanied by the following information with the applicable regulations for the past
and documents: three years, including an auditor’s report
− General information for the applicant, from an authorized auditor, if the audit is
− Name of the responsible person, warranted by law;
− Type of the energy activity to be carried out, − Proof that the applicant is not subject to
− Brief description of the license claimed, liquidation procedure;
− Statement of accuracy of the information − Statement from the Central Registry that
and the submitted documents, signed by the the applicant is not banned from carrying
authorized person, out professional activities, and that it is not
− Statement on the time period of the request sentenced for criminal deed.
for the award of the license,
− Proof of payment of the fee for the award of In addition to the above-mentioned documents,
the license, the applicant is also obliged to submit additional
− Proof of entry in the Central Registry, documentation on the specific technology for
− Founding act and/or Statute of the company, generation of electricity and the use of natural
− Evidence of the ownership right or of the resources, in accordance with Article 14 of the
land use right and of the basic capital, Rulebook on the licenses for performance of energy
− Concession agreement if the energy activity activities.
is to be carried out on the basis of exploi- The Energy Regulatory Commission shall ex-
tation of natural resources or concession amine the request for award of license and the
agreement for provision of public service, accompanying documentation and shall adopt a
or proof of the right of exploitation of the Conclusion within 8 days. If the documentation for
natural resources; the award of the license is in compliance with the
WIND POWER PLANTS 37

Rulebook on the licenses for performance of energy Following the receipt of the license for genera-
activities, and other relevant laws and regulations, tion of electricity, the investor may, if the technical
the Energy Regulatory Commission shall oblige the conditions so allow, generate and sell electricity
applicant go prepare a notification for the request before the acquisition of the status of preferential
within 3 days and to submit it to the Energy Regu- producer (refer to 4.13) and before signing the
latory Commission for approval. If the submitted power purchase agreement with MEPSO (refer to
documentation has formal and other omissions, 4.14). For this purpose the investor should sign an
then the Energy Regulatory Commission shall oblige agreement with:
the applicant to remove the shortcomings within − the Operator of the electricity transmission
15 days and to submit a complete documentation system (MEPSO),
in accordance with the Rulebook on the licenses − electricity supplier, or
for performance of energy activities. − electricity trader.
The investor is obliged to publish the request
for the award of license for generation of electricity Such agreement may be with definite duration,
from renewable sources on its expense in at least i.e. until the acquisition of the status of preferential
two daily newspapers on both official languages. producer, or alternatively – with indefinite dura-
The announcement serves to notify the award of tion, if the investor fails to obtain the status of
the license and to invite all interested stakeholders preferential producer or chooses to renounce it.
to comment and to present their case.
Following the publication of the request, the 4.12. Registration of the facility
Energy Regulatory Commission shall schedule a in the Register of electricity
preparatory session that shall take place within 50 generation facilities from
days from the date of submission of the request. renewable energy sources
If the Energy Regulatory Commission establishes
at the preparatory session, that the requirements The investor must register its wind power plant
for the award of the license have been fulfilled, it in the Register of electricity generation facilities
shall schedule a regular session within 10 days to from renewable energy sources, maintained by
formally endorse the decision for the award of the Energy Agency. For this purpose, the investor
the license. should submit a request to the Energy Agency for
The Energy Regulatory Commission shall registration in the Register of electricity generation
publish the decision and the license for energy facilities from renewable energy sources, along
activities in the Official Gazette. with the following documents:
If the license has been awarded prior to the 1. Use approval for the energy facility, or
technical commissioning or receipt of the use per- technical commissioning report, in case
mit, whilst the investor has obtained the technical where the use approval is not required, and
commissioning report and the use permit in the Confirmation from the electricity trans-
meanwhile, the investor should submit these ad- mission system operator that the energy
ditional documents in accordance with Article 32 facility is connected on the appropriate
of the Rulebook on the licenses for performance (transmission or distribution) system,
of energy activities. Following the receipt of the 2. Topographic map, on a scale of 1:25.000 show-
additional documentation, the Energy Regulatory ing the location of the wind power plant,
Commission shall issue the decision on the entry 3. Schematic drawings of the wind power plant
in force of the previously awarded license within and the installed equipment, in particular
8 days from the date of submission. the metering equipment, and
38 WIND POWER PLANTS

4. Copy of the license for electricity generation hold a license for carrying out energy activity – gen-
(Rulebook on renewable sources of energy, eration of electricity for the power plant in question.
article 8). The requests shall be submitted to the En-
ergy Regulatory Commission in written form, on
If the Energy Agency establishes that the a template for the request of a decision for the
request is incomplete, it shall notify the appli- award of status of a preferential producer, signed
cant and invite him to complete the necessary and stamped by the applicant (Template BRPP), as
documentation within 30 days from the day of well as a filled-in template for the request for the
the submission of the notification. Should the use of preferential tariff, signed and stamped by
applicant fails to complete the documentation the applicant (Template BKPT).
within the specified deadline, the Energy Agency The applicant is obliged to select and especially
will reject the request, as incomplete. mark the documents with confidential information;
If the Energy Agency establishes the request in the contrary, all submitted documents shall be
and the accompanying documentation is complete treated as non-confidential. The requests for the
and correct, and that all conditions for awarding use of preferential tariff relate to the tariff that
the status of preferential producer are met, it shall applied on the date of adoption of the temporary
adopt a decision for registering the applicant in the decision for the award of status of a preferential
Register of preferential producers of electricity producer of electricity.
within 15 days of the date of submission of the re- The applicant is obliged to accompany the re-
quest. The Energy Agency may decide to perform an quest with the following information and documents:
on-site inspection of the facility prior to the award − Project design of the constructed facility in
of the decision. The Energy Agency shall submit accordance with the Law on Construction, if
the investor the Resolution for registration in the modifications from the basic project design
Register of preferential producers of electricity have been made during the construction;
within three days of the date of adoption of the − Proof of entry in the Register of producers of
decision. The investor shall be registered under a electricity from renewable energy sources, is-
unique registration number, which may not change sued by the Energy Agency, in accordance with
or be transferred (Rulebook on renewable sources of the Rulebook on renewable energy sources;
energy, article 9). − Proof of payment of the fee in accordance
with Article 13-a of the Rulebook on preferen-
4.13. Award of status of tial producers of electricity from renewable
preferential producer energy sources;
− Statement of accuracy of the request and
Following the receipt of the temporary decision the submitted information, signed by an
for the award of status of a preferential producer authorized representative of the applicant,
of electricity from renewable energy sources, the registered at the Central Register.
investor should request the award of status of a
preferential producer of electricity from renewable The submitted documents should be the origi-
energy sources and should simultaneously submit nal document or notarised copy.
a request for the use of preferential tariff for elec- In addition to the requests, the applicant is
tricity obtained from renewable energy sources. obliged to submit a proof that he/she has transferred
As a prerequisite, the power plant should be com- an irrevocable monetary fee to the account of the
missioned within the deadline established in the Energy Regulatory Commission to cover the costs
temporary decision, whereas the applicant should borne during the procedure (the Energy Regulatory
WIND POWER PLANTS 39

Commission should actually transfer this fee to the applicant and to submit it the draft decision for
Energy Agency pursuant to the tariff adopted by the award of status of preferential producer and
the Energy Agency). draft decision for the use of preferential tariff of
The procedure for the award of status of pref- electricity from renewable energy sources not
erential producer and the adoption of the decision later than 7 (seven) days before the holding of the
for the use of the preferential tariff comments on preparatory session. In addition to the applicant,
the date of receipt of the request in the archive of the Energy Regulatory Commission may also invite
the Energy Regulatory Commission. authorized representatives of interested stakehold-
Following the receipt of the requests, the ers, institutions and organizations.
Energy Regulatory Commission shall establish if The Energy Regulatory Commission shall hold
the documentation is complete and if it is submit- a regular session within 5 (five) days from the date
ted in the proper procedure and form. The Energy of holding of the preparatory session to formally
Regulatory Commission shall request a confirma- adopt the Decision for the award of status of a
tion from the Energy Agency within 5 (five) days preferential producer of electricity from renew-
from the date of receipt of the requests, that the able energy sources and the Decision for the use
power plant has been built and that it complies of preferential tariffs for electricity obtained from
with the specific requirements, in particular on renewable energy sources.
the installed capacity, laid down in the Ordinance, The decisions shall be published in the Official
that applied on the date of issuing of the temporary Gazette, as well as on the website of the Energy
decision for the award of status of a preferential Regulatory Commission. On the day of entry on
producer. The Energy Agency is obliged to issue the force of the decision, the Energy Regulatory Com-
confirmation not later than 15 (fifteen) days from mission shall enter the information related to the
the date of receipt of the request by the Energy applicant and the power plant, as well as to the
Regulatory Commission. For the issuing of the applicable preferential tariff in the Register of
confirmation, the Energy Regulatory Commission preferential producers. The Energy Regulatory
pays a fee to the Energy Agency, in accordance with Commission shall submit the decisions to the ap-
the tariffs adopted by the Energy Agency, reflecting plicant, to the Electricity Market Operator and to
the costs of the Energy Agency in the procedure the Energy Agency.
for the issuing of the confirmation.
If the Energy Regulatory Commission estab- 4.14. Power purchase agreement
lishes that the requests and the documentation are with the electricity
complete and do not have any shortcomings, and market operator
if the conformation issued by the Energy Agency
is positive, the Energy Regulatory Commission The electricity market operator (MEPSO) is obliged
conclude within 20 (twenty) days from the date of to purchase the entire electricity generated by the
receipt of the requests that the documentation is preferential electricity producers pursuant to an
complete and that the procedure may continue. agreement, in accordance with the Energy Law,
The Energy Regulatory Commission shall submit the Decision on the application of feed-in tariff
a copy of the conclusions to the applicant. issued by the Energy Regulatory Commission and
The Energy Regulatory Commission shall the Electricity Market Rules. The investor should
schedule a preparatory session to examine the submit a request for signing a power purchase
requests within 35 (thirty five) days from the date agreement to MEPSO.
of receipt of the requests at the latest. The Energy MEPSO is obliged to sign the power purchase
Regulatory Commission is obliged to invite the agreement within 30 days from the date of receipt
40 WIND POWER PLANTS

of the request. The power purchase agreement must This step marks the end of the application
enter in force on the day the Decision on awarding process. After the acquisition of the status of
the status of preferential electricity producer was preferential producer, the investor may apply and
issued by the Energy Regulatory Commission. use the feed-in tariffs laid down in the Ordinance
The investor may decide to terminate the on preferential tariffs for electricity (Article 7).
power purchase agreement, thereby losing the The exact feed-in tariff applicable to the genera-
status of preferential electricity producer and tion facility depends on the monthly amount of
the right to obtain the status again (Energy Law, electricity generated and sold per each block.
Article 153). Depending on the amount of electricity generated
The investor is obliged to sell the entire each month, the actual feed-in tariff applicable
amount of electricity generated to MEPSO, and to the facility may vary. The feed-in tariffs apply
to submit electricity generation plans to MEPSO. for a period of 20 years.

5. Award of guarantees of origin for


the electricity generated from
renewable energy sources

In case where the investor did not succeed in sources of energy. It should be noted that the pref-
acquiring a status of preferential producer of erential tariff is incompatible with the guarantee
electricity and thereby benefit from the prefer- of origin – the investor may either use one or the
ential tariff, or if the investor has voluntarily other. If the investor uses the preferential tariff,
abandoned the power purchase agreement with he/she may not apply for guarantees of origin.
the electricity market operator (see chapter 4.15. Where relevant, the investor should submit
above), the investor may apply for guarantees of a request for the award of guarantees of origin
origin to claim premium price for the electricity for the electricity generated in its wind power
generated in his wind power plant. plant to the Energy Agency. The request should
Guarantees of origin are usually warranted be accompanied by:
by electricity transmission system operators or − A proof of paying the fee for the issuance of
electricity traders that are under obligation to guarantees of origin, and
pay premium prices for electricity generated from − A proof of the electricity transmission or
renewable sources of energy. It should be noted distribution system operator for the quan-
that the preferential tariff is incompatible with the tity of electricity generated and sold by the
guarantee of origin – the investor may either use facility.
one or the other. If the investor uses the preferential
tariff, he/she may not apply for guarantees of origin. If the Energy Agency establishes that all condi-
The manner and procedure for the award of tions for the award of the guarantees of origin for
guarantees of origin is governed by the Rulebook the electricity generated from renewable energy
on renewable sources of energy. Where relevant, sources are fulfilled, it shall award the decision
Guarantees of origin are usually warranted by elec- within 30 days from the date of receipt of the request.
tricity transmission system operators or electricity A guarantee of origin is issued per 1 MW.
traders that are under obligation to pay premium The guarantees of origin are valid for a period
prices for electricity generated from renewable of 12 months.
WIND POWER PLANTS 41

6. Addresses and contact details of


competent institutions

6.1. Government of the RM 6.6. Distribution System Operator/


Address: blvd Ilinden, 2 Supplier (EVN Macedonia)
1000 Skopje Address: 11 Oktomvri, 9
Telephone: + 389 02 31 18 022 1000 Skopje
Website: www.vlada.mk Telephone: + 389 2 3205 000
E-mail: info@evn.mk
6.2. Ministry of Economy, Website: www.evn.mk
Department of Energy
Address: Jurij Gagarin, 15 (1st floor) 6.7. Ministry of Environment
1000 Skopje and Spatial Planning
Telephone: + 389 2 3093 485, Address: Goce Delcev, 18
+ 389 2 3093 485 1000 Skopje
E-mail: info@economy.gov.mk Telephone: + 389 2 32 51 403,
+ 389 2 32 51 503,
Website: www.economy.gov.mk
+ 389 2 32 51 460
Website: www.moepp.gov.mk
6.3. Energy Agency
Address: Orce Nikolov, 68
6.8. Ministry of Transport and
1000 Skopje
Communications
Telephone: + 389 2 32 30 300
Address: Dame Gruev, 6
E-mail: ea@ea.gov.mk
1000 Skopje
Website: www.ea@ea.gov.mk
Telephone: + 389 2 3145 497,
+ 389 2 3123 292
6.4. Energy Regulatory Commission
Website: www.mtc.gov.mk
Address: Dimitrie Cupovski, 2, 4th floor
1000 Skopje 6.9. Ministry of Agriculture, Forestry
Telephone: + 389 2 32 33 580, and Water Economy
+ 389 2 32 54 010 Address: Aminta Treti, 2
E-mail: erc@erc.org.mk 1000 Skopje
Website :www.erc.org.mk Telephone: + 389 2 31 34477
E-mail: info@mzsv.gov.mk
6.5. Electricity Market Operator/ Website: www.mzsv.gov.mk
Transmission System Operator (MEPSO)
Address: Maksim Gorki, 4 6.10. Central Register
1000 Skopje Address: Kuzman Josifovski Pitu, 1
Telephone: + 389 2 31 49 811 1000 Skopje
E-mail: info@mepso.com.mk Telephone: + 389 2 3288100
Website: www.mepso.com.mk Website: www.crm.com.mk
42 WIND POWER PLANTS

7. Relevant legislative and


regulatory acts
Law on Energy (Official Gazette No. 16/2011, 136/2011, land in the airport zone and the land in its
79/2013, 164/2013, 41/2014 and 151/2014) immediate proximity (Official Gazette, No.
Ordinance on preferential tariffs for electricity 130/2007 and 156/2012)
(Official Gazette, No. 56/2013) Ordinance on the procedure for selling, long-term
Decision on the total installed capacity of preferen- lease and short-term lease of State-owned
tial producers of electricity generated from construction land, by public bidding, solici-
each specific renewable source of energy tation of offers and by direct agreement, the
(Official Gazette No. 56/2013 and 10/2014) costs for the sale and lease procedure, and the
price of the land and lease (Official Gazette,
Law on Construction (Official Gazette No. 130/2009,
No. 147/2008, 71/2009, 16/2009, 162/2009,
124/2010, 18/2011, 36/2011, 54/2011, 13/2012,
113/2010, 148/2010, 172/2010 and 40/2011)
144/2012, 25/2013, 79/2013, 137/2013, 163/2013,
27/2014, 28/2014, 42/2014, 115/2014, 149/2014, Law on ownership and other real rights (Official
187/2014 and 44/2015) Gazette, No. 18/2001, 92/2008, 139/2009 and
35/2010)
Law on Construction Land (Official Gazette No.
82/2008, 143/2008 and 56/2010) Ordinance on types of projects and the criteria
for establishing the need for conducting the
Law on Agricultural Land (Official Gazette No. 135/07,
procedure of environmental impact assess-
18/11, 148/11, 95/12, 79/13, 87/13, 106/13, 164/13,
ment (Official Gazette No. 74/2005)
39/14, 130/14 and 166/2014)
Rulebook on the form and content of the elaborate
Law on Forests (Official Gazette No. 64/2009, 24/2011,
study for the protection of the environment,
53/2011, 25/2013, 79/2013, 147/2013, 43/2014,
the procedure of its approval and the manner
160/2014, 33/2015 and 44/2015)
of keeping the Register of approved elaborate
Law on Environment (Official Gazette No. 53/2005, studies (Official Gazette No. 50/2009)
81/2005, 24/2007, 159/2008, 83/2009, 48/2010,
Rulebook on the licenses for performance of en-
124/2010, 51/2011, 123/2012, 93/2013, 187/2013,
ergy activities (Official Gazette, No. 143/2011,
42/2014)
78/2013 and 33/2015)
Law on Spatial and Urban Planning (Official Gazette
Rulebook on renewable sources of energy (Official
No. 199/2014 and 44/2015)
Gazette, No. 113/2011)
Rulebook on the form and content of the application,
Rulebook on preferential producers of electricity
documentation and form of the approval for
from renewable energy sources (Official Ga-
the construction of facilities and installation
zette, No. 18/2012, 97/2012, 63/2013, 41/2014,
of equipment for which a construction permit
151/2014 and 26/2015)
is not required (Official Gazette, No. 147/2009)
Electricity Market Rules (Official Gazette, No.
Rulebook on the conditions for the placement,
38/2014, 57/2014 and 194/2014)
construction and designation of facilities,
installations and devices in the zone of an Electricity Distribution Grid Code (Official Gazette,
airport, facilities and flight control devices No. 87/2012, 30/2014, 161/2014, 189/2014 and
and facilities outside the airport zone, that 50/2015)
can affect the safety of air traffic and on the Electricity Transmission Grid Code (2015)
conditions and manner of treatment of the
MANUAL
për procedurat për zhvillimin dhe ndërtimin e
centraleve për prodhimin e energjisë elektrike nga
burimet të ripërtëritshme të energjisë
CENTRALET ME ERË
44 CENTRALET ME ERË

Përmbajtja

1. Hyrja............................................................................................................................... 45
2. Shqyrtimi i tarifave të zbatueshme për hidrocentralet................................................... 46
3. Diagram i hollësishëm për procedurën dhe dokumentet për ndërtim..............................47
4. Shqyrtimi i hapave, procedurave dhe dokumenteve........................................................ 48
4.1. Parakushtet kryesore: Themelimi i kompanisë....................................................... 48
4.2. Koncesion për përdorimin e ujit për prodhimin e energjisë elektrike..................... 48
4.3. Shndërrimi i tokës.................................................................................................. 50
4.4. Studim për vlerësimin e ndikimit mbi mjedisin jetësor............................................ 51
4.5. Miratim për ndërtim................................................................................................52
4.6. Marrja e statusit të përkohshëm të prodhuesit të autorizuar...................................52
4.7. Pëlqim për kyçje në sistemin distribuues................................................................ 54
4.8. Projektimi dhe zbatimi i impiantit...........................................................................55
4.9. Miratim për përdorim..............................................................................................55
4.10. Licencë për prodhimin e energjisë elektrike........................................................... 56
4.11. Regjistrimi i objektit në Regjistrin e objekteve për prodhimin e
energjisë elektrike nga burime të ripërtëritshme të energjisë................................ 58
4.12. Marrja e statusit prodhues i autorizuar.................................................................. 58
4.13. Marrëveshje për blerjen e energjisë elektrike me ndonjë
operator në tregun e energjisë elektrike................................................................. 60
5. Sigurimi i garancive për prejardhjen e energjisë elektrike të
prodhuar nga burimet të ripërtëritshme të energjisë......................................................61
6. Adresa dhe të dhëna kontaktuese të institucioneve kompetente.................................... 62
7. Legjislatura relevante dhe aktet rregullatore................................................................. 63

Ky publikim është përgatitur me ndihmën e Bashkimit Evropian. Përmbajtja e këtij publikimi është përgjegjësi
vetëm e ATC Consultants dhe partnerëve të saj të konsorciumit dhe në asnjë mënyrë nuk pasqyron pikëpamjet e
Bashkimit Evropian.
CENTRALET ME ERË 45

1. Hyrje

Ky manual ka për qëllim të sigurojë rekomandime VËREJTJE:


të hollësishme për investitorët në procesin e
zhvillimit dhe zbatimit të projekteve për burime Ky Manual nuk përqendrohet në çështjet lidhur
të ripërtëritshme të energjisë, më konkretisht të me:
hidrocentraleve. Manuali nuk paraqet shqyrtim të − themelimin e kompanisë apo themelimin
thuktë dhe të thellë. Për informacione më të thukëta e filialeve të huaja në vendin shfrytëzues
përqendrohuni në legjislaturën relevante dhe aktet të projektit dhe punën e tyre;
rregullatore të cilat janë në fund të këtij Manuali. − marrjen e miratimit për ndërtim,
− marrjen e licencave për kuadrin profesional
Manuali është strukturuar në tre pjesë: dhe lejeve të tjera të punës dhe sociale,
Në pjesën e parë është dhënë shqyrtimi i − pronësinë e tokës, tjetërsimin dhe të drejta
tarifave të aplikueshme për të gjitha projektet të tjera pronësore,
për burimet të ripërtëritshme të energjisë, − Tatimin,
duke i përfshirë edhe tarifat e autorizuara për − Rregulloren për ndihmë shtetërore, etj.
hidrocentralet e vogla.
Në pjesën e dytë është dhënë një diagram Megjithatë, duhet ta keni parasysh se këto
i hollësishëm i procedurave për ndërtim dhe janë çështje të rëndësishme të cilat çdo investitor
dokumentet e nevojshme. duhet t’i analizojë me kujdes kur përgatit ndonjë
Në pjesën e tretë është dhënë shqyrtim i projekt për hidrocentralet.
hollësishëm i procedurave dhe kërkesave relevante
për ndërtimin, lëshimin në përdorim dhe
funksionimin e hidroentraleve të vogla. Lexuesin
e udhëzojmë vazhdimisht ta konsultojë këtë pjesë
dhe diagramin e hollësishëm, i cili është dhënë
në pjesën e dytë.
Në fund të manualit është dhënë listë me
organet kompetente me adresat dhe të dhënat
kontaktuese si dhe një listë me të gjitha ligjet
relevante dhe aktet e tjera rregullatore.

Rekomandimi ynë është që investitorët t’i konsultojnë organet kompetente për potencialin dhe
procedurat për ndërtimin e hidrocentralit para fillimit të procedurës si dhe gjatë procedurave
për mbështetje më të drejtpërdrejt në procesin e aplikimit.
46 CENTRALET ME ERË

2. Shqyrtimi i tarifave të zbatueshme


për centralet me erë

Tarifat e autorizuara të energjisë elektrike të cilën e prodhojnë dhe shesin centralet me erë (të cilat e
kanë marrë statusin e prodhuesit të autorizuar) janë përcaktuar në Dekretin mbi tarifat e autorizuara
për energji elektrike (Gazeta zyrtare nr. 56/2013) dhe është siç vijon:

Fuqia instaluese e centralit me erë 0 – 50 MW

Tarifa e autorizuar (€¢/kWh) 8.9

Kohëzgjatja e tarifës së autorizuar 20 vjet

Kuota e centraleve me erë të cilat mund të përdorin tarifa të autorizuara është përcaktuar në
Vendimin për fuqinë instaluese të përgjithshme të prodhuesve të autorizuar të energjisë elektrike e
prodhuar nga çdo burim i ripërtëritshëm i energjisë (Gazeta zyrtare nr. 56/2013 dhe 10/2014) siç vijon:

deri më 31 dhjetor deri më 31 dhjetor deri më 31 dhjetor


Periudha
2016 2020 2025
Kuota (Fuqia instaluese e
65 MW 100 MW 150 MW
centraleve me erë)

Në momentin e përgatitjes së këtij Manuali e deri më 31 dhjetor 2016, 13,2 MW akoma ishin në
dispozicion për centralet me erë të sapondërtuara1. Kuota do të rritet për 35 MW në vitin 2017, dhe
për 50 MW në vitin 2021.

Investitorët e mundshëm duhet ta dinë se korporatës në pronësi shtetërore ELEM i është dhënë licencë për
1

ndërtimin e centraleve të erës me një kapacitet total të instaluar prej 50 MW. ELEM shfrytëzoi 36,8 MW të
licencës së saj me lëshimin në përdorim të turbinave me erë në Bogdanci në vitin 2013. ELEM është duke
planifikuar që t›i shfrytëzojë 13,2 MW të mbetura për central të erës në periudhën pas vitit 2016.
3. Diagram i hollësishëm për procedurën dhe dokumentet për ndërtim
Kohëzgjatja Kohëzgjatja
Viti Viti 1 Viti 2 Viti 3 Viti 4 Viti 5
Muaj 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Procedura Institucioni kompetent
4.1 Themelimi i kompanisë 6.1
Matja e potencialit të erë për 1
4.2 6.3 Matja e potencialit të erës (minimum 2 vjet)
prodh. e Energjisë elektrike
6.1, 6.8, 6.9 ose
4.3 Përdorimi i tokës komuna 2
Miratim për kyçje në
4.4 Sistemin për përçues apo për 6.5 ose 6.6
distribuim

4.5
Studim për vlerësimin e ndikimit 6.7 ose komuna
mbi mjedisin jetësor
4.6 Autorizim për ndërtimin e 6.1 3
centralet me erë
4.7 Miratim për ndërtim 6.8 ose komuna 4
PROCESI I NDËRTIMIT

4.8
Marrja e statusit të përkohshëm 6.4
të prodhuesit të autorizuar
Projektimi dhe zbatimi i 6.5, 6.6 ose kompani
4.9 5
impiantit e autorizuar

4.10 Miratim për përdorim 6.8 ose komuna

Licencë për prodhimin e


4.12 6.4
energjisë elektrike
Regjistrimi i objektit në Regjistrin
CENTRALET ME ERË

e objekteve për prodhimin e


4.13 6.3
energjisë elektrike nga burime të
ripërtëritshme të energjisë
Ndarja e statusit të prodhuesit
4.14. të autorizuar 6.4

Marrëveshje për blerjen e


4.15 energjisë elektrike me operatorët 6.5
e tregut të energjisë elektrike

Fillimi i prodhimit dhe shitjes


së energjisë elektrike

Legjenda:

:
Rreziku 1: Rezultatet e matjes mund të mos e Rrezik 4: Pamundësia për t’u marrë miratim
Kohëzgjatja e procedurës 1 4
mbështesin zbatimin e projektit për këtë lokacion për ndërtim apo vonesë e paparashikuar

Kohëzgjatja e matjes së potencialit të erës për prodhimin e energjisë Rreziku 2: Pamundësia për të fituar të drejtën për shfrytëzimin e tokës Rreziku 5: Rritja e shpenzimeve për kyçje nëse nuk është
elektrike (minimum dy vjet) 2 ndërtimore, vonesë apo pasiguri nga rezultatet dhe shpenzimet 5 e mundur të bëhet lidhshmëria në impiantin më të afërt

Rreziku 3: Pamundësia për t’u plotësuar kërkesat për ndarjen


Punime ndërtimore 3 Fillimi i prodhimit dhe shitja së energjisë elektrike
e autorizimit për ndërtimin e një centrali të ri me erë
47
48 CENTRALET ME ERË

4 Shqyrtimi i hapave, procedurave


dhe dokumenteve
4.1. Parakushtet kryesore: zim i atillë nuk është i nevojshëm kur projekti
Themelimi i kompanisë kushtëzohet me nevojën e sigurimit të konce-
sionit për përdorimin e ujit, që është parakusht
Prodhim të energjisë elektrike mund të bëjnë për ndërtimini e hidrocentraleve. Në kushte të
persona vendorë dhe të huaj në bazë të licencës së këtilla, kushtet për ndërtimin e hidrocentralit për-
lëshuar nga Komisioni rregullator për energjetikë. caktohen në dokumentacionin e tenderit dhe në
Për të marrë licencën për prodhimin e energjisë marrëveshjen e koncesionit (Ligji për energjetikë,
elektrike, personat e huaj duhet të themelojnë neni 49).
filial (nëndegë) të regjistruar në regjistrin tregtar
të cilin e udhëheq Regjistri qendror (Ligji për 4.2. Koncesion për shfrytëzimin
energjetikë, neni 5). Në fakt, ky parakusht shpesh ci- e ujit për prodhimin e
tohet në dokumentacionin e tenderit për marrjen energjisë elektrike
e koncesionit për përdorimin e ujit për prodhimin
e energjisë elektrike, i cili, ndër të tjerash, është Shfrytëzimi i ujërave për prodhimin e energjisë
edhe parakusht për ndërtimin e hidrocentralit. elektrike mund të bëhet vetëm në bazë të lejës për
Kjo kërkesë kontrollohet duke e shqyrtuar cer- shfrytlëzimin e ujit, përkatësisht me koncesionin
tifikatën në Regjistrin qendror. për shfrytëzimin e ujit për prodhimin e energjisë
Prodhimi i energjisë elektrike nuk mund të elektrike (Ligji për ujëra, neni 53).
fillojë para se të merret licenca përkatëse. Licenca Koncesionin e jep Qeveria në procedurën e
për veprimtari energjetike jepet për periudhë prej dhënies së koncesionit. Procedurën e tenderit dhe
tre deri në 35 vjet varësisht prej llojit të veprim- koncesionin e shfrytëzimit të ujit për prodhimin e
tarisë energjetike, llojit dhe vëllimit të obligimit energjisë elektrike e udhëheq Ministria e Mjedisit
për sigurimin e shërbimit publik në kryerjen e Jetësor dhe Planifikim Hapësionor.
veprimtarisë energjetike, vëllimin e mjeteve të Duhet të keni parasysh se koncesioni jepet
nevojshme për zbatimin e veprimtarisë energje- në procedurë për dhënien e koncesionit, që do
tike, kohëzgjatjen e së drejtës për shfrytëzimin/ të thotë se më shumë shtrues mund të aplikojnë
koncesionin e burimit përkatës energjetik, si dhe për të. Gjithashtu duhet ta keni parasysh se Qe-
kërkesa konkrete të zbatuesit të veprimtarisë veria mund ta refuzoj koncesionin për shkak të
energjetike. Kohëzgjatja e zakonshme e licencës mangësive ose gabimeve eventuale në dokumen-
për prodhimin e energjisë elektrike është 35 tet e patjetërsueshme, mosplotësimin e ndonjë
vjet. Personit të njëjtë mund t’i jepen më shumë kërkese si dhe për gjetje personale. Kjo paraqet
licenca për zbatimin e veprimtarive energjetike imperativ që të përgatitet dhe të dorëzohet ofertë
(Ligji për energjetikë, neni 37). e plotë dhe e saktë dhe të propozohet kompensim
Hidrocentrali i vogël (me fuqi instaluese konkurrues i koncesionit i cili do të mundësojë
për prodhimin e energjisë elektrike prej 10 kryerje të qëndrueshme të veprimtarisë. Sidoqoftë,
MW) mund të ndërtohet pa „autorizimin për çdo investitor i interesuar duhet të presë prej
ndërtimin e objekteve të reja për prodhimin e Qeverisë thirrje për dorëzimin e ofertave për
energjisë elektrike“ të cilën e lëshon Qeveria me dhënien e koncesionit për shfrytëzimin e ujit për
propozimin e Ministrisë së Ekonomisë. Autori- prodhimin e energjisë elektrike në lokacionet që
CENTRALET ME ERË 49

janë përzgjedhur, të përgatitura me ligj dhe të kërkojë mendim prej palëve të interesuara në
propozuara prej Qeverisë. afat prej 15 ditëve.
Kur shtruesi do të përzgjidhet si ofrue- Ministria e Mjedisit Jetësor dhe Planifiki-
si më i volitshëm, marrëveshja e koncesionit mit Hapësinor është obligohet t’ia jap lejen për
nënshkruehet vetëm pasi të përmbushen kërkesat shfrytëzimin e ujit shtruesit në afat jo më të gjatë
e nevojshme për marrjen e lejës përkatëse për se tre muaj prej ditës së pranimit të kërkesës dhe
shfrytëzimin e ujit për prodhimin e energjisë pasi që t’i ketë marrë parasysh të gjitha mendimet
elektrike (Ligji për ujërat, neni 23). Këto kërkesa e dhëna prej organeve kompetente dhe palëve të
janë përcaktuar në dokumentacionin e tenderit. interesuara. Leja për shfrytëzimin e ujit hyn në
Kohëzgjatja maksimale e koncesionit për fuqi pas pranimit të raportit pozitiv nga kontrolli
shfrytëzimin e ujit për prodhimin e energjisë i kryer në objekt dhe pajisjet nga ana e Komisionit
energjike është në vijim: prej pesë antarëve i përbërë prej përfaqësuesve
− Për hidrocentralet me fuqi prej 2 deri 10MW të emëruar nga Ministria e Mjedisit Jetësor dhe
– 50 vjet, Planifikimit Hapësinor. Leja për shfrytëzimin e
− Për hidrocentrale me fuqi deri 2 MW – 30 ujit jepet me kohëzgjatje të kufizuar varësisht
vjet. (Ligji për ujërat, neni 57). prej karakteristikave specifike të objektit, por
Gjegjësisht, kohëzgjatja e zakonshme e kon- jo më gjaët se 10 vjet (Ligji për ujërat, neni 28-41).
cesionit për shfrytëzimin e ujit për prodhimin Leja për shfrytëzimin e ujit ndër të tjerash
e energjisë elektrike për hidrocentrale të vogla mund të mos vlejë nëse:
është 23 vjet. − shfrytëzuesi nuk fillon me aktivitetet për
ndërtim në afat prej dy viteve prej ditë së
Kusht për dhënien dhe nënshkrimin e dhënies së lejës,
marrëveshjes së koncesionit për shfrytëzimin − shfrytëzuesi nuk i ka mbaruar aktivitetet
e ujit për prodhimin e energjisë elektrike është për ndërtim në afatin e caktuar me leje,
marrja e lejës për shfrytëzimin e ujit të cilën e − shfrytëzuesi nuk e shfrytëzon ujin pa shkaqe
jep Ministria e Mjedisit Jetësor dhe Planifikimit të arsyeshme në periudhë me të gjatë se dy vjet.
Hapësinor (Ligji për ujërat, neni 56). − leja e dhënë nuk përputhet më me ndryshi-
Shtruesi dorëzon deri te Ministria e Mjedi- met dhe plotësimet e planit(-eve) për me-
sit Jetësor dhe Planifikimit Hapësinor kërkesë naxhimin e pellgjeve lumore, falimentimi i
për marrjen e lejes për shfrytëzimin e ujit, së shfrytëzuesit të ujit (Ligji i ujërave, neni 47).
bashku me kushtet për ekonomizim të ujërave
për projektim dhe kushtet për mbrojte të ekosiste- Leja për shfrytëzimin e ujit merrat përderisa:
meve të cilat varen prej ujit. Ministria e Mjedisit − uji shfrytëzohet në kundërshtim me kushtet
Jetësor dhe Plnaifikimit Hapësinor obligohet e përcaktuara në leje,
të fillojë të veprojë për kërkesën në afat prej 7 − shfrytëzuesi nuk ka paguar kompensim për
ditëve prej datës së pranimit, dhe nëse është e shfrytëzimin e ujit,
nevojshme, t’i rekomandojë shtruesit përsëri − Shfrytëzuesit i është shqiptuar sanksion
të dorëzojë disa dokumente dhe informata të kundërvajtës ndalëse për zbatimin e ve-
cilat kanë munguar ose kanë qenë të gabuara. primtarisë në lidhje me shfrytëzimin e ujit
Ministria e Mjedisit Jetësor dhe Planifikimit (Ligji për ujërat, neni 51).
Hapësinor është obligohet ta publikojë kërkesën
për dhënien e lejës për shfrytëzimin e ujit në Përveç kësaj, në rast të mungesës së ujit të
ueb faqen e saj, si dhe në shtypin ditor dhe të pijshëm, Ministria e Mjedisit Jetësor dhe Planifi-
50 CENTRALET ME ERË

kimit Hapësinor mund të bëjë ndryshim të lejes Afati i dorëzimit të ofertave është se paku
për shfrytëzimin e ujit dhe t’i limitojë sasitë e 30 ditë. Nëse dokumentacioni i tenderit nuk për-
ujit të cilat janë të disponueshme për prodhi- caktohet ndryshe, afati për vlerësimin e ofertave
min e energjisë elektrike. Ngjashëm me këtë, është 30 ditë. Marrëveshja për koncesion mund
Qeveria mund ta marrë lejen për shfrytëzimin të nënshkruhet kur vendimi i ofertës më të mirë
e ujit përshkak të sigurimit të intersit më të bëhet në formë të prerë, përkatësisht kur do të
lartë publik. Në këto raste, shfrytëzuesi mund shtrerohen të gjitha të drejtat për paraqitjen e
të kërkojë kompensim të dëmit në pajtueshmëri ankesës. (Ligji për koncesion dhe partneritet publik
me rregullat e përgjithshme për kompensimin e privat, neni 30, 35, 36).
dëmit (Ligji për ujërat, neni 47 dhe 52). Ta keni parasysh se koncesioni shfuqizohet
Shfrytëzuesit e ujit, duke i përfshirë edhe në rastet kur:
shfrytëzuesit e ujit për prodhimin e energjisë − Leja për shfrytëzimin e ujit është e pezulluar
elektrike, janë të obliguar të paguajnë kompensim apo ka skaduar
për shfrytëzimin e ujit. Obligimi për pagimin e − Koncesioneri nuk ka filluar me kryerjen
kompensimit për shfrytëzimin e ujit fillon prej e veprimtarive për koncesion në afatin e
kur leja fillon të prodhojë veprim ligjor. Shuma e caktuar në marrëveshjen e koncesionit,
kompensimit që paguhet për shfrytëzimin e ujit − Me skadimin e afatit të vlefshmërisë të
për prodhimin e energjisë elektrike është 1% prej paraparë në marrëveshjen e koncesionit,
çmimit prodhues tpër një orë kilovat të pragut − Me blerjen e parakohshme të koncesionit
të hidrocentralit. Prodhuesi i energjisë elektri- për interes publik,
ke është i obliguar ta paguaj kompensimin për − Në rast të prishjes së njëanëshme të
shfrytëzimin e ujit një herë në muaj në llogari të marrëveshjes së koncesionit,
veçantë për pagesë në kornizat e llogarisë trezore − Me falimentimin ose likuidimin e
(Ligji për ujërat, neni 213). koncesionarit,
Në rast të koncesionit për shfrytëzimin e − Raste të tjera të parapara në marrveshen
ujit, koncesioneri është i obliguar të paguaj kom- për koncesion.
pensim për shfrytëzimin e ujit (i definuar në
lejen për shfrytëzimin e ujit) dhe kompensim të 4.3. Shndërrimi i tokës
koncesionit. Kompensimi i koncesionit përbëhet
prej dy pjesëve, duke përfshirë: Zakonisht, toka e cila është përkatëse për ndërti-
− Kompensim i njëhershëm i cili paguhet me min e hidrocentraleve të vogla është tokë bujqëso-
dhënien e koncesiont, dhe re (kullota, tokë e përpunueshme, pyje etj) në
− Kompensim vjetor i cili paguhet për çdo pronë shtetërore. Në këtë rast, investitori duhet
vit gjatë kohëzgjatjes së koncesionit. të kërkojë inicimin e dy procedurave:
1. Shndërrimin e tokës bujqësore në tokë
Zbatuesi është i obliguar ta paguaj kompen- ndërtimore, dhe
simin e koncesionit prej më herët, si kompensim 2. Blerjen, qira afatgjate apo marrëveshje për
fillestar ose me këste. Shuma e kompensimit të koncesion për shfrytëzimin e tokës.
njëfishtë për prodhimin e energjisë elektrike nuk
duhet të jetë më e vogël se shuma e dhjetëfishtë e Nëse parcela(t) e tokës në të cilën investitori
kompensimit vjetor sipas vlerësimit të arritjeve ka për qëllim ta ndërtojë hidrocentralin e vogël
në vitin e parë të shfrytëzimit (Ligji për ujërat, është klasifikuar si tokë bujqësore (tokë e përpu-
neni 58). nueshme, pyje, kullota etj.), investitori mund të
CENTRALET ME ERË 51

shtrojë kërkesë deri te Ministria e Transportit dhe madhësinë e projektit dhe të sipërfaqes
dhe Lidhjeve apo deri te Komuna, varësisht rastit së nevojshme të tokës;
të kërkojë, nga Ministria e Bujqësisë, Pylltarisë − Përshkrim për mjedisin jetësor dhe
dhe Ekonomisë së Ujërave të bëjë shndërrimin lokacionit e tij;
e përhershëm të tokës bujqësore përkatëse në − Përshkrim për trashëgiminë natyrore,
tokë ndërtimore (Ligji për tokë bujqësore, neni kulturore dhe historike dhe përshkrim të
49). Kohëzgjatja e kësaj procedure varet nga peizazhit;
ndërlikueshmëria e përgatitjes dhe shqyrtimit − Përshkrim të llojit dhe sasive të pritura të
të dokumentacionit të projektuar. Shpenzimet emisioneve, veçanërisht të emisioneve të
për sigurimin e dokumentacionit projektues i ajrit, ujrave të zeza, mbeturinave të ngurta
bart investitori. si dhe informacione të tjera të nevojshme
Përveç nëse parcela e tokës në të cilën inve- për vlerësimin e ndikimeve më të mëdha
stitori ka për qëllim ta ndërtojë hidrocentralin të projektit mbi mjedisin jetësor;
nuk është në pronë private, investitori duhet ta − Përshkrimin e masave për parandalimin,
blejë tokën, të nënshkruajë marrëveshje për blerje uljen dhe eliminimin e ndikimit mbi mjedisin
afatgjate me Qeverinë apo të marrë koncesion për jetësor, si dhe të masave për kthimin në
shfrytëzimin e tokës (Ligji për tokë ndërtimore, gjendje të mëparshme;
nenet 13 – 40). Procedurat për tjetërsim, dhënien − Përshkrimin e ndikimeve të projektit mbi
nën qira afatgjate dhe koncesion të tokës ndër- mjedisin jetësor duke e pasur parasysh
timore me pronë shtetërore bëhen me ankand nivelin e zhvillimit të shkencës dhe
publik, që sjell rrezik që të mos fitohet në ankand metodave të pranueshme për vlerësim;
ndonjë parcelë tokësore konkrete. − Përshkrimin e karakteristikave të
Nëse parcela tokësore është në pronë private, teknologjisë e cila përdoret;
investitori dhe pronari i tokës munden së bashku − Përshkrimin e zgjidhjeve alternative për
të dakordohen për tjetërsim, qiramarrje afatgjate realizimin e projektit të cilat i ka pasur
apo për të drejtën e shfrytëzimit të tokës. parasysh investitori dhe shkaqet kryesore
për përzgjedhjen e alternativës së propozuar;
4.4. Studim për vlerësimin e gjithmonë përfshihet edhe alternativi nulta
ndikimit mbi mjedisin jetësor (zero)
− Rezyme për studimin e dorëzuar pa detaje
Ju lutemi që ta keni parasysh se hidrocentralet teknike;
varen nga kërkesat për përgatitjen dhe dorëzi- − Analizë për vështirësitë (mangësitë teknike
min e Studimit për vlerësimin e ndikimit mbi apo mungesën e njohurive) me të cilat
mjedisin jetësor. Që këtu, hidrocentralet nuk investitori apo eksperti janë ballafaquar
mund të ndërtohen apo të fillojnë me punë para gjatë përgatitjes së studimit; dhe
se të merret vendim pozitiv për Studimin për − Propozim për madhësinë dhe karakteristikat
vlerësimin e ndikimit mbi mjedisin jetësor në e ndryshimeve potenciale për të cilat duhet
pajtim me Ligjin për mjedis jetësor. (Ligji për të azhurnohet Studimi për vlerësimin e
ujërat, neni 177). ndikimit mbi mjedisin jetësor.
Studimi për vlerësimin e ndikimit mbi mje-
disin jetësor duhet të përmbajë: Studimi për vlerësimin e ndikimit mbi
− Përshkrim për projektin bashkë me mjedisin jetësor duhet të strukturohet në këtë
informacione për lokacionin, karakterin mënyrë:
52 CENTRALET ME ERË

1) Të dhëna të përgjithshme; – Projekt ideor,


2) Lloji i elaboratit; – dëshmi për të drejtën e ndërtimit (pronësi,
3) Organi kompetent për miratimin e ela- të drejtë shfrytëzimi, koncesion),
boratit; – elaborat gjeodezik për parcelë tokësore.
4) Përshkrimi i projektit në të cilin bëhet
veprimtaria apo aktiviteti; Ministria e Transportit dhe Lidhjeve apo
5) Përshkrimi i mjedisit jetësor rreth loka- Komuna, varësisht rastit, është e obliguar ta
cionit të projektit; shqyrtojë dhe të sjell vendim për ndarjen e mi-
6) Ndikimi i projektit mbi mjedisin jetësor; ratimit për ndërtim në afat prej 15 ditëve nga
7) Program për mbrojtjen e mjedisit dita e dorëzimit të dokumentacionit të plotë
jetësor; dhe të saktë. Para se ta marrë miratimin për
8) Konstatim; ndërtim, shtruesi duhet ta paguaj kompensimin
9) Lista e anekseve; për rregullimin e tokës ndërtimore. Miratimi për
10) Deklaratë. ndërtim jepet në afat prej pesë ditëve të punës nga
dorëzimi i dëshmisë për kompensimin e paguar
Investitori duhet të marrë miratim për Studi- për rregullimin e tokës ndërtimore.
min për vlerësimin e ndikimit mbi mjedisin jetësor. Miratimi për ndërtim shfuqizohet nëse
Organi kompetent për shqyrtimin dhe miratimin shtruesi nuk fillon me ndërtimin në afat prej
e Studimit (në këtë rast të hidrocentraleve mbi 2 (dy) viteve, apo nuk e përfundon në afat prej
1 MW) është Drejtoria për mjedis jetësor, organ 10 (dhjetë) viteve (në rastin me hidrocentralet
në përbërje të Ministrisë së Mjedisit Jetësor dhe mbi 1 MW) apo në afat prej 6 (gjashtë) viteve
Planifikimit Hapësinor. Kryetari i komunës është (në rastin e hidrocentraleve deri në 1 MW) nga
kompetent për shqyrtimin dhe miratimin e Studi- dita e lëshimit të miratimit për ndërtim (Ligji
mit (në këtë rast të hidrocentraleve deri në 1 MW). për ndërtim, neni 59 - 68). Hidrocentrali mund
të lëshohet në përdorim vetëm pas miratimit
4.5. Miratim për ndërtim të pranimit teknik nga ana e supervizorit të
autorizuar, ndërsa Ministria e Transportit dhe
Për ndërtimin e hidrocentralit nevojitet miratim Lidhjeve apo Komuna, varësisht rastit, nuk do të
për ndërtim. Ministria e Transportit dhe Lidhjeve lëshojë miratimin për shfrytëzimin e ndërtimit.
është kompetente për dhënien e miratimit për Investitori gjithashtu është i obliguar të ndërtojë
ndërtimin e hidrocentraleve me fuqi instaluese infrastrukturë të mirë qasëse deri te lokacioni,
prej mbi 1 MW përderisa, Komuna në territorin duke përfshirë rrugë, mure mbështetëse, ura,
e së cilës është paraparë të ndërtohet hidrocen- tunele, kanale etj., në pajtueshmëri me kërkesën
trali është kompetente për dhënien e miratimit për ndërtimin e infrastrukturës linjore (Ligji për
përderisa hidrocentrali është me fuqi instaluese planifikim hapësinor dhe urbanistik, neni 52).
deri në 1 MW (Ligji për ndërtim, neni 57, 58).
Bashkë me kërkesën për miratimin për ndër- 4.6. Marrja e statusit të
tim duhet t’i dorëzoni dokumentet vijuese: përkohshëm të prodhuesit
– certifikatë të planit urbanistik detajues të autorizuar
lokal;
– projekt arkitektoniko-urbanistik (i rishikuar Komisioni rregullator për energjetikë solli Rre-
dhe i miratuar), gullore për prodhuesit e autorizuar të energjisë
– projekt bazë (i rishikuar dhe i miratuar), elektrike prej burimeve të ripërtëritshme të
CENTRALET ME ERË 53

energjisë (Gazeta zyrtare nr. 18/2012, 97/2012, • Projekti bazë i centralit me erë i punuar
63/2013 dhe 25/2015). Në pajtueshmëri me Ligjin prej personit të licencuar juridik,
për energjetikë dhe Rregulloren për prodhues të • Deklaratë për besueshmërinë e kërkesës
autorizuar të energjisë elektrike prej burimeve të dhe të dhënave dhe dokumenteve të dorëzu-
ripërtërishme të energjisë, Komisioni Rregullator ara, të nënshkruara prej udhëheqësit të
për energjetikë jep vendim për marrjen e statu- autorizuar për përfaqësimin e shtruesit të
sit të përkohshëm të prodhuesit të autorizuar, regjistruar në Regjistrin qendror.
vendim për marrjen e statusit të prodhuesit të
autorizuar dhe vendim për shfrytëzimin e tarifës Nëse Komisioni Rregullator për energjetikë
së autorizuar, të njëjtat i publikon në ueb faqen e përcakton se dokumentacioni është i plotë dhe
tij si dhe në Gazetën Zyrtare. Gjithashtu, në ueb nuk ka mangësi, në afat prej 5 (pesë) ditëve prej
faqen e Komisionit rregullator për energjetikë ditës së marrjes së kërkesës do të sjellë përfundim
publikohet edhe Regjistri i prodhuesve të autori- për rregullshmërinë e kërkesës dhe vazhdimin
zuar, si dhe diagrami i procedurave për marrjen e procedurës në pajtueshmëri me dispozitat e
e statusit prodhues i autorizuar dhe shfrytëzimin Rregullores për licenca për zbatimin e aktivi-
e tarifave të autorizuara: www.erc.org.mk. teteve energjetike. Komisioni rregullator për
Procedura për dhënien e vendimit të për­ energjetikë dorëzon një ekzemplar të përfundimit
kohshëm për marrjen e statusit të përkohshëm të deri te shtruesi.
prodhuesit të autorizuar fillon me shtrimin e kër- Komisioni Rregullator për energjetikë në
kesës deri te Komisioni rregullator për energjetikë. lidhje me kërkesën e dorëzuar për dhënien e
Kërkesa shtrohet deri te Komisioni rregullator vendimit të përkohshëm për marrjen e statusit
për energjetikë ne formë të shkruar si formular i prodhues i autorizuar do të caktojë seancë për-
plotësuar për kërkesë për dhënien e vendimit të gatitore e cila do të mbahet në afat i cili nuk do
përkohshëm për marrjen e statusit prodhues i au- të mund të jetë më i gjatë se 25 (njëzet e pesë) ditë
torizuar, e nostrifikuar me nënshkrim dhe vulë prej prej ditës së pranimit të kërkesës. Për pjesëmarrje
shtruesit (Formulari KVPPA): Shtruesi është i obli- në seancën përgatitore, komisioni rregullator për
guar t’i ndajë dhe t’i shënojë në mënyrë të veçantë energjetikë e fton shtruesin, si dhe përfaqësuesit
dokumentet të cilat janë me karakter kofidencial. e autorizuar të ndërmarrjeve, institucioneve dhe
Në të kundërtën do të konsiderohet se dokumentet organizatave të interesuara.
e dorëzuara nuk janë me karakter kofidencial. Komisioni Rregullator për energjetikë, së
Shtruesi është i obliguar t’i dorëzojë të dhënat paku në afat prej 5 (pesë) ditëve nga dita e për-
dhe dokumentet në vijim: fundimit të seancës përgatitore, do të mbajë
• Kërkesë për dhënien e vendimit të për­ seancë të rregullt në të cilën do të sjell vendim të
kohshëm për marrjen e statusit prodhues përkohshëm për marrjen e statusit të prodhuesit
i autorizuar, i nostrifikuar me nënshkrim të autorizuar të energjisë elektrike të prodhuar
dhe vulë prej udhëheqësit; nga burime të ripërtërishme të energjisë. Vendimi
• Vendim për regjistrim në Regjistrin qendror, i përkohshëm do të publikohet në Gazetën Zyrtare,
origjinali ose kopje të nostrifikuar në noter; ndërsa hyn në fuqi prej ditës së sjelljes.
• Dëshmi për plotësimin e kushtit (miratim i Në vendimin e përkohshëm theksohet fuqia
plotfuqishëm për ndërtim ose marrëveshje e elektrocentralit (gjegjësisht të njësive gjene-
për koncesion ose marrëveshje për part- ratore).
neritet publik privat) origjinali ose kopje e Komisioni Rregullator për energjetikë në
notifikuar në noter. vendimin e përkohshëm e përcakton afatin deri
54 CENTRALET ME ERË

kur elektrocentrali duhet të lëshohet në përdorim. − Koordinata të hapsirës për makineri ku do


Validiteti i vendimit të përkohshëm është i bara- të jenë të instaluara pajisjet e elektromaki-
bartë me afatin deri kur elektocentrali duhet të nerisë të imipiantit prodhues, dhe
lëshohet në përdorim. Brenda këtij afati, bartësi
i vendimit të përkohshëm është i obliguar ta Karakteristika teknike të impiantit prodhues
ndërtojë elektrocentralin, të sigurojë dokumente në pajtim me Rregullat e rrjetit për distribuimin
të lëshuara prej organeve kompetente për përdo- e energjisë elektrike.
rimin e elektrocentralit ose raport për kontroll EVN Maqedoni ka për obligim të sjellë Vendim
të kryer teknik në pajtueshmëri me Ligjin për për pëlqim për kyçje në sistemin distribuues
ndërtim dhe të posedojë licencë për kryerjen e në afat prej 40 ditëve prej ditës së paranimit të
aktiviteteve energjetike – prodhimin e energjisë kërkesës së kompletuar. Dhënia e Vendimit për
elektrike. pëlqim për kyçje në sistemin distribuues është
e shoqërurar me nëmshkrimin e Marrveshjes
4.7 Pëlqim për kyçje në për kyçje në rrejetim distribuues të përgatitur
sistemin distribuues nga ana e EVN Maqedonia, e cila është shtojcë e
Rregullave të rrjetit për distribuim të energjisë.
Objektet për prodhimin e energjisë me fuqi insta- Kompensimin e për kyçjen e prodhuesit
luese deri në 10 MW, si kufi i sipërm për hidro- të energjisë elektrike të rrjetit distribuues për-
centralet të cilat janë të gatshme për marrjen e caktohet në pajtueshmëri me Metedologjinë për
statusit si prodhues të autorizuar, zakonisht kyçen mënyrën e përcaktimit të kompensimit për kyçje
në rrjetin distribuues. Për këtë shkak, pëlqimi në rrjetin ditribuues të energjisë elektrike e cila
për kyçjen e hidrocentraleve të vogla në rrjetin është e dhënë në shtojcën e Rregullave të rrejtit
për distribuimin e energjisë elektrike duhet të për ditribuimin e energjisë elektrike.
merret prej operatorit të sistemit distribuues të Shpenzimet për kyçje, siç janë përcaktuar nga
energjisë elektrike (EVN Maqedoni). ana e EVN Maqedoni, i bart investitori, ndërsa EVN
Në praktikë, kërkesa për pëlqimin për kyçje Maqedoni obligohet të vendos pajisje për matje me
duhet të shtrohet në fazën fillestare të punimeve shpenzimet e veta. Duke i pasur parasysh rastet
ndërtimore. Kërkesa duhet të shtrohet deri te në të cilat hidrocentrali nuk mundet në mënyrë
EVN Maqedoni në formular BSP-2, të cilin mund të siguritë të lidhet me impiantin më të afërt për
ta gjeni në qendra-energjetike të EVN-së ose ta kyçje, i këshillojmë investitorët që të kontrollojnë
shkarkoni nga ueb faqja e EVN Maqedoni. në EVN Maqedoni ku do të jetë impianti i tyre
Bashkë me kërkesën duhet t’i dorëzoni doku- faktik që të mund të bëjnë vlerësimin e shpenzi-
mentet në vijim: meve dhe kohëzgjatjen e zbatimit të impiantit.
− Vendimi për t’u regjistuar në Regjistrin
qendror me gjendjen vijuese 4.8 Projektimi dhe zbatimi
− Projekti kryesor për impiantin prodhues i i impiantit
cili është lëndë për kyçje në rrjetin distri-
buues, Pas marrjes së Vendimit për pëlqim për kyçje në
− Certifikatë nga plani i kadastrës me me rrjetin distribuues, shfrytëzuesi është i obliguar
objektet e projektuara, të nënshkruajë marrëveshje për projektimin dhe/
− Miratim për ndërtim ose marrëveshje me ose zbatimin e impiantit deri te pika kyçëse.
koncesion për ujë për prodhimin e energjisë Nëse investitorit i është dhënë Vendimi për
elektrike pëlqim për impiant jostandard, gjegjësisht kyçje
CENTRALET ME ERË 55

për shfrytëzues të izoluar ose nëse planifikohet Kadastrës si dëshmi për të drejtën e pronësisë ose
impianti të shfrytëzohet vetëm për objekt për të drejtave të tjera për përdorimin e objektit (Ligji
prodhimin e energjisë elektrike, investitori mund për ndërtim, neni 87). Në rast se kërkesa e miratimit
të vendos që impianti: për përdorim është e pakompletuar, Ministria
− të projektohet dhe të zbatohet nga EVN e Transportit dhe Lidhjeve do t’i rekomandojë
Maqedoni, ose shtruesit që t’i dorëzojë dokumentet përkatëse
− të projektohet dhe zbatohet prej kompa- dhe të kompletuara në afat prej shtatë ditëve nga
nisë së autorizuar të listës së kompanive pranimi i kërkesës për leje për përdorim.
të përzgjedhura ne tender nga ana e EVN Komisioni i përbërë prej tre inxhinierëve
Maqedoni. të autorizuar për mbikëqyrje të emëruar prej
Ministrisë së Transportit dhe Lidhjeve duhet të
Nëse EVN Maqedoni konstaton se impian- bëjë kontroll teknik të ndërtimit pas pranimit
tin jostandard mund ta përdorin më shumë të kërkesës për miratimin për përdorim në afat
shfrytëzues të ardhshëm, impiantin e projekton prej 15 ditëve prej ditës së pranimit të kërkesës
dhe zbaton EVN. Në këtë rast, investitori paguan së plotë për miratimin për përdorim. Në rast të
shumë e cila është e barabartë me prodhimin prej hidrocentralit me fuqi instaluese deri në 1MW,
vlerës së përgjithshme të impiantit jostandard Komuna e jep miratimin për përdorim në bazë
dhe sasisë midis fuqisë së miratuar maksimale të raportit të kontrollit teknik të inxhinierit
të njëkohshme që i ndahet investitorit dhe vlerën të autorizuar për mbikëqyrje. Komisioni ose
e përgjithshme të fuqisë instaluese aktive të inxhinieri mbikëqyrës, përcakton në mënyrë
impiantit. përkatëse se:
Investitori i mbart shpenzimet e projektimit − objekti është ndërtuar në pajtueshmëri me
dhe/ose zbatimit të impiantit, të llogaritura në projektin themelor ose në rast të ndryshi-
pajtueshmëri me Metodologjinë për konstatimin meve gjatë ndërtimit, projektit në gjendje
e shpenzimeve për kyçje në sistemin distribuues, të zbatueshme dhe miratimit për ndërtim,
i cili është pjesë përbërëse e Rregullave të rrjetit − objekti është i sigurt dhe mund të përdoret.
për distribuim të energjisë elektrike.
Në qoftë se komisioni, ose inxhinieri për
4.9 Miratim për përdorim mbikëqyrje në mënyrë përkatëse, konstatojnë
çfarëdo mangësi të cilat do ta dëmtojnë stabilite-
Për ta lëshuar në përdorim në mënyrë zyrtare tin mekanik dhe rezistencën e objektit, mund të
hidrocentralin duhet miratim për përdorim. kërkojë prej investitorit t’i korrigjojë këto aspekte
Varësisht prej fuqisë instaluese të hidrocentralit, në afat prej 30 ditëve, ose mund të propozojë të
miratimin për përdorim e jep Ministrai e Trans- mos jepet miratimi për ndërtim (Ligji për ndërtim,
portit dhe Lidhjeve (për centrale me fuqi instaluese neni 89-92).
deri në 1 MW ose më shumë) ose Komuna e cila Në rast të raportit pozitiv të komisionit, ose të
e ka dhënë miratimin për ndërtim (për centralet inxhinierit për mbikëqyrje, Ministria e Transportit
me fuqi instaluese deri në 1 MW). dhe Lidhjeve, apo Komuna, në mënyrë përkatëse
Ministria e Transportit dhe Lidhjeve e jep mi- është e obliguar të japë miratim për përdorim në
ratimin për përdorim në bazë të projektit themelor afat prej 15 ditëve prej ditës së kontrollit teknik të
(apo projektit në gjendje të zbatueshme përderisa ndërtesës. Shpenzimet për kryerjen e kontrollit
gjatë realizimit janë bërë ndryshime të mëdha), teknik dhe dhënies së miratimit për përdorim i
raportit të kontrollit teknik dhe certifikatës prej bart investitori.
56 CENTRALET ME ERË

4.10 Licencë për prodhimin e • Kompensim i paguar për marrjen e licencës


energjisë elektrike • Vendim për regjistrim në Regjistrin qendror
• Akt për themelimin dhe/apo Statutin e
Kushtet për dhënien e licencës për prodhimin e kompanisë,
energjisë elektrike prej burimeve të ripërtëritsh- • Dëshmi për të drejtën e pronësisë ose të
me janë përcaktuar në Rregulloren për licenca drejtën e shfrytëzimit të tokës dhe mjeteve
për zbatimin e veprimtarive energjetike (Gazeta themelore
zyrtare nr. 141/2011, 78/2013 dhe 33/2015). In- • Marrëveshje për koncesion nëse veprimtaria
vestitori mund të kërkojë t’i jepet licencë për bëhet me përdorimin e pasurisë natyrore
prodhimin e energjisë elektrike prej burimeve ose marrëveshje për koncesion për shërbim
të ripërtëritshme prej komisionit Rregullator publik, gjegjësisht dëshmi për të drejtën e
për energjetikë edhe para marrjes së raportit përdorimit të pasurisë natyrore në pajtu-
për pranim të kryer teknik ose leje përdorimi eshmëri me ligjin;
prej organeve kompetente në rastet në vijim: • Strukturë organizative e shtruesit, duke
− Nëse investitori për objektin energjisë ka përfshirë edhe informacione për të punësua-
siguruar miratim për ndërtimin e objektit rit, shkollimin dhe kompetencat profesionale
në rast kur për ndërtimin e objektit nuk të personave të cilët do ta udhëheqin objektin
është i nevojshëm autorizimi për ndërtim dhe kuadrin i cili do të punojë me pajisjet
e objektit, ose • Projekt, miratim për ndërtim, përderisa
− Nëse investitori i objektit të energjisë e ka objekti është i ndërtuar edhe raport për
fituar të drejtën për ndërtimin e objektit kontroll teknik të kryer ose miratim për
në bazë të procedurës së kryer përmes vënien në funksion të objektit, si dhe autori-
thirrjes publike për ndërtimin e objektit zim për ndërtimin e objektit për prodhimin
për prodhimin e energjisë elektrike, ose e energjisë elektrike, në rast se ndërtimi i
− Nëse investitori ka marrë të drejtën për objektit është lëndë e kërkesës së atillë;
ndërtimin e objektit në bazë të marrëveshjes • Deklaratë për strukturën e pronësisë së kom-
së nënshkruar me koncesion. panisë, duke përfshirë edhe informacione
dhe përshkrim detajues të pjesëmarrjes së
Investitori duhet të dorëzojë kërkesë për shtruesit në kompani të tjera dhe pjesëmarr-
marrjen e licencës deri te Komisioni rregullator jes së kompanive të tjera në kompaninë e
për energjetikë së bashku me informacionet dhe shtruesit;
dokumentet në vijim: • Vërtetim për bonitet i shtruesit i dhënë nga
• Informata të përgjithshme për shtruesin, organet kompetente;
• Emri i personit përgjegjës, • Certifikatë për taksa të paguara dhe tarifa të
• Lloji i veprimtarisë energjetike e cila duhet tjera publike prej Drejtorisë për të ardhura
të zbatohet, publike;
• Përshkrim i shkurtër i licencës së kërkuar, • Raporte financiare të përgatitura në pajtu-
• Deklaratë për besueshmërinë e të dhëna- eshmëri me rregullativat e për tre vitet e
ve dhe dokumentacionit të dorëzuar të fundit, duke i përfshirë edhe raportet revi-
nënshkruar prej anës së personit të auto- zore prej revizorit të autorizuar, përderisa
rizuar, revizioni është vërtetuar me ligj;
• Deklaratë për periudhën kohore për kër- • Vërtetim se shtruesi nuk është lëndë e ndon-
kesën për marrjen e licencës, jë procedure për falimentim ose likuidim;
CENTRALET ME ERË 57

• Vërtetim nga Regjistri qendror se shtru- 50 ditëve prej ditës së fillimit të procedurës. Nëse
esit dhe përfaqësuesit të autorizuar nuk komisioni rregullator për energjetikë konstaton
u është shqiptuar ndalesë për kryerjen e prej seancës përgatitore si dhe prej dokumenta-
profesionit, veprimtarisë dhe obligimeve cionit, se janë plotësuar kushtet për marrjen e
si dhe vërtetim se nuk janë të dënuar për licencës do të caktojë seancë të rregullt në afat
ndonjë vepër penale. prej 10 ditëve që të sjell vendim për dhënien e
licencës.
Përveç dokumenteve të lartpërmendura Komisioni Rregullator për energjetikë e
shtruesi është i obliguar të dorëzojë edhe doku- shpall vendimin dhe licencën për kryerjen e
mentacion shtesë në lidhje me teknologjinë aktiviteteve energjetike në Gazetën Zyrtare.
specifike për prodhimin e energjisë elektrike Përderisa licenca është e dhënë për objekt
në pajtueshmëri me nenin 14 të Rregullores për pa leje për përdorim ose raport për pranim të
licenca për kryerjen e aktiviteteve energjetike. kryer teknik, ndërsa investitori ka siguruar leje
Komisioni rregullator për energjetikë do për përdorim ose raport për pranim të kryer
ta shqyrtojë kërkesën për marrjen e licencës teknik, është e nevojshme investitori të dorëzojë
dhe dokumentacionin e dorëzuar dhe në afat dokumentet në pajtueshmëri me nenin 32 të
prej 8 ditëve do të sjellë Konstatim. Përderisa Rregullores për kryerjen e aktiviteteve energjeti-
dokumentacioni për marrjen e licencës është ke. Pas dokumentacionit të dorëzuar Komisioni
në pajtueshmëri me Rregulloren për licenca për rregullator për energjetikë në afat prej 8 ditëve
kryerjen e aktiviteteve energjetike si dhe ligjet prej dorëzimit do të sjellë vendim për hyrjen në
e tjera, Komision Rregullator për energjetikë fuqi të licencës dhënë paraprakisht.
do ta detyrojë shtruesin të përgatit njoftim për Pas marrjes së licencës për prodhimin e
kërkesën dhe në afat prej 3 ditëve dhe ta dorëzojë energjisë elektrike, investitori ka mundësi, nëse
deri te Komisioni Rregullator për energjetikë për ekzistojnë kushte teknike, të prodhojë dhe të
miratim. Në rast se dokumentacioni i dorëzuar ka shesë energji elektrike para marrjes së statusit
mangësi formale dhe të tjera atëherë Komisioni prodhues i autorizuar i energjisë elektrike (shiko
Rregullator për energjetikë do ta detyrojë shtrue- 4. 12) dhe para nënshkrimit të marrëveshjes për
sin e kërkesës në afat prej 15 ditëve t’i mënjanojë blerjen e energjisë elektrike prodhuese me SH.A
mangësitë dhe ta kompletojë dokumentacionin MEPSO (shiko 4.13). Për këtë qëllim, investitori
në pajtueshmëri me Rregulloren për licenca për duhet të bëjë marrëveshje me:
kryerjen e aktiviteteve energjetike. − operatorin e sistemit distribuues
Investitori është i obliguar ta shpall kërkesën − me ndonjë furnizues të energjisë elektrike,
për dhënien e licencës për prodhimin e energjisë ose
elektrike nga burime të ripërtëritshme me shpen- − tregtar me energji elektrike
zime të veta së paku në dy gazeta të përditshme
në të dy gjuhët zyrtare. Shpallja bëhet me qëllim Marrëveshja e këtillë mund të jetë me
që të publikohet dhënia e licencës dhe të ftohen kohëzgjatje të kufizuar, përkatësisht deri sa
të gjitha palët e interesuara të komentojnë për të merret statusi i prodhuesit të autorizuar të
dhënien e licencës dhe ta prezentojnë rastin e energjisë elektrike, ose me kohëzgjatje të paku-
tyre. fizuar, përderisa investitori nuk arrin të marrë
Pas shpalljes së kërkesës, Komisioni rre- statusin prodhues i autorizuar i energjisë elektrike
gullator për energjetikë do të caktojë seancë ose zgjedh të heqë dorë prej statusit.
përgatitore e cila duhet të mbahet në afat prej
58 CENTRALET ME ERË

4.11. Regjistrimi i objektit në pletuar dhe i saktë dhe se të gjitha kushtet për
Regjistrin e objekteve marrjen e statusit të prodhuesit të autorizuar janë
për prodhimin e energjisë të plotësuara, ai do të sjellë vendim për regjistri-
elektrike nga burime të min e shtruesit në Regjistrin e prodhuesve të auto-
ripërtëritshme të energjisë rizuar të energjisë elektrike në afat prej 15 ditëve
prej datës së dorëzimit të kërkesës. Agjencia për
Investitori duhet ta regjistrojë hirocentralin energjetikë mund të vendos ta shqyrtoj objektin
e tij në Regjistrin e objekteve për prodhimin e para se ta japë vendimin. Agjencia për energjetikë
energjisë elektrike me burime të ripërtëritsh- ia dorëzon investitorit Vendimin për regjistrim
me të energjisë të cilin e drejton Agjencia për në Regjistrin e prodhuesve të autorizuar për
energjetikë. Për këtë qëllim, investitori duhet energji elektrike në afat prej tre ditëve prej datës
të dorëzojë kërkesë deri te Agjencia për energje- së sjelljes së vendimit. Investitori regjistrohet
tikë për regjistrim në Regjistrin e objekteve për me numrin e vetëm të regjistrit i cili nuk mund
prodhimin e energjisë elektrike prej burimeve të ndryshohet apo të transferohet (Rregullorja
të ripërtëritshme të energjisë, bashkë me doku- për burime të ripërtëritshme të energjisë, neni 9).
mentet në vijim:
1. Miratim për përdorimin e objektit energjetik 4.12. Marrja e statusit të
ose raport për kontrollin e kryer teknik, në prodhuesit të autorizuar
rast kur nuk është i nevojshëm miratimi
për përdorim dhe vërtetimi i operatorit të Pas marrjes së vendimit të përkohshëm për marrjen
sistemit përçues për energji elektrike me të e statusit të prodhuesit të autorizuar të energjisë
cilin vërtetohet se objekti i energjisë është elektrike të prodhuar prej burimeve të ripërtërish-
i kyçur në sistemin përkatës (përçues ose me të energjisë, investitori duhet të dorëzojë
distributiv), kërkesë për marrjen e vendimit për marrjen e
2. Hartë topografike me përmasë 1:25.000 ku statusit prodhues i autorizuar i energjisë elektrike
është i shfaqur lokacioni i hidrocentralit, të prodhuar prej burimeve të ripërtërishme të
3. Prezantim skematik të hidrocentralit dhe energjisë dhe njëkohësisht të dorëzojë kërkesë për
i pajisjeve të instaluara, veçanërisht të shfrytëzimin e tarifës së autorizuar të energjisë
pajisjeve për matje, dhe elektrike të prodhuar prej burimeve të ripërtërish-
4. Kopje të licencës për prodhimin e energjisë me të energjisë. Pas kësaj, elektrocentrali duhet
elektrike (Rregullorja për burime të lëshohet në përdorim në afatin e caktuar në vendi-
ripërtëritshme të energjisë, neni 8). min e përkohshëm dhe shtruesi duhet të posedojë
licencë për kryerjen e aktiviteteve energjetike
Nëse Komisioni rregullator për energjetikë – prodhimin e energjisë elektrike për elektro-
konstaton se kërkesa nuk është e plotë, ai do ta centralin për të cilin kërkohet statusi prodhues
njoftojë shtruesin dhe do t’i bëjë thirrje që ta i autorizuar i energjisë elektrike të prodhuar
kompletojë me dokumentacionin e duhur në afat prej burimeve të ripërtërishme të energjisë.
prej 30 ditëve prej ditës së dorëzimit të njoftimit. Kërkesat dorëzohen deri te Komision Rregul-
Nëse shtruesi nuk e kompleton dokumentacionin lator për energjetikë në një ekzemplar në formë të
në afatin e caktuar, Agjencia për energjetikë do shkruar, si formular i plotësuar për kërkesë për
ta refuzojë kërkesën si të pakompletuar. lëshimin e vendimit për marrjen e statusit prodhu-
Nëse Agjencia për energjetikë konstaton se es i autorizuar, i nostrifikuar me nënshkrim dhe
kërkesa dhe dokumentacioni shtesë është i kom- vulë të shtruesit (Formulari KVPA), si dhe formular
CENTRALET ME ERË 59

i plotësuar për kërkesë për shfrytëzimin e tarifës nari, sipas bursës së mesme të Bankës Popullore
së autorizuar, i nostrifikuar me nënshkrim dhe në ditën e shtrimit të kërkesave.
vulë të shtruesit (formulari KSHTA). Procedurat për lëshimin e vendimit për
Shtruesi është i obliguar t’i ndajë dhe t’i marrjen e prodhuesit të autorizuar dhe sjelljen
shënojë në mënyrë të veçantë dokumentet të cilat e vendimit për shfrytëzimin e tarifës së autorizuar
janë me karakter kofidencial. Në të kundërtën do fillojnë në ditën e pranimit të kërkesës në arkivin
të konsiderohet se dokumentet e dorëzuara nuk e Komisionit Rregullator për energjetikë.
janë me karakter kofidencial. Pas marrjes së kërkesave, Komisioni Rre-
Kërkesat dorëzohen për shfrytëzimin e tarifës gullator për energjetikë përcakton nëse është
së autorizuar e cila ka vlejtur në ditën e sjelljes së dorëzuar dokumentacioni i nevojshëm për sjelljen
vendimit të përkohshëm për marrjen e statusit e vendimit dhe sjelljen e vendimit, si dhe nëse
prodhues i autorizuar i energjisë elektrike. dokumentacioni është dorëzuar në formë dhe
Së bashku me kërkesën, shtruesi është i obligu- mënyrë të caktuar. Komisioni rregullator për
ar t’i dorëzojë të dhënat dhe dokumentet në vijim: energjetikë në afat prej 5 (pesë) ditëve nga dita
• Projekt për gjendjen e zbatueshme në pajtim e pranimit të kërkesave, do të kërkojë vërtetim
me Ligjin për ndërtim, nëse janë bërë ndrys- nga Agjencia për Energjetikë se elektrocentrali
hime gjatë ndërtimit; është ndërtuar dhe i plotëson kushtet specifike
• Vendim për regjistrim në Regjistrin e elektro- dhe fuqinë instaluese të përcaktuar me Dekretin
centraleve të cilat shfrytëzojnë burime të të cilat kanë qenë në fuqi në ditën e lëshimin të
ripërtërishme të energjisë për prodhimin vendimit të përkohshëm për marrjen e statusit
e energjisë elektrike, lëshuar nga Agjencia të prodhuesit të autorizuar.
për Energjetikë, në pajtim me Rregulloren Agjencia për Energjetikë obligohet ta lë-
për burime të ripërtërishme të energjisë; shojë vërtetimin në afat jo më të gjatë se 15
• Dëshmi se është paguar kompensimi në (pesëmbëdhjetë) ditë nga dita e shtrimit të kërkesës
pajtim me nenin 13-a të Rregullores për deri te Komisioni Rregullator për energjetikë.
prodhues të autorizuar për energji elektrike Për lëshimin e vërtetimit, Komisioni rre-
të burimeve të ripërtërishme të energjisë; gullator për energjetikë i paguan kompensim
• Deklaratë për besueshmërinë e kërkesës Agjencisë për Energjetikë, sipas tarifores së sjellë
dhe të dhënat detajuese, të nënshkruar nga Agjencia për energjetikë, i përgatitur në bazë
nga personi i autorizuar për përfaqësimin e të shpenzimeve të Agjencisë për Energjetikë në
shtruesit të regjistruar në Regjistrin qendror. procedurën për lëshimin e vërtetimit.
Nëse Komisioni Rregullator për energjetikë
Dokumentet duhet të jenë origjinale ose kopjet përcakton se kërkesat dhe dokumentacioni është
e dokumenteve origjinale të jenë të nostrifikuara i kompletuar dhe se nuk ka mangësi dhe se vërte-
në noter. timi i lëshuar nga Agjencia për Energjetikë është
Me kërkesën, shtruesi në mënyrë të obliguar pozitiv, në afat prej 20 (njëzetë) ditëve nga dita e
duhet të shfaq dëshmi se në llogarinë e Komisionit pranimit të kërkesës do të sjellë konstatime për
rregullator për energjetikë është paguar kompen- rregullshmërinë e kërkesave dhe vazhdimin e
sim i pakthyeshëm në të holla për shpenzimet e procedurave. Nga një ekzemplar, Komisioni rre-
bëra në procedurë (kompensimin të cilin Komisi- gullator për energjetikë e dorëzon deri te shtruesi.
oni Rregullator për energjetikë duhet t’ia paguaj Komisioni rregullator për energjetikë, në
Agjencisë për Energjetikë sipas tarifores së sjellë lidhje me kërkesat e shtruara, do të caktojë seancë
nga Agjencia për Energjetikë ) në kundërvlerë de- përgatitore e cila duhet të mbahet në afat i cili
60 CENTRALET ME ERË

nuk mund të jetë më i gjatë se 35 (tridhjetë e pesë) ke të prodhuar nga prodhuesit e autorizuar të
ditë nga dita e pranimit të kërkesave. Ftesa për energjisë elektrike në pajtueshmëri me kontratën,
pjesëmarrje në seancën përgatitore bashkë me pro- që është në pajtueshmëri me Ligjin për energjetikë,
pozimin e vendimit për fitimin e statusit të prodhu- vendimin për shfrytëzimin e tarifave të autori-
esit të autorizuar dhe propozimit të vendimit për zuara i dhënë prej Komisionit rregullator për
shfrytëzimin e tarifës së autorizuar të energjisë energjetikë dhe Rregullave të tregut të energjisë
elektrike të prodhuar nga burimet të ripërtëritsh- elektrike. Investitori duhet të dorëzojë kërkesë
me të energjisë dorëzohet më së voni 7 (shtatë) ditë për nënshkrimin e marrëveshjes për blerjen e
para mbajtjes së seancës përgatitore. Për prani dhe energjisë elektrike deri te MEPSO.
pjesëmarrje në seancën përgatitore, Komisioni M E P S O obl i g oh e t t a n ë n sh k r u a j ë
rregullator për energjetikë e fton shtruesin, si marrëveshjen për blerjen e energjisë elektrike
dhe përfaqësuesit e autorizuar të ndërmarrjeve, në afat prej 30 (tridhjetë) ditëve prej datës së
institucioneve dhe organizatave të interesuara. pranimit të kërkesës. Marrëveshja për blerjen
Komisioni rregullator për energjetikë më së e energjisë elektrike duhet hyjë në fuqi ditën e
voni në afat prej 5 (pesë) ditëve nga dita e përfun- dhënies së Vendimit për marrjen e statusit të
dimit të seancës përgatitore do të mbajë seancë të prodhuesit të autorizuar të energjisë elektrike prej
rregullt në të cilën do të sjellë vendim për marrjen anës së Komisionit rregullator për energjetikë.
e statusit të prodhuesit të autorizuar të energjisë Investitori mund të vendos ta prish
elektrike të prodhuar nga burimet të ripërtëritsh- marrëveshjen për blerjen e energjisë elektrike
me të energjisë dhe vendim për shfrytëzimin e ta- me çka do ta humbas statusin e prodhuesit të
rifës së autorizuar të energjisë elektrike të prodhu- autorizuar të energjisë elektrike dhe të drejtën që
ar nga burimet e ripërtëritshme të energjisë. përsëri ta marrë këtë status. (Ligji për energjetikë,
Vendimet publikohen në Gazetën Zyrtare neni 153).
dhe në ueb-faqen e Komisionit Rregullator për Investitori është i obliguar ta shesë të gjithë
energjetikë. sasinë prodhuese të energjisë elektrike të MEPSO
Me ditën e hyrjes në fuqi të vendimeve, Komisi- dhe të dorëzojë plane për prodhimin e energjisë
oni Rregullator për energjetikë i shënon të dhënat elektrike deri te MEPSO.
e bartësit të vendimit dhe elektrocentralit si dhe Ky hap e shënon fundin e procesit për aplikim.
të dhënat për tarifën e autorizuar në Regjistrin Pas marrjes së statusit të prodhuesit të autorizuar,
e prodhuesve të autorizuar. investitori mund t’i zbatojë dhe përdorë tarifat
Vendimet e Komisionit Rregullator për e autorizuara të përcaktuara në Dekretin e ta-
energjetikë i dorëzon deri te shtruesi, operatori rifave të autorizuara të energjisë elektrike (Neni
i tregut të energjisë elektrike dhe deri te Agjencia 7). Tarifa e saktë e autorizuar e cila përdoret në
për Energjetikë. objekt për prodhimin e energjisë elektrike varet
prej sasisë mujore të prodhuar dhe të shitur të
4.13. Marrëveshje për blerjen energjisë elektrike në çdo bllok. Varësisht prej
e energjisë elektrike me sasisë të prodhuar të energjisë elektrike për
operatorë e tregut të çdo muaj, tarifa e autorizuar faktike e cila është
energjisë elektrike e zbatueshme për objekt mund të ndryshojë.
Tarifat e autorizuara zbatohen për një periudhë
Operatori i sistemit elektropërçues (MEPSO) prej 20 viteve.
është i obliguar ta blejë të gjithë energjinë elektri-
CENTRALET ME ERË 61

5. Sigurimi i garancive për prejardhjen e


energjisë elektrike të prodhuar prej
burimeve të ripërtëritshme të energjisë
Në rast kur investitori nuk ka arritur të regjistro- Aty ku është relevante, investitori duhet të
het në Regjistrin e objekteve për prodhimin e dorëzojë kërkesë për ndarjen e garancive për
energjisë elektrike prej burimeve të ripërtëritshme prejardhjen e energjisë elektrike të prodhuar në
të energjisë me çka do të kishte dobi prej tarifave hidrocentralin e tij deri te Agjencia për energje-
të autorizuara, ose nëse investitori vullnetarisht tikë. Bashkë me kërkesën duhet dorëzuar edhe:
ka hequr dorë nga marrëveshja për blerjen e
energjisë elektrike me operatorin e tregut të − Dëshmi për pagimin e kompensimit për
energjisë elektrike (shiko 4.14. më lartë), investitori dhënien e garancisë për prejardhje, dhe
mund të përdorë garanci për prejardhjen në bazë − Dëshmi për operatorin e sistemit për përçim
të së cilës do të kërkonte çmim të autorizuar për ose distribuim të energjisë elektrike për
energjinë elektrike të prodhuar në hidrocentralin sasinë e energjisë elektrike të prodhuar
e tij, nëse ky opsion është i paraparë në kontatën dhe të shitur prej objektit.
për koncesion.
Garanci për prejardhje zakonisht u jepet Nëse Agjencia për energjetikë konstaton se
operatorëve të sistemeve elektropërçuese ose janë plotësuar të gjitha kushtet për ndarjen e
tregtarëve të energjisë elektrike të cilët e kanë garancive për prejardhjen e energjisë elektrike
për obligim të paguajnë çmime të autorizuara për të prodhuar prej resurseve të ripërtëritshme të
energjinë elektrike të prodhuar prej burimeve energjisë, Agjencia jep vendim në afat prej 30
të ripërtëritshme të energjisë. Duhet theksuar ditëve prej ditës së pranimit të kërkesës.
se tarifa e autorizuar është jokompaktibile me
garancinë për prejardhje – investitori mund ta Garancia për prejardhje jepet nga 1 MW.
përdorë ose njërën ose tjetrën. Nëse investitori Garancitë për prejardhje vlejnë 12 muaj.
e përdorë tarifën e autorizuar, ai/ajo nuk mund
të paraqitet për garanci për prejardhje.
62 CENTRALET ME ERË

6. Adresa dhe të dhëna kontaktuese të


institucioneve kompetente

6.1. Qeveria e RM 6.6. Operatori i Sistemit për


Adresa: Bul. Ilinden nr. 2 Distribuim/Furnizim me Energji
1000 Shkup Elektrike (EVN Maqedoni)
Telefoni: + 389 02 31 18 022 Adresa: 11 Oktomvri nr. 9
Ueb faqja: www.vlada.mk 1000 Shkup
Telefoni: + 389 2 3205 000,
6.2. Ministria e Ekonomisë, Е-maili: info@evn.mk
Sektori për energjetikë Ueb faqja: www.evn.mk
Adresa: Jurij Gagarin nr. 15 (kati 1)
1000 Shkup 6.7. Ministria e Mjedisit Jetësor dhe
Telefoni + 389 2 3093 485, Planifikimit Hapësinor
+ 389 2 3093 485 Adresa: Goce Dellçev nr. 18
Е-mail: info@economy.gov.mk 1000 Shkup
Ueb faqja: www.economy.gov.mk Telefoni: + 389 2 32 51 403,
+ 389 2 32 51 503,
6.3. Agjencia për Energjetikë + 389 2 32 51 460
Adresa: Orce Nikollov nr. 68 Ueb faqja: www.moepp.gov.mk
1000 Shkup
Telefoni: + 389 2 32 30 300 6.8. Ministria e Transportit dhe Lidhjeve
Е-maili: ea@ea.gov.mk Adresa: Dame Gruev nr. 6
Ueb faqja: www.ea@ea.gov.mk 1000 Shkup
Telefoni: + 389 2 3145 497,
6.4. Komisioni Rregullator për energjetikë + 389 2 3123 292
Adresa: Dimitrie Çupovski nr. 2, kati 4 Ueb faqja: www.mtc.gov.mk
1000 Shkup
Telefoni: + 389 2 32 33 580, 6.9. Ministria e Bujqësisë, Pylltarisë
+ 389 2 32 54 010 dhe Ekonomisë së Ujërave
Е-maili: erc@erc.org.mk Adresa: Aminta i Tretë nr. 2
Ueb faqja: www.erc.org.mk 1000 Shkup
Telefoni: + 389 2 31 34477
6.5. Operatori për Tregun e Energjisë Е-mail: info@mzsv.gov.mk
Elektrike/Operatori i Sistemit Ueb faqja: www.mzsv.gov.mk
Eelektropërçues (MEPSO)
Adresa: Maksim Gorki nr. 4 6.10. Regjistri qendror
1000 Shkup Adresa: Kuzman Josifovski Pitu nr. 1
Telefoni: + 389 2 31 49 811 1000 Shkup
Е-maiil: info@mepso.com.mk Telefoni: + 389 2 3288100
Ueb faqja: www.mepso.com.mk Ueb faqja: www.crm.com.mk
CENTRALET ME ERË 63

7. Legjislatura relevante dhe


aktet rregullatore

Ligji për energjetikë (Gazeta zyrtare nr. 16/2011, Dekret për përcaktimin e projekteve dhe për kri-
136/2011, 79/2013, 164/2013, 41/2014 dhe teret në bazë të së cilave përcaktohet nevoja
151/2014) për zbatimin e procedurës për vlerësimin e
Ligji për ujërat (Gazeta zyrtare nr. 87/2008, 6/2009, ndikimit mbi mjedisin jetësor (Gazeta zyrtare
161/2009, 83/2010, 51/2011, 44/2012, 23/2013, nr. 74/2005)
163/2013, 180/2014) Rregullore për formën dhe përmbajtjen e elabo-
Ligji për pyjet (Gazeta zyrtare nr. 64/2009, 24/2011, ratit për mbrojtjen e mjedisit jetësor, proce-
53/2011, 25/2013, 79/2013, 147/2013, 43/2014, durën për miratimin e tyre si dhe mënyrën
160/2014, 33/2015 dhe 44/2015) e udhëheqjes së regjistrit të elaborateve të
Ligji për koncesione dhe partneritet privat publik miratuara (Gazeta zyrtare nr. 50/2009)
(Gazeta zyrtare nr. 6/2012, 144/2014) Rregullore për formën dhe përmbajtjen e kërkesës,
Ligji për mjedis jetësor (Gazeta zyrtare nr. 53/2005, dokumentacionit të nevojshëm dhe formu-
81/2005, 24/2007, 159/2008, 83/2009, 48/2010, larin e Vendimit për zbatimin e ndërtimeve
124/2010, 51/2011, 123/2012, 93/2013, 187/2013, përkatësisht vendosjen e paisjeve për të cilat
42/2014) nuk është i nevojshëm miratimi për ndërtim.
Ligji për ndërtim (Gazeta zyrtare nr. 130/2009, (Gazeta zyrtare, nr 147/2009)
124/2010, 18/2011, 36/2011, 54/2011, 13/2012, Rregullore për licenca për kryerjen e veprimtari-
144/2012, 25/2013, 79/2013, 137/2013, 163/2013, ve energjetike (Gazeta zyrtare nr. 143/2011,
27/2014, 28/2014, 42/2014, 115/2014, 149/2014, 78/2013 dhe 33/2015)
187/2014 dhe 44/2015) Dekret për tarifa të autorizuara për energji elektrike
Ligji për tokë bujqësore (Gazeta zyrtare nr. 135/07, (Gazeta zyrtare nr. 56/2013)
18/11, 148/11, 95/12, 79/13, 87/13, 106/13, 164/13, Vendim për fuqinë instaluese të përgjithshme të
39/14, 130/14 dhe 166/2014) prodhuesve të autorizuar të energjisë elektrike
Ligji për planifikim hapësinor dhe urbanistik (Gazeta prej secilit burim ripërtëritës të energjisë
zyrtare nr. 199/2014 dhe 44/2015) (Gazeta zyrtare nr. 56/2013 dhe 10/2014)
Ligji për pronësi dhe të drejta të tjera pronësore Rregullore për burime të ripërtëritshme të energjisë
(Gazeta zyrtare nr. 18/2001, 92/2008, 139/2009 (Gazeta zyrtare nr. 113/2011)
dhe 35/2010) Rregullore për prodhues të autorizuar të energjisë
Dekret për mënyrën dhe procedurën e tjetërsimit, elektrike nga burime të ripërtëritshme të
dhënien me qira afatgjate dhe qira afatshkur- energjisë (Gazeta zyrtare nr. 18/2012, 97/2012
tre, toka në pronësi të shtetit, me ankand dhe 63/2013)
publik, përmes grumbullimit të ofertave dhe Rregulla për tregun e energjisë elektrike (Gazeta
me marrëveshje të drejtpërdrejt, lartësinë zyrtare nr. 38/2014, 57/2014 dhe 194/2014)
e shpenzimeve të procedurës për tjetër- Rregulla të rrjetit për distribuimin e energjisë
sim dhe dhënien me qira si dhe lartësinë e elektrike (Gazeta zyrtare nr. 87/2012, 30/2014,
çmimit të tokës dhe qirasë (Gazeta zyrtare 161/2014, 189/2014 dhe 50/2015)
nr. 147/2008, 71/2009, 16/2009, 162/2009, Rregulla të rrjetit për përçimin energjisë elektrike
113/2010, 148/2010, 172/2010 dhe 40/2011) (2015)