GRANT 55198-001 SOL: Preparing the Honiara Sustainable Solid Waste Management Project (Project Readiness
Financing) - 1 Preparing the Honiara Sustainable Solid Waste Management Project
Date Published: 19-Nov-2021    Deadline of Submitting EOI: 18-Dec-2021 11:59 PM Manila
Back Express Interest
local time

Profile Terms of Reference Cost Estimate


Cost Estimate

Amount in
Competitive Items USD
Remuneration and Other Expenses 2,261,500
All activities and inputs in the TOR but not limited to remuneration, per diem, air
travel, miscellaneous travel expenses, report preparation, production, and
transmission, land transportation, communications, etc.
Sub-total 2,261,500
Amount in
Non-Competitive Items USD
Provisional Sums 330,000
Contingency 135,000
Sub-total 465,000
TOTAL 2,726,500